2021-10-05 LLWTP Minutes of Design Meeting 56 Final (1)

advertisement
Minutes
Project title
Laguna Lake (Poblacion) Water Treatment Job number
264582
Plant (LLWTP - Poblacion)
Meeting name and number
Design Meeting 56
File reference
Microsoft Teams Meeting
Time and date
Location
08-01
3:00 PM –
4:10 PM
5 October 2021
Purpose of meeting
Discussion of the progress and concerns on the design activities of the
project
Present
Luth Villacarlos (LV) – Process Engineer (Maynilad)
Elmer Brent Cauton (EBC) – Process Engineer, WSO (Maynilad)
John Michael Perez (JP) – Officer, TP Maintenance (Maynilad)
Raymund Rasco (RR) – Process Engineer (Maynilad)
Javier Ruiz Gonzalez (JRG) – Project Director (AA-DMCI)
Noel Villanueva (NRV) – Project Manager (AA-DMCI)
Ana Alario Fernandez (AAF) – Process-Mechanical Lead (AA-DMCI)
Lou Bautista (LB) – MEP Head (AA-DMCI)
Francisco Gimenez Contreras (FGC) – Engineering Coordinator (AADMCI)
Miguel Sanz Gomara (MSG) – Civil Interface Engineer (AA-DMCI)
Paolo Joseph Kiocho (PK) – Design Coordinator (AA-DMCI)
John Hamilton (JDH) – Project Manager (Arup)
Angelo Landicho (AL) – Deputy Project Manager / Design Lead (Arup)
Spencer Quiachon (SQ) – Design Coordinator (Arup)
Apologies
Theresa Deyto (TBD) – Project Manager (Maynilad)
Jerahmeel Layco (JL) – Head, A&I (Maynilad)
Maria Eliza Cruz (MC) – PAD Specialist (Maynilad)
Eugene De Castro (ED) – PM Engineer (Maynilad)
Glenald Gregorio (GG) – Electrical Engineer, PMD (Maynilad)
Jemar Sing (JS) – Electrical Engineer, PMD (Maynilad)
Edison Malahito (EM) – Head, WSF (Maynilad)
Adrian Tomas Villafanez (ATF) – BIM Manager (AA-DMCI)
Elisa Segura Castellon (ESC) – Design Coordinator (AA-DMCI)
Renante Donida (RD) – Electrical Engineer (AA-DMCI)
Arceo Manila (AM) – Civil Engineer (AA-DMCI)
Circulation
Those present
+ Apologies
Prepared by
Date of circulation
Date of next meeting
Angelo Landicho / Spencer Quiachon
07 Oct 2021
12 Oct 2021
\\MANNTS02\PROJECTS\264582-00 150MLD LAGUNA LAKE WTP\08 MEETINGS\08-01 DDR MEETING\08-01-02 DRAFT\2021-10-05 DES MTG 56\2021-10-05 LLWTP MINUTES OF DESIGN
MEETING 56_FINAL.DOCX
Arup | F0.5
Page 1 of 7
Minutes
Project title
Job number
Laguna Lake (Poblacion) Water Treatment Plant (LLWTP Poblacion)
264582
Date of Meeting
5 October 2021
Action
1.
Core Design
Status of remaining documents are as follows:
•
System Architecture – under review of Maynilad
•
Equipment Lists and CFD Reports – currently endorsed to
Maynilad for conditional acceptance as these documents are
not able to meet Code 1 until completion of Developed
Design.
Discussion to be made between Maynilad and Arup for the
proposed Confirmation of Core Design.
2.
Developed Design
2.1
Submission Progress
167 out of 277 (60%) Developed Design has been submitted by
AA-DMCI as of date.
2.2
Note
Note
Note
Structural Design
AA-DMCI clarified that there has been lapses with the target date of
submissions for the revised structural design packages due to internal
checks for clashing with other design disciplines.
2.2.1
Maynilad
Note
Reviews
AA-DMCI to provide the following documents for review:
•
Intake – AA-DMCI to send the remaining sheets within
this week – Post-meeting note: submitted on 06 Oct 2021
•
BAF – AA-DMCI to send the remaining sheets within this
week – Post-meeting note: submitted on 06 Oct 2021
•
•
Diesel Storage Tank / Firefighting Water Tank – advance
review of Arup sent to AA-DMCI
DAF - TBC
•
Disc Cloth Filter / Oxidation Tank - TBC
•
Reservoir – advance copy submitted
•
Treated Water Pump Station - advance copy submitted
•
Admin Building – submission of architectural package on
8 Oct 2021, then structural package on 11 Oct 2021
Note
\\MANNTS02\PROJECTS\264582-00 150MLD LAGUNA LAKE WTP\08 MEETINGS\08-01 DDR MEETING\08-01-02 DRAFT\2021-10-05 DES MTG 56\2021-10-05 LLWTP MINUTES OF DESIGN
MEETING 56_FINAL.DOCX
Arup | F0.5
Page 2 of 7
Minutes
Project title
Job number
Laguna Lake (Poblacion) Water Treatment Plant (LLWTP Poblacion)
264582
Date of Meeting
5 October 2021
Action
Arup and AA-DMCI agreed to refrain from reviewing the advance
copies of the Reservoir and Pump Station design packages since
more than two weeks have already lapsed and the formal
submission has yet to be made.
2.2.2
IFCs
AA-DMCI to resubmit Intake IFC drawings to address the
concerns raised by Arup on the quality of the document. For close
out within the week.
2.3
Architectural
2.3.1
Admin Building Architectural Layout
AA-DMCI to consider the final architectural layout to use as basis
for the loading key plan in the preparation of the corresponding
structural design. To be submitted on 11 Oct 2021
2.4
•
Progress metrics
•
4D simulation – Intake and fence completed, and
development is on-going for the BAF. Basis of the
programme is still general and is yet to incorporate the
proposed revised programme.
•
Clash Detection Reports – recent clash detection report for
Intake submitted on 05 Oct 2021
2.5
Mechanical
2.5.1
Valves Data Sheet
AA-DMCI informed that the accreditation of the proposed vendor
(Belgicast) for the butterfly and wafer swing check valves have
been submitted to Maynilad pending its review. No updates on the
status of evaluation.
Note
AA-DMCI
Maynilad
Local Support (MC Spencer / CVN)
AA-DMCI confirmed that the nominated local support of the DAF
Air Saturator Tank is engaged to provide after sales services as long
as it is within the scope of the warranty up to DLP.
3.
AA-DMCI
BIM
AA-DMCI to submit and give updates on the following items:
2.5.2
Note
Note
HAZOP Stage 2
AA-DMCI tentatively schedules this workshop in November
2021.
Note
\\MANNTS02\PROJECTS\264582-00 150MLD LAGUNA LAKE WTP\08 MEETINGS\08-01 DDR MEETING\08-01-02 DRAFT\2021-10-05 DES MTG 56\2021-10-05 LLWTP MINUTES OF DESIGN
MEETING 56_FINAL.DOCX
Arup | F0.5
Page 3 of 7
Minutes
Project title
Job number
Laguna Lake (Poblacion) Water Treatment Plant (LLWTP Poblacion)
264582
Date of Meeting
5 October 2021
Action
Preparation of study plan to commence upon approval of System
Architecture and considering the reviews of the P&ID IFC
drawings that will be sent within the week.
4.
4.1
Note
Changes
AA-DMCI raised that several equipment with change proposals
pending for approval have already started its manufacturing and
are not advisable to cancel the orders in case of rejecting the
change proposals.
Note
As for the other change proposals pending for first submission,
AA-DMCI clarified that these are already technically agreed and
will be submitted on a later date.
Note
Contractor Changes
Six (6) change proposal that are currently considered as “live”
changes are as follows:
•
CP-C-003: UF CEB and Backwash Piping – Accepted as
Code 2 with pending review for cost reduction. AA-DMCI
to consider Pipe Arrangement submission in the cost
review.
•
CP-C-004: ATS from Solenoid to CB – Pending
discussion between Maynilad and Arup
•
CP-C-006: Change of PCP to CP for Residual Backwash
Tank – Accepted as Code 2 with requests for further
information on the cost breakdown. Arup is coordinating
with AA-DMCI and Maynilad on the possibility of
providing the cost information.
•
CP-C-007: Change in UF Inlet Analyzer – Accepted as
Code 2 but subject for cost reduction review during
developed design.
Note
•
CP-C-009: Change in Coupling type for Main Pumps –
Pending discussion between Maynilad and Arup.
Maynilad / Arup
•
CP-C-010: Change of ORP Analyzer Location and
Configuration – AA-DMCI to submit the revised
document following Maynilad’s recommendation on the
provision of the spare analyser.
•
CP-C-011: Change of Local PLC for Intake Equipment –
Accepted as Code 2 but subject for cost review during
Developed Design.
AA-DMCI
Maynilad / Arup
Maynilad / Arup
AA-DMCI
Note
\\MANNTS02\PROJECTS\264582-00 150MLD LAGUNA LAKE WTP\08 MEETINGS\08-01 DDR MEETING\08-01-02 DRAFT\2021-10-05 DES MTG 56\2021-10-05 LLWTP MINUTES OF DESIGN
MEETING 56_FINAL.DOCX
Arup | F0.5
Page 4 of 7
Minutes
Project title
Job number
Laguna Lake (Poblacion) Water Treatment Plant (LLWTP Poblacion)
264582
Date of Meeting
5 October 2021
Action
•
CP-C-013: Change in Isolation Valves – AA-DMCI to
submit its formal change proposal.
•
CP-C-014: Change in BAF Media Material – Under
review of Arup for endorsement with Maynilad. Datasheet
for proposed material is also submitted for review.
Arup
CP-C-015: Change in Check Valve from Double Flanged
to Wafer Swing Check Valve Proposal – AA-DMCI to
submit its formal change proposal.
AA-DMCI
•
4.2
4.3
AA-DMCI
Employer Changes
•
CP-C-504 (Initially sent by AA-DMCI as CP-C-0010):
Change in Head and Flow of Treated Water Pumps –
Pending discussion with Maynilad and Arup
Maynilad / Arup
•
CP-C-505: Additional Layer 2 Switches at RIO Panels –
under review of Arup for endorsement with Maynilad.
Arup
•
CP-C-506: Change in Distribution Pipe Material – AADMCI to send its formal change proposal upon receiving
the information on the cost incurred with the change. AADMCI informed that this change has been reflected in the
design documents.
AA-DMCI
Possible Changes
•
RO Rack Materials – Maynilad has previously rejected the
proposal from AA-DMCI to change the material of the
racks from SS316 to hot-dipped galvanized carbon steel.
AA-DMCI, however, has submitted a formal report
detailing the proposed change. Further discussions to be
made between Maynilad and AA-DMCI.
Note
•
Sulfuric Line – Maynilad indicated that the Consortium
may use PVDF, PFA, FRP, or Duplex SS as material for
the sulfuric line. In addition, it was also recommended to
have a single pipe material throughout the intended
pipeline. AA-DMCI to evaluate the materials for the
change proposal. In parallel, Arup will send its response to
AA-DMCI’s letter on the concern sent early this year.
AA-DMCI / Arup
\\MANNTS02\PROJECTS\264582-00 150MLD LAGUNA LAKE WTP\08 MEETINGS\08-01 DDR MEETING\08-01-02 DRAFT\2021-10-05 DES MTG 56\2021-10-05 LLWTP MINUTES OF DESIGN
MEETING 56_FINAL.DOCX
Arup | F0.5
Page 5 of 7
Minutes
Project title
Job number
Laguna Lake (Poblacion) Water Treatment Plant (LLWTP Poblacion)
264582
Date of Meeting
5 October 2021
Action
5.
Items for Interfacing with Maynilad
5.1
CCTV Layout
Pending for Maynilad security team and PMD inputs in the
preferred CCTV locations upon completion of Admin Building
Layout and process structures.
5.2
Distribution Network Information
AA-DMCI informed that the information that were sent in
response to its RFI does not allow to progress the Hydraulic
Transient Analysis. Further discussion will be made later today in
a separate meeting.
5.3
Note
LLRN Project
Further liaison shall be made with DPWH and LLRN consultants
on the concern of interfacing between LLWTP and LLRN. It is
projected that the LLRN interchange will clash with the proposed
brine line alignment.
6.
Maynilad / AADMCI
Note
Meralco Energization
The updated application was sent to Meralco on 7 Sep 2021. For
AA-DMCI follow-up.
Note
Post-meeting note: AA-DMCI has sent information on the
proposed locations of the transmission lines along Umali Street to
serve the LLWTP project. Target completion of this activity is on
Nov 2021 according to Meralco.
7.
Other Matters
7.1
Intake Levels
AA-DMCI clarified that based on its survey activities, it was
confirmed that the design levels are acceptable for use. AA-DMCI
will be sending a letter and the data collected from the survey.
7.2
AA-DMCI
Brine Line Alignment
AA-DMCI to revisit its brine line alignment to avoid clashing with
existing fish pens. AA-DMCI is already negotiating with fish pen
owners that will be affected by the brine line for acquisition.
AA-DMCI
Changing the brine line alignment will require re-application of the
Lease Agreement with LLDA.
Note
\\MANNTS02\PROJECTS\264582-00 150MLD LAGUNA LAKE WTP\08 MEETINGS\08-01 DDR MEETING\08-01-02 DRAFT\2021-10-05 DES MTG 56\2021-10-05 LLWTP MINUTES OF DESIGN
MEETING 56_FINAL.DOCX
Arup | F0.5
Page 6 of 7
Minutes
Project title
Job number
Laguna Lake (Poblacion) Water Treatment Plant (LLWTP Poblacion)
264582
Date of Meeting
5 October 2021
Action
7.3
FAT Notification and Procedure
AA-DMCI’s submission of the proposed third-party inspector is
under review of Maynilad.
AA-DMCI to consider presenting its progress and projected monthly
inspections for FAT on a weekly basis. AA-DMCI to confirm.
7.4
9.
Note
Meeting Adjournment
With no further items to discuss, the meeting was adjourned at
4:10 PM.
Note
Next meeting is scheduled on 12 Oct 2021.
Note
Meeting Recording
https://arupapcmy.sharepoint.com/:v:/g/personal/angelo_landicho_arup_com/Ed
Mo2fwOn3pBkl8p9lvY1_QBlLC86QiFSUa9zgB6ACNH1w
10.
AA-DMCI
UF Array and Skids Arrangement
Maynilad has expressed its intent on having a common discharge
valve and manifold between the UF rows of each array. To be
discussed further during commissioning stage.
8.
Maynilad
Note
Attendance
\\MANNTS02\PROJECTS\264582-00 150MLD LAGUNA LAKE WTP\08 MEETINGS\08-01 DDR MEETING\08-01-02 DRAFT\2021-10-05 DES MTG 56\2021-10-05 LLWTP MINUTES OF DESIGN
MEETING 56_FINAL.DOCX
Arup | F0.5
Page 7 of 7
Engineering Report
(Developed Design)
As of 3-Oct-21
Engineering
Developed Design – Overall (AA & DMCI)
275
Relevant documents
Technical Specifications
108
No. of
Pckgs
7
32
1
Not Submitted
Code 4
Code 3
Code 2
Code 1
Total
All Code 1
Structural Design Calculations
16
Design Drawings
83
Process Design
1
Full set PIDs Code 1
Mechanical Arrangements
14
Intake and Treated Water Reservoir– Code 2
Electrical Design
11
Generator, Transformer, Capacitor Bank , Load Flow,
Short circuit - IFA
A&I Design
9
Instru. dwgs & Det. Fieldbus network Archi. Code 3
Data Sheets – Mechanical Equip.
48
Sludge Flocculation Tower, GRP Tanks – Code 1
Sludge Thickener, Silo, BAF Process Blower – Code 2
Data Sheets – Pumps
19
Data Sheets - Valves
13
Data Sheets – Pipes & fittings
10
Data Sheets – Electrical
20
Data Sheets – A&I
15
Thermal mass Flowmeter Code 1
Other Design Package
9
CFD Raw Water Pumping Station – Code 1
78
56
Comments
Puddle Pipes Code 2
PVC Pipes, GRP, Carbon Steel IFA
Engineering
Developed Design – Civil and Structural :
Relevant documents
106
No. of
Pckgs
Comments
Technical Specifications
7
All Code 1
Structural Design Calculations
16
3 - currently under revision
Design Drawings
83
4 - currently under revision
50
38
7
11
0
Not Submitted
Code 4
Code 3
Code 2
Code 1
Total
Engineering
Developed Design – MEP :
169
58
Relevant documents
No. of
Pckgs
Process Design
1
Code 1 - Full set PIDs
Mechanical Arrangements
14
Intake and Treated Water Reservoir– Code 2
Electrical Design
11
Generator, Transformer, Capacitor Bank Calc, Load
Flow, Short circuit - IFA
A&I Design
9
Instrumentation drawings and Detailed Fieldbus
network Archi. – Code 3
45
40
25
Comments
Data Sheets – all disciplines
125
Sludge Flocculation Tower, GRP Tanks – Code 1
Sludge Thickener, Silo, BAF Process Blower – Code 2
1
Not Submitted
Code 4
Code 3
Code 2
Code 1
Total
Other Design Package
9
CFD Raw Water Pumping Station – Code 1
Engineering
Developed Design - Mechanical Arrangement :
Documents
14
10
1
0
0
Not Submitted
Code 4
Code 3
Code 2
Code 1
Total
Comments
MA UF-RO
Code 1
Rev.4
MA DAF and MA Sludge
Code 1
Approved
MA Intake
Code 2
Rev.2
Code 1
Rev.2 BAF flowmeter
Code 1
Treatment Water Flowmeter
Code 1
Rev.2 Intake Flowmeter
MA Cloth Filter
Code 1
Rev.3
MA Diesel Storage
Code 1
Rev.3
MA Treated Water Reservoir
Code 2
Rev.2
MA Electrical Building
Code 1
Rev.2
MA Transformers and
Generators
Code 3
Rev.1
MA BAF
Code 1
Rev.3
MA Chemical
Code 2
Rev.3 IFA
MA Flowmeter
3
Status
Next submission
15th Oct
15th Oct
Engineering
Developed Design - Electrical Design Packages :
11
4
4
3
0
Not Submitted
Code 4
0
Code 3
Code 2
Code 1
Total
Relevant documents
Earthing System
Status
Code 2
Comments
Rev.2 IFA
Electrical Package 1
Code 3
•
Transformer Sizing
Code 2
Rev.3 IFA
•
Generator Sizing Calculation
Code 2
Rev.3 IFA
•
UPS Sizing
Code 3
Rev.1 ongoing revision
•
Capacitor bank – Sizing calc.
Code 2
Rev.4 IFA
•
General Layout - Plan & Details
Next submission
8th Oct
28th Oct
TBS
Electrical Package 2
Code 3
•
Arc Flash
Code 3
30th Sep
•
Harmonics
Code 3
30th Sep
•
Cable tray sizing
Code 3
30th Sep
•
Voltage drop and cable sizing
Code 3
Rev.2 IFA
•
Short circuit
Code 3
Rev.2 IFA
•
Protection coordination
Code 3
7th Oct
Single Line Diagram Full set
Code 2
38 drawings
14th Oct
Electrical Load List
Code 2
Rev.5 IFA
Internal submission monthly
Cable Routing & List Schedule
Code 3
Engineering
Developed Design – Automation & Instrumentation Design Packages :
Working documents
9
Status
Comments
System Architecture
&Network Diagrams
Code 2
Belong to CD.
To close out and develop under
DD
A&I Design Criteria
Code 1
Rev.4 Approved
Hook-up drawings
Code 4
Guideline of instrumentation
Rack Arrangements
TBS
Next Submission
Hook-up
4
Code 3
Detail of instrumentation
installation
15th Oct
Functional Design Specs
Code 3
To propose internal submission
1th Nov
I/O List
Code 3
To propose internal submission
15th Oct
Instrumentation dwgs
4
Vendor information
Live documents
After DCS Approval
1
Not Submitted
Code 4
Code 3
0
0
Code 2
Code 1
Detailed Fieldbus
Network Architecture
Total
SCADA Screens
Code 3
3rd Nov
TBS
30th Nov
Engineering
Developed Design – Data Sheets :
Relevant documents
125
29
0
Not Submitted
Code 4
Code 3
Code 2
Code 1
Total
Next submission – 2 weeks
ahead
48
Air Compressor, Nozzles, Flexible
Coupling, Lamellas, Chemical,
vertical mixer
Pumps
19
Raw Water – Code 1
4 Main pumps – Code 2
9/10 Secondary pumps – Code 1
Progressive cavity pumps – Code 3
Main Pump, residual BW,
Valves
13
Butterfly valves – Code 3
Non-return valves - Code 3
Knife and gate
Pipes & Fittings
10
Puddle Pipes Code 2
PVC Pipes, GRP, Carbon Steel IFA
Carbon Steel
Electrical
20
Power Cables, Main Transformers
Generator & ATS, VFD, local
control panel, first private pole
Automation &
Instrumentation
15
Thermal Mass Flowmeter Code 1
Analysers
29
16
Comments
18 DS – Code 1
8 DS – Code 2
10 DS – Code 3
1 DS – IFA
Main Mechanical
equipment
51
No. of
Pckgs
Engineering
Other Design Packages:
Relevant documents
9
5
2
0
0
Not Submitted
Code 4
Code 3
2
Code 2
Code 1
Total
Status
Comments
•
Design Management Plan
Code 1
• Rev.4 Approved - Closed
•
BIM Execution Plan (BEP)
Code 1
• Rev.2 Approved - Closed
•
CFD raw water pumping station
Code 1
• Rev.3
•
CFD flocculation/flotation
Code 2
• Rev.2 IFA
•
CFD Oxidation Tanks
Code 3
• Only will be approved once civil design is finished
•
CFD Treated Water Reservoir
Code 3
• Only will be approved once civil design is finished
•
Tagging procedure
Code 1
• Rev.4
•
Lifting and handling plan
Code 2
• Rev.2
•
Hazop summary report
Code 1
• Rev.2 Approved (1 of 3 reports)
BIM [For Update]
ACONEX – BIM Progress / Weight:
ACONEX– BIM Progress %:
BIM [For Update]
INTERNAL – BIM Progress / Wheight:
INTERNAL– BIM Progress %:
Download