Current Production Process Operation Regular Shirts Labor Content (minutes per shirts) No. of workers Minutes Per Shirts/Worker 1. Make collar 3,90 8 0.49 2. Make cuffs 2,00 4 0.50 0,65 2 0.33 4. Make front 2,50 6 0.42 5. Make back 1,70 4 0.43 0,66 2 0.33 1,65 4 0.41 1,55 4 0.39 0,65 2 0.33 1,80 4 0.45 11. Attach cuffs 1,55 4 0.39 12. Hem bottom 1,70 4 0.43 13. Inspect 1,50 4 0.38 14. Iron 1,95 4 0.49 1,75 4 0.44 3.Make sleeves 6. Join shoulders 7. Attach collar 8. Attach sleeves 9. Stitch down sleeves 10. Sew side seam 15 .Fold, package From the table it is clear that cuff making is the slowest process and hence the cycle time of the regular sized shirt making is equal to the time of cuff making= 0.5 min Actual cycle time: It is the time required to make one shirt. Total available time in a month (mins) = 20 days X 8 hours X 60 mins = 9600 mins Total number of shirt produced in a month = 16000 shirts Therefore, the actual cycle time would be= 9600 mins/16000 shirts = 0.6min/shirts Manufacturing Lead time (days) is the time clear the WIP in the given production capacity WIP Inventory (shirts) = 11760 shirts Production capacity= 800 shirts/day Manufacturing Lead time = 11760/800 = 14.7 days Work in Progress Inventory: Inventory (shirts) held up at different stage of operations Average WIP –196 batches with 60 shirts= 11760 shirt Production capacity: Is the number of shirts produced in the ideal cycle time Number of mins available in a day= 8 X 60 = 480 mins Ideal cycle time= 0.5 mins/shirt Therefore, the production capacity is = 480 mins/0.5 mins = 960 shirts Capacity utilization: Is the how much of the total capacity utilized Actual Production capacity = 800 shirts Ideal production capacity= 960 Shirts Capacity Utilization= 800/960 = 83.33% Direct labor Content: Is the time taken by all workers to complete the job Cutting time by 4 workers = 1 min/shirt Assembly time = 25.51 mins/shirt Total time = 26.51 mins/shirt