Version 4.0 SAT (Site Acceptance Test) 1.0 2.0 Table of Content Site Acceptance Test ................................................................................................................... 2 1.1 Introduction....................................................................................................................... 2 1.2 Purpose ............................................................................................................................ 2 1.3 Scope ............................................................................................................................... 2 1.4 Definitions......................................................................................................................... 3 1.5 Definitions for Special Conditions & Tests ....................................................................... 4 1.6 SAT Process Flowchart.................................................................................................... 4 Appendices ................................................................................................................................... 5 2.1 Requirement/Appendices ................................................................................................. 5 Appendix A : SAT Test Form Requirements Appendix B : SAT Test Procedure Requirements Appendix C : SAT Tester and Equipment Requirements Appendix D : SAT Testing Program Requirements Appendix E : SAT Defect Logbook Requirements Appendix F : SAT Drawings, Manuals, Contract Specifications and Relay Settings Requirements Appendix G : SAT for Multicore Cable Termination Appendix H : SAT for Substation AC/DC System Appendix I : SAT Secondary Injection for Relays and Instruments Appendix J : SAT for Primary Equipments Appendix K : SAT for Lines and Cable Appendix L : SAT Primary Injection Tests for CT Circuit Appendix M : SAT Secondary Injection Test for Voltage Circuit Appendix N : SAT for Protection and Control Scheme Appendix O : SAT Stability Test of Unit/Differential Protection Appendix P : SAT Final Inspection and Check Appendix Q : SAT for Secondary Live Maintenance Appendix R : On load Tests Appendix S : Post Commissioning Test Appendix T : SAT Process Flowchart 1.1 Site Acceptance Test 1.1 Introduction SAT for any new Grid Facilities shall carried out after SCA has passed. The SAT is carried out by tester, vendor, or TNB. In order to ensure that all SAT is carried out as per the requirement of TNB Grid, this document has been written. It shall be used a guideline by all parties involved in the SAT for any Grid Facilities. 1.2 Purpose The purpose of this document is to: • To clearly define the requirement imposed on the tester in ensuring quality of work and all TNB requirements being implemented accordingly in TNB Grid facility. • To define and standardise the process and requirements of Site Acceptance Test for TNB Grid Facilities. • Provide a reference for the Project Manager, Tester and the Main Contractor involved in the testing works. • Avoid any conflicts that arise at site with regard to tests that are to be carried out. This document shall be applicable for SAT carried out to commission all turnkey and in-house projects of TNB Grid facilities. This shall include but will not be limited to: 1.3 Scope • • • • • Any Grid / power plant interconnection facility Both AIS and GIS type substations Cables And Lines Digital Substation Substations installed with Remote Terminal Units (RTU) Teleprotection end-to-end test shall be covered for the above including Interconnection to large power consumers, LPC. For telecommunication equipment only the end-to end is covered in this document. Refer to ICT procedures. Energy meters and related equipment are not covered by this document. Whereas for telecontrol equipment, tests shall be covered up to the regional or national control center (NLDC) (refer to Appendix Q; 5.0 for the scope of the work). Any equipment failure detected during SAT shall be recorded and reported to TNB to initiate equipment root cause analysis process. A notification (Product Issue Notification / Product Submission for Investigation) as per Appendix A shall be filled by Contractor / Tester. !" Under TNB Relay Failure Management process, any defect or failure detected during DV, FAT, SAT and EOW shall be replaced immediately to avoid impacting project timeline. Any cost incurred related to the replacement work including testing shall be borne by Main Contractor under project implementation until EOW period. 1.4 Relay Failure Management The affected relay shall be subject to further failure root cause analysis by OEM as per the requirement under Product Acceptance Process. A notification (Product Issue Notification / Product Submission for Investigation) as per Appendix A shall be filled up immediately after failure is detected by Main Contractor / Panel Builder and to be submitted to TNB for proper tracking. 1.5 Definitions / Abbreviations Terms TNB Grid GAM PM End User Grid Facility Tester Energy Commission, Malaysia (EC) Electrical Service Engineer (ESE) EC Competent Engineer (ECP) ESE’s Authorised Personnel (EAP) Site Acceptance Test (SAT) Pre-commissioning Inspection and Testing (PIAT) Project Quality Assessment (PQA) Design Verification (DV) Factory Acceptance Test (FAT) End of Warranty Test (EOW) Definition Tenaga Nasional Berhad Grid Division, TNB Grid Asset Management Department Project Manager Grid Asset Maintenance, Distribution Network, ICT etc. The Grid substation, line and/or cable eq uipment (of 66kV and above) or part thereof. However distribution equipment in the Grid substation shall also be included. A testing contractor / Electrical Service Contractor employing a full-time Electrical Service Engineer. Suruhanjaya Tenaga Malaysia / Energy Commission (formerly known as Jabatan Bekalan Elektrik dan Gas). Electrical Service Engineer certified by Energy Commission, Malaysia. Electrical Competent Engineer certified by Energy Commission, Malaysia. A person authorised in writing by the ESE to act on his behalf for any SAT activity and who fulfils TNB’s requirements. Inspection and testing performed at site on the Grid Facility. Quality Assessment activity performed by project manager after the successful completion of SAT stage 2 to determine the readiness of the Grid Facility to start SAT stage 3 and 4. Quality Assessment activity performed by AMD after the successful completion of SAT to determine the readiness of the Grid Facility to be energised. Inspection and testing performed prior to FAT, usually conducted in the presence of TNB representative Inspection and testing performed after DV and before the product sent out to site for SAT, usually conducted by TNB Quality Assurance Inspector (QAI) Inspection and testing performed prior to warranty expiry for all Grid Facility # !" 1.6 Definitions for Special Conditions & Tests Terms Live Plant Live Bay Unit Protection Primary Injection Stability Test End-to-end test On load tests 1.7 SAT Process Flowchart Definition A fenced area with energised high voltage equipment. Any bay e.g. transformer, line/cable, bus-coupler or bus-section bay that is being energised at high/low voltage & DC System. Live means not isolated or not earthed. Protection system with a clearly defined zone of protection usually demarcated between 2 or more sets of CT’s. Testing by means of injecting current into the primary circuit to verify CT ratio, CT polarity and CT secondary circuits. Primary injection is not considered as stability test. Test performed to assess unit protection as a complete scheme that remains stable for all out-zone faults and operates only for in-zone faults. Teleprotection function tests for lines and cables including carrier send & receive tests, intertripping and stability test. Any tests/measurement using the energised secondary voltage and secondary load current after a circuit has been energised. The SAT process is categorized into the following four stages: • Stage 1 – Multicore termination checks and AC/DC system commissioning • Stage 2 – Component level testing for primary and secondary equipments • Stage 3 – CT/VT circuit check, switchgear operation test and Control scheme test • Stage 4 – Protection scheme test, stability test and trip test • Stage 5 – On Load test and Post commissioning test These stages shall be carried out as the above-mentioned sequence. For completeness of the commissioning process PIAT and PQA will be conducted. Appendix T provides explanation and illustration of the SAT process flow in further detail. !" 2.0 Appendices The primary objective of this document is to provide guidance on ‘what tests shall be carried out’ instead of ‘how the tests are to be carried out’. 2.1 Requirement/ Appendices In addition to the question of ‘what tests’, certain specific requirements required to carry out a particular test is also mentioned. The following documents shall provide specific requirements of the SAT: No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Document SAT Test Form Requirements SAT Test Procedure Requirements SAT Tester and Equipment Requirements SAT Testing Program Requirements SAT Defect Logbook Requirements SAT Drawings, Manuals, Contract Specifications and Relay Settings Requirements SAT for Multicore Cable Termination SAT for Substation AC/DC System SAT Secondary Injection for Relays and Instruments SAT for Primary Equipments SAT for Lines and Cables SAT Primary Injection Tests for CT Circuit SAT Secondary Injection Test for Voltage Circuit SAT for Protection and Control Scheme SAT Stability Test of Unit/Differential Protection SAT Final Inspection and Check SAT for Secondary Live Maintenance On load Tests Post Commissioning Test SAT Process Flowchart Appendix Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Appendix H Appendix I Appendix J Appendix K Appendix L Appendix M Appendix N Appendix O Appendix P Appendix Q Appendix R Appendix S Appendix T . $ " SAT Appendix A: SAT Test Form Requirement 1.0 2.0 3.0 Purpose ...................................................................................................................................... 1 General Requirement ................................................................................................................. 1 Additional Requirement .............................................................................................................. 2 1.0 Purpose The purpose of specifying the test form requirement is to standardise the: • • • • 2.0 General Requirement Content of the test form Method of recording the test results Procedure for verifying the test result Procedure for validating the test form The following general information shall be mentioned and standardize in any test form used by the tester. • • • • • • • • • • • • • • • • • • !" Name Of The Testing Company Contract No. Tender No. Title of the test form Name of the substation or installation being tested Name Of Client – name of main contractor Bay or Circuit identification – Feeder name Bay identification – by number/code (bay number) Manufacturers details e.g. Make, Model, and Type etc. Test equipment details – name, serial number, calibration record etc Settings Reference including version. Testers Name – Name of person conducting the test Witnessed By – Name of the appointed TNB staff Verified By – Name and seal of the ESE Comment - ESE shall comment whether the particular test has passed or failed. Page number or Sheet no. Test Procedure Reference No. – With reference to the particular test procedure described in Appendix B. Date. # # 3.0 Additional Requirement In addition to the above general requirements, the following shall also be adhered to: a. All tests conducted shall be documented on a proper test form. b. Expected values shall be presented on the test form for all test/measurement results. A test shall only commence when the expected range of values of the test is available and presented on the test form. Where the test result involves obtaining a particular measurement, then error calculation for each measurement shall be made available on the test form. c. For testing where the value of the injection can be obtained – this value shall be recorded. For testing performed to check a function, the result should be recorded as “OK” if the test/check results is as expected, “FAIL” if the test/check result is not as expected, “NR” if the test/check is not required. Ticking “/” as result shall not be practised. No test result column shall be left blank. d. For test/check result that is not within the expected range, the tester is required to mention it clearly in the comment column of the test form. The tester is also required to immediately update this defect in the Master Defect List (MDL) log. e. All results shall be entered onto the test form immediately upon completion of a test. Recording test results elsewhere and later transferring it onto the test form shall not be practised. f. The witnessing personnel shall initial each test result table in a test form separately immediately after each test. It is the tester’s responsibility to get all the test results initialled immediately by the witnessing personnel. Any test result not initialled by the witnessing personnel will not be accepted. g. All test results recorded on the test form shall be crosschecked with the manufacturer’s factory data whenever available. h. Results shall be recorded using black/blue ink and any changes shall be crossed and initialled in red ink. i. A reference to the test equipment manuals and test procedure used shall be clearly mentioned on the test form. j. Print out from test equipment shall be attached with the test report whenever available. k. All test result valid for six months if the station was idle condition. Re-testing shall be conducted. Tester shall prepare a risk assessment report and propose on test to be re-conducted. TNB to review and approve the retesting to be done l. Any equipment failure detected during SAT shall be recorded in (Product Issue Notification / Product Submission for Investigation) form as attached and report to TNB to initiate equipment root cause analysis process. # !" # # Protection, A utomation & Control GRID SOLUTION EXPERTISE RELAY FAILURE MANAGEMENT Product Issue Notification / Product Submission for Investigation REQUESTOR Reference No: TNB/GRID/GSE(PAC)/RFM 3/1/100 Purpose: Product Issue Notification ………………………………. Submission for RCA Product Information: Installation Information: ! " ! # ! $ Problem Statement: ! % &'( '( $ !! ! % % )(! ! Submission Checklist: !$ #$% * ! #+% * ! + $ * & ' * ! , + - , & . ' % ' $ / '$)%$ ' ! ' ! $'%' + ' ! ' 0 2 33333333311 1 Issue/Failure During FAT and SAT: ( " $ /$ $ $ /$ 4 /$ # Submission by: Name ! Contact No Submission Date: 10/07/2017 RFM No.: Received Date: Delivery Date to OEM: Updated by: Update System Date: OEM Contact Person: For Secretariat Use: SAT Appendix B: SAT Test Procedure Requirement 1.0 2.0 Purpose ..................................................................................................................................... 1 General Requirements .............................................................................................................. 1 1.0 Purpose The purpose in preparing the testing procedure is to: • • • 2.0 General Requirements Study & comment on the given procedure before carrying out the test Document the testing method used for future reference Be used as a site reference for the tester/witnessing personnel a. Testers are required to prepare test procedures for all tests and scheme check, explaining in detail the steps taken to conduct each test. These test procedures shall conform to certain standards and practises. b. The following information shall be clearly mentioned in each test procedure. i. Step by step instructions on how the test is performed. ii. Connectivity diagram of the test setup. iii. Detail of the test equipment used by the tester. The test equipment used shall comply to Appendix C iv. Reference made to an international standard e.g. IEC, BS or equipment manuals. v. Any calculation required prior to conducting the test. vi. Test result form of the particular test. Preparation of the test result form shall comply to Appendix A vii. All safety aspects of performing a particular test shall be documented such as getting appropriate PTW, placing danger signs etc. viii. A checklist on the preparation required before carrying out the test. ix. A checklist on the normalization required after performing the test. c. Additional specific requirements, instructions or precautionary notes shall be clearly mentioned in the test procedure if it is to be used in a live substation. d. A copy of the complete test procedure shall be handed over to the PM in advance for comments before commencing with the SAT. e. Tester shall be able to provide explanation on the testing procedure upon request by the witnessing personnel. f. All safety aspects required to carry out the test shall be clearly documented in the test procedure. ! "# $ $ SAT Appendix C: SAT Tester and Equipment Requirement 1.0 2.0 3.0 4.0 Purpose ..................................................................................................................................... 1 Testers Role & Responsibility ................................................................................................... 1 Test Equipment Requirements ................................................................................................. 2 Requirements To Be A Tester .................................................................................................. 2 1.0 Purpose The purpose of specifying tester and test equipment requirements are: • • • • To ensure that the tester abides to all TNB and Energy Commission regulations. To ensure the safety of the personnel and equipments. To ensure that the ‘right’ test equipment is used for the ‘right’ test. To ensure that the equipment used meets certain specified international standard and is properly calibrated. a. All protection & control related test results shall only be endorsed by an Electrical Service Engineer (ESE). 2.0 Testers Role & Responsibility b. Tester to ensure scheme is in compliance to the approved conceptual drawing. c. c. For any SAT activity in a live plant e.g. extension work: i. The Permit to Work shall be taken by an Energy Commission certified Electrical Service Engineer or his authorised Energy Commission Competent Engineer who fulfils TNB’s requirements. ii. All activity shall be documented in detail and the Service Engineer shall endorse this. For any SAT activity performed on a live station involving any live bay (with or without outage) e.g. scheme modification, relay changing and testing. Risk analysis report shall be produced prior to obtaining PTW. Risk analysis shall consist of the following: i. Activity to be carried out detailing the risks to the system, the rest of the plant, or to personnel involved. ii. Steps taken to minimize any risks identified to the system, the rest of the plant, or to personnel involved. iii. Step by step instruction on all activities to be carried out. iv. Checklist before carrying out the activities e.g. all isolations to be made. v. Checklist after carrying out the activities to re-energize the bay. vi. The risk analysis report shall be endorsed by Electrical Service Engineer (ESE). d. Any protection and control related activities on a live or commissioned bay shall require the presence and direct supervision of the Electrical Service Engineer or his authorized personnel. !" # # a. General requirement for test equipments are: 3.0 Test Equipment Requirements i. All test equipment used shall be calibrated by a recognized body e.g. SIRIM and proof of this shall be made available upon request at site. ii. Test equipment used shall be calibrated at least once in every two years. iii. Tester shall produce upon request the manual of the test equipment used for the reference of the witnessing personnel at site. iv. Tester shall be able to provide explanation on ‘how to operate’ the test equipment upon request by the witnessing personnel. v. PC based test equipment are preferred. Secondary injection set shall be able to produce pure sinusoidal waveform for voltage and/or current. vi. For scheme/relays with 3-phase voltage and 3-phase current input, tests for such a case shall use appropriate 3-phase voltage and 3-phase current injection test equipment. vii. The test procedure as per Appendix B, shall clearly explain how the test equipments used is wired and configured to carry out a particular test. b. Test equipment used shall have built-in safety features in order to avoid any damage to the relay/instrument being tested and to personnel from accidental high voltages/currents injection. c. Safety procedure of using specific test equipment as documented in the test procedure (Appendix B) for a particular test shall be followed especially when carrying out high voltage test. a) Any tester, in order to be considered eligible to be engaged to undertake any pre-commissioning, commissioning or any other related work in transmission facility, shall comply with the following requirements:- 4.0 Requirement To Be A Tester • • Be a registered company with the EC as an Electrical Service Contractor and have in his employment a full time ESE. The ESE shall register himself with the EC as an Electrical Service Engineer. Registered with TNB Transmission Division, as a qualified tester. b) The tester shall have in his possession the adequate testing equipments and instruments to perform the relevant tests. The ESE and authorized person shall be able to operate all the testing equipments correctly and safely. c) The tester shall follow the procedures as outlined in the TNB Transmission facility Site Acceptance Test. d) The tester shall submit work program, work procedures, checklists and risk analysis report (if required) for approval before work can be commenced. e) The ESE is accountable for all of the testing & commissioning works. However the ESE may also delegate certain works to his ECP or EAP for them to carry out. Thus, in order to ensure that all the pre-commissioning activity is carried out as per the TNB Transmission Safety and SAT requirements, the respective person shall be present during the activity as tabulated in table 1: # !" # # ! " # $ %" ' !" $ ( . %&# ) & * , # ' + & - ' $ ' Table 1 Note 1. To take Permit to Work (PTW) – for SAT activity in a live plant. ECP shall be allowed to take PTW for Site Acceptance Test (SAT) provided that; a) The ECP is employed and registered by the Tester / Electrical Service Contractor (ESC). b) The ECP holds a valid EAP certificate under that ESC. c) Submitted the Risk Analysis Report (refer to Appendix C. para 2.c) 2. To take PTW for construction in a live plant. ECP‘s other than Note 1 above are only allowed to take PTW for construction purposes. f) The tester shall submit list of name of his team members before work can be commenced. g) Changes or replacement of ECP or EAP shall not be allowed in an ongoing project without the consent from the TNB. h) The tester shall be suspended or deregistered from TNBT Panel of Testers for the following reasons: • • i) Violation of condition as imposed in clause (a) to (g) of this paragraph. Cause a tripping or mal-operation, which has been proven to be due to his negligence. TNB may review / withdraw the suspension upon complete and satisfactory fulfilment of any other condition imposed thereby. $ !" # # SAT Appendix D: SAT Testing Schedule Program Requirements 1.0 2.0 3.0 Purpose ..................................................................................................................................... 1 General Requirement ................................................................................................................ 1 Additional Requirement ............................................................................................................. 1 1.0 Purpose The purpose of this section is to provide a guideline when preparing the testing program in order to: • • • 2.0 General Requirement Standardise the content of the test program. Avoid too many activities being carried out simultaneously. Plan the sequence of the tests. a. The testing schedule prepared by the tester/ main contractor shall be submitted and accepted in advance by TNB Transmission prior to the commencement of the SAT. b. The testing program shall be prepared in such a way that: Not too many testing activities are carried out simultaneously (preferably not more than two at the same time). Means of recording the actual progress at site shall be provided on the test form. The main contractor shall coordinate the activities of all the testers involved (if different testing companies are involved). If there are any changes in the testing program during the SAT: 1. These changes shall be informed in written by the tester to the PM. 2. One week advance notice on the changes shall be given before the test. 3. Upon receiving information on the changes, the PM shall inform Asset Maintenance. Testing activities during public holidays, weekends or after office hours shall only be carried out if agreed upon by the PM. A daily updated test program on the test progress shall be kept at site. (To be displayed at site) Daily briefing on next day activities 3.0 Additional Requirement Upon completion of the SAT, the final updated testing program shall be compiled and documented together with the test reports. !" # # SAT Appendix E: SAT Defect Logbook 1.0 2.0 Purpose ..................................................................................................................................... 1 General Requirement ................................................................................................................ 1 1.0 Purpose The purpose of having a defect logbook during SAT is to: • • • • • 2.0 General Requirement Standardize defect logging method To monitor the progress of the rectification work To ensure all critical outstanding work has been completed To confirm whether the plant is safe to be energized To assist the PM in producing the final Master Defect List which is required during PQA. a. The PM is responsible to prepare a defect logbook at site titled “SAT Defects”, to record all defects found during the SAT. b. Upon identifying a defect or irregularity, the immediate action shall be to: Inform the PM verbally Record the defect in the SAT defect logbook c. The detail of each defect, shall include but will not be limited to the following: Defect/item no. – A unique reference number for the particular defect. Location of defect – bay name followed by equipment name Detail of defect – a brief description of the defect Date Reported – Date the defect was reported Reported By – The person who reports the defect. Rectification target date – The proposed target date for rectification. Action By – Party responsible to rectify the defect Action Taken – Activity taken to rectify the defect Date Rectified – Date when the defect was rectified Critical/Non critical status – Each defect shall be categorized as critical or non-critical based on the TNBT definition of critical/non-critical defects. Status – The status of action on the defect item – “DONE” – if completed, “OS” – if still outstanding, “IP” if the rectifying action is in progress. d. A copy of this logbook shall be made available upon request. e. The PM is responsible to update this defect logbook every day. f. Any minor defect identified and rectified shall also be mentioned in the defect logbook. g. Any rectification shall only be carried after obtaining appropriate approval from the relevant parties involved. ! "# $ $ SAT Appendix F: SAT Drawings, Manuals, Contract Specifications, Relay Settings and Substation Configuration Files Requirements 1.0 2.0 3.0 4.0 Purpose ..................................................................................................................................... 1 Definition ................................................................................................................................... 1 General Requirement for Drawings & Manuals ........................................................................ 1 Relay Settings & Related Documents ....................................................................................... 2 The purpose in establishing the SAT requirements for drawings, manuals, contract specification, relay settings and substation configuration files are: 1.0 Purpose • • • • • • • • 2.0 Definition 3.0 General Requirement for Drawings & Manuals To ensure all documentation required to commence with the SAT is adequate, complete and available at site. To ensure that these documents are updated continuously during the process of SAT. To facilitate and expedite the process of preparing the as-built documentation. To ensure that SAT for relays is carried out with the approved final settings. To ensure that work is done in accordance to the contract specification. To ensure proper handing over of required documents in hardcopy and softcopy format to TNB cloud for storage. All the softcopy files shall be named based on standard naming approved by TNB. PM is responsible to store these documents in TNB document repository, such as Enterprise Content Management (ECM) System. i. Working Copy : Set of drawings used by tester. ii. Master Copy : Set of drawings where all updating is done neatly for any discrepancies found or design changes based on the corrections in the working copy. All drawings, manuals, contract documents, equipment factory test reports, design verification report and TNBR Factory Acceptance Test report of the plant to be commissioned shall be complete and made available at site before the SAT commences. At least two sets of complete drawings shall be made available at site. One set of the drawings shall be labeled as “Master Copy” and the other as “Working copy” The working copy is intended for the tester for testing purposes, which shall be used to update any discrepancies found during the SAT. The master copy shall be maintained and updated by the main-contractor daily. The updating shall be done neatly using only red ink. The name and date shall be indicated in revision column of the title block. The master copy shall be made available at site during SAT. During the SAT, the PM is responsible to ensure that manuals for all secondary and primary equipments are complete. ! " # # a. A complete set of the final relay settings approved/endorsed by the Protection Setting Unit (PRST), Grid Maintenance Department of TNB and relay configurations shall be made available at site by the PM. 3.0 Relay Settings & Related Documents b. SAT for relays shall setting/configuration. c. carried out with the approved final The relay setting/configuration document shall include both the settings issued by PRST Unit and the complete configuration of the relay. The relay configuration shall include but will not be limited to the following: i. ii. iii. iv. v. vi. vii. viii. d. be Relay Binary Output contacts configuration Relay Opto Inputs configuration Relay LED/Relay Indication configuration Relay Event List configuration Relay Scheme Logic Publisher/Subscriber GOOSE configuration Client/Server MMS configuration System Configuration Description (SCD) file For numerical and/or digital relays, the submission for relay setting and configuration endorsement shall include : i. Declaration by ESE confirming that the tested and implemented relay settings for the devices have been validated to be as per intended design ii. Setting comparison result between setting in the relay and setting issued by PRST in PDF format with verification by ESE iii. Relay setting and configuration file in relay native software format named with standard naming convention For non-numerical relays, the submission for relay setting and configuration endorsement shall include : i. ii. Declaration by ESE confirming that the tested and implemented relay settings for the devices have been validated to be as per intended design Relay setting in hardcopy format e. The System Configuration Description (SCD) file shall be verified to ensure the correct version with reference to Design Verification version. Any changes made to the SCD file will need to be approved by TNB GSE and recorded in the Master Defect List (MDL). The final copy shall be handed over to TNB to store in ECM. f. PM shall ensure all relay setting and configuration, drawing and SCD file (if required) endorsed and verified by all related parties before PQA. g. The PM shall be responsible to ensure all parameters used for setting calculation are accurate e.g. CT ratio, line length, and all protection scheme. h. All the required document as per item c shall be handed over to TNB in a softcopy format. # ! " # # SAT Appendix G: Multicore Cable & Communication Cable Termination Check & Test 1.0 2.0 3.0 4.0 5.0 6.0 Purpose ..................................................................................................................................... 1 General Requirement ................................................................................................................ 1 Commencing Multicore and communication cables Termination Check .................................. 1 Performing Multicore and communication cables Termination Check...................................... 2 Performing Multicore and communication cables Termination Test ......................................... 3 Recording Multicore and communication cables Termination Check & Test Result ................ 3 1.0 Purpose In order to minimize problems during the SAT functional and scheme test, a thorough check & test for all multicore and communication cables termination shall be carried out. The purpose of Appendix G is to provide guidelines on: • Requirements prior to multicore and communication cable termination check & test Checks required to be carried out Tests required to be carried out • • Communication cables cover fibre optic, CAT5e/6, twisted pair, etc. 2.0 General Requirement a. The prerequisite to the commencement of SAT is to successfully complete the multi-core & termination check and tests. No SAT activities shall proceed unless all multicore and communication cables termination has been confirmed to be in order. b. The same tester performing the SAT shall carry out the multicore and communication cables termination check and test. c. All multicore and communication cables of the facility to be commissioned shall be checked and tested. This shall include multicore cables from switchgear cubicles/panels to the Marshalling Kiosk, communication cables between communicating devices and all other cables between cubicles/panels. d. Multicore and communication cables block diagram shall be included with the multicore and communication cables schedule. a. Multicore and communication cables termination check and test shall only commence once: 3.0 Commencing Multicore and communication cables Termination Check !" i. A complete and updated cable core schedule has been made available to the tester and the PM by the main-contractor. Main-contractor shall perform the responsibility as required by the contract and Tester Terms of Reference (TOR). ii. All multicore and communication cables termination activities have been properly completed. Cable numbering, terminal block numbering, core numbering and ferrule numbering shall be in accordance with the specification and arranged neatly. # # a. Requirements of the contract specification shall be used as a reference for carrying out multicore and communication cables termination check. 4.0 Performing Multicore and communication cables Termination Check b. For multicore cable, at least the following shall be checked and confirmed to be in accordance with the cable core schedule: The multicore cables are numbered at both ends. The multicore cables core size used. The multicore cables colour. The multicore screen/armour is effectively grounded if applicable. All spare cores are numbered if applicable. Check all spare multicore are separated numbered (cable and ferrule number) and grouped according to cable number. The terminal blocks type and numbering. No jointing along the multicore cables. Type of cable marker and ferrule used. Core numbering and terminal block numbering. The termination is neat, proper and tight. Correct size of cable glands and lugs are used. Separate multicore cables used for AC/DC circuit. c. For fiber optic cable, at least the following shall be checked and confirmed to be in accordance with the general guideline as per annexed in this Appendix: i. ii. iii. iv. The communication cables are numbered at both ends. The communication cables type, wavelength, cores size and mode. The communication cables screen/armour is effectively grounded if applicable. v. All spare cores are numbered and terminated appropriately. vi. The termination at patch panel (if applicable) and connectors of fibre optic is neat, proper and tight. vii. Ensure proper fibre optic laying method is applied to reduce macrobending and microbending effects, such as : • No bending, snagging and kinking • Dedicated fiber optic trunking within panels • Dedicated fiber optic cable tray at cable cellar • Excessive fiber optic shall be coiled and managed with Cable Management # !" # # 5.0 Performing Multicore and communication cables Termination Test a. At least the following test shall be performed on each multicore cable:- b. Insulation resistance at 1kV DC. Any equipment, which may be damaged by the application of the test voltage, shall have the appropriate terminal isolated or short-circuited. c. Continuity check. d. The following tests shall be performed on each fibre optic communication cable, inclusive of all the patch cords and armored fiber cables. The testing reference is annexed in this Appendix :a. Fibre or Power Loss measurement to ensure the decrease in power loss measured in dB is acceptable b. Cable continuity by verifying the laser transmitted from a source is visible at the opposite end Power Measurement equipment requires calibration on the measurement range used based on the international standards. The equipment shall have a good resolution with the intention to measure loses over a short length of fiber cable. 6.0 Recording Multicore and communication cables Termination Check & Test Result a. Preferably the cable core schedule itself should be used to record all the above checks/tests for each core/channel. b. Any discrepancies found on the cable schedule shall be updated immediately. c. Upon completion of the multicore and communication cables termination check and test, the final updated cable core/channel schedule shall be available at site for the PIAT / PQA inspection and later for the production of the as-built version. $ !" # # SAT Appendix H: SAT for Substation AC/DC System 1.0 2.0 3.0 Commissioning of AC Board ..................................................................................................... 1 Commissioning of Battery Charger System .............................................................................. 1 Testing of Battery Bank & DC Distribution Board ..................................................................... 2 1.0 Commissioning of AC Board Tests required to commission the AC Board: a. b. c. d. e. f. g. h. i. Test AC configuration is as per the single line diagram provided. Perform DC insulation resistance test for the AC Board. Test all indicating meters and lights of the AC Board. Test all relays where applicable. Test AC distribution circuits and ensure the labelling is in order. Test any interlock provided on the AC board. Test that the AC sources are not paralleled at the distribution side. Test on transducer if available. To ensure all outgoing feeders for charger, transformer supplies are distributed on different section of AC bus bar 2.0 Commissioning of Battery Charger System a. Preferably, the commissioning of the battery charger shall be performed by the charger manufacturer. b. Implement all charger settings. c. The Charger shall be commissioned first before being connected to the batteries. d. Test form as required in Appendix A shall be provided. The following additional information shall be included in the test form: Complete charger details Complete battery details Complete charger settings e. At least the following tests shall be performed. In addition to the tests required/recommended by the manufacturer, the tests to be performed shall include but will not be limited to the following: Boost interlocking scheme Float voltage setting Boost voltage setting Boost charging current High voltage alarm setting Low voltage alarm setting A/C fail condition Charger fail condition Low electrolyte level alarm DC earth fault – positive and negative Transducer (if available) f. ! "# All facia for the above test shall be recorded. $ $ 3.0 Testing of Battery Bank & DC Distribution Board a. Test form as required in Appendix A shall be provided. b. In addition to the tests recommended by the manufacturer, the tests to be performed shall include but shall not be limited to the following: Complete charge and discharge test for all battery cells including the spares. Appropriate equipment with constant current discharge shall be used. Discharge test shall be carried out for a minimum duration of 8 hours. Specific gravity measurement shall be taken at the start and end of the discharge test. Voltage measurement for each cell shall be taken hourly during discharge test. Terminal connection tightness check. (Torque check – as per recommended by manufacturer). Check all battery cell, isolation fuse, distribution board, MCB are labeled clearly. Checks that the Distribution Board is configured as per the single line diagram and confirm labeling of all distribution MCB’s are in order by test. The insulation to earth of the complete DC installation shall be tested. Test battery bank isolation system. Open circuit voltage of the battery when it is fully charged shall be measured and recorded. Multicore cable shall be checked as per Appendix G. $ ! "# $ $ SAT Appendix I: SAT for Secondary Injection of Relays and Instruments 1.0 Purpose ............................................................................................................................................. 1 2.0 General Requirement ........................................................................................................................ 2 3.0 Protection and Control functions ....................................................................................................... 5 3.1 Line Differential Protection Function ................................................................................................. 5 3.2 Pilot Wire Protection Function ........................................................................................................... 5 3.3 Distance Protection Function ............................................................................................................ 6 3.4 Autoreclose and Synchronizing Check Function .............................................................................. 6 3.5 Thermal Overload Function............................................................................................................... 7 3.6Transformer/Reactor Bias Differential Protection Function ............................................................... 7 3.7 Transformer / Reactor High Impedance Protection and Restricted Earth Fault Function ................ 8 3.8 Overcurrent Protection Function ....................................................................................................... 8 3.9 Standby Earth Fault Protection Function .......................................................................................... 9 3.10 Busbar and Stub High Impedance Protection Function .................................................................. 9 3.11 Low Impedance Busbar Protection Function ................................................................................ 10 3.12 Breaker Failure Protection ............................................................................................................ 10 3.13 Manual synchronizing Check Protection Function ........................................................................ 10 3.14 Demand/Load Shedding Function ................................................................................................ 11 3.15 Automated Voltage Regulator Function ........................................................................................ 11 3.16 Unbalanced Capbank Protection Function ................................................................................... 11 3.17 Overload Capbank Protection Function ........................................................................................ 12 3.18 Under Voltage Or Over Voltage Capbank Function...................................................................... 12 3.19 Point of Wave Controller ............................................................................................................... 12 3.20 Earth Switch Under Voltage Function ........................................................................................... 12 3.21 Transducers/ Meters or Instrument Meter (DPM) Function .......................................................... 13 3.22 Input and Output IED .................................................................................................................... 13 4.0 Integrated Protection and Control applications ............................................................................... 13 4.1 Integrated Line Protection ............................................................................................................... 13 4.2 Integrated Backup Distance with Thermal Overload Protection ..................................................... 13 4.3 Circuit Breaker Management .......................................................................................................... 13 4.4 Bay Controller ................................................................................................................................. 13 4.5 Overload and Overcurrent Capbank ............................................................................................... 13 4.6 Overvoltage and Undervoltage Capbank ........................................................................................ 13 5.0 Functional Test Guideline ............................................................................................................... 14 5.1.1 Current Differential Function: Pick Up Test.................................................................................. 14 5.1.2 Current Differential Function: Timing Test .................................................................................. 14 5.2.1 Distance Function: Reach Test .................................................................................................... 14 5.2.2 Distance Function: Reach Test: Timing Test ............................................................................... 15 5.2.3 Distance Function: Reach Test: SOTF & TOR Test .................................................................... 15 5.2.4 Distance Function: VTS Test ....................................................................................................... 15 5.3.1 Autoreclose Function: Pick Up Test ............................................................................................. 16 5.3.2 Synchronizing Function: Pick Up Test ......................................................................................... 16 5.3.3 Synchronizing Function: Voltage Check ...................................................................................... 17 5.4.1 Transformer Biased Differential Function: Timing Test (Lower & Upper Slope).......................... 17 5.4.1 Transformer Biased Differential Function: Biased Characteristic Test ........................................ 18 5.5.1 High Impedance Differential Function: Biased Characteristic Test ............................................. 18 5.5.2 Hi Impedance Function : Pick Up And Timing Test ..................................................................... 18 1.0 Purpose To provide SAT requirements in carrying out secondary injection tests for all types of control, protection and instrument devices as an individual component ! "# $ $ 2.0 General Requirement a. Secondary injection shall only commence once stage 1 of the flowchart as per Appendix S has been completed. b. Secondary injection shall be carried out on all relays and instrument with voltage and/or current inputs. c. The relay shall be tested with its final approved/endorsed setting & configuration. Verify the relay setting, such as CT or VT ratio as per actual site. d. Verify and record that all relays are configured to TNB’s approved standard configuration, Terminal Functional Diagram (TFD). It shall include BI, BO and LED. For Digital Substation, this also included Virtual Input, MMS and GOOSE. e. Relay settings used to test the performance of the relay shall be noted in the test form before injection. f. Secondary injection shall only be carried out using dedicated test facilities provided for the protection relay or instrument g. Check and record all protection relays, instruments, test terminal blocks, trip links and group isolation links are labelled clearly as per specification and approved drawing. h. Check and record that by inserting/removing the test plug, trip link and group isolation link, the following action will take place: The DC supply for the relay or instrument is not interrupted. The signaling circuits for alarm, fascia, and SCADA and digital recorder are not interrupted. Tripping circuit inclusive Breaker Fail start, initiation of Master trip to be isolated Control circuit inclusive A/R initiation signal, A/R closing command to be isolated (whichever applicable) Insertion of test plug shall isolate in the following sequence:• First, all tripping signals from the relay are isolated. • Followed by the incoming current circuits are short-circuited. • Finally, the incoming voltage circuits are open-circuited. i. In addition to test required in this document, all tests required by the relay or instrument manufacturer shall also be performed. j. For relay and instruments with three phase voltage and/or current inputs, e.g. distance protection relay, the test equipment used shall be computer based with at least three-phase voltage and current output. k. Any repair work on a relay after the completion of secondary injection tests, shall subject the relay to a full retest. l. Any relay configuration and setting changes on a relay after the completion of secondary injection tests, shall subject the relay to a full retest. For protection relays, all functions that are in use (configured and setting) shall be tested. Any function not in use shall be proven to be defeated. m. For relays with the group settings function, all the setting groups in use shall be tested e.g. Directional Overcurrent relay. $ ! "# $ $ n. The pickup setting for a particular type of protection shall be established by secondary injection, where it is impractical to ascertain this value by primary injection. Injection shall be made across the appropriate relay bus wires with all associated relays, setting resistors and CTs connected. o. Each relay must be provided with a test form. In addition to the general information required in a test form as in Appendix A, at least the following details of the relay under test shall be mentioned: Relay Make Relay type Version No. Relay input rating – Vac, Iac, Hz, Vdc Burden (VA) Serial No. Year of manufacturing p. All test plug terminal numbers used during secondary injection shall be mentioned in the test form. q. Expected results and/or acceptance criteria of the test shall be made available prior to any test. In general, 5% error tolerance is acceptable unless specified by manufacturer for pick up test. For timing test, additional 30ms is allowed to accommodate relay operation time and contact made time. For Under/Over Frequency & Under/Over Voltage relay, the expected relay operation time and contact made time depends on the design and internal algorithm. r. Timing test for any contacts initiating tripping inclusive direct trip and master trip circuit. s. Error shall be recorded for any results obtained. t. During secondary injection of protection relays, all output contacts shall be monitored and recorded for its functionality as per TFD. For example: i. ii. iii. iv. v. vi. vii. viii. ix. x. Contacts initiating trip circuits Contacts initiating master trip relay Contacts initiating breaker failure Contacts initiating auto-reclose Contacts initiating counter/HMI (Digital Substation) Contacts initiating annunciator Contacts wired to digital fault recorders Contacts wired to SCADA GOOSE signal to associated IED MMS signal to clients For example, during overcurrent secondary injection test, the performance of all output contacts used can be recorded in the following format (Table 1): Function to be tested OC Definite OC High Set OC Start OC IDMT EF High Set OUTPUT CONTACT OPERATION Lockout Counter SCADA Trip Trip Ct. 1 Trip Ct. 2 Yes No Yes No Yes No Yes No No Yes No No Yes No No Yes No No Yes No Dist. Rec. Alarm Yes No Yes No Yes No No Yes No No Yes No No Yes No % ! "# $ $ EF Start EF IDMT DC Fail No Yes No No Yes No No Yes No No Yes No No Yes No No Yes No No Yes Yes Table 1 For Digital Substation, Table 2 can be referred. Function to be tested OC Definite OC High Set OC Start OC IDMT EF High Set EF Start EF IDMT DC Fail Trip Ct. 1 OUTPUT CONTACT/VIRTUAL OUTPUT OPERATION Trip Lockout Fascia SCADA Digital HMI Ct. Trip Rec. (Alarm) 2 Yes Yes Yes Yes Yes Yes Yes Yes No No No No No No No No No Yes No Yes No Yes No Yes No Yes No Yes No Yes No Yes No No No No No No No No No Yes No Yes No Yes No Yes No Yes No Yes No Yes No Yes No No No Yes No No Yes Yes EGW (Alarm) Table 2 u. Test and record all digital inputs and GOOSE inputs (Digital Substation) as per TFD of a protection relay or instrument. v. Test and record the functionality of the all possible communication interrogation facility of the relay e.g. PC-relay communication or remotely if applicable. w. Test and record all built-in supervision facility of the relay e.g. relay watchdog facility, relay self-supervision. x. Relay signalling & monitoring facility at local (at substation, such as HMI (Digital Substation) and EGW) and remote (SCADA) shall be checked and verified. y. Pick-up and drop-off test shall be performed for all the relays. z. Contact/Virtual Output Timing test shall be performed for the following output contacts of the protection relay:Contacts initiating trip circuits Contacts initiating breaker failure Contacts or GOOSE Output initiating auto-reclose Contacts or GOOSE Output initiating digital fault recorders Contacts or MMS Output initiating HMI (Digital Substation)/EGW/SCADA Both the pick-up and reset delay time shall be measured during the contact timing test. aa. For relays with any of the following functions, the function shall be tested and documented. ! "# $ $ Built-in instrument or metering function Built-in event recorders. Built-in fault recorders. bb. DC Fail simulation shall be performed to confirm IRF indication and relay does not trip during DC interruption (e.g. after DC recover and when relay is rebooting) cc. Any equipment failure detected during SAT shall be recorded in (Product Issue Notification / Product Submission for Investigation) form as attached and report to TNB to initiate equipment root cause analysis process. 3.0 Protection and Control functions The following secondary injection tests shall be performed based on the general requirements of Section 2.0 of this Appendix I. 3.1 Line Differential Protection Function The following secondary injection tests shall be performed: a. At least the following secondary injection test shall be performed, to ensure the relay operates only for its intended function and not otherwise: All phase to phase fault All phase to ground fault Three phase fault Trip (5 x Pick Up setting) and timing test Communication fail test b. DC Fail 3.2 Pilot Wire Protection Function The following secondary injection tests shall be performed : a. At least the following secondary injection tests shall be performed, to ensure the relay operates only for its intended function and not otherwise. i. All phase to phase fault ii. All phase to ground fault iii. Three phase b. OC Check pick up and timing test to be tested. c. Pilot wire Intertrip via external initiation to be tested. d. To check measured loop resistance and test supervision function. e. DC Fail & ! "# $ $ The following secondary injection tests shall be performed: 3.3 Distance Protection Function a. At least the following secondary injection test shall be performed irrespective of whether the function is used or switched off: i. Reach test for forward and reverse direction for Zone 1, Zone 2, Zone 3, Zone 3R (where applicable) and starting Zone for the R-N, Y-N, B-N, RY, Y-B, B-R and RYB faults. This test shall be done at 10-degree line angle interval for the two forward and reverse quadrants. ii. Perform output contact operating for all type of faults in Zone 1, Zone 2, Zone Aided (where applicable), Zone 3 and Zone 3R (where applicable). Timing shall be measured at line angle at 80% of each Zone reach (avoiding boundary) iii. Test Directional Earth Fault (DEF) Feature if applicable. All following tests shall be carried out for R-N, Y-N and B-N faults: • DEF directional • DEF carrier send time • DEF trip time • DEF echo time iv. Test the VT supervision feature (Pickup/Drop off and alarm timing) v. Test the VT MCB blocking feature vi. Test the SOTF feature where applicable vii. DC Fail 3.4 Autoreclose and Synchronizing Check Function The following secondary injection tests shall be performed: a. At least the following functions of the relay shall be tested: AR pick up for dead time and reclaim time Synchronising pick up test for angle setting, frequency setting and voltage difference To verify voltage status at 15% (dead status), 50% (undefined status) and 85% (live status) of the incoming input voltage. To verify voltage status at 15% (dead status), 50% (undefined status) and 85% (live status) of the running input voltage b. To verify Synchronizing and Voltage check function : • Dead Line/Dead Bus (DL/DB) scheme • Live Line/Dead Bus (LL/DB) scheme • Dead Line/Live Bus (DL/LB) scheme • Live Line/Live Bus (LL/LB) scheme c. To verify Voltage Check blocking d. DC Fail " ! "# $ $ The following secondary injection tests shall be performed: 3.5 Thermal Overload Function a. At least the following functions of the relay shall be tested: Pick Up Stage 1 THOL timing test for alarm b. DC Fail 3.6Transformer/ Reactor Bias Differential Protection Function The following secondary injection tests shall be performed: a. At least the following secondary injection tests shall be performed: i. All phase to phase fault (for all windings i.e. HV, LV, tertiary) ii. All phase to ground fault (for all windings i.e. HV, LV, tertiary) iii. Operation and restraint with timing test iv. Un-restraint test (where applicable) v. Second harmonic restraintt and cross blocking function vi. Full Load Relay Secondary Stability Test (HV-LV) vii. Overflux stage 1 (alarm) and stage 2 (tripping) Test (when applicable) b. DC Fail ' ! "# $ $ 3.7 Transformer / Reactor High Impedance Protection and Restricted Earth Fault Function The following secondary injection tests shall be performed: a. The following setting calculation shall be done before testing i. Measurement of pilot loop resistance (Lead + CT resistance) for all feeders ii. This reading should be recorded in the resistive diagram. iii. Calculation of stabilizing voltage and resistor iv. Setting of stabilizing resistor. b. Set the relay accordingly d. High impedance voltage or current operated relay, the point of injection for relay voltage setting tests shall be across the relay and stabilizing resistance or metrosil where applicable. Both operating voltage and current shall be recorded. e. All typ of phase to ground secondary injection test shall be performed. f. Record the measured value and verify with the calculated setting and ohmic value. Voltage drop across and current into the high impedance scheme (relay and resistor) Total IPOC (primary operating current). Injection to be performed without CT circuit isolated to allow CT magnetizing current to be included g. DC Fail 3.8 Overcurrent Protection Function The following secondary injection tests shall be performed: a. At least the following secondary injection tests shall be performed, to ensure the relay operates only for its intended function and not otherwise. i. ii. iii. iv. OC/EF Start OC IDMT EF IDMT TCS (Trip circuit supervision – where applicable, usually at 33kV and below) v. CBF (Circuit breaker failure alarm – where applicable, usually at 33kV and below) c. Only characteristic type e.g. IDMT NI, EI and DT (for Capbank) used to be tested. Example; for an Overcurrent relay with IDMT normal inverse setting and set for phase fault only, only OC IDMT shall be performed. d. DC Fail ( ! "# $ $ The following secondary injection tests shall be performed: 3.9 Standby Earth Fault Protection Function a. At least the following secondary injection test shall be performed, to ensure the relay operates only for its intended function and not otherwise: SBEF element pick up All the timer stage b. 3.10 Busbar and Stub High Impedance Protection Function DC Fail The following secondary injection tests shall be performed to test the following relays: Check-Zone high impedance relay All discriminative Zone high impedance relay CT supervision relay (where applicable) a. The following setting calculation shall be done before testing: i. Measurement of pilot loop resistance (Lead + CT resistance) for all feeders ii. This reading should be recorded in the resistive diagram. iii. Calculation of stabilizing voltage and resistor iv. Setting of stabilizing resistor. v. Calculation of CT Supervision relay setting b. Set the relay and CT Supervision relay accordingly c. High impedance voltage or current operated relay, the point of injection for relay voltage setting tests shall be across the relay and stabilizing resistance or metrosil where applicable. Both operating voltage and current shall be recorded. d. Record the measured voltage drop across and current into the high impedance scheme and verify with the calculated setting and ohmic value. e. For CT supervision relays timer and pick up to be tested. f. Record the measured value and verify with the calculated setting and ohmic value. Voltage drop across and current into the high impedance scheme (relay and resistor) Total IPOC (primary operating current). Injection to be performed without CT circuit isolated to allow CT magnetizing current to be included g. DC Fail ) ! "# $ $ The following secondary injection tests shall be performed: 3.11 Low Impedance Busbar Protection Function a. All tests recommended by the relay manufacturer. b. At least the following secondary injection test shall be performed: Injection at each feeder (Bay Unit) to validate CT ratio and measurement Injection at selected feeder (Bay Unit) to validate relay pick up, drop off and operation time for each Zone Verify substation topology. Confirm correct busbar Zone operation CT Supervision blocking function, pick up, drop off, timer and alarm c. DC Fail The following secondary injection tests shall be performed: 3.12 Breaker Failure Protection a. At least the following secondary injection test shall be performed: Verify the phase segregation for all the starting signals. Verify the phase segregation for all the current circuits. Verify relay pick up with both starting elements and current elements Timing test for stage 1 and stage 2. Verify timer reset via either removal of starting signals or current elements. b. DC Fail 3.13 Manual synchronizing Check Protection Function The following secondary injection tests shall be performed: a. At least the following functions of the relay shall be tested: 11 Synchronising pick up test for angle setting, frequency setting and voltage difference 12 To verify voltage status at 15% (dead status), 50% (undefined status) and 85% (live status) of the incoming input voltage. 13 To verify voltage status at 15% (dead status), 50% (undefined status) and 85% (live status) of the running input voltage b. To verify Synchronising and Voltage Check function: • Dead Line/Dead Bus (DL/DB) scheme • Live Line/Dead Bus (LL/DB) scheme • Dead Line/Live Bus (DL/LB) scheme • Live Line/Live Bus (LL/LB) scheme c. To verify Voltage Check blocking d. DC Fail ! "# $ $ The following secondary injection tests shall be performed: 3.14 Demand/Load Shedding Function a. At least the following secondary injection test shall be performed : i. ii. iii. iv. Under frequency for all stages. Under voltage for all stages Timing test for all stages. Under voltage blocking for Under frequency and Under voltage stages Pick up shall be performed based on frequency ramping methodology with at least 0.01Hz/s rate (1mHz at every 100ms) Timing test shall be performed based on frequency ramping methodology with at least 1Hz/s rate (10mHz at every 10ms) Based on the methodology as stated above, the expected relay operation time is about 130ms for an expected instantaneous operation. b. DC Fail 3.15 Automated Voltage Regulator Function The following secondary injection tests shall be performed: a. At least the following secondary injection test shall be performed : i. ii. iii. Verify pick up for voltage regulation and bandwidth. Timing tests with definite time. Verify pick up for Over voltage/under voltage and confirm blocking for any raise or lower operation. Operation Mode Auto / Manual verification • For circulating current paralleling scheme, it can be tested during on-load • Raise and lower for manual operation iv. b. CB/Isolator status check to confirm correct auxiliary contact are wired c. Topology check as per actual system configuration. For 1HCB system, verify the topology and Busbar Decoupling Switch is functioning as per intended design. The Busbar Decoupling Switch shall be switched open when all diameters are decoupled between the two busbars of the 1HCB system and reflected correctly in the topology. d. DC Fail 3.16 Unbalanced Capbank Protection Function The following secondary injection tests shall be performed: a. At least the following secondary injection test shall be performed: i. ii. iii. b. DC Fail ! "# $ $ Operating current pick up for all stages without taking into account natural unbalance compensation. Operating current pick up for all stages with the effect of natural unbalanced compensation setting Timing test for all stages. The following secondary injection tests shall be performed: 3.17 Overload Capbank Protection Function a. At least the following secondary injection tests shall be performed: i. ii. iii. b. 3.18 Under Voltage Or Over Voltage Capbank Function Pick up test for stage 1 (alarm) and stage 2 (trip) Timing test for stage 1 with Definite time Timing test for stage 2 with IDMT DC Fail The following secondary injection tests shall be performed: a. At least the following secondary injection tests shall be performed,. i. ii. iii. 3.19 Point of Wave Controller 3.20 Earth Switch Under Voltage Function Pick up test for all stages under and over voltage Timing test on under voltage stage 1 with Definite time Timing test on over voltage stage 1 and 2 with Definite time b. DC Fail c. To verify CB Open condition does inhibit undervoltage function The following secondary injection tests shall be performed: a. To verify correct point of wave switching, test shall be carried out by current or voltage injection. For reactor, verify CB opening at zero current crossing and for capacitor, verify CB closing at zero voltage crossing and CB opening at maximum voltage. b. For 132kV ungrounded capacitor, it is expected 2 poles closing (e.g. Y and B pole) during phase-phase voltage crossing (e.g. Y-B) and followed by last pole (e.g R pole) after 5ms. For 275kV grounded capacitor, the 1-pole operated CB closing shall be verified at each phase zero voltage crossing. c. For 132kV ungrounded capacitor, it is expected 1 pole opening (e.g. R pole) at phase voltage maximum (e.g R ph when current is almost zero) and followed by two other phases (e.g Y-B pole) opening during phasephase) voltage crossing (e.g Y-B ph after 5ms. For 275kV capacitor, the 1pole operated CB opening shall be verified at each phase voltage maximum. d. For reactor, 1-pole CB closing shall be verified at each phase zero voltage crossing. e. For reactor, 1-pole CB opening shall be verified at each phase maximum voltage crossing. The following secondary injection tests shall be performed: a. At least the following secondary injection tests shall be performed, i. ii. b. Pick up test for under voltage Timing test DC Fail $ ! "# $ $ 3.21 Transducers/ Meters or Instrument Meter (DPM) Function The following secondary injection tests shall be performed: a. Calibration of indicating meters and transducers shall be done over its complete range (if applicable). b. The accuracy check of transducers through secondary injection. Error Tolerance shall refer to the Transducer class. The following secondary injection tests shall be performed: 3.22 Input and Output IED • • • Measurement function (Station IOIED) Tripping function (Transformer IOIED) Hardwiring to GOOSE signal conversion function (Station & Transformer IOIED) a. Verify all relays BIBO are configured as per section 2.0 b. Verify DC System 4.0 Integrated Protection and Control applications 4.1 Integrated Line Protection This application consists of these functions: • Current Differential Protection (Section 3.1) • Backup Distance Protection (Section 3.3) • Thermal Overload (Section 3.5) 4.2 Integrated Backup Distance with Thermal Overload Protection This application consists of these functions: • Backup Distance Protection (Section 3.3) • Thermal Overload (Section 3.5) 4.3 Circuit Breaker Management This application consists of these functions and Scheme: • Breaker Failure Protection (Section 3.12) • Autoreclose and Synchronizing Check (Section 3.4) • Overcurrent Protection for Transformer and Capbank (Section 3.8) • Pole Discordance Scheme 4.4 Bay Controller This application consists of these functions and Scheme: • Switchgear Operation & Interlocking Scheme • Manual Synchronizing Check (Section 3.13) • Earth Switch Interlock (Section 3.20) • Measurements (Section 3.21) 4.5 Overload and Overcurrent Capbank This application consists of these functions: • Overload function (Section 3.17) • Overcurrent function (Section 3.8) 4.6 Overvoltage and Undervoltage Capbank Station IOIED/IOIED consists of these functions and Scheme: • Overvoltage function (Section 3.18) • Undervoltage function (Section 3.18) % ! "# $ $ 5.0 Functional Test Guideline The following test form for Protection Function shall be served as a guideline and be extended to complete all the testing scope as per requirement in Section 1 to Section 4 in this document. 5.1.1 Current Differential Function: Pick Up Test Setting Is (A) Expected value Differential Operation (Id>), Setting ( Actual current Max. Allowable range ) Allowable Error R ±5% Y B R-Y Y-B B-R R-Y-B note : Usually the tolerance or actual pick up value is based on injection condition and characteristic of the relay. 5.1.2 Current Differential Function: Timing Test Setting Is (A) Red Current Injection 5A Yellow 5A Blue 5A Differential Operation (Id>) Actual time (ms) Max. Allowable range Allowable Error <30ms 5.2.1 Distance Function: Reach Test Zone Zone 1 Zone 2 Zone 3 Fault Type Expected Reach (Setting) 0º Line Angle (Quad) or (as per 90 º setting) (mho) R-N Y-N B-N R-Y Y-B B-R R-Y-B R-N Y-N B-N R-Y Y-B B-R R-Y-B R-N Y-N B-N R-Y ! "# Measured Reach 0 º (Quad) or 90 º (mho) Line Angle (as per setting) Max. Allowable range Allowable Error % ±5% $ $ Zone Fault Type Expected Reach (Setting) 0º Line Angle (Quad) or (as per 90 º setting) (mho) Measured Reach 0 º (Quad) or 90 º (mho) Line Angle (as per setting) Max. Allowable range Allowable Error % Y-B B-R R-Y-B R-N Y-N B-N R-Y Y-B B-R R-Y-B Rever se Zone 5.2.2 Distance Function: Reach Test: Timing Test Zone Z1 Timing Setting Z1 ( ), Z2 ( ), Z3 ( Actual time (ms) Max. Allowable range R-N Z2 Y-N Z3 R-Y-B Z3 Rev Y-B ), Z3Rev ( ) Allowable Error Setting + 10ms (contact make time) 5.2.3 Distance Function: Reach Test: SOTF & TOR Test 1. 2. 3. 4. Simulate TOR (Trip on Reclosing) at CBM. This test can be performed during CBM (AR) functional test Simulate Manual closing from Bay Controller. Verify if there is any AR initiation (CBM), M/Trip operation, Intertrip to remote end being initiated. “AR Lock Out Intertrip” to remote end can be verified by retrieving relay event list Normalize the system after testing Procedure / Activity Simulate SOTF condition as per 1 & 2 by initiate manual closing or TOR, simultaneously, inject R-N phase fault AR Operation Master trip operation No AR M/Trip Operated Lockout Intertrip to Remote End Yes Actual Result (P/F) 5.2.4 Distance Function: VTS Test 1. 2. 3. 4. 5. Switch off C.Diff function during the test Simulate MCB Trip (Off MCB), and observe any alarm, indication at Station HMI Simulate MCB Trip condition and inject Z1 R-N fault Verify if there is any relay operation Normalize the system after testing Procedure / Activity Simulate MCB Trip (Off MCB), and observe any alarm, indication etc Relay Operation Actual Result (P/F) VTS operated (Station HMI & LED) & ! "# $ $ Procedure / Activity Relay Operation Actual Result (P/F) Simulate MCB Trip condition and inject Z1 RN fault No relay operation and No tripping issued 5.3.1 Autoreclose Function: Pick Up Test Setting Is (A) Setting Actual Pick Up Test Result (P/F) Dead Time (1 Pole) Allowable Error Dead time should be calculated from AR In Progress up to contact make time = setting + 10ms Dead Time (3 Pole) Reclaim Time 5.3.2 Synchronizing Function: Pick Up Test Setting Is (A) Setting Actual Pick Up Test Result (P/F) Allowable Error Voltage Diff ( V) Frequency Diff (Hz) ±5% Phase Angle Diff ( ) " ! "# $ $ 5.3.3 Synchronizing Function: Voltage Check Voltage Check Condition DBLL DLLB DLDB Sync Check DB 0 LL >80% VI : Line VT Fail (From BCU) N DB 0 LL 60% N N Not Allow DB 0 LL >80% N FAIL Not Allow DB 0 LL >80% N FAIL on RBB Allow DB 0 LL >80% FAIL N Allow Fix injection VI : BB VT Fail (MBB1), unless specified otherwise N Expected result (BO : CB Close ) DL 0 LB >80% N N Allow 0 LB 60% N N Not Allow DL 0 LB >80% FAIL N Not Allow DL 0 LB >80% N FAIL Allow DL 0 LB 0 N N Allow DL 60% DB 60% N N Not Allow DL 0 LB 0 FAIL FAIL Not Allow DL 0 DB 0 FAIL N Not Allow DL 0 DB 0 N FAIL Not Allow LL >80 % >80 % LB >80% N LB >80% FAIL a. Simulate Bay under MBB1 MBB2 = 50% RBB = 70% Vn and MBB1 = 100% Vn) b. Simulate Bay under MBB2 MBB1 = 50% RBB = 70% Vn and MBB2 = 100% Vn) c. Simulate Bay under MBB1 MBB1 = 50% MBB2 = 70% Vn and MBB1 = 100% Vn) N FAIL (P/F) Allow DL LL Running Voltage Vary injection (Voltage) Allow Allow MBB1 voltage is referred MBB2 voltage is referred RBB voltage is referred 5.4.1 Transformer Biased Differential Function: Timing Test (Lower & Upper Slope) Refer to relay characteristic to select injection points. As an example, for lower slope, I Diff (0.5A) with I Biased (1A), whereas for higher slope, I Diff (1A) with I Biased (4A) can be of selection for Trip Region Note: FAT requirement: minimum 6 tests (2 test in each phase) and shall be randomly selected by Inspector. DV or Routine Test requirement: all the tests (4 test in each phase) shall be completed Phase Region R Trip Trip Restraint Restraint I Diff (A) I Biased (A) Operating Time Allowable range Allowable Error PU ±5% Operating ' ! "# $ $ Y B Trip Trip Restraint Restraint Trip Trip Restraint Restraint time < 30ms 5.4.1 Transformer Biased Differential Function: Biased Characteristic Test Phase Ibias Expected IDiff* Actual IDiff Allowable Range 0.50In 2.00In 4.00In 0.50In Y 2.00In 4.00In 0.50In B 2.00In 4.00In *Expected IDIFF can be obtained from Relay Characteristic Graph Allowable Error % R ±5% 5.5.1 High Impedance Differential Function: Biased Characteristic Test RELAY ACCESSORIES VERIFICATION Verify if the accessories and connection as per design: No Accessories Range (Ohm) 1 External Metrosil 2 External shunt R: stabilizing adjustable Y: B: resistor 3 External series R: stabilizing adjustable Y: resistor B: Connection Point R: Y: B: R: Y: B: 5.5.2 Hi Impedance Function : Pick Up And Timing Test 1. 2. This testing shall be performed with a typical setting of Ipoc = 0.2A and Voltage setting of 100V. Resistors shall be adjusted accordingly prior to testing. Note : If test set is not able to produce adequate current up to 0.2A, it is advisable to change to voltage output source mode during the testing. Voltage operated relay: Adjust Shunt stabilizing resistor until total injection current reach around 0.2A. Current operated relay: Set relay to operate at 0.2A. Adjust series stabilizing resistor until voltage across relay and series resistor is about 100v. Record all the result: Actual Injection Current (Primary Operating Current), voltage across relay scheme (relay + series resistor if any), adjusted resistor value, and operating time. ( ! "# $ $ Phase Operating Time Current IPOC Voltage across relay scheme (relay + series Resistor if any) Resistor value Rseries Error % Ipoc Rshunt R PU ±5% Y Operati ng time < 30ms B ) ! "# $ $ SAT Appendix J: SAT for Primary Equipment 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 Purpose .................................................................................................................................... 2 General Requirement ............................................................................................................... 2 Circuit Breaker Testing ............................................................................................................ 4 Gas Insulated Substation (GIS) ............................................................................................... 7 Power Transformer (Applicable for 132kV and Above) ......................................................... 12 Earthing Transformer Testing ................................................................................................ 18 Neutral Earthing Resistor (NER) Testing ............................................................................... 21 Disconnector Testing ............................................................................................................. 23 Current Transformer Testing.................................................................................................. 25 Voltage Transformer Testing (Capacitive / Inductive) ........................................................... 28 Capacitor Bank Testing.......................................................................................................... 31 Surge Arrestor Testing ........................................................................................................... 33 Sealing End Testing ............................................................................................................... 35 Reactor (Oil Immersed Type) Testing .................................................................................... 36 Reactor (Dry Type) Testing.................................................................................................... 39 Switchyard Installations Testing ............................................................................................ 40 11kV and 33kV Switchgear Testing ....................................................................................... 42 Standby Diesel Engine Driven Generator………………………………………………………..47 ! "# $ $ 1.0 Purpose 2.0 General Requirement To provide SAT requirements when carrying out Primary Equipment tests . a. All tests to be carried out together with those listed in the contract specification. b. All tests for primary equipment shall be completed under stage 2 (Appendix S flowchart) unless specified otherwise. c. All primary equipment shall be checked in accordance with Nameplate Rating and Contractual Technical Specification. d. All inspections, checks and tests carried out shall be recorded. e. All alarms for primary equipment shall be tested by actual simulation unless specified otherwise or no facilities provided. f. All bolts and nuts shall be torqued accordingly checked and to be free from rust. g. All equipment installed shall be checked to have minimum safety, electrical and ground clearances. h. All the cubicle doors, marshalling kiosks and panels shall be checked and proven to be vermin and moisture proof, and properly ventilated and having locking facility. i. All the components of the equipment shall be checked to function and operate as intended. j. All the bushings and insulators shall be checked and to be free from cracks / chip off and deposits. k. All installation of primary equipment shall be in accordance with the approved drawings and installation instruction by the manufacturer. l. All related primary equipment operation & maintenance manuals shall be made available on-site prior to the commencement of Site Acceptance Test (SAT). These shall include but not limited to: i. Equipment O&M ii. Site Drawings approved by TNB iii. Factory Acceptance Test Results. iv. Contract Specifications. m. Contractors to ensure that inspections, testing and commissioning shall be carried out by competent, certified and/or qualified person. n. All primary equipment shall be earthed in accordance with the approved earthing design. o. Check of the completeness, correctness and condition of earth connections, labelling, clearances, painted surfaces, cables, wiring, pipework, valves, blanking plates and all other auxiliary and ancillary items. p. Checks for no sign of (insulation medium) system leak. q. Spares and loose items to be handed over shall be listed, checked and correctly stored e.g. blanking plates, special tools, etc. $ ! "# $ $ r. All recommended values, tolerances and tested values to be recorded. s. All equipment to be locked upon completion of SAT and prior to commissioning. t. Cleanliness checks shall be performed. u. Tests listed shall be applicable for all voltage levels unless specified otherwise. v. All equipment with Online Monitoring System (OMS) shall be tested (but not limited) as follows: i. Check for physical condition – i.e. leaking, any physical defects. ii. Cabling tray, test tap connection for bushing monitoring. iii. Operational test i.e. alarm indication, system healthiness. % ! "# $ $ 3.0 Circuit Breaker Testing 3.1 Test Form Requirement a. All general information as required in Appendix A. b. At least the following details of the switchgear shall be mentioned in test sheet: i. ii. iii. iv. v. vi. vii. viii. ix. x. 3.2 Testing Required Circuit Breaker make Circuit Breaker type Operating medium Insulating medium pressure Rated nominal, short circuit current Operating sequence Basic Insulation Level (BIL) Serial No. Rated Voltage Date of manufacture a. All testing required/recommended by the manufacturer of the switchgear and its accessories shall be conducted and recorded clearly in the test form. b. In addition, the following physical check shall include but not limited to: i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii. xiv. xv. xvi. ! "# $ $ To check for insulation medium leaks Checks for any corrosion, damage or defect Tightness of connections using correct torque Insulator bushings checks for cracks Earthing connection Wire and cable connections Cable entrance to control cubicle shall be from bottom, sealed and water and vermin proof Heaters and lamps in working order Ensure recommended thermostat temperature setting label is available inside the control cubicle. Check for linkages connection between poles and mechanism. Lubrication and grease for gears and linkages. Gauges shall be visible, leakage, upper/lower limit. Check SF6 Piping installed properly (dents and welding point). Check valve in operation position (where applicable). Locking facilities for mechanism / CB box. Labeling for CB Mechanism Box. c. The following electrical test on the equipment shall include but not limited to: No Test Details Limit 1 Contact resistance test • Shall be carried out for all phases • Test point shall be as close as possible to the CB contacts unless recommended otherwise by manufacturer. • Based on factory routine test result/ O&M • Within manufacture’s recommended / tolerance value as prescribed in Routine test / FAT • Shall be consistent for all phases. 2 Timing test For all phases: • Close and trip timing • C-O operation • Synchronism between the main contact in the three phases • Timing on main contact on each pole (for 275kV, 500kV & Capbank) • • • • • Based on factory routine test result/ O & M. Within manufacture’s recommended / tolerance value as prescribed in Routine test / FAT Pole spread shall be <5ms To follow O&M proposed limit No contact bouncing detected 3 Insulation resistance test Applying 5 kV DC using insulation tester for insulator and conductor to earth • More than 1G • Shall be consistent for all phases. 4 Close open operation For all type of CB • Motor run time from start of motor to motor stop Within recommended manufacture’s tolerance as prescribed in factory test 5 Auto reclose operation • Within recommended manufacture’s tolerance as prescribed in factory test Determine A/R block (CB ready) signal presence at A/R relay & ! "# $ $ 6 SF6 Pressure To do actual operation of SF6 leakage with series connection for Stage 1 & 2 : Stage 1- Alarm Stage 2 – Trip & Lockout Within recommended manufacture’s tolerance as prescribed in factory test For Generator Feeder with series connection for Stage 1 & 2: Stage 1- Alarm Stage 2 – Lockin d. The following are Insulating medium (SF6) – IEC 60376/ IEC 60480 test shall include but not limited to: No 1 Test Details Moisture Content SF6 dew point test 2 SF6 purity test 3 S02 content To check composition of SF6 gas To check present of SO2 in SF6. Limit < -300C @ ATM (46 ppm-mass) > 97% < 12ppmv * OEM has to clarify should there be a ±10% variance in the SF6 gas value tested prior to commissioning and 8 months after commissioning. e. Operation, indication and interlock test shall be carried out: i. ii. iii. iv. v. vi. vii. Inspection on the wiring, position indicators, auxiliary switches, terminal blocks and components e.g. Labeling, tightness, colour coding. Manual operation of switchgear shall be conducted e.g. slow closing, manual spring charging, manual tripping, etc Operational tests shall be carried out on the operating mechanism system and the SF6 monitoring system. All recommended values and tested values to be recorded e.g. duration, switches/protection setting, gauges reading and counter reading Control and operation tests to be carried out e.g. control, protection, alarm and indications circuit All indications related to the equipment to be tested and proven working Checks and operation shall be made on the Interlocks and safety features e.g. electrical and mechanical interlocks and safety valves " ! "# $ $ 4.0 Gas Insulated Substation (GIS) 4.1 Test Form Requirement a. All general information as required in Appendix A. b. At least the following details of the GIS shall be mentioned: i. ii. iii. iv. v. vi. vii. viii. 4.2 Testing Required Rated voltage Rated current Equipment model Operating mechanism Serial number Date of manufacture Bay/Compartment involved Short circuit rating Following are the tests required to pre-commission the GIS: a. All testing required/recommended by the manufacturer of the GIS and its accessories shall be conducted and recorded clearly in the test form. b. In addition, all the following physical check/inspection shall also be conducted and recorded clearly in the test form. i. i. ii. iii. iv. v. vi. vii. viii. ix. x. Tightness of connections using correct torque Insulator bushings checks for cracks Earthing connection Wire and cable connections Cable entrance to control cubicle shall be from bottom, sealed and water and vermin proof Heaters and lamps in working order Ensure recommended thermostat temperature setting label is available inside the control cubicle Earth switch indication To check GIS/GIB enclosure is clean and free from fungus. Locking facilities. To do actual calibration test to verify SF6 gauge pressure is accurate. c. The following are electrical test to be carried out: No 1 Test Disconnectors and Circuit Breaker Contact resistance test Details Limit • Based on factory • Shall be carried routine test result/ out for all phases O&M • Test point shall be as close as • Within recommended manufacture’s possible to the tolerance as prescribed CB contacts in factory test unless recommended • Shall be consistent for otherwise by all phases. manufacturer. • Disconnectors to be tested if facility permit. ' ! "# $ $ 2 Timing test For all phases: • Close and trip timing • C-O operation • Synchronism between the main contact in the three phases • Timing on main contact on each pole (275kV & Capacitor bank) • • • • Based on factory routine test result/ O&M. Within recommended manufacture’s tolerance as prescribed in factory test Pole spread shall be <5ms To follow O&M proposed limit 3 Insulation resistance test Applying 5 kV DC using insulation tester for insulator and conductor to earth • • 4 Close open operation For all type of CB • Motor run time from start of motor to motor stop Within recommended manufacture’s tolerance as prescribed in factory test > 1G Shall be consistent for all phases. For hydraulic CB • Motor start pressure • Motor stop pressure • Alarm stage pressure • Trip stage pressure • (Actual pressure release) 5 Auto-reclose operation For hydraulic CB • Manually openclose-open (o-co) sequence and record pressure • Determine A/R block (CB ready) signal presence at A/R relay Within recommended manufacture’s tolerance as prescribed in factory test ( ! "# $ $ 6 SF6 Pressure To do actual operation of SF6 leakage with series connection for Stage 1 & 2: Within recommended manufacture’s tolerance as prescribed in factory test Circuit Breaker / Line Disconnectors Stage 1- Alarm Stage 2 - Trip & Lockout Busbar Disconnector Stage 1- Alarm Stage 2- Lockin d. The following tests (8&9) are to be carried out after completion of the above tests and all other pre-commissioning tests prior to commissioning. No 8 Test Short duration power frequency withstand voltage test to be performed phase by phase Details 132 kV GIS: Able to withstand 235kV RMS for 1 min Limit Based on IEC 62271203. 275 kV GIS: Able to withstand 380kV RMS for 1 min **Conditioning to be performed phase by phase as per OEM requirement ) ! "# $ $ 9 Partial discharge measurement to be performed phase by phase by the preferred UHF method. This test should be conducted after test no 8. This is to ensure all particles will be active and can be detected after HV test Acoustic method shall be used only when GIS construction does not have epoxy spacer. 132 kV PD test voltage (phase to earth): • 101kV rms (1.2xrated voltage/ 3) Based on IEC 62271203 and IEC 60270. For PD measurement Maximum allowable Discharge 10pC measured by Conventional or UHF. For acoustic measurement no discharge should be detected. 275 kV PD test voltage (phase to earth): • 208kV rms (1.2 x rated voltage/ 3) During short duration power frequency withstand voltage test, the Voltage Transformer, Surge Arrester and Power Cable to be isolated. e. Following are the test required for GIS insulating medium (SF6) – IEC 60376 & IEC 60480. This test shall be conducted after all electrical test. No 1 Test Moisture Content Details SF6 dew point test Limit CB compartment: < -30oC @ATM (46 ppm-mass) *For Toshiba & Hitachi make; < -36oC @ATM (24 ppm-mass) Other compartment: < -27oC @ATM (63 ppm-mass) 2 3 ! "# $ $ SF6 purity test SO2 Content * For Toshiba & Hitachi make; < -30oC @ATM (46 ppm-mass) To check composition of > 97% SF6 gas at every compartment To check SO2 content inside each compartment < 12ppmv * OEM has to clarify should there be a ±10% variance in the SF6 gas value tested prior to commissioning and 8 months after commissioning. For GIB / Cable box compartment the above test shall be conducted after connection to transformer / cable. f. The following operation, indication and interlock test shall be done but not limited to: i. ii. iii. iv. v. vi. vii. Inspections on the wiring, position indicators, auxiliary switches, terminal blocks and components e.g. labelling, tightness, colour coding. Manual operation of switchgear shall be conducted e.g. slow closing, manual spring charging, and manual tripping. Operational Tests shall be carried out on the spring/hydraulic operating system and the SF6 monitoring system. All recommended values and tested values to be recorded e.g. Duration, switches/protection setting, gauges reading and counter readings. Control and operation tests to be carried out e.g. Control, protection, alarm and indications circuit. All indications related to the equipment to be tested and proven working. Checks and operation shall be made on the Interlocks and safety features e.g. electrical and mechanical interlocks and safety valves. g. Online Monitoring System (OMS) – If applicable i. ii. iii. ! "# $ $ Check for physical condition – i.e. leaking, any physical defects. Cabling tray, test tap connection for bushing monitoring. Operational test i.e. alarm indication, system healthiness. 5.0 Power Transformer (Applicable for 132kV and Above) a. All general information as required in Appendix A shall be provided. 5.1 Test Form Requirement b. At least the following details of the power transformer shall be mentioned. i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. 5.2 Testing Required Transformer make Transformer type Vector Group Capacity Impedance Ratio Serial No Rated Voltage Date of manufacture Short Circuit Rating OLTC Data Following are the test required to pre-commission the power transformer: a. All testing required/recommended by the manufacturer of the power transformer and its accessories shall be conducted and recorded clearly in the test form. b. In addition, all the following physical check shall also be conducted and recorded clearly in the test form: i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii. xiv. xv. xvi. xvii. xviii. xix. xx. c. Check for any corrosion, damage or defect Co-coordinating gaps (alignment and gap measurement) Check for insulation leaking Labeling e.g. valve, transformer numbering etc. Earth connections Explosion vent / pressure relief device, bucholz relay for main and OLTC tank. SA/CVT droppers’ connection not to have branch connection. Breathers (properly inspect for leaks, silica gel, etc.) Valves in operational positions (to be checked during erection of transformer) Correct oil levels in main tank & OLTC conservator, oil pocket, cable box and bushing. Safety clearances as per approved drawing Ensure all terminal blocks, oil level gauges and other accessories including marshalling kiosks are fully sealed/moisture and vermin proof. All additional special equipment (e.g. Transformer explosion prevention system/ RPR) to be checked and tested. For Auto transformer tertiary winding, to check 1 phase earth connection are done. Plinth check shall be within required specification Locking facilities for valve and ladder Ladder – Anti climbing Device Housing for PRD, Bucholz and OLTC Surge Relay available Bushing test plug- no moisture ingress, no damage on the tread, cover intact. Gas collecting device for conservator air bag. The following electrical tests shall be conducted and recorded clearly in the test forms. The test value(s) shall conform to the limits specified below: $ ! "# $ $ No 1 Test Insulation resistance Details The test shall be performed using a 5 kV insulation tester at 1 min. The following measurement shall be recorded: 1. Between Primary and Earth 2. Between Secondary and Earth 3. Between Primary and Secondary 4. Between Tertiary and Earth Ratio of HV: LV windings. 2 Turns Ratio 3 Vector Group Vector Group of the transformer 4 Winding resistance (DC) Measurements of winding resistance for i) ii) 5 Excitation Current HV – All tap positions LV – Nominal tap position Measurements of excitation current for all phases at 10kV Note: Tx should not be magnetize Limit > 1 GΩ @ 20°C Within +0.5% of nameplate ratio at all taps. Vector diagram obtained from measurement shall be the same with manufacturer’s vector diagram. 1. Within 2% of factory measurements after insulation temp correction. 2. Within +5% between phases after correction to 75°C 3. No break during tap changer operation. 1. 3 phase Tx pattern of 2 higher currents on the outer phase together with a lower current on the center phase. 2. 1 phase Tx values must be consistent for all phase 3. Difference between R & B phase shall be < 10% 4. Single phase transformer values must be within 10% for all phases (same manufacturer) % ! "# $ $ 6. Verification of the fan operation, pump operation, alarm and trip settings of OTI and WTI For OTI temperature shall be raised to the relevant settings and verification made. For WTI temperature shall be raised and full load secondary current shall be injected at the bushing CT to the relevant setting and verification made. Factory test results/O & M. Within recommended manufacturer’s tolerance as prescribed in factory test During this test temperature meters installed on the RTCC panel shall also be checked. For pump and fan operation shall be raised to the relevant settings and verification made. 7. 8. Winding Power Factor (See Note 1) Bushing Power Factor (See Note 1) Refer to setting table N1(a) Measurement of Power Factor of windings. Correction factor to follow IEEE C57.12/90 – 1995 Measurement of Power Factor of all bushings Correction factor to follow IEEE C57.12/90 – 1995 <0.5% at 20°C For C1: 1. < 0.7%. 2. Power factor for all three phases <100% difference between phases. ∗ For any bushing where the power factor difference exceeds 100%, to be replaced. For C2: 1. C2 bushing power factor < 5% 9. 10 ! "# Dielectric Response on Winding (CHL) (See Note 1) Oil Power Factor (See Note 1) $ $ % by Dry weight of Moisture Content in Solid Insulation Measurement of Power Factor of Tx Oil Correction factor to follow IEEE C57.12/90 – 1995 Capacitance change +5% from FAT result < 1.0% (% moisture content by dry weight) < 0.1% at 20°C 11. Sweep Frequency Response Analysis (SFRA) (See Note 1) Measurement of the Winding movement of the transformer. 12. Insulation Resistance (Winding) (See Note 1) Insulation Core Resistance Earth Core at 20°C Frame (Core & Frame) Frame (See Note Earth 1) Leakage Reactance (See Note 1) Insulation resistance measurement of the winding 13. 14. 15. Polarization Index *PI test not applicable for oil based transformers. Insulation resistance measurement of the core 1. Pattern for all phases overlapping each other except yellow phase slightly lower at frequency between 100kHz to 1kHz. 2. Same pattern when compared with FAT result or sister unit. IR at 1 minute > 1G IR at 1 minute > 1G IR at 1 minute > 1G IR at 1 minute > 100M Leakage reactance measurements are performed by short-circuiting the low voltage winding. This test also named as short circuit impedance test. The results must within 3% of the nameplate values. The test shall be performed using a 5 kV insulation tester. The following measurement shall be recorded: 1. Between Primary and Earth 2. Between Secondary and Earth 3. Between Primary and Secondary 4. Between Tertiary and Earth > 1.2 (R10/R1min) Note 1: These test shall be carried out by TNB in the presence of the contractor. The contractor shall assist in preparing the transformer for this test. Oil and Winding Setting for Power Transformer ONAN/ONAF STAGE 1 - FANS STAGE 2 - FANS (WHERE USED) STAGE 1 - ALARMS STAGE 2 - TRIPS OTI(TOP OIL ) ON 0C OTI(TOP OIL ) OFF 0C WINDING (HOT SPOT) ON 0C 65 55 70 WINDING (HOT SPOT) OFF 0C 60 70 60 75 65 90 105 80 95 95 120 85 110 & ! "# $ $ ONAN/ODAN/ODAF OTI(TOP OIL ) ON 0C OTI(TOP OIL ) OFF 0C WINDING (HOT SPOT) ON 0C 65 70 90 105 55 60 80 95 70 75 95 120 STAGE 1 - PUMPS STAGE 2 - FANS STAGE 1 - ALARMS STAGE 2 - TRIPS Table N1(a) WINDING (HOT SPOT) OFF 0C 60 65 85 110 d. All Automatic Voltage Regulating (AVR) Relay shall be tested as in Appendix M. e. For the transformer oil, PM shall ensure that the following tests are conducted on the sample of oil for all compartment (Main tank, cable box, OLTC) sent for laboratory test and recorded clearly in the test form. The following are the test required for the transformer insulating oil. The test value(s) shall conform to the limits specified below: No 1 Property Absolute Moisture Content in ppm (Not temperature corrected) Limits Highest Voltage for Equipment (kV) 72.5 – >170 170 < 10 ≤ 0.03 ≤ 0.03 IEC 422 Min 40 Min 40 IEC 422 IEC 422 Acidity (mg KOH/g) 3 Interfacial Tension (mN/m) 4 Colour ≤ 2.0 ≤ 2.0 5 Dielectric Dissipation Factor at 90°C Max 0.015 Max 0.015 Density Test 7 Inhibitor Content 8 Electric Strength, kV (breakdown voltage) IEC 422 < 10 2 6 Test Standard IEC 422 Max 0.895 g/ml Max 0.895 g/ml IEC 296 Not detected Not detected - > 60 > 60 IEC 422 10 Polybuthene oil test for cable box Max 60mg/kg IEC 60963 11 Carbon content Cp (Paraffinic Content<50%) – Naphthenic Oil. " ! "# $ $ f. The following mechanical test shall be conducted and recorded clearly in the test form. The test value(s) shall conform to the requirements specified below: No 1 Test Oil leak test Condition The transformer shall be able to withstand a pressure of 30 kPa / 0.3 Bar from the top of conservator filled with oil for 24 hours with no oil leakage and no permanent deformation on the structure. g. The following functional test/check shall be conducted and recorded clearly in the test form: i. ii. iii. iv. Transformer guard check – all alarm, indication, flags, facia and relay operation at transformer, relay panel and control panel shall be recorded clearly. Actual operation for each signal of all transformer guards shall also be checked and mentioned except for PRD. PRD functional check shall be conducted by simulation. Oil level indicator shall be functional. Oil Level (if any) shall be within permissible range. Pressure gauges shall be check to be functional. (if applicable) All temperature indicators shall be operational. v. OLTC Check The OLTC shall be check to be operational for: a) Step by step b) Out of step c) Transformer paralleling scheme check d) Individual Oil Filter (where applicable) vi. Cooler control check The cooler operation and indications which comprise of pumps and fans shall be checked for the following status: a) Local b) Auto c) Remote The time delay between pumps operation (where applicable) shall be more than 3 sec. vii. To ensure/verify transformer guard relays contacts making or not. ' ! "# $ $ 6.0 Earthing Transformer Testing 6.1 Test Form Requirement a. All general information as required in Appendix A. b. At least the following details of the switchgear shall be mentioned: i. ii. iii. iv. v. vi. vii. viii. ix. x. 6.2 Testing Required EarthingTransformer make Earthing Transformer type Vector Group Capacity Impedance Ratio Serial No Rated Voltage Date of manufacture Short Circuit Rating Following are the test required to pre-commission the earthing transformer: a. All testing required/recommended by the manufacturer of the earthing transformer and its accessories shall be conducted and recorded clearly in the test form. b. In addition, all the following physical check shall also be conducted and recorded clearly in the test form. i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. c. Check for any corrosion, damage or defect Co-coordinating gaps (alignment and gap measurement) where applicable Labeling or nameplate. Earth connections Explosion vent / pressure relief device Bucholz relay Breathers (properly inspect for leaks, silica gel and etc.) Valves in operational positions Correct oil levels in main tank conservator Missing components Ensure all terminal blocks, oil level gauges and other accessories are fully sealed/moisture and vermin proof The following electrical test shall be conducted and recorded clearly in the form. The test value(s) shall conform to the limits specified below. No Test 1 Insulation resistance Details The test shall be performed using an insulation tester. The following measurement shall be recorded: 1. Between Primary and Earth (5 kV) 2. Between Secondary and Earth (1 kV) 3. Between Primary and Secondary (5 kV) Limit IR at 1 minute > 1G . ( ! "# $ $ 2 Turns Ratio Ratio of HV: LV windings 3 Impedance Voltage Winding resistance (DC) % Measurement of zero and positive sequence impedance Measurements of winding resistance at all tap positions 5 Winding Power Factor (See Note 1) 6 Oil Power Factor (See Note 1) 7 Vector Group Measurement of Power Factor of windings. Correction factor to follow IEEE C57.12/90 – 1995 Measurement of Power Factor of Oil. Correction factor to follow IEEE C57.12/90 – 1995 Vector Group of the transformer 8 Polarization Index 4 *PI test not applicable for oil based transformers. The test shall be performed using a 5 kV insulation tester. The following measurement shall be recorded: 5. Between Primary and Earth 6. Between Secondary and Earth 7. Between Primary and Secondary 8. Between Tertiary and Earth Within 0.5% of nameplate ratio of the rated voltage. +2% of FAT Within +5% between phases after correction to 75oC < 0.5% at 20°C < 0.1% at 20°C Vector diagram obtained from measurement shall be equal with manufacturer’s vector diagram. > 1.2 (R10/R1min) Note 1: This test shall be carried out by TNB in the presence of the contractor. The contractor shall assist in preparing the transformer for this test. d. PM to ensure transformer insulating oil test are conducted on the sample of oil sent for laboratory test. The value(s) shall conform to the limits specified below: No 1 2 3 Property Absolute Water Content in ppm (Not temperature corrected) Neutralization Value (mg KOH/g) Interfacial Tension (mN/m) Limit Highest Voltage for Equipment (≤ 72.5 kV) Test Standard < 10 IEC 422 Max 0.03 IEC 422 Min 40 IEC 422 ) ! "# $ $ 4 Color 5 Electric strength, kV (breakdown voltage) 6 Dielectric Dissipation Factor at 90°C Max 2.0 IEC 422 > 60 IEC 422 Max 0.015 e. The following functional test/check shall be conducted and recorded clearly in the test form. i. Transformer guard check – all alarm, indication, flags, fascia and relay operation at transformer, relay panel and control panel shall be recorded clearly. Actual operation for each signal of all earthing transformer guards shall also be checked and mentioned except for PRD. PRD functional check shall be conducted by simulation. ii. Oil level indicator shall be functional. Oil Level (if any) shall be within permissible range. iii. All temperature indicators shall be operational. (if applicable) iv. To ensure/verify earthing transformer guard relays contacts making or not. $ ! "# $ $ 7.0 Neutral Earthing Resistor (NER) Testing a. All general information as required in Appendix A 7.1 Test Form Requirement b. At least the following general information of the NER shall be listed. i. ii. iii. iv. 7.2 Testing Required Make Type Serial Number Rated Resistance a. All testing required/recommended by the manufacturer of the NER and its accessories shall be conducted and recorded clearly in the test form. c. Physical check/inspection to be carried out to check for any : i. ii. Check for any corrosion, damage or defect and galvanizing test. Control cubicle box shall be airtight and sealed for moisture & vermin proof. iii. To confirm no foreign objects (e.g. bar) within the NER. d. Electrical test to be carried out: No 1 2 3 Test Details NER 33 kV & 11 kV Using a 5 kV insulation tester Insulation resistance Resistance To be conducted using 5kV of the NER insulation tester with earth resistor connected and disconnected. NER Testing on Individual Earthing Grounding Rods Resistance Testing after connected to earth grid Limit Measured value > 500 MΩ The value shall conform to the manufacturer’s specified value (± 5%) Ohmic value shall preferable not exceed 10Ω The ohmic value shall not exceed 1Ω $ ! "# $ $ 4 NER Blade Measurement of the contact Switches resistance to be conducted between the contacts and between the arms • Based on factory routine test result/ O&M • Within manufacturer’s recommended / tolerance value as prescribed in Routine test / FAT • Shall be consistent for all blades. $$ ! "# $ $ 8.0 Disconnector Testing 8.1 Test Form Requirement a. All general information as required in Appendix A. b. At least the following general information of the disconnector line shall be listed. v. vi. vii. viii. Rated voltage Rated current Operating mechanism Short circuit rating a. All general information as required in Appendix A. 8.2 Testing Required b. Physical check/inspection to be carried out: i. ii. iii. iv. v. Tightness of connections using correct torque Insulator bushings checks for cracks and chip off Earthing connection Wire and cable connections Cable entrance to control cubicle shall be from bottom, sealed and water proof vi. Heaters and lamps in working order vii. Ensure recommended thermostat temperature setting label is available inside the control cubicle viii. Check for locking facilities (padlock) for both open and close position. ix. Check linkages and gears lubricated c. Mechanical test/check: i. Alignment checks for the operating blades (manual and motor mode) No 1 Test Manual (hand crank) operation of isolator Details Manual closing and opening to confirm contact pressures, contact resistance, simultaneous operation of all phase operation and ease of operation Limit $% ! "# $ $ a. Electrical tests: 8.2 Testing Required (Cont1) No 1 Test Details Contact Minimum 100 A DC resistance for all applied across full phases current carrying path Limit • Based on factory routine test result/ O&M • Within manufacturer’s recommended / tolerance value as prescribed in Routine test / FAT • Shall be consistent for all phases. 2 Auxiliary contact • After completion of alignment & this test, to mark timing test permanently with a straight line both the isolator open and close position. • Timing of Isolator open close To meet factory tolerances. b. Operation, indication and interlock test: i. ii. iii. iv. v. vi. vii. Inspections on the wiring, position indicators, auxiliary switches, terminal blocks and components e.g. Labelling, tightness, colour coding for phases. Manual operation of isolator shall be conducted e.g. manual closing and opening Operational Tests shall be carried out on the operating mechanism including motor drive unit. All recommended values and tested values to be recorded e.g. Duration and switches/protection setting. Control and operation tests to be carried out e.g. Control, protection, alarm and indications circuit. All indications related to the equipment to be tested and proven working. Checks and operation shall be made on the Interlocks and safety features e.g. electrical and mechanical interlocks and safety valves. $ ! "# $ $ 9.0 Current Transformer Testing 9.0 Current Transformer Test Form a. Test Form requirements as per Appendix A. b. At least the following details of the CT shall be listed. i. ii. iii. iv. v. vi. vii. viii. ix. Rated voltage Rated nominal primary current Rated maximum primary current Rated thermal short time current Short circuit rating Insulation Power Factor (IPF) value (factory measured) Serial number for all phases. Manufacturer details, e.g. Make, type, and model. Date of manufacturer. c. The following details of the CT also shall be recorded: CT intended function – e.g. Distance Protection, Metering Ratio - To record all ratios and underline the ratio to be used. Class – e.g. Class 5P20, Class 0.2 etc. Burden (VA) - Burden of the CT Vk - Knee point voltage Im - Magnetizing current Make - Name of the CT manufacturer CT type - CT type or model as provided by the manufacturer Serial No. - Serial no. of the CT unit/phase under test. Phase - CT phase under test – e.g. R, Y, B, N. Rated Voltage - The highest operating primary voltage d. All tests results recorded on the test form shall be crosschecked with the manufacturer’s factory data. 9.1 Inspection & Check Required Note: This section shall be read together with Section 9 of Appendix N1 of this chapter. The following inspections and checks shall be carried out on the CT before any test: Confirm CT details are as per the design and specification requirement. Check nameplate contents are complete. Check nameplate installed on equipment. Check nameplate installed on structure. Physical check on the CT for any damage or defect. Check that bellow cushion has been removed. Confirm the primary positioning of the CT – P1 and P2 are according to the schematic drawing. Check that the CT terminal box is clean and the seal is in good condition and confirm the terminal labelling is as per schematic drawing $& ! "# $ $ Inspection at the Marshalling Kiosk: Check that the ratio selection (for a multi-ratio CT) is made at the Marshalling Kiosk. Confirm that the star point of the CT is derived at the MK. Confirm the neutral grounding of the CT secondary. Check for appropriate shorting link All the above inspections and checks shall be recorded. 9.2 Testing Conditions & Restrictions a. The following conditions shall be adhered when performing SAT on CT:i. All access to CT secondary wiring during testing shall be made at the marshalling kiosk (MK). ii. For CTs in which the primary terminals are not accessible at all i.e. transformer bushing mounted CTs, the polarity and the ratio shall be confirmed during the on-load commissioning test. b. The following conditions shall be adhered when performing SAT on CT:- 9.3 Testing Required i. All access to CT secondary wiring during testing shall be made at the marshalling kiosk (MK). ii. For CTs in which the primary terminals are not accessible at all i.e. transformer bushing mounted CTs, the polarity and the ratio shall be confirmed during the on-load commissioning test. All testing required/recommended by the manufacturer of the CT and its accessories shall be conducted and recorded clearly in the test form. a. Physical check/inspection to be carried out: i. ii. iii. iv. v. vi. vii. b. Inspect physical conditions: no damage, no missing hardware and correct vertical and horizontal alignment Correct oil level and consistence between all phases Check for oil leak (if applicable); Verify correct mounting of the CT, earth connections and electrodes Check cable entrance for tidiness, protection from sharp metallic edges, no injury in insulation and vermin proof. Visual check of primary and secondary circuits against approved drawings. Using circuit diagram, check that P1 and P2 primary terminals are correctly connected Electrical tests to be carried out: i. DC Insulation Resistance test • Between primary and earth (5 kV) • Between secondary and earth (1 kV) • Between primary and secondary (5 kV) ii. Polarity test • All tappings shall be flick tested • For CT polarity tests using the flicking method, analog voltmeters shall be used. $" ! "# $ $ iii. Measurements of the CT resistances • shall be taken at the CT terminal. • For CTs used in high impedance protection schemes, loop resistance measurements shall be made on all current transformers. • Lead resistance and all measurements shall be recorded on the lead resistance diagram. iv. Magnetisation test • A minimum of 10 readings shall be obtained to plot the magnetization curve. • The curve shall be plotted immediately and compared with the factory test report and the comparison to be recorded. • The knee point voltage from the plotted magnetization curve shall be identified and compared with the rated value. This comparison shall be recorded. • Magnetization curves for all CT phases meant for a specific protection/function shall be plotted on the one graph only. This is to confirm that the CT characteristics match. This confirmation shall be recorded. • For CTs where the knee-point is above 2kV, the saturation point from factory test report shall be acceptable. • Effect of remenance flux shall be minimised during the test. v. Ratio Test • This test shall only be carried out after the completion of the above tests. • For multi-ratio CTs, all ratios shall be checked. The ratio that is intended for use shall be tested last. • The rated burden of the CT shall be connected during the ratio check. • The primary current value shall be equivalent to the rated value or 600A whichever is lower. • Ratio test may be repeated after performing demagnetization test incase ratio test failed. vi. Power Factor No 1 Test Details Power Factor To check uniformity of results due to transportation and storage in relation to factory results. The values shall be referred at the rated frequency. Test voltage is to be 10kV at power frequency. Record the correction factor to 20°C and record the temperatures. For all phases, record the value of IPF corrected to 200 C. vii. Limit 1) <0.5% at 20°C 2) Power factor for all three phases <100% difference between phases. Test done by TNB with presence of Contractor/OEM Capacitance measurement • Measurement of capacitance shall be as a finger print test as a reference value for end of warranty test. $' ! "# $ $ Test done by TNB with the presence of the contractor. viii. 10.0 Additional test for interposing Current Transformer (ICT) • Vector group test - Only for ICT used in Differential Protection scheme. • Impedance test - Only for ICT used in Differential Protection scheme. i. Measurement of Positive Sequence Impedance ii. Measurement of Zero Sequence Impedance Voltage Transformer Testing (Capacitive / Inductive) a. Test Form requirements as per Appendix A. 10.1 Capacitive / Inductive Voltage Transformer Test Form b. The following details of the VT shall be recorded. VT intended function – e.g. Distance Protection, Metering Ratio - To record all ratios and underline the ratio to be used. Class Burden (VA) - Burden of the VT Make - Name of the VT manufacturer VT type - VT type or model as provided by the manufacturer Serial No. - Serial No. of the VT unit/phase under test. Phase - VT phase under test – R, Y, B. Rated Voltage - The highest operating primary voltage At least the following details of the VT shall be listed. i. ii. iii. iv. v. vi. Rated voltage Serial Number Core number, ratio, Class and Burden Short Circuit rating Capacitive value and associated tolerance Data of manufacturer All test results recorded on the test form shall be crosschecked with the manufacturer’s factory data. At least the following details of the Intermediate Voltage Transformer (IVT) shall be mentioned. Winding & Ratio Serial No. Nominal Intermediate Voltage 10.2 Inspection & Check The following inspections and checks shall be carried out on the VT before any test: $( ! "# $ $ Required a. Confirm VT details are as per the design and specification requirement. Check nameplate contents are complete. b. Physical check on the VT for any damage or defect. c. Check that bellow cushion has been removed. d. Confirm the primary positioning of the VT – e.g. a and n are according to the schematic drawing. e. Check that the VT terminal box is clean and the seal is in good condition and confirm the terminal labelling is as per schematic drawing. f. Inspection at the Marshalling Kiosk: Check that the ratio selection (for a multi-ratio VT) is made at the Marshalling Kiosk. Confirm that the star point of the VT is derived at the MK. Confirm that the neutral grounding of the VT secondary. f. Check Oil Level (if any) is within the permissible range g. All the above inspections and checks shall be recorded. 10.3 Testing Required a. All on-site tests as recommended in the VT manual. b. All testing required/recommended by the manufacturer of the VT and its accessories shall be conducted and recorded clearly in the test form. c. Physical check/inspection to be carried out. i. Check correct oil level (if applicable); ii. Verify satisfactory mounting of the VT, earth connections and electrodes iii. Inspect physical conditions: no damage, no missing hardware and correct vertical and horizontal alignment iv. Check cable entrance for tidiness, protection from sharp metallic edges, no injury in insulation and vermin proof. v. Visual check of primary and secondary circuits. d. Electrical tests to be carried out for capacitive VT: No Test 1 Capacitance measurement Details Total Capacitive measurement Limit Capacitance ±5% variance from nameplate/factory measurement. Test done by TNB with presence of Contractor/OEM $) ! "# $ $ 2 Insulation resistance test The test shall be conducted between: No disruptive discharge Consistent for all phases >10MΩ **Polarization Index to Secondary to earth (1kV) be performed if value <10MΩ Primary to earth (5kV) Primary to Secondary(5kV) 3 Ratio test at least 1% of the primary rated voltage shall be injected and all windings shall be tested 4. Power Factor To check uniformity of results due to transportation and storage in relation to factory results. The values shall be referred at the rated frequency. Test voltage is to be 10kV at power frequency. Record the correction factor to 20°C and record the temperatures. For all phases, record the value of IPF corrected to 200 C. e. Within manufacturer’s recommended / tolerance value as prescribed in Routine test / FAT 1) <1% at 20°C 2) Power factor for all three phases <100% difference between phases. *Test to be done without isolating EMU from capacitive divider. Test done by TNB with presence of Contractor/OEM Electrical tests to be carried out for inductive VT: No 1 2 3 4 Test Power Factor (C1) Capacitance (C1) Details Measurement of power factor of the IVT. Total Capacitive measurement Insulation resistance test The test shall be conducted between: Ratio test Limit <0.5% at 20°C Not to exceed ±5% variance from FAT test measurement. No disruptive discharge • Primary to earth (5kV) Consistent for all phases • Secondary to earth (1kV) • Primary to Secondary(5kV) >10MΩ **Polarisation Index to be performed if value <10MΩ at least 1% of the primary rated voltage shall be injected and all windings shall be tested Within manufacturer’s recommended / tolerance value as prescribed in Routine test / FAT % ! "# $ $ 10.4 Additional Check Check name plate installed on equipment. Check name plate installed on structure. Check both name plates are complete and in order. Confirm single pole MCB (one MCB for each phase) is used at MK for all VT circuits. Confirm alarm is provided if the MCB is tripped. Record rating of fuses/MCB at VT boxes. Records rating of single pole MCB at MK. Ensure the rating of MCB’s and fuses are discriminated accordingly. Confirm grounding of VT secondary is done at the VT. Confirm grounding of Intermediate VT is according to manufacturer recommendation except for CVT with line coupling unit for PLC equipment for all phases. Check ground switch is closed when PLC equipment not in use for all phases (if available) Check voltage tap ground switch is kept open for all phases. 10.5 Special Tests for Inductive Voltage Transformer 11.0 For Inductive VT testing, where applicable, the above requirement shall apply. Induced Voltage Test at rated secondary voltage. Necessary precautions shall be taken during this test. Capacitor Bank Testing 11.1 Test Form Requirement a. All general information as required in Appendix A. b. At least the following details of the Capacitor Bank shall be listed. i. ii. iii. iv. v. 11.2 Testing Required Capacitance value Date of manufacture Manufacturer Type Serial number a. All testing required/recommended by the manufacturer of the Capacitor Bank and its accessories shall be conducted and recorded clearly in the test form. b. Physical check/inspection to be carried out: i. ii. iii. iv. v. vi. vii. All live parts (terminals, cap, etc) shall be shrouded Physical check on the equipment for any corrosion, damage or defect Check for correct connection diagram Check for correct labeling Earth connections Tightness of connections using correct torque To check alignment of connections % ! "# $ $ viii. Insulators undamaged and clean ix. Safety clearances x. Check for missing components c. Electrical tests to be carried out after the installation the capacitor shall be tested by the: No 1 Test Capacitance Measurement 2 Internal Discharge Resistor Value Point of wave switching 3 Details Measurement shall be carried out for the following arrangement: • Each Can • Each Stack • Each Phase Limit Within tolerance declared by manufacturer > 20% of factory test value This test shall be carried out by current and voltage injection and CB operation. The performance of CB opening and closing shall be monitored and compared with waveform using disturbance recorder. TNB will assist this test by providing the disturbance recorder and the printout. Analysis of the printout shall form part of the test report. Within tolerance declared by manufacturer. 4. Capacitor can terminalto-terminal insulation resistance test. 1. All values shall exceed 1G . 2. Values shall be consistent for all cans. 5. Capacitor can terminalto-case insulation resistance test. 3. All values shall exceed 1G . 4. Values shall be consistent for all cans. %$ ! "# $ $ 12.0 Surge Arrestor Testing 12.1 Test Form Requirement a. All general information as required in Appendix A. 12.2 Testing Required a. All testing required/recommended by the manufacturer of the reactor and its accessories shall be conducted and recorded clearly in the test form. b. At least the following details of the Surge Arrester shall be listed i. Rated voltage (kV) ii. Continuous volt (kV) iii. Nominal discharge current (kA) iv. Short circuit rating v. Leakage current vi. Serial number of each phase vii. Type, e.g. zinc oxide, gapless, gap, etc. viii. Date of manufacture ix. Class b. Physical check/inspection to be carried out: i. ii. iii. iv. v. vi. vii. viii. Verify correct mounting of the SA, counter, earth connections and electrodes. Verify that the pressure-relief discharge nozzles are not directed as to harm neighboring equipment when they operate. Verify that the earthing connections are as straight and short as possible so as not to reduce the SA protective level & to avoid high frequency phenomenon during surges. Verify the insulated connections from SA earthing terminal to surge counter and leakage current meter. Verify that the edge-to-edge distance between grading rings conforms to the required phase-phase distance. Inspect physical conditions: no damage, no missing hardware and correct vertical and horizontal alignment Verify that the SA base is insulated from the equipment structure. The counter display shall be visible, free from crack and moisture condensation %% ! "# $ $ 12.2 Testing Required (Cont1) c. No 1 2 Electrical tests to be carried out: Test DC Insulation Resistance Test Watt Loss Details To indicate condition of arrester housing and elements, this can be compared to other similar units unless moisture, foreign deposits or other contamination are present. The test shall be conducted between primary terminals to earth of all phases using a 5kV insulation tester Measurement of Watt Loss Limit >100 M <0.1W (TNB suggested limit) Test done by TNB with presence of Contractor/OEM % ! "# $ $ 13.0 Sealing End Testing 13.1 Test Form Requirement c. All general information as required in Appendix A. d. At least the following details of the Sealing End shall be listed i. ii. iii. Rated voltage (kV) Serial number of each phase Date of manufacture ______________________________________________________________ 13.2 Test Required a. All testing required/recommended by the manufacturer shall be conducted and recorded clearly in the test form. b. Physical check/inspection to be carried out: i. ii. iii. iv. Physical check on the equipment for any corrosion, damage or defect Labeling Earthing connections Missing components a. Electrical tests for dry type reactor to be carried out: No 1 Test Insulation Resistance Details The test shall be performed using a 500 V insulation tester except for HV – E, 5 kV insulation tester shall be used. The following measurement shall be recorded: 1. Between Primary and Earth Limit All values shall exceed 200 MΩ %& ! "# $ $ 14.0 Reactor (Oil Immersed Type) Testing 14.1 Test Form Requirement a. All general information as required in Appendix A. b. At least the following details of the Reactor shall be listed i. ii. iii. iv. v. vi. vii. viii. Rated voltage Rated current Short circuit rating Operating mechanism Capacity Manufacturer Manufactured Date Impedance a. All testing required/recommended by the manufacturer of the Surge Arrestor and its accessories shall be conducted and recorded clearly in the test form. 14.2 Testing Required b. Physical check/inspection to be carried out: i. ii. iii. iv. Check on the equipment for any corrosion, damage or defect. Impact Recorder Reading. Inert gas pressure. Co-coordinating gaps (alignment and gap measurement) where applicable. v. Labelling vi. Earthing connections vii. Explosion vent / pressure relief device viii. Breathers ix. Valves in operational positions x. Tightness of fastenings xi. Insulators/bushings undamaged and clean xii. No oil leaks. xiii. Correct oil levels in main tank conservator xiv. Safety clearances. xv. Missing components xvi. Ensure all terminal blocks, oil level gauges and other accessories are fully sealed/moisture and vermin proof %" ! "# $ $ c. 14.2 Testing Required (Cont1) Electrical tests to be carried out: No Test 1 Insulation Resistance 2 Winding Resistance (DC) 3 Winding Power Factor Bushing Power Factor (If Applicable) 4 Details Limit The test shall be IR at 1 minute > 1G performed using 5 kV insulation tester. The following measurement shall be recorded: between Primary and Earth. 1. Within +5% between phases after correction to 75°C 2. Consistence between phases Test done by TNB with presence of Contractor/OEM Measurement of Power < 0.5% at 20°C Factor of all windings Measurement of Power For C1: Factor of Bushing 1. < 0.7%. 2. Power factor for all three phases <100% difference between phases. ∗ For any bushing where the power factor difference exceeds 100%, to be replaced. For C2: 1. C2 bushing power factor < 5% Capacitance change +5% from FAT result (Test done by TNB in the presence of the contractor.) 5 Oil Power Factor Measurement of Power < 0.1% at 20°C Factor of oil Test done by TNB with presence of Contractor/OEM %' ! "# $ $ d. Following are insulating oil tests: No 1 2 3 Property Absolute Water Content in ppm (Not temperature corrected) Neutralization Value (mg KOH/g) Interfacial Tension (mN/m) 4 Color 5 Electric strength, kV (breakdown voltage) 6 Dielectric Dissipation Factor at 90°C Limit Highest Voltage for Equipment (≤ 72.5 kV) Test Standard < 10 IEC 422 Max 0.03 IEC 422 Min 40 IEC 422 Max 2.0 IEC 422 > 60 IEC 422 Max 0.015 e. Functional test: 14.2 Testing Required (Cont2) ii. iii. iv. v. vi. vii. viii. ix. f. All testing required/recommended by the manufacturer of the reactor. Calibration of all oil and winding temperature indicators. Cooling fan and/or pump operation check- if provided Reactor guard check – all alarm, indication, flags, fascia and relay operation at reactor, RCC, relay panel and control panel to recorded clearly. Simulation method for each signal shall also be mentioned. Check name plate provided on equipment Check Oil Level (if any) is within permissible range. Audible sound level test. Vibration Test Mechanical tests: No 1 Test Oil leak test Condition The reactor shall be able to withstand a pressure of 30 kPa / 0.3 Bar from the top of conservator filled with oil for 24 hours with no oil leakage and no permanent deformation on the structure. %( ! "# $ $ 15.0 Reactor (Dry Type) Testing 15.1 Test Form Requirement a. All general information as required in Appendix A. b. At least the following details of the Reactor shall be listed ix. x. xi. xii. xiii. xiv. xv. xvi. 15.2 Test Required Rated voltage Rated current Short circuit rating Operating mechanism Capacity Manufacturer Manufactured Date Impedance a. All testing required/recommended by the manufacturer of the Reactor and its accessories shall be conducted and recorded clearly in the test form. b. Physical check/inspection to be carried out: v. vi. vii. viii. c. Physical check on the equipment for any corrosion, damage or defect Labeling Earthing connections Missing components Electrical tests for dry type reactor to be carried out: No 1 Test Insulation Resistance 2 Impedance @ rated voltage Insulation Power Factor 3 Details The test shall be performed using a 500 V insulation tester except for HV – E, 5 kV insulation tester shall be used. The following measurement shall be recorded: 2. Between Primary and Earth Limit All values shall exceed 200 MΩ Standards TNB standard Limits within ±5% TNB standard TNB standard Test done by TNB with presence of Contractor/ OEM. %) ! "# $ $ 16.0 Switchyard Installations Testing 16.1 Test Form Requirement a. All general information as required in Appendix A. b. At least the following details of the switchyard installations shall be listed. i. ii. iii. iv. v. vi. vii. 16.2 Testing Required Busbar capacity Down dropper sizes Connectors make Earthing system Gantry Earth mast Switchyard lighting a. All testing required/recommended by the manufacturer of the switchyard installations and its accessories shall be conducted and recorded clearly in the test form. b. Physical check/inspection: i. ii. Phasing connection check Check for proper feeder and switching device labelling, e.g. use of aluminum, embossed and proper size and riveted. iii. Check phase indication color iv. Check bolts tightness (correct torque) v. Surface contact for earthing conductor vi. Tinning of copper interfaces with other metals vii. Visual inspection of busbar alignment viii. Check on galvanizing, rust, etc. ix. Earthing connection as per engineering approval x. Visual inspection of earthing connections at the steel structure for tidy workmanship xi. Check all fitting tightness for insulators and bushing (correct torque) xii. Check all welded points where applicable. xiii. Ensure all bolts and nuts are tied with washers and spring washers in correct position. xiv. Ensure exposed earth tape painted completely. xv. Check marshalling kiosks for sealed door, proper ventilation, functioning heater and lightings. xvi. Electrical, safety, statutory and ground clearances to conform to specification. xvii. Check of no broken strands, no rubbing between earth mast conductors, and correct fittings of earth masts. xviii. All connections shall be treated with contact grease/paste and free from water collection and rust. Clamp shall be cleaned by emery paper / metallic wire brush. xix. To check bi-metal link application for aluminum-copper. xx. To ensure lighting arrester to be removed at gantry with SA xxi. To check Stone chipping thickness shall be more than 150mm xxii. Flexible busbar and connection shall be checked to ensure that the correct tensions, sags and clearances will be maintained in different environmental conditions and loads without stress to other equipment. xxiii. Rigid busbar and connections shall be checked to ensure that there will be no overloading of the supporting insulators under load conditions and under different environmental conditions xxiv. Busbar clamp type installed as per TNB approval – e.g. Expansion, ! "# $ $ Sliding, fixed and contraction is accommodated by flexible connections. 16.2 Testing Required (Cont1) c. Electrical/mechanical test to be carried out: i. Torque measurement shall be carried out on all flexible conductor, connections ii. Contact resistance test shall be carried out on all flexible busbar, connections and joints, which are made at site. This may be carried out as a complete circuit test of a bay and the reading between phases shall be uniform. d. Earthing check/test: i. Test shall be made on the effectiveness of the bonding and earthing connections. ii. Checks shall be also made on precautions taken to avoid corrosion attack on the earthing system. iii. The earth resistance shall be measured and recorded as follows: a) Earth grid after completion and backfilling of the trenches. Value shall be less than 1Ω. b) Individual earth rods resistance measured shall preferably be less than 10Ω for SA, NER and Transformer HV Neutral. ! "# $ $ 17.0 11kV and 33kV Switchgear Testing 17.1 Test Form Requirement a. All general information as required in Appendix A. b. At least the following details of the metalclad switchgear shall be listed. i. ii. iii. iv. v. vi. vii. Rated voltage Rated current Operating mechanism Serial number Model Manufacturer Date of manufacture a. All testing required/recommended by the manufacturer of the metalclad switchgear and its accessories shall be conducted and recorded clearly in the test form. 17.2 Testing Required b. Physical check/inspection: i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. Proper labeling on panel front, rear and CB truck. Earthing switch connected to earth grid. Busbar shutter operation and VCB truck alignment and racking in/out Cable entry e.g. Proper clamping and sealed Dust and Vermin proof i.e. all holes shall be covered externally and internally, including the earth switch-operating rod (rubber lining for door and boot for the earth-operating rod to be installed. Tightness of connections using correct torque Earthing connection Wire and cable connections Cable entrance to control cubicle shall be from bottom, sealed and water proof Heaters and lamps in working order Ensure recommended thermostat temperature setting label is available inside the control cubicle Locking facilities $ ! "# $ $ c. 17.2 Testing Required (Cont1) Electrical test to be carried out: No 1 Test Power frequency withstand test (AC pressure test) Details Test voltage equals 70 kV for 33kV S/G, 50 kV for 22kV S/G and 28 kV for 11 kV S/G for 1 minute. Test to be performed on busbar inclusive of circuit breaker in closed and open position 2 CB Timing test 3 Insulation resistance of the busbar & individual CB before and after power freq. test Vacuum check on vacuum bottle. Contact resistance measurement on breaker. Complete circuit loop resistance measurement. 4 5. 6. This test shall be conducted on each phase with the 2 remaining phases earthed. To check for closing & tripping time, closing and tripping coil current. check synchronism of main contacts for all phases. • Close and trip timing • C-O timing. Testing conducted by using a 5 kV insulation tester Limit No flashover shall occur. Stable leakage current readings. This test shall be conducted under stage 4 (after completion of all tests). As manufacturer’s recommended tolerance. More than 1 G No discharge. Consistent value As manufacturer’s recommended tolerance Minimum of 100amps DC shall be applied. To conform to the routine tests value Minimum of 100amps DC shall be applied. Measured value for all phases shall be consistent. This test shall be performed for complete circuit with isolators and CB for each phase. % ! "# $ $ d. Operation, indication and interlock test: 17.2 Testing Required (Cont2) i. ii. iii. iv. v. vi. vii. viii. Inspections on the wiring, position indicators, auxiliary switches, terminal blocks and components e.g. labelling, tightness, color coding. Insulation test of control wiring and auxiliary devices. Manual operation of switchgear shall be conducted e.g. slow closing, manual spring charging, and manual tripping. Operational Tests shall be carried out on the spring operating system. All recommended values and tested values to be recorded e.g. Duration, switches/protection setting and counter readings Control and operation tests to be carried out e.g. Control, protection, alarm and indications circuit All indications related to the equipment to be tested and proven working Checks and operation shall be made on the Interlocks and safety features e.g. Electrical and mechanical interlocks and safety valves e. Special requirements for 33kV & 11KV SF6 insulated switchgears. i. All testing required/recommended by the manufacturer of the 33kV & 11kV SF6 insulated switchgear and its accessories shall be conducted and recorded clearly in the test form. ii. To check for SF6 gas leak. iii. Insulating medium test (SF6) as follows: No 1 ! "# 2 Test Moisture Content SF6 purity test 3 S02 Content $ $ Details SF6 dew point test Limit < -23o C To check composition of > 97% SF6 gas at every compartment To check S02 content < 12ppmv inside each compartment 18.0 Standby Diesel Engine Driven Generator a. All general information as required in Appendix A. 18.1 Test Form Requirement b. At least the following detail of the generator shall be listed i. Make ii. Type iii. Serial Number iv. Rated Voltage v. Date of manufacture vi. Continuous output kW vii. Continues output KVA a. All testing required/recommended by the manufacturer of the Standby Generator Standby Diesel Engine Driven Generator and its accessories shall be conducted and recorded clearly in the test form. 18.2 Test Required b. Physical check/inspection to be carried out: i. ii. iii. iv. v. vi. vii. viii. ix. x. Visual inspection on engine, alternator, radiator, and various systems of the generating set Visual inspection on Control Cubicle Visual inspection on welding surfaces and primer coating for Underground/ Daily Services Fuel Tank Physical check on the equipment for any corrosion, damage or defect Proper labeling Effective and adequate earth bonding have been provided for the engine and alternator. Missing components Tightness of connections using correct torque Wire and cable connections Locking facilities c. Electrical/ Mechanical tests for Standby Generator Standby Diesel Engine Driven Generator to be carried out shall include but not limited to: 1. Tests on the wiring installation in accordance with Section E of the IEE Regulations including tests on the earthing system. 2. Earth electrode resistance tests to the general mass of earth 3. Check of insulation resistance for all electrical machines 4. Check for correct operation of fuel oil system 5. Check for correct lubricant and coolant levels. 6. Battery charger output test 7. Check for correct operation of the following: i) Governor and engine speed adjustment. ii) All safety devices. iii) All manual controls. iv) All alarms, indicators, instruments, meters and gauges. v) Voltage regulation. & ! "# $ $ 8. Load Test - Up to 8 hours reliability trial run shall be carried out by the contractor. This trial run may have to be carried out at night, possibly after midnight. The contractor shall provide a resistive load of sufficient capacity for this test. All necessary fuel required for such test shall be furnished by the contractor at his own expense. 9. Load transfer test 10. Meter readings, gauge readings, satisfactory operation of all devices, manual controls, etc., shall be noted and included on the test certificates. 11. Acoustic noise level measurement shall not exceed 70dB at 1 meter from enclosure wall " ! "# $ $ SAT Appendix K: SAT for Lines and Cable 1.0 2.0 3.0 Purpose ........................................................................................................................1 Transmission Line Testing ............................................................................................1 Power Cable Testing ....................................................................................................6 To provide SAT requirements when carrying out Lines and cable test 1.0 Purpose 2.0 Transmission Line Testing a. All general information as required in Appendix A. 2.1 Test Form Requirement b. At least the following details of the switchgear shall be mentioned in test sheet: i. ii. iii. iv. v. vi. vii. viii. ix. Name of line Lines rating, capacity, voltage Conductor Type Earth wire / OPGW Total number of towers Type of towers Route length All electrical, safety, ground and statutory clearances to be declared. GPS coordinate c. At least the following details of the transmission line shall be listed for each tower inspected i. Tower Type (inc details of Body & Leg Extension) ii. Tower Number iii. Date of Inspection 2.2 Testing Required before OHL commissioning a. All testing required/recommended by TNB and the manufacturer of the transmission lines and its accessories, shall be conducted and recorded clearly in the test form b. Physical check/inspection: ! "# i) Rentice a) Measurement of width of rentice b) Undergrowth removal (to be maintained within 300mm) c) Danger trees to be cleared d) Debris leftover to be cleared e) Centerpath within the rentice f) Electrical, safety, statutory and ground clearances to conform to specification g) Activities and permanent structures h) Any crossing (River, road, utilities, railways) ii) Conductor/Earth Conductor/OPGW a) Damage/broken strands b) Number of mid span joint c) Earth wire bonding / jumper d) Condition of armour rod (if applicable) $ $ 2.2 Testing Required before OHL commissioning (Cont 1) e) Phase Jumper iii) Foundation a) Soil erosion b) Concrete surface for cracks c) Drainage d) Turfing e) Foundation frustrum iv) Tower Earthing System a) Design of Tower Earthing (as per drawing) b) Type of counterpoise c) Type of rod d) Connection of counterpoise and rod (must be by EXOTHERMIC welding only, no U-Bolts are allowed) e) Paint f) Soil Resistivity measurement g) TFR measurement v) Lattice structures a) Tightness of bolts, nuts and washers and minimum of 3 bolt threads leftover. (To be checked using torque wrench) b) Step bolts above ACD c) Galvanising (more than 86 micron) and paint d) Vandal proof bolts and nut e) Check for Missing member f) Painting of chimney cap g) Phase plate h) Airborne plate i) Anti-climbing device (ACD) j) Danger plate k) Rest platform l) Tower painting if applicable vi) Insulators (cap & pin) a) Check for Zinc sleeve for all towers (porcelain/glass) All insulators supplied are with zinc sleeve b) Insulator details per string (i.e. quantity, type of insulator etc.) c) Physical condition (crack, cleanliness, broken, chip) d) Uniform and even surface of cement base (at pin area) prior to installation vii) Insulators (composite) a) Insulator details per string (i.e. quantity, type of insulator etc.) b) Physical condition of rubber sheds (crack, cleanliness, broken, chip) c) End fitting seal (rubber to the metal fitting interface area at both end) viii) Tower Lightning arrester (TLA) a) Tower number (where it is supposedly to be installed). $ ! "# $ $ 2.2 Testing Required before OHL commissioning (Cont 2) b) c) d) e) f) Installation arrangement -phases on tower (as per instructed arrangement) Gap distance (as per OEM’s recommendation & drawing) Tightness of bolts, nuts and washers Downlead conductor to connect to tower body (for wooden/composite crossarms) Fault indicator, if any (proper installation) ix) Fittings a) Earthwire 1. Tightness of bolts, nuts and washers 2. Installation of split pin for D-shackles 3. Spiral damper for OPGW 4. Vibration damper for ACSR Skunk 5. Downlead clamp for OPGW earthwires b) Conductor 1. Number of spacers or spacer damper for phase conductors 2. Quantity and type of vibration dampers for both phase conductor and earth wire 3. Tightness of bolts and nuts for jumper tube 4. Spacer damper and damper installation shall be as the approved placement chart. c) Insulator 1. Installation of locking device - W clips (R clips stainless steel for 500kV) 2. Tightness of bolts, nuts and washers 3. Vertically of string shall not deviate more than 2 degrees (for single suspension string) 4. Split Pins x) Torque check at all electrical connections/fittings e.g. jumper, dropper and landing to be recorded. xi) OPGW joint box to be located at the middle cross arm and 3 meter above the ground on substation gantry (subjected to alteration) with the facility to be lowered to ground level and equipped with sufficient down lead clamp. xii) ADSS for sag and proper fitting to tower body xiii) Solar panel and battery, control panel, light, cable and aircraft warning spheres. c. Electrical check / test i) Test for Optical Fibre Cables/OPGW No Test Details 1 Total A laser source and power Attenuation meter shall be used for Test these attenuation measurements. End to end test to check the continuity of each fibre. The measurement shall be done from both ends and the average computed. Test shall be done with two wavelength, 1310nm and 1550nm. Limit The value shall be less than Calculated Value. Formula: Value < Cxd + Sxn + Kxk C=Fibre Cable Lost (constant) d=Fibre Cable Length S=Splice Loss in dB (constant) n=Number of splices K=Connector Loss in dB (constant) k=Number of Connector % ! "# $ $ 2.2 Testing Required before OHL commissioning (Cont 3) C=0.40dB/km at 1310nm wavelength 0.25dB/km at 1550nm wavelength S=0.10dB for both wavelength K=0.50dB for both wavelength 2 ii) Splice Loss Test An optical time domain reflectometer (OTDR) shall be used for these attenuation measurements. The measurements shall be recorded by a printer. The optical loss measured shall not exceed the specified maximum allowable attenuation for the per unit loss. Test shall be done with two wavelength, 1310nm and 1550nm. The value shall not be more than 0.10dB. Measurement of TFR (using high frequency equipment): a) One measurement on each erected tower before stringing, without earth connection. b) One measurement on each erected tower before stringing, complete with earth connection. - using Fluke & Chauvin Arnox. Only this two brands of earthing measurement equipment suitable for the application of Transmission towers are acceptable and allowed to be used. - Limits of 10 ohms for 132kV & 275kV, 5 ohms for 500kV Limits of 5 ohms for all Monopoles iii) Line test/check a) Line Impedance b) Induced voltage measurement c) Insulation resistance test d) Phasing test e) D.C Resistance test iv) Measurement to be carried out on conductor/earth/OPGW conductor: No 1 Test Conductor sagging Details Sagging measurement of each conductor at the lowest point is to be carried out and properly recorded. Limit Shall not depart from the correct erection sag by more than -4% and conductors forming the pairs in each phase shall not differ from each other by more than 40 mm 2 Conductor to connector resistance Resistance measurement of each jumper, dead end clamp and mid span joint to be carried out and properly recorded. Resistance of any such ittings shall not exceed 75% of the resistance of an eqv. length of conductor,measured adjacent to the fitting, and the current carrying capacity shall be at least 100% of that of the conductor. Conductor resistance values:Curlew – 0.0548 /km ! "# $ $ Zebra – 0.0674 /km Batang - 0.08914 /km Wolf – 0.1828 /km Skunk – 0.4566 /km TACSRCurlew-0.0434 TACSR Zebra- 0.0534 ACCC Lisbon- 0.0887 ACCC Dublin- 0.0534 /km /km /km /km ACIR 275kV – 0.0674 /km ACIR 132kV – 0.0892 /km For other conductors please refer to manufacturer’s declared values. d. Functional Checks i) ii) iii) iv) Air craft warning light system Bulb Photocell Charger & ! "# $ $ 3.0 Power Cable Testing a. All general information as required in Appendix A. 3.1 Test Form Requirement b. At least the following general information of the power cable shall be listed. i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. Cable (insulation) type Cable length Route length Cable Rating ( Voltage, MVA) Short circuit rating No of feeders Conductor size No of core Sheath bonding (direct earth or open end) Date of manufacture Pressure Tank details ( No of cells, volume, gas constant) All electrical, safety, ground and statutory clearances to be declared. a. The following requirement shall apply for all type and voltage level above 11kV of Power Cable installation e.g. Transformer tail, transformer cable, feeder cable & interconnector cable, unless stated otherwise. 3.2 Testing Required b. All testing required/recommended by the manufacturer of the cable system and its accessories shall be conducted and recorded clearly in the test form. c. Verification of all buried works e.g. sand bedding, cable depth check, PVC/HDPE pipe class, laying configuration, joint bay layout shall be carried out span by span. d. Physical check/test required: i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii. xiv. xv. xvi. xvii. xviii. xix. xx. Check cable route markers Check cable joint markers. Check link boxes Check of cable tagging i.e. jointers’ ID. Correctly sized earthing bar/leads Verify the labelling of the phases, circuits and feeder name Verify the direction indications of leads Verify the use of sand bedding (span by span check before jointing, by project supervisor). Check pressure of oil. Check for no crack/chip-off at cross bond link boxes. Check for no rust. Verify sufficient clearances are met. Check for all the terminations were done correctly/properly. Check for sufficient creepage distances for terminations. No physical damage/scratch marks at the outer jacket. No oil leak at the cable box. No cracked/split tape at the termination in the oil filled cable box. Verify the use of crimped, cast type cable lugs (for 33kV and 11kV transformer cable tail only). Verify the use of cable slabs (concrete reinforced). Bending radius shall not exceed manufacturer’s specified value. xxi. Check on the trenches (if applicable). " ! "# $ $ • • • • 3.2 Testing Required (Cont 1) xxii. xxiii. xxiv. xxv. Smooth, finished concrete Cable shall not touch the trench corners Trays won’t collapse Ensure no multiple circuits laid on top of each other. Check for Cathodic Protection Check for cable ducting e.g. PVC, HDPE Check on Multiple Cable Transit (MCT) if available Check Cable Bridge (structure, covers, anti-crossing device and signage). e. Electrical tests to be carried out: i. General check • • ii. Phasing check before and after jointing Continuity check Oil Filled Cable (275kV & 132kV) No Test 1 Cable insulation resistance test 2 Sheath insulation test 3 HV pressure test 4 Corrosionresistance covering test Oil flow test 5 6 7 Check of gas constant for Pressure Tank Impregnation coefficient Details Limit The test shall be conducted for the conductor using a 10 kV insulation tester. The test shall be done for every span before jointing works and to be repeated for the complete circuit. Consistent values between phases The test shall be Leakage current shall be less than 10 conducted for the sheath using a 10kV DC mA high voltage test set. The test shall be done for every span before jointing works and to be repeated for the completed circuit. Test voltage applied No discharge between conductor and screen equals to 3.5 Uo DC for 15 minutes Test voltage equals 10 No discharge kV DC applied for 1 min Measurement of the pressure drop Measurement of the pressure drop at PT cells A measured quantity of oil drawn from the cable system and the consequent drop in pressure noted Value compared to the theoretical value Value compared to the theoretical value Impregnation coefficient shall not be greater than 16 x 10 exp -6 ' ! "# $ $ 8 3.2 Testing Required (Cont 2) iii. Earthing resistance test. Measurement of earthing resistance between link box’s earthing terminal to earth. Transition Joint (Hybrid Cable System) No Test 1 Cable insulation resistance test Details The test shall be conducted for the conductor using a 10kV insulation tester. Sheath insulation test 3 Oil Flow test 4 Check on gas constant for pressure tank Oil test (Dielectric Breakdown) BDV Oil test ( Moisture To be done before Content) Jointing AC voltage test Cable on soak for 24 hours 5 6 7 Limit Consistent values between phases The test shall be Leakage current conducted for the shall be less than 1 sheath using a 10kV DC mA (measured per high voltage test set. span) The test shall be done for every span before jointing and to be repeated for the completed circuit. Measurement of Value compared to pressure drop the theoretical value Measurement of Value compared to pressure drop at PT the theoretical value cells To be done before > 60kV jointing 2 iv. The measured value shall be less than 3Ω. < 30ppm No failure or breakdown XLPE Cable (275kV &132kV) No Test 1 Cable insulation resistance test Details Limit The test shall be conducted for the conductor using a 10 kV insulation tester. The test shall be done for every span before jointing works and to be repeated for the completed circuit. Consistent values between phases ( ! "# $ $ 3.2 Testing Required (Cont 3) f. 2 Sheath insulation test The test shall be conducted for the sheath using a 10kV DC high voltage test set. The test shall be done for every span before jointing and to be repeated for the completed circuit. Three phase current of 100 A applied to the phase conductor. The resulting sheath current and voltages to earth at the cross bonding positions are measured 3 Cross bonding test 4 Sheath Voltage Limiter test A DC voltage applied (depend on the type of SVL) between the terminals and earth 5 AC voltage test 6 Earthing resistance test. Cable on soak for 24 hours Measurement of earthing resistance between link boxes to earth. Leakage current shall be less than 1 mA (measured per span) • The sheath current value shall not exceed the declared value by > 3% • The measured voltage shall not exceed 65V IR between SVL and casing shall be ≥ 10MΩ. The leakage current shall be compared against the manufacturer’s data sheet and shall not exceed ± 10% No failure or breakdown The measured value shall be less than 3Ω. XLPE Cable (33kV and below, single core cable for transformer cable tails) No Test 1 Cable insulation resistance test 2 Sheath insulation test 3 AC voltage test Details The test shall be conducted for the conductor using a 5 kV insulation tester The test shall be conducted for the sheath using 10kV DC high voltage test set. Cable on soak for 24 hours Limit Consistent values between phases Leakage current shall be less than 10 mA No failure or breakdown ) ! "# $ $ 3.2 Testing Required (Cont 4) g. Supervisory Telephone Type Pilot Cable. No Test 1 Cable insulation resistance test 2 Conductor resistance measurement. 3 High voltage test. Details The insulation resistance shall be measured between each conductor and the remainder connected together and to the aluminium screen and armour wires. The measurement shall be carried out at 500 volts DC for at least 1 minute. The conductor resistance of each core shall be measured and recorded. Each core shall be tested for 1 minute with the following DC test voltages: • Between the conductors of each twin twisted pair – 15kV. • Between each conductor and the remainder connected together and to the metallic screen, armour wires and earth 25kV. The above test setup shall include termination facilities in the junction box. ! "# $ $ Limit The value shall not be less than 1 GΩ. As per declared value. The leakage current value shall be less than 1mA. h. Optical Fibre Cable laid with Power Cable. 3.2 Testing Required (Cont 5) No Test Details 1 Total A laser source and Attenuation Test power meter shall be used for these attenuation measurements. End to end test to check the continuity of each fibre. The measurement shall be done from both ends and the average computed. Test shall be done with two wavelength, 1310nm and 1550nm. Limit The value shall be less than Calculated Value. Formula: Value < Cxd + Sxn + Kxk C=Fibre Cable Lost (constant) d=Fibre Cable Length S=Splice Loss in dB (constant) n=Number of splices K=Connector Loss in dB (constant) k=Number of Connector C=0.40dB/km at 1310nm wavelength 0.25dB/km at 1550nm wavelength S=0.10dB & K=0.50dB for both wavelength 2 ! "# $ $ Splice Loss Test An optical time domain The value shall not be reflectometer (OTDR) more than 0.10dB. shall be used for these attenuation measurements. The measurements shall be recorded by a printer. The optical loss measured shall not exceed the specified maximum allowable attenuation for the per unit loss. Test shall be done with two wavelength, 1310nm and 1550nm. SAT Appendix L: SAT for Primary Injection Tests for CT Circuit 1.0 2.0 3.0 4.0 5.0 Purpose ..................................................................................................................................... 1 Requirement Prior to Primary Injection ..................................................................................... 1 Testing Condition & Restrictions ............................................................................................... 1 Primary Injection Tests ............................................................................................................. 2 Specific Requirement ................................................................................................................ 4 1.0 Purpose 2.0 Requirement Prior to Primary Injection 3.0 Testing Condition & Restrictions The purpose of primary injection for the CT circuits is to: • Ensure that the secondary wirings of the CT are correctly connected to its intended protection scheme. • Ensure that the connected CT ratio is as per design requirement. • Detect any mistakes in the CT polarity termination. This test should only be started after the following activities have been successfully completed: a. All wiring activities in the bay under test. b. Wiring check as required in Appendix G c. CT tests as per Appendix J d. Secondary injection of all instruments and relays at both relay and control panels. e. The required CT ratio connection (for multi-ratio CT’s) have been decided and connected. f. Test procedure as per Appendix B shall be available. The following conditions shall be adhered to during the test: a. The minimum primary injection current should be at least 10% of the rated CT ratio connected. b. Phase to ground primary injections shall be conducted first followed by the phase to phase primary injections. c. When primary injection tests are being carried out in a live substation all necessary isolation shall be documented in the testing procedure. d. Primary injection test shall be performed on all CT’s. e. Test form as required in Appendix A shall be prepared with the following additional information: i. ii. iii. iv. v. ! "# CT Ratio CT Function Phase Injected Primary Injection value Secondary Measurement Result $ $ 4.0 Primary Injection Tests The following primary injection tests shall be conducted: a. Phase to ground primary injections: i. Only the particular core of the phase being tested should be left connected to its intended function with all other cores of the phase kept shorted. For example, in diagram Figure O1 below, during primary injection of CT core R1 the other cores in the phase i.e. R2. R3 and R4 shall be kept shorted. ii. Measurement of the secondary current shall be taken for all phases and neutral at point A (MK) and at point B (instrument/relay) as indicated in Figure O1. iii. All cores of a phase shall be tested similarly. b. Phase to phase primary injections: i. c. The secondary current shall be measured for all phases and neutral at the instrument/relay. For example during a R-Y phase to phase primary injection measurements are to be taken from points A, B, C and D as indicated in Figure O2 At least the following tests shall be carried out for (a) and (b) above. i. ii. For Phase to ground – Y-N For Phase to Phase -- R-Y and B-R d. For CT’s used for multiple functions, measurements shall be taken at all components as indicated in Figure O3 below. $ ! "# $ $ !" !" # ' ( $% " & ' !" # !" ' ( ' % ! "# $ $ # ) ( ( !" ' ( 5.0 Specific Requirement Following are the specific requirements, to be checked during primary injection for: a. High impedance busbar protection current circuit i. ii. Busbar isolator auxiliary contact timing shall be set and tested and marked permanently as required before the primary injection. Timing diagram shall be plotted for all isolator’s auxiliary contacts. For busbar protection current circuit which checks through the busbar isolator auxiliary contacts, the following shall be confirmed during primary injection as in Figure O4 • Short-circuiting of the CT when both busbar isolators are open (A). • Each circuit that checks through isolator auxiliary contact (B) & (C). b. Inaccessible CT – For CT’s positioned such that primary injection is not possible e.g. transformer bushing CT, all circuits involved would then have to be proved using load current after energizing. c. For protection scheme with paralleled CT, e.g. distance protection CT on 1½ breaker scheme using 2 sets of CT for each phase, each CT shall be tested independently first and then as a composite. The following example illustrates this requirement as in Figure O5. ! "# $ $ ( ' ( ) ' ( ) ' ( ' * ( +, 12! 12! & %" -" %. /!0 3 4! 0 .5 -" %. %. 6% ' !7 %.6 !" %. & ! "# $ $ SAT Appendix M: SAT for Secondary Injection Tests for Voltage Circuit 1.0 2.0 3.0 4.0 Purpose ..................................................................................................................................... 1 Requirement Prior to Voltage Circuit Secondary Injection........................................................ 1 Testing Condition & Restrictions ............................................................................................... 1 Secondary Voltage Injection Tests ........................................................................................... 2 1.0 Purpose The purpose of secondary injection test for the voltage circuits are to: • • 2.0 Requirement Prior to Voltage Circuit Secondary Injection Ensure that the secondary cores of the CVT/PT are correctly connected to its intended protection relay, instrument and recorders. To ensure correct phase connections from CVT/PT to its intended protection relay, instrument and recorders. This test should only be started after the following activities have been successfully completed: a. All wiring activities in the bay under test. b. Wiring check as required in Appendix G c. CVT/PT tests as per Appendix J d. Secondary injection of all instruments and relays at both relay and control panels. e. Test procedure as per Appendix B shall be made available. 3.0 Testing Condition & Restrictions The following conditions shall be adhered to during the test: a. All precaution to avoid back energizing of the CVT/PT shall be taken. b. Three phase voltage source, with different voltage magnitudes for each R, Y, and B e.g. 63.5, 60, 57 respectively shall be used to prove all VT circuits. c. When this test is performed in a live substation all necessary isolation shall be documented in the testing procedure. d. Each voltage circuit from the CVT/PT shall be tested separately up to the protection relay, instrument and recorders. e. All voltage circuits in the plant shall be tested e.g. voltage selection, synchronizing circuits etc. f. ! "# Test form as required in Appendix A shall be prepared with the following additional information: i. VT circuit function ii. Injection value at source iii. Voltage measurement at protection relays, instruments and recorders. $ $ 4.0 Secondary Voltage Injection Tests The following example as illustrated in Figure P1 shows the method of secondary voltage injection tests: a. Inject three phase test voltage at point X for circuit 1 and measure at points A, B, C and D. b. Repeat the test for injection at point Y for circuit 2. c. Measurements shall be made for all voltage circuits. ! #$ % & # " $ ! "# $ $ SAT Appendix N: SAT for Protection and Control Scheme ! " # $# % &' ( % & # #) ' % *+, % . ' - / % %"& 0 & 1 2 ) ( ( & 3 4 & 3 / & 3 & 3 # 5 ( &' 3 6 2 3 7& 3 " 3 81 () % $ 9 & 3 $ * 23 , ( ( 81 & 3 ! &9-) & 3 * 23 , ( 9 0 & 3 4 ., ( 9 0 & 3 9 7 ) & 3 + &' 3 6 2 3 7& 3 ($4 ( &3 (( 2 & 3 "# : 2 2 & 3 % '& 3 ; 0 ( 0 7 & 3 81 ( 0 7 & 3 ! ; ( $81 : 2 0 7 & 3 / 1 &. 3 2 & 3 : 2 & & 3 41 & 3 &. 32 8 <, 7 2& 3 $, & 3 " ,8,+ 2 =& ,8,- & 3 ! , 2 ( ( & 3 ! , 2 (4 & 3 ! , 2 ( / 3 3 81 ( & 3 ! 9 7 + 2 & 3 ! 9 ' & 3 ! " 81 ( ( 81 0 7& 3 !%; ( 1 2 ( 81 1 2 0 7& 3 1.0 Purpose " " " ! ! (- 3) & 3 " % % % " To provide general SAT requirements on conventional or digital substations when carrying test on the various protection and control schemes. ! "# $ $ 2.0 Definitions No. 1. Name Negative check 2. Positive check 3. 4. Switching devices or switchgears CECOMS 5. EGW 6. ESM 7. GSO 8. HMI 9. ICT 10. IED 11. NCC 12. NLDC 13. RTU 14. SCADA 15. SGW Description A test performed to check the incomplete condition shall not cause operation. A test performed to check the successful operation of the intended function. Circuit Breaker, Busbar Isolator, and Line Isolator & Earth Switch. Centralized Equipment Condition and Online Monitoring System (CECOMS) – The TNB Grid enterprise monitoring system, for monitoring of substation equipment as part of maintenance activity. Enterprise Gateway – Device that forms the interface between the IEC 61850 IEDs, including other smart devices within a substation and the enterprise monitoring system, namely CECOMS. Managed Ethernet Switch – Layer 2 network device. Multiple ESMs are used to form the IEC 61850 communication network in a digital substation. ESM is also used for RTU to communicate with Modbus TCP transducer. Grid System Operator – The entity that manages the grid power system via the SCADA system at NLDC. Human Machine Interface - The main user interface for station level monitoring and control of the power system and substation equipment within a digital substation. Information Communication Technology – TNB ICT Division is responsible to provide telecommunication services for SCADA and protection applications. Intelligent Electronic Device – Microprocessorbased controller of power system equipment, primarily used as digital protective relay in a digital substation. Network Control Centre – Generic term for NLDC. National Load Dispatch Centre – The grid NCC with SCADA master facilities operated by GSO. Remote Terminal Unit – Device that interfaces with NLDC SCADA system in a conventional substation to provide network level control and monitoring for the substation. Supervisory Control and Data Acquisition – SCADA system is used for managing the grid power system. It consists of SCADA master, operated by GSO at NLDC, and remote devices at substations (RTU or SGW), maintained by TNB Grid Division. SCADA master and remote devices are connected by telecommunication system managed by TNB ICT Division. SCADA Gateway – Device that forms the interface between the IEC 61850 IEDs within a $ ! "# $ $ 16. STS digital substation and the NCC. Substation Time Server – Device that provides time-synchronization function for all IEC 61850 IEDs and client devices (SGW, EGW and HMI) in a digital substation. % ! "# $ $ 3.0 General Requirement General requirement for Protection and Control scheme test: a. All schematic / detail wiring drawings shall be as per TNB approved conceptual / scheme drawing. Testing shall only be carried out based on the schematic drawings and not based on an individual’s past experience. All schemes available in the plant as indicated in the schematic drawing shall be tested. (Note: if any design error discovered during testing, tester is required to record in Master Defect List) b. Schematic drawings of a scheme being tested shall be highlighted with a fluorescent marker. c. For all protection schemes e.g. distance protection, auto-reclose etc. a conjunctive test report shall be made available. d. For installation with Global Positioning System (GPS) facility, it shall also be tested. For Digital Substation, time synchronization test using Substation Time Server (STS) shall also be covered. e. Both the positive and negative checks of a logic circuit shall be checked and documented. For example, as per figure Q1 to test the operation of relay X, all the following tests shall be performed: ! "#" $%& $ & 1 1 1 1 *+, $ ! "# ) With contacts A, B, C and D closed relay shall operate – Positive check Open contact D and the relay shall reset – Negative check Close contact D and open contact C and the relay shall reset – Negative check Close contact C and the relay shall operate again – Positive check Open contact B, relay should remain energized – Positive check Open contact A (with B still open) relay shall reset – Negative check Close B and relay shall energize once again – Positive check The above test should be documented as per the table below. Status of Logic No. A B C D 1 Close Close Close Close 2 Close Close Close Open 3 Close Close Close Close 4 Close Close Open Close ) & ' ( $ $ Relay X Operate Reset Operate Reset 5 6 7 8 Close Close Open Open Close Open Open Close Close Close Close Close Close Close Close Close Operate Operate Reset Operate Once the above test on relay X is completed, the rest of the test to check the trip (E) and alarm (F) signal from the relay can be performed by activating the relay X by giving a direct positive to point D. Only after all the above tests, the circuit is proven to be in order. This concept shall be applied for any logic test especially for control circuit and interlock circuits in particular. g. For Digital Substation, software based control and interlocking logic shall be tested using the similar concept as the above table. h. For the following protection scheme test, secondary injection shall be carried out from the terminal blocks instead of test terminal blocks: o o o o o o o Protection trip test. Auto-reclose test. Signaling check to control panel facia indication/counter Signaling check to SCADA facility (RTU/SCADA Gateway) Signaling check to HMI (for Digital Substation) Signaling check to EGW/CECOMS Signaling check to digital fault recorder i. For switching devices (isolator & CB) opening operation tests (supervisory/station/bay), all applicable switching devices in the plant shall be kept in the closed position, only the intended switching device shall Open. k. For switching devices (isolator & CB) closing operation tests (supervisory/station/bay), all applicable switching devices in the plant shall be kept in the opened position, only the intended switching device shall Close. l. Isolator position indication shall be tested such that Close status is indicated when isolator is fully closed and Open status is indicated when isolator is fully opened. m. For interlock check involving isolators position, test shall be made to prove interlock is permitted only when the isolator is fully open or close. n. Test the DC supply segregation of each scheme. Each individual scheme shall be tested with only its scheme DC supply kept ‘ON’. For example: i. ii. *+, ) $ .& During interlock test, only the DC supply for the control scheme shall be kept ‘ON’ and all other DC supply e.g. protection DC kept ‘OFF’. During voltage selection test, only the DC supply of the voltage selection scheme shall be kept ‘ON’ and all other DC of all bays shall be ‘OFF’. o. Non-protection trip test e.g. transformer guard, SF6 stage 2 tripping of CB or GIS busbar shall also be performed and recorded. p. For switchgear position indication check, test that the position indication e.g. at control panel or NLDC, is only given when the switchgear is fully closed or open. & ! "# $ $ q. For all interlock tests, test that the interlock operation is permitted when the switchgears is fully open or fully closed. r. Scheme tests for protection trip, alarm, disturbance recorder, SCADA facility, HMI (Digital Substation) and EGW shall be carried out by actual simulation of the signal. Contact shorting to simulate a test signal is to be avoided unless there are no other means of simulating the test signal. s. For each test, the signal simulation method and the result of the simulation shall be stated in the test form. t. For signal simulation by shorting, the shorting shall be carried out at the point nearest to the component under test and the terminal shall be stated in the test form. u. Check all relay, indications flag, fascia, HMI, SCADA, and EGW description are in order, accurate and clearly explaining the intended purpose as per Grid Substation Signaling Requirements (GTS-GSE-SSR). v. Detailed test procedure with relevant diagrams, test combinations shall be provided for all scheme tests. All scheme tests shall be documented in detail. Test conditions and its results shall be easily understood. w. Any modification on a scheme that has been tested shall subject that particular scheme to a complete retest. " ! "# $ $ Protection trip test shall be performed with the following arrangement: 4.0 Protection Trip Tests All breakers in the plant should be kept in closed position during the trip test. Only intended breaker(s) to trip. 0 Trip test shall be performed using the actual CB (not dummy breaker). For single pole CB operation, ensure the single pole tripping signal trip the correct phase (applicable for 275kV and above OHL only). To test the DC supply segregation of the tripping scheme, only the protection DC supply of the trip coil under test is kept on. All other DC supply e.g. annunciator, control, indication, shall be switched off. ( During each trip test the performance of CB, all associated indication and events shall be recorded e.g. counter, relay flag, SCADA facility, HMI, EGW and fascia. Isolation link facility (Test terminal block, Group Isolation Link Analog and Digital, and Trip Link) shall be tested during trip test. Direct tripping and tripping via master trip shall be tested. Analog Group Isolation Link is only applicable for 275kV and above OHL and cable. For trip scheme with two trip coil, the tripping shall be repeated for each coil with the other coil isolated. 2 Following is the example of a busbar protection trip test performed for a double busbar configuration as per Figure Q2 The method used in this example shall be the guiding principle when performing any trip test for other types of protection scheme: 1 1 1 1 1 Both positive and negative checks as described in Appendix N shall be performed. Record all associated indication and events for each trip test. Record counter operation for each trip test Test isolation link (Test terminal block, Group Isolation Link, and Trip Link) functionality Check all relay indications are in order so that a faulted busbar phase and its zone can be easily identified. Perform trip test for each trip coil independently. When performing trip test on trip coil 1, trip coil 2 of all breaker shall be isolated and vice versa. For main and duplicate busbar protection scheme each main and duplicate scheme shall be tested independently. When performing trip test for the main, the DC supply of the duplicate scheme shall be switched off. All the above tests shall be documented. ' ! "# $ $ 4.0 Protection Trip Tests (Cont. 1) / /. 2 . .0 1 * ' (' 3 1 1 The following table lists examples of busbar protection trip test results with all trip isolation link not removed. No 1 2 3 4 5 6 7. Test Condition With Trip Link Not Removed All feeder on Main busbar (M1 & M2) and all CB closed All feeder on Main busbar (M1 & M2) and all CB closed All feeder on Main busbar (M1 & M2) and all CB closed All feeder on Reserve busbar and all CB closed All feeder on Reserve busbar and all CB closed All feeder on Reserve busbar and all CB closed Switch off Main 1. All feeders on Main 1 Trip Test simulated Result Initiate check zone followed by reserve busbar trip Initiate check zone followed by M1 busbar trip Initiate check zone followed by M2 busbar trip Initiate check zone followed by M1 busbar trip Initiate check zone followed by Main 2 busbar trip Initiate check zone followed by Reserve busbar trip Initiate check zone followed by Main 1 B/C trip Feeder 1, 2, B/S and B/C trip Feeder 3, 4 and B/S trip B/C trip B/C trip Feeder 1,2,3,4 and B/C trip No trip. Similar table shall be provided for trip test with trip isolation facility been ( ! "# $ $ removed. The following table lists examples of protection trip test results. 4.0 Protection Trip Tests (Cont. 2) Protection Trip test No Function tested Simulation Method 1 Overcurrent protection Secondary injection of phase to phase fault. (R-Y) 2 Main 1 Busbar protection Secondary injection of busbar protection relay CB tripped, Fascia, Counter, relay Indication, HMI, SCADA facility and EGW/CECOMS CB tripped: • HV CB • LV CB Relay indication: R, Y Counter (CBM/physical): incremented Fascia (conventional): • Overcurrent operated • Master trip. Fascia (DS): • Protection Trip CB tripped: • All feeders on Main 1 • Bus-section • Bus-coupler Counter(CBM/physical): incremented Fascia (conventional): • Main Busbar operated • Master trip on all feeders on Main 1 Fascia (DS): • Protection Trip on all feeders on Main 1 ) ! "# $ $ 5.0 Annunciator/ Alarm Test In addition to complete alarm and annunciator tests, the following shall also be carried out and recorded: a. Test the DC supply segregation from the annunciator scheme. Test the annunciator DC supply is independent of all other DC source e.g. protection, control etc. b. Ensure lamp test function is working properly at control panel and annunciator. c. Test functions such as “ACKNOWLEDGE” and “RESET” are functioning properly for all bays. d. Test functionality of the annunciator scheme when the annunciator DC supply fail or its DC-DC converter fails. e. Test functionality of all discrepancy indication and its alarm operation. f. Test “ATTEND/ UNATTEND” function is operating properly. g. All alarm signals to fascia and flag relay shall be tested. The following table lists some examples of conventional annunciator signal tests. Annunciator alarm test No Function Simulation Method tested 1 Bucholz Alarm Press test button at Bucholz relay 2 Winding Temp Turning test handle at winding Trip temperature indicator 3 Overcurrent protection Overcurrent protection Overcurrent relay faulty CB SF6 stage 1 alarm 4 5 6 ! "# $ $ Secondary injection of phaseto-phase fault. Secondary injection of earth fault. Isolate DC supply to relay Short X1 and X2 terminal at pressure gauge Result/Remark Buchholz Alarm Winding temp trip. Master trip operated. Overcurrent op. Master trip op. Overcurrent op. Master trip op. Overcurrent relay faulty SF6 stage 1 alarm 6.0 General Requirement for System Communication and Clients Test a. System test covers validation of communication, SCADA facility, HMI (for Digital Substation), and EGW. The tests shall be coordinated and initiated by PM with relevant parties. b. SCADA test shall include RTU or SCADA Gateway. All SCADA facilities shall be tested up to the regional or national control center (NLDC). c. For substations equipped with RTUs, the SAT shall be carried out to verify the following:i. ii. SCADA functionality test: • Between SCADA Interface Panel(s) and Plant • Between RTU and SCADA Interface Panel(s) (Local Test & Physical Inspection) • Between SIP and Control Centre • Between Control Center and Plant Conjunctive test: Protection Scheme Test d. For Digital Substations equipped with SCADA Gateway (SGW), the SAT shall be carried out to verify the following:i. ii. e. 6.1 SCADA Facility Test SCADA functionality test: • Between Source (Plant/Non-IEC 61850 relays) and IOIED/BCU • Between IED and Control Center • Between Source (Plant/Non-IEC 61850 relays) and Control Center Conjunctive test: Protection Scheme Test The test results shall be recorded in the relevant checklist a. SCADA operation and control circuit i. Test all switchgear operation from NLDC both under supervisory (”positive check”) and remote/station (“negative check”) modes. ii. For switchgear opening tests it shall be conducted under the following conditions:• All applicable switchgear shall be kept in the closed position. Only the intended switchgear shall open after the test. • All other applicable switchgear shall be kept in the open position. No switchgear shall close during this open test. iii. For switchgear closing tests it shall be conducted under the following conditions: • All applicable switchgear shall be kept in the open position. Only the intended switchgear shall close after the test. • All other applicable switchgear shall be kept in the close position. No switchgear shall open during this closing test. For CB with synchronising facility, all combination of synchronised closing e.g. live-line live-bus, dead-line dead-bus, live-line dead-bus, dead-line live bus, including the synch bypass scheme shall be tested. For transformers tap changers control, perform raise and lower tap by • Selecting supervisory control with manual operation (“positive check”) • Selecting supervisory control with auto operation (“negative check”) b. SCADA signal point to point test ! "# $ $ c. i. All signals to NLDC shall be tested. i. All alarms and indications shall be initiated from the source by actual operation or injection. Shorting of contacts is only allowed at the source end when the actual operation cannot be simulated. SCADA switching devices position indication. All switchgear position indication shall be tested. For position indication check involving isolators position, test shall be made to prove correct position indication is given only when the isolator is fully open or fully close. Testing to be carried out by actual operation of switchgear. d. Sequence of event validation test shall be performed to validate correct events, correct sequence, and time tagging accuracy of events reported by SGW/RTU. This test is to be conducted together with all the scheme tests as listed in this appendix. e. Metering/instrumentation for substation with RTU facility is tested by secondary injection from control panel and measure at SCADA interface panel and verified at relevant control center and EGW. Verify that the measurement readings at meter, control center and EGW are consistent. Record the secondary injection value and any measurement or reading made. f. NLDC redundancy (main/standby) communication test i. Manual switchover – NLDC SCADA Engineer to switch from main to standby channel and vice versa ii. Automatic switchover – Simulate communication breakdown on main channel and ensure automatic switchover to standby channel and vice versa $ ! "# $ $ a. HMI operation and control circuit 6.2 HMI Test i. Test all switchgear operation from HMI under station with supervisory off (”positive check”) and station with supervisory on (“negative check”) modes. ii. For switchgear opening tests it shall be conducted under the following conditions:• All applicable switchgear shall be kept in the closed position. Only the intended switchgear shall open after the test. • All applicable other switchgear shall be kept in the open position. No switchgear shall close during this open test. iii. For switchgear closing tests it shall be conducted under the following conditions:• All applicable switchgear shall be kept in the open position. Only the intended switchgear shall close after the test. • All other applicable switchgear shall be kept in the closed position. No switchgear shall open during this closing test. For transformers tap changers control, perform raise and lower tap by • Selecting station control with manual operation (“positive check”) • Selecting station control with auto operation (“negative check”) b. HMI signal point to point test i. All signals to HMI shall be tested. ii. All alarms and indications shall be initiated from the source by actual operation or injection. Shorting of contacts is only allowed at the source end when the actual operation cannot be simulated. c. HMI switching devices position indication. All switchgear position indication shall be tested. For position indication check involving isolators position, test shall be made to prove correct position indication is given only when the isolator is fully open or fully close. Testing to be carried out by actual operation of switchgear. d. Sequence of event validation test shall be performed to validate correct events, correct sequence, correct addressing (Information Object Address/IOA) and time tagging accuracy of events reported by HMI (refer to the diagram below). This test is to be conducted together with all the scheme tests as listed in this appendix. % ! "# $ $ e. For Digital Substation metering/instrumentation test, perform secondary injection at Bay Controller for bay measurement and Station IOIED for Busbar measurement and observe the measurements at:• • • • • Control Centre HMI EGW Bay Controller/Station IOIED Digital Instrument Meter ( 3 ( ' > 1 ( ' Verify that the measurements are consistent. f. ( All signals configured shall appear in the appropriate HMI displays listed below as per HMI GUI Design Guideline i. Dashboard ii. Station Overview/System Architecture page iii. Single Line Diagram page iv. Bay Diagram page • Bay Single Line Diagram • Bay Fascia • Analog Measurement • Synchronisation • Interlock v. Event page vi. Alarm page vii. Station Fascia page ! "# ( 2 $ $ This test is to be assisted by TNB. All verification is done using UIP (Universal Interface Platform). 6.3 Enterprise Gateway (EGW) Test a. EGW signal point to point test i. All signals to SCADA and HMI as per signal list shall be tested to reach to EGW. ii. All alarms and indications shall be initiated from the source by actual operation or injection. Shorting of contacts is only allowed at the source end when the actual operation cannot be simulated. b. EGW switching devices position indication. All switchgear position indication shall be tested. For position indication check involving isolators position, test shall be made to prove correct position indication is given only when the isolator is fully open or fully close. Testing to be carried out by actual operation of switchgear. c. Sequence of event validation test shall be performed to validate correct events, correct sequence, and time tagging accuracy of events reported by EGW. This test is to be conducted together with all the scheme tests as listed in this appendix. d. For Digital Substation metering/instrumentation test, perform secondary injection at Bay Controller for bay measurement and Station IOIED for Busbar measurement and observe the measurements at:• • • • • Control Centre HMI EGW Bay Controller/Station IOIED Digital Instrument Meter Record the secondary injection value and any measurement or reading made. Verify that the measurements are consistent. e. For Digital Substation, MMS file transfer service shall be tested. Fault record shall be retrieved by EGW upon fault record made, triggered via MMS by relay. 6.4 Communicatio n Test a. All device communication settings e.g. IP Address, Subnet Address and Multicast GOOSE Address shall be configured as per approved documents (approved drawings, Design Verification results) b. Validation of Managed Ethernet Switches (ESM): iii. Port mirror settings iv. RSTP redundancy test v. Port configuration and connection 6.5 Substation Time Server a. Time synchronization function for all devices: i. No time sync error at IEDs ii. Event time stamp within 1ms error. This test can be performed during client point-to-point test iii. Resynchronization between IED and STS. This test can be performed by disconnecting the STS from the network and reconnecting it. & ! "# $ $ b. GPS antenna installation i. Located at optimum location • Vertical position • Unobstructed view of the sky • At high as possible • Conduit path (along the wall) ii. Locked to optimum number of satellites " ! "# $ $ a. 7.0 Digital Fault Recorder The recorder shall be set and configured as per Product Guidebook i. Line parameters i.e. length and impedance (Reference to Computer Aided Protection Engineering data) ii. CT and VT ratio iii. User name, Password, station number (if applicable) etc. iv. Communication settings and any other information required to communicate with the recorder remotely. v. Recorder setting details. e.g. pre-triggering time, post-triggering time, triggering threshold, weight value (where applicable), auto-polling/autocalling (where applicable) vi. Digital and Analog channel name b. For recorder, test form as required in Appendix A shall be prepared with all the additional information as per (a). c. For recorders, secondary injection shall be carried out to verify All analog inputs for pick-up values Directional test (confirm CT connection and star point as per TNB standard application document) d. Test all digital signal inputs to the recorder by simulation at the signal source point. Verify the signals for: Triggering on pick-up Triggering to store event Cross triggering between subunits (where applicable) e. For Digital Substation with virtual inputs, verify correct subscription to GOOSE message from each IED by simulation at the signal source point. Verify the signals for: Trigger on pick-up Trigger to store event Cross triggering between sub-units (where applicable) f. Test all alarm signals from the recorder. g. The Global Positioning System (GPS) facility for time synchronization shall also be tested. h. At least the following tests shall be performed under the Scheme test: 1 The consistency of digital signal initiation from relay to recorder, SCADA and facia shall be checked and verified during auto-reclose test with actual circuit breaker (See Section 8.0 – Auto-reclose). During this test at least the secondary injection voltage source shall be connected to the recorder in parallel. For line differential protections, the secondary current injection to the relay shall be wired in series to the recorder. For recorders installed on transformers and power cables without autoreclose facility, the above test shall be carried out with appropriate modifications Test the remote communication functions of the recorder e.g. directory view, event file retrieval, auto-polling/auto-calling, remote setting configuration and manual triggering. This test must be conducted in TNB Operational Network. ' ! "# $ $ Protection and Control Scheme shall be tested and verified upon completion of secondary injection as per Appendix I, and can be done together or before Primary injection test for VT and CT as per Appendix L or M, stability test as per Appendix O whenever required. 8.0 Protection and Control Scheme Test form as required in Appendix A shall be prepared for all the related tests. The following test shall be performed to commission the differential protection scheme: 8.1 Line Differential Protection Scheme a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. AR (applicable for line application) and CBF initiation test i. All phase to phase fault ii. All phase to ground fault iii. Three phase fault c. Lockout Intertrip test to verify lock out operation and blocking of auto reclose scheme at remote end when local end close onto fault via internal Line Differential communication d. End to end communication test (single end injection) to verify intertripping function and measurement available at remote end. For 3-terminal application, this test shall be carried out at all ends, e.g A to B, A to C and B to C. e. DC System of the protection scheme f. Perform trip test as per Section 4.0 The following test shall be performed to commission pilot wire protection scheme: 8.2 Pilot Wire Protection Scheme a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation b. For pilot wire the following test shall be performed on every core: Continuity test Insulation resistance Pilot resistance measurement c. For pilot wire supervision scheme, the following test shall be performed: Short-circuit at remote end Open-circuit at remote end Wire crossing at remote end For all the above conditions, the relay shall be able to detect and initiate the appropriate alarm. d. Test the functionality of the Overcurrent check scheme e. DC System of the protection scheme. f. Perform trip test as per Section 4.0 ( ! "# $ $ The following test shall be performed to commission the distance protection scheme: 8.3 Distance Protection Scheme a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. AR (applicable for line application) and CBF initiation test i. All phase to phase fault ii. All phase to ground fault iii. Three phase fault 8.4 AutoReclose and Synchronizing Check Scheme c. DC System of the protection scheme. d. Perform trip test as per Section 4.0 The following test shall be performed to commission the Autoreclose and Synchronizing protection scheme a. Any blocking signal to the auto-reclose scheme from main protection shall be tested by simulating the signal at the source point of the signal. b. Auto-reclose test shall be performed with all relays e.g. Current Differential, and being set with the final settings. c. During the auto-reclose simulation test, the synchronising condition shall be achieved by actual injection of voltage to the CBM relay. d. Where main and duplicate protection is used, the whole test shall be repeated for both protections. e. During all auto-reclose tests, the following signals shall be monitored and recorded. Auto-reclose initiate signal from the main protection relay Block auto-reclose hardwire signal from the main protection relay Alarm initiated at SCADA, HMI, and EGW 1 Alarm initiated at fascia 1 All trip and closing signals 1 All indication at main protection relay and AR relay f. Auto-reclose test for selected faults shall be performed under the following conditions (if the functions are available) for all combination of phase to ground fault, phase to phase fault or three phase faults accordingly 1 1 1 1 Auto reclose switch OFF Auto reclose switch ON – DAR only with sync OK Auto reclose switch ON – DAR only with sync fail Auto reclose switch ON – SPAR & DAR (evolving faults) with sync OK Auto reclose switch ON – SPAR & DAR (evolving faults) with sync fail Auto reclose switch ON – SPAR & DAR (evolving faults) with sync OK and with external A/R blocking signal Repeat ii-vi with Auto reclose switch selection to 3 and 1+3 g. Test the A/R scheme is not initiated if the CB is initially open. h. Test the A/R scheme with CB closing circuit isolated. ) ! "# $ $ i. Test the “Sync. Fail timer scheme”. j. During the auto-reclose test, timing of the following signals shall be monitored and documented for selected faults: Measure length of A/R close pulse to the CB closing coil Measure reclaim time Measure SPAR dead time 1 Measure DAR dead time 1 Measure sync fail timer k. Upon successful completion of all above tests, tests as per the Table below shall be repeated with the actual CB and disturbance recorder connected. Main Protection No Fault Injected 1 R-N 2 B-N 3 l. 4 5 R-N followed by B-N (evolving fault) R-Y Y-B 6 7 B-R R-N 8 9 10 B-N R-N followed by R-N immediately upon autoreclosing (TOR) Y-N 11 Y-N Scheme condition to be tested Successful single pole A/R (SPAR) Successful SPAR followed by second fault in 1 sec of reclaim time R-N fault followed by evolving fault on YN fault at 650 ms Successful delay A/R (DAR) Successful DAR followed by second fault in 20th sec of reclaim time SOTF φ-N, fault immediately after Manual Close Of CB φ-N, fault with CB initially open TOR (Expected local and remote end lockout. Remote end Auto-reclose will be interrupted) Auto Reclose switched to OFF resulting in Three-pole tripping with lockout operation. Auto Reclose fail resulting in Three-pole tripping without lockout operation Confirm any backup protection not initiate Auto Reclose m. For 1½ breaker system, all tests, which are applicable, shall be carried out including but not limited to: • Trip on Reclose (TOR) (TOR from bus circuit breaker shall interrupt operation of center circuit breaker auto-reclosing) • Priority release scheme to be tested but not limited as per the table below No 1 Fault Injected R-N Bus Auto Reclose 1+3 Center Auto Reclose 1+3 2 Y-B 1+3 1+3 3 RYB 1+3 1+3 4 R-N OFF 1+3 Scheme condition to be tested Single phase to ground fault (SPAR). Expected dead time difference of 1 sec between bus and center CB. Phase-to-phase fault (DAR). Expected dead time difference of 1 sec between bus and center CB. Three-phase fault. No AR. Center CB Auto-Reclose on SPAR. Expected $ ! "# $ $ 5 Y-B OFF 1+3 6 Y-N 1+3 1+3 7 B-N 1+3 1+3 Center CB dead time as per setting without extension. Center CB Auto-Reclose on DAR. Expected Center CB dead time as per setting without extension. Bus CB in open condition. Center CB Auto-Reclose on SPAR. Expected Center CB dead time as per setting without extension. Simulate Bus CB fail to close. Expected dead time difference of 1 sec between bus and center CB. At least the following combinations shall be tested • Each CB individually using dummy breaker • Both CBs simultaneously using actual breaker n. 8.5 Thermal Overload Function DC system of the protection scheme. The following test shall be performed to commission the thermal overload protection scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. DC system of the protection scheme. c. 8.6 Transformer /Reactor Bias Differential Protection Scheme Perform trip test as per Section 4.0 to validate there is no tripping circuit wired as per design. The following test shall be performed to commission the bias differential protection scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. DC system of the protection scheme. c. Perform trip test as per Section 4.0 $ ! "# $ $ 8.7 Transformer / Reactor High Impedance Protection and Restricted Earth Fault Scheme 8.8 Overcurrent Protection Scheme The following test shall be performed to commission the high impedance protection scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. DC system of the protection scheme. c. Perform protection trip test as per section 4.0. The following test shall be performed to commission the Overcurrent protection scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. DC system of the protection scheme. c. 8.9 SBEF Protection Scheme Perform protection trip test as per section 4. The following test shall be performed to commission the Standby Earth Fault (SBEF) protection scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. DC system of the protection scheme. E.g. SBEF DC supply shall be from the respective Transformer LV relay panels. (not B/S LV panel). c. Perform trip test. $$ ! "# $ $ 8.10 High Impedance Busbar Protection Scheme The following test shall be performed to commission a busbar high impedance protection scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. For CT supervision operation test, verify Alarm operation Current circuit shorting and no operation c. For numerical high impedance relay with external CT shorting using bi-stable relay, verify the LED “CT Supervision” at main relay reset upon bi-stable relay reset (CT shorting removed). d. Test the busbar protection ‘in-service’ & ‘out of service’ facility. e. Perform BDACS (Busbar Disconnector Auxiliary Contact Supervision) for all feeders. f. CBF Stage 2 initiation to operate correct busbar zone. g. Verify that during live transfer, busbar protection must be allowed to trip the bus coupler and/or bus section breakers based on busbar configuration. h. DC system of the protection scheme. i. Perform busbar protection trip test as per section 4.0. $% ! "# $ $ The following test shall be performed to commission a busbar low impedance protection scheme: : 8.11 Low Impedance Busbar Protection Scheme a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. CB/Isolator status check to confirm correct auxiliary contact are wired. Simulate isolator invalid status and bridging condition to verify alarm is sent after time delay. c. For Bus Coupler/Bus Section Dead Zone Protection function, simulate Bus Coupler/Bus Section in open position and simulate fault between CT and CB. Verify the correct busbar zone operation. d. CBF Stage 2 initiation to operate correct busbar zone e. For 1HCB End Fault Protection function, verify intertrip and CBF initiation send to remote end. It shall be further verify that for 500kV system, the initiation shall be performed via two teleprotection channel. f. Test the busbar protection ‘in-service’ & ‘out of service’ facility. g. DC system of the protection scheme h. Perform protection trip test as per section 4.0 8.12 Breaker Failure Protection Scheme The following test shall be performed to commission the Circuit Breaker Failure protection scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. CBF initiation shall be performed with all relays which initiating CBF e.g. Current Differential, and being set with the final settings c. Simulate AR in 3 Pole position and simulate a single phase fault condition. Verify CBF initiation are resulted in all 3 phases d. Simulate AR failed and simulate a single phase fault condition. Verify CBF initiation are resulted in all 3 phases e. DC system of the breaker failure scheme. f. Perform trip test as per section 4.0. g. All requirements for busbar protection trip test shall be validated. $ ! "# $ $ 8.13 Manual Synchronizing Check Scheme The following test shall be performed to commission the synchronizing scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. To verify all voltage circuits. c. Secondary injection validation on the synchroscope d. Test any DC interlock priority scheme. Test that only one bay can be synchronized at a time. e. Synchronized closing of CB shall be tested from remote and supervisory. f. For supervisory control, the test shall be carried out first by initiating control (by shorting) from the SCADA Interface Panel (RTU) followed by initiation test from the Control Center after communications to the Control Center have been established. g. The following conditions of CB closing shall be tested: 1 Live Line - Live Bus (Synchronized closing) Live Line – Dead Bus (Voltage checked closing) Dead Line – Live Bus (Voltage checked closing) Dead Line – Dead Bus (Voltage checked closing) h. Any synchronising bypass or override scheme (where applicable) shall be tested. i. CVT MCB trip and CVT isolator open blocking signal from the source ends shall be tested for blocking the voltage check closing function. Verify that synchronizing closing is not affected. j. All necessary tests to prove that any component or relay failure in the scheme do not cause any of the CVT’s to be back energized shall be performed. k. The performance of the synchronizing scheme shall also be tested during live transfer condition with synchronized closing. l. All possible conditions tested shall be clearly mentioned in the test report. $& ! "# $ $ 8.14 Demand/Load Shedding Scheme The following test shall be performed to commission the Demand Shedding scheme: a. Secondary injection as per Appendix I to test alarm (fascia HV panel and LV panel, HMI, EGW), SCADA and counter operation. b. Verify On/Off Selector switch functionality. Ensure function inhibited when switch is turned off (DC supply to relay remain intact). c. Verify FR (relay fault record) cross triggering function by simulation. d. Verify external undervoltage blocking function for UV element e. DC system of the protection scheme. f. 8.15 Automatic Voltage Regulation Scheme Perform trip test as per Section 4.0. Ensure transformers tripping circuit is wired based on paralleling capability grouping. The following test shall be performed to commission the AVR scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. Confirm single phase voltage and current tapped accordingly as per setting requirement c. Verify maximum and minimum Tap Change Position as per actual OLTC. Simulate all the position and to confirm AVR reads the correct tap position. d. Confirm Raise and Lower operation to RTCC Panel e. Verify the actual maximum running time of OLTC for one tap changing time and set the AVR accordingly. Simulate a longer operation time and verify alarm is sent. f. Verify over voltage/under voltage blocking for any raise or lower operation at OLTC. g. Verify manual AVR control from HMI with CAS (Control Authority) Switch set to ‘Station’. h. Verify manual AVR control from supervisory with CAS (Control Authority) Switch set to ‘Supervisory’. i. Verify emergency operation by simulation AVR fail and tap changing operation can be performed at RTCC panel with physical Raise and Lower Buttons. j. Emergency Stop button to stop tap changing operation (at RTCC panel). $" ! "# $ $ The following test shall be performed to commission the PD scheme: 8.16 Pole Discrepancy Scheme a. Simulate CB single pole, 2 pole and 3 pole opening and verify PD operation b. Timing Test and CB Auxiliary contact (NO / NC) verification c. Test alarm (fascia, HMI, EGW), SCADA and counter operation d. Protection trip test as per section 4.0 8.17 Unbalanced Capbank Protection Scheme The following test shall be performed to commission the Unbalanced Capbank Protection scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. Perform trip test as per Section 4.0 The following test shall be performed to commission the Overload Capbank Protection scheme: 8.18 Overload Capbank Protection Scheme a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. Perform trip test as per Section 4.0 8.19 Under/Over Voltage Capbank Protection Scheme The following test shall be performed to commission the Under/Overvoltage Capbank Protection scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. Verify UV element blocking with CB status during energization. c. 8.20 Point of Wave Switching Control Scheme Perform trip test as per Section 4.0 The following test shall be performed to commission the Point of Wave switching control scheme: a. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. b. Verify CB closing circuit is wired as per intended c. Perform CB operational test as per Section 4.0. The performance of CB opening (reactor bay) and closing (capacitor bay) shall be monitored and verified using test set. $' ! "# $ $ 8.21 Voltage Selection Scheme The following test shall be performed to commission the Voltage Selection scheme: a. Secondary voltage injection as per Appendix M to test all voltage circuits b. Where bus-section and bus coupler bays are available, all possible configurations shall be tested. c. For Digital Substation design, the VSS scheme shall include: • Verify the busbar CVT is correctly wired up to the corresponding buswire • Verify the correct running bus voltage reached to the Bay Controller and CBM (only applicable for OHL with AR Scheme) with the correct Q1 and Q2 assignment. • Verify the incoming voltage reached to the Bay Controller and CBM (only applicable for OHL with AR Scheme). d. For Conventional Substation with Busbar CVT, the VSS scheme shall include: • Verify the busbar CVT is correctly wired up to the corresponding buswire • Verify the correct running bus voltage reached to the bay (only applicable for OHL with AR Scheme) with the correct Q1 and Q2 assignment. • Verify the incoming voltage reached to the bay (only applicable for OHL with AR Scheme). e. For Substation without Busbar CVT, the VSS scheme shall include verification of priority scheme for each bay: For example in a double busbar configuration as illustrated in Figure Q3 the priority scheme shall be tested for all possible operating conditions e.g.: /. / 2 . *04 2 1 No Feeder under test * 3 ) !' 1 Test condition Result on secondary voltage selection bus $( ! "# $ $ 1 Feeder 4 on R Bus 2 Feeder 4 on R Bus 3 Feeder 4 on R Bus. Feeder 3 on M2 4 Feeder 1 on M1. Feeder 3 on M2. Feeder 2 and 4 on R bus Feeder 1, 2 and 4 on R bus. Feeder 3 on M2 5 f. Feeder 1, 2, 3 CB open. B/C and B/S closed. Feeder 1, 2, 3 CB open. B/C open and B/S closed. Feeder 1, 2 and B/C CB open and B/S closed All CB closed All CB closed Voltage for bus M1, M2 and R shall be from feeder 4. No voltage on M1 and M2 bus. Voltage for R shall be feeder 4. Voltage for M1, M2 from feeder 3 and voltage for R from feeder 4 Voltage for M1, M2 and R bus shall be from feeder 1. Voltage for M1, M2 and R bus shall be from feeder 3. Any AC interlock, negative DC or positive DC priority scheme provided shall be tested. g. CVT MCB trip and busbar CVT Open blocking signals from the priority bay shall be tested for all bays. h. All necessary tests to prove that any component or relay failure in the scheme do not cause any of the CVT’s to be back energized shall be performed. i. The performance of the voltage selection scheme shall also be tested during live transfer. j. All possible conditions tested shall be clearly mentioned in the test report. k. Test for any alarm provided for the scheme. $) ! "# $ $ 8.22 Live Transfer Scheme The following test shall be performed to commission the Live Transfer scheme: For Digital substation, Live Transfer scheme implementation is in Bay Controller Unit. a. Test form as required in Appendix A shall be prepared. b. Test live transfer interlock scheme for each bay for all the following conditions: Live transfer from Main to Reserve Bus Live Transfer from Reserve to Main Live Transfer with Bus-Coupler and/or Bus-Section open. c. Bus-coupler and Bus-section trip blocking shall be checked during live transfer for each bay. Verify trip blocking applicable to all protection except busbar protection. d. Opening of isolator during live transfer is permitted only when the other isolator is fully closed. This test shall be carried out for all isolators. e. All possible conditions tested shall be clearly mentioned in the test report. f. Test for any alarm provided for the scheme e.g. live transfer in progress. % ! "# $ $ 8.23 Switchgear Operation & Interlocking Scheme The following test shall be performed to commission the Interlock scheme: For Digital substation, Switchgear Operation and Interlocking scheme implementation is in Bay Controller. Local interlock verification in this section is still required for Digital Substation. a. Section 3.0 shall be strictly followed to perform the operation and interlock tests. b. Interlock test shall only be performed after: i. ii. c. Alignment test of all isolators completed Isolator auxiliary contact timing test completed Interlocking condition from busbar isolator, line isolator and earthing switch shall only be given when the isolator’s primary arm is fully open or close. d. Position indication of switchgear at remote and supervisory shall only be given when the isolator’s primary arm is fully open or fully closed. e. Verify Reconnection Inhibit for Capacitor circuit breaker. Confirm CB is not allowed to close immediately after it was detected open until timer elapsed f. Interlock test for all switchgears shall be tested from the following positions: Local operation interlock Remote operation interlock Supervisory operation interlock g. Both mechanical and electrical interlock shall be tested. h. Verify Earth Switch Interlock. i. Test for any alarm provided for the scheme. % ! "# $ $ 8.24 Carrier /Intertrip Scheme The following test shall be performed to commission the carrier/intertrip scheme: a. All signals whichever available shall be tested and shall include but not be limited to the following: 1 1 1 1 c. Distance protection Main 1 Carrier Send, Distance protection Main 2 Carrier Send, Distance protection Main 1 Carrier Receive, Distance protection Main 2 Carrier Receive, Intertrip send (Eg: CBF, Stub, SF6) Intertrip receive (Eg: CBF, Stub, SF6) CBF initiation to remote end (where applicable, usually for Stub Protection and End Zone Fault in 1HCB) The following test shall be performed on all above signals: 1 1 1 1 Check all the Send signals reach the remote end relays or CBM (Digital Substation) with correct indication. Check all the Receive signals from remote end reach the local relays or CBM (Digital Substation) with correct indication at the local end. Record fascia operation for Send and Receive Record relay operation for Send and Receive e.g. flag relays, CBM Timing test for signal transmission delay, for all available signals. Reset time of the receive signal for at least one signal. Minimum signal window timing (e.g. less than 2.5 ms) of at least one signal to simulate noise shall be tested. This is to avoid any transient/spurious signal being transmitted. d. All general alarms from communication equipment and 48V DC system. %$ ! "# $ $ IOIED consist of the following functions: 8.25 IOIED (Transformer Management, Station IOIED) Scheme • • • Tripping Function (Transformer IOIED) Busbar Measurements (Station IOIED) Hardwiring Input to digital signals a. Check DC system is wired as per design. b. All possible conditions tested shall be clearly mentioned in the test report. c. Verify all required signals (measurement, alarm, indications, status, etc.) from the IOIED are reported to HMI, EGW and SGW Hardwiring Input to Digital Signals Function a. Verify all the hardwired signal from the source end is reported to the HMI, EGW and SGW. Tripping Function (applicable for Transformer Management IOIED) a. Perform Trip Test as per Section 4.0. Simulate transformer guard operation by initiating from the source ends. Shorting of contacts is only allowed at the source end when the actual operation cannot be simulated Busbar Measurements Function (applicable for Station IOIED) a. Perform measurement accuracy checks for the complete range. b. Measurement parameters shall include all the required parameter as per Grid Substation Signaling Requirements c. Verify information consistency among IOIED, HMI, SCADA and EGW. 9.0 Integrated Protection and Control Scheme Protection and Control Scheme shall be tested and verified upon completion of secondary injection as per Appendix I, and can be done together or before Primary injection test for VT and CT as per Appendix L or M, stability test as per Appendix O whenever required. Test form as required in Appendix A shall be prepared for all the related tests. %% ! "# $ $ 9.1 Integrated Line Protection Scheme Integrated Line Protection consist of the following functions: • • • Current Differential Protection Backup Distance Protection Thermal Overload Check DC system is wired as per design. 0 All tests shall be carried out using dummy breaker. All possible conditions tested shall be clearly mentioned in the test report. ( Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation Current Differential Protection The following test shall be performed to commission the differential protection scheme: a. AR (applicable for line application) and CBM initiation test i. All phase to phase fault ii. All phase to ground fault iii. Three phase fault b. Lockout Intertrip test to verify lock out operation and blocking of auto reclose scheme at remote end when local end close onto fault via internal Line Differential communication c. End to end communication test (single end injection) to verify intertripping function and measurement available at remote end. For 3-terminal application, this test shall be carried out at all ends, e.g A to B, A to C and B to C. d. Perform trip test as per Section 4.0 Distance Protection The following test shall be performed to commission the distance protection scheme: a. CBM initiation test. i. All phase to phase fault ii. All phase to ground fault iii. Three phase fault b. Perform trip test as per Section 4.0 Thermal Overload The following test shall be performed to commission the thermal overload protection scheme: a. Perform trip test as per Section 4.0 to validate there is no tripping circuit wired as per design. 9.2 Integrated Distance with Thermal Overload Protection Integrated Backup Distance with Thermal Overload consist of the following functions: • • Backup Distance Protection Thermal Overload % ! "# $ $ Scheme Check DC system is wired as per design. All tests shall be carried out using dummy breaker. 2 All possible conditions tested shall be clearly mentioned in the test report. 3 Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation Distance Protection The following test shall be performed to commission the distance protection scheme: a. CBM/CBF initiation test. i. All phase to phase fault ii. All phase to ground fault iii. Three phase fault b. Perform trip test as per Section 4.0 Thermal Overload The following test shall be performed to commission the thermal overload protection scheme: a. Perform trip test as per Section 4.0 to validate there is no tripping circuit wired as per design. %& ! "# $ $ 9.3 Circuit Breaker Management Scheme Circuit Breaker Management (CBM) consist of the following functions: • • • • • Circuit Breaker Failure Auto-Reclose and Synchronization (applicable for Overhead Line application) Remote End Intertrip (applicable for Overhead Line application) Pole Discrepency (applicable for 275kV bays application) Overcurrent (Applicable for Transformer and Capacitor Banks application) a. Check DC system is wired as per design. b. All tests shall be carried out using dummy breaker. c. All possible conditions tested shall be clearly mentioned in the test report. d. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. Circuit Breaker Failure Function The following test shall be performed to commission the Circuit Breaker Failure protection scheme: a. CBF initiation shall be performed with all relays which initiating CBF e.g. Current Differential, and being set with the final settings. b. CB/Isolator status input check from source end to confirm correct wiring for feeder (NO and NC Contacts). Simulate invalid status and verify alarm is sent after time delay c. Simulate isolator bridging condition from source end and verify alarm is sent after time delay d. Simulate AR in 3 Pole position and simulate a single phase fault condition. Verify CBF initiation are resulted in all 3 phases. e. Simulate AR failed and simulate a single phase fault condition. Verify CBF initiation are resulted in all 3 phases. f. Perform Stage 2 trip test to verify remote end and correct busbar trip accordingly. This test is to validate relay internal logic and the dedicated CBF bus wiring scheme. g. Perform trip test as per section 4.0. Auto-Reclose Function a. Any blocking signal to the auto-reclose scheme from main protection shall be tested by simulating the signal at the source point of the signal. b. Auto-reclose test shall be performed with all relays e.g. Current Differential, and being set with the final settings. c. During the auto-reclose simulation test, the synchronizing condition shall be achieved by injection of voltage to the CBM relay. %" ! "# $ $ d. Where main and duplicate protection is used, the whole test shall be repeated for both protections. e. During all auto-reclose tests, the following signals shall be monitored and recorded. Auto-reclose initiate GOOSE signal from the main protection relay Block auto-reclose GOOSE signal from the main protection relay Alarm initiated at HMI, SGW, and EGW Alarm initiated at fascia All trip and closing signals All indication at main protection relay and CBM relay 1 1 1 f. Auto-reclose test for selected faults shall be performed under the following conditions for all combination of phase to ground fault, phase to phase fault or three phase faults accordingly Auto reclose switch OFF Auto reclose switch ON – DAR only with sync OK Auto reclose switch ON – DAR only with sync fail Auto reclose switch ON – SPAR & DAR (evolving faults) with sync OK Auto reclose switch ON – SPAR & DAR (evolving faults) with sync fail Auto reclose switch ON – SPAR & DAR (evolving faults) with sync OK and with external A/R blocking signal Repeat i-vi with Auto reclose switch selection to 3 and 1+3 (applicable for 275kV and above) 1 1 1 1 g. Test the A/R scheme is not initiated if the CB is initially open. h. Test the A/R scheme with CB closing circuit isolated. i. Test the “Sync. Fail timer scheme”. j. During the auto-reclose test, timing of the following signals shall be monitored and documented for selected faults: Measure length of A/R close pulse to the CB closing coil Measure reclaim time Measure SPAR dead time Measure DAR dead time Measure sync fail timer 1 1 k. Upon successful completion of all above tests, tests as per the Table below shall be repeated with the actual CB and disturbance recorder connected. Main Protection No Fault Injected 1 R-N 2 B-N 3 4 5 R-N followed by B-N (evolving fault) R-Y Y-B 6 7 B-R R-N 8 B-N Scheme condition to be tested Successful single pole A/R (SPAR) Successful SPAR followed by second fault in 1 sec of reclaim time R-N fault followed by evolving fault on YN fault at 650 ms Successful delay A/R (DAR) Successful DAR followed by second fault in 20th sec of reclaim time SOTF φ-N, fault immediately after Manual Close Of CB φ-N, fault with CB initially open %' ! "# $ $ 9 l. 10 R-N followed by R-N immediately upon autoreclosing (TOR) Y-N 11 B-N 12 R-N TOR (Expected local and remote end lockout. Remote end Auto-reclose will be interrupted) Auto Reclose switched to OFF resulting in three-pole tripping with lockout operation. This is to verify external AR bridging circuit. Auto Reclose fail resulting in three-pole tripping without lockout operation and trip counter operate accordingly. This is to verify external AR bridging circuit. Auto Reclose switched to three Pole resulting in three-pole tripping without lockout operation and trip counter operate accordingly. This is to verify external AR bridging circuit. Confirm any backup protection not initiate Auto Reclose m. For 1HCB system, all tests, which are applicable, shall be carried out including but not limited to: • Trip on Reclose (TOR) (TOR from bus circuit breaker shall interrupt operation of center circuit breaker auto-reclosing) • Priority release scheme to be tested but not limited as per the table below No 1 Fault Injected R-N Bus Auto Reclose 1+3 Center Auto Reclose 1+3 2 Y-B 1+3 1+3 3 RYB 1+3 1+3 4 R-N OFF 1+3 5 Y-B OFF 1+3 6 Y-N 1+3 1+3 7 B-N 1+3 1+3 Scheme condition to be tested Single phase to ground fault (SPAR). Expected dead time difference of 1 sec between bus and center CB. Phase-to-phase fault (DAR). Expected dead time difference of 1 sec between bus and center CB. Three-phase fault. No AR. Center CB Auto-Reclose on SPAR. Expected Center CB dead time as per setting without extension. Center CB Auto-Reclose on DAR. Expected Center CB dead time as per setting without extension. Bus CB in open condition. Center CB Auto-Reclose on SPAR. Expected Center CB dead time as per setting without extension. Simulate Bus CB fail to close. Expected dead time difference of 1 sec between bus and center %( ! "# $ $ CB. At least the following combinations shall be tested • Each CB individually using dummy breaker • Both CB’s simultaneously using actual breaker Synchronization and Voltage Check Function The following test shall be performed to commission the synchronizing scheme: a. The following conditions of CB closing shall be tested: 1 Live Line - Live Bus (Synchronized closing) Live Line – Dead Bus Dead Line – Live Bus Dead Line – Dead Bus b. CVT MCB trip (incoming and running voltage) and Busbar CVT isolator open (running voltage) blocking signal shall be tested for blocking the voltage check scheme. c. Synchronizing scheme shall also be tested for any CVT MCB trip/Busbar CVT isolator open condition (expected synchronization permitted when simulating Live Line Live Bus). Pole Discrepancy Function The following test shall be performed to commission the PD scheme: a. Simulate CB single pole, 2 pole and 3 pole opening and verify PD operation b. Timing Test and CB Auxiliary contact (NO / NC) verification c. Protection trip test as per section 4.0 Intertrip Function (External initiation) The following test shall be performed to commission the intertrip scheme: a. All signals whichever available shall be tested: Intertrip send (Eg: CBF, Stub, SF6) Intertrip receive (Eg: CBF, Stub, SF6) CBF initiation to remote end (where applicable, usually for Stub Protection and End Zone Fault in 1HCB) e. The following test shall be performed on all above signals: 1 1 1 1 Check all the Send signals reach the remote end CBM with correct indication. Check all the Receive signals from remote end reach the local relays or CBM with correct indication at the local end. Record fascia operation for Send and Receive Record relay operation for Send and Receive e.g. flag relays, CBM Timing test for signal transmission delay, for all available signals. Reset time of the receive signal for at least one signal. Minimum signal window timing (e.g. less than 2.5 ms) of at least one signal to simulate noise shall be tested. This is to avoid any %) ! "# $ $ transient/spurious signal being transmitted. f. All general alarms from communication equipment and 48V DC system Overcurrent Function The following test shall be performed to commission the Overcurrent and Standby protection scheme: a. Perform protection trip test as per section 4. ! "# $ $ 9.4 Bay Controller Scheme Bay Controller (BC) consist of the following functions: • • • • • • • Manual Synchronization and Voltage Check (where applicable) Switchgear Operation and Interlock (Supervisory, Station, and Bay Levels) Undervoltage Earth Switch Interlock Live Transfer Bay Measurements Hardwiring Input to digital signals (MMS, GOOSE) Trip Counter a. Check DC system is wired as per design. b. All tests shall be carried out using dummy breaker. c. All possible conditions tested shall be clearly mentioned in the test report. d. Verify all required signals (measurement, alarm, indications, status, etc) from the Bay Controller are reported to HMI, EGW and SGW Manual Synchronizing and Voltage Check Function The following test shall be performed to commission the synchronising scheme: a. Secondary voltage injection as per Appendix I to test all voltage circuits. b. Secondary injection as per Appendix I on the synchroscope (275kV and above) c. Verify Order Run function such that only one bay can be synchronized at a time. d. Control Hierarchy facilities (Control Authority Selector, bay selector and local selector switches) shall be tested e. Synchronized closing of CB shall be tested from Supervisory, Station and Bay levels. The control priority shall be as follows (from highest to lowest): i. ii. iii. iv. f. Local (switchyard) Bay (Bay Controller) Station (HMI) Supervisory (Control Center) For Supervisory control, the test shall be carried out by initiating control from the Control Center after communications from the Control Center have been established via wired SGW. g. The following conditions of CB closing shall be tested: Live Line - Live Bus (Synchronized closing) Live Line – Dead Bus (Voltage checked closing) Dead Line – Live Bus (Voltage checked closing) Dead Line – Dead Bus (Voltage checked closing) 1 h. CVT MCB trip (incoming and running voltage) and Busbar CVT isolator open (running voltage) blocking signals shall be tested for blocking the voltage check function. The input shall be simulated at all source ends (VT MCB at MK, VT MCB at VT box etc) ! "# $ $ i. All necessary tests to prove that any component or relay failure in the scheme shall not cause any of the CVT’s to be back energized shall be performed. j. The performance of the synchronizing scheme shall also be tested during live transfer condition. following conditions: Switchgear Operation and Interlock (Supervisory, Station, and Bay Levels) Functions a. Section 3.0 shall be strictly followed to perform the operation and interlock tests. b. Interlock test shall only be performed after: Alignment test of all isolators completed Isolator auxiliary contact timing test completed. c. Interlocking condition from busbar isolator, line isolator and earthing switch shall only be given when the isolator’s primary arm is fully open or close. d. Position indication of switchgear at remote and supervisory shall only be given when the isolator’s primary arm is fully open or fully closed. e. Interlock test for all switchgears shall be tested from the following positions: Bay operation interlock Station operation interlock Supervisory operation interlock f. Verify Order Running function which allow control permission one bay at one time. g. Verify emergency CB opening is only allowed when Bay Controller fail. h. Verify Reconnection Inhibit for Capacitor circuit breaker. Confirm CB is not allowed to close immediately after it was detected open until timer elapsed. i. During bay operation interlock check, verify interlock indication light up only when interlock check has been fulfilled. Undervoltage Earth Switch Interlock The following test shall be performed to commission the Undervoltage Earth Switch Interlock scheme: Test earth switch interlock scheme to allow or block the earth switch operation during local control (switchyard) Live Transfer Function The following test shall be performed to commission the Live Transfer scheme: a. Test live transfer interlock scheme for each bay for all the following conditions: Live transfer from Main to Reserve Bus Live Transfer from Reserve to Main Live Transfer with Bus-Coupler and/or Bus-Section open. $ ! "# $ $ b. Bus-coupler and Bus-section trip blocking shall be checked during live transfer for each bay. Verify trip blocking applicable to all protection except busbar protection. c. Opening of isolator during live transfer is permitted only when the other isolator is fully closed. This test shall be carried out for all isolators. Bay Measurements Function The following secondary injection tests shall be performed: a. The measurement accuracy check for the complete range. b. Communication test (e.g Modbus) with other devices (e.g. HMI/SGW/EGW) c. Measurement parameters shall include all the required signals as per Grid Substation Signalling Requirements. d. Verify information consistency among Bay Controller, HMI, SCADA and EGW. Hardwiring Input to Digital Signals (MMS, GOOSE) Function a. Verify all the hardwired signal from the source end is reported to the HMI, EGW and SGW via the Bay Controller. Trip Counter Function a. Verify that all tripping from protection relays and master trip relay will operate the trip counter. % ! "# $ $ 9.5 Overload and Overcurrent Capbank Scheme This application consists of the following functions: • • Overload Capbank Overcurrent Capbank a. Check DC system is wired as per design. b. All possible conditions tested shall be clearly mentioned in the test report. c. Verify all required signals (measurement, alarm, indications, status, etc.) from the IOIED are reported to HMI, EGW and SGW Overload Capbank a. Perform Trip Test as per Section 4.0. Overcurrent Capbank a. Perform Trip Test as per Section 4.0. Busbar Measurements Function (applicable for Station IOIED) The following test shall be performed to commission the Overcurrent scheme: a. Perform protection trip test as per section 4. The following test shall be performed to commission the Under/Overvoltage Capbank Protection scheme: k. Secondary injection as per Appendix I to test alarm (fascia, HMI, EGW), SCADA and counter operation. l. Verify UV element blocking with CB status during energization. m. Perform trip test as per Section 4.0 ! "# $ $ 9.6 Undervotlage and Overvoltage Capbank Scheme This application consists of the following functions: • • Undervoltage Capbank Overvoltage Capbank a. Check DC system is wired as per design. b. All possible conditions tested shall be clearly mentioned in the test report. c. Verify all required signals (measurement, alarm, indications, status, etc.) from the IOIED are reported to HMI, EGW and SGW Undervoltage Capbank a. Verify UV element blocking with CB status during energization. b. Perform Trip Test as per Section 4.0. Overvoltage Capbank a. Perform Trip Test as per Section 4.0. & ! "# $ $ SAT Appendix O: SAT Stability Test of Unit/Differential Protection 1.0 2.0 3.0 4.0 5.0 6.0 Purpose ..................................................................................................................................... 1 Requirement prior to Stability Test............................................................................................ 1 Testing Conditions and Restrictions ......................................................................................... 2 Stability Tests for Unit Protection .............................................................................................. 3 Stability Tests for Differential/ Comparison Protection ............................................................. 4 Stability Tests for High Impedance Busbar Protection ............................................................. 6 Stability test using synchronized secondary injection method…………………………………...7 1.0 Purpose To provide SAT requirements in carrying out stability tests for all types of unit/differential protection e.g.: • High Impedance protection for: Transformer High Impedance Transformer HV REF Transformer LV REF Busbar protection T-zone protection • • 2.0 Requirement prior to Stability Test Differential protection for: Transformer Generator Line Cable Low Impedance busbar protection The pre-requisites for carrying out stability tests include: a. Drawing and design verification of the particular unit/differential protection. b. CT ratio selection of the unit/differential protection has been finalized. CT loop resistance measurement shall be completed and clearly documented. c. Ratio and vector group of the Interposing CT in the unit/differential protection has been finalized. d. All final settings of the unit/differential protection have been calculated, implemented and documented including stabilizing resistor if any. e. Test procedure as per Appendix B shall be available. ! "# $ $ 2.0 Requirement prior to Stability Test (Cont. 1) f. Test form as required in Appendix A shall be prepared with the following additional information: CT Ratios and knee point voltage of all CT’s in the unit/differential protection. ICT ratio and vector group for all ICT’s in the unit/differential protection if any. Relay settings For transformer differential protection, the following additional information is to be included: Transformer MVA Transformer Ratio Transformer Vector Group Fault simulated e.g. R-N, Y-N, in-zone, out-zone etc. Primary current values – at least 10% of rated CT ratio Secondary current readings: At CT After ICT’s Relay operating current 3.0 Testing Conditions and Restrictions a. All stability tests of the plant shall be carried out as the last SAT activity prior to the plant being commissioned. This may include stability tests for busbar protection, transformer differential protection and transformer high impedance protection. b. Any modification on a unit/differential protection scheme that has been tested shall subject that particular scheme to a complete retest. c. When stability tests are being carried out in a live substation all necessary isolation and precautions shall be documented in the testing procedure. $ ! "# $ $ 4.0 Stability Tests for Unit Protection # % $ $ ! " a. Based on Figure R1 stability tests shall be carried out for all unit protection e.g. transformer HV REF, LV REF etc. as follows: Tests shall be carried out for in-zone fault at point XX and out-zone fault at point YY. The test shall be performed for all phases, R-N, Y-N and B-N. During the test, record the following readings: Primary currents at both points A and B. CT secondary currents at the MK (points C and D) Relay operating current (point E) Voltage measurement at relay (point F) for high impedance protection. & ! " ' ! "$ b. For unit protection using three CT’s as illustrated in Figure R2, e.g. T-zone protection of 1½ breaker system, stability test shall be proven between points A & C and points A & B or points B & C. % ! "# $ $ 5.0 Stability Tests for Differential/ Comparison Protection % ! % ! '' ( a. ) ! " '' Based on Figure R3, stability tests shall be carried out for all differential/ comparison protection e.g. transformer differential protection, line/cable differential protection etc, as follows: Tests shall be carried out for In-zone three-phase fault at point XX. In-zone single phase fault at point XX (If and when possible for one phase only) Out-zone three phase fault at point YY. Out-zone single phase fault at point YY (If and when possible for one phase only) During the test, record the following readings: Primary currents of all phases at both points A and B. CT secondary currents of all phases at the MK (points C and D) Secondary current after ICT (point E and F) – where possible. Relay operating current of all phases ! "# $ $ 5.0 Stability Tests for Differential/ Comparison Protection (Cont. 1) * ! " ' )+ , # " '' b. For unit protection using three CT’s as illustrated in Figure R4 e.g. 3 winding transformers, stability test shall be proven between points A & C and points A & B or points B & C. c. For cable and line feeder with unit protection complete stability test shall be performed. Where it is not possible to perform the stability test, can be proven during on-load tests. & ! "# $ $ 6.0 Stability Tests for High Impedance Busbar Protection a. Stability tests shall be carried out for both high impedance and low impedance busbar protection scheme. For low impedance busbar protection scheme, stability test shall be carried as recommended in the manufacturer’s manual. b. Fault simulation and measurement points shall be as per the stability test for unit protection. c. Stability test shall be performed both for the check zone and all discriminative zones. d. Both in-zone and out-zone fault conditions shall be simulated and tested for all phase. e. The following is the stability test example meant for a double busbar configuration with bus-coupler and bus-section as illustrated in Figure R5 Similar concept shall be used to test other types of busbar configurations. f. One feeder shall be selected and maintained as a reference bay. All tests as listed in the table below shall be carried out to prove the stability. / 1 0 -& - . & . ! " ) $ $" * ' $ " ! "# $ $ 7.0 Stability test using synchronized secondary injection method a. The synchronized secondary injection method is applicable when there is no CT replacement, and requires: i. ii. iii. iv. Two units of secondary test set with same capability and characteristic (one at each ends of the differential scheme) Synchronized injection (using GPS) - differences in injection time will cause phase difference which will cause inaccurate / incorrect results Secondary injection should be carried out as close as possible to the secondary terminal of the CT (Marshaling Kiosk) - this will ensure that all secondary wiring will be part of the stability test For 3-terminal scheme, the secondary injection should be carried out from A to B terminal, and then proceed with A to C terminal. b. The test shall be conducted to low impedance unit protection i.e. OHL/UGC feeders, interconnectors and transformers differential where necessary. 8.0 Stability test using synchronized primary injection method a. The synchronized primary injection method when there is CT replacement, and requires: i. ii. iii. c. Two units of primary test set with same capability and characteristic (one at each ends of the differential scheme) Synchronized primary injection (using GPS) - differences in injection time will cause phase difference which will cause inaccurate / incorrect results For 3-terminal scheme, the primary injection should be carried out from A to B terminal, and then proceed with A to C terminal. The test shall be conducted to low impedance unit protection i.e. OHL/UGC feeders, interconnectors and transformers differential where necessary. ' ! "# $ $ SAT Appendix P: SAT for Final Inspection and Check 1.0 2.0 3.0 4.0 5.0 6.0 7.0 Purpose ..................................................................................................................................... 1 Requirement.............................................................................................................................. 1 Panel Inspection........................................................................................................................ 1 Setting Check ............................................................................................................................ 2 Primary Equipment & Switchyard Inspection ............................................................................ 2 Building & Civil .......................................................................................................................... 2 Final Operation & Trip Test ....................................................................................................... 2 1.0 Purpose At the end of the SAT, one day before energizing, the following final inspection and check shall be carried out : • • • Panel Inspection Setting check Final operation and trip test 2.0 Requirement a. The final inspection and check shall be carried out by the contractor and witnessed by TNB. Each check list shall be countersigned by both parties. 3.0 Panel Inspection a. All cubicles and panels as shall be subjected for panel inspection e.g.: CB, isolator control cubicles Transformer Local control panel, RTCC panel Protection control and relay panels b. The inspection shall be carried out using a proper check list. Each cubicle shall have a dedicated check list. Panel Inspection shall be documented as part of the commissioning report. c. The following shall be checked for in each panel: Heater switched on All MCB’s are switched on. All terminal block links are closed and tight including spares. All wires are properly terminated except spare wires. A proper note (with the purpose, person-in-charge and date) shall be made available for any: Terminal block links left open intentionally Wire open/disconnected intentionally. MCB left ‘OFF’. Check that there are no openings e.g. holes, doors not properly closed and door gaskets. Cubicle/panel lighting facility shall be functioning. Panel earthing and component earthing is complete. Check cubicle/panel for cleanliness. All temporary shorting/looping removed. d. Panels/cubicles shall be locked upon completion of the above inspection. !" # # 4.0 Setting Check All protection relay settings shall be re-checked with the documented final approved/endorsed settings. All other settings e.g. SF6 pressure gauge, winding temperature trip etc. shall also be checked. Confirm date and time of relays etc are set correctly. Clear all test records/events from relays and recorder a. Check all valves on transformers are in operational position. 5.0 Primary Equipment & Switchyard Inspection b. All temporary earthing in switchyard removed. c. All fuses are in and MCB are ON. a. Check fire-fighting system is on 6.0 Building & Civil b. Check A/C and all electrical and mechanical system. c. Check Switchyard lighting a. Test operation of all switchgear from substation control room. 7.0 Final Operation & Trip Test b. Perform one trip test from each protection relay i.e. distance, overcurrent, differential protection etc, by secondary injection. All circuit breakers shall be subjected to this trip test. # !" # # SAT Appendix Q: SAT for Secondary Live Maintenance 1.0 2.0 3.0 4.0 Purpose ..................................................................................................................................... 1 Requirement Prior to Live Maintenance Verification ................................................................. 1 Main Line Intergrated Current Differential Protection ............................................................... 1 Circuit Breaker Management .................................................................................................... 2 1.0 Purpose To perform secondary injection test for protection relays in live condition to validate Live maintenance features as intended design and certified the panel as “Live Maintenance Ready”. 2.0 Requirement Prior to Live Maintenance Verification This test should only be started after the following activities or conditions have been successfully verified: a. To check local/remote weather in good condition. b. Ensure all relays are in good condition. Ensure no relay indications are in operation. c. Ensure all tools (meters and shorting leads) are in good condition d. Ensure all test plug connection are as per drawing e. To check loading for the tested OHL/UGC bay at both ends and the parallel bay. Ensure that the load current is no less than 10% of the line rating. Also ensure the bay under test and its parallel bay both carry less than 50% of its total capacity to ensure N-1 contingency f. Ensure that there is no direct DC Earth Fault. Live Maintenance can proceed on high resistance DC Earth Fault (80% voltage) condition. g. Inform NLDC on Live Maintenance Works and Head of Zone after approval by NLDC. h. Label the relays being tested “LIVE MAINTENANCE TESTING IN PROGRESS” i. Refer to Testing Checklist as annexed in this document: a. b. 3.0 Main Line Integrated Current Differential Protection SAT Live Maintenance Certification (Phase 2) Testing Checklist F11L M1/M2 Line Integrated Current Differential Protection for 275/500kV OHL/UGC SAT Live Maintenance Certification (Phase 2) Testing Checklist F52CBM Circuit Breaker Failure Protection for 275/500kV OHL/UGC The following procedure shall be taken in the order as per below. The following example is performed on the Main 1 Line Integrated Current Differential Protection: a. Read and record Ibias and Idiff, voltage and power direction for all phase at the F11L(M1) relay at both ends. Expected value of all current input should be identical at both ends and Idiff must be zero. If measurements are not as per expected value, further investigation is to be carried out. b. Remove/pull out Group Isolation Link for F11L(M1) at both stations and ! "# $ $ validate the action by voltage measurement. Ensure measured voltage is zero at the following output contacts: i. ii. iii. iv. c. Trip Coil 1 (Bus CB and Center CB for 1HCB) Master Trip 1 & 2 (Bus CB and Center CB for 1HCB) Start CBF – R, Y, B, 3-ph (Bus CB and Center CB for 1HCB) Block AR (Bus CB and Center CB for 1HCB) Apply second trip isolation, shorting CT and Opening VT circuit by inserting test plug for F11L(M1) at both ends. Relay may operate and trigger indication at fascia at this point. Ensure there are no tripping to the Circuit Breaker. d. Check and verify from F11L(M1) HMI that there are no current input, voltage, Ibias and Idiff at both ends. This verifies the relay is already isolated from the CT and VT circuit via the test plug. e. Remove/pull out CT shorting and VT Group Isolation Link for F11L(M1). Ensure that the secondary current and voltage at the F11L(M1) test terminal block is zero. f. Perform both 87L and 21Z trip test function via the test plug. All tests shall use wet contact from the test plug only and the positive and negative supply can be taken directly from the test plug. Confirm and verify that there are no tripping of the Circuit Breaker, Master Trip Relay operation, and initiation to start the CBF function. g. Reset all fascia and relay indications. h. Normalizing the system by first insert/put in CT/VT shorting and CT Group Isolation Link for F11L(M1) at both ends. i. Measure and record the secondary current and voltage at the F11L(M1) test terminal block. Ensure that the current and voltage input from the CT and VT reaches up to the test terminal block at both ends. j. Remove the test plug for F11L(M1) at both ends. Relay may operate and trigger indication at fascia at this point. Ensure there are no tripping to the Circuit Breaker. k. Check and verify from the F11L(M1) HMI the current input, voltage, Ibias and Idiff at both ends. Ensure that the current and voltage input from the CT and VT reaches up to the F11L(M1) relay terminal at both ends. Ensure Idiff is zero and the relay is not in operation. l. Insert/put in Group Isolation Link for F11L(M1) at both stations. Ensure measured voltage is negative at the following output contacts. i. ii. iii. iv. 4.0 Circuit Breaker Management Trip Coil 1 (Bus CB and Center CB for 1HCB) Master Trip 1 & 2 (Bus CB and Center CB for 1HCB) Start CBF – R, Y, B, 3-ph (Bus CB and Center CB for 1HCB) Block AR (Bus CB and Center CB for 1HCB) The following procedure shall be taken in the order as per below: a. Read and record the current and voltage measurement for all phase at the F50CBM relay. $ ! "# $ $ b. Remove/pull out Group Isolation Link for F50CBM. Ensure measured voltage is zero after isolation: i. ii. iii. iv. v. c. Master Trip 1 & 2 (Bus CB and Center CB for 1HCB) CBF Stage 2 to Busbar (Bus CB for 1HCB) CBF Stage 2 to Center CB (Bus CB for 1HCB) CBF Stage 2 to Bus CB (Center CB for 1HCB) Intertrip to remote end (Both feeders for Center CB in 1HCB) Perform second trip isolation and shorting CT and Opening VT circuit by inserting test plug for F50BCM. Relay may operate and trigger indication at fascia at this point. Ensure there are no tripping to the Circuit Breaker. d. Check and verify from F50BCM HMI that there are no current and voltage input to the relay. This verifies the relay is already isolated from the CT and VT circuit via the test plug. Measure and record the current circuit the Digital Fault Recorder and relay HMI. e. Apply second CT shorting and VT opening by removing/pulling out CT shorting and VT Group Isolation Link for F50CBM. Ensure that the secondary current and voltage at the F50CBM test terminal block is zero. Measure and record the secondary current and voltage at the F50CBM relay test terminal block. f. Perform the following functions via the test plug: i. ii. iii. iv. v. CBF Stage 1 CBF Stage 2 Pole Discordance Intertrip Receive and Send Auto-Reclose Start and Blocking All tests shall use wet contact from the test plug only and the positive and negative supply can be taken directly from the test plug. Confirm and verify that there are no tripping of the Circuit Breaker, Master Trip Relay operation, and initiation to start the CBF function. g. Reset all fascia and relay indications. h. Insert/put in CT shorting and CT Group Isolation Link for F50CBM. i. Measure and record the secondary current and voltage at the F50CBM test terminal block. Ensure that the current and voltage input from the CT and VT reaches up to the test terminal block. j. Remove the test plug for F50CBM. Relay may operate and trigger indication at fascia at this point. Ensure there are no tripping to the Circuit Breaker. k. Check and verify from the F50CBM HMI the current and voltage input. Ensure that the current and voltage input from the CT and VT reaches up to the F50CBM relay terminal. All current and voltage input at the F50CBM relay is expected to be the same as the Digital Fault Recorder. Further investigation is to be carried out if measurement values are not as expected l. Insert/put in Group Isolation Link for F50CBM. Ensure measured voltage is negative at the following output contacts: i. ii. iii. Master Trip 1 & 2 (Bus CB and Center CB for 1HCB) CBF Stage 2 to Busbar (Bus CB for 1HCB) CBF Stage 2 to Center CB (Bus CB for 1HCB) % ! "# $ $ iv. v. • 5.0 Certification ! "# CBF Stage 2 to Bus CB (Center CB for 1HCB) Intertrip to remote end (Both feeders for Center CB in 1HCB) Test shall be verified and certified by all the relevant parties, namely Tester, Electrical Service Engineer and TNB representative (PM and GM). Upon completion, “Live Maintenance Ready” sticker shall be provided to the panel per said. $ $ SAT Live Maintenance Certification (Phase 2) Testing Checklist F11L M1/M2 Line Integrated Current Differential Protection for 275/500kV OHL/UGC CONTENTS: 1. WORK OBJECTIVE 2. LOCATION 3. SCOPE OF WORK 3.1 Work Description 3.2 Work Program 4. RISK ANALYSIS 5. DETAILS WORK PROCEDURES (WORK INVOLVE) 5.1 Prerequisite Check (System Condition Check) 5.2 Wiring &Setting Check (F11L(M1) 5.3 Isolation / Scheme Defeat (F11L(M1) 5.4 Testing Work (F11L(M1) 5.5 Normalization & Scheme Restoration 6. CONTIGENCY ACTION PLAN 1. WORK OBJECTIVE To perform secondary injection test for Main 1 & Main 2 Line Integrated Current Differential Protection relay in live condition to validate Live maintenance feature as intended design and certified the panel as “Live maintenance Work Compliance”, 2. LOCATION PMU: ………………………………………. Panel Designation: ……………………… 3. SCOPE OF WORK 3.1 Work Description • To perform operational and timing test secondary injection for Main1 F11L & Main 2 F11L in live condition and apply live maintenance feature. • To verify all tripping output and SCADA & annunciator indication in functional and good condition. • To certify the panel ready to perform Preventive Live Maintenance 3.2 Work Program Work Description Remark 1) Preliminary check at Site/Bay/Panel for verification of CT circuit, VT circuit, tripping circuit, Test Socket & Isolation check list 2) Trip isolation and short CT/Open VT circuit at F11L(M1/M2) 3) Testing F11L(M1/M2) protection relay 4) Normalize trip output and CT/VT circuit at F11L(M1/M2) 4. RISK ANALYSIS Detail work description, the RISK of each activity and the Mitigation involved Description 1. Testing Activity Risk involved Personnel a) DC or AC supply insulation leak may cause electrical shock. b) Flashover due to wrong termination may cause Mitigation / Minimizing Risk Personnel i) Use proper PPE & tools. ii) Check insulation resistance of wiring to earth. iii) Do not leave any cut Description Risk involved injury. Apparatus/Equipment a. Damage to relays due to testing b. Damage of CT due to CT open Circuit Mitigation / Minimizing Risk wires in the trucking. Apparatus/Equipment i) Injection values must not exceed rated values stated in the relay manuals. ii) When handling relay printed circuit board always earth body to prevent static voltage. iii) Use the correct DC voltage to energize relay inputs. i) Make sure shorting leads and test plug in good condition. ii) Confirm function no. from relay to terminal block is correct. iii) Make current measurement to confirm shorting done properly. System i) Extra care to be taken to ensure the correct bay under-test at both ends is i) Wrongly implementing live maintenance procedure identified ii) Ensure that test plug in in sequence good condition ii)DC earth fault can cause iii) Ensure the correct mal operation to the relays been identified for existing system. iii) protection scheme is not testing for both ends. iv) Ensure correct fully switched off/defeated. sequence during isolation before perform testing with validation System Tripping of live bays. 5.0 DETAILS WORK PROCEDURES (WORK INVOLVE) 5.1 Prerequisite Check (System Condition Check) Action To check local/remote weather in good condition Make sure Protection personal at remote END ready for; • To remove group isolation link Make sure all relays in good conditions. Ensure no relay indication operated To make sure all required tools in good condition (meters and test plug) To make sure all test plug connection as per drawing. To check loading for tested OHL/UGC bay at both end and the parallel bays. Ensure load current not less than 10% of line rating Note: At any condition, bay under test and parallel bays shall carry less than 50% load to allow for N-1 contingency Prerequisite before testing Measure DC voltage to check for any DC earth fault 1) If there is direct DC Earth Fault. Live maintenance shall not be proceeded 2) If the DC Earth Fault was high resistive (80% voltage), Live Maintenance can be proceeded with consensus from TNB. Inform to TNB management or Head Of Unit Inform NLDC for Live Maintenance Transfer all bay to Reserve busbar and tested bay at Main busbar at both stations. Set Bus Separation zone 2 instantaneous Remarks 5.2 Isolation / Scheme Defeat 87L(M1) Objective Step 1 To confirm Ibias & Idiff of 87L Action Read & record I bias & I diff measurement, voltage and power direction all phase at F11L(M1) relay at both end PMU A: Phase I local I remote I bias (Amp) I diff (Amp) Voltage Power Direction I local I remote I bias (Amp) I diff (Amp) Voltage Power Direction Verification/ Remark Ensure measurement at both station identical and I diff expected 0 amp Red Yellow Blue PMU B: Phase Red Yellow Blue Note: Expected all current value input should be identical at both end and I diff must be zero. If measurement is not as per expected value, further investigation to be carried out. Step 2 To apply isolate tripping F11L(M1) i- Remove/Pull out Group Isolation Link for F11L(M1) at both stations. Note: For 1HCB, remove group isolation link for each CB Measure output from F11L(M1) at test plug Description Expected Voltage CB Trip Coil 1 R phs 0 CB Trip Coil 1 Y phs 0 CB Trip Coil 1 B phs 0 Master trip 1 Operated 0 Master trip 2 Operated 0 Start CBF phs. R 0 Start CBF phs. Y 0 Measured Voltage Confirm and verify 0 V dc voltage at output contact for tripping and CBF initiation at test plug PASS/FAILED Objective Action Verification/ Remark Start CBF phs. B 0 Start CBF 3 phs. 0 Block A//R 0 CB Trip Coil 1 R phs- Q0B 0 CB Trip Coil 1 Y phs -Q0B 0 CB Trip Coil 1 B phs-Q0B 0 Master trip 1 Operated-Q0B 0 Master trip 2 Operated-Q0B 0 Start CBF phs. R -Q0B 0 Start CBF phs. Y -Q0B 0 Start CBF phs. B -Q0B 0 Start CBF 3 phs. -Q0B 0 Block A/R-Q0B 0 Note: -Q0B Center CB for 1HCB ii- Check and verify input CBM “A/R Inhibit BI” records no voltage Measure at CBM relay Description Expected Voltage Main 1 A/R Inhibit 0V Main 2 A/R Inhibit + 60 V Measured Voltage Confirm and verify at relay CBM voltage at input “A/R Inhibit” for Main 1 or 2 (whichever under tested) not available PASS/FAILED Main 1 A/R Inhibit Note: Only applicable for 1HCB center CB 0V Main 2 A/R Inhibit Note: Only applicable for 1HCB center CB Step 3 To apply 2nd trip isolation and short CT & open VT circuit + 60 V i- Insert test plug RTXP24 for F11L(M1) at both end Note: During insert test plug, F11L(M1) relay may operate and indication at facia will trigger. Expect no tripping to CB as Group Isolation link has isolated the tripping circuits. ii- Check and verify from F11L(M1) LCD no current input, voltage, Ibias and Idiff at both end. This verify F11L(M1) already isolated from CT & VT circuit by test plug. Confirm and verify from F11L(M1) HMI/LCD that no current input, voltage, Ibias and Idiff at both ends. Objective Action Verification/ Remark PASS/FAILED PMU A: Phase I local I remote I bias (Amp) I diff (Amp) Voltage Local I local I remote I bias (Amp) I diff (Amp) Voltage Local Red Yellow Blue PMU B: Phase Red Yellow Blue iii- Reset relay F11L at both ends. Ensure no relay operation. Insert back group isolation link. Verify tripping related circuits isolation with test plug insertion by measuring output from F11L(M1) at relay terminal. Description Expected Voltage CB Trip Coil 1 R phs 0 CB Trip Coil 1 Y phs 0 CB Trip Coil 1 B phs 0 Master trip 1 Operated 0 Master trip 2 Operated 0 Start CBF phs. R 0 Start CBF phs. Y 0 Start CBF phs. B 0 Start CBF 3 phs. 0 Block A//R 0 CB Trip Coil 1 R phs- Q0B 0 CB Trip Coil 1 Y phs -Q0B 0 CB Trip Coil 1 B phs-Q0B 0 Measured Voltage Confirm and verify no tripping and no CBF initiation by voltage measurement. verify 0 V dc voltage at output contact for tripping and CBF initiation at relay terminal PASS/FAILED Objective Action Verification/ Remark Master trip 1 Operated-Q0B 0 Master trip 2 Operated-Q0B 0 Start CBF phs. R -Q0B 0 Start CBF phs. Y -Q0B 0 Start CBF phs. B -Q0B 0 Start CBF 3 phs. -Q0B 0 Block A/R-Q0B 0 Note: -Q0B Center CB for 1HCB iii- Check and verify CBM “A/R Inhibit BI” records voltage Measure at CBM relay Description Expected Voltage Main 1 A/R Inhibit + 60 V Main 2 A/R Inhibit + 60 V Measured Voltage Main 1 A/R Inhibit Note: Only applicable for 1HCB center CB + 60 V Main 2 A/R Inhibit Note: Only applicable for 1HCB center CB + 60 V iv- Remove Group trip isolation link again to ensure double trip isolation implemented Step 4 To apply 2nd short CT Circuit F11L at terminal block Remove or pull out CT Shorting & VT group isolation link for F11L(M1) Measure and record secondary current and voltage at terminal test block relay F11L(M1) PMU A Phase Red Yellow Blue Current (Amp) Voltage Confirm and verify CT/VT cirucit is shorted and isolated by AC Group Isolaiton link. Measure no current and voltage input, voltage both end. PASS/FAILED Objective Action Verification/ Remark PMU B Measure and record secondary current and voltage at terminal test block relay F11L(M1) Phase Current (Amp) Voltage Red Yellow Blue 5.3 Testing Work (F11L(M1) Objective Verification/ Remark Action Step 5 To verify relay communication Record existing communication Setting for Local and remote. Address LOCAL REMOTE Address for loop back testing Address LOCAL REMOTE Step 6 To proceed with functional F11L testing Perform 87L trip test function at both ends. Ensure lockout relay 86E 1/2 not operated, no initiation to CBF Phase R-N Y-N B-N R-Y-B Relay Operation 86E1/2 Start CBF CB Operation Confrim and verify no CB tripping, 86E operation and no CBF initiation. PASS/FAILED Objective Verification/ Remark Action Perform 21Z trip test function Phase Relay Operation 86E1/2 Start CBF CB Operation Zone 1 R-N Zone 2 Y-N Zone 3 B-N * All testing using wet contact from test plug only and supply +ve or –ve can be taken directly from RTXP24 87L(M1) test plug 5.4 Normalization & Scheme Restoration (F11L(M1) Objective Action Step 7 Ready for normalization Reset all facia and relay operation ! " Normalize CT circuit and VT circuit Insert or pull-in CT shorting & VT group isolation link for F11L(M1) at both end Measure and record secondary current and voltage at terminal test block relay F11L(M1) PMU A Phase Current (Amp) Voltage Verification/ Remark Confirm and verify from CT/VT terminal F11L(M1) current and voltage input available at both end Red Yellow PASS/FAILED Blue PMU B Phase Red Yellow Current (Amp) Voltage Objective Action Verification/ Remark Blue ! " To normalize CT & VT circuit to relay F11L(M1) i- Remove test plug RTXP24 for F11L(M1) at both end Note: During remove test plug, F11L(M1) relay may operate and indication at facia will trigger. Ensure no tripping to CB ii- Check and verify from F11L(M1) LCD current input, voltage, Ibias available and Idiff at both end 0 amp. This verify F11L(M1) already connected from CT & VT circuit. PMU A: Phase I local I remote I bias (Amp) I diff (Amp) Voltage Local Red Yellow Blue Confirm and verify no tripping and no CBF initiation. Confirm and verify from F11L(M1) LCD current input, voltage, Ibias available and Idiff 0 A at both end. PASS/FAILED PMU B: Phase I local I remote I bias (Amp) I diff (Amp) Voltage Local Red Yellow Blue Verify trip isolation from test plug by measure output from F11L(M1) at test plug Description Expected Voltage CB Trip Coil 1 R phs 0 CB Trip Coil 1 Y phs 0 CB Trip Coil 1 B phs 0 Master trip 1 Operated 0 Master trip 2 Operated 0 Start CBF phs. R 0 Start CBF phs. Y 0 Start CBF phs. B 0 Measured Voltage Confirm and verify 0 V dc voltage at output contact for tripping and CBF initiation at test plug PASS/FAILED Objective Action Verification/ Remark Start CBF 3 phs. 0 Block A//R 0 CB Trip Coil 1 R phs- Q0B 0 CB Trip Coil 1 Y phs -Q0B 0 CB Trip Coil 1 B phs-Q0B 0 Master trip 1 Operated-Q0B 0 Master trip 2 Operated-Q0B 0 Start CBF phs. R -Q0B 0 Start CBF phs. Y -Q0B 0 Start CBF phs. B -Q0B 0 Start CBF 3 phs. -Q0B 0 Block A/R-Q0B 0 Note: -Q0B Center CB for 1HCB Step 10 To normalize tripping output i- Insert Group Isolation Link for F11L(M1) at both stations. Note: Insert each group isolation link for respective CB and measured output contact at terminal relay. Description Expected Voltage CB Trip Coil 1 R phs -60 V CB Trip Coil 1 Y phs -60 V CB Trip Coil 1 B phs -60 V Master trip 1 Operated -60 V Master trip 2 Operated -60 V Start CBF phs. R -60 V Start CBF phs. Y -60 V Start CBF phs. B -60 V Start CBF 3 phs. -60 V Block A/R -60 V CB Trip Coil 1 R phs- Q0B -60 V Measured Voltage Confirm and verify –ve dc voltage at output contact for tripping and CBF initiation at terminal relay PASS/FAILED Objective Action Verification/ Remark CB Trip Coil 1 Y phs -Q0B -60 V CB Trip Coil 1 B phs-Q0B -60 V Master trip 1 Operated-Q0B -60 V Master trip 2 Operated-Q0B -60 V Start CBF phs. R -Q0B -60 V Start CBF phs. Y -Q0B -60 V Start CBF phs. B -Q0B -60 V Start CBF 3 phs. -Q0B -60 V Block A/R-Q0B -60 V Note: -Q0B Center CB for 1HCB ii- Check and verify main 1/2 “A/R Inhibit BI” records voltage Measure at CBM relay Description Expected Voltage Main 1 A/R Inhibit +60 V Main 2 A/R Inhibit +60 V Main 1 A/R Inhibit Note: Only applicable for 1HCB center CB +60 V Main 2 A/R Inhibit Note: Only applicable for 1HCB center CB Step 10 To normalize Bus Separation relay +60 V Normalize Bus Separation zone 2 setting Measured Voltage Confirm and verify at relay CBM input that A/R Inhibit for Main 1 and 2 available PASS/FAILED 6. CONTIGENCY ACTION PLAN 1) Specify other source /emergency supply restoration Example: Probable Incident/ Tripping Cause of Incident /Tripping Corrective Action 1a) Tripping • Bay under test • Bay not tested Wrong Injection or incomplete tripping isolation Stop testing Report to NLDC/RCC Request for authorization and do investigation. Normalize back CB. Actual fault occurred, and tripping by others protection relays Stop testing Report to NLDC/RCC Request for authorization and do investigation. Normalize back CB. Resume testing prior to normalize back CB or Resume testing in other time Stop testing Normalize back all CT circuit immediately Stop Testing and normalize the system. Do investigation 2)CT Harming CT open circuit 3) DC Earth Fault appear Improper secondary wiring during testing #$ $% % %& ' ( #$ $% % %& ( ' ) *+ ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, - ( . - + ) / $1$ ( + & $& ! ) $& % $% !$ % 0 $ % -- ( + ) 2 $( !$ % 0 3"" + 2 $( $% % %& ) ") % !$ % 0 !$ % 0 SAT Live Maintenance Certification (Phase 2) Testing Checklist F52CBM Circuit Breaker Failure Protection for 275/500kV OHL/UGC CONTENTS: 1. WORK OBJECTIVE 2. LOCATION 3. SCOPE OF WORK 3.1 Work Description 3.2 Work Program 4. RISK ANALYSIS 5. DETAILS WORK PROCEDURES (WORK INVOLVE) 5.1 Prerequisite Check (System Condition Check) 5.2 Wiring &Setting Check (F11L(M1) 5.3 Isolation / Scheme Defeat (F11L(M1) 5.4 Testing Work (F11L(M1) 5.5 Normalization & Scheme Restoration 6. CONTIGENCY ACTION PLAN 1. WORK OBJECTIVE To perform secondary injection test for Main 1 & Main 2 Line Integrated Current Differential Protection relay in live condition to validate Live maintenance feature as intended design and certified the panel as “Live maintenance Work Compliance”, 2. LOCATION PMU: ………………………………………. Panel Designation: ……………………… 3. SCOPE OF WORK 3.1 Work Description • To perform operational and timing test secondary injection for Main1 F11L & Main 2 F11L in live condition and apply live maintenance feature. • To verify all tripping output and SCADA & annunciator indication in functional and good condition. • To certify the panel ready to perform Preventive Live Maintenance 3.2 Work Program Work Description Remark 1) Preliminary check at Site/Bay/Panel for verification of CT circuit, VT circuit, tripping circuit, Test Socket & Isolation check list 2) Trip isolation and short CT/Open VT circuit at F11L(M1/M2) 3) Testing F11L(M1/M2) protection relay 4) Normalize trip output and CT/VT circuit at F11L(M1/M2) 4. RISK ANALYSIS Detail work description, the RISK of each activity and the Mitigation involved Description 1. Testing Activity Risk involved Personnel a) DC or AC supply insulation leak may cause Mitigation / Minimizing Risk Personnel i) Use proper PPE & tools. ii) Check insulation Description Risk involved electrical shock. b) Flashover due to wrong termination may cause injury. Apparatus/Equipment a. Damage to relays due to testing b. Damage of CT due to CT open Circuit Mitigation / Minimizing Risk resistance of wiring to earth. iii) Do not leave any cut wires in the trucking. Apparatus/Equipment i) Injection values must not exceed rated values stated in the relay manuals. ii) When handling relay printed circuit board always earth body to prevent static voltage. iii) Use the correct DC voltage to energize relay inputs. i) Make sure shorting leads and test plug in good condition. ii) Confirm function no. from relay to terminal block is correct. iii) Make current measurement to confirm shorting done properly. System i) Extra care to be taken to ensure the correct bay under-test at both ends is i) Wrongly implementing live maintenance procedure identified ii) Ensure that test plug in in sequence good condition ii)DC earth fault can cause iii) Ensure the correct mal operation to the relays been identified for existing system. iii) protection scheme is not testing for both ends. iv) Ensure correct fully switched off/defeated. sequence during isolation before perform testing with validation System Tripping of live bays. 5.0 DETAILS WORK PROCEDURES (WORK INVOLVE) 5.1 Prerequisite Check (System Condition Check) Action To check local/remote weather in good condition Make sure all relays in good conditions. Ensure no relay indication operated To make sure all required tools in good condition (meters and shorting leads) To make sure all test plug connection as per drawing. To check loading for tested OHL/UGC bay at both end and the parallel bays. Ensure load current not less than 10% of line rating Note: At any condition, bay under test and parallel bays shall carry less than 50% load to allow for N-1 contingency Prerequisite before testing Measure DC voltage to check for any DC earth fault 1) If there is direct DC Earth Fault. Live maintenance shall not be proceeded 2) If the DC Earth Fault was high resistive (80% voltage), Live Maintenance can be proceeded with consensus from TNB. Inform to TNB management or Head Of Unit Inform NLDC for Live Maintenance Transfer all bay to Reserve busbar and tested bay at Main busbar at both stations. Set Bus Separation zone 2 instantaneous Remarks 5.2 Isolation / Scheme Defeat F52CBM Step 1 Objective Action Verification/ Remark To confirm current & voltage input at relay Read & record Current and voltage measurement all phase at F50CBM relay Record measurement current and voltage at HMI relay Phase Current Voltage Red Yellow Blue Step 2 To apply isolate tripping F50CBM i- Remove/Pull out Group Isolation Link for 50CBF ii- Check and verify all tripping output and lock-out relay at test plug 50CBF with no –ve to ground to ensure all tripping output was isolate by group isolation link. Description Step 3 To apply 2nd trip isolation and short CT & open VT circuit Expected Voltage Master Trip 1 -A 0 Master trip 2 - A 0 CBF Stage 2 busbar tripping 0 Intertrip remote end-A 0 Master Trip 1 -B 0 Master trip 2 - B 0 CBF Stage 2 CB center/Bus trip 0 Intertrip remote end-A 0 Measured Voltage Insert test plug RTXP 14 for F50CBM. Note: During insert test plug, F50CBM relay may operate and indication at annunciator will trigger. Ensure no tripping to CB i- Check and verify from F50CBM HMI record no current input to verify F50CBM is already isolated from CT circuit by test plug ii- Measure and record current circuit at Fault Recorder and relay HMI: Confirm and verify 0 V dc voltage output contact for tripping at test plug CBM. PASS/FAILED Confirm and verify from F50CBM HMI/LCD that no current input & voltage. Confirm circuit continuaity to DFR by current measurement/reading PASS/FAILED Objective Action Phase Current at F50CBM HMI Verification/ Remark Voltage F50CBM HMI Current at Fault Recorder Red Yellow Blue iii- Reset relay F50CBM and ensure no relay operation. Insert back group isolation link. iv- Check and verify all tripping output and lock-out relay at terminal relay with no –ve to ground to ensure all tripping output was isolate by group isolation link. Description Step 4 To apply 2nd short CT Circuit F50CBM at terminal block Expected Voltage Master Trip 1 -A 0 Master trip 2 - A 0 CBF Stage 2 busbar tripping 0 Intertrip remote end-A 0 Master Trip 1 -B 0 Master trip 2 - B 0 CBF Stage 2 CB center/Bus trip 0 Intertrip remote end-A 0 Measured Voltage Measure and record secondary current and voltage at terminal test block relay 50CBM PMU A Red Yellow Blue Current (Amp) Voltage Verify 0 V dc voltage output contact for tripping at relay terminal CBM. PASS/FAILED Remove or pull out CT Shorting & VT group isolation link for F50CBM Phase Confirm and verify tripping circuit isolation by voltage measurement. Current at Fault Recorder Confirm and verify CT/VT cirucit is shorted and isolated by AC Group Isolaiton link. Measure no current and voltage input, voltage both end and no current interruption to DFR PASS/FAILED 5.3 Testing Work F52CBM Objective Verification/ Remark Action Step 6 To proceed with functional F50CBM testing Perform Pole discordance operation Confirm and verify no tripping and no CBF initiation. Perform simulate Intertrip receive and send function PASS/FAILED Perform CBF function testing stage 1 operation Perform CBF function stage 2 operation Phase Relay Operation 86E1/2 Bus Trip CB Operation CBF stg.1 CBF stg.2 Pole Discordance Inter-trip send Inter-trip Receive * All testing using wet contact from test plug only and supply +ve or –ve can be taken from RTXP24 87L(M1) test plug 5.4 Normalization & Scheme Restoration F52CBM Objective Step 7 Ready for normalization Action Reset all facia and relay operation Verification/ Remark Objective ! Normalize CT circuit and VT circuit Action Insert or pull-in CT shorting & VT Group isolation link for F50CBM. Measure and record secondary current and voltage at terminal test block relay 50CBM PMU A Phase Current (Amp) Voltage Current at DFR Red Verification/ Remark Confirm and verify from CT/VT terminal F50CBM current and voltage input available voltage PASS/FAILED Yellow Blue Running Voltage ! To normalize CT & VT circuit to relay F11L(M1) i- Remove test plug RTXP24 at F52CBM ii- Check and verify from F52CBM HMI/LCD and recorder that current and voltage is available This action is to verify F50CBM already connected to CT & VT circuit. Phase Current at F50CBM HMI Voltage F50CBM at HMI Current at Fault Recorder Red Yellow Blue Note: All current input and voltage input at CBM and at fault recorder should be available as expected. If measurement is not as per expected value, further investigation to be carried out. Check and verify all tripping output and lock-out relay at test plug relay has no –ve to ground to ensure all tripping output was isolated by group isolation link. Confirm and verify from F50CBM HMI that current and voltage input available PASS/FAILED Objective Action Description Step 10 To normalize tripping output Expected Voltage Master Trip 1 -A 0 Master trip 2 - A 0 CBF Stage 2 busbar tripping 0 Intertrip remote end-A 0 Master Trip 1 -B 0 Master trip 2 - B 0 CBF Stage 2 CB center/Bus trip 0 Intertrip remote end-A 0 Measured Voltage PASS/FAILED i- Insert in Group Isolation Link for F50CBM ii- Check and verify all tripping output and lock-out relay at terminal 50CBM with –ve to ground to ensure all tripping output was connected by group isolation link. Description Expected Voltage Master Trip 1 -A -60 V Master trip 2 - A -60 V CF Stage 2 busbar tripping -60 V Master Trip 1 -B -60 V Master trip 2 - B -60 V Intertrip remote end-B Measured Voltage Confirm and verify –ve dc voltage at output contact for tripping and CBF initation. PASS/FAILED 0V Intertrip remote end-A CF Stage 2 CB center/bus trip Verification/ Remark Confirm and verify 0 V dc voltage output contact for tripping at test plug CBM. 0V -60 V Note: -Q0B Center CB for 1HCB Step 11 To normalize Bus Separation relay Normalize Bus Separation zone 2 setting " 6. CONTIGENCY ACTION PLAN 1) Specify other source /emergency supply restoration Example: Probable Incident/ Tripping Cause of Incident /Tripping Corrective Action 1a) Tripping • Bay under test • Bay not tested Wrong Injection or incomplete tripping isolation Stop testing Report to NLDC/RCC Request for authorization and do investigation. Normalize back CB. Actual fault occurred, and tripping by others protection relays Stop testing Report to NLDC/RCC Request for authorization and do investigation. Normalize back CB. Resume testing prior to normalize back CB or Resume testing in other time Stop testing Normalize back all CT circuit immediately Stop Testing and normalize the system. Do investigation 2)CT Harming CT open circuit 3) DC Earth Fault appear Improper secondary wiring during testing #$ $% % %& ' ( #$ $% % %& ( ' ) *+ ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, - ( . - + ) / $1$ ( + & $& ) $& % $% $ % 0 $ % -- ( + ) 2 $( $ % 0 3!! + 2 $( $% % %& ) !) % $ % 0 $ % 0 SAT Appendix R: On Load / Commissioning Test 1.0 General Requirement ................................................................................................................ 1 a. On energizing of a plant, measurements shall be made all associated VT and CT circuits of the plant. 1.0 General Requirement b. Upon commissioning, verify correct operation of point of wave opening switching device. Verify the opening is performed at the zero crossing current and closing at the peak voltage. TNB will assist this test by providing the power quality analyzer and the printout. Analysis of the printout shall form part of the test report. c. For voltage circuits the following secondary measurements and tests shall be carried out at the end point e.g. MK and at the component end e.g. protection relays, instruments, recorders etc. All phase to phase voltage measurements All phase to neutral voltage measurements All phase to ground voltage measurements All phase sequence tests Phasing test (if a reference bay is available) c. For current circuits the following secondary measurements shall be carried out at the component end e.g. protection relays, instruments, recorders etc. All phase current measurement All neutral current measurement d. For primary circuits (415V – 33kV switchgear), the following measurements and tests shall be made at the primary side of the component end. Appropriate instruments shall be used for such high voltage measurements and tests. All phase to phase voltage measurement All phase to neutral voltage measurement Phasing test (if a reference bay is available) e. For all protection with specific operation direction e.g. distance protection, DEF, directional tests shall be performed. Any protection relay that requires compensated parameters shall be set based on load measured values. (E.g. Unbalanced current for capacitor bank, charging current for line differential, circulation current for AVR) f. Circulating current method shall be used to prove stability of differential protection e.g. transformer, busbar, line and cable differential protection. g. Measurement shall also be made on broken delta voltages and residual current circuit. h. For all protection relays with built-in instrument functions, all measurement reading available from the relay shall be recorded. ! "# i. All fault recorders to be manually triggered and verified. j. Live transfer scheme for all bays shall be tested for both conditions e.g. from main to reserve and from reserve to main. $ $ k. 1.0 General Requirement (Cont.) For CB with synchronizing facilities all the following closing conditions shall be tested from REMOTE and SUPERVISORY. Live Line – Live Bus Live Line – Dead Bus Dead Line – Live Bus l. For transformer, the on load tap changer facility shall be checked e.g. parallel operation (reactive current), independent operation, auto tap raising and lowering. m. For capacitor bank – CB closing via Point of wave operation shall be recorded and verified. n. All the above on-load tests shall be documented clearly as part of the commissioning test report. o. All spare bays shall also be energized and any applicable on-load tests above shall be performed. p. For 415 AC Board test to be carried out to ensure there is no back feed / paralleling of two sources via load circuit. (With bus tie open and one source feeding). $ ! "# $ $ SAT Appendix S: SAT for Post Commissioning Test 1.0 Purpose…………………………………………………………………………………………………1 2.0 General Requirement………………………………………………………………………………….2 3.0 Roles and Responsibility………………………………………………………………………………3 4.0 Primary Equipment…………………………………………………………………………………….3 5.0 Secondary Equipment………………………………………………………………………………..14 1.0 Purpose To provide SAT requirements / limit when carrying out post commissioning test for all equipment in the plant. !" # # a. Post commissioning test is carried out after the plant is energized. 2.0 General Requirement b. All test conducted shall be documented on a proper test form. c. The details of the testing shall be referred / specified in the respective test in earlier Appendix for pre-commissioning test. d. All tests shall be carried out together with those listed in the contract document e. There are three period of Post Commissioning testing in the plant: i. Test which is conducted within 1 week – 3 months as load is connected. ii. End of Warranty test which is conducted 8 months after commissioning. iii. End of Warranty test for which is conducted 8 months and 56 months after commissioning (for primary equipment with 5 years warranty). f. On-load stability (minimum 10%) shall be conducted as load is connected for circulating current to the facilities if it is not done during commissioning. E.g. transformer using circulating of VARs, line and cable differential protection. For AVR relays, perform setting for the permissible circulating current. This test shall be conducted within 3 months after commissioning. g. On-load measurement (minimum 10%) for all relays shall be conducted as load is connected within 3 months after commissioning. h. Live maintenance facilities certification (as per Appendix U) for 275kV and above UGC and OHL shall be conducted as load (minimum 10%) is connected within 3 months after commissioning. The test report shall be endorsed by the ESE. Upon successful live maintenance certification, a sticker stating live maintenance readiness provided by Grid Development Department shall be displayed on the panel with the date of the certification. i. Physical inspection for all equipment during End of Warranty shall be conducted as per pre-commissioning list, which includes the following items: i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii. Charger Battery Banks DC Distribution Board Protection Panel Control Panel RTCC / AVR Marshalling Kiosk Digital Fault Recorder Battery Alarm Test RTU Clients (HMI, EGW) ESM & STS SCADA # !" # # 3.0 Roles and Responsibility a. For on-load test (1 week – 3 month), test shall be conducted by contractor / tester unless specified. b. For End of Warranty test, test shall be conducted by TNB (unless specified in contract) with the presence of contractor representative. Any deviation on the results, contractor shall be fully responsible. 4.0 Primary Equipment Equipment Post Commissioning 1.0 Circuit Breaker 1 week 8 Months 56 Months Contact Resistance Test √ √ As per precommissioning limits Timing test √ √ As per precommissioning limits Insulation resistance test √ √ • • Close open operation √ √ Auto-reclose operation √ √ As per precommissioning limits SF6 Pressure Operation √ √ As per precommissioning limits √ √ As per precommissioning limits SF6 Purity test √ √ SF6 > 97% SO2 content √ √ < 12ppmv CB Profiler SF6 Dew Point √ Limit No Discharge Must be consistent for all phases. • IR to be within 20% difference from precommissioning value • Based on factory routine test result/ O&M • Within recommended manufacture’s tolerance as prescribed in factory test As per precommissioning limits 2 weeks $ !" # # Equipment Post Commissioning 2.0 Gas Insulated Substation (GIS) 8 Months 56 Months Disconnectors and Circuit Breaker Contact resistance test √ √ Timing test √ √ Insulation resistance test √ √ Close open operation √ √ Auto reclose operation √ √ SF6 Pressure √ √ Partial discharge / acoustic measurement √ √ √ √ SF6 Dew Point !" # # 1 week √ Limit •Based on factory routine test result/ O&M •Within recommended manufacture’s tolerance as prescribed in factory test •Must Shall be consistent for all phases. • Based on factory routine test result/ O & M. • Within manufacture’s recommended / tolerance value as prescribed in Routine test / FAT • Pole spread shall be <5ms • To follow O&M proposed limit • No contact bouncing detected • More than 1G • Shall be consistent for all phases. Within recommended manufacture’s tolerance as prescribed in factory test Within recommended manufacture’s tolerance as prescribed in factory test Within recommended manufacture’s tolerance as prescribed in factory test Based on IEC 62271203 and IEC 60270. For PD measurement Maximum allowable Discharge 10pC measured by Conventional or UHF. For acoustic measurement, no discharge should be detected. As per precommissioning limits. Equipment Post Commissioning 1 week 8 Months 56 Months 2 weeks SF6 Purity test √ (For all compartments including Busbar compartments) √ √ 2 weeks SO2 content √ Limit As per precommissioning limits. SF6 > 97% (for 8 & 56 months) √ 2 weeks √ (For all compartments including Busbar compartments) As per precommissioning limits. < 12ppmv (for 8 & 56 months) (For all compartments including Busbar compartments) 3.0 Transformer Insulation resistance √ All values shall exceed 800MΩ Consistence between phases Polarization Index √ As per precommissioning limits Turns Ratio √ As per precommissioning limits Winding resistance (DC) √ As per precommissioning limits Excitation Current √ Verification of the fan operation, pump operation, alarm and trip settings of OTI and WTI Winding Power Factor √ As per precommissioning limits As per precommissioning limits √ Shall not increase more than 20% from pre-com value Bushing Power Factor √ Shall not increase more than 20% from pre-com value Insulation Resistance Core √ As per precommissioning limits Leakage Reactance √ As per precommissioning limits % !" # # Equipment Post Commissioning 1 week Functional Test a. Operation Check b. Transformer Guard Check Oil Test Moisture Content (ppm) 8 Months 56 Months Limit √ As per precommissioning limits √ As per precommissioning limits As per precommissioning limits As per precommissioning limits Neutralisation Value (mg KOH/g) Interfacial Tension (mN/m) Oil Colour Index √ Dielectric Breakdown Voltage (kV) Test gap 2.5mm Oil Power Factor √ √ √ As per precommissioning limits As per precommissioning limits √ As per precommissioning limits √ To follow TNB Guideline Limit √ To follow TNB Guideline Limit DGA √ Using Full Gas Extraction and Headspace Methods Furan Analysis 4.0 Earthing Transformer Insulation resistance 2 weeks √ 2 weeks √ √ All values shall exceed 800MΩ Consistence between phases As per precommissioning limits As per precommissioning limits Shall not increase more than 20% from pre-com value Polarization Index √ √ Turns Ratio √ √ √ √ Functional Test a. Transformer Guard Check Oil Test Moisture Content (ppm) √ √ As per precommissioning limits √ √ Neutralisation Value (mg KOH/g) Interfacial Tension √ √ √ √ As per precommissioning limits As per precommissioning limits As per pre- Winding Power Factor ! !" # # Equipment Post Commissioning 1 week (mN/m) Oil Colour Index 8 Months 56 Months Limit commissioning limits As per precommissioning limits √ √ √ √ √ √ As per precommissioning limits √ √ To follow TNB Guideline Limit Insulation resistance √ √ Shall not increase more than 20% from pre-com value Resistance of the NER resistor √ √ The value shall conform to the pre-com specified value (± 2%) Insulation resistance test √ √ Contact resistance for all phases √ √ IR to be within 20% difference from precommissioning value As per precommissioning limits for 8 months Dielectric Breakdown Voltage (kV) Test gap 2.5mm Oil Power Factor As per precommissioning limits DGA √ Using Full Gas Extraction and Headspace Methods 5.0 NER 6.0 Disconnector 7.0 Current Transformer 2 weeks Auxiliary contact alignment & timing test Motor MCB Protection √ √ √ √ Insulation Resistance √ √ Capacitance measurement √ √ Power Factor √ √ within 10% difference from precommissioning value for 56 months As per precommissioning limits As per MCB setting • No Discharge • Must be consistent for all phases. • IR to be within 20% difference from precommissioning value within 10% difference from precommissioning value Shall not increase more than 20% from pre-com value & !" # # Equipment Post Commissioning 8.0 Voltage Transformer 9.0 Capacitor Bank 1 week 8 Months 56 Months Insulation Resistance √ √ Capacitance measurement √ √ CVT secondary voltage measurement Power Factor √ √ √ √ √ √ √ √ √ √ √ √ Can Measurement Point of Wave Switching 10.0 Surge Arrester Leakage Current measurement (Test done by TNB) Limit • No Discharge • Must be consistent for all phases. • IR to be within 20% difference from precommissioning value within 10% difference from precommissioning value To be within 60 – 70 Volts ( 63.5 V ) Shall not increase more than 20% from pre-com value Shall not increase more than 20% from pre-com value Upon energisation transient shall be performed to verify correct operation of point of wave closing switching device. TNB will assist this test by providing the disturbance recorder and the printout. Analysis of the printout shall form part of the test report. 1 week - Values less than declared 8 months - Shall not exceed 2% from earlier value. 56 months - Shall not exceed 5% from earlier value. 11.0 Reactor (Oil Immersed Type) Insulation Resistance √ √ As per precommissioning limits Polarization Index √ √ As per precommissioning limits Winding Resistance (DC) √ √ As per precommissioning limits ' !" # # Equipment Post Commissioning 1 week 8 Months 56 Months Limit Winding Power Factor √ √ As per precommissioning limits Oil Test Moisture Content (ppm) √ √ As per precommissioning limits Neutralization Value (mg KOH/g) Interfacial Tension (mN/m) Oil Color Index √ √ √ √ √ √ As per precommissioning limits As per precommissioning limits As per precommissioning limits Dielectric Breakdown Voltage (kV) Test gap 2.5mm Oil Power Factor √ √ √ √ √ √ Insulation Resistance √ √ As per precommissioning limits Polarization Index √ √ As per precommissioning limits Winding Resistance (DC) √ √ As per precommissioning limits Insulation Power Factor √ √ As per precommissioning limits As per precommissioning limits As per precommissioning limits DGA √ Using Full Gas Extraction and Headspace Methods 12.0 Reactor (Dry Type) 13.0 Switchyard 14.0 Metal Clad Switchgear Thermal Vision Scanning and Ultrasound to be carried out above 20% rating of load but less than 3 month All physical check 2 weeks √ √ √ To follow TNB Guideline Limit Less than 10 degree c between phases and less than 40 degree with ambient As per precommissioning limits As per precommissioning limits Earthing Test √ Pressure Test √ As per precommissioning limits CB Timing Test √ As per precommissioning limits ( !" # # Equipment 15.0 Standby Generator Post Commissioning 1 week 8 Months 56 Months Limit Insulation Resistance test √ As per precommissioning limits Contact Resistance test √ As per precommissioning limits SF6 Pressure Operation √ As per precommissioning limits SF6 Dew Point √ As per precommissioning limits SF6 Purity test √ SF6 > 97% Insulation Resistance √ Shall not increase more than 20% from pre-com value Check for correct operation test √ As per precommissioning limits For Transformer with 5 years warranty:COMMISSIONING TEST POST COMMISSIONING NON-INTRUSIVE INSPECTION- (8 MNTHS AFTER COMMISSION) QUALITY & HEALTH TEST (UPON COMPLETE ERECTION) END OF WARRANTY TEST – (4 YRS 8 MNTHS) *start after commissioned OR 6 mnths after delivery date to site/store ACCEPTANCE VALUES USING MEAN VALUE OF COMMISSIONING TEST AND IN SERVICE CONDITION. Physical Inspection as per SAT Appendix J – 5.2 (b) Physical inspection: - Sign of leak Physical Inspection as per SAT Appendix J – 5.2 (b) Physical Inspection as per SAT Appendix J – 5.2 (b) Verification of the fan operation, pump operation, alarm and trip settings of OTI and WTI Factory test results/O & M. Within recommended manufacture’s tolerance as prescribed in factory test Verification of the fan operation, pump operation, alarm and trip settings of OTI and WTI *(use temporary supply) Verification of the fan operation, pump operation, alarm and trip settings of OTI and WTI Functional Test c. Operation Check d. Transformer Functional Test a. Operation Check Functional Test a. Operation Check - Corrosive parts - Moisture ingress !" # # COMMISSIONING TEST POST COMMISSIONING NON-INTRUSIVE INSPECTION- (8 MNTHS AFTER COMMISSION) QUALITY & HEALTH TEST (UPON COMPLETE ERECTION) END OF WARRANTY TEST – (4 YRS 8 MNTHS) *start after commissioned OR 6 mnths after delivery date to site/store ACCEPTANCE VALUES USING MEAN VALUE OF COMMISSIONING TEST AND IN SERVICE CONDITION. Guard Check Absolute Moisture Content in ppm (Not temperature corrected) Max 10ppm b. Transformer Guard Check **(use temp supply) Oil Test Absolute Moisture Absolute Moisture Content in ppm (Not Content in ppm (Not temperature temperature corrected) corrected) (as comm) Max 10ppm b. Transformer Guard Check Absolute Moisture Content in ppm (Not temperature corrected) Acidity (ppm) / Neutralisation Value (ppm) ≤ 0.03 Acidity (ppm) / Neutralisation Value (ppm) (as comm) Interfacial Tension (mN/m) Interfacial Tension (mN/m) <72.5kV: <17.5ppm 72.5kV-170kV: <15ppm >170kV: <12.5ppm OLTC: <25ppm Acidity (ppm) / Neutralisation Value (ppm) <72.5kV: <0.12 72.5kV-170kV: <0.07 >170kV: <0.07 Interfacial Tension (mN/m) (as comm) >30 >35 Colour Colour (as comm) ≤ 2.0 Dielectric Dissipation Factor at 90°C Dielectric Dissipation Factor at 90°C (as comm) Max 0.015 Density Test Density Test Max 0.895 g/ml Inhibitor Content Inhibitor Content Not detected Electric Strength, kV (breakdown voltage) Electric Strength, kV (breakdown voltage) Not detected Electric Strength, kV (breakdown voltage) > 60kV (as comm) (as comm) !" # # Electric Strength, kV (breakdown voltage) <72.5kV: >45kV 72.5kV-170kV: >50kV >170kV: >55kV OLTC: >45kV COMMISSIONING TEST POST COMMISSIONING NON-INTRUSIVE INSPECTION- (8 MNTHS AFTER COMMISSION) QUALITY & HEALTH TEST (UPON COMPLETE ERECTION) END OF WARRANTY TEST – (4 YRS 8 MNTHS) *start after commissioned OR 6 mnths after delivery date to site/store ACCEPTANCE VALUES USING MEAN VALUE OF COMMISSIONING TEST AND IN SERVICE CONDITION. Polybuthene oil test for cable box Polybuthene oil test for cable box (as comm) Max 60 Carbon content Carbon content Paraffinic content shall be typically below 50% for pure naphtenic base oil with positive tolerance variation of 2% is allowed DGA DGA Using Full Gas Extraction and Headspace Methods Using Full Gas Extraction and Headspace Methods **(N/A if Tx not commissioned) Furan Analysis **(N/A if Tx not commissioned) Electrical Test Winding resistance (DC) 1. Within 2% of factory measurements after insulation temp correction. 2. Within +5% between phases after correction to 75°C No break during tap changer operation. Excitation Current 1. The test value of R ph and B ph should be within 10% of each other and the Y ph should not be greater than the two other phases. 2. Single phase transformer values must be within 10% Winding resistance (DC) (as comm) Winding resistance (DC) 1. Within +5% between phases after correction to 75°C No break during tap changer operation. Excitation Current (as comm) Excitation Current (as comm) # !" # # COMMISSIONING TEST POST COMMISSIONING NON-INTRUSIVE INSPECTION- (8 MNTHS AFTER COMMISSION) QUALITY & HEALTH TEST (UPON COMPLETE ERECTION) END OF WARRANTY TEST – (4 YRS 8 MNTHS) *start after commissioned OR 6 mnths after delivery date to site/store ACCEPTANCE VALUES USING MEAN VALUE OF COMMISSIONING TEST AND IN SERVICE CONDITION. for all phases (same manufacturer) Winding Power Factor <0.5% at 20°C Bushing Power Factor For C1: 1. < 0.7%. 2. Power factor for all three phases <100% difference between phases. For C2: 1. C2 bushing power factor < 5% Capacitance change +5% from FAT result Dielectric Response on Winding (CHL) < 1.0% (% moisture content by dry weight) Oil Power Factor < 0.1% at 20°C Sweep Frequency Response Analysis (SFRA) 1. Pattern for all phases overlapping each other except yellow phase slightly lower at frequency between 100kHz to 1kHz. 2. Same pattern when compared with FAT result or sister unit. Insulation Resistance (Winding) IR at 1 minute > 1G Insulation Resistance at 20°C (Core & Frame) Core-Earth: 1G at 1 minute Core-Frame: 1G at 1 minute Frame-Earth: 1G at 1 minute Leakage Reactance The results must within Winding Power Factor (as comm) Bushing Power Factor For C1: 1. < 0.7%. 2. Power factor for all three phases <100% difference between phases. For C2: 1. C2 bushing power factor < 5% Capacitance change +5% from FAT result Dielectric Response on Winding (CHL) (as comm) Winding Power Factor <1.0% at 20°C Bushing Power Factor For C1: 1. <0.7%. 2. Power factor for all three phases <100% difference between phases. Capacitance change +7.5% from FAT result Oil Power Factor (as comm) Sweep Frequency Response Analysis (SFRA) Oil Power Factor < 0.3% at 20°C Insulation Resistance (Winding) (as comm) Insulation Resistance at 20°C (Core & Frame) (as comm) Insulation Resistance (Winding) IR at 1 minute > 500M Insulation Resistance at 20°C (Core & Frame) Core-Earth: 500M at 1 minute Core-Frame: 500M at 1 minute Frame-Earth: 500M at 1 minute Leakage Reactance (as comm) Leakage Reactance (as comm) $ !" # # COMMISSIONING TEST POST COMMISSIONING NON-INTRUSIVE INSPECTION- (8 MNTHS AFTER COMMISSION) QUALITY & HEALTH TEST (UPON COMPLETE ERECTION) END OF WARRANTY TEST – (4 YRS 8 MNTHS) *start after commissioned OR 6 mnths after delivery date to site/store ACCEPTANCE VALUES USING MEAN VALUE OF COMMISSIONING TEST AND IN SERVICE CONDITION. 3% of the nameplate values. Oil leak test The transformer shall be able to withstand a pressure of 30 kPa / 0.3 Bar from the top of conservator filled with oil for 24 hours with no oil leakage and no permanent deformation on the structure. Oil leak test For Power Cables, warranty period shall be 2 years from the date of commissioning (unless stated otherwise in the contract). EOW inspection & test to be conducted 21 months after commissioning as follows:Test No 1 5.0 Cable insulation resistance test Details Limit The test shall be conducted for the conductor using a 10 kV insulation tester. The test shall be done for every span before jointing works and to be repeated for the complete circuit. Greater than 1Gohm for cable greater than 500m length; Greater than 10Gohm for cable less than 50m length. DAR greater than 1.5. Consistent values between phases Secondary Equipment The following secondary equipment inspection and injection tests shall be performed during End Of Warranty (EOW) Test. All the CT circuit shall be verified in good and tightened condition. To perform thermographic scanning and manual checking during 1st and 5th year of EOW test to identify any loose connection. Extra care shall be given during the CT circuit checking. 5.1 Overcurrent Scheme The following testing and inspection shall be performed: a. b. c. d. e. f. g. !" Check and confirm power supply unit is healthy Check local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Measurement of CT input to relay Confirm settings and configuration Operational and timing test Built in Trip circuit supervision test if in used Confirm the operation of the tripping circuits # # h. Check for lock out operation i. Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: 5.2 SBEF Scheme a. b. c. d. e. f. g. Check and confirm power supply unit is healthy Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Confirm settings and configuration Operational and timing test Confirm the operation of the tripping circuits Check for lock out operation Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: 5.3 High Impedance Protection Scheme a. b. c. d. e. f. g. h. i. j. Check and confirm power supply unit is healthy Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Confirm settings and configuration Operational and Timing Test for all zones Test on CT Supervision Circuit Check the condition of the tripping circuits Isolator auxiliary contact in tripping circuit for all bays Transfer trip to remote end if applicable Check for lock out operation Check the tripping isolation facilities (test terminal block, group isolation link, trip link) !" % 5.4 Pilot Wire Protection Scheme # $ & The following testing and inspection shall be performed: a. b. c. d. e. f. g. h. i. j. k. l. m. Check and confirm power supply unit is healthy Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Check condition and integrity of pilot wire Measurement of CT inputs to relay Confirm settings and configuration Functional Test Pilot wire supervision End to end injection tests Inter-tripping circuit Timing test Confirm the operation of the tripping circuits Check for lock out operation Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: 5.5 Bias Differential Protection a. Check and confirm power supply unit is healthy b. Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) % !" # # Scheme c. d. e. f. g. h. i. j. k. l. m. Measurement of CT input to relay Confirm settings and configuration Functional Test Operational test Biased characteristic test Inrush Blocking Over-excitation / Over-fluxing if in used Timing test Confirm the operation of the tripping circuits Check for lock out operation Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: 5.6 Line Differential, Phase Comparison, Current Comparison Protection Scheme a. b. c. d. e. f. g. h. i. j. k. l. m. Check and confirm power supply unit is healthy Check CB and Isolator auxiliary contacts to relay Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Check Tele-protection signals Measurement of CT (Or VT if used) inputs to relay Confirm settings and configuration Functional Test Transfer or Inter-trip tripping if available Backup Distance check if used ( Refer to Distance Relays Tests) Timing test Confirm the operation of the tripping circuits Check for lock out operation Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: 5.7 Distance Protection Scheme a. b. c. d. e. f. g. Check and confirm power supply unit is healthy Check CB and Isolator auxiliary contacts to relay Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Check Tele-protection signals Measurement of CT and VT input to relay Confirm settings and configuration Functional Test i. Distance Reach check ii. Timing test iii. Power Swing Blocking operation iv. Switch On To Fault functions v. Voltage Transformer Supervision functions h. Confirm the operation of the tripping circuits i. Check for lock out operation j. Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: 5.8 AR & Synchronising Scheme a. Check and confirm power supply unit is healthy b. Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) c. Measurement of VT input to relay ! !" # # d. e. f. g. h. i. j. Confirm settings and configuration Functional Test Check CB auxiliary contacts to the relay Check CB Ready input wired to permanent positive Operation Test with actual breaker (Auto reclose relay) Check out for lock out operation. (Auto reclose relay) Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: 5.9 Breaker Failure Scheme a. Check and confirm power supply unit is healthy b. Check CB and Isolator auxiliary contacts to relay if wired a. Confirm isolator bridging and isolator invalid status condition shall send alarm after time delay (applicable to CBM of Digital Substation). c. Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) d. Measurement of CT input e. Check protection initiation to breaker failure f. Confirm settings and configuration g. Operational and timing test h. Check the condition of the tripping circuits i. Isolator auxiliary contact in tripping circuit ii. Transfer trip to remote end. i. Check for lock out operation j. Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed for Under/Over Frequency & Under/Over Voltage Scheme: 5.10 Demand/ Load Shedding Scheme a. Check and confirm power supply unit is healthy b. Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) c. Measurement of VT input to relay d. Confirm settings and configuration e. Confirm On/Off Selector switch functionality. Ensure scheme inhibited when switch switched off (DC supply to relay remain). f. Operational and timing test g. Confirm Undervoltage Blocking function h. Confirm the operation of all relevant tripping circuits i. Check for lock out operation j. Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: 5.11 Low Impedance Busbar Protection Scheme a. b. c. a. Check and confirm power supply unit is healthy Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Check CB and Isolator auxiliary contacts to relay Confirm isolator bridging and isolator invalid status condition shall send alarm after time delay (applicable to CBM of Digital Substation). d. Measurement of CT inputs from all bays e. Confirm settings and configuration f. Check the condition of the tripping circuits (negative check) g. Check the tripping isolation facilities (test terminal block, group isolation link, trip link) & !" # # The following testing and inspection shall be performed: 5.12 Unbalanced Capbank Protection Scheme a. b. c. d. e. f. g. h. i. j. Check and confirm power supply unit is healthy Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Measurement of VT input to relay Confirm settings and configuration Operational and timing test Functional test Confirm the operation of all relevant tripping circuits Check for lock out operation Check the tripping isolation facilities (test terminal block, group isolation link, trip link) Ensure the natural unbalanced current has been set and compensated by the relay The following testing and inspection shall be performed: 5.13 AVR Scheme 5.14 Pole Discrepancy Relays a. b. c. d. e. Check and confirm power supply unit is healthy Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Measurement of CT and VT input to relay Operational and timing test Check the tripping isolation facilities (test terminal block) The following functional tests shall be performed: a. b. c. d. e. f. Check and confirm power supply unit is healthy Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Operational and timing test Confirm the operation of all relevant tripping circuits Check for lock out operation Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: 5.15 Overload Capbank Protection Scheme 5.16 Under/Over Voltage a. Check and confirm power supply unit is healthy b. Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) c. Measurement of CT input to relay d. Confirm settings and configuration e. Operational and timing test f. Confirm the operation of all relevant tripping circuits g. Check for lock out operation h. Check the tripping isolation facilities (test terminal block, group isolation link, trip link) The following testing and inspection shall be performed: a. Check and confirm power supply unit is healthy ' !" # # Capbank Protection Scheme b. c. d. e. f. g. h. 5.17 Transducers & Meters The following testing and inspection shall be performed: 5.18 Bay Controller Check Local Alarms & annunciation (Fascia, SCADA, HMI, EGW/CECOMS) Measurement of VT input to relay Confirm settings and configuration Operational and timing test Confirm the operation of all relevant tripping circuits Check for lock out operation Check the tripping isolation facilities (test terminal block, group isolation link, trip link) a. Secondary Injection test b. Verify that the measurement readings at meter, HMI (Digital Substation) control center and CECOMS are consistent. c. Accuracy test (if applicable) The following testing and inspection shall be performed: a. Secondary Injection test to verify switchgear operation, interlocking function and manual synchronizing function b. Verify the measurement function and compare readings at meter, HMI (Digital Substation) control center and CECOMS are consistent. c. Ensure all the hardwiring input are intact and able to publish GOOSE to HMI and other clients 5.19 Input and Output IED The following testing and inspection shall be performed: d. Secondary Injection test for tripping function e. Verify the measurement function and compare readings at meter, HMI (Digital Substation) control center and CECOMS are consistent. f. Ensure all the hardwiring input are intact and able to publish GOOSE to HMI and other clients ( !" # # SAT Appendix T: SAT Process Flowchart 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 Overview ................................................................................................................................... 1 Stage 1 – Multicore Termination Checks and AC/DC System ................................................. 1 Stage 2 – Component Level Testing for Primary & Secondary Equipment .............................. 2 Stage 3 – CT/VT Circuit Check, Switchgear Operation Test & Control scheme Tests ............ 2 Stage 4 – Protection scheme Tests, Stability Tests and Trip Tests ......................................... 3 Stage 5 – On Load and Post Commissioning Test ................................................................... 4 PQA & Plant Energising ........................................................................................................... 4 SAT Process Flowchart ............................................................................................................ 5 The SAT process is categorized into the following five stages: 1.0 Overview i. Stage 1 – Multicore commissioning termination checks and AC/DC system ii. Stage 2 – Component level testing for primary and secondary equipments iii. Stage 3 – CT/VT circuit check, switchgear operation test and Control scheme test iv. Stage 4 – Protection scheme test, stability test and trip test v. Stage 5 – On Load test and Post commissioning test These stages shall be carried out as the above-mentioned sequence. For completeness of the commissioning process PIAT (after Stage 2) and PQA (after stage 4) will be conducted. At this stage the following activities shall be carried out: 2.0 Stage 1 – Multicore Termination Checks and AC/DC System a. Complete multi-core termination of the plant b. Complete AC distribution system commissioning c. !" Complete DC commissioning. # # charger, battery bank and DC distribution board a. At this stage all primary and secondary equipments shall be tested at the component level. 3.0 Stage 2 – Component Level Testing for Primary & Secondary Equipment b. Component level test for primary equipment, for example: i. ii. iii. iv. v. vi. vii. viii. ix. c. CB timing tests, contact resistance etc. Switchgear operation, Alignment, Torque test for CB, isolators and earth switch at local etc. Circuit resistance measurements CT SAT tests VT SAT tests Isolator auxiliary contact setting and timing test Electrical and safety clearances Power Transformer, Earthing Transformer, NER equipments Earth grid test Component level test for secondary equipment, for example: i. ii. iii. iv. v. Secondary injection test for all protection relays Secondary injection test for all instruments, transducers and meters Secondary injection test for all disturbance and fault recorders RTU local test Verification of SCS Components in working order. d. At the end of this Stage, all equipment in the plant has been proven to be in good working condition. e. Any of the primary and secondary equipment component level tests can be carried out simultaneously. With this, SAT of the component level testing completed and now the plant shall be ready for PIAT. a. At this stage, the following activities shall be completed first: 4.0 Stage 3 – CT/VT Circuit Check, Switchgear Operation Test & Control scheme Tests i. Secondary current circuit test by primary injection ii. Secondary voltage circuit test by secondary voltage injection iii. Switchgear operation test from LOCAL and REMOTE including position indication verification at REMOTE b. Followed by the control scheme test below: i. ii. iii. iv. v. c. Switchgear Interlock test Live transfer test Voltage selection test Synchronising scheme test All SCADA test except from Control Centre. Upon completion of communication facility test from both SCADA and protection. Full SCADA test from supervisory shall be performed. d. At the end of this stage all control related tests of the plant is completed and now it is ready for final protection scheme test. # !" # # At this final stage of SAT, following activities shall be completed. 5.0 Stage 4 – Protection scheme Tests, Stability Tests and Trip Tests Firstly, protection scheme test for: i. ii. iii. iv. v. vi. Auto-reclose Counter Annunciator/Alarm SCADA, SCS End to end Fault/Disturbance recorder scheme Secondly, protection trip test for all available protection schemes i.e.: i. ii. iii. iv. Busbar protection Breaker failure Feeder protection Transformer protection Third, protection stability test i.e.: i. Busbar protection stability ii. Transformer protection stability Finally, general check of the plant i.e.: i. Settings check ii. Panel Inspection iii. Final operation and trip test With this, SAT of the plant is completed and now the plant shall be ready for PQA. $ !" # # 6.0 Stage 5 – On Load and Post Commissioning Test This stage will be conducted upon energization of the plant, following activities shall be completed. a. Firstly, On Load Test which is conducted immediately upon energization as below i.e: iv. v. vi. vii. Voltage and current measurement Phasing Test Directional & Stability Test Live transfer and Synchronizing test b. Secondly, Post Commissioning Test after energization within a month period, for example viii. Thermo scanning Test ix. Leakage Current Measurement x. Insulating Oil Test – DGA c. Finally, Post Commissioning Test after 8 months of energization shall be done as End of Warranty Test, for example: xi. Component level testing xii. Component operation check Upon successful completion of PQA, the plant is ready for energisation. Upon energisation, live tests shall be carried out. 7.0 PQA & Plant Energising !" # # 8.0 SAT Process Flowchart SAT Commissioning Process Flowchart 72 ! 5 3+ )* 62 !"#$ %& 72 ! ' #( # '( + , 72 $ ! $ ( . . " 2 * ! $ . & / 0 3 4 3 4 3 4 ' #5 12 ) 72 $ 6 PIAT Result FAIL To rectify item failed % !" # # A CT, VT Control and Circuit Test STAGE 3 CT & VT Secondary circuit checks. i.e. by Primary Current and Secondary Voltage Injection Operation Test for all switchgear e.g. CB, isolator, earth switch from local and remote Completed No Yes Protection Scheme Test Control Scheme Test e.g. Interlock test, Live transfer test, voltage Selection, Synchronising Scheme, etc. STAGE 3 Protection Scheme Test e.g. A/R Test, Annunciator Test, Counter Test, Disturbance Recorder Scheme Test, End-ToEnd Communication Test, SCADA STAGE 4 Trip Test For all Protection Scheme OK YES Protection Stability Test e.g. Busbar Protection, Transformer Protection etc NO OK YES Setting Checks, Panel Inspection, Final Operation and Trip Test STAGE 4 RSV FAIL Result To rectify item failed PASS On - Load Tests after plant commissioned STAGE 5 Plant energization completed Post Commissioning Test STAGE 5 ! !" # #