Uploaded by Ramy Ashraf

1.TS Risk Assesment

advertisement
ID
Duration
Start
Finish
Start Variance
Successors
3 days
11/17/21 8:00 AM
11/20/21 5:00 PM
0 days
4SS,11,12
1 day
11/17/21 8:00 AM
11/17/21 5:00 PM
0 days
4
Receive notice to proceed and sig
n contract
Prepare and submit project sched
ule
Obtain the approved design
1 day
11/20/21 8:00 AM
11/20/21 5:00 PM
0 days
5SS
5
Obtain preliminary shop drawings
1 day
11/20/21 8:00 AM
11/20/21 5:00 PM
0 days
8
8
Submit shop drawings and order l
ong lead items - casing
Set up site office
1 day
11/21/21 8:00 AM
11/21/21 5:00 PM
0 days
1 day
11/21/21 8:00 AM
11/21/21 5:00 PM
0 days
14
1 day
11/21/21 8:00 AM
11/21/21 5:00 PM
0 days
9
11
Submit shop drawings and order l
ong lead items - steel
Install temporary power
1 day
11/21/21 8:00 AM
11/21/21 5:00 PM
0 days
13SS
12
Install temporary water service
1 day
11/21/21 8:00 AM
11/21/21 5:00 PM
0 days
13SS
16
Mobilize machinery - set number
01
Stone site access and temporary
parking area
Set line and grade benchmarks
4 days
11/22/21 8:00 AM
11/25/21 5:00 PM
0 days
28
2 days
11/22/21 8:00 AM
11/23/21 5:00 PM
0 days
22
1 day
11/22/21 8:00 AM
11/22/21 5:00 PM
0 days
1 day
11/22/21 8:00 AM
11/22/21 5:00 PM
0 days
2 days
11/22/21 8:00 AM
11/23/21 5:00 PM
0 days
21SS
1 day
11/22/21 8:00 AM
11/22/21 5:00 PM
0 days
21SS
2 days
11/24/21 8:00 AM
11/25/21 5:00 PM
0 days
23,24
Install casing, drilling and casting
non working test
Check storm drainage, dewaterin
g and re-install and shifting
Install exterior fire line and buildin
g fire riser
Perform final site grading
24 days
11/27/21 8:00 AM
12/23/21 5:00 PM
0 days
29
2 days
11/27/21 8:00 AM
11/28/21 5:00 PM
0 days
25FF+1 day
1 day
11/27/21 8:00 AM
11/27/21 5:00 PM
0 days
25
1 day
11/29/21 8:00 AM
11/29/21 5:00 PM
0 days
26
Erect building batter boards and l
ayout building
Mobilize machinery - set number
02
Install casing, drilling, steel install
ation, pouring and cleaning
Loading working test
2 days
11/30/21 8:00 AM
12/1/21 5:00 PM
0 days
4 days
12/13/21 8:00 AM
12/16/21 5:00 PM
0 days
70 days
12/25/21 8:00 AM
3/15/22 5:00 PM
0 days
30SS+7 days
70 days
1/2/22 8:00 AM
3/23/22 5:00 PM
0 days
32,33,34,35
Mobilize machinery - set number
03
Complete all tests inspection certif
ication
Complete punch list items from
all inspections
Obtain certificate of occupancy
4 days
1/10/22 8:00 AM
1/13/22 5:00 PM
0 days
1 day
3/24/22 8:00 AM
3/24/22 5:00 PM
0 days
1 day
3/24/22 8:00 AM
3/24/22 5:00 PM
0 days
1 day
3/24/22 8:00 AM
3/24/22 5:00 PM
0 days
Issue final completion document
s including warranties
Demobilization of machinery, stu
ff and tools - Contract Closure
1 day
3/24/22 8:00 AM
3/24/22 5:00 PM
0 days
1 day
3/26/22 8:00 AM
3/26/22 5:00 PM
0 days
2
3
13
7
21
14
9
15
20
22
28
23
24
25
26
17
29
30
18
32
33
34
35
36
Risk Task Name
fabrication details - purchasing or
ders (steel - casing)
Prepare site - lay down yard, benc
h mark and safety lines
Plat form check, leveling, clearanc
e and entrance
Rough grade site (cut and fill)
36
ID
========
========
Risk Task Name
============== ==========================
============== ====
Duration
Start
Finish
Start Variance
Successors
============
============
111 days
=================
=============
11/17/21 8:00 AM
=================
=============
3/26/22 5:00 PM
=================
=============
0 days
====================
==========
Download