Uploaded by mubangizifelex05

P2 15thApril 1130 EE Mubangizi Nuwagirabyona

advertisement
DESIGN AND IMPLEMENTATION OF A
ROBUST PROTECTION SYSTEM FOR
DISTRIBUTION TRANSFORMERS
Presented by;
Mubangizi Felex (17/U/574) & Nuwagirabyona Stuart (17/U/954)
BSc. Electrical Engineering
Main supervisor: Mr. Oketch Innocent
Co-supervisor: Dr. Mugwanya Patrick
PRESENTATION SUMMARY

Introduction

Project background

Problem statement

Significance

Objectives

Methodology

Project Scope

Estimated budget

Expected results

References
INTRODUCTION
•
Distribution transformers are used to step down voltages to the
suitable values required by consumers. Distribution transformers are
classified into two that is primary and secondary distribution
transformers depending on their ratings.
•
Distribution transformers’ performance determines the overall
efficiency of the power system and they are among the most
expensive and critical units in the system.
INTRODUCTION continued…
•
There are over 12,000 distribution transformers on the
network managed by UMEME which is a Uganda’s current
local utility power company.
•
Replacing a single 50kVA distribution transformer costs the
utility company US$12,000.
PROJECT BACKGROUND
Currently, distribution transformers are being protected by use of ;

Surge arrestors and fuses for line surges.

Peak load analysis scheme to determine transformer load
conditions.

On-site oil level checking done manually by technicians

Oil Natural Air Natural for cooling.
PROBLEM STATEMENT
•
There is no remote monitoring system available to constantly monitor the
distribution transformer parameters like over current, over voltages,
temperature.
•
To evaluate effectiveness and healthiness of these protection devices and
equipment being protected.
•
Reliability of both delivered power and protection scheme is compromised.
PROBLEM STATEMENT continued….
Instead, current monitoring requires human intervention to periodically visit a distribution
transformer site which limits the detection of ;

False working of surge arresters

Overloading and load imbalance

Over heating
Other human intervention challenges include;

Delayed/Late recognition of fault

No record of the fault occurrence
Of which all these has led to reduction in transformer life span, length power outages and high
costs of maintenance and replacement incase of a fault.
SIGNIFICANCE
The mentioned challenges and consequences create a need for a
Robust protection system that;

can continuously monitors transformer parameters to assess
health of protection scheme in place and

intelligently isolates the transformer when any protection
mechanism is no longer effective.

sends notification to the utility about abnormality occurrence in the
transformer.

auto reclosing after fault clearance.
SIGNIFICANCE continued…..
Robust protection system will be of importance;
To end-users:
o
Ensures reliable power
To the utility company like UMEME:
•
•
Minimizes maintenance and replacement costs.
Eases decision-making to resize the transformer and/or redistribute
loads in phases
PROJECT OBJECTIVES
Main objective
To design and test a robust protection system for the distribution
transformer.
SPECIFIC OBJECTIVES

To study the probability of occurrence of various types of faults and
existing methods of distribution transformer protections and their
challenges.

To design and simulate circuit for robust protection system of a
distribution transformer.

To build and implement the prototype of the designed circuit.

To test and implement a fully robust protection system for the
distribution transformer.
PROJECT SCOPE

Presentation of project idea and drafting a concept paper

System Requirements Engineering

System Design and Specification

System development and implementation

Simulating and Testing the model

Report Writing and Project Presentations
METHODOLOGY
METHODOLOGY continued…
EXPECTED OUTPUT
o
Remote and user friendly monitoring system of a distribution
transformer.
o
Reliable power to consumers
o
Low maintenance costs (transport costs and labor)
o
Increase in distribution transformer life span
o
Rural electrification through savings obtained.
PROJECT TIMELINE
ESTIMATED BUDGET FOR THE
PROJECT
ITEM
QUANTITY
UNIT PRICE (UGSHs)
TOTAL(UGSHs)
Bulb
3
15,000
15,000
Arduino Board
1
100,000
100,000
Jumper wires
20
500
10,000
Bread boards
2
18000
18,000
9V Battery
1
28,000
28,000
CT Transformer
2
60,000
120,000
Relay modules
2
5000
10,000
Load sensor
1
10,000
10,000
ESTIMATED BUDGET continued…
GSM Module
1
12000
12,000
LCD Display
1
18,000
18,000
Sim Card
2
5000
10,000
Thermistor
1
5000
5,000
Current sensor
1
12,000
12,000
Rectifier
1
5000
5,000
Ultrasonic sensor
1
16,000
16,000
Transformer module
1
60,000
60,000
1
Total
UGSHs454,000/=
REFERENCES
1. A.N. A. A. F. N. Julius Businge, "UMEME POWER transforming Uganda," UMEME Web
book, p. 148, 2018.
2. E. R. A. (. Uganda, "Study on Distribution System Losses and Collection Rates by
UMEME lltd," Parsons Brinckerhoff Africa (PTY) Ltd., 2016.
3. M. A. E. Nantaba, "High costs as transformer goes up in flames," INDEPENDENT,
Kampala, 2014.
4. Y.-L. KE, "Pow-er Distribution System Switching Operation," RESEARCH GATE, vol. 01,
p. 1, 2013.
5. IEEE, "CAUSES OF DISTRIBUTION TRANSFORMERSFAILURES IN UGANDA," 2018.
[Online]. Available: https://ieeexplore.ieee.org/document/8535655. [Accessed March 2021].
REFERENCES continued…
6. D.DAS, ELECTRIC POWER SYSTEMS, West Bengal: New Age International (P)
LTD, publishers, 2006.
7. T. Patel, "Electronic Design," 26 JAN 2015. [Online]. Available:
https://www.electronicdesign.com/power-management/article/21800530/select-theright-varistors-for-overvoltage-circuit-protection. [Accessed 17 FEB 2021].
8. B. B. a. S. M. B. Jennipher A, "Monitoring and protection of Distribution
Transformer using GSM Module," International Journal of Engineering and
Techniques, vol. VOLIUME 4, no. Issue 1, p. 5, 2018.
PEOPLE CONSULTED
1. Mr. Musolo Steven
UMEME Technician at Makerere-Kavule , Bombo Road.
Tel. 0778188485
THANK YOU FOR
LISTENING
ANY QUESTION?
Download