CPCCBC4002A Manage OH&S in the Building & Construction Workplace
Assessment Task 3.1 - Write a SWMS
Organisation Details
Organisation Name:
Lukas Builders
Contact Name::
Taj
ACN/ABN
018433
Contact Position:
Employee
Address:
80 Colier Drive Cudmirrah
Contract Phone No:
0401070101
Project Details:
Project:
Replace rotten joists on back patio
Area:
Use of power tools, working at heights
This SWMS has been developed in consultation
with:
Back of house
Activity:
Gavin Lukas
Reviewed by: ________________________
(Note high risk tasks):
Position: Boss
__________________ Date: _27/1/21
/ __ /
Resources / Trades Involved:
Carpenters
Equipment Used:
Nailgun, Circular saw, battery drill, reciprocator saw, Hand tools, correct ppe
Maintenance checks:
Chorded tools undergo mandatory check and tag if necessary
Materials Used:
timber posts, timber decking , timber joists, timber beams,shade cloth, bolts,bugel screws and nails.
Work Health Safety or
Environmental Legislation:
© Master Builders Association Assessment Tools Nov 2018 V 2.0
Codes or Standards
applicable to the
works:
managing the risks of falls at the workplace,
managing electrical risks in the workplace
CPCCBC4002A Manage OH&S in the Building & Construction Workplace
Level
H (1)
(High level of harm)
M (2)
(Medium level of
harm)
Description of Consequence or Impact
Consequence
Likelihood / Probability
Potential death, permanent disability or major structural failure/damage. Off-site environmental
discharge/release not contained and significant long-term environmental harm.
Potential temporary disability or minor structural failure/damage.
On-site environmental discharge/release contained, minor remediation required, short-term
environmental harm.
L (3)
(Low level of harm)
Incident that has the potential to cause persons to require first aid.
On-site environmental discharge/release immediately contained, minor level clean up with no
short-term environmental harm.
Level
Likelihood / Probability
Likely
Could happen frequently
Moderate
Could happen occasionally
Unlikely
May occur only in exceptional circumstances
© Master Builders Association Assessment Tools Nov 2018 V 2.0
L
Likely
M
Moderate
U
Unlikely
H (1)
(High)
1
1
2
M (2)
(Medium)
1
2
3
L (3)
(Low)
2
3
3
CPCCBC4002A Manage OH&S in the Building & Construction Workplace
Item
Job steps
Hazards
remove old decking boards/ inspect damage
nails, hitting/cutting self
Risk
Class/
Ranking
L
Controls
corrrect ppe, take your time
Name of persons
responsible for
work
Workers
remove old shadecloth/rafters
nails, manual lifting, fallingM
remove old beams
Nails, falling objects, manual
M lifting Correct ppe, correct lifting, correct work platform
Workers
remove old posts
falling objects, Manual lifting,Nails
L
Correect ppe, correct lifting
workers
remove rotten joists and replace
Nails, manual lifting, handLtools
Correct ppe, take your time
workers
stand new posts
manual lifting
L
Correct ppe, correct lifting
Workers
replace new beams/rafters
manual lifting, heights
M
Correct ppe, Correct work platform
workers
install shadecloth
falling, cutting self
M
Correct ppe, correct work platform
workers
lay new decking
manual labour, Cutting self
L
Correct pee, take time, lift correctly
Workers
© Master Builders Association Assessment Tools Nov 2018 V 2.0
correct ppe, correct lifting, correct work platform
Workers
CPCCBC4002A Manage OH&S in the Building & Construction Workplace
Item
Job steps
© Master Builders Association Assessment Tools Nov 2018 V 2.0
Hazards
Risk
Class/
Ranking
Controls
Name of persons
responsible for
work
CPCCBC4002A Manage OH&S in the Building & Construction Workplace
Qualifications and experience required to complete the
task
The workers should know the house layout
Personnel, Duties and Responsibilities
(Supervisory staff and others)
There will be two tradesmen and one builder.
and be experienced with power tools.The worker Builder will oversee all work.
Training Required to Complete Work
No extra training is required to complete
this job other than learning houses layout.
should have a cert 3. Job is over $5000 so a
licensed builder is needed.
Also note below how the controls within this SWMS
will be implemented, monitored and reviewed
These controls will be implemented by making
sure that the workers are involved in the swms
procedure and they understand the risks
involved along with the correct procedures to
negate all possible risks. The builder takes the
role of supervising that all procedures
put in place are stuck to for the entirety of the job At the site meetings there will be a review of
this will happen atleast weekly and anything
Engineering Details / Certificates / SafeWork Approvals:
© Master Builders Association Assessment Tools Nov 2018 V 2.0
the procedures and their effectivness.
that is brought up will be discussed and quickly implemented.
CPCCBC4002A Manage OH&S in the Building & Construction Workplace
This SWMS has been developed through consultation with our workers and has been read, understood and signed by all workers undertaking the works:
Print Names:
Signatures:
Dates:
Taj Lukas
gnjrdbgk
27/1/21
Review No
01
02
Initial:
Date:
© Master Builders Association Assessment Tools Nov 2018 V 2.0