ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) (V1.0) ZTE CORPORATION Confidential and Proprietary Information of ZTE CORPORATION. ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Planned by: UMTS Customer Service Dept., Mobile Product Support Center Complied by: Tang Jia-bin Reviewed by: * * Li Chun-he * Zhu Biao * ZTE CORPORATION Address: ZTE Plaza, #889 Bibo Road, Zhangjiang Hi-tech Park, Shanghai, P. R. China Post code: 201203 Technical support website: http://tsm.zte.com.cn Hotline: +86 755 26770800 800-830-1118 Fax: +86 755 26770801 Confidential and Proprietary Information of ZTE CORPORATION. ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Legal Information All rights reserved. No part of this documentation may be excerpted, reproduced, translated, annotated or duplicated, in any form or by any means without the prior written permission of ZTE Corporation. and are the registered trade marks of ZTE Corporation. The names and logos of ZTE products are proprietary logos or registered trade marks. The names of other products and companies mentioned in this manual may be proprietary to their owners respectively. Without the prior written permission of ZTE or the owners of third-party trade marks or trade names, this manual does not grant the reader any permission or right to use any marker appeared in the manual. The product described herein conforms to the design requirements of environment protection and human security. The storage, usage, and discard of the product shall comply with the manual, related contract, or laws and regulations of related countries. The actual product may differ from what is described in this standard due to frequent update of ZTE products and fast development of technologies. Please contact the local ZTE office for the latest updating information of the product. For the latest document information, please visit our website: http://tsm.zte.com.cn Confidential and Proprietary Information of ZTE CORPORATION. ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Feedback Table You are invited to give your suggestions and opinions to improve ZTE user manuals and enjoy better service by sending emails to ydshyf@zte.com.cn. Thank you for your cooperation! Document Name ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Product Version No. V4.0 Document Version No. V1.0 Please provide your information for further contact: Name Company Post Code Address Tel E-mail Very Good General View Preparation flow Environment requirements Auxiliary equipment Comments Working interface Work instruction Convenient to consult Correct content Complete content Straightforward expression Confidential and Proprietary Information of ZTE CORPORATION. Good Ordinary Bad Very Bad ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 You may give suggestions from any perspective such as the content, structure, details, depth, expression, figures/tables, special tools, FAQ and so on. The suggestions are not confined to this document. Suggestions Confidential and Proprietary Information of ZTE CORPORATION. ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Revision Records Document Version No. V1.0 Prepared/Revised by Prepared/Revised on Tang Jia-bin 2009-08-10 Total Pages Reason for Revision None Contents of Revision (Key Points Only) None Note 1: This table must be completed before updating the archived document (the document archived in the archival room of the division or the Company). Note 2: Fill "None" in "Reason for Revision" and "Contents of Revision" when archiving this document for the first time. Confidential and Proprietary Information of ZTE CORPORATION. ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Preface Manual Description This manual details the main procedure and precautions for the ZXSDR B8200&R8840 (V4.0) NodeB installation (BBU indoors & RRU indoors) according to the installation flow on the site. Application Scope This manual is applicable to the onsite engineering installation personnel and the personnel from the local offices and the customer service department. Abstract In the form of rich texts and abundant figures, this manual introduces the typical installation mode and installation procedures (installing B8200 indoors and R8840 indoors) of ZXSDR B8200&R8840 NodeB (V4.0), the cable connection and distribution requirements for both the equipment and auxiliary equipment. It describes the main installation procedure, precautions, key points as well as the installation tools and materials so as to improve installation efficiency and reduce mistakes. It aims to provide reliable instruction for the onsite working personnel. Confidential and Proprietary Information of ZTE CORPORATION. ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Contents Chapter 1 Installation Tools .......................................................................................................................................................1 1.1 Special Tools ............................................................................................................................................................2 1.2 Punching Tools .........................................................................................................................................................2 1.3 Common Tools .........................................................................................................................................................3 1.4 Measurers ................................................................................................................................................................3 1.5 Pliers and Clamps ....................................................................................................................................................4 1.6 Protective Tools ........................................................................................................................................................5 1.7 Auxiliary Tools...........................................................................................................................................................5 Chapter 2 Introduction to B8200&R8840 NodeB......................................................................................................................6 2.1 B8200.......................................................................................................................................................................7 2.2 R8840.......................................................................................................................................................................8 2.3 Simple Installation Bracket .......................................................................................................................................9 2.4 19-Inch Standing Installation Rack .........................................................................................................................10 2.5 RRU Standing Installation Rack .............................................................................................................................11 2.6 BC8180 Cabinet .....................................................................................................................................................12 Chapter 3 Auxiliary Engineering Materials .............................................................................................................................13 Confidential and Proprietary Information of ZTE CORPORATION. i ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 4 B8200&R8840 Engineering Installation Flow ........................................................................................................19 Chapter 5 Installation Preparation...........................................................................................................................................21 Chapter 6 Installing B8200 Indoors .........................................................................................................................................28 Chapter 7 Installing R8840 Indoors & Antennas ....................................................................................................................37 Chapter 8 Cable Connection for Indoor Equipment...............................................................................................................41 Chapter 9 Making Cable Connectors and Labeling ...............................................................................................................66 Confidential and Proprietary Information of ZTE CORPORATION. ii ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 1 Installation Tools Confidential and Proprietary Information of ZTE CORPORATION. 1 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 1.1 Special Tools Feeder connector cutter Coaxial cable wire stripper Multifunction crimping pliers VSWR gauge Ground resistivity gauge Optical multimeter Drill bit Dust cleaner Multimeter 1.2 Punching Tools Electric impact drill Confidential and Proprietary Information of ZTE CORPORATION. Wiring board 2 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 1.3 Common Tools Cross screwdriver Slotted screwdriver Adjustable wrench Electric iron Soldering tin thread Rubber hammer 5m steel tape Level ruler Two-use wrench 1.4 Measurers 50m tape measure Confidential and Proprietary Information of ZTE CORPORATION. Goniometer 3 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Compass Plumb 1.5 Pliers and Clamps Hacksaw Sharp nose pliers Diagonal pliers Pincer pliers Multi-use files Nippers Paint brush Scissors Confidential and Proprietary Information of ZTE CORPORATION. 4 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Heat gun Solder removal tool Hydraulic pliers Safety helmet Anti-slip gloves Ropes Ladder Crowbar 1.6 Protective Tools Antistatic bracelet 1.7 Auxiliary Tools Pulley block Confidential and Proprietary Information of ZTE CORPORATION. 5 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 2 Introduction to B8200&R8840 NodeB Confidential and Proprietary Information of ZTE CORPORATION. 6 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 2.1 B8200 B8200 dimension: 482.6mm×197mm×88.4mm (W×D×H), not more than 8.75kg in full configuration Confidential and Proprietary Information of ZTE CORPORATION. 7 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 2.2 R8840 R8840 dimension: 320mm×160mm×370mm (W×D×H), 16.5kg R8840 supports both the -48V DC power supply and the 220V AC power supply. And its nominal transmission power is 40W/60W. Confidential and Proprietary Information of ZTE CORPORATION. 8 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 2.3 Simple Installation Bracket Dimension of simple installation bracket: 530mm×235mm×200mm (W×D×H) Confidential and Proprietary Information of ZTE CORPORATION. 9 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 2.4 19-Inch Standing Installation Rack Dimension of 19-inch standing installation rack: 520mm×385mm×1600mm (W×D×H) Confidential and Proprietary Information of ZTE CORPORATION. 10 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 2.5 RRU Standing Installation Rack Dimension of RRU standing installation rack: 550mm×100mm×1600mm (W×D×H) Confidential and Proprietary Information of ZTE CORPORATION. 11 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 2.6 BC8180 Cabinet Dimension of BC8180 cabinet: 400mm×600mm×300mm (H×W×D) Confidential and Proprietary Information of ZTE CORPORATION. 12 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 3 Auxiliary Engineering Materials Confidential and Proprietary Information of ZTE CORPORATION. 13 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Name yellow-green fire-resistance multi-strand cable copper lugs and different colors of heat-shrink sleeves Description yellow-green PGND cable power cables and PGND cables shall use the copper lugs and heat-shrink sleeves to make terminals black DC power cable BS8800 DC power cable copper ground bar copper ground bar (used indoor or outdoor) Confidential and Proprietary Information of ZTE CORPORATION. Figure 14 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Name Description white ties to bind indoor cables waterproof insulating tape to make waterproof measures for connectors PVC insulating tape/black to make waterproof measures for connectors black nylon fastening tape to bind indoor tail fibers antistatic bracelet antistatic bracelet Confidential and Proprietary Information of ZTE CORPORATION. Figure 15 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Name input/output dry contact node cable Description Figure 6-way input and 2-way output, and one end is DB25 connector 75ohm E1 cable 4-way or 8-way 75ohm mini-coaxial E1 cable 120ohm E1 cable 4-way or 8-way 120ohm mini-coaxial E1 cable 1-to-4 SA cable, which contains a E1 cable, a dry SA cable contact node cable, an RS232/485 cable and a ground cable 2-core outdoor woven shielded power cable (with meter marks on it) Confidential and Proprietary Information of ZTE CORPORATION. to connect DC ILP and OLP 16 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Name Description R8840 rack-top jumper (2m, 3m, 5m) 1/2-inch rack top jumper (2 for each sector) R8840 special monitoring cable To monitor R8840 OLP status ground clip of outdoor cable ground clip of outdoor cable R8840 special DC power cable R8840 special AC power cable Confidential and Proprietary Information of ZTE CORPORATION. Figure DC power cable from OLP to R8840 (containing 4 cores - 2 blue and 2 black) AC power cable from R8840 to OLP (containing 3 cores – 1 brown, 1 blue and 1 black) 17 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Name 75ohm E1 terminal Confidential and Proprietary Information of ZTE CORPORATION. Description Figure 75ohm E1 terminal 18 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 4 B8200&R8840 Engineering Installation Flow Confidential and Proprietary Information of ZTE CORPORATION. 19 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Confidential and Proprietary Information of ZTE CORPORATION. 20 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 5 Installation Preparation Confidential and Proprietary Information of ZTE CORPORATION. 21 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 5.1 Installation Preparation Installation Figures 5.1.1 Site Environment Check Installation Steps 1 Check the site location, power supply system, site transmission, lightning protective ground, etc. according to the project design documents. 2 3 4 5 6 Key Points and Precautions 1 2 Installation Tools Installation Materials 3 1 2 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 22 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 5.2 Unpacking and Inspection 5.2.1 Goods Check Installation Steps Installation Figures 1 Check the total number of the goods and the condition of the packing boxes. Check if the arrival location is consistent with the actual installation location (see Figure 1). 2 Open the packing box and take out Equipment Inspection Checklist and Unpacking and Inspection Report to check if the goods are consistent with Equipment Inspection Checklist (see Figure 2). 3 4 Figure 1 Figure 2 5 6 Key Points and Precautions Installation Tools pen 1 Equipment Inspection Checklist and Unpacking Inspection Report should be archived. 2 If the goods are missed/delayed/broken, the goods quantity is incorrect, or wrong goods are delivered, find out the reason. And the project supervisor should fill in Unpack and Inspection Feedback Table and send it to ZTE Corporation ASAP for timely handling. Installation Materials 1 2 3 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 23 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 5.2 Unpacking and Inspection Installation Steps Installation Figures Figure 1 5.2.2 Unpacking Wooden Boxes Figure 2 1 Insert a slotted screwdriver or a claw hammer into the metal locker of the top cover. (see Figure 1). 2 Turn the screwdriver or hammer to loosen the sheet iron (see Figure 2). 3 Use a crowbar or pliers to remove the sheet iron. 4 Repeat Step 1 to 3 to remove other sheet irons and open the top cover (see Figure 3) 5 Take out the equipment from the wooden box. 6 Key Points and Precautions 1 It is prohibited to wear damp or dirty gloves to touch the equipment or parts. 2 Figure 3 Installation Tools slotted screwdriver claw hammer 1 screwdriver 2 pliers Installation Materials 3 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 24 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 5.2 Unpacking and Inspection Installation Steps Installation Figures Figure 1 5.2.3 Unpacking Cartons Figure 2 1 Cut the tape along the seam of the carton with a paper knife or other tools. Please note do not cut too deep into the carton (see Figure 1). 2 Open the carton and take out the foam boards. 3 Check the goods according to the enclosed goods-delivery list inside the carton. 4 Take out the antistatic packing bag from the carton, open it and take out the electronic equipment or parts (see Figure 2). 5 6 Key Points and Precautions 1 It is required to make antistatic measures before taking out the electronic equipment and parts. 2 paper knife Installation Tools screwdriver Installation Materials 3 1 2 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 25 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 5.2 Unpacking and Inspection Installation Figures 5.2.4 Inspection and Handover Installation Steps 1 Carefully check the goods according to the goods names, models, quantity, etc. listed in Packing List. Record the goods one by one. 2 After the inspection, the user and the project supervisor must jointly sign Unpacking and Inspection Report. The goods should be handed over to the user. Both parties should keep a copy of the signed Unpacking and Inspection Report. 3 4 5 6 Key Points and Precautions 1 2 Installation Tools pen Installation Materials Within seven days after the inspection, the project supervisor should feed back the Inspection Conclusion in Unpacking and Inspection Report to ZTE Corporation for archive. Decide the goods handover mode according to the actual conditions on the site. 3 1 2 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 26 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 5.3 Preparation before Installation Installation Figures 5.3.1 Preparation of Tools Installation Steps 1 Prepare the installation tools for the installation of the indoor part of NodeB. 2 Prepare the installation tools and protective tools for the installation of the outdoor part of NodeB. 3 4 5 6 Key Points and Precautions 1 For the construction personnel working on high buildings, it is required to check if the protective tools (such as the safety belt, safety helmet and anti-slip gloves) are reliable to ensure personal safety. 2 Installation Tools Installation Materials 3 1 2 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 27 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 6 Installing B8200 Indoors Confidential and Proprietary Information of ZTE CORPORATION. 28 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 6.1 Using the Existing 19-Inch Standing Installation Rack Installation Figures Figure 1 Figure 2 6.1.1 Installing B8200 Installation Steps 1 Check if the existing 19-inch installation rack meets the installation requirements (in view of space and heat radiation). 2 Insert the fixing nut into the installation hole of the idle 5U slot in the rack for the installation of B8200 and cable trough (see Figure 1). 3 Mount the cable trough to the 1U space near the fixing nut. And fix it securely with a screwdriver (see Figure 2 and Figure 3). 4 Install B8200 above the cable trough in the same way as stated in Step 1 and 2 (see Figure 4). 5 Check if B8200 has been installed firmly. It should not shake in the rack. 6 Key Points and Precautions Figure 3 Installation Tools cross screwdriver 1 2 1 Figure 4 Installation Materials auxiliary fixing screws The existing 19-inch installation rack should meet the installation requirements on space: a). at least 5U or more of installation space is available; b. 1U of space should be reserved at the top, 2U in the middle is for B8200, and 1U lower is for the cable trough, and the bottom 1U is for cabling. Note: 1U=1.75 inch=44.45mm B8200 radiating requirements: At least 40mm of space should be reserved at the two flank sides of the ventilation and radiation intake/outtake after the B8200 is installed (the air flow in B8200 is from right to left). There shall be no radiation outtakes of other equipment to the right of the B8200. If there is, the equipment should not be installed at the same horizontal level of the B8200. 2 B8200 equipment 3 3 1U cable trough Confidential and Proprietary Information of ZTE CORPORATION. 29 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 6.2 Installing B8200 to the Wall with a Simple Installation Bracket Installation Figures Installation Steps 1 Determine the installation position of the simple installation bracket. Mark out the punching positions on the wall according to the template or the bracket (see Figure 1). 2 Punching: (see Figure 2) a). Punch in the marked positions with an electric impact drill (drill bit with a diameter of 10mm); b). The depth of the holes is between 50mm and 60mm. Install expansion bolts: a.) Knock the expansion bolt into the hole and make the expansion tube enter the ground completely. b. Screw down the bolt with an adjustable wrench; c. Remove the nut, spring washer and flat washer from the bolt. They will be used to install the simple installation bracket. And let the insulating pad go through the bolts, with the pad holes matching the ground holes. Let the simple installation bracket go through the bolts and rectify the location of the bracket. Place the insulating flange, flat washer and spring washer into the bolt in sequence, and screw down the nuts with a wrench in a diagonal manner (see Figure 3 and Figure 4). Check if the simple installation bracket is fixed firmly. It shall not shake when pushed with hands. 3 Figure 1 Figure 2 6.2.1 Installing Simple Installation Bracket 4 5 Key Points and Precautions Figure 3 1 Keep the drill bit perpendicular to the wall and remove the dust with a dust cleaner during punching. 2 The insulating flange must go through the simple installation bracket and insulating pad until it touches the wall. 3 Requirements for the location of the simple installation bracket: The bracket should have at least 400mm of maintenance space, and at least 100mm of space at the flank sides to facilitate cabling and heat radiation. 4 B8200 heat radiating requirements: Figure 4 Installation Tools marker pen electric impact drill 1 dust cleaner drill bit 2 rubber hammer adjustable wrench Installation Materials simple installation bracket auxiliary installation parts (holing template, expansion bolt components, insulating pad) B8200 should have at least 40mm of space at the flank sides for ventilation and heat radiation (the air flow in B8200 is from right to left). Confidential and Proprietary Information of ZTE CORPORATION. 30 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 6.2 Installing B8200 to the Wall with a Simple Installation Bracket Installation Figures 6.2.2 Installing B8200 (in a Simple Installation Bracket) Installation Steps 1 Install the cable trough in the 1U space at the bottom of the simple installation bracket. Insert the cable trough and tighten the screws with a screwdriver (see Figure 1 and Figure 2). 2 Install B8200 above the cable trough in the same way as Step 1 (see Figure 3 and Figure 4). 3 4 Figure 1 Figure 2 5 6 Key Points and Precautions 1 Figure 3 Installation Tools cross screwdriver There are all together 4U of space in the simple installation bracket. The 2U in the middle is for B8200, the top 1U is kept idle temporarily or installed with GPS components (if AC power supply is adopted, AC/DC power switching unit PSU can be installed here), and the bottom 1U is for the cable trough. Figure 4 2 1 Installation Materials auxiliary fixing screws 2 B8200 equipment 3 3 1U cable trough Confidential and Proprietary Information of ZTE CORPORATION. 31 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 6.3 Installing B8200 With a 19-Inch Standing Installation Rack Installation Figures Installation Steps 1 2 Figure 1 6.3.1 Installing 19-Inch Standing Installation Rack Assemble the 19-inch standing installation rack in the vacant space on the site, fix the beam and upright column at the top by using four nuts (see Figure 1), assemble the pedestal and upright columns at two sides, and tighten the eight nuts by hands (see Figure 1). Determine the installation location of the 19-inch standing installation rack, and draw the locations for the holes of the assembled pedestal (see Figure 2) 3 Punching: a). Punch in the marked positions with an electric impact drill (drill bit with a diameter of 10mm); b). The depth of the holes is between 50mm and 60mm. 4 Install expansion bolts: a.) Knock the expansion bolt into the hole and make the expansion tube enter the ground completely. b. Screw down the bolt with an adjustable wrench; c. Remove the nut, spring washer and flat washer from the bolt. They will be used to install the simple installation bracket (see Figure 3). 5 Let the installation rack go through the bolts and rectify the location of the rack. Place the flat washers and spring washers into the bolts in sequence, and screw down the nuts with a wrench in a diagonal manner (see Figure 4). Figure 2 Key Points and Precautions Figure 3 Installation Tools marker pen electric impact drill 1 dust cleaner drill bit 2 rubber hammer adjustable wrench 1 The requirements for the installation location are as follows: The installation rack should stay at least 400mm away from the front row of devices, the upright columns should stay at least 400mm away from the rear wall or rear row of racks, and there should be a space of at least 100mm at both sides. Figure 4 2 Installation Materials 19-inch standing installation rack It is recommended that the B8200 should be installed at the position of the 19-inch installation rack 1 m above the ground. 3 auxiliary installation parts (holing template, expansion bolt components) When drilling holes, you should keep the drill bit perpendicular to the ground and clear the dust with the dust cleaner or other tools. 4 Check whether the 19-inch standing installation rack is fixed securely, and ensure that the installation rack cannot be wobbled by hands. 5 For details on how to install the B8200, see 6.1 Using the Existing 19-Inch Standing Installation Rack. 3 Confidential and Proprietary Information of ZTE CORPORATION. 32 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 6.4 Installing B8200 With a Hang-to-Wall BC8180 Cabinet Installation Steps Installation Figures Figure 1 6.4.1 Installing B8200 With a Hang-to-wall BC8180 Cabinet Figure 2 1 Decide the installation position for the BC8180 cabinet which is to be hanged to the wall. And mark out the punching positions on the wall for the installation rack. 2 Punch and install expansion bolts. See Step 2 and Step 3 in 6.2.1 Installing Simple Installation Bracket. 3 Let the insulating pad go through the bolts, and then let the BC8180 installation rack go through the bolts. Place the flat washers and spring washers into the bolts in sequence, adjust the BC8180 installation rack and screw down the nuts in a diagonal manner. 4 Hold the BC8180 cabinet, let its back hook fit in the installation rack to hang it to the rack (see Figure 1), and then tighten the screws at the two side in the BC8180 cabinet (see Figure 2). The BC8180 cabinet has been installed with the 1U cable trough before it leaves the factory. 2U above the cable trough is reserved for the B8200, whose installation steps are similar to 6.2.2 Installing B8200 (in a Simple Installation Bracket) (see Figure 3). 5 6 If the AC power supply is adopted, an AC/DC PSU should be installed in the IU under the cable trough. Other idle slots can be filled by blank filler panels. Tighten all screws with a screwdriver (see Figure 3). Key Points and Precautions Figure 3 1 If the equipment room is too small, The B8200 can adopt in this installation mode and be installed to the wall near the corridor or stair. However, it shall not be installed outdoors. 2 Requirements for the installation position of the BC8180 cabinet: The cabinet should stay at least 400mm away from the front row of devices to facilitate maintenance, and there should be a space of at least 100mm at both sides. Check whether the BC8180 cabinet is fixed securely, and ensure that the BC8180 cabinet cannot be wobbled by hands. Figure 4 Installation Tools electric impact drill marker pen Installation Materials BC8180 installation rack 3 1 dust cleaner drill bit 2 auxiliary installation parts 4 rubber hammer adjustable wrench 3 BC8180 cabinet cable trough) B8200 cross screwdriver 4 Confidential and Proprietary Information of ZTE CORPORATION. (including the To guard against theft, it is required to lock the cabinet door after the equipment is installed and hand it over to the operator. 33 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 6.5 Installing B8200 With an RRU Standing Installation Rack Installation Figures Figure 1 Figure 2 6.5.1 Installing RRU Standing Installation Rack Installation Steps 1 Assemble the RRU standing installation rack, then fix the standing support to the RRU installation rack base, and tighten the six auxiliary nuts at both sides with an adjustable wrench (see Figure 1 and Figure 2). 2 Decide the installation position for the 19-inch standing installation rack. Mark out the punching positions according to the assembled base (see Figure 3). 3 Punch and install expansion bolts. See Step 3 and Step 4 in 6.3.1 Installing 19-Inch Standing Installation Rack. 4 Let the RRU standing installation rack go through the bolts, place the flat washers and spring washers into the bolts in sequence, rectify the RRU standing installation rack, and screw down the nuts in a diagonal manner (see Figure 4). 5 6 Key Points and Precautions 1 2 Figure 3 Figure 4 Installation Tools electric impact drill marker pen 1 dust cleaner drill bit 2 rubber hammer adjustable wrench 3 cross screwdriver Requirements for the installation position of the RRU standing installation rack: The cabinet should stay at least 800mm away from the front row of devices to facilitate maintenance, the standing support should stay at least 800mm from the rear wall or rear row of racks, and there should be a space of at least 100mm at both sides. When drilling holes, you should keep the drill bit perpendicular to the ground and clear the dust with the dust cleaner or other tools. Installation Materials components of RRU standing installation rack auxiliary installation parts 3 Check whether the RRU standing installation rack is fixed securely, and ensure that the installation rack cannot be wobbled by hands. 4 4 Confidential and Proprietary Information of ZTE CORPORATION. 34 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 6.5 Installing B8200 With an RRU Standing Installation Rack Installation Figures Installation Steps 1 2 3 4 Figure 1 Figure 2 6.5.2 Installing B8200 (With an RRU Standing Installation Rack) To install a B8200 to the RRU standing installation rack, a simple installation bracket is required. After the RRU standing installed rack is assembled, decide the position of the simple installation bracket. Usually, the position is 400mm above the base (see Figure 1). Let the insulating flanges, simple installation bracket, insulating pads, RRU standing installation rack, spring washers, flat washers and fastening nuts go through the auxiliary nuts in sequence, and screw down the nuts with a wrench in a diagonal manner (see Figure 2). Install the cable trough in the 1U space at the bottom of the simple installation rack – carefully insert the cable trough and tighten the screws with a screwdriver (see Figure 3). Install the B8200 above the cable trough. The installation method is similar to Step 3 (see Figure 4). 5 6 Key Points and Precautions 1 Check whether the simple installation rack is fixed securely, and ensure that the installation rack cannot be wobbled by hands. 2 Figure 3 Installation Tools two adjustable cross screwdriver wrenches Figure 4 Installation Materials simple installation bracket 3 1 2 auxiliary installation parts 4 3 B8200 4 1U cable trough Confidential and Proprietary Information of ZTE CORPORATION. 35 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 6.6 Installing Power Distribution Box to the Wall Installation Figures Figure 1 Figure 2 6.6.1 Installing AC/DC Power Distribution Box to the Wall Installation Steps 1 Decide the installation position of the AC/DC power distribution box, and mark out the punching position according to the box (see Figure 1). 2 Punch and install expansion bolts. See Step 2 and Step 3 in 6.2.1 Installing Simple Installation Bracket (see Figure 2). 3 Hold the AC/DC power distribution box, insert the bolts into the holes in the wall and tighten the screws with a screwdriver in a diagonal manner (see Figure 3). 4 Check whether the AC/DC power distribution box is fixed securely, and ensure that the AC/DC power distribution box cannot be wobbled by hands. 5 6 Key Points and Precautions 1 2 Figure 3 Installation Tools marker pen electric impact drill Installation Materials DC power distribution box 3 1 hammer 2 AC power distribution box (optional) 4 3 auxiliary installation parts cross screwdriver 4 Confidential and Proprietary Information of ZTE CORPORATION. 36 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 7 Installing R8840 Indoors & Antennas Confidential and Proprietary Information of ZTE CORPORATION. 37 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 7.1 Installing R8840 Installation Steps Installation Figures Figure 1 7.1.1 Installing R8840 to the Wall Indoors Figure 2 1 Determine the installation location of the hang-to-wall installation rack, and mark out the punching positions with the holing template (see Figure 1). 2 For details on how to drill holes and install the expansion bolts, see Step 2 and 3 in 6.2.1 Installing Simple Installation Bracket. 3 Let the hang-to-wall installation rack go through the bolts, place the insulating flange, flat washer, and spring washer, rectify the location of the hang-to-wall installation rack, and tighten the nuts in a diagonal manner (see Figure 2). 4 Hold R8840, clip the fixing beam at its back to the pallet of the hang-to-wall installation rack, and tighten the four inner-hexagon cheese-head screws at both sides to fix R8840 to the hang-to-wall installation rack tightly (see Figure 3 and Figure 4). Check whether R8840 is fixed securely, and ensure that R8840 cannot be wobbled by your hands. 5 Key Points and Precautions Figure 3 Installation Tools marker pen electric impact drill 1 The interfaces of R8840 and OLP should face downwards, and there should be a space of at least 300mm under them to facilitate cabling. 2 The insulating flange should go through the hang-to-wall installation rack and insulating pad until its front end touches the wall so as to ensure that the equipment is insulated from the wall. Figure 4 1 dust cleaner drill bit 2 rubber hammer adjustable wrench 3 4 Installation Materials hang-to-wall installation rack auxiliary installation parts (holing template, expansion bolt components, insulating pad) R8840 equipment Confidential and Proprietary Information of ZTE CORPORATION. 3 Requirements for the R8840 installation position: There should be a space of at least 300mm above R8840 to facilitate heat radiation. In the space 300mm below R8840, there should be no barriers that hamper the outgoing cables or connection of cables. 38 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item Installation Steps 7.1 Installing R8840 Installation Figures Figure 1 7.1.2 Installing R8840 with an RRU Standing Installation Rack Figure 2 1 To install one R8840 to the RRU standing installation rack, a set of general installation components is required. One R8840 should be equipped with one set of general installation components. 2 After the RRU standing installed rack is assembled, decide the position of the general installation components (see Figure 1). The typical configuration is 3 RRUs and 1 BBU installed to 1 RRU standing installation rack. 3 Let the bolts go through spring washers, flat washers, insulating flanges, general installation components, insulating pads in sequence (see Figure 2). 4 Use two adjustable wrenches to securely fix the front screw and the rear one to the RRU standing installation rack (see Figure 3). 5 Hold the R8840, let its back hook fit in the general installation components to hang it to the rack, and then tighten the four inner-hexagon cheese-head screws at the two side to fix R8840 to the general installation components tightly (see Figure 4). 6 Key Points and Precautions 1 2 Figure 3 Installation Tools two adjustable inner-hexagonal wrenches wrench Before the installation, it is required to decide the installation positions and number of respective equipment in the RRU standing installation rack, to avoid subsequent problems during the installation. The R8840 port should face downward and at least 300mm of space should be reserved under the port. Figure 4 Installation Materials R8840 3 1 2 general installation components 4 3 auxiliary installation parts 4 Confidential and Proprietary Information of ZTE CORPORATION. 39 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 7.2 Antenna Installation and Cable Connection Installation Figures Figure 1 Figure 2 7.2.1 Antenna Installation and Cable Connection Installation Steps 1 All the antennas must be installed securely. They shall not move and should meet the wind-resisting requirements. The poles installed at the rooftop must be grounded and located within the lightning-protective range. 2 The antenna port is at one end of the antenna. There are two red protective caps on the jumper connectors. The lowest port is the electrically regulated port (see Figure 1). 3 Carefully hold the antenna, fix the installation rack to the pole, put the flat washers, spring washers and nuts in sequence and finally slightly screw the nuts with hands (see Figure). 4 Adjust the antenna installation position, horizontal angle and vertical angle, and tighten the nuts (see Figure 4). 5 The azimuth error of the directional antenna should be within ±5°. And the pitching error of the directional should be within ±0.5°. And the single-polarized antennas in the same sector should have consistent pitching angle and azimuth angle. 6 Key Points and Precautions 1 2 The antenna should be within the protective range of the lightning rod, which means that the lightning rod should be higher than the antenna. Protective angle: not more than 45° in the plain and not more than 30° in high mountains and thunder-dense areas. To ensure safety, safety measures should be taken before the antennas are installed. Figure 3 Installation Tools wrench 1 Installation Materials antennas 2 auxiliary fixing screws 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 3 If the antenna is installed to the iron tower, it is required to lift it to the tower top: a) Bind the upper side and the lower side of the antenna installation rack respectively with two ropes. b) To prevent the antenna from hitting the tower body, during the lift, one person should take one of the ropes and lift the antenna upward; another person should take anther rope to adjust the rack. c) Because working on the tower top is very dangerous, it is recommended to use the crown block to lift the antenna. 40 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 8 Cable Connection for Indoor Equipment Confidential and Proprietary Information of ZTE CORPORATION. 41 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures Figure 1 Figure 2 8.1.1 Connecting & Distributing DC Power Cable Installation Steps 1 For the simple installation bracket, 19-inch standing installation rack or RRU standing installation rack, insert the connector of the special power cable into the PM module and screw down the screws (see Figure 1). 2 Connect the other end of the power cable to the indoor DC power supply cabinet or power distribution box. Connect the blue strand to the -48V terminal and the black one to the -48V GND terminal (see Figure 2). 3 Lay the power cable (the power cable can be bundled with the PGND cables) as follows: a). Bind the power cable along the left side of the simple installation bracket toward the wall, and lead the power cable to the cable tray vertically along the PVC cable trough (see Figure 3). b). Lay the power cable vertically along the left side of the 19-inch standing installation rack or RRU standing installation rack, and bind the power cable once at an interval of 100mm (see Figure 4). 4 Key Points and Precautions 1 The B8200 special power cable is a 3-strand black cable. It contains one blue strand and one black strand (2×2.5mm2) as well as an idle strand that has insulating pretreatment. 2 Figure 3 Installation Tools cross screwdriver diagonal pliers 1 adjustable wrench 2 Figure 4 Installation Materials B8200 special power cable, containing one blue and one black strands (2×2.5mm2) white ties Confidential and Proprietary Information of ZTE CORPORATION. 3 4 42 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures 8.1.2 Connecting & Distributing DC Power Cable (for BC8180) Installation Steps 1 2 3 For the BC8180 cabinet, first move the sliding gaskets at the left and the right sides at the cabinet bottom with a cross screwdriver to extend the aperture and make the cable connectors smoothly enter the cabinet. After all cables are distributed, move the gaskets to the original places (see Figure 1). Lead the special power cable into the cabinet from the cabinet bottom, and insert one end of the cable into the PM module and tighten the screw (see Figure 2 and 3). Distribute the special power cable along the left side of the cabinet and bind it with the ties in the cabinet (see Figure 4). 4 Figure 1 Figure 2 5 6 Key Points and Precautions 1 2 Figure 3 Installation Tools cross screwdriver diagonal pliers 3 1 Figure 4 Installation Materials white ties 2 B8200 special power cable 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 43 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures Installation Steps 1 If the BC8180 cabinet adopts the AC power supply, it is required to install a power switching unit (PSU). 2 Both ends of the B8200 special power cable have a special connector. Connect one end to B8200 and the other end to PSU DC power port (at the left side of the module), lay the cable along the left side of the cabinet, and bind the cable with ties in the cabinet (see Figure 1). Lead the AC power cable into the cabinet through the hole at the left side of the cabinet, connect the cable to the PSU AC power port (3-core), lay it along the cabinet bottom, and bind it with ties in the cabinet (see Figure 2). 3 4 Figure 1 Figure 2 8.1.3 Connecting & Distributing AC Power Cable (for BC8180) One end of the input/output dry-contact-node cable is a DB9 connector. Connect the DB9 connector to the monitor port at the PSU right side, and connect another end of the cable to the dry-contact-node port of the SA cables for the B8200. Lay the cable along the cabinet bottom and bind it neatly (see Figure 3 and 4). 5 6 Key Points and Precautions Figure 3 Installation Tools cross screwdriver diagonal pliers Figure 4 Installation Materials 1 PSU 2 Auxiliary AC/DC power cable and monitoring cable white ties 3 Confidential and Proprietary Information of ZTE CORPORATION. 1 Before connecting the AC power cable, switch OFF the PSU switch. 2 The input/output dry-contact-node cable is a customized cable. One end of the cable is a DB9 connector and the other end is SB25 connector. 3 4 44 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures Installation Steps 1 2 3 Figure 1 8.1.4 Connecting & Distributing PGND Cable Make the PGND cable terminals on the site. For details, see 9.1.1 Making DC Power Cable & PGND Cable Terminals. For the simple installation bracket, the 16mm2 yellow-green PGND cables are used. Connect the copper lug of the PGND cable to the ground terminal of the simple installation bracket, and the other end to the terminal of the indoor copper ground bar (see Figure 1). For the simple installation bracket, the connected PGND cable can be laid along the PVC cable trough to the cable tray together with the DC power cable (see Figure 2). 4 The 19-inch standing installation rack and RRU standing installation rack have no GND terminal. It is required to connect the copper lug of the PGND cable to the ground terminal at the right side of B8200, connect the other end to the terminal of the indoor copper ground bar, and tighten them with a cross screwdriver (see Figure 3). 5 For the 19-inch standing installation rack and RRU standing installation rack, the PGND cable can be laid at the interior side of the left upright column together with the DC power cable. After bundling the cables respectively, lead the PGND cable to the cable tray (see Figure 4). Figure 2 Key Points and Precautions Figure 3 Installation Tools cross screwdriver diagonal pliers adjustable wrench 1 Figure 4 Installation Materials 16mm2 yellow-green PGND cable 2 white ties 1 Because the simple installation bracket has a ground point, there is no need to add another PGND cable. 2 Because the 19-inch standing installation rack and RRU standing installation rack have 2 no ground terminal, the 16mm yellow-green cable can serve as the B8200 PGND cable by connecting the B8200 to the indoor ground bar. Otherwise, the ground bus bar can be installed at the flank side of the installation rack, and in this case the engineer should lead the B8200 PGND cable to the grounding terminal of the ground bus bar and connect the ground bus bar with the indoor ground point. 3 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 45 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures Figure 1 Figure 2 8.1.5 Connecting & Distributing PGND Cable (for BC8180) Installation Steps 1 Make the PGND cable terminals on the site. For details, see 9.1.1 Making DC Power Cable & PGND Cable Terminals. 2 For the BC8180 cabinet, a short PGND cable is delivered with the cabinet. Connect the copper lug of the PGND cable to the ground point at the left side of the B8200, and tighten the screw with a cross screwdriver (see Figure 1). 3 The BC8180 cabinet contains a built-in ground bar. Connect the other end of the short PGND cable to one terminal of the built-in ground bar in the cabinet. Also tighten the screw with a cross screwdriver (see Figure 2). 4 The ground terminal of the BC8180 cabinet is at the left side of the cabinet bottom. Remove the nut and washer from the ground point with an adjustable wrench (see Figure 3). Add the washer, 16mm2 yellow-green PGND cable, and nut in sequence to the ground point, and screw down the nut with an adjustable wrench (see Figure 4). 5 6 Key Points and Precautions 1 2 Figure 3 Installation Tools cross screwdriver adjustable wrench 1 Figure 4 Installation Materials 16mm2 yellow-green PGND cable 2 3 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 46 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures Installation Steps 1 Connect the SCSI50 connector of the SA cable to the SA panel, and tighten the fixing screws with a screwdriver (see Figure 1). 2 Connect the short ground cable of the SA cable to the B8200 ground terminal, and tighten the screw with a cross screwdriver (see Figure 2). 3 The other end of the SA cable provides three connectors (E1, RS232, and dry-contact-node connectors). Hide the SA cables and the three connectors in the cable trough below B8200, bundle the cables and lead them rightward, and distribute the cables along the right side. Figure 3 shows how to distribute the SA cable on the simple installation bracket and RRU standing installation rack. Figure 4 shows how to distribute the SA cable on the 19-inch standing installation rack. 4 Figure 1 Figure 2 8.1.6 Connecting & Distributing SA Cable 5 Key Points and Precautions 1 The E1 connector of the SA cable should be connected to the E1 cable. Decide whether to connect the dry-contact-node and RS232 connectors according to the onsite demands. 2 Figure 3 Installation Tools cross screwdriver diagonal pliers Figure 4 Installation Materials 1 white ties 2 SA cables 3 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 47 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures 8.1.7 Connecting & Distributing SA Cable (for BC8180) Installation Steps 1 Connect the SCSI50 connector of the SA cable to the SA panel, and tighten the fixing screws with a screwdriver (see Figure 1). 2 Connect the short ground cable of the SA cable to one ground terminal in the BC8180 cabinet, and tighten the screw with a cross screwdriver (see Figure 2). 3 The other end of the SA cable provides three connectors (E1, RS232, and dry-contact-node connectors). Neatly arrange the SA cable and three connectors, and lead the cable along the left side to the cabinet bottom (see Figure 3). 4 Figure 1 Figure 2 5 6 Key Points and Precautions 1 2 Figure 3 Installation Tools cross screwdriver Installation Materials 1 3 SA cables 2 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 48 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures Figure 1 Figure 2 8.1.8 Connecting & Distributing E1/RS232 Cables Installation Steps 1 According to the labeling condition of the E1 cables, find the E1 cables of Pair 1 to 4 at the other end to match the SA E1 cable (see Figure 1). 2 The connectors of the 75ohm E1 cable must be made on the site and connected to the DDF. Refer to 9.1.2 Making 75ohm E1 Cable Connectors to learn how to make the connectors. The 120ohm E1 cable should be connected to DDF through a wire clamp. 3 Connect the E1 cable and RS232 cable respectively to corresponding connectors of the SA cable (see Figure 2). 4 For the simple installation bracket, all the cables and fibers are laid along the PVC trough on the wall, and then led downward from the right side of the simple installation bracket and through the cable trough at the bracket bottom. After the FE cable and outdoor fibers are connected, bundle the SA cables together with them at the right side (see Figure 3). For the 19-inch standing installation rack and RRU standing installation rack, all the cables and fibers are laid from the interior side of the right-upright column and led to the cable trough at the B8200 bottom. After the FE cable and outdoor fiber are connected, bundled the SA cables together with them (see Figure 4). 5 Key Points and Precautions Figure 3 Installation Tools diagonal pliers cross screwdriver 1 E1 cables fall into 2 categories: 75ohm and 120ohm. Usually the 8-pair 75ohm E1 cable is used in China. One end of the cable is a DB44 connector while the other one divides into 2 cables (each cable has 8 cores [Core 1 to 8] and each cable supports 4 pairs of E1 links). 2 1 Figure 4 Installation Materials white ties 2 E1 cable (75/120ohm) 3 3 RS232, dry contact node cables 120ohm E1 cables also fall into 2 categories: 4-pair and 8-pair. One end is the DB44 connector while the other end is one 4-pair cable or two 4-pair E1 cables. Each 4-pair cable has 8 cores (Core 1 to 8) and supports 4 pairs of E1 links. The connector at the DDF side is connected through a wire clamp. If the B8200 and R8840 both adopt the indoor installation, decide whether to use the input/output dry-contact-node cable and RS232 cable according to the actual conditions. 4 cables Confidential and Proprietary Information of ZTE CORPORATION. 49 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures Installation Steps 1 2 3 4 Figure 1 Figure 2 8.1.9 Connecting & Distributing Outdoor Optical Fibers 5 6 If the optical interface of the FS module is not fitted with an optical module, install an optical module. Note that the blue handle should face upwards. Insert the optical module tightly. Make temporary labels at both ends of the outdoor fiber according to the optical module directions and sectors, and connect the outdoor fiber to the TX and RX interface of the FS module. Please note that you should insert the fiber in the direction of the optical module. After connecting the fiber correctly, you can hear a “KA” sound (see Figure 1). Reserve an enough bending radius when the outdoor fiber is laid to the cable trough (see Figure 2). For the simple installation bracket, all the cables and fibers are laid along the PVC trough on the wall, led downward from the right side of the simple installation bracket and through the cable trough at the bracket bottom. After other cables are connected, bundle the outdoor fiber together with them (see Figure 3). For the 19-inch standing installation rack and RRU standing installation rack, all the cables and fibers are laid from the interior side of the right-upright column and led to the cable trough at the B8200 bottom. After other cables are connected, bundle the outdoor fiber together with them (see Figure 4). When the outdoor fiber is laid indoors, the outdoor fiber should be long enough for cabling in the cable trough. Do not place heavy objects or other heavy cables on the outdoor fiber. The redundant outdoor fiber should be coiled and placed neatly under R8840 or nearby. Key Points and Precautions Figure 3 Installation Tools 1 Figure 4 Installation Materials outdoor optical fibers, whose length depends on the survey result 1 Before the FS board is delivered, the required optical modules usually have been built in. 2 After the equipment is powered on, do not look into the optical module to protect your eyes from being damaged. 3 Connect the outdoor fibers to B8200 correctly according to the correspondence between the outdoor fibers and sectors. For example, the outdoor fiber of the first sector is connected to TX0 and RX0 (at the right side of the FS board) of the first port on the FS panel, and the others follow the same rule. 4 The other end of the outdoor fiber should be connected to the LC1 interface of the R8840. 2 3 Confidential and Proprietary Information of ZTE CORPORATION. 50 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures Installation Steps 1 The RJ45 connectors of the FE cable should be made on the site. For details, refer to 9.1.4 Making RJ45 Connector of the FE Cable. 2 Connect one end of the FE cable to the eth0 RJ45 port on the CC panel and the other end to the optical terminal equipment (see Figure 1). 3 For the simple installation bracket, the FE cable is laid along the PVC trough on the wall, led downward from the right side of the simple installation bracket and through the cable trough at the bracket bottom. And then bundle it together with the E1/RS232/dry-contact-node cables and outdoor fibers, and the interval should be 100mm (see Figure 2). Figure 3 shows the general cabling layout of the simple installation bracket. 4 Figure 1 Figure 2 8.1.10 Connecting & Distributing FE Cable 5 6 For the 19-inch standing installation rack, the FE cable is laid from the interior side of the right-upright column and led to the cable trough at the B8200 bottom. And then bundle it together with the E1/RS232/dry-contact-node cables and outdoor fibers, and the interval should be 100mm (see Figure 4). For the RRU standing installation rack, the FE cable is laid along the right-upright column and led to the cable trough at the bottom of the simple installation bracket. And then bundle it together with other cables, and the interval should be 100mm. Key Points and Precautions 1 2 Figure 3 Installation Tools diagonal pliers 1 2 Figure 4 Installation Materials Category-5 unshielded Ethernet cable white ties 3 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 51 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Steps Installation Figures Figure 1 8.1.11 Connecting & Distributing BC8180 Transmission Cable Figure 2 1 For the BC8180 cabinet, the E1 cable, FE cable and outdoor optical fibers all enter the cabinet through the cable hole at the right side of the cabinet bottom (see Figure 1). 2 Connect the E1 cable to the E1 port of the SA cable, and lay them at the bottom of the cabinet (see Figure 2). 3 Connect the FE cable to the eth0 RJ45 port on the CC panel and the outdoor optical fibers to corresponding optical ports on the FS board. 4 Lay the FE cable and the outdoor optical fiber along the right side of the cabinet, and bundle them with the ties in the cabinet (see Figure 3). 5 Lead the cables at both the left and the right side of the BC8180 cabinet along the cabinet bottom to the wall, and then lay them along the PVC cable trough at both sides to the indoor cable tray. 6 Figure 4 shows the general layout of an installed BC8180 cabinet. Key Points and Precautions 1 Connect the outdoor fibers to B8200 correctly according to the correspondence between the outdoor fibers and sectors. For example, the outdoor fiber of the first sector is connected to TX0 and RX0 (at the right side of the FS board) of the first port on the FS panel, and the others follow the same rule. 2 Figure 3 Installation Tools cross screwdriver diagonal pliers 1 2 Figure 4 Installation Materials E1 cables 3 Category-5 unshielded cable outdoor optical fibers 4 white ties Confidential and Proprietary Information of ZTE CORPORATION. 3 Ethernet 4 52 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.1 Cable Connection at the B8200 Side Installation Figures 8.1.12 Connecting Antistatic Bracelet Installation Steps 1 Insert the antistatic bracelet into the hole in the middle-right part of B8200 (see Figure 1). 2 Fix the antistatic nipper to the installation rack (or post) at the right side (see Figure 2). 3 For the BC8180 cabinet, place the antistatic bracelet at the right side of the cabinet (see Figure 3). 4 Figure 1 Figure 2 5 6 Key Points and Precautions 1 2 Figure 3 Installation Tools Installation Materials 3 1 2 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 53 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.2 Connection & Distribution of Cables for Power Distribution Box 8.2.1 Connecting & Distributing Cables for DC Power Distribution Box Installation Steps 2 Installation Figures Figure 1 Figure 2 1 Remove 8~10mm of the cable sheath from one end of the 16mm blue DC power cable with a wire stripper or knife. And make the same operation on the 16mm2 black DC power cable and the PGND cable (see Figure 1). 2 Insert the naked core wires of the PGND cable into a hole of the ground bar at the left of the DC power distribution box, and tighten the wires with a cross screwdriver (see Figure 2). 3 Lead the blue and black DC power cables into the box respectively through the cable holes at the top of the DC power distribution box (see Figure 3). 4 Connect the blue and black power cables to the corresponding input ends of the DC power distribution box, and then tighten them with a cross screwdriver (see Figure 4). 5 The PGND and power cables shall all be laid along the PVC troughs on the wall and led into the cable tray. Besides, the PGND cable and the power cables shall be laid separately in the cable tray and they shall not be bundled with other cables. 6 Key Points and Precautions Figure 3 Installation Tools wire stripper knife 1 cross screwdriver 2 1 During the cable connection, first connect the PGND cable and then other cable. During the disconnection, the PGND cable should be the last one to be disconnected. 2 Before the PGND cable is connected, arrange its core wires neatly to make sure all the wires are close to each other. It is prohibited to expose any core wire in the air after the core wires are inserted into the wiring hole. The power cable between the DC power distribution box and the DC power cabinet should be either a blue power cable plus a black power cable or 2-core unshielded cable. Figure 4 Installation Materials 16mm2 yellow-green PGND cable 3 16mm2 blue and black DC power cables 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 54 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.2 Connection & Distribution of Cables for Power Distribution Box Installation Figures Installation Steps 1 Remove 8~10mm of the cable sheath from one end of the AC power cable (containing a brown cable, a blue cable and a black cable) with a wire stripper or knife. 2 Lead the AC power cable into the power distribution box through the cable hole at the top of the power distribution box, connect the brown cable, blue cable and black cable respectively to corresponding input ends of the power distribution box, and tighten the screw with a cross screwdriver (see Figure 1). Similar to Step 2, connect the RRU AC power cables to the output ends of the power distribution box. During the connection, conform to the connection in Figure 2 and pay attention to the port L, N, and GND. 3 4 Figure 1 Figure 2 8.2.2 Connecting & Distributing Cables for AC Power Distribution Box For the AC power distribution box, insert the PGND (black) cable of the AC power cable to a hole of the ground bar at the left side of the box, and tighten the screw with a cross screwdriver (see Figure 3). 5 Key Points and Precautions 1 The core wires of the AC power cable should all be arranged neatly before they are inserted to the cable holes. It is prohibited to expose any core wire in the air. 2 Installation Tools Installation Materials wire stripper knife 1 cross screwdriver Heat gun 2 3 AC power cable (containing a brown cable, a blue cable and a black cable) 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 55 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.3 Connecting the Cables at the R8840 Side 8.3.1 Connecting the DC Power Cable Installation Steps Installation Figures 1 If DC power supply is used for the R8840, four special 1.5mm2 DC power cables are used (including two blue power cables and two black power cables) (see Figure 1). 2 Connect the special interface of the special power cables to the PWR interface at the bottom of the R8840 (Note: The red marking point should be targeted at the mark of the PWR interface), and then tighten the connector (see Figure 2). 3 Respectively strip 8~10mm of cable sheaths from the two blue power cables and two black power cables at the other end with a wire stripper or knife (see Figure 3). 4 Connect the other end to the power output end of the DC power distribution box (connect the two blue power cables to the 48V terminal, and connect the two Figure 1 black power cables to the 48V GND terminal), fix the power cables tightly by using Figure 2 the clip in the box, and tighten the fastening screw at the power output end with a cross screwdriver (see Figure 4). Key Points and Precautions 1 2 Figure 3 Figure 4 Installation Tools Installation Materials wire stripper knife cross screwdriver diagonal pliers 1 3 R8840 special DC power cable, whose specification is 4×1.5mm 2 2 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 56 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.3 Connecting the Cables at the R8840 Side Installation Figures 8.3.2 Connecting the AC Power Cable Installation Steps 2 If AC power supply is used for the R8840, three special 1mm AC power 1 cables are used (the brown cable is the live wire (L), the blue cable is the null wire (N), and the black cable is the GND cable) (see Figure 1). 2 Connect the special interface end of the special AC power cables to the PWR interface at the bottom of the R8840 (Note: The red marking point should be targeted at the mark of the PWR interface), and then tighten the connector 3 At the other end, strip the 8~10mm of sheaths from the three cables with a wire stripper or knife. Handle the outdoor AC power cable in the same way. Figure 1 Figure 2 4 Connect the other end to the power output end of the AC power distribution box (connect the brown power cable to the L terminal, connect the blue power cable to the N terminal, and connect the black power cable to the GND terminal), fix the power cables tightly with the clip in the power distribution box, and tighten the fastening screw at the power output end with a cross screwdriver (see Figure 2). Key Points and Precautions 1 You need to apply waterproof treatment to all interfaces of the R8840. For details, see the content on waterproof treatment for equipment interfaces. Installation Tools wire stripper knife Installation Materials 1 R8840 special AC power cable, whose specification is 3×1.0mm cross diagonal pliers 2 2 You need to cut off the redundant alarm cables. 2 screwdriver Confidential and Proprietary Information of ZTE CORPORATION. 57 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.3 Connecting the Cables at the R8840 Side Installation Figures 8.3.3 Connecting the Rack-Top Jumper (A) Installation Steps 1 The R8840 is configured with two ports, which are connected to each other through the rack-top jumper (see Figure 1). 2 Plug the N-type feeder connector of one feeder cable to the RF cable interface of the transmit/receive diversity (RX/TX) in the lower part of the R8840, and tighten the feeder connector by using the wrench (see Figure 2). 3 Plug the N-type feeder connector of another feeder cable to the RF cable interface of the receive diversity (TX) in the lower part of the R8840, and tighten the feeder connector by using the wrench (see Figure 3). 4 Figure 1 (to be continued in next page) Figure 2 Key Points and Precautions 1 (See next page) 2 Figure 3 Installation Tools (See next page) 1 Installation Materials (See next page) 2 3 Confidential and Proprietary Information of ZTE CORPORATION. 3 58 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.3 Connecting the Cables at the R8840 Side Installation Figures Figure 1 4 8.3.3 Connecting the Rack-Top Jumper (B) Installation Steps R8840 feeder grounding principles: a) If the feeder is shorter than 5m, it does not need grounding. b) If the feeder is longer than 5m but shorter than 10m, it is required to ground at one point, and the ground point is at the antenna side and within 2m from the antenna-feeder connector. c) If the feeder is longer than 10m but shorter than 20m, it is required to ground at two points, one point within 2m from the R8840 feeder connector and the antenna-feeder connector. d) If the feeder is longer than 20m and shorter than 60m, it is required to add one ground point within 2m from the point where the feeder leaves the tower or the rooftop. e) If the feeder is longer than 60m, it is required to add one more ground point for each 20 more meters. Figure 2 Key Points and Precautions 1 You need to apply waterproof treatment to all interfaces of the R8840. For details, see 8.5.1 Waterproof Measures for Equipment Connectors. 2 The R8840 is usually installed close to the antennas. The following materials are selected: a. When the feeder cable between the R8840 and the antenna is less than 5 m in length, you can select the fixed-length 1/2” rack-top jumper or make the jumper on site (for details on how to make the jumper, refer to the manual provided by the manufacturer). Figure 3 Installation Tools adjustable wrench b. When the feeder cable between the R8840 and the antenna is less than 20 m in Installation Materials 1 length, you need to select the 1/2” feeder cable. R8840 special rack-top jumpers c. When the feeder cable between the R8840 and the antenna is more than 20 m 2 but less than 60 m in length, you need to select the 7/8” feeder cable. 3 d. When the feeder cable between the R8840 and the antenna is more than 60 m in length, you need to select the 5/4” feeder cable. 3 At the connection position of the feeder cable, you do not need to install a lightning arrester. Confidential and Proprietary Information of ZTE CORPORATION. 59 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.3 Connecting the Cables at the R8840 Side 8.3.4 Connecting the Outdoor Optical Fiber Installation Steps Installation Figures 1 Before plugging the R8840 end of the optical cable to the LC interface of the R8840, remove the white protective cap. 2 Target the red mark upwards at the interface. After plugging the R8840 end properly, you can hear a “click” sound. Finally, tighten the protective cap (see Figure 1 and Figure 2). 3 Connect the other end to the TX/RX interface of the FS module according to the mapping between the optical module directions and sectors. 4 Figure 1 Figure 2 5 6 Key Points and Precautions 1 2 Installation Tools Installation Materials 1 outdoor optical fibers, whose 3 lengths and specifications depend on the survey result 2 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 60 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.4 Bundling and Distributing Indoor Cables in the Cable Tray Installation Figures 8.4.1 Bundling and Distributing Indoor Cables in Cable Tray Installation Steps 1 On the indoor cable tray, the DC power cable should be separated from the AC power cable (they should stay at least 50mm away from each other), the DC power cable should be separated from the unshielded signal cable (they should stay at least 50mm away from each other if they are laid in parallel), and the AC power cable should be separated from the unshielded signal cable (they should stay at least 150mm away from each other if they are laid in parallel). 2 Cables must be bound closely, and appear to be straight and orderly. 3 Cable ties should be distributed at regular intervals to ensure the tightness of cables. The interval between cable ties should be consistent with the interval between cable trays (usually, 300 to 700 mm). The redundant cable ties should be cut off. The indoor cable ties must be cut to the same length from the bottom. Black cable ties cannot be confused with white cable ties. The indoor cable ties should be white ties. 4 5 The redundant cable ties should be cut off. The indoor cable ties must be cut to the same length from the bottom. Black cable ties cannot be confused with white cable ties. The indoor cable ties should be white ties. 6 The power cables (including the GND cable) and signal cables are laid at two sides of the cable tray respectively. Key Points and Precautions Installation Tools diagonal pliers 1 Installation Materials white ties Confidential and Proprietary Information of ZTE CORPORATION. 1 The cable routes should meet the project design requirements. 2 Different types of cables should be laid separately from each other. Cable should be routed clearly and straightly. Cables should not intersect each other. Cables should be bound tightly to a moderate extent. 3 61 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.5 Waterproof Measures for Equipment Connectors Installation Figures Figure 1 Figure 2 8.5.1 Waterproof Measures for Equipment Connectors (A) Installation Steps (to be continued in next page) 1 Before the waterproof treatment, firstly clean off the dusts and dirt from the connector. 2 Firstly wrap the PVC insulating tape from the bottom upward. The upper layer covers 1/2 of the lower layer. PVC insulating tape should cover the entire feeder connector so that the waterproof insulating tape will not adhere to the connector (see Figure 1). 3 Then wrap the waterproof insulating tape. Unfold the waterproof insulating tape, remove the release paper and paste the tape end to the point 20~50mm under the connector (with the gelatinous layer inward) (see Figure 2). 4 Stretch the waterproof insulating tape evenly to make its width shrink to 75%~50% of the original width and keep certain elasticity. Wrap the connector from the bottom upward. The upper layer covers 1/2 of the lower layer (see Figure 3). 5 When the waterproof insulating tape reaches 20~50mm above the connector, wrap from the top downward to 20~50mm beneath the connector in the same way, and finally wrap from the bottom upward again. Therefore, 3 layers of waterproof insulating tape are required (see Figure 4-5). (to be continued in next page) Key Points and Precautions 1 (See next page) 2 Figure 3 Installation Tools (See next page) Figure 4 1 Installation Materials (See next page) Confidential and Proprietary Information of ZTE CORPORATION. 3 62 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.5 Waterproof Measures for Equipment Connectors Installation Figures Figure 5 8.5.1 Waterproof Measures for Equipment Connectors (B) Installation Steps (follow the previous page) 6 After 3 layers of waterproof insulating tape are wrapped, press the tape layers with hands to make sure there is no air between the layers (see Figure 6). 7 And then wrap the PVC insulating tape from the bottom upward. Both ends should cover 20mm more from those of the waterproof insulating tape layer. The upper layer should cover 1/2 of the lower layer. 3 layers of PVC insulating tape should be wrapped in the sequence: from the bottom upward, from the top downward and finally from the bottom upward (see Figure 7). 8 Bind both ends tightly with black ties after the wrapping (see Figure 8). Figure 6 Key Points and Precautions Figure 7 scissors Installation Tools diagonal pliers 1 Waterproof measures should be taken for antenna-jumper connectors, jumper-feeder connectors, ground points between feeders and ground clips, ground points of the outdoor cable ground clips, all R8840 connectors (including the feeder connectors, power connectors, optical connectors, monitoring connectors, AISG connectors, etc.). 2 During the wrapping process, do not stretch the tape too much. Figure 8 Installation Materials PVC insulating tape 3 1 The antenna-jumper connector must be wrapped from the bottom upward. And after the wrapping, both ends of the tape should be bond with black ties. 2 waterproof insulating tape 4 3 black ties The wrapping direction should be the same as the connector screwing direction. It is prohibited to wrap in the reserve direction. 4 Confidential and Proprietary Information of ZTE CORPORATION. 63 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.6.1 Checking B8200 Equipment Power-up/Power-down 8.6 Checking B8200&R8840 Equipment Power-up/Power-down Installation Figures Installation Steps 1 Check if the PGND cable at the equipment side has been connected correctly. And check if the DC power cables at the DC power supply cabinet side have been connected correctly (the polarities shall not be reverse). 2 Check and make sure the power switches at the DC power supply cabinet side are in the OFF state (see Figure 1). 3 Use a multimeter to test if the voltage at the DC power supply cabinet side is normal (see Figure 2). If it is normal, power up the DC power supply cabinet (turn ON the power switch). 4 Check if the B8200 fan runs normally and check the states of the board and module LED indicators (see Figure 3). Figure 1 Figure 2 5 After the power-up check, turn OFF the power supply at the DC power supply cabinet side. Key Points and Precautions 1 The normal voltage at the DC power supply cabinet side ranges from -40V DC to -57V DC. 2 Observe the fan module and board LED indicators to judge the running status. Figure 3 Installation Tools cross screwdriver multimeter Installation Materials 1 2 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 64 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 8.6.2 Checking R8840 Equipment Power-up/Power-down 8.6 Checking B8200&R8840 Equipment Power-up/Power-down Installation Figures Installation Steps 1 Check if the DC power cables and the PGND cable at the DC ILP/OLP side and the R8840 side have been connected correctly. 2 Check and make sure the power switches at both the DC power supply cabinet side and the ILP side are in the OFF state. 3 Use a multimeter to test if the voltage at the DC power supply cabinet side is normal. If it is normal, power up the DC power cabinet (turn ON the power switch). 4 Use a multimeter to test if the input voltage at the DC ILP side is normal (see Figure 1). If it is normal, turn ON the R8840 power switch in the DC ILP (see Figure 2). Figure 1 Figure 2 5 6 Open the DC OLP with a socket wrench and use a multimeter to test if the input voltage is normal (see Figure 3). If it is normal, wait for 5 minutes and touch the R8840 top to feel the heat. If there is heated, it indicates the equipment is running normally (see Figure 4). 7 After the power-up, turn OFF the power switches of DC ILP and DC power supply cabinet one by one. Key Points and Precautions 1 The normal voltages at the DC power supply cabinet side and the DC ILP/OLP side range from -40V DC to -57V DC. 2 Figure 3 Figure 4 Installation Tools Installation Materials cross screwdriver socket wrench multimeter If R8840 adopts AC power supply, refer to Installation Steps on this page. 3 1 2 4 3 Confidential and Proprietary Information of ZTE CORPORATION. 65 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Chapter 9 Making Cable Connectors and Labeling Confidential and Proprietary Information of ZTE CORPORATION. 66 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 9.1 Making Cable Connectors Installation Steps Installation Figures Figure 1 9.1.1 Making DC Power Cable & PGND Cable Terminals Figure 2 1 Remove about 15mm of the power cable sheath from one end of the cable. Trim the core wires with diagonal pliers (see Figure 1). 2 Cover the core wires with a matching copper lug (see Figure 2). 3 Use the multifunction crimping pliers to firmly crimp the copper lug. It the core wires can move in the lug, crimp the lug again (see Figure 3). 4 Cover the copper lug with the same color of heat-shrink sleeve, that is, the blue DC power cable should be covered with the blue heat-shrink sleeve. 5 Heat the heat-shrink sleeve with a heat gun to make it tightly wrap the crimping joint (see Figure 4). 6 Key Points and Precautions 1 The PGDN cable terminals are made in the same way as the DC power cable terminals. Please note the color of the heat-shrink sleeve must be the same as that of the cable. 2 Figure 3 Installation Tools wire stripper multifunction crimping pliers heat gun Figure 4 3 1 Installation Materials DC power cable 2 PGND cable 4 3 matching copper lugs 4 heat-shrink sleeve Confidential and Proprietary Information of ZTE CORPORATION. 67 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 9.1 Making Cable Connectors Installation Steps Installation Figures Figure 1 9.1.2 Making 75ohm E1 Cable Connectors Figure 2 1 Take a strand from the 75ohm E1 cable. Remove about 10mm of its sheath with a wire stripper to expose the inner sheath (see Figure 1). 2 Let the 75ohm E1 terminal go through the rear cover and the fastening ring. 3 Remove about 5mm of the inner sheath with a wire stripper to expose the inner core wire. Let the 75ohm E1 terminal go through the hole in the front cover of the connecting terminal (see Figure 2). 4 Weld the metal part of the hole and the core wire securely with an electric iron and a soldering tin thread (see Figure 3). 5 Hold the fastening ring against the rear end of the front cover and crimp the strand with the multifunction crimping pliers. (see Figure 4) 6 Screw down the front cover the rear cover of the connecting terminal. Key Points and Precautions 1 2 Figure 3 Installation Tools wire stripper multifunction crimping pliers electric iron soldering tin thread Figure 4 1 2 Installation Materials 75ohm E1 cable connecting terminals for 75ohm E1 cable 3 4 3 Confidential and Proprietary Information of ZTE CORPORATION. 68 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 9.1 Making Cable Connectors Installation Steps Installation Figures Figure 1 9.1.3 Clamping 120ohm E1 Cable Figure 2 1 Every 10 strands of the 120ohm E1 cable form a circle. See Figure 1, the 1st circle from bottom upward are blue/red, blue/black-pink/red, pink/black-green/red, green/black-orange/red, orange/black-gray/red, and gray/black. 2 Every strand in the 1st circle is marked with 1 red point, and every strand in the 2nd circle is marked with 2 red points. Other circles adopt the same rule. 3 Clamp every wire into the corresponding slot. Make sure the wire clamp is facing the correct direction (the cutting edge faces inward). Press the clamp post downward and the wire will be clamped after a sound of “KA”. The redundant wire will be cut off automatically (see Figure 2). 4 5 Key Points and Precautions 1 Determine how to connect the 120ohm E1 cable to DDF according to the conditions on the site. 2 Installation Tools wire clamp 1 Installation Materials 120ohm E1 cable 2 3 4 3 Confidential and Proprietary Information of ZTE CORPORATION. 69 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 9.1 Making Cable Connectors Installation Steps Installation Figures Figure 1 9.1.4 Making FE Cable Connectors Figure 2 1 Remove 20mm~30mm of the sheath with a wire stripper or some other tool to expose the core twisted-pair wires, Cut off the anti-stretch thread (see Figure 1). 2 According to the 568B standard, if the RJ45 sheet metal faces upward, the wires from left to right are white-orange, orange, white-green, blue, white-blue, green, white-brown, and brown (see Figure 2). 3 Trim the core wires with a wire stripper or some other tool and leave about 14mm outside the sheath. Arrange them in the correct order. 4 Insert the core wires into the RJ45 connector pins and push them against the inner end of the RJ45 connector (see Figure 3). 5 Check if every wire is in the correct position and clamp the RJ45 connector with the multifunction crimping pliers (see Figure 4). 6 After the cables are made, use the RJ-45 cable gauge to check if the FE cables are made up to the standard. Key Points and Precautions Figure 3 Installation Tools multifunction wire stripper crimping pliers 1 In Step 3, the naked core wires should not be too long. Otherwise the sheath may not be clamped in the RJ45 connector and the wires may become flexible later. 2 After inserting the core wires to the RJ45 connector, it is required to check and make sure the core wires have reached the top end in the connector. Figure 4 1 2 Installation Materials Category-5 unshielded Ethernet cable RJ45 connectors 3 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 70 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 9.1 Making Cable Connectors Installation Steps Installation Figures Figure 1 9.1.5 Making Feeder Connectors Figure 2 1 Remove about 29mm of the feeder sheath with a feeder connector cutter or a knife and expose the metal part. Use a brush to clean off the dusts after the cutting (see Figure 1). 2 Apply grease to the metal part. Let the rear cover of the connector go through the metal part and make the spring ring against the external metal part of the feeder (see Figure 2). 3 Move the rear cover of the connector to the front part until the spring ring against the external metal part. Remove the dust and sharp edges in the cross section (see Figure 3). 4 Take out the front cover of the connector. Connect the inner conductor in the connector to the feeder core, push the connector and make sure the connector and the feeder contact securely. Screw the rear cover of the connector to make it contact the screw thread in the connector. 5 6 Fix the connector and the rear cover firmly. All the feeder connectors must have waterproof measures. Refer to 8.5.1 Waterproof Measures for Equipment Connectors for detailed information (see Figure 4). Key Points and Precautions 1 Here takes the straight 7/16-inch DIN coaxial connector and the 7/8-inch feeder as the example to illustrate how to make the feeder connector. Refer to the above steps when making other types of feeder connectors. 2 Figure 3 Installation Materials feeders 3 1 brush 2 matching feeder connectors 4 feeder connector cutter (optional) 3 knife Installation Tools 2 adjustable wrenches Figure 4 Confidential and Proprietary Information of ZTE CORPORATION. 71 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 9.2 Labeling Installation Figures 9.2.1 Outdoor Labeling Installation Steps 1 All the labels should be ZTE private labels. 2 Paste labels at both ends of the rack-top jumpers: one point 200mm from the master feeder connector and one point 200mm from the BS8800 rack top. 3 Paste labels at both ends of the -48V DC power cable, -48VGND DC power cable, and the ground cable. At the power supply cabinet side, the labels should be 20mm from the power terminals; at the ground bar side, the labels should be 20mm from the ground terminals. Paste labels at both ends of the optical fibers, network cables, and trunk cables. The labels should be 20mm from the cable ends. 4 5 The labels should face a consistent direction, with the side indicating the outgoing direction upward or facing the operations and maintenance panel, to facilitate reading. Key Points and Precautions Installation Tools 1 Installation Materials paper labels 2 1 Labels fall into two categories: printed paper labels (used indoors) and tags (used outdoors). 2 It is prohibited to paste labels or write on the boards. If the writing is required, the handwriting must be neat and the labels must be pasted tidily. 3 4 3 4 Confidential and Proprietary Information of ZTE CORPORATION. 72 ZXSDR B8200&R8840 (V4.0) NodeB Engineering Installation Guide (BBU Indoors & RRU Indoors) V1.0 Procedure Item 9.2 Labeling 9.2.2 Outdoor Labeling Installation Steps Installation Figures 1 All the labels should be ZTE private outdoor labels in complete sets (see Figure 1). 2 Paste labels at both ends of the outdoor antenna jumpers and rack-top jumpers. The labels should be 200mm from the jumper connectors. 3 A master feeder must have at least 3 labels: 2 labels 200mm from the feeder connectors at its both ends, 1 label 200mm from the feeder outlet before it enters the equipment room, and 1 label 200mm from the point where it leaves the iron tower. 4 Paste clear labels at both ends of the outdoor cables and ground cables. The labels should be 200mm from the cable ends. 5 Paste clear labels at both ends of the outdoor optical cables. The labels should be 200mm from the cable ends. 6 The outgoing directions indicated by the labels should be consistent with the actual cable routes. Key Points and Precautions 1 Labels of the master feeder are in a composite mode and the ZTE-WCDMA tags should be used to identity the system. 2 Installation Tools Installation Materials 1 3 tags 2 4 3 Confidential and Proprietary Information of ZTE CORPORATION. 73