Term 3, 2021 CVEN9723 DESIGN OF CONSTRUCTION OPERATIONS Earthwork Planning Instructor: Dr X Shen Date: 14 September 2021 Dr X Shen©2021 OUTLINE • • • • • Introduction Soil Volume-Change Characteristics Earthwork Quantity Take-off Innovations in Earthmoving Construction Teaching Lab Dr X Shen©2021 2 Earthmoving Construction Dr X Shen©2021 3 (Courtesy: Glenden Australia) What’s Earthmoving? Earthmoving is the process of moving soil or rock from one location to another and processing it so that it meets construction requirements of location, elevation, density, moisture content, etc. Dr X Shen©2021 4 Typical Earthmoving Operations Haul, Loaded Return, Empty Dr X Shen©2021 5 Soil Volume-Change Characteristics Soil Conditions – Bank: natural state before disturbance • Referred to as: “in-place” or “in-situ” • Unit: bank cubic meter (BCM) – Loose: material that has been excavated or loaded • Unit: loose cubic meter (LCM) – Compacted: material after compaction • Unit: compacted cubic meter (CCM) Dr X Shen©2021 6 Soil Volume-Change Characteristics 1 BCM Bank 1.25 LCM Loose Dr X Shen©2021 7 0.9 CCM Compacted (Courtesy: Nunnally 2011) Load Factor A conversion factor to simplify the conversion of loose volume to bank volume Load factor = Weight/loose unit volume Weight/bank unit volume Dr X Shen©2021 8 Shrinkage Factor A factor used for the conversion of bank volume to compacted volume Weight/bank unit volume Shrinkage factor = Weight/compacted unit volume Dr X Shen©2021 9 Soil Volume-Change Characteristics Dr X Shen©2021 10 (Courtesy: Nunnally 2011) Earthmoving Operations Dr X Shen©2021 11 Earthmoving Estimate Cycle Time for Transporting Material – Loading Time – Traveling Time (haul, loaded) – Unloading Time – Returning Time (empty) The time required for each element should be determined for cost estimate Dr X Shen©2021 12 Earthmoving Estimate Production Rate – The number of units of work produced by a unit of equipment or a person in a specified unit of time, e.g. m3/hour Efficient Factor – A machine or a worker may work only 45 min in an hour – Actual production rate is 0.75 of maximum Dr X Shen©2021 13 Earthmoving Estimate • Production rates are crucial to estimate the time and cost of the projects • The total project time is determined by dividing the total quantity of work by the production rate • Cost of labour and equipment can be determined by multiplying the total time by the hourly rate of labour and equipment Dr X Shen©2021 14 Estimation Procedures Step 1: Quantity of Work Step 2: Cycle Time Step 3: Production Rate Step 4: Project Time Step 5: Total Cost Step 6: Unit Cost Dr X Shen©2021 15 Example 1 A total 120 m3 of clay has to be transported to a job site 15 km away using a 10 m3 dump truck. A tractor loader is used to load the truck at a rate of 80 m3/hour. The travel times for haul and return of the truck are 32 minutes and 25 minutes, respectively. It takes 3 minutes to dump the load. The cost of the truck is $ 42 /hour, the truck driver is $ 28 /hour. The cost of the loader is $ 55 /hour, the loader operator is $ 32 /hour. The average working time is 45 minutes in one hour. Determine the total time, total cost, and the cost/unit of transporting the clay. Dr X Shen©2021 16 Productivity Improvement? • How to improve the loading efficiency? • What is the difference using labour or a loader for loading? • How to match the number of the loader and the haul trucks? No. of Trucks = Total Cycle Time Load Time Dr X Shen©2021 17 Example 2 Using the data in Example 1, determine the economical number of trucks such that the load time and transport time balance. Dr X Shen©2021 18 Productivity Improvement? What if there are 2 loaders and 10 trucks? How to estimate the project cost? Dr X Shen©2021 19 (Courtesy: CYCLONE Simulation) Earthwork Quantity Take-off Dr X Shen©2021 20 (Courtesy: Donaldson Garrett) Earthwork Quantity Take-off • When planning or estimating an earthmoving project, it is often necessary to estimate the volume of material to be excavated or placed (Cut vs. Fill) • Quantity take-off is a detailed measurement of earthwork volume to complete a construction project Dr X Shen©2021 21 Earthwork Quantity Take-off • Contractors are paid for the volume of excavation • Earthwork can be roughly estimated by counting the number of truckloads Dr X Shen©2021 22 (Courtesy: CAT) Pit Excavations Small, relatively deep excavations Volume = Horizontal area × Average depth Dr X Shen©2021 23 (Courtesy: FictionU) Pit Excavations Calculation – Step 1: Divide the horizontal area into a convenient set of rectangles, triangles, or circular segments – Step 2: Determine the total area as the sum of the segment areas – Step 3: Calculate the average depth Dr X Shen©2021 24 Example 3 Estimate the volume of excavation required for the basement. Values shown at each corner are depths of excavation. Dr X Shen©2021 25 (Courtesy: Nunnally 2011) Trench Excavations Usually constructed for utility lines Volume = Cross-sectional area × Length Dr X Shen©2021 26 (Courtesy: Joyceroad) Example 4 Find the volume of excavation required for a trench 0.92 m wide, 1.83 m deep, and 152 m long. Assume that the trench sides will be approximately vertical. Dr X Shen©2021 27 (Courtesy: ecmweb) Large Areas Dividing the area into a grid indicating the depth of excavation or fill at each grid intersection Dr X Shen©2021 28 (Courtesy: wplinternational) Large Areas Dr X Shen©2021 29 (Courtesy: CAT) Large Areas Average Depth – Assign the depth at each corner or segment intersection a weight according to its location • Interior points: Weight of four • Exterior points at the intersection of two segments: Weight of two • Corner point: Weight of one Dr X Shen©2021 30 Large Areas Average Depth = Sum of products of depth × Weight Sum of weight Dr X Shen©2021 31 Example 5 Dr X Shen©2021 32 Mass Diagram Dr X Shen©2021 33 (Courtesy: ugpti.org) Mass Diagram • A continuous curve representing the accumulated volume of earthwork plotted against the linear profile of a roadway or airfield • Prepared by highway and airfield designers Dr X Shen©2021 34 Mass Diagram • Used to assist in selecting an alignment which minimizes the earthwork required to construct the facility while meeting established limits of roadway grade and curvature • Very useful for construction manager Dr X Shen©2021 35 Example 6 Dr X Shen©2021 36 (Courtesy: Nunnally 2011) Dr X Shen©2021 37 (Courtesy: Nunnally 2011) Innovations in Earthmoving Komatsu - Autonomous Haulage System Dr X Shen©2021 38 (Courtesy: aerometrex) Aerial Innovation Dr X Shen©2021 39 (Courtesy: THIESS) UAV Resources at UNSW Multirotor UAVs DJI Phantom 3 Professional Vulcan Heavy Lift Octocopter • • • • • • • • Weight: 1.28 Kg Sensor: 12MP Camera Flight time: 20 min No. of Propellers: 4 Dr X Shen©2021 40 Weight: 14 Kg Sensors: LiDAR/Infrared Cam Flight time: 1 Hour No. of Propellers: 8 UAV Resources at UNSW Fixed Wing UAVs SenseFly eBee RTK SenseFly swinglet CAM • • • • • • • • Weight: 0.73 kg Sensor: 12MP RGB & NIR Cams Flight time: 40 min Wingspan: 0.96 m Dr X Shen©2021 41 Weight: 0.5 kg Sensors: 12 MP Camera Flight time: 30 min Wingspan: 0.8 m Case Study – Narrabeen Beach, NSW Home waypoint Flight path of UAV Orthomosaic of site Dr X Shen©2021 42 (Courtesy: Max Stannard 2014) Point Cloud input into AutoCAD Civil 3D Dr X Shen©2021 43 (Courtesy: Max Stannard 2014) TIN volume surface 1m x 1m grid volume surface 10m x 10m grid volume surface Cut - Purple Fill - Orange Dr X Shen©2021 44 (Courtesy: Max Stannard 2014) Station = 200 (1,4) Cut Fill Net (1,3) Cut Fill Net (1,2) Cut Fill Net (1,1) Cut Fill Net (2,4) -339.03 Cut 3377.87 Fill 3038.84 Net (2,3) -369.58 Cut 6150.42 Fill 5780.84 Net (2,2) -767.39 Cut 2571.26 Fill 1803.87 Net (2,1) -16886.4 Cut 0 Fill -16886.4 Net (3,4) -80.1 Cut 9110.38 Fill 9030.28 Net (3,3) -0.3 Cut 8612.65 Fill 8612.35 Net (3,2) -4340.94 Cut 1405.93 Fill -2935.01 Net (3,1) -12902.5 Cut 0 Fill -12902.5 Net (4,4) 0 Cut 7323.39 Fill 7323.39 Net (4,3) -3925.35 Cut 2952.51 Fill -972.84 Net (4,2) -12883.9 Cut 0 Fill -12883.9 Net (4,1) -5207.85 Cut 290.47 Fill -4917.38 Net (5,4) -1483.51 Cut 4078.89 Fill 2595.38 Net (5,3) -10798 Cut 4.7 Fill -10793.3 Net (5,2) -2737.64 Cut 680.51 Fill -2057.13 Net (5,1) -8.68 Cut 4463.59 Fill 4454.91 Net -805.97 2998.13 2192.16 -489.57 2881.72 2392.15 -0.14 6717.91 6717.77 Earthwork Planning Cut - Purple Fill - Orange -0.29 10447.92 10447.63 Station = 0 Alignment Dr X Shen©2021 45 (Courtesy: Max Stannard 2014) Questions? Dr X Shen©2021 46