LIBRARY BUILDING RENOVATION PROJECT NORTH SEATTLE COLLEGE Project Request Report - 2016 Washington State Board of Community & Technical Colleges NORTH SEATTLE COLLEGE PROJECT STEERING COMMITTEE Dr. Warren Brown, President Kristen Jones, Vice President for Instruction Alan Ward, Interim Vice President for Administrative Services Alissa Agnello, Dean of Math and Science Jeffrey Vasquez,Student Leadership Jason Francois, Director of Facilities Curtis Bonney, Dean of Basic and Transitional Studies Julianne Kirgis, Dean of Arts, Humanities and Social Sciences Kathleen Chambers, E-Learning, Instructional Design Sharon Simes, Dean of Library Amy LaZerte, Rental Coordinator Farideh Faraz, Room Scheduling/ Utilization PRIMARY CONTACT Kristen Jones, Vice President for Instruction North Seattle College 9600 College Way N Seattle, WA 98103 206.934.3701 Kristen.Jones@seattlecolleges.edu STATE OF WASHINGTON, DEPARTMENT OF ENTERPRISE SERVICES Indra Jain, Project Manager CONSULTANT TEAM SCHACHT ASLANI ARCHITECTS Cima Malek-Aslani, AIA, Principal Walter Schacht, FAIA, Principal Eric Aman, AIA, Principal Glen Stellmacher, Intern Architect Magnusson Klemencic Associates, Structural Engineer Hargis Engineers, Mechanical Engineer Hargis Engineers, Electrical Engineers and IT C&N Consulting, Cost Estimator Please note: The PDF version of the document contains hyperlinks in the Table of Contents and at references to Appendix in the Project Request Report. Click to jump to the referenced page. Table of Contents 1. Executive Summary��������������������������������������������������������������������������������������������������������������������������������������������������������������������������1 2. Scope and Project Description ��������������������������������������������������������������������������������������������������������������������������������������������������3 3. Prior Planning ��������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������6 4. Needs Analysis������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������9 5. Issues Analysis ��������������������������������������������������������������������������������������������������������������������������������������������������������������������������������� 15 6. Site Feasibility����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������� 15 7. Space Utilization ����������������������������������������������������������������������������������������������������������������������������������������������������������������������������� 16 8. Capital Cost Development��������������������������������������������������������������������������������������������������������������������������������������������������������� 17 9. Operating Budget Impacts��������������������������������������������������������������������������������������������������������������������������������������������������������� 18 10. Schedule ��������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������� 18 11. Implementation������������������������������������������������������������������������������������������������������������������������������������������������������������������������������� 19 Attachments Project Budget (Form C-100)��������������������������������������������������������������������������������������������������������������������������������������������������������� 23 Project Parameters Form ����������������������������������������������������������������������������������������������������������������������������������������������������������������� 33 Minimum & Overarching Criteria��������������������������������������������������������������������������������������������������������������������������������������������� 35 DAHP Application Material����������������������������������������������������������������������������������������������������������������������������������������������������������� 37 Construction Cost Estimate ����������������������������������������������������������������������������������������������������������������������������������������������������������� 41 Diagrams & Sketches Existing Campus Plan ����������������������������������������������������������������������������������������������������������������������������������������������������������������������� 61 Building Area Takeoff Plan ����������������������������������������������������������������������������������������������������������������������������������������������������������� 62 Building Plans����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������� 63 Building Sections ��������������������������������������������������������������������������������������������������������������������������������������������������������������������������������� 67 Appendix Design Team Conditions Analysis (Engineer’s Reports)��������������������������������������������������������������������������������������������� 71 Facility Conditions Survey - Excerpts������������������������������������������������������������������������������������������������������������������������������������� 95 NSC Master Plan - Excerpts������������������������������������������������������������������������������������������������������������������������������������������������������� 105 NSC Strategic Plan - Excerpts �������������������������������������������������������������������������������������������������������������������������������������������������� 109 Photographs of Existing Conditions ���������������������������������������������������������������������������������������������������������������������������������������115 Best Practices to Reduce Greenhouse Gas Emissions������������������������������������������������������������������������������������������������ 121 Accreditation Report - Excerpts ���������������������������������������������������������������������������������������������������������������������������������������������� 123 LEED Checklist���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������� 125 Campus Space Utilization Calculations ������������������������������������������������������������������������������������������������������������������������������ 127 Attached Support Files Space Utilization Calculations (see attached excel file.) Library Building Renovation Project i ii North Seattle College 1. EXECUTIVE SUMMARY A. PROBLEM STATEMENT / TYPE OF REQUEST 1. CRITICAL NEEDS North Seattle College serves the rapidly growing and increasingly diverse population of Seattle’s north end. It has made significant strides to adapt to the changing needs of its service district, integrating employment, health and human service agencies with its own student services, increasing its focus on innovative professional-technical programs such as nanotechnology while continuing a tradition of excellence in academic transfer programs. The college continues to evolve to meet the city’s, the state’s and nation’s changing economic and educational needs. Employers are looking for job candidates with communications, critical thinking and teamwork skills. Cutting across a wide range of occupations is the need for people who can manage information resources. This requires learning environments and student study spaces to support project based learning, group work and peer-to-peer engagement. Considerable research confirms the contributions that academic libraries make to student success, engagement and retention. The Association of College & Research Libraries study, “Academic Library Contributions to Student Success: Documented Practices from the Field,” includes community colleges and universities in Washington State. It reports that library instruction builds students’ confidence, contributing to retention and persistence, particularly for first year students. Students who receive library instruction as part of their courses achieve higher grades and demonstrate better information literacy competencies than others. A Johns Hopkins University publication, “Library Use and Undergraduate Outcomes: New Evidence for Retention and Academic Success,” reports that participation in library-related activities were positively correlated with student engagement in other areas; namely, participation in information technology was associated with competencies in active and collaborative learning, student-faculty interactions, and overcoming academic challenges. North Seattle College’s library has the potential to play a significant role in providing these resources. The college’s aging facility, however, does not have the required spaces or infrastructure to achieve these goals. The 1969 Library Building is part of the original, monolithic, concrete campus that was designed on a model that does not serve contemporary education. Its deficiencies were identified in the college’s 2013 accreditation report which called for a major renovation of the building. The state’s 2011, 2013 and the 2015 Facility Condition Surveys all identify the need for a comprehensive renovation of the facility. Student study spaces for individual and group work should be at the center of the library but that space is filled with under utilized book stacks. Student should have broad access to information technology but the limited resources constrain information literacy. The Student Media Center, Teaching and Learning Center, and e-Learning Support Center should be configured as an integrated, shared assembly of digital resources for students, Library Building Renovation Project 1 faculty and staff but they were shoehorned into the building in an incremental series of retrofits which limit their function. Classrooms in the library were designed for lectures, not group work or project based learning. The five, sloped-floor lecture halls get limited use because they can only serve a static lecture pedagogy. The building has exterior circulation which segregates its functions by floor. Access and wayfinding are difficult. There is limited space for student interaction. The forty-six year old building is in poor condition and has never been significantly improved. It lacks adequate lateral strength to resist a seismic event and does not meet contemporary standards for life safety. Mechanical systems are beyond their service life. The main service switchboard and power distribution equipment are at the end of their useful life. Inadequate IT infrastructure limits the college’s ability to adequately train and prepare students in the digital age. 2. TYPE OF REQUEST The request is for a renovation of the Library Building. B. PROPOSED SOLUTION Renovating the Library Building will extend the life of the building for more than 50 years. The 58,177 square feet project will support the college’s strategic goals of advancing student success and achievement, adapting to a rapidly changing world, building community and creating a culture of innovation and collaboration. The library will be transformed to an Information Commons that provides contemporary library services, consolidates digital resources and supports collaborative learning. Study areas will provide a variety of space for individual and group work. Floors in four of the tiered lecture halls will be leveled to create flexible classrooms space that can accommodate multiple programs and uses. They will be the first active learning environments on campus, available for use by all programs on campus. One tiered space will be retained for use as multi-purpose space for larger assemblies including music, theater, film, performing arts, presentations and lectures. Informal study lounges will be located immediately adjacent to these spaces to promote peer-to-peer interaction before and after class. The renovated Library Building will support on-line, web-enhanced and traditional education. In the context of North Seattle’s campus with its labyrinth of exterior walkways it will offer one of the few interior public spaces where people can gather, study in groups and collaborate. Structural systems will be updated to meet contemporary life safety code requirements for resisting seismic forces. Mechanical and electrical systems will be replaced to meet functional and energy code requirements. Infrastructure renewal will be coordinated with programmatic renewal. 2 North Seattle College C. PROGRAMS ADDRESSED BY PROJECT The project addresses all of the college’s library services including the Student Media Center and the Teaching and Learning Center and the e-Learning Support Center. It provides flexible classrooms and student study spaces that will be utilized by all programs on campus and a multi-purpose performance venue that will be shared by the music and performing arts programs. D. PROBABLE COST SUMMARY AND COMPARISON TO BENCHMARK Category Acquisition Consultant Services Construction Contracts Equipment Artwork Other Costs Total (Rounded to $1,000) Cost % Total Budget $0 $4,562,681 $24,658,764 $1,566,595 $102,268 $173,228 $31,064,000 0% 14.68% 79.38% 5.04% 0.33% 0.57% 100.00% Total project cost per square foot is less than 100% of the expected cost for the facility type. E. PROJECT SCHEDULE Phase Predesign Design Construction Start Complete Sep-2016 Jul-2017 Jul-2019 Mar-2017 Jun-2019 Jan-2021 F. FUNDING The project is anticipated to be funded through general obligation bonds allocated through the state’s capital budget. 2. SCOPE AND PROJECT DESCRIPTION A. THE PROJECT AND ITS BENEFITS 1. PROJECT DESCRIPTION Renovating the forty-six year old Library Building will provide space for student instructional support, research and information literacy skills. It will contain contemporary classrooms and informal student study spaces that support active, project based learning, group work and peer-to-peer engagement and be shared by all programs on campus. Library Building Renovation Project 3 2. BENEFITS The Library Building renovation supports North Seattle College’s mission by implementing its three core themes. a. Core Theme 1: Advancing Student Success • A variety of learning environments that promote student engagement and faculty/ student engagement. • Informal student study and group study rooms adjacent to right sized classrooms to support a combination of active, collaborative and self-directed learning. • Adjacencies of instructional spaces that are adaptable to interdisciplinary learning. • Access to modern, professional media equipment, hardware and software and technology support through a right sized and properly equipped Student Media Center. This access will give students the knowledge and skills needed to prepare them for successful careers in our global, competitive economy. • Access to a full range of e-learning support services for online, hybrid, and web-enhanced campus classes including orientation resources, technical support, workshops, and monitored test proctoring in an updated e-learning support facility. • Access to information resources expected by students in the digital age by providing data systems that support new knowledge resources. b. Core Theme 2: Excelling Teaching and Learning 4 • Flexible, level classrooms that enable the college to deliver to active learning pedagogies that focus on collaborative learning and group work. • Appropriate space and adjacencies for services including the e-learning Support Center and the Teaching and Learning Center that will foster faculty development through collaboration, shared spaces and resources in response to evolving pedagogies. • Resources and access to digital information and software for all faculty and staff that promote excellence and innovation in the classroom and on campus. • A facility that bridges faculty and student services by bringing students and their instructors together physically and virtually. North Seattle College c. Core Theme 3: Building Community. Renovating the Library Building will provide contemporary learning environments that enable the college to build upon its partnerships with state universities, industry and local high schools. • North Seattle College has partnership agreements, and shares library and instructional space with Western, Central and Eastern Washington Universities. College graduates who hold Direct Transfer Agreement associate degrees may enroll in selected B.A. degree programs offered by the universities without leaving their home campus. • North Seattle College also has partnerships with businesses including Boeing, Phillips Health Care, Rolex, and Fluke Inc. who provide financial resources, equipment, and curricular input for the engineering, electronics, health care, and technology programs. The college partners with local K-12 Schools, including programs with Ingraham High School Readiness Academy and College in High School at Ingraham and Nathan Hale high schools. B. PROGRAM AND RELATED SPACE TABLE Program Existing Proposed Change 17,728 19,100 1,372 952 1,270 318 Teaching & Learning Center Offices, Lab and Conference 1,274 1,240 (34) E-Learning Offices, Learning Lab and Conference 1,048 1,670 622 0 550 550 2,874 9,906 7,032 11,469 4,989 (6,480) Assignable Square Feet (ASF) 35,345 38,725 3,380 Support Spaces 22,832 19,452 (3,380) Gross Square Feet (GSF) 58,177 58,177 0 Efficiency 61% 67% 6% Library Reading Room, Reference Area, Makers Space, Periodicals, Circulation and Reference Desk, Study Rooms, Shipping and Receiving and Library Support Student Media Center Offices, Media Studio, Editing Lab and Work Room Shared Spaces Conference Room and Collaboration Lounge Shared Instructional Space Classrooms, Seminar, Study & Breakout Rooms Music/Performance/Lecture Multi-Purpose Hall, Support Spaces, Rehearsal Areas Library Building Renovation Project 5 C. INCREASED FTES ACCOMMODATED BY THIS PROJECT Demand for education in the college’s service district is growing. The 2017 CAM projects that college’s Type 1 FTES will increase by 140 students and that Type 2 FTES will grow to 172 by 2024. Increased public transit access to the college is projected to further increase enrollment at the college. Sound Transit’s Northgate light rail station will serve over 15,00 passengers a day when it opens in 2021. A major pedestrian and bicycle bridge will connect the college to the light rail station and the existing Northgate multi-modal center. The bridge will land at the north end of campus and is anticipated to be used by 7,000 people every day. D. TABLE OF EXISTING BUILDINGS WITH UNIQUE FACILITY IDENTIFIERS UFI A09018 * Building Name Library Building Year Built FCS Survey Score Project Type FCS GSF* 1969 460 Renovation 80,192 Total 80,192 58,177 gross square feet will be renovated for the project. Reconfiguring the tiered lecture halls reduces the amount of square footage that needs to renovated on the ground floor of the building. See Page 62 in the Appendix for floor plans that indicate area to be renovated. 3. PRIOR PLANNING A. HISTORY OF THE BUILDING & ORIGINAL FUNDING SOURCE The Library Building was constructed in 1969 as part of the original North Seattle College campus. The project was funded by the State. The building remains as it was originally constructed. Improvements consist of minor changes to interior walls. No upgrades have been made to the building systems which are at the end of their service life. B. INSTITUTIONAL GOALS, STRATEGIC PLAN, & FACILITIES MASTER PLAN 1. INSTITUTIONAL GOALS & STRATEGIC PLAN The 2013 Northwest Commission on Colleges and Universities Year Three Evaluation Report indicated that renovation of the Library Building was required to adequately support academic and other programs that are integral to the college’s Strategic Plan focuses on three core themes. See Page 109 in the Appendix for highlighted sections of NSC’s strategic plan. 6 North Seattle College Strategic Plan Core Theme Library Building Renovation Project 1. ADVANCING STUDENT SUCCESS Create a culture that intentionally places student learning and growth at the center of what the college does; Promote student engagement with coursework, faculty and staff, and cocurricular activities; Foster active, collaborative, self-directed learning; Support student perseverance and goal completion; Provides flexible classrooms that enable student centered, collaborative learning. Provides student study rooms and informal learning spaces for project based learning that enables learning to continue outside the classroom. Provides learning environments that enable students to learn marketable business world skills along with the academic material. Provides informal student study spaces that foster social and academic conversations enabling students to build the social connections that contribute to retention. 2. EXCELLING IN TEACHING & LEARNING Engage in the work of teaching and learning with passion, vision, and creativity; Adapt to the needs of a rapidly changing world by changing curriculum, services, and practices; Ensure the effectiveness and quality of work through ongoing assessment and professional development. Provides a-state-of-the-art Teaching and Learning Center to enable faculty and staff to explore new styles and methodologies of instruction, classroom support and delivery of student services. Provides adjacencies of space that enable the Teaching and Learning Center to collaborate and share resources with the e learning Support Center 3. BUILDING COMMUNITY Create a diverse, inclusive, and safe environment accessible to all; Strengthen college community through open communication, civility, accountability, and mutual respect; Reach outside the institution to form local and global partnerships and pursue civic engagement; Work in ways that are environmentally, socially and fiscally sustainable. Provides an appropriate mix of instructional and informal gathering spaces that attract, retain and promote a community of learners. Extends the life of a 40 plus-year old campus structure for another generation. Meets goals for energy-efficiency as outlined by LEED Silver standards. Supports existing partnerships with state universities. Library Building Renovation Project 7 2. FACILITY MASTER PLAN The facility master plan identifies renovation of the Library Building as the college’s first priority for major capital development. Previous major project priorities outlined in the plan have been implemented. See Pages 105-107 in the Appendix for excerpts from NSC’s Long Range Campus Plan. The Long Range Campus Master Plan is based on a commitment to renewing the college’s aging, original buildings through a series of comprehensive renovations that will extend their life for future generations of college students. The existing buildings have the capacity to serve the college’s long range needs but they do not serve contemporary instructional programs. Deficient structural, mechanical and electrical systems in the aging facilities threaten their usefulness. A major goal of the master plan is to update structural systems to ensure the life safety of occupants, replace mechanical and electrical systems to meet current codes and reduce maintenance and operating costs. The master plan also calls for the development of interior common spaces to create a sense of community and provide safe access to restrooms and other building services which are lacking in the original structures. C. SBCTC SYSTEM DIRECTION GOALS 1. ECONOMIC DEMAND Strengthen state and local economies by meeting the demands for a well-educated workforce. Employers want employees to be able to work in groups, communicate effectively and to think critically. The Library Building renovation will provide instructional spaces to enable project based, active learning. Project based learning requires collaboration and group work outside the classroom. The renovation will provide a variety of spaces to support learning beyond the classroom. The Student Media Center in the library provides North Seattle’s students with access to media resources and basic instruction enabling them to incorporate digital and analog audiovisual media into their course assignments and presentations. The Student Media Center will be reconfigured to provide students with better access to media equipment and staff support that enables students to hone their communications skills. In the context of learning academic content, students are able to develop marketable skills employers seek. 2. STUDENT SUCCESS Achieve increased educational attainment. Access to instructional spaces, information technologies, library, and support services is critical to improving student success at all levels, from basic skills to degree attainment. This is particularly true in the college’s catchment area, where the population is becoming older and more diverse, and the average income level is declining. The Library Building renovation will provide a balance of group instruction and individual study 8 North Seattle College spaces that support both formal and informal learning to support increased educational attainment. 3. INNOVATION Use technology, collaboration, and innovation to meet the demands of the economy and improve student success. Reconfiguration of the Student Media Center, the Teaching and Learning Center and the e-Learning Support Center provides opportunities for collaboration through adjacencies. These programs build upon the College’s goal to create an information and innovation commons where students and staff inspire one another. Specialty spaces within the Library Building become readily available and include: • Presentation/ Seminar rooms • Collaboration rooms with access to video conferencing software • Makers Space • Media Production Rooms The Makers Space is an innovation laboratory that uses digital and other technologies to create and test prototypes. This lab will give students access to and instruction in operating equipment that businesses will expect students to be familiar with. It will be another project based learning venue that students will utilize to fulfill their assignments. 4. NEEDS ANALYSIS A. THE CAPITAL PROBLEM 1. BUILDING AGE & CONDITION The 46-year-old Library Building is in the worst condition of any building on campus, does not meet the needs of its programs and represents a life safety hazard due to its inability to resist seismic forces and lack of a fire suppression system. The state’s 2015 Facility Conditions Survey (FCS) recommended that the building be renovated. It is a long standing problem – the 2011 and 2013 Facility Condition Surveys also called for a comprehensive renovation of the facility. The facility is at a pivotal moment in its service life. Each succeeding biennium that nothing happens accelerates the deterioration. A summary of the state board’s FCS comments follows. See Page 95-104 in the Appendix for applicable excerpts from the 2015 FCS report. Library Building Renovation Project 9 Category 2015 Library Building Facility Conditions Survey Score 460, Needs Improvement/Renovation Structure: Seismic improvements needed. Primary Systems Secondary Systems Service Systems Exterior Closure: Some deterioration of exterior closure is evident. Roofing: Leaking and deterioration, a new roof is required Floor Finishes: Extensive deterioration and unevenness Doors and Hardware: Original door hardware is old, worn and failing. Renovation of the library calls for all new doors and hardware. Plumbing: Some leaking apparent. HVAC: Air handler fan and drive motor bearings are at the end of their useful life, failing and should be replaced. In-line fan motors have become unreliable due to component failure. Duct sealant has deteriorated allowing air to escape. Inadequate capacity, zoning and distribution; equipment deteriorating. No A/C in office areas, no ventilation in hazardous areas. Chilled/ hot water cooling/ heat with VAV from central plant; bad electric re-heat boxes funded for replacement Electrical: Capacity does not accommodate future needs. Life/ Safety: The aluminum handrails on the elevated walkways and stairwells are original/46 years old and in various stages of deterioration. Deficiencies include badly cracked and spalling cement at post bases, bent and broken balusters, and damaged and broken top rails. The damaged rails should be repaired or replaced depending on the level of damage to each section to meet current codes. Quality Standards Heat Loss Fire/ Safety: The building is not equipped with a fire suppression system. Maintenance: Deferred maintenance is evident. Comments: Good renovation candidate. Insulation: Present but does not meet current energy code standards. 2. FUNCTIONALITY Library Services The library’s service model has changed significantly since the Library Building was constructed nearly fifty years ago. It has evolved from its role as a book depository and quiet study to an information commons that should be a digital hub with places for group study that is capable of serving the broad needs of the college’s diverse community. The existing facility does not serve those needs. The Library Building is not conducive to research or study for students, faculty and staff. It does not support the library’s goal of fostering information literacy. As instruction moves to on-line and web-enhanced delivery, the importance of the Library as a physical place on the campus where students engage and collaborate with their peers and faculty increases. In the context of North Seattle College, a campus characterized by exterior 10 North Seattle College public circulation and limited common space, the Library Building is the only place where students can gather for group study. There are limited places for individual or group study. The library’s major open space, on the upper level, is filled with under-utilized ranges of book shelves. Consolidating the shelving to meet the current book count would open this space up for tables and chairs, putting students in the heart of the library. The building lacks the digital infrastructure to support the multiple digital resources that students must access to complete their assignments. It does not have adequate wireless data and electrical power to support mobile computing. Lighting does not support individual or group work. Digital Resources The library’s core resources include the Student Media Center, the Teaching and Learning Center, and the e-Learning Support Center which provide critical support services to students and faculty. They should work together as an integrated unit, increasing access and sharing space. However, space for these functions was created piecemeal. The result is three nearly unusable service areas. None of the departments have enough space to function properly. For example, the Student Media Center is too small to serve the number of students who use it every quarter. Presentation practice rooms lack the resources required to provide students with media equipment experience or develop communication skills for business and industry. The configuration of the Teaching and Learning Center (TLC) and eLearning Support Center make them difficult to secure. Thefts occur even though the staff is present. Classrooms and Multi-purpose Space The college’s instructional model has changed significantly since the Library Building opened in 1969. Five steeply raked halls, three with 150 seats and two with 60 seats, were designed for the static, instructor-centered pedagogy of the time. They do not serve contemporary student-centered pedagogy, which utilizes active learning, group work and peer-to-peer engagement. One of the large halls was designated as a multi-purpose performance venue but does not contain the variable acoustics, sound reinforcement or projection systems necessary to accommodate a wide range of uses. Another of the large halls was converted to a theater for use by the drama program. There is no adjacent break out rooms or informal study space for students. The facilities get limited use because they do not support project-based learning or collaboration. Power and Data Electrical systems are beyond their service life. The main service switchboard and power distribution equipment need to be replaced. The building needs substantial improvements in terms of wireless infrastructure, cable pathways, server rooms and mechanical systems to cool computer equipment. See Page 91-94 in the Appendix. Library Building Renovation Project 11 3. HEALTH, LIFE SAFETY & BUILDING CODE The Library Building has significant life safety and building code deficiencies. Inability to resist an earthquake and lack of a fire suppression systems are foremost among the college’s concerns for its students, faculty and staff. Seismic Issues A Tier 1 Structural Analysis found that this building does not have adequate capacity to resist significant lateral loads from an earthquake (see pages 71-73 and 75-85 in the Appendix), which represents a life safety hazard. It cites specific deficiencies including: • The existing concrete shearwalls lack adequate capacity to resist seismic loads. Shear stresses exceed the Tier 1 evaluation limit of 100 psi by a significant margin. • One inch seismic joints are too small to accommodate expected lateral displacements and could result in pounding of adjacent structures in a seismic event. • Structural irregularities between the Library Buildings concrete walls and floor could contribute to the adverse overall seismic performance. • Deficient precast concrete wall connections could lead to falling building components. • Deficient concrete shearwall connections weaken an already deficient lateral system. Other Life Safety Issues • The facility does not have a fire sprinkler system, which is required for a building of this type larger than 5,000 square feet. See Page 87 in the Appendix. • Handrails on the elevated walkways and stairwells are unsafe. Badly cracked and spalling cement at post bases, bent and broken balusters, and damaged and broken top rails have weakened the system. It is no capable of resisting a typical lateral force. • Building ventilation does not meet code requirements for outside air. See Page 87 in the Appendix. • Emergency lighting does not meet code. See Page 92 in the Appendix. ADA/Barrier-Free Access The Library Building presents significant obstacles to barrier-free access. The fire alarm system does not have audible and visual alarms required to meet intelligibility and ADA requirements. See Page 93 in the Appendix. Toilet rooms do not have adequate capacity to serve the building’s occupants and do not meet ADA accessibility standards. See Page 87 in the Appendix. Energy Codes • 12 The mechanical system is driven by electrical power which does not meet the requirements of the Seattle Energy code. It operates 24/7 because it is a constant heating and ventilation system without variable speed drives or an energy North Seattle College management system to reset the temperature within the air handlers. See Page 87 in the Appendix. • The building’s envelope and lighting controls do not comply with the energy code. See Page 92 in the Appendix. B. OBVIOUS AND CRITICAL NEEDS 1. NEW SPACE FOR ENROLLMENT DEMAND No new space is proposed by this project. 2. RENOVATION/REPLACEMENT a. Program Mix Changes The Library Building will continue to house the college’s library and instructional spaces that will be shared by all programs on campus. Space will be reconfigured to serve contemporary program needs. • Library space currently apportioned to book shelving will be reduced and reapportioned to student study areas. • Four static, steeply raked lecture halls will be converted to six flat floor classrooms that are right-sized for contemporary active learning environments that support project-based learning and can be adapted for use by a wide range of programs. Break out rooms and informal student study areas will be added adjacent to the classrooms. • Space previously converted for use as a theater will be returned to instructional use. • One tiered performance space will remain and will be renovated for multiple uses by music and theater programs, and other campus-wide issues. b. Simplifying Space Relationships • The library’s core digital resources, the Student Media Center, e-Learning Support Center and Teaching and Learning Center will be reconfigured to provide the adjacencies that enable them to share space and resources. This will increase opportunities to provide support services to staff and students. • Creation of common, circulation space inside the building will improve access and security. • Gross to net square footage efficiency will be increased from 61% to 67%. C. ACCREDITATION NEEDS The 2013 Northwest Commission on Colleges and Universities Year Three Evaluation Report stated that the Library Building, as well as the college’s Instructional Building, needed a major renovation. Excerpts from the report are included on Page 123-124 in the Appendix. Library Building Renovation Project 13 The report said that “ HVAC systems, lighting systems, window systems, furniture systems, and other infrastructure systems in the Library & Theater Building and the Instructional Building are in real need of renovation/upgrade, as identified in the Physical Infrastructure section”. The evaluators recommended that the college take the steps necessary to implement the recommendations of the 2011 Facility Condition Survey (FCS), which called for renovation of both buildings. The Library Building is in the worst condition of any facility on campus as reflected by its FCS score and needs a comprehensive renovation to continue to serve its programmatic goals and provide adequate life safety to its occupants. D. ALTERNATIVES CONSIDERED The college considered a range of alternatives to renovating the Library Building. 1. PROGRAMMATIC & FACILITY RELATED There are no programmatic alternatives to renovating the Library Building. The library and its related learning spaces are fundamental to the instructional mission of the college. There are no facility-related alternatives to comprehensively renovating the facility. Addressing the wide range of seismic deficiencies with the envelope, structure, mechanical and electrical systems cannot be done incrementally. Improving seismic resistance requires demolishing a significant portion of the interiors in order to connect new elements to the existing structure. Reconfiguring the lecture halls to create classrooms that serve contemporary pedagogy will trigger building wide code upgrades. The building cannot be replaced. It is one of the five original, concrete buildings which were constructed together. The original assembly forms an integral whole. Four of the buildings are built over a common below-grade parking garage. The fifth, the Library Building is immediately adjacent and connected to the campus infrastructure. Replacing the structure would not be cost-effective because portions of the remaining structures would have to be shored, existing circulation paths and egress patterns would be disconnected. The only practical way to deal with the aging building is to comprehensively renovate it and renew the life of the overall structure for the next 50 years or more. 2. CONSEQUENCES OF DOING NOTHING According to the 2011, 2013 and 2015 Facilities Conditions Surveys, North Seattle’s Library Building needs to be renovated. Deferring the renovation further creates the potential for significant negative consequences: • 14 The facility will continue to be a hazard in terms of life safety. It is not capable of resisting a significant seismic event and does not have a fire suppression system. North Seattle College • The roof, envelope, mechanical and electrical systems have the potential to fail. At some point incremental maintenance and repairs will not be adequate to keep them in operation. • The building will continue to be under-utilized. Instructional space will be further vacated over time. • The college’s library services will continue to lag behind needs, reducing the college’s ability to recruit, support and retain students, faculty and staff. • North Seattle College students will not have access to the support services and instructional spaces required to teach information competency, teamwork and collaboration. 5. ISSUES ANALYSIS A. USEFUL LIFE OF THE PROPOSED FACILITY Renewing the library will create a flexible, durable facility that serves the college and the changing needs of its students for the next 50 years. The exterior envelope will be improved to meet energy code requirements. The structural system will be improved to meet seismic requirements. The mechanical and electrical systems will be completely replaced. B. DISCUSSION OF SUSTAINABILITY The building is planned and budgeted to maximize building system performance and reduce the total cost of ownership. • The building is targeted for LEED Silver v4 certification, which places significant emphasis on energy efficiency and material selection. See Page 125 in the Appendix. • Eight of the State’s required Best Practices to Reduce Greenhouse Gas Emissions have been identified as achievable for this project (see Page 121 in the Appendix). C. IMPACT ON DEFERRED MAINTENANCE AND REPAIR BACKLOG The deferred maintenance and repair backlog costs identified in the 2015 Facility Condition Survey (FCS) would be eliminated by a comprehensive renovation of the building. The cost to maintain a building of this age are significant as indicated by $780,000 roof replacement currently listed as a Minor Works Preservation project for the 2015-17 capital budget. The renovation project would replace finishes, roof, envelope, mechanical and electrical systems that are beyond their service life and no longer cost effective to maintain. 6. SITE FEASIBILITY A. ACQUISITION, MITIGATION, AND NEIGHBORHOOD ISSUES The renovation project is located on the North Seattle College campus. No land acquisition is required. There are no neighborhood or mitigation issues. Library Building Renovation Project 15 B. PARKING EXPANSION No parking expansion is required for the project. C. PERMIT ISSUES Renovation of the Library Building is part of the Major Institution Master Plan adopted by the City of Seattle. The college will obtain a Master Use Permit under the guidelines of the master plan. D. UTILITY AND OTHER INFRASTRUCTURE NEEDS Existing campus water, sanitary sewer and electrical lines will serve the renovation project. Electrical switchgear, switchboards, and transformers will be replaced. E. STORMWATER No stormwater improvements are required for the renovation project since it does not increase impermeable surfaces. F. ROADS AND TRAFFIC SIGNALS Off campus roads and traffic signals will not be affected by this project. G. DAHP REVIEWS The project will comply with the Executive Order 05-05. An EZ-1 Project Review Sheet has been submitted to Department of Archaeology and Historic Preservation initiating the formal review process of any ground disturbances. At the time of issuance for this Project Request Report all necessary steps with DAHP have been completed and no further action is required until the project receives funding. 7. SPACE UTILIZATION A. FALL 2014 UTILIZATION OF CAMPUS INSTRUCTIONAL SPACE 1. EXISTING SPACE UTILIZATION TABLE Space utilization yields the following recent data for classrooms and labs (See Page 127 in the Appendix.) 16 Quarter Program Space Utilization (hours per week) Fall Quarter 2014 Classrooms Labs 10.25 6.13 North Seattle College B. NEW PROGRAMS, CHANGING MIX OF PROGRAMS The renovated Library Building will contain its existing programs. This includes the library with its Student Media Center, Teaching and Learning Center, and e-Learning Support Center, the music program, drama program, and instructional spaces that are used by all programs on campus. Music and drama will share the 150-seat multi-purpose performance seat. The existing theater, which occupies one of the original 150-seat tiered lecture halls, will be converted back to instructional space. C. USE OF VACATED SPACE No floor space will be vacated as part of the renovation project. The five existing tiered lecture halls are two-story volumes. they will be reduced to one-story volumes when their floors are levelled to create flexible, adaptable classrooms. The residual space below will be utilized as a mechanical plenum. D. NEED & AVAILABILITY FOR SURGE SPACE The library, music programs and classrooms will be relocated during the construction phase of the project. Surge space was anticipated in the Long Range Campus Plan. Vacated space in the college’s old cafeteria will provide a place for these programs to function until the Library Building is ready for occupancy. E. FLEXIBILITY & ADAPTABILITY OF PROPOSED SPACE Flexibility is the ability to support multiple learning activities in one classroom. The proposed renovation would create classrooms that are sized for flexible furnishings that may be arranged in different configurations to support lecture, group work and individual work. Classrooms will accommodate active group learning by allowing students and instructors to move between digital and analog tools for collaboration during class. Student study rooms and informal student study space are adjacent to classrooms to encourage interdisciplinary collaboration. The adjacencies provide flexibility to adapt pedagogies that utilize group learning and group problem-solving. The informal learning spaces adjacent to classrooms facilitate learning outside the classroom and support evolving pedagogies. Adaptability is the ability to adapt the building to growth and changes over time. The proposed adjacencies in the renovation between library services allow these spaces to flex and integrate over time as services change. Library Building Renovation Project 17 8. CAPITAL COST DEVELOPMENT A. PREDICTION OF OVERALL PROJECT COST 1. PROJECT BUDGET Category Cost % Total Budget $0 0% $4,562,681 14.68% $24,658,764 $1,566,595 $102,268 $173,228 $31,064,000 79.38% 5.04% .33% .57% 100.00% Acquisition Consultant Services Construction Contracts Equipment Artwork Other Costs Total (Rounded to $1,000) 2. EXPECTED COST CALCULATION* The project budget is lower than the expected cost. Facility Type CTC Libraries Classrooms Expected $/GSF GSF by Type Expected $ $504 $587 37,082 21,095 58,177 $18,967,792 $12,375,102 $31,072,984 Total * From Expected Cost Calculation Table provided by SBCTC. B. COMPARABLE SBCTC PROJECT COST/FTE 1. Project Budget / Net New FTES Comparison Current SBCTC Projects Project Cost New FTES $/Net New FTES Whatcom Community College Learning Commons $31,624,000 *181 $174,718 **$27,333,205 *172 $158,914 65,195 square feet North Seattle College Library Renovation Project 58,177 square feet * New FTES is calculated using Type 2 = Day On-Campus + On-line; Project types serve combined FTES -Academic, Vocational and Basic Skills/Development. ** North Seattle College cost is in unescalated dollars to align with costs from SBCTC Status Reports. 18 North Seattle College 9. OPERATING BUDGET IMPACTS A. ANTICIPATED ANNUAL IMPACT ON COLLEGE’S O&M BUDGET There is no anticipated impact on the college’s operations and maintenance budget due to the fact that the renovated facility does not add new square footage, which requires additional maintenance and operations costs. 10. SCHEDULE Phase Start Complete Sep-2016 Mar-2017 Design Jul-2017 Jun-2019 Construction Jul-2019 Jan-2021 Predesign 11. IMPLEMENTATION A. TIMING OF THE BUDGET REQUEST This request is for a project that would be funded for design in the 2017-2019 Biennium and for construction in the 2019-2021 Biennium. The Library Building renovation is North Seattle College’s number one capital priority. B. JUSTIFICATION FOR DESIRED METHOD OF CONSTRUCTION The college evaluated three methods of project delivery. ALTERNATIVE PROJECT DELIVERY GCCM (General Contractor/Construction Manager) • GCCM may be utilized on projects with construction costs of $10 million or more where early involvement of the contractor is a benefit in terms of scheduling, phasing, or coordination, construction at an occupied facility; a complex or technical work environment; or specialized work on a building that has historic significance. • GCCM may involve increased costs for design fees related to working with the contractor and preparing multiple bid packages; and for the GCCM risk contingency. Design Build • Design Build may be utilized on projects with construction costs of $2 million or more where construction activities are highly specialized; there is an opportunity for greater innovation or efficiencies between the designer and the builder; or significant savings in project delivery time would be realized. • Design Build may involve increased costs due to the effort to prepare the RFQ/RFP, stipends for competitors in the RFP phase and the ongoing participation of programming consultants. Library Building Renovation Project 19 CONVENTIONAL PROJECT DELIVERY Design Bid Build • Design Bid Build is used to procure the majority of public works in Washington State and almost all projects for the State Board of Community and Technical College. The process encourages price competition. Responsibility criteria may be utilized to ensure that a qualified contractor is awarded the project. • The college is experienced with this delivery type. It successfully utilized Design Bid Build for two comparable renovations – in terms of scope, complexity and cost – to the proposed project. • Design and construction contingencies adequate to manage project have been included in budget. As a result of the evaluation, the college identified Design Bid Build procurement as the desired method of construction for the project. 20 North Seattle College ATTACHMENTS Library Building Renovation Project 21 22 North Seattle College Project Budget (Form C-100) PROJECT BUDGET (FORM C-100) STATE OF WASHINGTON AGENCY / INSTITUTION PROJECT COST SUMMARY Agency Project Name OFM Project Number SBCTC North Seattle College - Library Building Renewal Contact Information Name Phone Number Email Gross Square Feet Usable Square Feet Space Efficiency Construction Type Remodel Alternative Public Works Project Inflation Rate Sales Tax Rate % Contingency Rate Base Month Project Administered By Predesign Start Design Start Construction Start Construction Duration Statistics MACC per Square Foot Escalated MACC per Square Foot 0.0% A/E Fee Class College classroom facilit A/E Fee Percentage Yes Projected Life of Asset (Years) Additional Project Details No Art Requirement Applies 3.08% Higher Ed Institution 9.60% Location Used for Tax Rate 10% November-15 DES 58,177 September-16 July-17 July-19 18 Months Schedule Predesign End Design End Construction End $307 $352 B 10.28% 50 Yes Yes Seattle March-17 June-19 January-21 Green cells must be filled in by user Total Project Project Cost Estimate $27,333,205 Total Project Escalated Rounded Escalated Total C-100(2014) Page 1 of 2 $31,063,536 $31,064,000 12/22/2015 Library Building Renovation Project 23 Project Budget (Form C-100) STATE OF WASHINGTON AGENCY / INSTITUTION PROJECT COST SUMMARY Agency Project Name OFM Project Number SBCTC North Seattle College - Library Building Renewal Cost Estimate Summary Acquisition Subtotal Predesign Services A/E Basic Design Services Extra Services Other Services Design Services Contingency Consultant Services Subtotal Acquisition $0 Acquisition Subtotal Escalated Consultant Services $385,000 $1,395,619 $881,500 $1,103,017 $376,514 $4,141,649 Consultant Services Subtotal Escalated $0 $4,562,681 Construction Construction Contingencies Maximum Allowable Construction Cost (MACC) Sales Tax Construction Subtotal Equipment Sales Tax Non-Taxable Items Equipment Subtotal Artwork Subtotal $1,788,677 $17,886,768 $1,888,843 $21,564,288 Construction Contingencies Escalated Maximum Allowable Construction Cost (MACC) Escalated Sales Tax Escalated Construction Subtotal Escalated Equipment $1,250,000 $120,000 $0 $1,370,000 Equipment Subtotal Escalated Artwork $102,268 Artwork Subtotal Escalated $2,045,352 $20,453,520 $2,159,892 $24,658,764 $1,566,595 $102,268 Agency Project Administration Agency Project Administration Subtotal DES Additional Services Subtotal Other Project Admin Costs $0 $0 Project Administration Subtotal $0 Other Costs Subtotal Total Project $0 Project Administation Subtotal Escalated Other Costs $155,000 Other Costs Subtotal Escalated Project Cost Estimate $27,333,205 Total Project Escalated Rounded Escalated Total C-100(2014) 24 North Seattle College Page 2 of 2 $0 $173,228 $31,063,536 $31,064,000 12/22/2015 Project Budget (Form C-100) Cost Estimate Details Item Purchase/Lease Appraisal and Closing Right of Way Demolition Pre-Site Development Other Insert Row Here ACQUISITION TOTAL Acquisition Costs Escalation Base Amount Factor $0 NA Escalated Cost Notes $0 Green cells must be filled in by user Cost Details - Acquisition Page 1 of 1 12/22/2015 Library Building Renovation Project 25 Project Budget (Form C-100) Cost Estimate Details Item 1) Pre-Schematic Design Services Programming/Site Analysis Environmental Analysis Predesign Study Tenant Relocation Sub TOTAL $385,000 $1,395,619 3) Extra Services Civil Design (Above Basic Svcs) Geotechnical Investigation Commissioning Site Survey Testing LEED Services Voice/Data Consultant Value Engineering Constructability Review Environmental Mitigation (EIS) Landscape Consultant $30,000 $12,000 $25,000 $0 $15,000 $120,500 $30,000 $65,000 $65,000 $5,000 $35,000 Site Measurement and Verification $5,000 Renderings, Models, Presentations $10,000 Lighting Consultant Signage Consultant Acoustical Consultant Audio/ Visual Consultant Hazardous Materials Consultant Security Consultant Interior -Equipment and Furnishings Design $45,000 $37,000 $18,000 $17,000 $25,000 $7,500 Theatre/ Perfoming Arts Consultant $125,000 Building Envelope Consultant MUP/ Legal Services- Permit Coordination Tenant Relocation Design $22,000 Energy Conservation Model (ELCCA) $50,000 Life Cycle Cost Analysis Tool Artwork Design Coordination Document Reproduction Services for VE & Constructability $25,000 $5,000 North Seattle College Escalated Cost Notes $185,000 $200,000 2) Construction Documents A/E Basic Design Services Other Insert Row Here Sub TOTAL Cost Details - Consultant Services 26 Consultant Services Escalation Base Amount Factor 1.0518 $1,395,619 $404,943 Escalated to Design Start 69% of A/E Basic Services 1.0829 $1,511,316 Escalated to Mid-Design $27,000 $18,000 $35,000 $7,500 Page 1 of 2 12/22/2015 Project Budget (Form C-100) Insert Row Here Sub TOTAL 4) Other Services Bid/Construction/Closeout HVAC Balancing Staffing Testing and Inspections Hazardous Material Testing and Monitoring Building Envelope (WAB) Testing and Inspections Document Reproduction (Bid/Construction) $881,500 1.0829 $954,577 Escalated to Mid-Design $627,017 $75,000 31% of A/E Basic Services $90,000 $15,000 $58,000 $32,000 Additional Construction Observation $162,000 As-Built Documentation Advertising Equipment Training Insert Row Here Sub TOTAL $36,000 $3,000 $5,000 $1,103,017 5) Design Services Contingency Design Services Contingency Other Insert Row Here Sub TOTAL $376,514 CONSULTANT SERVICES TOTAL $4,141,649 1.1435 $1,261,301 Escalated to Mid-Const. 1.1435 $430,544 Escalated to Mid-Const. $376,514 $4,562,681 Green cells must be filled in by user Cost Details - Consultant Services Page 2 of 2 12/22/2015 Library Building Renovation Project 27 Project Budget (Form C-100) Cost Estimate Details Construction Contracts Escalation Base Amount Factor Item 1) Site Work Notes G10 - Site Preparation G20 - Site Improvements G30 - Site Mechanical Utilities G40 - Site Electrical Utilities G60 - Other Site Construction Other Insert Row Here Sub TOTAL $0 1.1176 $0 2) Related Project Costs Offsite Improvements City Utilities Relocation Parking Mitigation Stormwater Retention/Detention Other Insert Row Here Sub TOTAL $0 1.1176 $0 1.1435 $20,453,520 3) Facility Construction A10 - Foundations A20 - Basement Construction B10 - Superstructure B20 - Exterior Closure B30 - Roofing C10 - Interior Construction C20 - Stairs C30 - Interior Finishes D10 - Conveying D20 - Plumbing Systems D30 - HVAC Systems D40 - Fire Protection Systems D50 - Electrical Systems F10 - Special Construction F20 - Selective Demolition General Conditions $1,831,373 $1,787,969 $111,041 $1,130,361 $36,439 $1,404,413 $55,695 $765,986 $3,281,904 $454,884 $3,583,073 $459,750 $760,486 $1,728,893 Insert Row Here Sub TOTAL $17,886,768 4) Maximum Allowable Construction Cost MACC Sub TOTAL Cost Details - Construction Contracts 28 Escalated Cost North Seattle College $494,500 $17,886,768 $20,453,520 Page 1 of 2 12/22/2015 Project Budget (Form C-100) This Section is Intentionally Left Blank 7) Construction Contingency Allowance for Change Orders Other Insert Row Here Sub TOTAL $1,788,677 $1,788,677 1.1435 $2,045,352 Other Insert Row Here Sub TOTAL $0 1.1435 $0 Sub TOTAL $1,888,843 $2,159,892 CONSTRUCTION CONTRACTS TOTAL $21,564,288 $24,658,764 8) Non-Taxable Items Sales Tax Green cells must be filled in by user Cost Details - Construction Contracts Page 2 of 2 12/22/2015 Library Building Renovation Project 29 Project Budget (Form C-100) Cost Estimate Details Item E10 - Equipment E20 - Furnishings F10 - Special Construction Other Insert Row Here Sub TOTAL Equipment Escalation Base Amount Factor $350,000 $900,000 Escalated Cost Notes $1,250,000 1.1435 $1,429,375 Other Insert Row Here Sub TOTAL $0 1.1435 $0 Sub TOTAL $120,000 $137,220 EQUIPMENT TOTAL $1,370,000 $1,566,595 1) Non Taxable Items Sales Tax Green cells must be filled in by user Cost Details - Equipment 30 North Seattle College Page 1 of 1 12/22/2015 Project Budget (Form C-100) Cost Estimate Details Item Artwork Escalation Factor Base Amount Escalated Cost Notes Project Artwork $0 0.5% of Escalated MACC for new construction Higher Ed Artwork $102,268 Other Insert Row Here ARTWORK TOTAL 0.5% of Escalated MACC for new and renewal construction $102,268 NA $102,268 Green cells must be filled in by user Cost Details - Artwork Page 1 of 1 12/22/2015 Library Building Renovation Project 31 Project Budget (Form C-100) Cost Estimate Details Item Agency Project Management Additional Services Other Insert Row Here PROJECT MANAGEMENT TOTAL Project Management Escalation Base Amount Factor $0 $0 Escalated Cost 1.1435 Notes $0 Green cells must be filled in by user Cost Estimate Details Item Mitigation Costs Hazardous Material Remediation/Removal Other Costs Escalation Base Amount Factor $25,000 Escalated Cost Notes $0 Historic and Archeological Mitigation $0 Building Permit/ Master Use Insert Row Here OTHER COSTS TOTAL $130,000 $155,000 1.1176 $173,228 Green cells must be filled in by user Cost Details - Project Management 32 North Seattle College Page 1 of 1 12/22/2015 Project Parameters Form PROJECT PARAMETERS FORM Type of Space Renovation of Existing Project Parameters Square Footage (S1) = 58,177 Percent 100% New Space (S2) Demolished Area (S3) Total Affected Area 58,177 Net Area Change = New – Demo 0 Costs Dollars Acquisition 0 Consultant Services $4,562,681 14.68% Construction Contracts (w/o eligible Infrastructure) $24,658,764 79.38% Equipment $1,566,595 5.04% Artwork $102,268 .33% Other Costs $173,228 .57% Total Project Cost (C1) $31,064,000 100% Funding Dollars Percent State Appropriation $31,064,000 100% 100% Percent Eligible Infrastructure Contracts (from C100) Project Management Financed – backed by State Appropriation Local Funds – Cash (see list of qualifying funds) Ma Financed – backed by Local Funds Mb Total Project Funding $31,064,000 100% Matching Variance = Cost – Funding 0 Project Weighting Equivalent Area Percent 58,177 100% 58,177 100% Matching Infrastructure Renovation Replacement New Total Library Building Renovation Project 33 Project Parameters Form 34 North Seattle College Minimum & Overarching Criteria MINIMUM & OVERARCHING CRITERIA Library Building Renovation Project 35 Minimum & Overarching Criteria 36 North Seattle College DAHP Application Material DAHP APPLICATION MATERIAL PROJECT REVIEW SHEET – EZ1 HISTORIC & CULTURAL RESOURCES REVIEW PROPERTY / CLIENT NAME: FUNDING AGENCY: Washington State Board for North Seattle College Community and Technical Colleges Project Applicant: Contact Person: Address: City, State: Phone/ FAX: E-Mail: Funding Agency: Organization: Address: City, State: Phone: North Seattle College Jason Francois, Director of Facilities North Seattle College Seattle, WA 9600 College Way N Zip: 98103 County: King 206.934.3701 Kirsten.Jones@seattlecolleges.edu State of Washington Enterprise Services 1500 Jefferson St. SE Olympia, WA Zip: 98501 360.407.2200 PLEASE DESCRIBE THE TYPE OF WORK TO BE COMPLETED PLEASE DESCRIBE THE PROPOSED WORK AND DETAIL ALL GROUND DISTURBING ACTIVITIES AND PROVIDE (Be as detailed as possible to avoid having to provide additional information) PHOTOS OF AREAS OF WORK. Provide a detailed description of the proposed project: Execute substantial rennovation, code compliance, and seismic retrofit to existing, forty six (46) year old, four (4) level, North Seattle College library buidling. Existing windows to be replaced. Describe the existing project site conditions: The existing building sits within the campus of North Seattle College. Exterior paths and walkways allow for circulation of students around and into the building. Describe the proposed ground disturbing activities: Ground disturbances are expected only within the footprint of the building at discrete points where substantial seismic retrofit requires strengthened foundation elements of the structure. Check if building(s) will be altered or demolished. If so please complete a DAHP Determination of Eligibility “EZ2 form” using our on-line Historic Property Inventory Database for each building, 45 years or older, effected by the proposed project. Library Building Renovation Project 37 DAHP Application Material PLEASE ATTACH A COPY OF THE RELEVANT PORTION OF A 7.5 SERIES USGS QUAD MAP AND OUTLINE THE PROJECT INPACT AREA. USGS Quad maps are available on-line at http://maptech.mytopo.com/onlinemaps/index.cfm Project Location Township: 26 Range: 4 Section: 32 Address: 9600 College Way N City: Seattle, WA Mail this form to: ( W i t h in County: King Department of Archaeology and Historic Preservation or E-mail to: 1063 S. Capitol Way, Suite 106 P.O. Box 48343 Olympia, WA 98504-8343 3 0 d ay s DAHP wi l l ma i l th e i r op i ni o n Robert Whitlam, Ph.D. State Archaeologist, DAHP (360) 586-3080 rob.whitlam@dahp.wa.gov b a ck t o y o u . ) Please be aware that this form may only initiate consultation. For some projects, DAHP may require additional information to complete our review such as plans, specifications, and photographs. An historic property inventory form may need to be completed by a qualified preservation professional. 38 North Seattle College DAHP Application Material DETERMINATION OF ELIGIBILITY FORM – EZ2 FOR THE NATIONAL REGISTER OF HISTORIC PLACES North Seattle College Address: (in rural areas also include section, 9600 College Way N Township, and range) City: Seattle, WA County: 98103 PROPERTY / CLIENT NAME: Built Date: 1969 Information source: North Seattle College Optional Information: (property description, list of alterations, historic significance, historic use, etc…) Funding Agency: Manager Name: Organization: Address: City, State, Zip: Phone: Indra Jain State of Washington Enterprise Services 1500 Jefferson St. SE Olympia, WA Zip: 98501 360.407.2200 . PLEASE ATTACH ONE OR TWO CLEAR PHOTOS OF BUILDING (You may use 35mm film, Polaroid or a digital image. Photocopies of images are not acceptable) STATE HISTORIC PRESERVATION OFFICER OPINION (To be completed by the Department of Archaeology and Historic Preservation) I understand that the above said agency/jurisdiction is requesting the opinion of the State Historic Preservation Officer concerning the eligibility of the listed property for inclusion in the National Register of Historic Places. This statement confirms that I have consulted with the State Historic Preservation Office (SHPO) as required by the National Historic Preservation Act of 1966. (1) In my opinion, the property is eligible for inclusion in the National Register. As such further review by the SHPO is required for any alteration to the property. Please fill out Building Rehabilitation Worksheet completely and return to the SHPO office for further review. (2) In my opinion, the property is not eligible for inclusion in the National Register. No further review is required by the SHPO. Signed: Representative of State Historic Preservation Officer Date: _ Mail this form to: (W i t h in Log #: _____________ Department of Archaeology and Historic Preservation or E-mail to: 1063 S. Capitol Way, Suite 106 P.O. Box 48343 Olympia, WA 98504-8343 3 0 d ay s DAHP wi l l ma i l th e i r op i ni o n Russell Holter Preservation Design Reviewer (360) 586-3533 russell.holter@dahp.wa.gov b a ck t o y o u . ) Library Building Renovation Project 39 DAHP Application Material December 2, 2015 Mr. Indra Jain Architect Department of Enterprise Services 1500 Jefferson St SE Olympia, WA 98501 In future correspondence please refer to: Log: 120215-10-DES Property: Seismic retrofit and rehabilitation of North Seattle Community College Library Re: Area of Potential Impact Concur Dear Mr. Jain: We have reviewed the materials forwarded to our office for the above referenced project. Thank you for your description of the area of potential impact (API) for the project. We concur with the definition of the API. We look forward to the results of your cultural resources survey efforts, your consultation with the concerned tribes, and receiving the survey report. We would appreciate receiving any correspondence or comments from concerned tribes or other parties that you receive as you consult under the requirements of Governor’s Executive Order 05-05 (GEO 05-05) and the Historic Property Inventory when it is available. These comments are based on the information available at the time of this review and on behalf of the State Historic Preservation Officer in conformance with GEO 05-05. Should additional information become available, our assessment may be revised. Thank you for the opportunity to review and comment. If you have any questions, please feel free to contact me. Sincerely, Russell Holter Project Compliance Reviewer (360) 586-3533 russell.holter@dahp.wa.gov State of Washington • Department of Archaeology & Historic Preservation P.O. Box 48343 • Olympia, Washington 98504-8343 • (360) 586-3065 www.dahp.wa.gov 40 North Seattle College Construction Cost Estimate CONSTRUCTION COST ESTIMATE C&N Consultants Construction Cost Consultants 105 South Main Street, Suite 300A Seattle, WA 98104 Telephone 206-624-8539 Fax 206-624-8955 North Seattle College Library Renovation November 26, 2015 Seattle, WA PRR Estimate Library Building Renovation Project 41 Construction Cost Estimate November 26, 2015 North Seattle College Library Renovation PRR Estimate Building Exclusions from Construction Cost: INTRODUCTION Escalation Design fees Owners administration costs Building and land acquisition fees Legal and accounting fees Removal of unforeseen underground obstructions Owner’s furniture, furnishings and equipment Owners supplied materials Work outside the construction site boundary. Moving owners equipment and furniture Compression of schedule, premium or shift work, and restrictions on the contractor's working hours Assessments, finance, legal and development charges Assumption used in establishing the estimate: Open and competitive bidding among all proportions of the work Items that may affect the cost estimate: Modifications to the scope of work included in this estimate. Special phasing requirements other than mentioned above. Restrictive technical specifications or excessive contract conditions. Any non-competitive bid situations. Bids delayed beyond the projected schedule. Page 1 42 North Seattle College Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building OVERALL SUMMARY CONSTRUCTION COST Gross Area Building Escalation, excluded TOTAL CONSTRUCTION COST 58,177 SF Date: November 26, 2015 AC Prepared By: $/SF 307.45 $ 17,886,767 N/A 17,886,767 Alternates: Alternate 1: Replace Elevator 355,500 Alternate 2: Exterior lighting at building 51,594 Alternate 3: Softscape enhancements at water feature 63,406 Alternate 4: Level 3 roof terrace 141,291 Page 2 Library Building Renovation Project 43 Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building 58,177 SF Gross Floor Area: Date: November 26, 2015 Prepared By: AC Summary of Estimate No. Element Description A10 FOUNDATIONS A1010 A1020 A1030 A20 Standard Foundation Special Foundation Slab on grade BASEMENT WALL CONSTRUCTION Element Totals Group Totals Cost Per SF 494,500 352,349 121,178 20,973 8.50 6.06 2.08 0.36 - A2010 Basement Excavation - A2020 Basement Wall Construction - B10 SUPERSTRUCTURE B1010 Floor & Roof Construction B20 B2020 Exterior Windows B2030 Exterior Doors 31.48 31.48 1,787,969 30.73 236,806 4.07 1,428,120 24.55 123,042 2.11 ROOFING B3010 Roof Covering C10 1,831,373 EXTERIOR ENCLOSURE B2010 Exterior Walls B30 1,831,373 111,041 111,041 INTERIOR CONSTRUCTION 1.91 1.91 1,130,360 19.43 C1010 Partitions 566,807 9.74 C1020 Interior Doors 362,859 6.24 C1030 Fittings 200,695 3.45 C20 STAIRS C2010 Stair Construction C30 36,438 36,438 INTERIOR FINISHES 0.63 0.63 1,404,413 24.14 C3010 Wall Finishes 249,675 4.29 C3020 Floor Finishes 639,561 10.99 C3030 Ceiling Finishes 515,177 8.86 D10 CONVEYING D1010 Elevators & Lifts D20 55,695 PLUMBING D2010 Plumbing D30 55,695 HVAC 0.96 0.96 765,986 765,986 13.17 13.17 3,281,904 56.41 Page 3 44 North Seattle College Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building 58,177 SF Gross Floor Area: Date: November 26, 2015 Prepared By: AC Summary of Estimate No. Element Description Element Totals D3010 HVAC D40 3,281,904 FIRE PROTECTION ELECTRICAL 7.82 3,583,072 EQUIPMENT 61.59 61.59 29,129 29,129 FURNISHINGS 0.50 0.50 430,621 E2010 Fixed Furnishings F10 7.82 3,583,072 E1010 Equipment E20 56.41 454,884 D5000 Electrical E10 Cost Per SF 454,884 D4010 Sprinkler System D50 Group Totals 430,621 SPECIAL CONSTRUCTION 7.40 7.40 - - F1010 Special Structure F1020 Special Construction F20 SELECTIVE BUILDING DEMOLITION 760,486 F2010 Building Demolition 760,486 Sub-Total 16,157,874 277.74 Sub-Total 16,157,874 277.74 1,728,893 17,886,767 29.72 307.45 17,886,767 307.45 General Conditions 10.70% Sub-Total November 2015 Construction Cost 13.07 Escalation Included at Overall Summary TOTAL CONSTRUCTION COST $17,886,767 307.45 Page 4 Library Building Renovation Project 45 Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description A10 Quantity Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals FOUNDATIONS A1010 Standard Foundation A1011 Foundations Reinforced concrete footings and pile caps at brace frames and new and existing shear walls, allow 240 CY 1,468.12 352,349 352,349 Total For Standard Foundations A1020 Special Foundation A1021 Pile foundations Allowance for micropiles 1 LS 121,178.20 121,178 121,178 Total For Special Foundations A1030 Slab on Grade A1031 Standard slab on grade Reinforced concrete slab on grade patch and repair 1 LS 20,973.15 20,973 Total For Slab on Grade A20 20,973 BASEMENT CONSTRUCTION A2010 Basement Excavation A 2010 Basement Excavation Excavation and removal for pile caps foundations included in foundation and piling costs N/A Total For Basement Excavation A2010 Basement Walls A2021 Basement wall construction Concrete shear wall included in floor construction N/A Total For Basement Walls B1010 Floor & Roof Construction B 1010 Floor Construction Northern portion of building - renovation Level 1 floor slab at large lecture hall, theater and lecture halls Structural steel, 4#/SF Steel stud bearing walls at 4'-0" o.c. including bracing Metal deck Reinforced concrete slab on metal deck Level 3 floor slab reinforcement 24 21,824 10,600 10,600 T SF SF SF 7,457.12 5.24 4.89 8.86 181,805 114,430 51,874 93,866 Page 5 46 North Seattle College Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description Quantity Structural steel reinforcement at level 3 for relocated book stacks, allow 2#/SF across level 3 slab Northern portion of building - seismic Tie concrete slabs together at seismic joint including infill Widen Southermost seismic joint Widen Southermost seismic joint from 1" to 4" Brace frames Wide flange steel columns at brace frames Wide flange steel beams at brace frames Brace frame at Level 1 Brace frame at Level 2 Brace frame at Level 3 Tie brace frames into existing concrete "H" columns and steel collector plates to tie into floors, allow Intumescent paint at brace frames, not required Southern portion of building - seismic Widen Southermost seismic joint from 1" to 4" included in Northern portion of the building improvements Strengthen connections from existing concrete walls to existing slabs and columns Reinforced concrete shear wall, 1'-0" thick Allowance for structural modifications to multi purpose theater Allowance for suspended slab modifications B 1020 Roof Construction Steel framing at Level 3 roof slab for reinforcement of mechanical equipment penetrations and openings Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals 24 T 7,457.12 180,878 150 LF 264.43 39,664 128 LF 343.73 43,997 43 26 12 10 9 T T EA EA EA 7,457.12 7,457.12 12,397.46 10,766.22 11,418.72 317,673 190,716 148,770 107,662 102,768 1 LS 72,240.85 72,241 N/A N/A 1 1,080 1 1 LS SF LS LS 27,964.20 69.91 23,303.50 34,955.25 27,964 75,503 23,304 34,955 1 LS 23,303.50 23,304 1,831,373 Total For Floor Construction B20 EXTERIOR CLOSURE B2010 Exterior Walls B2011 Exterior wall construction Metal stud framing Batt insulation Gypsum board, 5/8" Paint exposed steel Graffiti resistant coatings over vertical concrete surfaces, allow B2013 Exterior louvers, screens and fencing Louvers, fixed extruded aluminum, allow 168 168 168 1 1 SF SF SF LS LS 10.25 1.17 3.26 9,321.40 9,321.40 1,723 196 548 9,321 9,321 1 LS 5,825.88 5,826 B2014 Exterior sun control devices Exterior sun control devices assumed not required B2015 Balcony walls and handrails Exterior guardrails with perforated metal panels and wood handrails at level 2 walkways N/A 798 LF 221.38 176,664 Caulking, sealants and firestopping Page 6 Library Building Renovation Project 47 Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description Quantity Caulking, sealants and firestopping Unit 1 LS Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals 33,207.49 Miscellaneous Canopy's not required 33,207 N/A 236,806 Total For Exterior Walls B2020 Exterior Windows B2022 Curtain walls Aluminum framed thermal glazed fixed curtain wall system at Level 1 B2023 Storefronts Aluminum framed thermal glazed fixed entrances and storefront glazing at Level 2 Aluminum framed thermal glazed fixed entrances and storefront glazing at Level 3 4,634 SF 110.69 512,945 6,180 SF 78.65 486,053 5,456 SF 78.65 429,122 1,428,120 Total For Exterior Windows B2030 Exterior Doors B 2030 Exterior Doors Aluminum glazed entrance doors and frame including hardware Double Single Specialty hardware 16 3 1 EA EA LS 6,350.20 3,262.49 11,651.75 101,603 9,787 11,652 123,042 Total For Exterior Doors ROOFING B3010 Roof Covering B3011 Roof finishes Bituminous membrane roofing replacement included under separate project in 2016 Bituminous membrane roofing, patching at skylights, allow 1 LS 7,573.64 N/A 7,574 B3014 Flashings and trim Sheet metal flashings and trim 1 LS 37,285.60 37,286 320 SF 134.00 42,878 1 LS 23,303.50 23,304 B3021 Glazed roof openings Aluminum framed skylight system Miscellaneous Rough carpentry Total For Roofing 111,041 Page 7 48 North Seattle College Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description C10 Quantity Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals INTERIOR CONSTRUCTION C1010 Partitions C1011 Fixed partitions Level 1 Metal stud framing Batt insulation Gypsum board, 5/8" Gypsum board underlayment Furring and gypsum board at H columns Level 2 Metal stud framing Batt insulation Gypsum board, 5/8" Gypsum board underlayment Furring and gypsum board at H columns Level 3 Metal stud framing Batt insulation Gypsum board, 5/8" Gypsum board underlayment Furring and gypsum board at H columns 13,944 11,852 27,888 9,064 2,688 SF SF SF SF SF 4.03 0.99 2.68 2.21 7.69 56,215 11,739 74,737 20,065 20,671 8,388 7,130 16,776 5,452 2,100 SF SF SF SF SF 4.03 0.99 2.68 2.21 7.69 33,816 7,061 44,958 12,070 16,149 12,416 10,553 24,831 8,070 4,883 SF SF SF SF SF 4.03 0.99 2.68 2.21 7.69 50,053 10,452 66,545 17,866 37,547 C1013 Operable and folding panel partitions Operable partitions, not required N/A C1016 Interior balustrades and screens Interior guardrails with perforated metal panels and wood handrails at level 3 open to below area 129 LF 314.60 40,583 C1017 Interior windows and storefronts Sound booth glazing at level 1 Interior glazing at level 2 Interior glazing at level 3 40 189 119 SF SF SF 93.21 68.16 68.16 3,729 12,883 8,111 1 1 LS LS 7,573.64 13,982.10 7,574 13,982 Miscellaneous Gypsum board bulkheads Blocking and backing, allow 566,807 Total For Interior Partitions C1020 Interior Doors C1021 Interior doors Interior doors, frames and hardware Hollow metal / wood / glazed door and frame including hardware Level 1 Single Double Level 2 Single 25 11 EA EA 2,388.61 4,369.41 59,715 48,063 28 EA 2,388.61 66,881 Page 8 Library Building Renovation Project 49 Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description Quantity Double Level 3 Single Double Specialty hardware, allow C1025 Interior door sidelights and transoms Interior door glazed sidelights C1026 Interior hatches and access doors Access doors Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals 3 EA 4,369.41 13,108 24 2 1 EA EA LS 2,388.61 4,369.41 12,234.34 57,327 8,739 12,234 57 EA 1,642.90 93,645 1 LS 3,145.97 3,146 362,859 Total For Interior Doors C1030 Specialties C1032 Fabricated compartments and cubicles Toilet partitions ADA toilet partition STD toilet partition Urinal screens C1033 Storage shelving and lockers Janitors mop rack and shelf C1035 Identifying devices Code signage Wayfinding and room identification signage Building signage, assume FF&E C1037 General fittings and misc. metals Miscellaneous metals, allow 0.4#/SF Fire extinguisher cabinets Corner guards, stainless steel Grab bars at restrooms per set Mirrors, custom, wall mounted Restroom accessories Markerboards / tackboards 6 15 2 EA EA EA 1,328.30 1,205.96 594.24 7,970 18,089 1,188 3 EA 535.98 1,608 58,177 58,177 SF SF 0.17 0.70 10,168 40,672 N/A 23,271 16 1 7 1 1 1 LB EA LS EA LS LS LS 2.74 272.65 10,253.54 219.05 1,631.25 17,128.07 22,371.36 63,719 4,362 10,254 1,533 1,631 17,128 22,371 200,695 Total For Fittings and Specialty Items C20 STAIRS C2010 Stair Construction C 2010 Stair Construction including railings and finish Handrail replacement at stairs Replace treads at main stairs and landings 80 265 Total For Stair Construction LF SF 314.60 42.53 25,168 11,270 36,438 Page 9 50 North Seattle College Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description Quantity Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals INTERIOR FINISHES C3010 Wall Finishes C3012 Wall finishes to interior walls Paint to new and existing walls Ceramic tile at restrooms Acoustical wall treatments Wood wall panels, allow Fabric wrapped wall panels 1 2,331 1 1,500 504 LS SF LS SF SF 81,562.25 19.23 60,589.10 34.96 20.39 81,562 44,814 60,589 52,433 10,277 249,675 Total For Wall Finishes C3020 Floor Finishes C3024 Flooring including base Level 0 Carpet tile at music studio and corridor Rubber base Level 1 Floor finishes at multi purpose performance and green room Ceramic tile at public corridors and lobby Ceramic tile at restrooms Carpet tile at classrooms and study areas Walk off mat at vestibules Rubber base Ceramic tile base Level 2 Linoleum at smaller workrooms and copy rooms Ceramic tile at public corridors and lobby Ceramic tile at restrooms Carpet tile Walk off mat at vestibules Rubber base Ceramic tile base Level 3 Access flooring system Ceramic tile at restrooms Carpet tile Walk off mat at vestibules Rubber base Ceramic tile base 530 140 SF LF 4.89 2.62 2,594 367 4,015 6,011 466 8,383 340 2,210 165 SF SF SF SF SF LF LF 8.16 17.24 17.24 4.89 11.65 2.62 17.48 32,747 103,657 8,036 41,024 3,962 5,794 2,884 2,881 8,025 392 4,034 95 1,387 867 SF SF SF SF SF LF LF 8.04 17.24 17.24 4.89 11.65 2.62 17.48 23,162 138,388 6,760 19,741 1,107 3,636 15,153 8,185 523 20,050 70 2,116 149 SF SF SF SF LF LF 13.98 17.24 4.89 11.65 2.62 17.48 114,443 9,019 98,119 816 5,547 2,604 639,561 Total For Floor Finishes C3030 Ceiling Finishes C3031 Ceiling finishes Ceiling finishes, allow 58,177 Total For Ceiling Finishes SF 8.86 515,177 515,177 Page 10 Library Building Renovation Project 51 Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description D10 Quantity Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals CONVEYING D1010 Elevator & Lift D1011 Passenger elevators Upgrade existing elevator cab finish Upgrade elevator controls, allowance 1 1 EA LS 12,583.89 9,903.99 12,584 9,904 D1013 Lifts Wheelchair lift 1 EA 33,207.49 33,207 55,695 Total For Elevator & Lifts D20 PLUMBING D2010 Plumbing Fire sprinkler estimate completed by Hargis engineers dated November 23rd, 2015 Plumbing, waste and vent Plumbing, cold and hot water piping Plumbing, fixtures and water heaters Plumbing, insulation 58,177 58,177 58,177 58,177 SF SF SF SF 3.96 2.56 5.83 0.82 765,986 Total For Plumbing D30 HVAC D3010 HVAC HVAC estimate completed by Hargis engineers dated November 23rd, 2015 HVAC, General provisions HVAC,Hydronic chilled / heating piping HVAC, Ductwork and insulation HVAC, Built up HVAC units HVAC, Run around heat recovery loop HVAC, Rooftop air to water heat pump HVAC, Variable air volume units HVAC, Outlets, inlets, exhaust fans, etc. HVAC, Energy management system 58,177 58,177 58,177 75,630 75,630 152 64 58,177 58,177 SF SF SF CFM CFM Tons EA SF SF 3.50 8.39 7.92 12.12 3.96 1,398.21 1,631.25 1.63 8.62 203,359 488,062 460,947 916,472 299,616 212,528 104,400 94,901 501,619 3,281,904 Total For HVAC D40 230,474 149,130 338,932 47,450 FIRE PROTECTION D4010 Fire Protection Fire sprinkler estimate completed by Hargis engineers dated November 23rd, 2015 Fire sprinkler system Fire riser, backflow, FDC and dry system 82,600 1 Total For Fire Sprinkler System SF LS 4.66 69,910.50 384,974 69,911 454,884 Page 11 52 North Seattle College Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description D10 Quantity Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals CONVEYING D1010 Elevator & Lift D1011 Passenger elevators Upgrade existing elevator cab finish Upgrade elevator controls, allowance 1 1 EA LS 12,583.89 9,903.99 12,584 9,904 D1013 Lifts Wheelchair lift 1 EA 33,207.49 33,207 55,695 Total For Elevator & Lifts D20 PLUMBING D2010 Plumbing Fire sprinkler estimate completed by Hargis engineers dated November 23rd, 2015 Plumbing, waste and vent Plumbing, cold and hot water piping Plumbing, fixtures and water heaters Plumbing, insulation 58,177 58,177 58,177 58,177 SF SF SF SF 3.96 2.56 5.83 0.82 765,986 Total For Plumbing D30 HVAC D3010 HVAC HVAC estimate completed by Hargis engineers dated November 23rd, 2015 HVAC, General provisions HVAC,Hydronic chilled / heating piping HVAC, Ductwork and insulation HVAC, Built up HVAC units HVAC, Run around heat recovery loop HVAC, Rooftop air to water heat pump HVAC, Variable air volume units HVAC, Outlets, inlets, exhaust fans, etc. HVAC, Energy management system 58,177 58,177 58,177 75,630 75,630 152 64 58,177 58,177 SF SF SF CFM CFM Tons EA SF SF 3.50 8.39 7.92 12.12 3.96 1,398.21 1,631.25 1.63 8.62 203,359 488,062 460,947 916,472 299,616 212,528 104,400 94,901 501,619 3,281,904 Total For HVAC D40 230,474 149,130 338,932 47,450 FIRE PROTECTION D4010 Fire Protection Fire sprinkler estimate completed by Hargis engineers dated November 23rd, 2015 Fire sprinkler system Fire riser, backflow, FDC and dry system 82,600 1 Total For Fire Sprinkler System SF LS 4.66 69,910.50 384,974 69,911 454,884 Page 11 Library Building Renovation Project 53 Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description D50 Quantity Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals ELECTRICAL D5000 Electrical Electrical estimate completed by Hargis engineers dated November 23rd, 2015 Electrical selective demolition, see demolition section Building electrical (Division 26) Main electrical switchgear replacement Theater lighting allowance Theater lighting controls allowance Building telecommunications (Division 27) Building Audio Visual (Division 27) Theater Audio Visual system Allowance Building fire alarm (Division 28) Building electronic security (Division 28) 58,177 1 1 1 58,177 58,177 1 58,177 58,177 SF LS LS LS SF SF LS SF SF 33.21 151,472.75 116,517.50 34,955.25 6.99 9.32 87,388.13 3.03 2.33 3,583,072 Total For Electrical E10 EQUIPMENT E1010 Equipment E1094 Residential equipment Residential equipment, assumed not required N/A E1022 Library equipment Library equipment, assumed not required N/A E1023 Theater and stage equipment Assumed not required N/A E1025 Audio-visual equipment Projection screens, allow E20 N/A 1,931,912 151,473 116,518 34,955 406,718 542,291 87,388 176,245 135,573 FURNISHINGS E2010 Fixed Furnishing E2012 Fixed casework Level 1 casework Breakout bar countertop Casework at theater / control booth Miscellaneous casework, allow Restroom vanities Level 2 casework Casework at TLC lab Circulation reference desk Miscellaneous casework, allow Restroom vanities Level 3 casework Library book stacks 1 LS 29,129.38 29,129 29,129 Total For Equipment 144 1 1 18 LF LS LS LF 145.65 2,796.42 4,078.11 188.76 20,973 2,796 4,078 3,398 1 32 1 12 LS LF LS LF 8,389.26 448.59 4,078.11 188.76 8,389 14,355 4,078 2,265 910 LF 342.56 311,731 Page 12 54 North Seattle College Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description Quantity Countertop to open stair area Restroom vanities E2013 Blinds and other window treatments Window treatments, allow Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals 35 13 LF LF 104.87 188.76 3,670 2,454 1 LS 52,432.88 52,433 E2014 Fixed floor grilles and mats Walk off mats included in floor finish section of the estimate N/A 430,621 Total For Furniture F10 SPECIAL STRUCTURES F1010 Special Structure No work anticipated N/A Total For Special Structure F1020 Special Construction No work anticipated N/A Total For Special Construction F20 SELECTIVE BUILDING DEMOLITION F2010 Building Element Demolition F2011 Building interior demolition Remove and dispose architectural elements Level 0 Miscellaneous architectural elements Level 1 Interior partitions Interior doors, per leaf Interior finishes Miscellaneous architectural elements Level 2 Interior partitions Interior doors, per leaf Interior finishes Miscellaneous architectural elements Level 3 Interior partitions Interior doors, per leaf Interior finishes Miscellaneous architectural elements Electrical selective demolition Mechanical selective demolition 1 LS 1,631.25 1,631 1,366 29 20,517 20,517 LF EA SF SF 16.90 68.63 1.63 3.03 23,079 1,990 33,468 62,155 735 27 17,787 17,787 LF EA SF SF 12.58 68.63 1.63 1.75 9,249 1,853 29,015 31,087 953 32 22,137 22,137 57,000 57,000 LF EA SF SF SF SF 12.58 68.63 1.63 1.75 1.46 1.63 11,992 2,196 36,111 38,690 83,019 92,981 F2012 Building exterior demolition Remove and dispose Page 13 Library Building Renovation Project 55 Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Building DETAIL OF ESTIMATE Item Description Quantity Level 1 Exterior doors, per leaf Exterior cladding system including temporary works Level 2 Exterior doors, per leaf Exterior cladding system including temporary works Level 3 Exterior doors, per leaf Exterior cladding to create openings for new exterior doors at roof terrace area Exterior cladding system including temporary works Roof Remove roofing and structure to accommodate level 3 skylight including temporary protection F 2020 Hazardous Components Abatement Hazardous Components Abatement, allow Unit Gross Floor Area: 58,177 SF Date: November 26, 2015 Prepared By: AC Unit Cost Totals 6 4,802 EA SF 73.41 4.78 440 22,940 10 6,180 EA SF 73.41 4.78 734 29,523 6 EA 73.41 440 1 5,456 LS SF 908.84 4.78 909 26,064 320 SF 34.96 11,186 1 LS 209,731.50 209,732 Total For Selected Demolition 760,486 Page 14 56 North Seattle College Construction Cost Estimate North Seattle College Library Renovation PRR Estimate Enhancements Date: Item Description Quantity November 26, 2015 Prepared By: AC Unit Unit Cost Totals LS EA EA SF 10,740.00 11,150.00 140,000.00 27.00 Alternate 1: Replace Elevator Demolition of existing elevator Elevator pit and ladder New elevator Shaft walls / Cladding 1 1 1 4,212 275,614 Sub-Total Estimating / Design Contingency 11.50% 31,696 307,310 10.70% 32,882 340,192 4.50% 15,309 355,500 Sub-Total General Conditions Sub-Total GC Fee 10,740 11,150 140,000 113,724 Sub-Total Escalation, excluded N/A 355,500 Total Construction Cost Alternate 1: Alternate 2: Exterior lighting at building Exterior lighting 1 LS 40,000.00 40,000 Sub-Total Estimating / Design Contingency 11.50% 4,600 44,600 10.70% 4,772 49,372 4.50% 2,222 51,594 Sub-Total General Conditions Sub-Total GC Fee 40,000 Sub-Total Escalation, excluded N/A 51,594 Total Construction Cost Alternate 2: Alternate 3: Softscape enhancements at water feature Demolishing at water feature Topsoil at water feature. 1'-6" thick Softscape planting at water feature Irrigation system, complete 4,400 4,400 4,400 4,400 SF SF SF SF 11.50% Sub-Total 9,680 9,778 23,100 6,600 49,158 Sub-Total Estimating / Design Contingency 2.20 2.22 5.25 1.50 5,653 54,811 Library Building Renovation Project 57 Construction Cost Estimate General Conditions 10.70% 5,865 60,676 4.50% 2,730 63,406 Sub-Total GC Fee Sub-Total Escalation, excluded N/A 63,406 Total Construction Cost Alternate 3: Alternate 4: Level 3 roof terrace B3012 Traffic toppings and paving membranes Precast concrete paver system at level 2 roof for new level 3 roof terrace 3,090 SF 23.50 72,615 Waterproofing system at level 2 roof for new level 3 roof terrace Modifications to Level 2 roof to accommodate new terrace 3,090 3,090 SF SF 10.20 1.75 31,518 5,408 109,541 Sub-Total Estimating / Design Contingency 11.50% 12,597 122,138 10.70% 13,069 135,206 4.50% 6,084 141,291 Sub-Total General Conditions Sub-Total GC Fee Sub-Total Escalation, excluded N/A Total Construction Cost Alternate 3: 58 North Seattle College 141,291 DIAGRAMS & SKETCHES Library Building Renovation Project 59 60 North Seattle College Existing Campus Plan EXISTING CAMPUS PLAN 2 3 4 1 5 6 N 8 1. 2. 3. 4. Library Building Instructional Building Arts & Sciences Physical Education 5. 6. 7. 8. 7 Education Building Health Science & Student Resource Opportunity Center College Center Library Building Renovation Project 61 Building Area Takeoff Plan BUILDING AREA TAKEOFF PLAN DN UP UP DN DN UP 3 Level 3 GSF - 21,092 SF Facility Type: Library 2 Level 2 GSF - 15,990 SF Facility Type: Library UP UP UP UP DN ELEC VAULT (E) - N UP DN 1 62 Level 1 GSF - 19,995 SF Facility Type: Classroom North Seattle College 0 Level 0 GSF - 1,190 SF Facility Type: Classroom LEVEL 3 LEVEL 2 LEVEL 1 LEVEL 0 Building Plans BUILDING PLANS UP UP UP ELEC VAULT (E) - Dashed red lines indicate new load-bearing walls to support floor structure above. N 0 8 16 LEGEND MUSIC / REHEARSAL RESTROOMS E - LEARNING E-Learning INFORMAL LEARNING SPACE STUDENT MEDIA CENTER Student Media Center STUDY ROOMS LIBRARY / LIBRARY SUPPORT MUSIC / REHEARSAL Library / Library Support SEMINAR / CLASSROOM ING AND LEARNING CENTER MUSIC / REHEARSAL RESTROOMS Music / Rehearsal ING AND LEARNING CENTER RNING RESTROOMS INFORMAL LEARNING SPACE Restrooms RNING NT MEDIA CENTER INFORMAL LEARNING SPACE STUDY ROOMS Study Rooms NT/ MEDIA CENTER RY LIBRARY SUPPORT STUDY ROOMS SEMINAR / CLASSROOM Seminar / Classroom RY / LIBRARY SUPPORT SEMINAR / CLASSROOM 32' TEACHING AND CENTER Teaching andLEARNING Learning Center Level 0 Plan Note: Facility Type Construction = Classrooms (1,190 GSF) 1 LEVEL 0 PLAN 1/32"=1' NOTE: FACILITY TYPE CONSTRUCTION = CLASSROOMS (1,100 GSF) Library Building Renovation Project 63 Building Plans N LEGEND MUSIC / REHEARSAL TEACHING AND CENTER Teaching andLEARNING Learning Center RESTROOMS E - LEARNING E-Learning INFORMAL LEARNING SPACE STUDENT MEDIA CENTER Student Media Center STUDY ROOMS LIBRARY / LIBRARY SUPPORT MUSIC / REHEARSAL Library / Library Support SEMINAR / CLASSROOM ING AND LEARNING CENTER MUSIC / REHEARSAL RESTROOMS Music / Rehearsal ING AND LEARNING CENTER RNING RESTROOMS INFORMAL LEARNING SPACE Restrooms RNING NT MEDIA CENTER INFORMAL LEARNING SPACE STUDY ROOMS Study Rooms NT CENTER Y / MEDIA LIBRARY SUPPORT STUDY ROOMS SEMINAR / CLASSROOM Seminar / Classroom Y / LIBRARY SUPPORT SEMINAR / CLASSROOM Level 1 Plan Note: Facility Type Construction = Classrooms (19,995 GSF) 1 LEVEL 0 PLAN 1/32"=1' 64 North College = CLASSROOMS (1,100 GSF) NOTE: FACILITY TYPE Seattle CONSTRUCTION Building Plans DN UP UP DN UP 0 8 32' LEGEND 16 N MUSIC / REHEARSAL TEACHING AND CENTER Teaching andLEARNING Learning Center RESTROOMS E - LEARNING E-Learning INFORMAL LEARNING SPACE STUDENT MEDIA CENTER Student Media Center STUDY ROOMS LIBRARY / LIBRARY SUPPORT MUSIC / REHEARSAL Library / Library Support SEMINAR / CLASSROOM ING AND LEARNING CENTER MUSIC / REHEARSAL RESTROOMS Music / Rehearsal ING AND LEARNING CENTER RNING RESTROOMS INFORMAL LEARNING SPACE Restrooms RNING NT MEDIA CENTER INFORMAL LEARNING SPACE STUDY ROOMS Study Rooms NT/ MEDIA CENTER RY LIBRARY SUPPORT STUDY ROOMS SEMINAR / CLASSROOM Seminar / Classroom RY / LIBRARY SUPPORT SEMINAR / CLASSROOM Level 2 Plan Note: Facility Type Construction = Library (15,990 GSF) 1 LEVEL 0 PLAN 1/32"=1' NOTE: FACILITY TYPE CONSTRUCTION = CLASSROOMS (1,100 GSF) Library Building Renovation Project 65 Building Plans DN 0 8 16 LEGEND 32' N MUSIC / REHEARSAL TEACHING AND CENTER Teaching andLEARNING Learning Center RESTROOMS E - LEARNING E-Learning INFORMAL LEARNING SPACE STUDENT MEDIA CENTER Student Media Center STUDY ROOMS LIBRARY / LIBRARY SUPPORT MUSIC / REHEARSAL Library / Library Support SEMINAR / CLASSROOM ING AND LEARNING CENTER MUSIC / REHEARSAL RESTROOMS Music / Rehearsal ING AND LEARNING CENTER RNING RESTROOMS INFORMAL LEARNING SPACE Restrooms RNING NT MEDIA CENTER INFORMAL LEARNING SPACE STUDY ROOMS Study Rooms NT CENTER Y / MEDIA LIBRARY SUPPORT STUDY ROOMS SEMINAR / CLASSROOM Seminar / Classroom Y / LIBRARY SUPPORT SEMINAR / CLASSROOM Level 3 Plan Note: Facility Type Construction = Library (21,092 GSF) 1 LEVEL 0 PLAN 1/32"=1' 66 North College = CLASSROOMS (1,100 GSF) NOTE: FACILITY TYPE Seattle CONSTRUCTION Building Sections BUILDING SECTIONS 1 N/S SECTION 1/64"=1' 1 N/S SECTION North-South 1/64"=1' 0 10 20 40' 0 10 20 40' 0 10 20 40' 0 10 20 40' Section East-West Section 2 E/W SECTION 1/64"=1' 2 E/W SECTION 1/64"=1' Library Building Renovation Project 67 68 North Seattle College APPENDIX Library Building Renovation Project 69 70 North Seattle College Design Team Conditions Analysis (Engineer’s Reports) DESIGN TEAM CONDITIONS ANALYSIS (ENGINEER’S REPORTS) November 20, 2015 Jay A. Taylor, P.E., S.E. Senior Principal Mr. Eric Aman Schacht Aslani Architects 901 Fifth Avenue, Suite 2720 Seattle, WA 98164 Subject: Library Building Renewal, North Seattle College Seattle, Washington Re: Structural Needs Analysis Dear Mr. Aman: As part of North Seattle College’s implementation of their Master Plan, the existing Library building is slated for renovation and renewal. The scope of the proposed renovation includes but is not limited to the following: Infill the raked seating at the existing Theatre and two Medium Lecture Rooms to add square footage at the First Floor Level for new Classrooms Repurpose the existing Musical Performance Room to be a new multi-purpose “black box” theater (mostly non-structural modifications) Demolish significant portions of the existing, east and west perimeter concrete walls at the First Floor Level and infill with a new curtain wall system Demolish non-structural partitions and re-organize the Second and Third Floor Levels to create new Offices, Meeting and Study Rooms, and an open Reading Room, including relocating and consolidating the book stacks at the north end of the Third Floor Provide new mechanical equipment penetrations through the existing Third Floor Level Mechanical Mezzanine concrete slab Provide new skylight openings in the roof above the Third Floor Reading Room The existing Library Building (identified as the Instructional Resources Center in the original 1968 construction drawings by Edward Mahlum & Associates, Architects) is a three-story, concrete-framed structure supported on continuous and isolated spread footings. A seismic assessment completed in 2007 by Magnusson Klemencic Associates (included in the Appendix) found that this building is seismically deficient. Because the proposed renovation will substantially extend the useful life of the building, the City of Seattle Department of Planning and Development will require that the structure be upgraded to meet current seismic performance level objectives. Library Building Renovation Project 71 Design Team Conditions Analysis (Engineer’s Reports) Mr. Eric Aman November 20, 2015 Page 2 The anticipated structural scope of work required to address the identified seismic deficiencies and renovation scope noted above are as follows: 72 Northern Portion of Building - Seismic Strengthening: — Eliminate the two seismic joints at the four-story, north portion of the building by mechanically tying the concrete slabs together across the joint. — Widen the southernmost seismic joint from 1 to 4 inches to keep the shorter, two-story south wing of the building separate. — Add four approximately 30-foot-long by 12-inch-thick concrete shear walls or six steel braced frames oriented in the north-south direction at the Second and Third Floor Levels. The walls or braced frames should tie into the existing concrete “H” columns. — Add three approximately 30-foot-long by 12-inch-thick concrete shear walls or four steel braced frames oriented in the east-west direction at the Second and Third Floor Levels. The walls or braced frames should tie into the existing concrete “H” columns. — Retain and strengthen four approximately 30-foot-long bays of existing perimeter concrete shear walls in the north-south direction at the First Floor Level or replace the demolished concrete walls with six steel braced frames. — Retain and strengthen four approximately 30-foot-long bays of existing concrete shear walls in the east-west direction at the First Floor Level or add six new steel braced frames. — Tie new concrete shear walls or steel braced frames — Provide new foundations at all added concrete shear walls or steel braced frames. Foundations would likely utilize micropiles to minimize foundation excavation and footing sizes. — Add new steel collector elements to tie existing floors to new concrete shear walls or steel braced frames. Northern Portion of Building – Renovation — Infill the raked seating at the existing Theater and two Medium Lecture Rooms with steel stud bearing walls spaced at 4 foot-on-center and a composite concrete slab on metal deck at the First Floor Level. — Reinforce the new mechanical equipment penetrations through the existing Third Floor Level Mechanical Mezzanine concrete slab with new steel framing. — Remove the existing concrete roof slab but retain the existing concrete roof joists at the new skylight openings in the roof above the Third Floor Reading Room. — Reinforce the existing Third Floor to support the code-required increased floor loading at the relocated book stacks with new steel framing. Southern Portion of Building - Seismic Strengthening — Widen the southernmost seismic joint from 1 to 4 inches to keep the shorter two-story, south wing of the building separate from the north wing. — Utilize the existing perimeter concrete walls by strengthening connections to the existing concrete floor slabs and columns. — Add new approximately 30-foot-long by 12-inch-thick concrete wall oriented in the east-west direction extending from Level 0 to Level 2 adjacent and parallel to the expanded seismic joint. — Provide new foundations under the new shear wall. Foundations would likely utilize micropiles to minimize foundation excavation and footing sizes. North Seattle College Design Team Conditions Analysis (Engineer’s Reports) Mr. Eric Aman November 20, 2015 Page 3 Southern Portion of Building – Renovation — Repurpose the existing Musical Performance Room to be a new multi-purpose “black box” theater (mostly non-structural modifications) Thank you for the opportunity to assist with the structural assessment of the North Seattle College Library project. Sincerely, Magnusson Klemencic Associates, Inc. Jay Taylor jtaylor@mka.com JAT/ls L:\NSCCSeis\corresp\Aman_NSCLibraryStructuralAnalysis_2015-11-20_final.docx Library Building Renovation Project 73 Design Team Conditions Analysis (Engineer’s Reports) SEISMIC ASSESSMENT North Seattle Community College Seattle, Washington April 4, 2007 Structural + Civil Engineers 1301 Fifth Avenue, Suite 3200 Seattle, Washington 98101-2699 T: 206 292 1200 F: 206 292 1201 74 North Seattle College Design Team Conditions Analysis (Engineer’s Reports) I N T R O D UC T I O N This report provides an assessment of the expected seismic performance of the main buildings on the North Seattle Community College (NSCC) campus. It includes an evaluation of the seismic-loadresisting ability of the lateral system, identifies potential deficiencies, and contains recommendations for seismic upgrades. SCOPE OF ASSESSMENT The assessment is based on visual observation of the building, a review of the available construction drawings, and limited structural calculations. The assessment is primarily concerned with the expected performance of structural elements. Nonstructural elements are only addressed if they pose significant life-safety hazards, such as blocking a primary means of egress. The seismic evaluation is based on the American Society of Civil Engineers standard Seismic Evaluation of Existing Buildings (ASCE 31). The evaluation is based on a Life Safety performance level (as defined by ASCE 31), which is consistent with common practice for buildings of this construction type and occupancy. The recommendations for seismic upgrades, where warranted, are based on the ASCE standard Seismic Rehabilitation of Existing Buildings (ASCE 41). The criteria and methodology for the seismic evaluation and rehabilitation are discussed in greater detail in a subsequent section. B UI L D I N G D E S C R I P T IO N S This seismic assessment focuses on the five main buildings that form the heart of the campus. These buildings are listed in the table below. Since the building names have changed somewhat from the original construction drawings, this table also includes a cross reference to the original building name. Table 1. NSCC Campus Buildings Abbreviation Building Name Name on Original Drawings CC College Center College Community Center LB Library Building Instructional Resources Center IB Instructional Building West Classroom Wing AS Arts and Science Building Science TB Technology Building Electronics All five buildings are documented in a single set of construction drawings by Edward Mahlum & Associates, Architects, dated September 1968. The structural design was based on the 1967 Uniform Building Code. The buildings have similar structural systems consisting of concrete floors and roofs supported by concrete columns on spread footings or pile foundations. The floor and roof systems consist of post-tensioned slabs and joists spanning between post-tensioned girders on the column lines. Seismic Assessment 1 North Seattle Community College, Seattle, Washington Library Building Renovation Project 75 Design Team Conditions Analysis (Engineer’s Reports) The buildings are architecturally interconnected by a series of bridge and tunnel structures, but these structures typically are seismically separated from one of the adjacent main buildings. Each main building also has exterior stair and mechanical tower structures that are structurally connected to the building. The typical floor and roof framing consist of a 4-1/2-inch-thick, post-tensioned slab and 30-inch-deep post-tensioned joists at 5 feet on center. The joists span to post-tensioned girders at the column lines. The columns are cast-in-place concrete with various configurations. The major columns are often U- or H-shaped, though some are box columns, others are double rectangles, and some minor columns are standard square-shaped columns. The column detailing at the floor level is somewhat unusual, consisting of a sliding joint located just below the underside of the girder. There is a positive interconnection between the column section above and below this sliding joint, which appears to be related to the construction sequencing of the post-tensioned floor system. The lateral system appears to consist primarily of the large U- and H-shaped columns (typically about 5 feet by 5 feet in plan dimension) acting as slender shear walls. Some buildings have concrete shear walls at some floors, and the concrete walls at the stairs and mechanical towers provide additional lateral resistance. The concrete floor and roof slabs act as structural diaphragms to deliver lateral forces into the walls and wall-columns, which in turn transfer the forces down to the foundation elements. COLLEGE CENTER The College Center (CC) building consists of two primary wings, a three-story plus basement east wing and a two-story plus basement west wing. The plan dimensions are approximately 320 feet by 90 feet at the east wing and 180 feet by 150 feet at the west wing. The structural system is the typical system of the campus buildings, and the foundation consists of spread footings. Seismic joints separate the west wing from the east wing, and two additional seismic joints divide the east wing into three similar-sized separate portions. LIBRARY BUILDING The Library Building (LB) has three stories plus a basement and measures approximately 310 feet by 120 feet in plan. The building is cascading in height, with the north-end roof at the third-floor level and the south-end roof at the second-floor level. The structural system is the typical system of the campus buildings, and the foundation consists of spread footings. Seismic joints divide the building into four similar-sized portions. INSTRUCTIONAL BUILDING The Instructional Building (IB) has three stories plus a basement and measures approximately 470 feet by 90 feet in plan. The structural system is the typical system of the campus buildings, with single-span joints spanning between exterior girder and column lines. The foundation consists of concrete-filled steel pipe piles with concrete pile caps. Seismic joints divide the building into five similar-sized portions. Seismic Assessment 2 North Seattle Community College, Seattle, Washington 76 North Seattle College Design Team Conditions Analysis (Engineer’s Reports) ARTS AND SCIENCE BUILDING The Arts and Science Building (AS) has one story plus a full basement and measures approximately 310 feet by 125 feet in plan. The structural system is the typical system of the campus buildings, with double-span joints spanning between exterior and interior girder and column lines. The foundation consists of concrete-filled steel pipe piles with concrete pile caps. Seismic joints divide the building into three similar-sized portions. TECHNOLOGIES BUILDING The Technologies Building (TB) has one story plus a full basement and measures approximately 290 feet by 125 feet in plan. The structural system is the typical system of the campus buildings, with doublespan joints spanning between exterior and interior girder and column lines. The foundation consists of concrete-filled steel pipe piles with concrete pile caps. Seismic joints divide the building into three similar-sized portions. S T R U C T UR A L C O N D I T IO N Minor cracking and spalling is typical at the exposed exterior of all the buildings; however, the buildings are generally in good condition. Minor cracking was noted at isolated locations at elevated walkway beams. Minor cracking or concrete staining is typical at the elevated walkway metal handrail connections as well as at precast panel connections between the precast panel handrails and the elevated walkway perimeter concrete beams. Minor cracking of the beams was noted in isolated locations in the garage. This cracking appears to be at locations where there is plaza area above. Maintenance reported excessive cracking in the garage beams below the kitchen of the College Center building. At the time of MKA's review, the beams have been repaired and a concrete pilaster installed at the retaining wall to provide additional support to the cracked beams. The repaired beams are in good condition, and no further deterioration has occurred. The post-tension anchors are concealed in slab pour-back strips per the historic drawings. They are not visible; however, the slabs do not show any indication of corrosion or spalling in the vicinity of the anchors, and the anchors are assumed to be in good condition. S E I S M I C E V A L UA T I O N INTRODUCTION TO THE SEISMIC EVALUATION The design of new buildings in Seattle typically is governed by the International Building Code (IBC). However, this code is neither intended for the evaluation of existing buildings nor is it typically appropriate for that use. Codes for new buildings, including the IBC, contain three basic types of requirements: strength, stiffness, and detailing. The strength and stiffness requirements are easily transferred to the evaluation of existing buildings, but the detailing provisions are not. The detailing requirements (for example, the proportioning of structural members and connections) in the IBC are in place to ensure that the systems that provide the building's strength and stiffness perform as intended. These requirements have been significantly revised throughout the code update cycles as the knowledge Seismic Assessment 3 North Seattle Community College, Seattle, Washington Library Building Renovation Project 77 Design Team Conditions Analysis (Engineer’s Reports) base of building performance has increased, either through observations from earthquakes or as a result of various research programs. Since the strength and stiffness of an existing building cannot be adequately addressed without assurances of proper detailing, guidelines have been developed specifically for the seismic evaluation of existing buildings. Evalu ation Gu idelin es The basis of the seismic evaluation is the American Society of Civil Engineers (ASCE) Standard 31-03, Seismic Evaluation of Existing Buildings, commonly referred to as ASCE 31. This document represents the most current practice for seismic evaluations, using a performance-based methodology. The purpose of ASCE 31 is to provide guidance in the review of an existing building's response to a predetermined level of earthquake based on a selected performance level. The ASCE 31 methodology consists of three phases, or tiers. The first phase is used to screen for any potential deficiencies in the lateral-load-resisting system. Potential deficiencies are then examined in more detail during the second phase, and if necessary, a rigorous, full-building evaluation can be performed as a third phase. The first phase, Tier 1, is a screening phase utilizing a series of checklists designed to identify potential flaws and weaknesses common to specific building types. Each checklist is a collection of evaluation statements describing building characteristics that are considered to be necessary to achieve the desired performance level. The second phase, Tier 2, is a further evaluation of the deficiencies identified during the Tier 1 evaluation. This analysis is typically performed on just those elements that were identified as being noncompliant with the Tier 1 acceptance criteria. ASCE 31 contains a Tier 3 phase, which involves performing a very detailed seismic evaluation of the building. This detailed analysis is beyond the scope of the current assessment program. ASCE 31 is intended to identify seismic deficiencies that may require mitigation. Although a seismic upgrade design is not included in the scope of this assessment, conceptual upgrade recommendations will be provided for any identified deficiencies. However, the design of the seismic upgrade is beyond the scope of the ASCE 31 standard. Where they are warranted, the conceptual upgrade approaches will be based on ASCE 41. ASCE 41 provides design requirements for new elements within an existing building and includes provisions that are intended to ensure adequate performance of the existing elements that are relied upon to provide lateral resistance or to support gravity loads. This standard provides a rational method for combining the strength and stiffness of new and existing elements within the strengthened building and includes provisions for the interconnection of these elements to form a complete and adequate lateral load path. It should be noted that ASCE 41 might require a greater scope of rehabilitation than that identified in the prior ASCE 31 evaluation. As stated in FEMA 35, Section C1.3, "ASCE 31 is specifically intended to accept somewhat greater levels of damage within each performance level than permitted by this standard, which is consistent with the historic practice of evaluating existing buildings for slightly lower criteria than those used for design of new buildings." In other words, once the decision has been made to seismically rehabilitate a building, the standard of care increases. Seismic Assessment 4 North Seattle Community College, Seattle, Washington 78 North Seattle College Design Team Conditions Analysis (Engineer’s Reports) Seismic Performan ce Objectives In traditional and current codes for new buildings, seismic performance is considered implicitly. Specified seismic force levels are used to provide adequate strength and stiffness based on implicit performance objectives, and prescriptive detailing requirements are used to provide a high degree of confidence that these performance objectives will be achieved. As indicated previously, this method is not applicable for existing buildings because the level of seismic detailing cannot be controlled in most cases. For this reason, the current seismic evaluation and rehabilitation guidelines are based on explicit performance objectives; such an approach is also known as "performance-based design." A specific seismic performance objective consists of two parts: a performance level and a seismic hazard (magnitude or frequency of earthquake). The seismic evaluation of the NSCC campus is based on the ASCE 31 Life Safety performance criteria for the seismic hazard level specified by ASCE 31. The design-level seismic hazard is taken as twothirds of the maximum considered earthquake (MCE). The MCE represents an earthquake with an average recurrence interval of approximately 2,500 years. A similar approach would be used for a seismic rehabilitation in accordance with ASCE 41. A building that achieves the Life Safety requirements of ASCE 31/ASCE 41 for this design-level seismic hazard is considered to provide a degree of protection against life-threatening injury resulting from a major earthquake that is roughly similar to that of a building conforming to the current building code, although with somewhat less reliability. Moreover, the subject building, like most buildings of this vintage, lacks the detailing that would serve to reduce the expected level of damage in smaller, more frequent earthquakes. Therefore, even if the building achieves a Life Safety performance level, it would be expected to provide less protection against economic loss (both direct and indirect resulting from temporary loss of use) than a new building. Since this type of performance-based design falls beyond the scope of the building code, it will be important to confirm building department acceptance of the performance objectives and design methodologies early in the design process. Based on our experience with similar buildings, the proposed criteria should be acceptable to the City of Seattle. We will propose to meet with the building department to present the stated seismic performance objectives, the proposed methodologies, and the findings of this report in order to obtain "preapproval" of the evaluation/rehabilitation concepts to be used for the renovation design. It should be noted that this seismic performance objective is consistent with the Seattle Building Code seismic requirements for buildings undergoing "Substantial Alterations." Seismic Hazard D etermin ation The seismic hazard in the Puget Sound region is governed by three types of events: (1) somewhat frequent, deep events below Puget Sound (similar in nature to but larger in magnitude than the events of the last century); (2) rare, deep events in the Cascadia Subduction Zone in coastal Washington and Oregon (last major event was in the year 1700); and (3) very rare, shallow crustal faulting in the local region (last major event was around the year 900). All of these events contribute to the probabilistic seismic hazard determination in the Seattle area, but the seismicity tends to be dominated by the close, shallow events. Seismic Assessment 5 North Seattle Community College, Seattle, Washington Library Building Renovation Project 79 Design Team Conditions Analysis (Engineer’s Reports) For a specified earthquake frequency, the level of ground shaking is related to the location of the building site as well as the type of soils at the site. The seismic response parameters for the NSCC campus are based on United States Geological Survey mapping using the site location of 47.699°N, 122.335°W. The site soils are assumed to conform to Site Class D. Table 2. Design Ground Motion Parameters Design Ground Motion Parameter Value Short-period spectral response acceleration parameter (SDS) 0.828 Spectral response acceleration parameter at a one-second period (SD1) 0.447 SUMMARY OF FINDINGS The five main buildings on the NSCC campus were designed and constructed prior to the adoption of modern seismic codes. There have been no global seismic improvement projects at these buildings. Although the buildings possess a complete seismic-force-resisting system, the system lacks adequate lateral strength to achieve the seismic performance objective of ASCE 31. We have performed an ASCE 31 Tier 1 evaluation on each of the buildings and partial Tier 2 evaluations on two buildings. A representative summary of the results follows: Sh ear Walls The existing concrete shear walls lack adequate capacity to resist the specified seismic loading. The shear stress in the walls exceeds the Tier 1 evaluation limit of 100 psi by a significant margin, especially at the three-story buildings. This indicates that the buildings do not possess an adequate amount of concrete shear walls to resist seismic loading effectively. For the CC, LB, and IB, the level of shear wall overstress determined in the Tier 1 calculations is such that a Tier 2 analysis would not result in a different conclusion. However, for the AS and TB, which have only one above-grade floor, a more detailed Tier 2 analysis of the existing shear walls indicates that the shear walls themselves could have adequate capacity. Nevertheless, these buildings have deficiencies associated with the shear wall detailing (sliding joints as discussed below) and with narrow seismic joints, such that even though the shear walls appear to have adequate capacity, some seismic rehabilitation work is required to achieve the specified seismic performance objective. Adjacen t Bu ildin gs The existing 1-inch seismic joints within and among the buildings and adjacent structures are too small, in particular at the upper floors of the three-story buildings. Seismic joints that are too small to accommodate the expected lateral displacements can result in "pounding" from the adjacent structures in a seismic event. Seismic Assessment 6 North Seattle Community College, Seattle, Washington 80 North Seattle College Design Team Conditions Analysis (Engineer’s Reports) Structural Irregularities It appears that some of the buildings (for example, the LB) have solid exterior concrete walls at some floors instead of the typical wall-columns. These walls, whether intended to act as shear walls or not, will act like shear walls and will cause those floors with these walls to be substantially more rigid than the floors without the solid walls. This condition could lead to adverse overall seismic performance during an earthquake. D eformation Compatibility At some of the buildings (for example, the LB), there are exterior precast concrete walls. It is possible that these walls were not detailed in such a manner that the connections could accommodate the expected lateral deflection of the buildings. The concern is damage to the precast concrete wall connections and potential falling hazards. Concrete Sh ear Wall Connections As indicated above, the typical shear walls have an unusual sliding joint connection at each floor. This joint impacts the continuity of the walls and could serve to further weaken an already deficient lateral system. R E C O M M E N D A T IO N S FO R S E I S M I C R E H A B I L I T A T I O N In order to mitigate these deficiencies and improve the building performance level to a Life Safety seismic performance objective, seismic upgrades will be required at these buildings. The specific seismic upgrade program would need to be developed during a subsequent phase, taking into account program impacts and design coordination. However, for the purposes of this report, the basic elements of a seismic rehabilitation program are provided in this section. The recommended seismic upgrade elements for each of the five buildings are similar in nature, consisting of added reinforced concrete shear walls and associated foundation and collector elements. The specific requirements for each building are discussed below, but the following section provides a general description of the seismic upgrade elements. GENERAL SEISMIC UPGRADE ELEMENTS Concrete Sh ear Walls Adding concrete shear walls will mitigate the deficiencies associated with the lack of adequate lateral strength and stiffness. In addition, by reducing the seismic loads on the existing shear walls, the potential deficiency due to a lack of continuity at the sliding joint is also effectively mitigated. Utilizing concrete shear walls for the seismic upgrade is the preferred solution based on compatibility with the existing concrete structures. For each building, we have indicated the approximate number of 30-foot-long by 12-inch-thick concrete shear walls based on a limited structural analysis. The 30-foot length is a reasonable minimum length that will allow some wall penetrations and minimize the amount of foundation work. The locations of the walls would need to be coordinated with the current or future Seismic Assessment 7 North Seattle Community College, Seattle, Washington Library Building Renovation Project 81 Design Team Conditions Analysis (Engineer’s Reports) programmed space of the buildings. The walls are assumed to be continuous from the basement to the roof, but it is possible that the wall length or thickness could be reduced at the upper floors. This level of refinement is beyond the scope of an evaluation report. To minimize the foundation work and to take advantage of the existing basement walls, it will be beneficial to align the new shear walls over the existing basement walls and to run the walls continuous between the existing wall/columns. This is the case, in particular, for the walls in the north-south direction where the column grid is typically 30 feet. Since the column spacing typically exceeds 30 feet in the east-west direction, we recommend that the walls be located in line with the existing column grid and that at least one end of each shear wall is connected to an existing wall/column. Foundations The new concrete shear walls will require new or strengthened foundations. As noted above, if the new walls align with the existing basement walls, this strengthening could be minimized or even eliminated depending largely on the final layout of the shear walls. For the purposes of this report, we assume that the new foundations at shear walls would match the existing foundation system at each building—that is, the new shear walls would be on spread footings at buildings with existing spread footings and would be on piles at buildings with existing pile foundations. We assume that micropiles will be the preferred option based on the limited overhead clearances within the existing basements. A geotechnical study will be required to evaluate pile options prior to the design of the upgrades. Where the shear walls do not run continuous between the existing columns at buildings with spread footings, it may be advantageous to provide micropiles at these foundations in order supplement the overturning resistance provided by the weight of the wall and footing themselves. Collectors The new concrete shear walls require collector elements at the connection between the walls and the existing floor and roof diaphragms. Based on the construction type, we recommend reinforced concrete collectors cast in-between existing joists. Based on limited analysis, we assume that each new concrete shear wall would require a 30-foot-long collector at the roof and all floor levels. The required collector length could be reduced by utilizing the existing girders located at the north-south column lines. Seismic Join ts As discussed in more detail below, we recommend either increasing the size of the existing seismic joints or closing the joints to interconnect the adjacent portions of the buildings. This upgrade is required since the joints are too narrow to protect against damaging contact due to pounding of adjacent structures. We recommend infilling several joints in order to minimize the number of new shear walls that are required. The existing seismic joint spacing is fairly close together, and this results in the buildings being divided into a relatively high number of independent structures. Since each independent structure would require a minimum of three new shear walls for lateral stability, the total number of added shear walls can be significantly greater than the minimum number of walls required for lateral strength. Therefore, we recommend infilling some of the joints. The joints are typically located in mild-reinforced pour strips, and thus connecting the two structures across the joints could be accomplished relatively easily by infilling with reinforced concrete or utilizing structural steel straps that are epoxy-bonded to the existing concrete slabs. Seismic Assessment 8 North Seattle Community College, Seattle, Washington 82 North Seattle College Design Team Conditions Analysis (Engineer’s Reports) SPECIFIC SEISMIC REHABILITATION RECOMMENDATIONS This section provides specific recommendations for each of the five subject buildings. College Center For the purposes of this seismic study, we have divided the building into two separate wings: the east and west wings as described previously. The three-story east wing is divided into three portions by means of two seismic joints located approximately at one-third points along the 320-foot-long direction of the building. To mitigate the deficiency associated with the insufficient joint width and to minimize the number of shear walls added, we recommend eliminating both seismic joints in this wing at all floors. For a single continuous structure at this wing, the recommended seismic upgrade involves adding four 30-foot-long by 12-inch-thick concrete shear walls in each of the building's primary axes, for a total added wall length of 240 feet. The two-story west wing has no internal seismic joints. The recommended upgrade of this portion of the building involves adding two 30-foot-long concrete shear walls in each main direction, essentially one wall on each of the four sides of the building. The shear walls in both portions of the building would require new spread footing foundations. Collector elements to transfer seismic loads from the existing structure to the shear walls also would be required. Finally, we recommend enlarging the seismic joint between the two buildings to at least 4 inches at all floors. Library Building For the Library Building, we recommend eliminating the two seismic joints at the three-story north portion of the building, while maintaining and enlarging the southernmost seismic joint to keep the shorter wing of this building separate. The added shear walls will eliminate the stiffness and strength discontinuity above the first floor and will increase the lateral stiffness of the building in order to reduce the potential for failures of the precast concrete panel connections. For a single continuous northern portion of this building, the recommended seismic upgrade involves adding four 30-foot-long by 12-inch-thick concrete shear walls in each of the building's primary axes, for a total added wall length of 240 feet. In addition, if the walls in the north-south orientation could align with the existing walls along the perimeter of the first floor, this would minimize the improvements required at this floor as well as minimize the foundation work. The seismic rehabilitation of the south wing would required three to four new shear walls that likely could be limited to 20 feet in length given the relatively small size of this structure. Ideally, the new walls would be located in line with the existing concrete walls at the first floor. Seismic Assessment 9 North Seattle Community College, Seattle, Washington Library Building Renovation Project 83 Design Team Conditions Analysis (Engineer’s Reports) The shear walls in both portions of the building would require new spread footing foundations. Collector elements to transfer seismic loads from the existing structure to the shear walls also would be required. Finally, we recommend enlarging the seismic joint between the two buildings to at least 4 inches at the second-floor level. I n stru ction al Bu ildin g The Instructional Building has four existing seismic joints, dividing the building into five portions. As part of the seismic upgrade, we recommend removing two or three of the joints and enlarging the remainder of the joints. This would result in two or three separate structures and will minimize the amount of new shear walls required. Assuming that three joints are infilled and there are two separate buildings, the seismic upgrade will require approximately five 30-foot-long shear walls in each direction for a total added wall length of 300 feet, distributed somewhat uniformly in both portions of the building. The shear walls in both portions of the building would require new or strengthened pile foundations. Collector elements to transfer seismic loads from the existing structure to the shear walls also would be required. Finally, we recommend enlarging the seismic joints that remain to at least 4 inches at all floors. Arts an d Scien ce Bu ildin g Since the Arts and Science Building has only one story above grade, the seismic demand on the firstfloor shear walls is substantially less than that for the multi-story buildings. Mitigation of the identified seismic deficiencies could involve one of two possible options for upgrade: New Concrete Sh ear Walls The first option is to add concrete shear walls similar to the other buildings. In conjunction with the shear walls, we would recommend eliminating both of the two existing seismic joints in order to combine the portions into one continuous structure. As indicated above, this will substantially reduce the amount of new shear walls that are required. Once the building is tied together, we estimate that two 30-foot-long by 12-inch-thick shear walls would be required in each direction, for a total added wall length of 120 feet. The shear walls would require new or enhanced foundations likely consisting of micropiles and would require new collector elements at the first floor and roof to transfer loading from the existing structure to the shear walls. The seismic joints would be tied together in a similar manner as for the other buildings described above. Seismic Assessment 10 North Seattle Community College, Seattle, Washington 84 North Seattle College Design Team Conditions Analysis (Engineer’s Reports) Existing Sh ear Wall Enhancemen ts Our more detailed, Tier 2 evaluation indicates that the existing shear walls are not significantly overstressed and that the seismic deficiencies could be mitigated by using localized improvements to the existing elements rather than adding new shear walls. This seismic rehabilitation program would involve the following elements: Eliminate the existing seismic joints at the floor and roof (two per building per floor) Eliminate the seismic joint in the shear walls from the basement to roof (four walls per building) Strengthen the existing sliding joint in the shear walls just below the first floor (20 walls per building) Improve the collectors at the roof and floor level With the improvements described above, the existing shear walls have adequate capacity to meet the seismic performance objective, and new shear walls are not required. This option has potentially less overall structural scope (especially when considering that foundation work is not required), but the work is distributed throughout the building rather than located at discrete shear wall locations. Tech n ologies Bu ildin g The Technologies Building is very similar to the Arts and Sciences Building. Refer to the description of the two upgrade options in the previous section. Seismic Assessment 11 North Seattle Community College, Seattle, Washington Library Building Renovation Project 85 Design Team Conditions Analysis (Engineer’s Reports) MECHANICAL NARRATIVE Information Resource A. Existing record drawings, provided by NSC B. Field investigation performed November 6th, 2015. C. Various existing drawings of the facility from NSC. General Overview The existing Library Building at North Seattle College is a late 60’s/early 70’s vintage building with various program spaces including a library, lecture halls and theater spaces. In general, the overall mechanical systems appear to be in fair condition, but at 40+ years old, many of the systems are at or near the end of their economic and useful life. The proposed mechanical systems use the existing locations for routing of all new ductwork, piping and energy management system infrastructure. The HVAC equipment will be modified in the same location and upgraded with all new dampers, heating/cooling coils and a fan array. The central plant system will be completely new to maximize the efficiency of existing electrical heating infrastructure. A run around refrigerant heat recovery system will be used to increase the efficiency on the ventilation component of the system. Description of the Existing Mechanical Systems HVAC System 1. Supply/Ventilation Air and HVAC Equipment: The supply air is provided from built‐up HVAC equipment located at the West side of the building. Large louvers centralize the equipment into four main units. There are two units dedicated for floors 0 and 1 and another two units for floors 2 and 3. This arrangement mitigates the requirements for fire/smoke dampers or fire dampers. The built‐up air handlers allow for full recirculation and full airside economizer. The built‐up units do not contain any heating coils ore electric heat. There are chilled water coils located in the HVAC units that come with eliminators and cooling coils. The supply and return/exhaust fans are from the original construction. The ductwork distribution is routed through a chase on the west side the building on floor 0 to serve floors 0 and 1. The ductwork distribution for floors 2 and 3 are served by a ‘doughnut’ that circulates the entire 3rd floor on the outside surface of the building. The 3rd floor has enough volume to allow offices below this routing. The ventilation quantity itself at the existing louvers appears to be enough to support the reconfiguration. 2. Exhaust Air: The building has exhaust provided at the restroom spaces. Exhaust is not provided at the heavy copy areas not meeting current health code requirements. Seattle 86North North SeattleCollege College Library Renovation – PRR Hargis Engineers, Inc. November 23, 2015 Design Team Conditions Analysis (Engineer’s Reports) 3. Central Plant: There is no existing central plant for this building. Heating is through electric re‐heat coils at variable air volume (VAV) boxes serving various zones. Chilled water is being provided through the central plant. 4. Heat Recovery: There is no heat recovery for this building. 5. Energy Management Control System: The control system within the building is a partially original pneumatic system with some upgrades to an energy management system. Some of the main air handlers and VAV boxes have been upgraded to an energy management system as systems have failed. The hydronic convectors at the exterior have all been disabled as the controls are stand alone. There is no scheduling at the thermostats or setback controls. The current system does not meet the current energy code. Plumbing Systems 1. Piping: The domestic water system is primarily galvanized and copper with some spot repairs and minimal ADA upgrades completed. The waste and vent system could not be viewed as part of this site study with the exception of some vent lines replaced with ABS as part of repair work. The system is original. 2. Domestic Water Heating: The domestic water heating system has been replaced at least once over the course of the buildings life. The current unit is beyond its service life and in need of replacement. 3. Plumbing Fixtures: The plumbing fixtures are a mix of original and conservation saving fixtures based on limited ADA upgrade work throughout the facility. The corresponding lavatories were not replaced in unison with the water closets and an attempt was made to make them ADA. The original water closets use 3.6 Gals/flush and urinals use 1.6 gals/flush wasting significant water and not meeting current environmental standards. The drinking fountains do not meet ADA requirements. Life Safety / Fire Protection system 1. Fire Sprinklers: There is no fire sprinkler system for this building. The building is over 5,000 SF requiring a fire sprinkler system. Mechanical Code / Health Code / Energy Code 1. The ventilation for the building does not currently meet the requirements for outside air. A demand control ventilation system has not been installed on the 4 main air handlers serving the building. The mechanical system is a constant heating and ventilation system without variable speed drives or the proper energy management system to reset the temperature within the air handlers appropriately. Many of the thermostats and air handler components are still using pneumatic controls that operate 24/7 and are not connected to the energy management system. The mechanical systems and controls installed have not met the energy code for at least the last ten years. North Seattle College Library Renovation – PRR Hargis Engineers, Inc. Library Building Renovation Project November 23, 2015 87 Design Team Conditions Analysis (Engineer’s Reports) Description of Proposed Mechanical System Approach HVAC System 1. Supply/Ventilation Air and HVAC Equipment: The existing built‐up air handlers can be modified in the current location and reuse the ductwork pathway for supply and return/exhaust air. The existing air handlers could reuse the existing louver locations. The existing cooling coil and eliminators would be removed along with the single belt driven vanaxial fans. The space created from the fan removal would allow space for a new heat recovery run around loop to be put in place between the outside air and exhaust louvers allowing for 50‐60% energy savings on the ventilation air for both heating and cooling. The proposal also includes a new heating and cooling coil within the unit as well as a new fan wall system. Based on the size of the fan units, we would expect around a 12 to 24 fan wall arrangement. Demand control ventilation through CO2 sensors and air flow measuring stations will be utilized at the main air handlers. VAV boxes with a hydronic reheat coil, but without fans and filters would provide the temperature control for each of the zones. The ductwork distribution path would remain the same, however, new ductwork would be provided throughout to support the reconfiguration of the spaces and zones. The air filtration system will be located at the main air handler and will be provided with both a 2” pre‐filter and a 4” filter meeting MERV 13 requirements or higher. Split system heat pumps will be used at MDF, IDF or elevator equipment room locations to support spot cooling. 2. Exhaust Air: The restroom spaces will be enlarged to support the restroom upgrades. The exhaust system will be replaced with new and updated to support the increased fixture count. Where heavy copying is shown on the plans, a dedicated exhaust system will be provide to meet the current health code. 3. Central Plant: The proposed system includes a central plant air to water heat pump located on the roof. The system will be modular and based on the Airstack equipment. The pumps, expansion tank, air separator, etc. will be included with the equipment. The system will be designed to work down to 0F outside air temperature. The heat pump itself will be designed with variable speed compressors and condenser fans to optimize the efficiency as well as a refrigerant based heat recovery system. Hydronic chilled water will be routed to the main air handlers. Hydronic heating water will be routed to the main air handlers and all of the VAV boxes. 4. Heat Recovery: Heat recovery will be provided through a refrigerant run around loop with the configuration noted in item A1 above. 5. Energy Management Control System: The college utilizes a Siemens energy management system (EMS). There was a recent upgrade for a couple of the main air handlers. The entire system will be updated and brought up to current energy code North Seattle College Library Renovation – PRR 88 North Seattle College Hargis Engineers, Inc. November 23, 2015 Design Team Conditions Analysis (Engineer’s Reports) and campus standards. The EMS system will have a connection to the fire alarm and security systems. Plumbing Systems 1. Piping: The domestic water system will replaced with new throughout with the exception of the sanitary waste piping. It is suggested that a scoping exercise be done to understand the condition of the existing piping and to quantitate the exact location of the piping and its depth for building upgrades. 2. Domestic Water Heating: The domestic water heating system will be new. The proposed system is a combination of an instantaneous hot water heater and a heat pump based hot water system as gas has not been brought to this location on site. The smaller tank size will allow for some capacity and recirculation. Since no showers or heavy hot water use is required, the instantaneous will save energy and provide the hot water when needed. 3. Plumbing Fixtures: The plumbing fixtures will be replaced with new throughout including water closets, urinals, lavatories, drinking fountains with bottle fillers, mop sinks and general use sinks as indicated on the architectural plans. 4. Storm Draining: The existing storm drainage risers will be upgraded with new piping and re‐routed as required to support the new reconfiguration of spaces. Life Safety / Fire Protection System 1. Fire Sprinklers: A new fire sprinkler system will be provided throughout the facility utilizing quick response heads. The most likely location for the main fire riser is within the basement area where the main switchgear and compressor for the pneumatic system is located. The riser with backflow device would be located in this location. The fire department connection would be located outside the building on the East wall adjacent this room. Piping would be distributed throughout. A dry system is likely based on the size of the louver plenums for the HVAC equipment. The dry risers would be located adjacent the HVAC equipment. Dry heads off a wet system are likely a requirement of the AHJ at all exits and entrances to the facility. A standpipe system may be required by the AHJ. Library Building Renovation Project 89 Design Team Conditions Analysis (Engineer’s Reports) 90 North Seattle College Design Team Conditions Analysis (Engineer’s Reports) ELECTRICAL NARRATIVE Information Resource A. Existing record drawings, provided by NSC B. Field investigation performed November 6th, 2015. C. Various existing drawings of the facility from NSC. General Overview The existing Library Building at North Seattle College is a late 60’s/early 70’s vintage building with various program spaces including a library, lecture halls and theater spaces. In general, the overall electrical systems appear to be in fair condition, but at 40+ years old, many of the electrical systems are at or near the end of their economic and useful life. Description of the Electrical Systems Power Distribution The Library building electrical is fed from Seattle City Light utility service at 480/277 Volts wye, 3‐phase, 4 wire. The existing electrical service size is adequate for the facility and the proposed renovation. The electrical main service equipment consists of switchboard construction manufactured by General Electric (GE), utilizing robust GE AK‐series drawout low‐voltage power circuit breakers. This equipment appears to be in fair condition, and is utilizing the original protective relays and trip units. This equipment has an expected life of approximately 50 years, but with upgrades and rebuilding of the power circuit breakers, as well as regular maintenance testing, we would anticipate that an additional 10 to 15 years of life could be realized. Since the library building renovation is a 40 to 50 year project, this switchgear should be considered for replacement. The building power distribution system consists of panelboards and feeders, most of which are original and 40+ years old. Selective upgrades have occurred over the years as spaces were renovated. This power distribution equipment is at the end of useful life, and will need to be replaced. A new system will includes provisions for building lighting, mechanical and miscellaneous power loads as well as specialty considerations for the Theater/Concert Hall. A minimum of 20% spare capacity and circuit breaker provisions will be provided in all switchboards and panelboards to allow for future growth and flexibility. Fixed‐mounted molded case circuit breakers will be utilized downstream of the main switchboard for overcurrent protection. Panelboards will have bolt‐on circuit breakers. Copper North Seattle College Library Renovation – PRR Hargis Engineers, Inc. December 16,Project 2015 91 Library Building Renovation Design Team Conditions Analysis (Engineer’s Reports) bus will be provided. Equipment will be fully rated for the available fault current; series‐rated devices will not be utilized. To enhance power quality and facilitate tracking of energy consumption, the electrical distribution system will be segregated by load type as much as practical. Separate panelboards for lighting, mechanical equipment, equipment power and classroom power will be provided. Large electrical loads and motors sized at 3/4 HP and larger will be served at 480 Volts, 3 phase. Lighting will be primarily 277 Volts and small convenience loads as well as power receptacles will be 120 Volts. Power monitoring will be provided at the main switchboard to allow for capturing the building energy data. In addition, power monitoring will be provided at major feeders to allow for capturing segregated data by load type (e.g. lighting, mechanical, etc.). Integration of this system with the building management system is anticipated. Emergency and Standby Power An emergency/standby generator system is not anticipated for this project. Anticipated code‐ required emergency loads will consist of emergency egress and exit lighting as well as the fire alarm system. A central emergency lighting battery/inverter system will be utilized for backup of emergency lighting, and will incorporate self‐diagnostics for monthly testing. Wiring Methods Feeders and branch circuits will utilize copper conductors with 600 Volt THWN/THHN insulation. Raceways will primarily consist of electrical metallic tubing with steel compression fittings. Lighting and Lighting Controls Systems The existing lighting system consists primarily of fluorescent sources, complemented with compact fluorescent and some incandescent where original dimming was utilized. The majority of fluorescent fixtures have been upgraded to T8 lamps and ballasts within the last 10 years. Existing lighting controls are generally pretty basic, utilizing relays and contactors for control of banks of lights. Some occupancy sensing controls have been added over the years. New lighting systems will be provided for the renovated building throughout. The lighting system will address specific “visibility” requirements for the project and each individual space. “Visibility” includes issues such as light quality, occupant comfort and aesthetics as well as industry standards including the Illuminating Engineering Society (IES). Energy‐efficient lighting sources such as LED will be utilized throughout. Lamp types will be specified in accordance with campus standards, while minimizing the number of different lamps. Lighting controls will be provided to meet the programmatic requirements for each space while optimizing energy performance and meeting energy code and project sustainability goals. Occupancy sensors will be utilized for many spaces including classrooms, offices and restrooms. 92 North Seattle College Library Renovation – PRR North Seattle College Hargis Engineers, Inc. December 16, 2015 Design Team Conditions Analysis (Engineer’s Reports) Supplemental time‐of‐day controls are anticipated for areas such as building common areas and exterior lighting. Automatic daylight harvesting controls will be provided. The Theater / Concert Hall space will have specialty requirements for lighting and lighting controls systems. New LED theatrical lighting will be provided to supplement existing lighting. A new theatrical dimming system will be provided. Fire Alarm System The existing building fire alarm system is a Siemens system matching the campus standard, utilizing a voice command system and speaker notification. The system appears to be in fair condition, but additional audible and visual alarms would be required to meet intelligibility and ADA requirements. A new building fire alarm system will be provided and connected to the existing campus fire alarm system. The system will be an intelligent, software‐controlled addressable voice fire alarm and detection system manufactured by Siemens, the campus standard manufacturer. Building fire alarm wiring will be installed within a designated raceway system. Telecommunications Structured Cabling System The telecommunications structured cabling system for the North Seattle College Library building will be designed in accordance with TIA industry and North Seattle College standards. The structured cabling system will include telecommunications rooms and spaces, horizontal and backbone cabling infrastructure and pathways to provide the infrastructure necessary to transport voice, data, wireless and streaming video applications to support the academic and administrative programs and objectives of the College. The students and programs using the College library will require mobility and flexibility and the ability for students and staff to access and exchange information using a variety of sources and devices including laptops, cellular phones and tablets from any location in the facility. To support these requirements the telecommunications infrastructure will include a comprehensive wireless network. The wireless network will also provide the capacity and bandwidth to deliver high data transfer rates to large numbers of users throughout the library. The new and emerging wireless standards can provide the required bandwidth and capacity but require additional wireless access points to provide the density of coverage and the new standards will require two Category 6A cables to each access point to power the device and deliver the necessary bandwidth. Category 6A cables have larger cable diameters and also require enlarged pathways to allow the cabling to be installed to the access points. The access points are powered using Power over Ethernet (PoE) network switches located in the Telecommunication Rooms. New Telecommunications rooms will be required to accommodate the new equipment and cabling. The PoE switches have higher power and heat loads and the power and cooling systems for these spaces will be sized to accommodate the additional power and head loads. The Telecommunication Rooms will include backup power North Seattle College Library Renovation – PRR Hargis Engineers, Inc. December 16, 2015 Library Building Renovation Project 93 Design Team Conditions Analysis (Engineer’s Reports) supplies and dedicated cooling systems to ensure the networks have a high degree of operational uptime and availability and minimize unplanned outages. The structured cabling Infrastructure will use the most current standards for optical fiber backbone and twisted‐pair copper horizontal cabling to provide capacity to ensure high‐ bandwidth administrative and instructional applications. Category 6A horizontal cables will be installed from telecommunications outlets in the library, classrooms and offices and other network device locations to a telecommunication room. The horizontal cabling will typically terminate on a modular connector mounted in a flush wall mounted face plate. The location and quantity of the telecommunications outlets for the building will be based on the programming requirements of the spaces and will include connections to support mechanical and electrical systems, and other automated building systems. The structured cabling will be installed above the accessible ceilings in cable trays or J‐hooks. Conduit pathways will be used in areas without accessible ceilings or where the spaces are open to structure. Audio Visual Systems The Audio Visual (AV) systems in the Library will facilitate ad hoc and collaborative student activities. This includes AV systems that allow student and staff to use their personal devices (e.g. laptops, smartphones and tablets) and present content from their device on a common display screen so all the members of the team can work together. The classroom AV systems will distribute audio and video signaling and will typically include AV input plates, speakers, amplifier, video switcher, control panel, mounting hardware, video projector or flat panel display, and wireless microphone system, and cabling. The Theater/Concert Hall will require sound reinforcement and audio visual systems. Security Systems The building will be equipped with electronic security systems including intrusion detection, access control, video surveillance to protect the property and the occupants of the building. A Distributed Antenna System (DAS) will provide enhanced two‐way radio coverage for emergency responders and a Rescue Assistance system will provide two‐way communication at elevator lobbies for persons requiring assistance exiting the building in the event the elevators have been recalled. 94 North Seattle College Facility Conditions Survey - Excerpts FACILITY CONDITIONS SURVEY - EXCERPTS Building Number Size (SF) Previous Score Updated Score Arts And Sciences (063-AS) 063AS 80,200 222 238 Childcare Center (063-CH) 063CH 7,557 196 211 Chiller Building (063-CB) 063CB 1,826 218 224 College Center (063-CC) 063CC 154,604 324 324 Education Building (063-ED) 063ED 42,117 182 182 Instructional Building (063-IB) 063IB 134,070 486 360 Instructional Building (063-IB) - Partial 063IB 41000 None 360 Library Building (063-LB) 063LB 80,192 474 460 Oce&E (063-OC) 063OC 45,052 146 146 Tech Building (063-TB) 063TB 55,470 546 146 Wellness Center (063-WC) 063WC 38,198 170 182 Grand Total Area (SF) 639,286 Building Name Weighted Average Score 290 17 Library Building Renovation Project 95 Facility Conditions Survey - Excerpts further evaluate the need for repair work. A deficiency located within a building planned for renovation, replacement or demolition was typically not considered for funding if the work was not absolutely required to maintain program functions until the larger project could be funded. It is difficult to justify spending capital funds on an asset that will likely be removed or replaced within a short period of time. The following table summarizes the college planning priories. Master Plan Campus Most recent full plan Most recent update Main Campus (063A) 2007 N/A Renovation Priorities Building Largest program deficiency or need Instructional Building (063-IB) Poor configuration - Inefficient space use Library Building (063-LB) Modernize - Improve instructional infrastructure Replacement Priorities Building Largest program deficiency or need None - 23 96 North Seattle College Facility Conditions Survey - Excerpts Deficiency F01 Carryover from prior survey (not yet funded) : Yes Location : Main Campus (063A) Building name : Multiple (063A) Unique Building Identifier (UBI) : 063A Funding category in capital budget : Minor Works Facility appropriation Uniformat category : B20-Exterior Enclosure Assessment : Asset is near or at the end of its useful life and should be replaced Quantity : 30 Unit of measurement : EA Component : Exterior Door Hardware Location within building or site : Campus wide Issue clarity : Adequate information was provided to assess deficiency Main cause of asset degradation or failure : Age/Wear Detailed description : Original door hardware is old, worn and failing. Replace failing locksets, emergency hardware, closers and automatic operators. The wood doors commonly warp as seasons change and need to be trimmed and adjusted. It is recommended that the worst of the doors and hardware be replaced. There are roughly 200 doors with deteriorated hardware. The worst 50 doors should be replaced with new closers and hardware. Any salvageable doors and closers should be used as spare parts for the remaining doors. Recommended funding schedule : Immediate Estimated remaining life (years) : 3 Estimated average life expectancy (years) : 25 Scoring priority category 1 : High Repair/Repl. Cost Category 1 percentage : 100 % Scoring priority category 2 : None Category 2 percentage : 0 % Project construction estimate (MACC): $39,000 Total repair estimate (including soft costs): $55,000 Deficiency score : 48 42 Library Building Renovation Project 97 Facility Conditions Survey - Excerpts Deficiency F02 Carryover from prior survey : No Location : Main Campus (063A) Building name : Multiple (063A) Unique Building Identifier (UBI) : 063A Funding category in capital budget : Minor Works Facility appropriation Uniformat category : D30-HVAC Assessment : Asset should be repaired to extend its useful life Quantity : 6 Unit of measurement : EA Component : Air handler Location within building or site : Multiple Issue clarity : Adequate information was provided to assess deficiency Main cause of asset degradation or failure : Age/Wear Detailed description : The air handler fan or drive motor bearings are failing or will fail shortly and should be replaced and rebalanced. The facility will conduct a vibrational test to determine which are in the worst condition and focus on those. Recommended funding schedule : Immediate Estimated remaining life (years) : 3 Estimated average life expectancy (years) : 20 Scoring priority category 1 : High Repair/Repl. Cost Category 1 percentage : 60 % Scoring priority category 2 : System Use Category 2 percentage : 40 % Project construction estimate (MACC): $100,000 Total repair estimate (including soft costs): $142,000 Deficiency score : 53 43 98 North Seattle College Facility Conditions Survey - Excerpts Deficiency F03 Carryover from prior survey : No Location : Main Campus (063A) Building name : Multiple (063A) Unique Building Identifier (UBI) : 063A Funding category in capital budget : Minor Works Facility appropriation Uniformat category : D30-HVAC Assessment : Asset should be repaired to extend its useful life Quantity : 20 Unit of measurement : EA Component : Fan motor Location within building or site : Ceiling Issue clarity : Adequate information was provided to assess deficiency Main cause of asset degradation or failure : Age/Wear Detailed D etailed description : The small in-line fan motors have become unreliable due to small component failure. There are roughly 100 motors, but only the worst 20 should be replaced. The associated duct work sealant has deteriorated, allowing air to escape the duct and should be repaired. Recommended funding schedule : Immediate Estimated remaining life (years) : 3 Estimated average life expectancy (years) : 20 Scoring priority category 1 : High Repair/Repl. Cost Category 1 percentage : 90 % Scoring priority category 2 : System Use Category 2 percentage : 10 % Project construction estimate (MACC): $25,000 Total repair estimate (including soft costs): $35,000 Deficiency score : 49 44 Library Building Renovation Project 99 Facility Conditions Survey - Excerpts Deficiency F06 Carryover from prior survey : No Location : Main Campus (063A) Building name : Multiple (063A) Unique Building Identifier (UBI) : 063A Funding category in capital budget : Minor Works Facility appropriation Uniformat category : D30-HVAC Assessment : Asset is near or at the end of its useful life and should be replaced Quantity : 5 Unit of measurement : EA Component : Air damper system Location within building or site : Roof Issue clarity : Adequate information was provided to assess deficiency Main cause of asset degradation or failure : Age/Wear Detailed De etailed description : The airflow damper controls in the cooling towers have failed and the blades have become warped and no longer function reliably. The actuators and fins should be replaced. Recommended funding schedule : Immediate Estimated remaining life (years) : 3 Estimated average life expectancy (years) : 25 Scoring priority category 1 : High Repair/Repl. Cost Category 1 percentage : 90 % Scoring priority category 2 : System Use Category 2 percentage : 10 % Project construction estimate (MACC): $220,000 Total repair estimate (including soft costs): $313,000 Deficiency score : 49 47 100 North Seattle College Facility Conditions Survey - Excerpts Deficiency S02 Carryover from prior survey (not yet funded) : Yes Location : Main Campus (063A) Building name : Site (063A) Unique Building Identifier (UBI) : 063A Funding category in capital budget : Minor Works Site appropriation Uniformat category : G20-Site Improvements Assessment : Asset is near or at the end of its useful life and should be replaced Quantity : 3750 Unit of measurement : LF Component : Aluminum Elevated Walkway and Stair Railing Location within building or site : Various locations Issue clarity : Adequate information was provided to assess deficiency Main cause of asset degradation or failure : Age/Wear Detailed description : The aluminum handrails on the elevated walkways and stairwells are 40 years old and in various stages of deterioration. Deficiencies include badly cracked and spalling cement at post bases, bent and broken balusters, and damaged and broken top rails. The damaged rails should be repaired or replaced depending on the level of damage to each section. Recommended funding schedule : Immediate Estimated remaining life (years) : 3 Estimated average life expectancy (years) : 25 Scoring priority category 1 : High Repair/Repl. Cost Category 1 percentage : 90 % Scoring priority category 2 : Health/Safety Category 2 percentage : 10 % Project construction estimate (MACC): $250,000 Total repair estimate (including soft costs): $355,000 Deficiency score : 53 53 Library Building Renovation Project 101 Facility Conditions Survey - Excerpts BUILDING CONDITION RATING Library Building (063-LB) STATE UFI: A09018 Main Campus (063A) AREA: 80,192 SF BUILT: 1969 REMODELED: No PREDOMINANT USE: Library CONSTRUCTION TYPE: Heavy CRV/SF: $301 REPLACEMENT VALUE: $24,137,792 Primary Systems COMPONENT: Structure RATING: 3 x WEIGHT: 8 = SCORE: 24 Some cracking evident but does not likely affect structural integrity; Visible defects apparent but are nonstructural COMMENTS: Poured in place concrete; seismic improvements needed COMPONENT: Exterior Closure RATING: 3 x WEIGHT: 8 = Sound and weatherproof but with somee deterioration evident COMMENTS: Spalling concrete areas need repair; wood w window trim COMPONENT: Roofing RATING: 5 x WEIGHT: 10 = Leaking and deterioration is to point where new roof is required COMMENTS: Bad BUR w many blisters; funded for replacement 2015 102 North Seattle College SCORE: 24 SCORE: 50 Facility Conditions Survey - Excerpts Secondary Systems RATING: 5 x WEIGHT: 6 = COMPONENT: Floor Finishes Extensive deterioration and unevenness COMMENTS: Carpet, concrete, vinyl tile, quarry tile SCORE: 30 COMPONENT: Wall Finishes RATING: 3 x WEIGHT: 6 = SCORE: 18 Aging surfaces but sound; some maintenance is required COMMENTS: Gypsum board, demountable partitions, brick, concrete, ceramic tile, CMU, vent wood COMPONENT: Ceiling Finishes RATING: 3 x WEIGHT: 6 = SCORE: 18 Some wear and tear; Minor staining or deterioration COMMENTS: Lay-in ceiling tile; gypsum board; aluminum channels; concealed spline tile; concrete structure COMPONENT: Doors & Hardware RATING: 3 x WEIGHT: 6 = SCORE: 18 Functional but dated COMMENTS: Interior/exterior wood doors w HM frames; deteriorated door hardware Service Systems COMPONENT: Elevators RATING: 1 x WEIGHT: 6 = Appropriate and functional for occupancy and use COMMENTS: 3 stop; elevators refurbished in 2010 COMPONENT: Plumbing RATING: 3 x WEIGHT: 8 = Fixtures are functional but dated; somee leaks; maintenance required COMMENTS: Copper, steel, cast iron and PVC piping; porcelain fixtures SCORE: 6 SCORE: 24 COMPONENT: HVAC RATING: 5 x WEIGHT: 8 = SCORE: 40 Inadequate capacity, zoning and distribution; equipment deteriorating; No A/C in office areas; no ventilation in hazardous areas COMMENTS: Chilled/hot water cooling/heat w VAV from central plant; bad electric re-heat boxes funded for replacement COMPONENT: Electrical RATING: 3 x WEIGHT: 8 = Service capacity meets current needs butt inadequate for future COMMENTS: 2400amp 480v SCORE: 24 COMPONENT: Lights/Power RATING: 3 x WEIGHT: 8 = SCORE: 24 Adequate work area illumination; adequate outlets for current use COMMENTS: Suspended strip, hanging can and recessed can fluorescent lighting. New outlets 2014. 77 Library Building Renovation Project 103 Facility Conditions Survey - Excerpts Safety Systems COMPONENT: Life/Safety RATING: 3 x WEIGHT: 10 = Generally meets codes for vintage of construction COMMENTS: No data COMPONENT: Fire Safety RATING: 3 x WEIGHT: 10 = Extinguishers and signed egress; no violations; no alarm or sprinklers COMMENTS: Addressable FA system, no sprinklers SCORE: 30 SCORE: 30 COMPONENT: Modifications RATING: 1 x WEIGHT: 7 = SCORE: 7 Modifications appear to be in compliance with codes and sound construction practices; HVAC/electrical service properly provided COMMENTS: Recent third floor media area and computer room remodel; good quality Quality Standards COMPONENT: Maintenance RATING: 3 x WEIGHT: 7 = SCORE: 21 Routine maintenance is required; deferred maintenance is evident; impact is minor to moderate COMMENTS: Deferred maintenance evident: exterior wall repair, roof replacement, doors and hardware COMPONENT: Remaining Life RATING: 3 x WEIGHT: 6 = Life expectancy is 5-15 years; moderate system deterioration COMMENTS: Good renovation candidate SCORE: 18 COMPONENT: Appearance RATING: 3 x WEIGHT: 6 = Average construction; average interior and exterior appearance COMMENTS: SCORE: 18 Heat Loss COMPONENT: Insulation RATING: 3 x WEIGHT: 6 = Insulation present, butt not to current standards (installed prior to 2010) COMMENTS: COMPONENT: Glazing RATING: 3 x Double glazing with aluminum/metal window frames COMMENTS: WEIGHT: 6 = SCORE: 18 SCORE: 18 TOTAL SCORE = 460 PREVIOUS BIENNIUM SCORE = 474 CONDITION: Needs Improvement/Renovation 78 104 North Seattle College NSC Master Plan - Excerpts NSC MASTER PLAN - EXCERPTS Library Building Renovation Project 105 NSC Master Plan - Excerpts 106 North Seattle College NSC Master Plan - Excerpts Library Building Renovation Project 107 NSC Master Plan - Excerpts 108 North Seattle College NSC Strategic Plan - Excerpts NSC STRATEGIC PLAN - EXCERPTS The North Seattle Community College Strategic Plan: Roadmap to 2016 March, 2013 northseattle.edu 9\nYf[af_Klm\]flKm[[]kk =p[]ddaf_afL]Y[`af_Yf\D]Yjfaf_ :mad\af_;geemfalq Library Building Renovation Project 109 NSC Strategic Plan - Excerpts Our world, our country, our city and the North Seattle community are changing rapidly. The pace of technological innovation, the reach of social media, the need for more sustainable practices and the new, shifting economy and job markets have impacted us in profound ways. Our service area is more diverse than ever and our neighborhoods are now beginning to reflect the changing face of America. And throughout our history, our “True North” has been our commitment to making a difference in our student’s lives. How we make that difference (e.g., our support services, instruction, etc.) has evolved over the years and will continue to evolve in the future, but our commitment to this mission remains our guiding star. Within this context of change and tradition, our strategic planning process helped us redefine what “changing lives through education” means. It means “Advancing Student Success”, “Excelling in Teaching and Learning” and “Building Community” (our core themes). This is North Seattle Community College’s Strategic Plan through the year 2016 and I encourage you to read it. As I mentioned on President’s Day of 2012, this is our “roadmap” that outlines our institutional direction over the next three and a half years. This document represents research, comments and recommendations from across our campus and from the communities we serve. Several special planning events and meetings and surveys were conducted to establish our core themes, objectives and benchmarks. The input from our community provided greater clarity regarding what we mean when we say we want to advance student success, excel in teaching and learning and build community in order to change our student’s lives. The benchmarks related to each of the themes establish very specific milestones along the path to our preferred future. We have until 2016 to meet these benchmarks which coincides with our Year Seven accreditation visit. While these benchmarks do not describe every inch of our journey over the next few years, they do serve as “mileage markers” that point to key achievements on the way to 2016 and our preferred future. 110 North Seattle College NSC Strategic Plan - Excerpts Core Theme One: 9\nYf[af_Klm\]flKm[[]kk Advancing Student Success means that we tDSFBUFBDVMUVSFUIBUJOUFOUJPOBMMZQMBDFTTUVEFOUMFBSOJOHBOEHSPXUIBUUIFDFOUFSPGXIBUXFEP tQSPNPUFTUVEFOUFOHBHFNFOUXJUIDPVSTFXPSL GBDVMUZBOETUBČ BOEDPDVSSJDVMBSBDUJWJUJFT tGPTUFSBDUJWF DPMMBCPSBUJWF TFMGEJSFDUFEMFBSOJOH tTVQQPSUTUVEFOUQFSTFWFSBODFBOEHPBMDPNQMFUJPO GZb][lan])2 5PTJHOJĕDBOUMZJODSFBTFUIFQFSDFOUBHFPGTUVEFOUTXIPTVDDFTTGVMMZDPNQMFUFUIFJSFEVDBUJPOBMHPBMTJODMVEJOHSFUFOUJPO QSPHSFTTJPO DPNQMFUJPO USBOTGFS BOEFNQMPZNFOUBOEUPJODSFBTFUIFFRVJUZPGBDBEFNJDPVUDPNFTBNPOHBMMTUVEFOUHSPVQT Af\a[Ylgjkg^9[`a]n]e]fl Student Achievement Indicators "OOVBM4UVEFOU"DIJFWFNFOUQPJOUTQFSTUVEFOU Retention Measures Baseline [Date] Benchmark [Date] <> <> Baseline [Date] Benchmark [Date] 2UP2GPSTUVEFOUTJOUFOEJOHUPTUBZBUMFBTUUXPRVBSUFST <TUBSUT> <GPSTUBSUT> 2UP2GPSTUVEFOUTXIPTFQMBOOFEMFOHUIPGTUBZJT iEPOULOPXwPSiCMBOLw <TUBSUT> <GPSTUBSUT> Baseline [Date] Benchmark [Date] Progression Measures: Developmental Math 1FSDFOUPGTUVEFOUTDPNQMFUJOHEFWFMPQNFOUBMNBUI TFRVFODFXJUIJOTJYRVBSUFSTZFBS <TUBSUT> <GPSTUBSUT> 1FSDFOUPGTUVEFOUTXIPTUBSUUISFFMFWFMTCFMPXDPMMFHFMFWFMBOE DPNQMFUFEFWFMPQNFOUBMNBUITFRVFODFTXJUIJOTJYRVBSUFST <TUBSUT> <GPSTUBSUT> 1FSDFOUPGTUVEFOUTXIPTUBSUUXPMFWFMTCFMPXDPMMFHFMFWFMBOE DPNQMFUFEFWFMPQNFOUBMNBUITFRVFODFTXJUIJOTJYRVBSUFST <TUBSUT> <GPSTUBSUT> 1FSDFOUPGTUVEFOUTXIPFBSO243XJUIJOFJHIURVBSUFST <TUBSUT> <GPSTUBSUT> Baseline [Date] Benchmark [Date] Progression Measures: Developmental English 1FSDFOUPGTUVEFOUTDPNQMFUJOHEFWFMPQNFOUBM&OHMJTITFRVFODF XJUIJOTJYRVBSUFST <TUBSUT> <GPSTUBSUT> 1FSDFOUPGEFWFMPQNFOUBM&OHMJTITUVEFOUTQBTTJOH&/( JOUIFJSTFDPOEZFBS <TUBSUT> <GPSTUBSUT> Progression Measures: ESL Transition Baseline [Date] Benchmark [Date] 1FSDFOUPGVQQFSMFWFM&4-TUVEFOUTUSBOTJUJPOJOHUPDPMMFHFMFWFM DPVSTFTXJUIJOUISFFZFBST <TUBSUT> <GPSTUBSUT> 1FSDFOUPGMPXFSMFWFM&4-TUVEFOUT -FWFMT USBOTJUJPOJOH UPVQQFSMFWFM&4-DPVSTFXPSLXJUIJOUISFFZFBST <TUBSUT> <GPSTUBSUT> Baseline [Date] Benchmark [Date] <TUBSUT> <GPSTUBSUT> Baseline [Date] Benchmark [Date] <$$44& 4VQQMFNFOUBM > <> Completion Measures 1FSDFOUPGEFHSFFTFFLJOHTUVEFOUTFBSOJOHEFHSFFDFSUJĕDBUJPO XJUIJOUISFFZFBST Student Self-Report of Goal Achievement 1FSDFOUPGTUVEFOUTSFQPSUJOHUIBUUIFZBSFiEFĕOJUFMZNFFUJOHw UIFJSFEVDBUJPOBMHPBMTBUUIFDPMMFHF Advancing Student Success con’t on next page Library Building Renovation Project 111 NSC Strategic Plan - Excerpts Advancing Student Success con’t Transfer Ready 1FSDFOUPGUSBOTGFSTUVEFOUTXIPBDIJFWFiUSBOTGFSSFBEZw TUBUVTXJUIJOUISFFZFBSTPGUIFJSĕSTUDPMMFHFMFWFMDPVSTF Job Placement Rates 1FSDFOUPGQSPGFTTJPOBMUFDIOJDBMDPNQMFUFSTXIPBSF FNQMPZFEXJUIJOPOFZFBSPGMFBWJOH/4$$ Equity of Academic Outcomes 'PSFBDIPGUIFBCPWFTUVEFOUTVDDFTTJOEJDBUPST UIF 'PS QFSDFOUEJČFSFODFJOBDIJFWFNFOUMFWFMTPGEJTBHHSFHBUFE TUVEFOUHSPVQTGSPNUIFBDIJFWFNFOUPGBMMTUVEFOUT Baseline [Date] Benchmark [Date] <PWFSBMM> <GPSTUBSUT> Baseline [Date] Benchmark [Date] <PWFSBMM> <> Baseline [Date] Benchmark [Date] 7BSJFTCZHSPVQ CZTUVEFOUTVDDFTT NFBTVSF *ODSFBTFTJOTVDDFTTSBUFTGPSBMM TUVEFOUT'PSEJTBHHSFHBUFEHSPVQT XIPTFTVDDFTTJTCFMPXUIFPWFSBMM NFBO BOJODSFBTFUPXJUIJOĕWFQFS DFOUBHFQPJOUTPGUIFNFBO<> Core Theme Two: =p[]ddaf_afL]Y[`af_Yf\D]Yjfaf_ Excelling in Teaching and Learning means that we tFOHBHFJOUIFXPSLPGUFBDIJOHBOEMFBSOJOHXJUIQBTTJPO WJTJPO BOEDSFBUJWJUZ tBEBQUUPUIFOFFETPGPVSSBQJEMZDIBOHJOHXPSMECZDIBOHJOHPVSTFMWFT PVSDVSSJDVMVN PVSTFSWJDFT BOEPVSQSBDUJDFT tFOTVSFUIFFČFDUJWFOFTTBOERVBMJUZPGPVSXPSLUISPVHIPOHPJOHBTTFTTNFOUBOEQSPGFTTJPOBMEFWFMPQNFOU GZb][lan]*2 5PEFFQFOBDPMMFHFXJEFDVMUVSFPGJORVJSZJOXIJDIFWJEFODFCBTFEBTTFTTNFOUMFBETUPJNQSPWFEUFBDIJOH MFBSOJOH TUVEFOUTVQQPSU BOETUVEFOUTVDDFTT Af\a[Ylgjkg^9[`a]n]e]fl Faculty assessment of student learning outcomes Baseline [Date] Benchmark [Date] 1FSDFOUPG'5'BOE15'TVCNJUUJOH"TTFTTNFOU-PPQ'PSNT BOOVBMMZ '515<> '515<> 1FSDFOUPGQSPHSBNTDPNQMFUJOHBTTJHOFEQPSUJPOTPG 1SPHSBN3FWJFXBOOVBMMZ <> <>> 1FSDFOUPGQPUFOUJBMGBDVMUZQBSUJDJQBUJOHJOBTTFTTNFOUPG JEFOUJĕFE&TTFOUJBM-FBSOJOH0VUDPNFFBDIZFBS <> <> Baseline [Date] Benchmark [Date] Student self-assessment achievement of learning outcomes "OOVBMTVSWFZPGHSBEVBUFTBTLJOHIPXNVDIUIFDPMMFHF DPOUSJCVUFEUPMFBSOJOHUIFTLJMMTMJTUFEJO$$44&2VFTUJPO BUISPVHIP <$$44&> <> 4VSWFZPGTUVEFOUTJODPVSTFTTFMFDUFEGPS&-0BTTFTTNFOU 4FUCBTFMJOFJO JODSFBTF<> Institutional effectiveness assessments 1FSDFOUPGBENJOJTUSBUJWFPďDFTBOETVQQPSUTFSWJDFT DPNQMFUJOHBOBTTFTTNFOUQSPKFDUBOOVBMMZ Professional development activities 112 Baseline [Date] Benchmark [Date] 4FUCBTFMJOFJO <> Baseline [Date] Benchmark [Date] 1FSDFOUPGFNQMPZFFTQBSUJDJQBUJOHJOQSPGFTTJPOBM EFWFMPQNFOUBDUJWJUJFTBOOVBMMZ 4FUCBTFMJOFJO JODSFBTF<> &NQMPZFFSBUJOHTPGQSPGFTTJPOBMEFWFMPQNFOUBDUJWJUJFT 4FUCBTFMJOFJO JODSFBTF<> North Seattle College NSC Strategic Plan - Excerpts Core Theme Three: :mad\af_;geemfalq Building Community means that we tDSFBUFBEJWFSTF JODMVTJWF BOETBGFFOWJSPONFOUBDDFTTJCMFUPBMM tTUSFOHUIFOPVSDPMMFHFDPNNVOJUZUISPVHIPQFODPNNVOJDBUJPO DJWJMJUZ BDDPVOUBCJMJUZ BOENVUVBMSFTQFDU tSFBDIPVUTJEFPVSJOTUJUVUJPOUPGPSNMPDBMBOEHMPCBMQBSUOFSTIJQTBOEQVSTVFDJWJDFOHBHFNFOU tXPSLJOXBZTUIBUBSFFOWJSPONFOUBMMZ TPDJBMMZBOEĕTDBMMZTVTUBJOBCMF GZb][lan]+ 5PTVTUBJOBOEFOIBODFBOJODMVTJWFFOWJSPONFOUJOXIJDIEJWFSTFTUVEFOUT FNQMPZFFT BOEDPNNVOJUZQBSUOFSTFOHBHF XJUIUIFDPMMFHF FYQFSJFODFBTFOTFPGCFMPOHJOH BOEEFSJWFNVUVBMCFOFĕU Af\a[Ylgjkg^9[`a]n]e]fl Employee and student diversity /VNCFSPGTFBSDIQSPDFTTFTNFFUJOHFBDIPGUIFTFDSJUFSJB "+PCEFTDSJQUJPOJODMVEFTUIFBQQSPWFEBďSNBUJWF BDUJPOTUBUFNFOU #+PCEFTDSJQUJPOSFRVJSFTTLJMMTUPJODSFBTFUIFTVDDFTTPG VOEFSSFQSFTFOUFETUVEFOUT $%PDVNFOUFEEJTUSJCVUJPOUPWFOVFTUPSFBDIVOEFS SFQSFTFOUFEOPOUSBEJUJPOBMDPNNVOJUJFT %5SBJOJOHGPSUIFTFBSDIDPNNJUUFF Activities to promote community and respect for diversity Baseline [Date] Benchmark [Date] <> <> Baseline [Date] Benchmark [Date] 1FSDFOUPGFNQMPZFFTQBSUJDJQBUJOHJOTQFDJĕFEBDUJWJUJFTUPCVJME DPNNVOJUZBOEEFWFMPQVOEFSTUBOEJOH SFTQFDUBOEBQQSFDJBUJPO GPSEJWFSTJUZ 4FUCBTFMJOFJO JODSFBTF<> 1FSDFOUPGTUVEFOUTQBSUJDJQBUJOHJOBDUJWJUJFTUPCVJMEDPNNVOJUZ BOEEFWFMPQVOEFSTUBOEJOH SFTQFDU BOEBQQSFDJBUJPOGPS EJWFSTJUZ*ODMVEF$$44&JUFNTT U BOED 4FUCBTFMJOFJO JODSFBTF<> &NQMPZFFBOETUVEFOUSBUJOHTPGUIFBDUJWJUJFT 4FUCBTFMJOFJO JODSFBTF<> Employee and student satisfaction Baseline [Date] Benchmark [Date] &NQMPZFFSBUJOHTPOBOOVBMDMJNBUFTVSWFZ EJTBHHSFHBUFECZ FNQMPZFFUZQF HFOEFSBOEFUIOJDJUZ 'SPN4QSJOHTVSWFZ "JODSFBTFJOPWFSBMM TBUJTGBDUJPO'PSEJTBHHSFHBUFE HSPVQTXIPTFTBUJTGBDUJPOJT CFMPXUIFPWFSBMMNFBO BO JODSFBTFUPXJUIJOĕWFQFSDFOUBHF QPJOUTPGUIFNFBO<> 4UVEFOUSBUJOHTPOBOOVBMDMJNBUFTVSWFZ EJTBHHSFHBUFECZ HFOEFSBOEFUIOJDJUZ 4FUCBTFMJOFJO "JODSFBTFJOPWFSBMM TBUJTGBDUJPO'PSEJTBHHSFHBUFE HSPVQTXIPTFTBUJTGBDUJPOJT CFMPXUIFPWFSBMMNFBO BO JODSFBTFUPXJUIJOĕWFQFSDFOUBHF QPJOUTPGUIFNFBO<> Building Community con’t on next page Library Building Renovation Project 113 NSC Strategic Plan - Excerpts Building Community con’t Community partnerships Baseline [Date] Benchmark [Date] "OOVBMTVSWFZPGFNQMPZFFTUPNFBTVSFOVNCFS UZQF TDPQF BOECFOFĕUTPGQBSUOFSTIJQT 4FUCBTFMJOFJO JODSFBTF<> "OOVBMTVSWFZPGFNQMPZFFTUPJEFOUJGZPVUSFBDIBDUJWJUJFT UPEJWFSTFDPNNVOJUJFT 4FUCBTFMJOFJO JODSFBTF<> "OOVBMTVSWFZPGQBSUOFSTGSPN5FDIOJDBM"EWJTPSZ $PNNJUUFFT 0$&& BOE0QQPSUVOJUZ$PVODJMUPJEFOUJGZ WBMVFPGBOEFOIBODFNFOUTUPQBSUOFSTIJQT 4FUCBTFMJOFJO JODSFBTF<> Baseline [Date] Benchmark [Date] <BWH> <ZFBSMZ> $$POUJOVJOH&EVDBUJPOBOOVBMSFHJTUSBUJPOT <BWH> <BWH> <BWH> <> <> 'PSNBMSFTFSWFBDDPVOUCBMBODFBTQFSDFOUPGPQFSBUJOHCVEHFU <> NJOJNVN<> 45"34 4VTUBJOBCJMJUZ5SBDLJOH "TTFTTNFOU3BUJOH 4ZTUFN SBUJOH #SPO[F3BUJOHPWFSBMM .BJOUBJO#SPO[F3BUJOH "OOVBMOPOTUBUFSFWFOVFGSPNTFMFDUFEPQFSBUJPOT Sustainability measures 4UBUFGVOEFE DPOUSBDUGVOEFE BOEDPOUJOVJOHFEVDBUJPO FOSPMMNFOUT "4UBUFGVOEFE'5&4BTQFSDFOUPGBOOVBMBMMPDBUJPO #$POUSBDUGVOEFE 3VOOJOH4UBSUBOOVBMJ[FE'5&4 *OUFSOBUJPOBM4UVEFOU4QSJOHIFBEDPVOU <> "(SBOUT DPOUSBDUT DVTUPNJ[FEUSBJOJOH PWFSDPTUT<> PWFSDPTUT<> #3FOUBMT <> <> $'PPE4FSWJDFT <> $PWFSDPTUT<> 1 5PXIBUFYUFOUBSFZPVNFFUJOHZPVSFEVDBUJPOBMPCKFDUJWFTBTBSFTVMUPGFOSPMMNFOUBUUIJTDPMMFHF i1PUFOUJBMGBDVMUZwSFGFSTUPUIFTVCTFUPGGBDVMUZ GVMMBOEQBSUUJNF XIPSFHVMBSMZUFBDIBDPVSTFUIBUJODMVEFTUIFUBSHFUFE&TTFOUJBM-FBSOJOH0VUDPNF FHBMMGBDVMUZUFBDIJOHDPVSTFTUIBUJODMVEFi*OGPSNBUJPO-JUFSBDZwBTBO&-0 T)BETFSJPVTDPOWFSTBUJPOXJUITUVEFOUTPGBEJČFSFOUSBDFPSFUIOJDJUZPUIFSUIBOZPVSPXOU)BETFSJPVTDPOWFSTBUJPOTXJUITUVEFOUTXIPEJČFSGSPN ZPVJOUFSNTPGUIFJSSFMJHJPVTCFMJFGT QPMJUJDBMPQJOJPOT PSQFSTPOBMWBMVFTDćFDPMMFHFFODPVSBHFTDPOUBDUBNPOHTUVEFOUTGSPNEJČFSFOUFDPOPNJD TPDJBM BOESBDJBMPSFUIOJDCBDLHSPVOET /PSUI4FBUUMF$PNNVOJUZ$PMMFHFEPFTOPUEJTDSJNJOBUFPOUIFCBTJTPGSBDFPSFUIOJDJUZ DPMPS BHF OBUJPOBM PSJHJO SFMJHJPO NBSJUBMTUBUVT TFY HFOEFSJEFOUJUZ TFYVBMPSJFOUBUJPO TUBUVTBTBWFUFSBOPSEJTBCMFEWFUFSBO QPMJUJDBMBďMJBUJPOPSCFMJFG DJUJ[FOTIJQTUBUVTBTBMBXGVMMZBENJUUFEJNNJHSBOU PSEJTBCJMJUZ 114 North Seattle College Photographs of Existing Conditions PHOTOGRAPHS OF EXISTING CONDITIONS PHOTOS OF EXISTING CONDITIONS PHOTOS OF EXISTING CONDITIONS View west to to the the Library LibraryBuilding’s Building’sLevel Level0 0&&1 from View looking looking west 1 from college’s central plaza. Image shows concrete framed structure View looking west to the Library Building’s Level 0structure &1 from and college’s central plaza. Image shows concrete framed columns that do not current seismic code requirements. college’s central plaza. shows concrete framed structure and and columns that do meet notImage meet current seismic code requirements. Opaque concrete walls prevent daylight to interiors. columns that do not meet current seismic requirements. Opaque concrete walls prevent daylight to code interiors. Opaque concrete walls prevent daylight to interiors. View looking south with Library Levels 0 and 1 to the right and upper levels overhead. Guardrails in image do1not meet current View looking south Library 00and and View south with with LibraryLevels Levels and 1totothe theright right and code. upper levels overhead. upper overhead. Guardrails Guardrailsininimage imagedo donot notmeet meetcurrent current code. code. Library Building Renovation Project 115 Photographs of Existing Conditions View looking lookingsouthwest southwestfrom fromadjacent adjacentInstruction InstructionBuilding Buildingtoward toward View Library Building. Building. Top Toptwo twolevels levelsarearelarger larger and offset from than Library and offset from than the the lower levels. Building requires the structure be upgraded to lower levels. Building requires the structure be upgraded to meet meet current seismic performance level objectives. current seismic performance level objectives. View of oflecture lecturehall hall(level (level00and and1). 1).Original Originaltables tablesand andchairs chairsare areat View at end of useful many broken or missing. Technical end of useful life,life, many are are broken or missing. Technical systems systems (HVAC, lighting and much of the A/V) are original, (HVAC, lighting and much of the A/V) are original, inadequate or inadequateTiered or deficient. Tierednolecture longerpedagogy serves deficient. lecture space longerspace servesnocurrent current pedagogy and is inflexible. and is inflexible. 116 North Seattle College Photographs of Existing Conditions Student media center has been created using left over/repurposed using left over/re-purposed Student mediacenter centerhas hasbeen beencreated created using left over/repurposed library space and is not efficient in its layout. Space notconducive conducive itsits layout. Space isisnot library space and is notefficient efficientinin layout. Space is not conducive to supporting technology. modern media technology. to supporting modern media technology. Library stacks make up a majority of the upper library level. The college been reducing its collection. New information Library stacks make upa amajority majority upper library level. Library has stacks make up ofof thethe upper library level. The The technology and tools along with study spaces are needed in lieu of college has been reducing its collection. New information college has been reducing its collection. New information technology large stackalong area. Electrical and data services need added technology andwith tools along with study spaces aretoneeded in lieu of and tools study spaces are needed in lieu ofbelarge stack throughout. large stack area. Electrical and data services need to be added area. Electrical and data services need to be added throughout. throughout. Library Building Renovation Project 117 Photographs of Existing Conditions Example images above Example above and and below belowshow showmultiple multiplepoints pointsofofentry entry at library. Doors at library. Doorsnonolonger longerserve serveasasaccess accesspoints pointsfor forentry entrydue duetoto Example images above and below show multiple points of entry at control security needs. control and library. Doors no longer serve as access points for entry due to control and security needs. 118 North Seattle College Photographs of Existing Conditions Re-purposed rooms rooms in the Repurposed the library library are areused usedfor forlabs labsand andclassroom classroom space. Rooms are undersized and function poorly as instructional space. Rooms are undersized and function poorly as instructional space. space. Offices do Many areare remote in location, Offices do not notsupport supportstaff staffasasintended. intended. Many remote in and inadequate size. Many rooms do not meet ADA/universal access location, and inadequate size. Many rooms due not meet ADA/ requirements. universal access requirements. Library Building Renovation Project 119 Photographs of Existing Conditions Circulation adapted over time to fit Circulationdesk deskand andstaff staffarea areahas hasbeen been adapted over time to fit Circulation desk and staff area has been adapted over time to fit into existing space. Configuration has been dictated by building into existing space. Configuration has been dictated by building into existing space. Configuration has been dictated by building structure toto IT/data andand power. A A structure and andsystems systemswhich whichlimit limitaccess access IT/data power. structure and systems which limit access to IT/data andinpower. A comprehensive renovation will provide needed flexibility this comprehensive renovation will provide needed flexibility in this comprehensive renovation will provide needed flexibility in this critical criticalarea areatotobetter betterserve servefaculty facultyand andstudents. students. critical area to better serve faculty and students. Hallway wide enough to meet ADA Hallwayaccess accesstotorestrooms restroomsis isnotnot wide enough to meet ADA Hallway access to restrooms is not wide enough to meet ADA clearance requirements. clearance requirements. clearance requirements. 120 North Seattle College Best Practices to Reduce Greenhouse Gas Emissions BEST PRACTICES TO REDUCE GREENHOUSE GAS EMISSIONS Included in Project? System / Best Practices Mechanical Solar water heating x Above code HVAC system efficiency Use natural gas instead of electricity for heating Geothermal heat pump x Post occupancy commissioning Electrical Photovoltaic energy systems Time of day and occupancy programming of lighting x Efficient lighting x Envelope Minimize building surface area for necessary floor area x Roofing materials with high solar reflectance and reliability Green roofs to absorb heat and act as insulators for ceilings Site Orient building for natural light and reduced heating and cooling loads x Trees and vegetation planted to directly shade building x Paving materials with high solar reflectance, enhanced water evaporation, or otherwise designed to remain cooler ore require less lighting than conventional pavements Increase transportation choices – drive, walk, bike, or public transit x Total number of these best practices included in project: 8 Library Building Renovation Project 121 Best Practices to Reduce Greenhouse Gas Emissions 122 North Seattle College Accreditation Report - Excerpts ACCREDITATION REPORT - EXCERPTS Library Building Renovation Project 123 Accreditation Report - Excerpts 124 North Seattle College Y Prereq Credit Y 4 Credit 2 Credit Credit Credit Credit 1 2 6 1 2 1 Credit Prereq Y 1 Prereq Y 1 Prereq 12 5 1 1 Access to Quality Transit Bicycle Facilities Reduced Parking Footprint 2 1 3 2 1 Site Development - Protect or Restore Habitat Open Space Rainwater Management Heat Island Reduction Light Pollution Reduction 6 2 Indoor Water Use Reduction Cooling Tower Water Use 18 1 2 3 1 2 Advanced Energy Metering Demand Response Renewable Energy Production Enhanced Refrigerant Management Green Power and Carbon Offsets Required Fundamental Refrigerant Management Optimize Energy Performance Required Building-Level Energy Metering 6 Required Minimum Energy Performance Enhanced Commissioning Required Fundamental Commissioning and Verification 33 1 2 Water Metering Required Outdoor Water Use Reduction Required Indoor Water Use Reduction Building-Level Water Metering Required Outdoor Water Use Reduction 11 1 Required Site Assessment Construction Activity Pollution Prevention 4 10 Energy and Atmosphere Y 19 Credit Credit 2 1 2 Credit Credit 1 3 Prereq 1 Y Prereq Y 1 5 Surrounding Density and Diverse Uses1 5 Water Efficiency Prereq 2 Credit Y 4 1 Credit Credit 1 2 Credit 1 1 Credit Credit 1 Prereq 2 2 High Priority Site 10 1 Sensitive Land Protection 0 Sustainable Sites 16 LEED for Neighborhood Development Location 16 1 1 1 5 Integrative Process Green Vehicles Credit 1 Credit Credit Credit Credit Credit Credit 3 2 Credit Y 5 Credit 5 Location and Transportation 0 N 1 1 1 1 3 6 ? 2 1 5 1 Project Checklist DRAFT LEED v4 for BD+C: New Construction and Major Renovation 1 1 2 2 Credit Credit Credit Credit Credit Prereq Credit Credit Credit Credit Credit Credit Credit Credit Regional Priority: Specific Credit Regional Priority: Specific Credit Regional Priority: Specific Credit Possible Points: Certified: 40 to 49 points, Silver: 50 to 59 points, Gold: 60 to 79 points, Platinum: 80 to 110 Credit Credit Credit Credit Regional Priority: Specific Credit LEED Accredited Professional 0 Regional Priority Credit Credit Innovation Acoustic Performance 110 1 1 1 1 4 1 5 6 1 1 3 Daylight Quality Views 2 Interior Lighting 1 Indoor Air Quality Assessment Thermal Comfort 1 2 Construction Indoor Air Quality Management Plan 3 2 Low-Emitting Materials Required Enhanced Indoor Air Quality Strategies 16 Required 2 2 2 Environmental Tobacco Smoke Control 2 Innovation 2 1 2 Credit Prereq Prereq Minimum Indoor Air Quality Performance Building Product Disclosure and Optimization - Material Ingredients Construction and Demolition Waste Management 2 5 Required Building Life-Cycle Impact Reduction Building Product Disclosure and Optimization - Environmental Product Declarations Building Product Disclosure and Optimization - Sourcing of Raw Materials Construction and Demolition Waste Management Planning 13 Required Storage and Collection of Recyclables 3 Indoor Environmental Quality 1 1 2 Prereq 4 Materials and Resources Lower Columbia College (LCC) - PRR Jan-16 51 30 29 TOTALS 1 1 2 1 1 2 1 2 1 1 1 1 1 1 1 5 1 1 1 1 4 1 1 1 1 1 Y Y 8 1 1 3 Y Y 5 Project Name: Date: LEED Checklist LEED CHECKLIST Library Building Renovation Project 125 126 North Seattle College Campus Space Utilization Calculations CAMPUS SPACE UTILIZATION CALCULATIONS CAMPUS UTILIZATION AND POINTS BASED ON 2017-19 MAJOR PROJECT SELECTION CRITIERA. These values are calculated based on user-input data on the Capture Hours, Room Data, and Class Data tabs. Classes Labs Campus New Area Points: Contact Hours 25,440.50 8,504.67 42,065.50 Workstations 2,483 1,388 3,871 Utilization 10.25 6.13 10.87 Capture Efficiency 88% 87% 88% 0 There are also up to nine points related to utilization available in the Overarching criteria for every project. The full data is available in the attached Space Utilization spreadsheet. Library Building Renovation Project 127 Campus Space Utilization Calculations 128 North Seattle College