Uploaded by b s rao

Summer preparation status of Unit 1,2,3

advertisement
Summer preparation status of Unit #1,2&3
1. Unit 1,2,3 cable galleries MVW spray erection not complete
2. Fire water hydrant and sprinkler pumps start panel as well as auto
start erection not complete
3. Diesel fire water hydrant & sprinkler system including start panel
incomplete
4. Fire water booster pump start panel incomplete
5. FDPS alarm panel not erected
6. LDO Pressurizing pump house,unloading pump house,LDO tanks
sprinkler system erection incomplete
7. LDO tanks fire quenching Foam system erection not complete
8. Main plant control room fire fighting system not erected
9. Drinking water supply system at various locations of unit as well as
BOP locations like LDO pump house,CW pump house,Fire water pump
house,Compressor house not erected
10. HVAC System not erected for control rooms,programmer rooms CER
rooms & charger rooms
11. Air washer system not erected
12. Unit -3 TG roof ventilation fans erection incomplete
13. Unit-2&3 Boiler above 30m elevation,Fire hydrant system erection
incomplete
14. PM Checks of all tower AC located at various locations of unit to be
done
Download