Summer preparation status of Unit #1,2&3 1. Unit 1,2,3 cable galleries MVW spray erection not complete 2. Fire water hydrant and sprinkler pumps start panel as well as auto start erection not complete 3. Diesel fire water hydrant & sprinkler system including start panel incomplete 4. Fire water booster pump start panel incomplete 5. FDPS alarm panel not erected 6. LDO Pressurizing pump house,unloading pump house,LDO tanks sprinkler system erection incomplete 7. LDO tanks fire quenching Foam system erection not complete 8. Main plant control room fire fighting system not erected 9. Drinking water supply system at various locations of unit as well as BOP locations like LDO pump house,CW pump house,Fire water pump house,Compressor house not erected 10. HVAC System not erected for control rooms,programmer rooms CER rooms & charger rooms 11. Air washer system not erected 12. Unit -3 TG roof ventilation fans erection incomplete 13. Unit-2&3 Boiler above 30m elevation,Fire hydrant system erection incomplete 14. PM Checks of all tower AC located at various locations of unit to be done