Business Blueprint Document (TO-BE) Maintenance Planning Plant & Fleet Management Client: DRC Implementation Partner: RSI Date Submission: July 2021 Authors Date Abdulla Jassim July 2021 Signature Document Number: Document Number PM_PREVENTIVE__V1.0 Document date July 2021 Version History: Version Number V1.0 Version date 11/07/2021 Summary of Changes As per the review comments Ref: Minutes of review Meeting held on July 2021 Approval List Name Signature Business Blueprint Document Page 2 of 123 Date TABLE OF CONTENT 1 2 3 BLUE PRINT AGREMENT LEGEND OVERVIEW 3.1 Introduction to RSI Proposal Maintenance Module 3.2 Scope of the document 4 ORGANIZATIONAL STRUCTURE 4.1 Maintenance Plant 4.2 Maintenance Planning Plant 5 MASTER DATA 5.1 Functional Location Master Data 5.1.1 Definition 5.1.2 Process Overview (As Is) 5.1.3 Process Overview (To Be) 5.1.4 Configuration data 5.1.5 RSI PROPOSAL Enhancement 5.2 Equipment Master Data 5.2.1 Definition 5.2.2 Process Overview (As Is) 5.2.3 Process Overview (To Be) 5.2.4 Configuration data 5.2.5 RSI PROPOSAL Enhancement 5.3 Bill of Material 5.3.1 Definition 5.3.2 Process Overview (As Is) 5.3.3 Process Overview (To Be) 5.3.4 Configuration data 5.3.5 RSI PROPOSAL Enhancement 5.4 Work Center 5.4.1 Definition 5.4.2 Process Overview (As Is) 5.4.3 Process Overview (To Be) 5.4.4 Configuration data 5.4.5 RSI PROPOSAL Enhancements 5.5 Task List Business Blueprint Document Page 3 of 123 7 8 9 9 11 12 13 14 15 15 15 15 16 19 19 20 20 20 21 25 26 27 27 27 28 30 30 31 31 31 31 32 32 33 5.5.1 Definition 5.5.2 Process Overview (As Is) 5.5.3 Process Overview (To Be) 5.5.4 Configuration data 5.5.5 RSI PROPOSAL Enhancements 5.6 Measurement Points and Counters 5.6.1 Definition 5.6.2 Process Overview (As Is) 5.6.3 Process overview (To Be) 5.6.4 Configuration data 5.6.5 RSI PROPOSAL Enhancement 5.7 Maintenance Plan 5.7.1 Definition 5.7.2 Process Overview (As Is) 5.7.3 Process Overview (As Is) 5.7.4 Configuration data 5.7.5 RSI PROPOSAL Enhancement 5.8 Codes and Catalogs 5.8.1 Definition 5.8.2 Process Overview (As Is) 5.8.3 Process Overview (To Be) 5.8.4 Configuration data 5.8.5 RSI PROPOSAL Enhancement 6 Maintenance Processing-General Data 6.1 Definition 6.2 Process Overview (As Is) 6.3 Process Overview (To Be) 6.4 Configuration Data 6.5 RSI PROPOSAL Enhancement 7 Preventive Maintenance Process (MNT01A) 7.1 Definition 7.2 Process Overview (As Is) 7.3 Process Overview (To Be) 7.3.1 Process Overview Description 7.4 Configuration Data 7.5 RSI PROPOSAL Enhancement 8 Reactive Maintenance (MNT01B) 8.1 Definition 8.2 Process Overview (As Is) Business Blueprint Document Page 4 of 123 33 33 33 34 34 35 35 35 35 35 35 36 36 36 37 39 39 40 40 40 40 40 40 41 41 41 42 48 49 50 50 50 51 53 56 56 57 57 57 8.3 Process Overview (To Be) 8.3.1 Process Overview Description 8.4 Configuration Data 8.4.1 RSI PROPOSAL Enhancement 9 Quality Inspection (MNT01F) 9.1 Definition 9.2 Process overview (As Is) 9.3 Process overview (To Be) 9.3.1 Process Description 9.4 Configuration Data 9.5 RSI PROPOSAL Enhancement 10 Cost Allocation (MNT01C) 10.1 Definition 10.2 Process Overview (As Is) 10.3 Process Overview (To Be) 10.3.1 Process Description 10.4 Configuration Data 10.5 RSI PROPOSAL Enhancement 11 Routine Maintenance (MNT01D) 11.1 Definition 11.2 Process Overview (As Is) 11.3 Process Overview (To Be 11.3.1 Process Description 11.4 Configuration Data 11.5 RSI PROPOSAL Enhancement 12 Fleet Management (FLT01) 12.1 Definition 12.2 Process Overview (As Is) 12.3 Process Overview (To Be) 12.3.1 Process Overview Description 12.4 Configuration Data 12.5 RSI PROPOSAL Enhancement 13 Fleet Hiring Process (FLT01B) 13.1 Definition 13.2 Process Overview (As Is) 13.3 Process Overview (To Be) 13.3.1 Process Description 13.4 Configuration Data 13.5 RSI PROPOSAL Enhancement Business Blueprint Document Page 5 of 123 58 60 64 64 66 66 66 67 68 69 70 71 71 71 72 73 77 77 78 78 78 79 81 84 85 86 86 86 87 88 90 90 92 92 92 93 95 99 99 14 Fuel Card Management (FLT01A) 14.1 Definition 14.2 Process Overview (As Is) 14.3 Process Overview (To Be) 14.3.1 Process Description 14.4 Configuration Data 14.5 RSI PROPOSAL Enhancement 15 MiscellanDRCus Processes (MNT01E) 15.1 Definition 15.2 Process Overview (As Is) 15.3 Process Overview (To Be) 15.3.1 Process Description 15.4 Configuration data 15.5 RSI PROPOSAL Enhancement 16 Procurement for Plant Maintenance 16.1 Definition 16.2 Process Overview (As Is) 16.2.1 Process Overview Description 16.3 Process Overview (To Be) 16.4 Configuration data 16.5 RSI PROPOSAL Enhancement 17 Budgeting for Plant Maintenance 17.1 Definition 17.2 Process overview (As Is) 17.3 Process overview (To Be) 17.3.1 Process Overview Description 17.4 Configuration data 17.5 RSI PROPOSAL Enhancement 18 Calibration Process (MNT01G) 18.1 Definition 18.2 Process overview (As Is) 18.3 Process overview (To Be) 18.3.1 Process Overview Description 18.4 Configuration data 18.5 RSI PROPOSAL Enhancement 19 Issues 20 Reporting Requirements Business Blueprint Document Page 6 of 123 100 100 100 101 103 105 105 106 106 106 107 108 110 110 111 111 111 111 111 112 112 113 113 113 113 113 114 114 115 115 115 116 118 121 121 122 123 1 BLUE PRINT AGREMENT Signing this document records your agreement to the contents of the Blueprint, and confirms that the remainder of the project can proceed Name Position Business Blueprint Document Page 7 of 123 Date Signature 2 LEGEND The following describes the symbols used in the process map: Legend Description Legend Description Process Start and End Decision Box Process / Activity step Document and Output Step Numbers Pre defined process & Automatic triggering of subsequent process Business Blueprint Document Page 8 of 123 Continuation of the process map to a different page and Process Link Manual Steps in the process 3 OVERVIEW Introduction to RSI Proposal Maintenance Module 3.1 Plant Maintenance comprises the following activities • Inspection: All measures which establish the actual condition of a technical system • Preventive maintenance: All measures which maintain the ideal condition of a technical system • Repair: All measures which restore the ideal condition of a technical system • Other measures taken using the maintenance organization Through integration with other modules (for example, Materials Management, Production, Sales and Distribution, Personnel Management, and Controlling) the data is always kept current and processes that are necessary for Plant Maintenance are automatically triggered in other areas (for example, a purchase requisition for non-stock material in the Materials Management/Purchasing area) Followings are the subsection within the plant maintenance module 1. 2. 3. 4. Management of Technical objects Preventive Maintenance Maintenance Processing Information System Management of Technical objects Management of technical objects section of RSI PROPOSAL covers the structuring of the functional location, Equipments and Bill of Materials. Advantages of structuring: • • • • The time required for managing the technical objects is reduced Maintenance processing is simplified The time spent entering data during maintenance processing is reduced considerably More specific, thorough and faster evaluation of maintenance data Business Blueprint Document Page 9 of 123 Preventive Maintenance Preventive Maintenance section of RSI PROPOSAL covers the activities of the maintenance, which are well planned in advance. You can use this component to: • • • Store activities to be performed, in the form of maintenance task lists Define the extent of preventive maintenance and inspection work and when it should be performed at pieces of equipment and functional locations Define the frequency of recurring maintenance and service tasks, either: o Time-based or counter-based o Time-based and counter-based Maintenance Processing Maintenance Processing section of RSI PROPOSAL covers processing of the all the documents (such as Processing of Maintenance Notification, Maintenance orders etc) that relevant for maintenance activities. Maintenance processing can be divided into the following three areas: • Description of the object condition The most important element in this area is the maintenance notification. This is used to describe the condition of the technical object, or to report a malfunction at a technical object and request the damage is repaired. • Execution of maintenance tasks The most important element in this area is the maintenance order. This is used to plan the execution of maintenance activities in detail, monitor the progress of work and settle the costs of maintenance tasks. • Completion of maintenance tasks The most important element in this area is the maintenance history. This is used for long-term saving of the most important maintenance data. This data can be called up for evaluation at any time. Information System The Plant Maintenance Information System can be used at a variety of levels (reports) in the decision making process as an instrument for monitoring, controlling and planning your business operations. Business Blueprint Document Page 10 of 123 It is a flexible tool for collecting, aggregating and evaluating data from Plant Maintenance. The information system allows you to view all information in the operative application from a wide range of perspectives. You can also define the level of detail in which you wish to see the information. 3.2 Scope of the document The functions identified to be implemented in this phase of implementation from Plant Maintenance and Fleet Management module in RSI PROPOSAL R/3 system are as follows: 1. Preventive Maintenance 2. Reactive/Breakdown Maintenance 3. Routine Maintenance 4. Cost Allocation 5. Hiring of Equipment/Fleet (Internal Hiring falls under the module ECO-ETM) 6. Procurement for Plant Maintenance (This falls under MM module) 7. Budgeting for Plant Maintenance (This falls under PS module) Business Blueprint Document Page 11 of 123 4 ORGANIZATIONAL STRUCTURE Maintenance and Fleet Management incorporate the existing organization structure by making assignments to the organizational units defined in Accounting and Logistics Modules. The Organizational Structures defined for DRC are as follows, Controlling area An organizational unit within a company, used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies For DRC, there would be only one controlling area, which is assigned to single company code as follows Sl No Controlling area Description 1 1000 DRC Controlling Area Company code Company code is the smallest organizational unit of Financial Accounting for which a complete self-contained set of accounts can be drawn up for purposes of external reporting. In Financial Accounting, business transactions are mainly entered, saved, further processed and managed at the level of company code. You can set up several company codes for each client, so that you can process the accounts of several independent firms at the same time. However, you must set up at least one company code. For DRC, there would be only one company code as follows Sl No 1 Company code 1000 Description DRC Plant In Logistics a plant is an organizational unit for dividing an enterprise according to production, procurement, maintenance, and materials planning. Plant is a place where materials are produced, or goods and services are provided. Business Blueprint Document Page 12 of 123 For DRC, following plants would be used Sl No Plant 1 1100 Projects Plant 2 1200 Facilities Management 3 1300 Landscape and Irrigation 4 1400 Transport and Engineering services 5 1500 DRC Plant Description Cost Center An organizational unit within a controlling area that represents a defined location of cost incurrence. The definition can be based on, functional requirements, allocation criteria, physical location, responsibility for costs Note: Please refer the Material Management (MM) and Finance Accounting and Controlling (FICO) blueprints for more details. 4.1 Organization Structure for Plant Maintenance 4.1.1 Maintenance Plant The plant, at which the operational systems of a company are installed, is called the maintenance plant. If the maintenance work is planned at this plant, the maintenance plant is also the maintenance planning plant. Locations subdivide a maintenance plant according to location criteria, for example, site, building, coordinates. A maintenance plant can also be subdivided into plant sections based on responsibility for production. The person responsible for the plant section is the contact person who coordinates production and maintenance (plant engineer). For DRC: The following are the maintenance plant for DRC Business Blueprint Document Page 13 of 123 Sl No Maintenance Plant Description 1 1200 Facilities Management 2 1300 Landscape and Irrigation 3 1400 Transport and Engineering services 4.1.2 Maintenance Planning Plant A maintenance planning plant is the organizational unit in which maintenance requirements are planned. These requirements can either come from your own plant or from another maintenance plant assigned to this maintenance planning plant. The planners within a maintenance planning plant are defined by maintenance planner groups. The units of capacity in Plant Maintenance are managed as maintenance work centers in the PM system. The maintenance work centers are usually assigned to the maintenance planning plant. However, you can also use maintenance work centers from other plants to perform maintenance tasks. For DRC: The following are the maintenance plant for DRC Sl No Maintenance Plant Maintenance Planning Plant Description 1 1200 1200 Facilities Management 2 1300 1300 Landscape and Irrigation 3 1400 1400 Transport and Engineering services Business Blueprint Document Page 14 of 123 5 MASTER DATA The basic data is stored in master records in the system. When processing business events and transactions, the system accesses master records and the data stored in them. 5.1 5.1.1 Functional Location Master Data Definition Functional locations are hierarchically ordered structures that represent a technical system, building, or part therDRCf. You can structure the functional location according to spatial (for example, building 1, building 2), technical (for example, press, press frame, press hydraulics), or functional, that is, process-oriented criteria (for example, polymerization, condensation). 5.1.2 Process Overview (As Is) Currently, there is no common database to store Functional Location. For facilities, project codes given by Projects Department are being utilized to identify each facility. Business Blueprint Document Page 15 of 123 5.1.3 Process Overview (To Be) Functional Location TESD/FMD/LID Start Project Handover Process Outside SAP 1 Receive the details of the new location and update details as per the functional location master data template Not approved 2 Get the approval Approved 3 Functional location Master data Create Functional Location master (If the number of records are less than 25, create them manually or use a BDC) End Roles: 1- User Department 2 – As per the delegation of authority 3 – Master data controller Business Blueprint Document Page 16 of 123 The aim of creating a functional location is to structure a technical system or building into units that are relevant for Plant Maintenance. The master record for the functional location uses the following views: General: Class, object type, reference data, and manufacturer data. Location: Location data, address Organization: Account assignment (for example, company code, cost center), responsibilities (for example, maintenance planning plant) Structure: For example, structure indicator, higher-level functional location, equipment Structure Indicator for Functional Location The identification for functional locations is created using the structure indicator. The structure indicator consists of two input fields: Edit mask Hierarchy levels The edit mask is used to control which characters may be used for identification (letters, numbers, or both) and how these characters are grouped together or split. The hierarchy levels are used to define which level ends at which character and how many hierarchy levels the structure may contain. For DRC: The Following Structure Indicator would be used DRC001 – Structure Indicator for DRC Edit Mask: Hierarchy Level: XXXX-XXX-AXX-XX-XX 1 2 3 4 5 X- Accepts both alphanumeric A - Accepts only alphabets Level 1: XXXX – Facility Number This level is represented by four characters. First character represents the type of facility as in the as-is system. Next three char are running serial number and/or alphanumeric combination for each facility. Level 2: XXX – Sub facility number This level will have three char. Running serial numbers and/or alphanumeric combination would be used to represent each sub facility. Business Blueprint Document Page 17 of 123 Level 3: AXX – This level is for Building and landscape. This level will have three characters. First character is an alphabet. For example A-for apartment, V-for Villas and L- for Landscape Second and third characters are running serial numbers and/or alphanumeric combination. Differentiating landscape by L at this level is for common landscapes or where there are no buildings and only landscape maintenance is carried out. Level 4: XX – This level is level indicates floors for apartment and type of landscape for landscapes. This level will have two characters. For example basement floor - B0, B1, B2 etc and for ground floor 00, first floor 01 and so on. For landscape, L1-Landscape, L2-Irrigation etc Level 5: XX – This level represents the physical location of the Equipment. For functional location at this level maintenance activity will be carried out. This level will have two characters. Running serial number and/or alphanumeric combination would be used. For the apartments, rooms within a house are identified by the description. Equipments are assigned only to level 5. Business Blueprint Document Page 18 of 123 5.1.4 Configuration data Code Description DRC001 Structure Indicator for DRC XXXX-XXX-AXX-XX-XX Edit Mask 1 5.1.5 2 3 4 5 Hierarchy Level RSI PROPOSAL Enhancement There are no enhancements for functional location master data. Business Blueprint Document Page 19 of 123 5.2 Equipment Master Data 5.2.1 Definition A piece of equipment is an individual physical object that is to be maintained as an autonomous unit. Pieces of equipment usually represent single objects (for example, pumps, motors, vehicles), for which maintenance tasks should be recorded. 5.2.2 Process Overview (As Is) Currently, there is no standard codification for equipment. Each department is following its own codification logic TESD For Registered Vehicle – Running serial number starting with V For Non Registered Vehicle – Running Serial number starting with P For Marine Equipments – Running serial number starting with M For long leased vehicles – Running serial number starting with LV FMD/LID Running serial number. Business Blueprint Document Page 20 of 123 5.2.3 Process Overview (To Be) Equipment Master Data TESD/FMD/LID Start Purchase Requisition Process (PRC01A) Outside SAP1 Project handover Process (PRJ02C) Receive the details of the new equipment and update details as per the equipment master data template distributed Not approved 2 Get the approval Approved 3 Equipment Master data Development Create Equipment master (If the number of records are less than 25, create them manually or use a BDC) Print barcode End Roles: 1- User Department 2 – As per the delegation of authority 3 – Master data controller Business Blueprint Document Page 21 of 123 5.2.3.1 Process Overview Description All the equipment/fleets would be created as master data in the system. These data are used while processing the maintenance order and notifications. Equipment can be installed/dismantled at functional locations. You can monitor the installation times for a piece of equipment from both the functional location view and the equipment view. The equipment master record uses the following views in the standard system: • General: Class, object type, reference data, and manufacturer data. • Location: Location data, address • Organization: Account assignment (for example, company code, cost center), responsibilities (for example, maintenance planning plant) • Structure: For example, structure indicator, higher-level functional location, equipment You can use the time-based data to monitor a piece of equipment dynamically, that is, track changes to the equipment over a specific period of time It automatically creates a new time segment whenever certain changes are made in the master record. The time segment describes the equipment usage. Fleet Master Data Fleet master record is extension of equipment master record. Fleet objects include cars, trucks, ships, building machinery and transport containers. A fleet object can be displayed as an equipment master record with fleet object-specific views. As a piece of equipment, a fleet object can be a reference object for a notification or an order. For example, fleet object-specific data can be: • Identification data (number plate, chassis number) • Dimension data (height, width, length) • Transport-relevant data (weight, maximum load, loading volume) • Task list data (counter reading data) • Other features (fuel card number, key number) • Engine data (engine type, engine performance, revolutions per minute, cubic capacity) • Fuel and lubricant data (fuel type, oil type) For DRC: Equipment structure will have two hierarchy levels. First level is main equipment, second level is sub equipment. Old unit IDs can be maintained on the field ‘Technical ID’ Business Blueprint Document Page 22 of 123 Equipment Category This allows you to control which basic characteristics a corresponding equipment master record should have. Using the control characteristics, you can decide how many and which equipment categories you require. The following are the some of the control characteristics of equipment category: • • • • • Screen sequence during the maintenance of master data Number interval and number assignment Ongoing usage history Option of installation at functional locations Documents verifying changes to master data For DRC: The following equipment categories would be used F – Fleet Objects – all vehicles. This category would be used to create a master data of all the fleet objects. This category would be mainly used all type of vehicles. This category would have external number range as existing in the present system. M – Machines This category is used to create master data of all the non fleet objects. L – Leased Vehicles This category would be used to create master data of long leased equipments, which are treated as DRC equipment from maintenance point of view. E – Equipments This category is used to create master data of all the equipments, used by FMD and LID. T- PRT (Production resource tools) and testing tools This category would be used to create master data of all the testing tools and production resource tools. G- General This category would be used to create equipment/fleet master which are not owned by DRC but maintained by DRC. Business Blueprint Document Page 23 of 123 Partner functions for equipment The business object 'Partner' is a natural person, organization, group of natural persons, or group of organizations, in which the company has a business interest. This can also be a person, organization, or group within the company. Types of partner are: Internal partner - for example, internal employees, partners in the HR personnel system External partner (for example, customers, vendors) Document Management Information about the technical object may be in the form of construction drawing, user manual, photographs etc. Documents are managed in Document management system (DMS) of RSI PROPOSAL and you can link the document master records directly to the master record of the technical object. Classes and Characteristics Classes Classes are used to group the objects together according to certain criteria that you define. One aim of classification is to assign features in detail to a technical object that the master record cannot handle in this quantity. A classification system has the task of describing objects using characteristics, and grouping similar objects into classes, to classify them and make them easier to find. For Example: TRUCK, CAR, BUS, MECH_EQUIP (Mechanical equipment), ELEC_EQUIP (Electrical equipment) etc. Characteristics Characteristics are used to describe the properties of the objects and are assigned to the class. The properties are specified by the values of a characteristic. For Example: For class CAR characteristics may be, type of cooling, type of coolant, Salik tag, Objects (Type of technical object) Technical object is a generic term user for a component in a technical system on which a maintenance task is performed (e.g. functional location) or a physical object that is maintained as an autonomous unit (e.g. equipment). Type of technical object or simply object is a division of a technical object for precise description. These objects may be assigned to a class. For example: SPLT_AC (Split A/C), which may be assigned to the class ELEC_EQUIP (Electrical equipment) Business Blueprint Document Page 24 of 123 5.2.4 Configuration data Equipment Category Equipment category Description F Fleet Objects M Machines E Equipments T Testing tools and PRT (Production Resource Tools) G General Equipments (Non DRC equipments) Number ranges For all the equipment category internal number ranging would be used. Equipment category Number Range Int/Ext F A-Z External M A-Z External E 1000000-1999999 Internal T 5000000-5999999 Internal G 6000000-6999999 Internal Partner Functions There would be one partner function PM with following partners Partner Function Description Partner Code Description PM PM partner function VN Supplier of the equipment PM PM partner function VU Employee PM PM partner function AB Department Responsible Business Blueprint Document Page 25 of 123 PM PM partner function VW Person Responsible PM PM partner function VU User responsible Objects (Type of technical object) The list of technical object to be configured would be decided during realization phase. Template to collect the required data has been distributed already. 5.2.5 RSI PROPOSAL Enhancement Following enhancement is required Enhancemen t Description Enhancement Additional screen and fields on Fleet master Output Bar code printing Remarks To maintain the following fields: Fuel card expiry date, fuel card supplier, salik card number, salik card expiry date. User should be able to print bar codes for equipment/asset number Business Blueprint Document Page 26 of 123 5.3 5.3.1 Bill of Material Definition A maintenance bill of material (BOM) is a complete, formally structured list of the components making up a technical object or an assembly. 5.3.2 Process Overview (As Is) Currently, there is no bill of materials for the equipments. Business Blueprint Document Page 27 of 123 5.3.3 Process Overview (To Be) Bill Of Material TESD/FMD/LID PCD Start 1 Equipment Master exist? No Equipment Master Data Yes 2 Is material master exist? No Material Master Data Yes Outside SAP 3 Update details as per the BOM master data template Not approved 4 Get the approval Approved 5 BOM master data Create Bill of Material (If the number of records are less than 25, create them manually or use a BDC) End Roles: 1,2, 3 - User Department 4 – As per the approval authority 5 – Master data controller Business Blueprint Document Page 28 of 123 5.3.3.1 Process Overview Description The BOM list contains the object numbers of the individual components together with their quantity and unit of measure. The components can be stock or non-stock spares or assemblies, which in turn can be described using maintenance BOMs. The maintenance bill of material has three important functions: Structuring of the object The structure of an object should be displayed as clearly as possible from a maintenance viewpoint. Spare parts planning in the order If a bill of material exists for a technical object, it can be used during the planning process of a maintenance order for the purpose of spare parts identification and planning. Spare parts planning in the task list Spare parts can be planned in the task list based on a bill of material. For DRC: The following Bill of materials would be used: Material BOM: A material BOM is a bill of material that is first created for a material (assembly/sub assembly) independently of a technical object. This bill of material can then be assigned to equipment. Equipment BOM: Equipment BOM contains material BOM and direct materials. Business Blueprint Document Page 29 of 123 5.3.4 Configuration data There is no specific configuration for DRC on BOM. RSI PROPOSAL standard settings would be used. 5.3.5 RSI PROPOSAL Enhancement There are no enhancements for BOM. RSI PROPOSAL standard functionality would be used. Business Blueprint Document Page 30 of 123 5.4 5.4.1 Work Center Definition A work center is a group of employees, machines etc which are responsible to carry out the maintenance activities. 5.4.2 Process Overview (As Is) Currently, there no concept of work center is followed in DRC. 5.4.3 Process Overview (To Be) 5.4.3.1 Process Overview Description A work center is an organizational unit within an operational system. A work center can be one of the following: - Machine - Group of machines - Person - Group of pDRCple In Plant Maintenance, work centers are used as: - Main work center in the master record for the equipment or functional location - Main work center in a maintenance item - Main work center in the task list header - Performing work center in the operations for a task list - Main work center in the order header - Performing work center in the operations for an order Work centers belong to the master data in PM and provide the capacity required to perform a task. Work center the basic data contains general data such as work center category, description, responsibility, and usage. Work center links provide the connection between work centers and other objects within the RSI PROPOSAL System. You can link a work center to a Cost center and HR master record. The links are valid for certain periods of time. The Work center is used for costing, scheduling and capacity planning Business Blueprint Document Page 31 of 123 5.4.4 Configuration data RSI PROPOSAL standard settings would be used for DRC. 5.4.5 RSI PROPOSAL Enhancements There are no enhancements for work center. RSI PROPOSAL standard functionality would be used. Business Blueprint Document Page 32 of 123 5.5 Task List 5.5.1 Definition Maintenance task lists describe a sequence of individual maintenance activities which must be repeatedly performed within a company. 5.5.2 Process Overview (As Is) Each department is having the list of activity for each type of maintenance. These lists contain the activities to be carried out, i.e. instruction set to the Technicians. 5.5.3 Process Overview (To Be) 5.5.3.1 Process Overview Description The maintenance task lists in the PM System are combined into task list groups. A task list group contains all the maintenance task lists with the same or similar maintenance steps. The maintenance task lists within a task list group are identified by the group counter, which numbers the task lists within the group sequentially. A task list structure consists of header data and operation list. The assignments which are made in the task list header are plant, work center, planner group, maintenance strategy, status etc. The assignments which are made to operation list are: The control key which defines whether an operation is to be processed internally or externally. Services can be assigned to an operation in the task list as service packages (= service master records) You can assign material components to the operations in maintenance task lists with stock/non stock indicator. The header data and operation list data of the task list are copied into the maintenance order when the maintenance task list is expanded in the maintenance order. You can execute the cost analysis program for task list for each task list type. The following data is entered in the cost analysis: - All material costs - All costs for external processing - All costs for internal processing For DRC The following three types of task lists would be used: Business Blueprint Document Page 33 of 123 • Equipment Task List - have a specific link to a piece of equipment • Functional Location Task List - is assigned to a specific functional location • General Maintenance Task List – These are used for general maintenance tasks. They do not refer to a specific technical object. All three task list types can be used for routine and preventive maintenance. The numbers for equipment task lists and task lists for functional locations are assigned internally. The numbers for general maintenance task lists can be assigned internally or externally. 5.5.4 Configuration data There are no configuration data for task list. RSI PROPOSAL standard settings would be used for DRC. 5.5.5 RSI PROPOSAL Enhancements There no enhancement for task list. RSI PROPOSAL standard settings would be used for DRC. Business Blueprint Document Page 34 of 123 Measurement Points and Counters 5.6 5.6.1 Definition Measuring points describe the physical and/or logical locations at which a condition is described, (for example, the coolant temperature in a Diesel Generator after the coolant has left the water jacket, vibration of the engine etc) 5.6.2 Process Overview (As Is) Only for the few of the equipments and for fleets, measurement points are being used. Measurement readings are not used for preventive maintenance triggering. 5.6.3 Process overview (To Be) Tools that we use to represent the wear and tear of an object, consumption, or the reduction of an object’s useful life are described as counters in the RSI PROPOSAL System (for example, the milometer for a vehicle, or an electricity meter for an electric-powered system). Measurement readings are taken at measuring points in particular measurement units at particular intervals. In Plant Maintenance, measuring points and counters are located on technical objects, in other words, on pieces of equipment or functional locations. For DRC: Standard functionality of RSI PROPOSAL will be used. Standard functionality allows you to maintain the measuring point for equipment/functional locations. The readings of the measurement point can be recorded in the measurement documents 5.6.4 Configuration data No configuration data for measurement point. RSI PROPOSAL standard settings would be used for DRC. 5.6.5 RSI PROPOSAL Enhancement Type of Enhancement Enhancement of User exit IMRC0001 Description An email should be triggered to the concerned person, when the measurement reading crosses the limit. Business Blueprint Document Page 35 of 123 5.7 5.7.1 Maintenance Plan Definition Maintenance plan is the description of the maintenance and inspection tasks to be performed at maintenance objects. 5.7.2 Process Overview (As Is) Currently, a weekly or monthly plan would be prepared for maintenance plan. FMD is using FSI software and TESD is using ‘Whitelink’ software to maintain the maintenance plans. LID is making maintenance plans manually. Business Blueprint Document Page 36 of 123 5.7.3 Process Overview (To Be) Maintenance Plan TESD/FMD/LID Start Equipment Master/ Functional location exists? No Equipment/ Functional location master data Yes Task list exists? Task List No Create Task List Yes Outside SAP 3 Update details as per the Maintenance Plan master data template Not approved 4 Get the approval Approved Create Maintenance Plan Single Cycle Multiple counter Strategy 5 5 Create Single cycle plan (If the number of records are less than 25, create them manually or use BDC) 5 Create strategy Plan (If the number of records are less than 25, create them manually or use BDC) Create multiple counter plan (If the number of records are less than 25, create them manually or use BDC) Maintenance Plan Roles: 1,2, 3 - User Department 4 – As per the approval authority 5 – Master data controller End Business Blueprint Document Page 37 of 123 5.7.3.1 Process Overview Description The maintenance plans describe the dates and scope of the tasks. A maintenance plan is used to generate a call object automatically for a particular date. A call object can be a maintenance order or maintenance notification. You can create maintenance plans for the technical objects in your company, thereby ensuring that your technical objects function optimally. The maintenance plan you use depends on the type of maintenance planning that you would like to use in your plant. Maintenance Plan has maintenance item and scheduling data. The maintenance item contains the following data: • Planning data: Maintenance planning plant, maintenance planner group, order type, maintenance activity type, main work center • Reference object • Task list The scheduling data consists of following details: Cycle start: Start date for calculating planned and call dates. Call horizon: Determines when a maintenance call object (for example, a maintenance order) should be generated for a waiting maintenance call. Scheduling period: Determines the period of time, for which the system generates planned or call dates during scheduling. Shift factors: The shift factors for early/delayed confirmation of a maintenance task define what percentage of the shift should be considered for the next date. Tolerances for shift factors: The tolerances for early/delayed confirmation define the time period, for which positive or negative differences between actual and planned dates do not affect subsequent scheduling. Scheduling indicator: Specifies the type of time-based scheduling involved A maintenance plan can consist of several maintenance items. In this case, an order (or notification) is created for each maintenance item. You can Start, Restart, Schedule, Manually call or deactivate a maintenance plan. For DRC: The following three types of maintenance plan would be used: - Maintenance planning with single cycle - Maintenance planning with strategy - Maintenance planning with cycle of different dimensions Maintenance planning with single cycle Business Blueprint Document Page 38 of 123 A single cycle plan is the simplest form of maintenance plan. You create a single cycle plan and define exactly one time-based or performance-based maintenance cycle, in which you specify the interval at which the maintenance plan should be executed. It might be used, for example, for the annual maintenance of a car or for the repair of a photocopier after every 10,000 copies. Maintenance planning with strategy You create a strategy plan and assign a maintenance strategy in which you have defined the maintenance packages. A maintenance strategy contains general scheduling information, and can therefore be assigned to as many maintenance plans and maintenance task lists as required. For example, it makes sense to use a strategy plan if different maintenance tasks for a car are due in different cycles: oil check every 1,242.74 mi, oil change every 6,213.71 mi. Multiple counter plan A multiple counter plan is a maintenance plan that can have cycles of different dimensions (for example, time and distance). You can assign cycles freely to the multiple counter plan. A strategy cannot be used here and a maximum of one time-based cycle can be used within a multiple counter plan. 5.7.4 Configuration data There is no configuration data for maintenance plans. RSI PROPOSAL standard settings would be used for DRC. 5.7.5 RSI PROPOSAL Enhancement No enhancement for maintenance plan Business Blueprint Document Page 39 of 123 5.8 Codes and Catalogs 5.8.1 Definition Catalogs are used to manage, uniformly define, and standardize information (for example, defect types, follow-up actions, tasks or characteristic attributes) on a client-wide or plant-wide basis for a notification. 5.8.2 Process Overview (As Is) Currently, no concept of codes and catalog is being used in DRC 5.8.3 Process Overview (To Be) The catalogs can help you to record and subsequently evaluate qualitative data, and to describe problems. Catalog: Combination of code groups, grouped together according to content (for example, damage and cause of damage). Code groups: Combination of code groups, grouped together according to content (for example, damage to vehicles, pumps, motors) or mechanical damage and electrical damage. Codes: Description of damage and activity. Advantages of catalogs: • Reduction in number of incorrect entries • Statistical evaluations are possible using the standard analyses in the Plant Maintenance Information System All the activities types can be codified into ‘Codes’ and report such as list of notification can be generated for each code. 5.8.4 Configuration data Required codes and catalogs would be created during realization phase. 5.8.5 RSI PROPOSAL Enhancement There are no enhancements for codes and catalogs. Standard RSI PROPOSAL settings would be used. Business Blueprint Document Page 40 of 123 6 Maintenance Processing-General Data 6.1 Definition The Maintenance Processing –General Data is the details on the documents i.e. Maintenance Notification and Maintenance Order required to carry out the maintenance activity. The maintenance process cycle consists of five steps: Step 1: Notification of a damage or request for particular work (for example, a new construction) Step 2: Creation and planning of an order based on the notification. Typical planning tasks include creating operations, making reservations for spare parts, or planning execution times. Step 3: Order control with availability check, provision of capacity, printing of order papers. Step 4: Actual execution of the work that was requested, including withdrawal of spare parts from the warehouse and execution of the order. Step 5: Completion of the work that was actually performed with confirmation and documentation of technical findings in order to record the condition of the technical object. The order is settled in Controlling. 6.2 Process Overview (As Is) For processing maintenance activity work order is being used. Work order contains the details such as work requested, facility, contact person, type of activity etc. Business Blueprint Document Page 41 of 123 6.3 Process Overview (To Be) Notification Notifications are used to convey maintenance requirements and the documentation for technical findings and activities performed. A Notification is used to • Describe the exceptional technical condition at an object • Request the maintenance department to perform a necessary task • Document work that has been performed Maintenance notifications document maintenance tasks completely, and make them available for analysis in the long term. You can use them for preliminary planning and execution of tasks. Each maintenance notification contains header data. Header data is information used to identify and manage the maintenance notification. This data is valid for the entire maintenance notification. You enter and maintain data in the notification item sub-screen area to specify object parts, damage and cause in detail. A notification can identify several items for which similar data can be maintained. Action Box Action Box contains the ‘Tasks’ and ‘Activities’ and are assigned to notification type. These are available at header level when processing notifications. When the function is called up, the system copies the task or activity defined into the notification. The following Notification types would be used for DRC Notification Description Remarks Service Request This Notification type is used for Type SR registering any maintenance request from the facility. SN Service Request- Non Maint. This Notification type is used for registering any non maintenance request from the facility. This Notification type will have one level of approval Business Blueprint Document Page 42 of 123 M1 Maintenance Request This Notification type is used for processing any maintenance activity other than facility request. This will be mainly used by TESD. M2 Breakdown Notification This notification is used for registering any breakdown of the equipment. N1 Inspection Notification This Notification would be used for processing and recording the inspection details of newly arriving vehicles. SY Survey Notification This Notification is used for period survey of customer satisfaction. AR Accident Report This Notification would be used for making a report on vehicle accidents. This will have one level of approval. Maintenance Order Maintenance Orders are used for detailed planning of tasks and their accompanying documentation. The order is a document which is used for planning, scheduling and executing of the maintenance task. Order captures the details of the resources consumed for the maintenance. The order is created independently using separate transaction code or directly from the notification. Orders are also triggered automatically by the system based on the maintenance plan You can use an order to: • Plan tasks in detail with regard to type, scope, dates and resources • Monitor the execution of tasks • Define rules for account assignment, settlement and budgets • Enter, assign and settle the costs which arise from tasks Some of the data on the Maintenance order are: • Header data is information that serves to identify and manage the maintenance order. It is valid for the whole maintenance order - for example, the number, description and type Business Blueprint Document Page 43 of 123 of order, scheduled dates for order execution, priority of tasks, creator, and the last person who changed the order. • Object List consists of functional locations and/or pieces of equipment and/or assemblies. You can enter these objects in the order header as reference objects and/or in the object list • Operations are used to describe the work to be performed when the maintenance order is executed. (For example, work center, standard time, control key) • Materials are spare parts, which are required and used or consumed when the maintenance order is executed • Cost data provides information on how high the estimated, planned and actual costs are in the value categories, which cost elements are relevant for the order etc The following Order types would be used for DRC Order Type PM01 Description Reactive Maintenance Remarks This Order type would be used for processing any type of maintenance requests PM02 Routine Maintenance This Order type would be used for processing the routine jobs. PM03 Preventive Maintenance This Order type would be used for processing planned activities. These automatically maintenance orders triggered from are the maintenance plans and users are not supposed to create it manually. PM05 Calibration Order This Order type would be used for processing the testing/inspection tool calibrations. Control key Business Blueprint Document Page 44 of 123 The control key is a default value which defines how an operation should be processed. The following are the some of the control function of the control key: Function Description External Controls whether an operation or sub-operation is processed externally. processing Schedule Controls whether an operation is scheduled or determines the time position of a sub-operation. Service Controls whether you can plan services for an operation. Maintenance activity type A key for the type of maintenance activity provided. Activities are divided into repairs, shutdowns, regular activities, inspections and so on. In cost evaluations (total costs, number of orders per technical object) you can differentiate the data using the maintenance activity type. For DRC: For example Routine, Breakdown, Plumbing, Painting etc would be used. Status Management You can use status management to describe and recognize whether particular business transactions can be performed for an object. There are two types of status: o System Status o User Status System Status: System statuses are set internally by the system within the framework of general status management when you perform certain business transactions. They inform you that a certain Business Blueprint Document Page 45 of 123 business transaction was performed on an object, which enables you to determine which business transactions you can now perform on the object as a result of this status. In Plant Maintenance module, system statuses are available for the following objects - Notification - Tasks on Notification - Order - Operation on order - Equipment master data - Functional location master data User Status: These statuses are defined by the user and can be used to further limit the business transactions allowed by the various system statuses. You can assign and delete any user statuses that have been defined in your system provided you have the appropriate authorization. In Plant Maintenance module, system statuses can be defined for the for the following objects - Notification - Tasks on Notification - Order - Operation on order - Equipment master data - Functional location master data For DRC user status will be defined for Maintenance Order and Equipment/Fleet Master. Object information You can use the object information to obtain a swift overview of the condition and history of the object concerned. The dialog box contains data (where available) about the classification of the object. It displays statistics for the maintenance notifications related to the object and the last three maintenance notifications entered for this object with short text, date, and completion. You can also call up information about orders, maintenance items, and maintenance dates Business Blueprint Document Page 46 of 123 Priority A priority can be assigned to each maintenance order and notification. This priority determines the required start date and end dates of the notification or order, relative to the creation date. In maintenance processing you can work with internal priority types for notifications and orders. Action Log Changes to notifications, orders, equipment, and functional locations are displayed in chronological order in an action log. This enables you to track who has changed the data or status of specific fields and when they were changed. To use this function, the respective change documents created (for each object, status, or partner) must be active. Document flow All the document types created for the order can be displayed under document flow such as: - Notification - Completion confirmation - Goods movement - Purchasing requisition - Purchase order Note: To start the maintenance processing, respective master data and WBS element is required. For example for the facilities, functional location and WBS element should exist before starting the maintenance process on RSI PROPOSAL. Business Blueprint Document Page 47 of 123 6.4 Configuration Data Control Key Control key PM01 PM03 Function Processing Internal Activity Processing External Services Status for Equipment Master Data Status No Code Description Remarks 10 INIT In Operation With this user status, it is not possible to set the Deletion indicator to the equipment master 20 SCRP Scrapped With this user status, it is not possible to create Maintenance order/Notification 30 SOLD Sold With this user status, it is not possible to create Maintenance order/Notification 40 OBS Obsolete With this user status, it is not possible to create Maintenance order/Notification Status for work orders Similar to the equipment master record, work order also have the system status and user status. For DRC: Following user status would be used for orders Status No Code Description Remarks 10 INIT Initial Technical Completion is not allowed for this user status 20 WIPS Work under progress at site Technical Completion is not allowed for this user status Business Blueprint Document Page 48 of 123 6.5 30 WIPW Work under progress at workshop Technical Completion is not allowed for this user status 40 WTFM Waiting for materials Technical Completion is not allowed for this user status 50 WFAP Waiting for approvals Technical Completion is not allowed for this user status 60 ROUT Sent out for repair Technical Completion is not allowed for this user status 70 TEMP Temporarily released Technical Completion is not allowed for this user status 80 JOBC Job Completed Only with this status technical completion is allowed. RSI PROPOSAL Enhancement There are no specific enhancements for this process. Business Blueprint Document Page 49 of 123 7 Preventive Maintenance Process (MNT01A) 7.1 Definition Preventive maintenance process is the one which is carried out periodically to ensure the high availability of technical systems, for example, equipment, fleet, or any other facility such as land and irrigation system. As the name indicated, all the activities along with the resources are planned in advance 7.2 Process Overview (As Is) On a periodic basis, each department is preparing a preventive maintenance plan. Work orders are created to carry out the activity. This work order has the details of the jobs carried out, material, labor required etc. Upon the completion of the activity quality inspection is carried out. After the satisfactory completion of the job, work order will be updated with jobs carried out. Once the job is completed, work order will put in history. Following processes are covered from the as-is document TESD General Process Preventive Maintenance Quality control in preventive maintenance - This is covered in separate process ‘Quality Inspection (MNT01F’) Equipment safety certification FMD General Process – Preventive Maintenance LV Electrical System health check up Lifts Systems Testing of Generators Control of Inspection, measuring and test equipments – This process is covered in a separate process ‘Calibration Process (MNT01G) Fire sprinkler testing system Fire alarm and Evacuation system Testing of fire hose reels and risers Cleaning LID General Process – Preventive Maintenance Business Blueprint Document Page 50 of 123 7.3 Process Overview (To Be) Preventive Maintenance (MNT01A) TESD/FMD/LID PCD Start 1 Create, Task list, maintenance plan 2 Schedule the maintenance Plan 3 B Auto triggering of maintenance order and/or Notification based on the scheduling data 4 Maintenance Order/Notification Release the order Development An auto mail would be triggered to Supervisor/ Engineer/Foreman Is material required No Yes Development 6 Material Reservation Slip Approval for the material reservation number 8 Print the material reservation number Purchase requisition for Materials (PRC01A) A Roles 1,2,4 – Maintenance Planner 8- Foreman/Engineer/Supervisor 6 – As per the delegation of authority Business Blueprint Document Page 51 of 123 FI/CO Preventive Maintenance (MNT01A) TESD/FMD/LID PCD FI/CO A Job done by Internal/ External manpower? External Auto triggering of Purchase Requisition Purchase Requisition Purchase requisition for services (PRC01A) Internal Development 9 Print the Work order and task list/Gate pass Work order Print Gate Pass Print for Warranty/outsourced repair Outside SAP 10 Perform the job Quality Inspection Process (MNT01A) No Is quality OK? Yes 11 WO Confirmation Confirmation Number Settlement Process 12 Technical completion B 13 Business completion End End Roles: 9, 11, 12 - Foreman/Engineer/Supervisor 10 – Technician 13 – Maintenance Planner Business Blueprint Document Page 52 of 123 7.3.1 Process Overview Description Preventive Maintenance Planning This is the first step in the preventive maintenance processing. This step involves creation of master data and maintenance plan etc. Check whether master data exists for technical object (equipment/fleet/functional location) on which you want to process the preventive maintenance. If the master data does not exist, create a master data for the technical objects and also create other master data such as such as maintenance item, task list and maintenance plan. If all the master data are available, schedule the maintenance plan. Scheduling of the maintenance plan refers to the starting of a maintenance plan. Based on the scheduling data on the maintenance plan, system give you list of planned date for the respective maintenance plan. Once the planned date is reached, system automatically triggers a maintenance order or maintenance notification depending on the call object set on the maintenance plan. Preventive Maintenance Scheduling This is the second step in the Preventive Maintenance processing. This process involves releasing of the order and maintaining the settlement rule on the work order. All the orders triggered are available as list. From the list, you can select the order to be processed and go to order change mode. In the work order you can enter additional operations, components etc (apart from the task list attached) if required. For the equipment which is under warranty, you can see the details from the object information on the notification or order header. Release the maintenance order. As soon as the work order is released an email will be triggered to the concerned engineer/supervisor/foreman. This is not a standard functionality of RSI PROPOSAL. This will be done through workflow. To trigger an email to the concerned person, ID of the responsible person should be maintained either on the equipment master record as partner function or on the maintenance order header as ‘person responsible’ A provision would be provided to access the RSI PROPOSAL through the web on the PDA. Supervisor/Engineer/Foreman would be able to access the RSI PROPOSAL with limited Business Blueprint Document Page 53 of 123 functionality on his PDA. There would be a custom screen to access RSI PROPOSAL with only few fields which would be developed during realization phase. Preventive Maintenance Execution This is the next step in preventive maintenance processing. Execution part involves, printing the Material Request, getting the material from warehouse, sending the technician to the site to carry out the maintenance activity. For stock items, a reservation number will be generated by the system (Similar to the existing MR number). Reservation number will have approval process as per the existing level of authority. Get the approval from the necessary authority. Print the reservation number and get the signature from the concerned person and handover it to warehouse. If the stock is available, Warehouse pDRCple will issue the material against the reservation number. For non stock item, a purchase requisition will be generated by PCD. This purchase requisition will have release strategy (approval process based on the existing level of authority). Further processing of purchase requisition will be done in MM. For more detail, please refer the document “Purchase requisition process (PRC01A)” For activities carried out internally, a confirmation number will be generated, which will be used for confirmation of the internal activity. For external activity, a purchase requisition will be triggered by the system. This purchase requisition will have release strategy (approval process based on the existing level of authority). Further processing of purchase requisition will be done in MM. For more detail, please refer the process “Purchase requisition process (PRC01A)” of MM to-be document. Print the work order/task list and execute the work. For equipment which are under warranty or the equipments which are to be sent to outside for repair, Gate pass printing provision would be provided. (This Gate pass printing is only for the equipments and not for the employees). Quality Inspection during Preventive Maintenance This step involves, inspecting the maintenance activity against some predefined standards. For quality inspection details, please refer the process ‘Quality Inspection Process (MNT01F) Business Blueprint Document Page 54 of 123 Confirmation During confirmation process, all the activities will have to be updated on the work order/Notification. Once the job is completed and quality is satisfactory, do the order confirmation. Confirmation involves: - Recording the actual time of the work performed by the internal manpower. - Recording the technical findings of maintenance activity on the notification. - Recording the measurement point/counter readings - Creation of the service entry sheet for the activity/service done by the external vendor and accept the service entry sheet. Further processing of service entry sheet will be done in MM. Completion This step involves completing the order from technical perspective and business perspective. • Technical completion of the order means, the work order is completed technically, i.e the work order is updated with all the details of the jobs carried out. The work order editing is no more after technical completion. System will set the work order status as ‘Technically complete’. Technical completion can be cancelled if required. Once the order is technically completed, system will schedule the next call date for the maintenance plan. • Settlement of the order refers to the transferring of the actual cost from order to receiving object. (In case of DRC, WBS is the receiving cost object). Settlement of the actual cost will be done either after the confirmation or after the technical completion. Order can be settled either partially or fully. • At the end of the financial year, close (business completion) the work order. System will set the order status as ‘Closed’. After the business closure no more cost will flow to the maintenance order. It is possible to reset the status. Business Blueprint Document Page 55 of 123 7.4 Configuration Data Order type Order Type Maintenance Code Description PM03 Preventive Maintenance Priority Following priorities would be used for maintenance order and notifications Priority type 7.5 Code Description PM 1 Very high PM 2 High PM 3 Medium PM 4 Low RSI PROPOSAL Enhancement Following enhancements are required to meet the business requirement Type Description Remarks Workflow Work order status ‘Released’ A mail should be triggered to the person responsible on the work order Form Work order print out for FMD/LID Maintenance person should be able to print the work order. Form Work order print out for TESD Maintenance person should be able to print the work order. Business Blueprint Document Page 56 of 123 8 Reactive Maintenance (MNT01B) 8.1 Definition Reactive maintenance process is the one which is carried out to restore the normal condition of the equipment. This may be small repair, break down repair or any request from the facilities. 8.2 Process Overview (As Is) Reactive maintenance starts with logging call against the customer complaint. It may be break down maintenance, corrective maintenance or may be a repair work. The reactive maintenance is carried out either at site (Facility) or at work shop. Following reactive maintenance processes are covered from as-is document: TESD General Process – Reactive Maintenance Breakdown repair of vehicle and equipment Quality control in break down jobs – This process is covered under separate ‘Quality Inspection’ process (MNT01F) Outsourced repair Warranty repair Maintenance and repair of Boats and Jet skies Marine Services during Events – This process is a part of PS module. Please refer the PS process documents (PRJ01A-C and PRJ02, PRJ02A-C) FMD Facilities request for services – Maintenance Work Facilities request for services – Non Maintenance Work - Critical Facilities request for services – Non Maintenance Work – Non Critical LID General Process – Reactive Maintenance Business Blueprint Document Page 57 of 123 8.3 Process Overview (To Be) Reactive Maintenance (MNT01B) FMD/TESD/LID PCD Start Development Out side SAP 1 Receive the call from the customer Print Notification Log a call and upon saving an auto mail would be triggered to the employee responsible Maintenance Notification 2 Access through PDA 3 Maintenance Order Create maintenance order Plan for the resources 4 Release the order Development An auto mail would be triggered to Supervisor/ Engineer/Foreman Is material required No Yes Development 5 Approval for the material reservation number Material Reservation slip 6 Print the Reservation number Purchase requisition for Materials (PRC01A) Job done by Internal/ External manpower? Internal External Auto triggering of Purchase Requisition Purchase Requisition Purchase requisition for services (PRC01A) A Roles 1, 2 - Call Center Agent 3,6 – Foreman/Engineer/Supervisor 4 – Maintenance Planner 5 – As per the delegation of authority Business Blueprint Document Page 58 of 123 FI/CO Reactive Maintenance (MNT01B) FMD/TESD/LID PCD FI/CO A Development 7 Print the Work order and task list /Gate pass Work order Print Gate Pass Print for Warranty/ outsourced repair Outside SAP 8 Perform the job No Quality Inspection Process (MNT01F) Is quality OK? Yes Confirmation Number 9 WO Confirmation Settlement Process 10 Technical completion 11 Business completion End End Roles 7,9,10 – Supervisor/Foreman/Engineer 8 – Technician 11 - Maintenance Planner Business Blueprint Document Page 59 of 123 8.3.1 Process Overview Description Call logging process: Call logging process involves the following steps: Receive the call from the client/user/operator Log the call. Logging the call is the creation of the notification. Details such as description of service requested, location, reference object, reported by, time by when the service is required, priority etc will be maintained on the notification. Upon saving the notification, a document number would be generated by the system. This is the reference number for processing all other activity. At the same time an auto mail would be triggered to the employee. This is not a standard functionality of RSI PROPOSAL. This will be done through workflow. To trigger an email to the concerned person, ID of the responsible person should be maintained either on the notification or on the equipment master record as partner function. There would be provision to print the Notification. For SMS functionality, through workflow as soon as the call is created and saved, an auto email would be triggered to the SMS service provider. Service provider in turn will trigger SMS to the respective mobile number. (As it is there in the as-is process). It is the responsibility of DRC to get the service from the SMS service provider. The Foreman/supervisor/Engineer would be able to access the call on PDA (Personal Digital Assistant). This is not a RSI PROPOSAL standard functionality. Provision would be give to the user to access RSI PROPOSAL over web with limited functionality. There would be custom screen, which will have only necessary fields which would be required by the field pDRCple to get the necessary information of the job requested. CIC: Customer Interaction Center: CIC is used for integrating the telephone technology with RSI PROPOSAL. CIC provided direct interaction with the client from RSI PROPOSAL. The detailed feature would be provided during realization phase. Maintenance Planning The following steps are involved in maintenance planning phase Business Blueprint Document Page 60 of 123 Create a Maintenance order from the notification, if spares and other resources are required. Enter the components (material required) required and quantity of the material. A reservation would be generated for the materials. Plan the activity in detail. Enter the man hours required for each activity. A confirmation number would be generated by the system for each operation If the activity is carried out by the external manpower (services), select the corresponding control key (PM03) and enter the required service master record. Enter the list of operations to be carried out, material required or external services required. Maintenance Scheduling Maintenance Scheduling involves, the following steps Release the maintenance order. As soon as the work order is released an email will be triggered to the concerned engineer/supervisor/foreman. This is not a standard functionality of RSI PROPOSAL. This will be done through workflow. To trigger an email to the concerned person, ID of the responsible person should be maintained on the equipment master record as partner function. For stock items, a reservation number will be generated by the system. Reservation number will have approval process as per the existing delegation of authority. Get the approval from the concerned authority. Maintenance Execution This is the next step in maintenance processing. Execution part involves, printing the Material Request, getting the material from warehouse, sending the technician to the site to carry out the maintenance activity. For stock items, a reservation number will be generated by the system (Similar to the existing MR number). Reservation number will have approval process as per the existing level of authority. Get the approval from the necessary authority. Business Blueprint Document Page 61 of 123 Print the reservation number and get the signature from the concerned person and handover it to warehouse. If the stock is available, Warehouse pDRCple will issue the material against the reservation number. For non stock item, a purchase requisition will be generated by PCD. This purchase requisition will have release strategy (approval process based on the existing level of authority). Further processing of purchase requisition will be done in MM. For more detail, please refer the document “Purchase requisition process (PRC01A)” For activities carried out internally, a confirmation number will be generated, which will be used for confirmation of the internal activity. For external activity, a purchase requisition will be triggered by the system. This purchase requisition will have release strategy (approval process based on the existing level of authority). Further processing of purchase requisition will be done in MM. For more detail, please refer the process “Purchase requisition process (PRC01A)” of MM to-be document. Print the work order/task list and execute the work. Quality Inspection This step involves, inspecting the maintenance activity against some predefined standards. For quality inspection details, please refer the process ‘Quality Inspection Process (MNT01F) Confirmation Once the job is completed and quality is satisfactory, do the order confirmation. Confirmation involves: - Recording the actual time of the work performed by the internal manpower. This done through activity confirmation. - Recording the technical findings of maintenance activity on the notification. - Recording the measurement point/counter readings - Creation of the service entry sheet for the activity/service done by the external vendor and accept the service entry sheet. Further processing of service entry sheet will be done in MM. Business Blueprint Document Page 62 of 123 Completion This step involves completing the order from technical perspective and business perspective. • Technical completion of the order means, the work order is completed technically, i.e the work order is updated with all the details of the jobs carried out. The work order editing is no more after technical completion. System will set the work order status as ‘Technically complete’. Technical completion can be cancelled if required. Once the order is technically completed, system will schedule the next call date for the maintenance plan. • Settlement of the order refers to the transferring of the actual cost from order to receiving object. (In case of DRC, WBS is the receiving cost object). Settlement of the actual cost will be done either after the confirmation or after the technical completion. Order can be settled either partially or fully. • At the end of the financial year, close (business completion) the work order. System will set the order status as ‘Closed’. After the business closure no more cost will flow to the maintenance order. It is possible to reset the status. Equipments under Warranty Warranty details should be maintained on the equipment master record. While creating Notification or Order, if the equipment under Warranty is entered as reference object, a message will be popped up in a separate window. If the equipment is not under warranty, this message will not be displayed. On the work order, enter the maintenance activity type as ‘warranty repair’. If the equipment to be sent outside for warranty repair, print the gate pass, and set the user status of the work order as ‘sent out for repair’. All other process steps are similar to the above process. Facilities Request for Services – Non Maintenance Work – Critical and Non Critical There would be a separate Notification type ‘SN- Service Request – Non Maintenance’ to process the non maintenance requests. This Notification type will have one level of approval. Until the Notification is approved, user will not be able to create a work order for this notification. Once the call is approved, further processing such as creation of the work order etc will follow the same procedure as normal service request. Priority on the Notification indicates the criticality of the call. Note: Call center persons have to decide whether it is maintenance or non maintenance request before creating a Notification, since changing of the Notification type after saving is not possible. Business Blueprint Document Page 63 of 123 Configuration Data 8.4 Order Type Order type Description PM01 Reactive Maintenance Number Range for Order type Number range Order Type From To Int/Ext 01 PM01 2000000 2999999 Internal Notification Type Notification type Description SR Service Request SN Service Request – Non Maintenance Number Range for Notification Type Number range Notification type From To Internal/External 01 SR, SN 2000000 2999999 Internal Priority Please refer the Preventive Maintenance Process. Same priority type would be used for Reactive Maintenance order too. 8.4.1 RSI PROPOSAL Enhancement Following enhancements are required: Type Triggering point Description Workflow Work order status ‘Released’ A mail should be triggered to the person responsible on the work order Business Blueprint Document Page 64 of 123 Form Work order print out for FMD/LID Maintenance person should be able to print the work order. Form Work order print out for TESD Maintenance person should be able to print the work order. Workflow Service Request created Upon creation of the service request a mail should be triggered to the person responsible maintain on the notification header. Business Blueprint Document Page 65 of 123 9 Quality Inspection (MNT01F) 9.1 Definition To ensure that the job is carried out satisfactorily, quality inspection is carried out. 9.2 Process overview (As Is) Once the maintenance activity is over, quality inspector will be intimated to inspect the quality of the work. Quality inspector inspects the quality of the work. If the quality is not as per the norms, QI will prepare a non confirmatory report and give the feed back to respective foreman. Foreman will get it rectified with the help of technicians. Non confirmatory report along with action taken will be sent to Director of the respective Department. Business Blueprint Document Page 66 of 123 9.3 Process overview (To Be) Quality Inspection TESD/FMD/LID Start Is notification Exist for Order 1 Yes Create a Notification 1 Assign the task, ‘Inspection request’, select the ‘employee responsible’ in the Notification Development A mail would be triggered to the employee responsible, requesting for the inspection 2 Quality Inspector will inspect the job and update as ‘Activity” done on the Notification 3 Set ‘Task’ ‘Quality Inspection Complete” in Notification Yes Is quality OK Development No A auto mail would be triggered to the ‘Person responsible’, which is entered on the Notification Header 4 Enter the task ‘Rework required’ , Enter any comments, explanation in the long text field. Development Auto mail would be triggered to the employee responsible End 5 Perform job and update it on notification 6 Set the task as ‘Inspection Request’ again and enter the ‘Person responsible’ Development Auto mail to ‘Person responsible’ Roles: 1,5,6 – Supervisor/ Engineer/Foreman 2,3,4 – Quality inspector Business Blueprint Document Page 67 of 123 Notification Process Description 9.3.1 • Quality inspection process starts with the completion of the maintenance activity. Check whether a Notification exists for the work order (Maintenance order). If the notification exists, proceed to the next step. If the notification does not exist, create a maintenance notification from the order. Header data of the order will be copied to the Notification. Quality inspection makes use of Notification and codes and catalogs. • On the Notification, enter ‘Task’ as ‘Inspection request’; System will prompt you to enter the employee responsible. Enter the employee who is responsible to carry out the Quality Inspection. • A mail would be triggered to the person responsible, entered on the task. This is not a standard RSI PROPOSAL feature. This will be done through work flow. • Quality Inspector will inspect the job carried out and enter the inspections done on the Notification as ‘Activity’. • If the quality is not satisfactory, QI will enter the ‘Task’ as ‘Rework required’. Additional comments can be maintained as long text for each task. • An auto mail would be triggered to the ‘person responsible’ who is maintained on the Notification header. This is not a standard RSI PROPOSAL feature. This will be done through work flow. • Carryout the rework, if any. Once the rework is over, enter the task ‘Inspection request’ once again. Auto mail would be triggered to the QI. This cycle is repeated until the quality of the job is satisfactory. • Once the quality of the job is satisfactory, QI will set the ‘Task’ as ‘Quality complete’. • Again an auto mail would be triggered to ‘person responsible’ who is maintained on the notification header. This is not a standard RSI PROPOSAL feature. This will be done through work flow. • Enter any other technical findings on the notification. • Once the job is over, close the notification along with the work order. Note: The above QI process is same for both quality inspections carried out at site and at work shop. The work order will have the user status whether the work is being carried out at site or at work shop. Business Blueprint Document Page 68 of 123 9.4 Configuration Data Notification type Notification type defined in the Preventive, Routine and Reactive Maintenance processes would be utilized for inspection process also. Number Range for Notification types Please refer the respective maintenance processes. Codes and catalogs Required codes and catalogs would be created during realization phase. Business Blueprint Document Page 69 of 123 9.5 RSI PROPOSAL Enhancement Following enhancements would be required to meet the business process. Type of enhancement Triggering point Description Workflow Task- ‘Inspection Requested’ A mail should be triggered to the person responsible enter for the task. Workflow Task - ‘Rework required’ A mail should be triggered to the person responsible on the Notification header Workflow Task-‘Inspection Complete’ A mail should be triggered to the person responsible enter for the task. Business Blueprint Document Page 70 of 123 10 Cost Allocation (MNT01C) 10.1 Definition Cost allocation refers to the actual distribution of the cost to the respective cost object such as to a cost center or to a WBS element. 10.2 Process Overview (As Is) Currently, there is no auto allocation of the cost to the respective cost center/project. A periodic cost summery is created on manpower, services and material and will be allocated to the respective Project/Facility. Business Blueprint Document Page 71 of 123 10.3 Process Overview (To Be) Cost Allocation (MNT01C) TESD/LID/FMD Start Internal Manpower cost Internal Manpower activity confirmation Material Cost External Services Cost Equipment Purchase Requisition process (PRC01A) Purchase Requisition process (PRC01A) Hiring process (FLT01) Actual Cost on Maintenance Order Periodic Settlement of maintenance Order Actual Cost on WBS Periodic settlement of WBS Actual Cost on Respective Cost center End Business Blueprint Document Page 72 of 123 10.3.1 Process Description • Value concept in Plant maintenance Based on the type of task (order type) and the processing stage, the values in the order can be differentiated according to costs, activities and settlements. Costs: In general, costs refer to the consumption of resources in order Activities: Activities are the result of the products and services required to execute an operation. Settlements: Settlements are the partial or complete transfer of costs from one object to another. The maintenance order is debited with costs at the rate of the respective resources consumed. Settlement means that the order is credited by transferring costs to another object. You can differentiate between the following costs, depending on the stage of order processing: Estimated costs In resource-independent order planning, you can specify the expected costs for an order. The estimated costs are entered manually in the order. Planned cost The system automatically determines planned costs for the order when order-specific resources are scheduled (operations with internal service, materials...). You cannot maintain planned costs manually. Actual costs Since resources (internal services, materials...) are consumed for an order, the order is automatically debited with actual costs during costing. You cannot enter actual costs manually. Both planned and actual costing procedures use specific rules for putting a value on resources. the value placed on internal service assigned to an operation is calculated from the rate assigned to the activity type for this purpose. For stock materials, the price is taken from the material master records. • Cost Views on Plant maintenance order Business Blueprint Document Page 73 of 123 Two views with differing levels of detail are used to monitor costs in the maintenance order: The cost report displays costs according to cost elements and thereby reflects the cost accounting view. You can also identify quantities here. MorDRCver, you can identify the amounts debited and credited during settlement. The cost overview displays the order costs in a condensed form, for example, after all the cost elements for stock materials have been combined into one value category for stock withdrawals. The focus here is more on displaying costs by type of resource rather than on account assignment of individual resources. You cannot identify quantities and credits here In addition to identifying the costs incurred by a specific cost element, you can also use the cost report to analyze which planned or consumed resources were responsible for planned or actual costs • Order Settlement You can use the maintenance order as an instrument for planning and executing maintenance work. This means that the order initially bears all the costs that result from the planning and consumption of resources. The costs generated by consuming the resources required appear on the debit side of the order as actual costs Depending on the type of task, the order is settled to its actual originator and credited with the costs of resources consumed. Order costs are borne by another receiver which is also a cost accounting object (For example Cost center, WBS element) A fully settled business transaction can be further debited by actual costs. This is particularly the case for orders that extend over a number of posting periods. This means that the balance of actual costs for the order is once again greater than zero and can be evened out with another settlement. The system allows you to perform a settlement, so long as you have not fully completed the order. For DRC order will be settled to the respective WBS element. • Option for order completion Business Blueprint Document Page 74 of 123 The completion of an order consists of many steps: The order is technically completed from a maintenance perspective as soon as all the necessary tasks have actually been executed. No cost flows take place in this case. Only the settlement rule is defined here, if it has not already been specified. You can no longer modify the order. After technical completion, you can settle the order when you choose. The order is credited with the actual costs. It is possible to debit the order with additional costs and then make another settlement. A fully settled order (that is, when the actual costs are equal to zero) can be fully completed, in other words, completed from a business perspective. After this point, you can no longer debit the order with actual costs. However, it is possible to reset this status. Material Cost: Actual cost of the material comes from the material master record. Once the goods issue happens, actual cost of the material will be allocated to the order automatically. Internal manpower cost: Actual cost of the internal manpower is allocated to the order once the internal activity is confirmed against the order. You can generate the report per operation in an order (like painting, plumbing etc). However these activity types have to be created in FICO, only then you can generate the report. Decision on activity types from the FI is still pending. Alternatively, apart from creating zones as work centers, you can create these groups (painting, plumbing) as work centers and maintain it on operation of the work order. You can generate the cost report for each work centers. Or for each activity, you have to create a separate work orders. External services: Actual cost of the external services will be allocated to the order, once the service entry sheet is accepted. If there is any variation in the cost on invoice, the invoice cost will be updated as actual cost on the maintenance order. Hired Equipment cost: Equipment cost will be directly allocated to respective WBS element. Equipment cost will not flow to the maintenance order. Fuel cost: Fuel cost will initially be posted to a common cost center and subsequently distributed to each project/facility. However consumption quantity for each equipment will be captured through measurement points. Please refer the “Fuel card management (FLT01A)” process. Business Blueprint Document Page 75 of 123 Business Blueprint Document Page 76 of 123 10.4 Configuration Data Value Categories Value categories are used to display the costs on the maintenance order. A consolidated value will be appeared on each value category. Each value category would be assigned to one or more cost elements. Following value categories would be defined Value category code Description Cost element INMN Manpower To be decided INMT Material To be decided SERV External Services To be decided 10.5 RSI PROPOSAL Enhancement No enhancement is required for this process Business Blueprint Document Page 77 of 123 11 Routine Maintenance (MNT01D) 11.1 Definition Routine Maintenance refers to the day to day maintenance activity. These activities are not well planned as in the case of Preventive Maintenance. Also, for Routine Maintenance, there may not be service request from the client as in the case of Reactive Maintenance 11.2 Process Overview (As Is) Currently, only FMD is having routine maintenance processes. Same process can be adopted by the other department, if the similar process exists. Following processes are covered in to-be from as-is documents. FMD Maintenance of Zaabeel Arena- Equestrian Surface Race Night Procedures – Sand Track NAS Tracks and Stables – Camel Race Meeting Godolphin Whether Tack The Turf Track Racing Procedure FMS Race horse training Track Procedure Camel Training Track Routines Turf Track Routines Endurance Training Track Routines Track and Stable Routines Business Blueprint Document Page 78 of 123 11.3 Process Overview (To Be Routine Maintenance (MNT01D) FMD/TESD/LID PCD Start 1 Maintenance Order Create maintenance order Plan for the resources 2 Release the order Development An auto mail would be triggered to Supervisor/ Engineer/Foreman Is material required No Yes Development 3 Material Reservation slip Approval for the material request 4 Print the material reservation Purchase requisition for Materials (PRC01A) Job done by Internal/ External manpower? External Auto triggering of Purchase Requisition Purchase Requisition Internal A Roles 1, 4 – Foreman/Engineer/Supervisor 2 – Maintenance Planner 3 – As per the delegation of authority Business Blueprint Document Page 79 of 123 Purchase requisition for services (PRC01A) FI/CO Routine Maintenance (MNT01D) FMD/TESD/LID PCD FI/CO A Development 5 Print the Work order and task list Work order Print Outside SAP 6 Perform the job No Quality Inspection Process (MNT01F) Is quality OK? Yes Confirmation Number 7 WO Confirmation 8 Technical completion Settlement Process 9 Business completion End End Roles 5,7,8 – Supervisor/Foreman/Engineer 6 – Technician 9 - Maintenance Planner Business Blueprint Document Page 80 of 123 11.3.1 Process Description Routine maintenance starts either with creation of Notification or directly Maintenance Order. The Routine Maintenance process procedure is similar to that of Reactive Maintenance. Maintenance Planning The following steps are involved in maintenance planning phase Create a Maintenance order from the notification, if spares and other resources are required. Enter the components (material required) required and quantity of the material. A reservation would be generated for the materials. Plan the activity in detail. Enter the man hours required for each activity. A confirmation number would be generated by the system for each operation If the activity is carried out by the external manpower (services), select the corresponding control key (PM03) and enter the required service master record. Enter the list of operations to be carried out, material required or external services required. Maintenance Scheduling Maintenance Scheduling involves, the following steps Release the maintenance order. As soon as the work order is released an email will be triggered to the concerned engineer/supervisor/foreman. This is not a standard functionality of RSI PROPOSAL. This will be done through workflow. To trigger an email to the concerned person, ID of the responsible person should be maintained on the equipment master record as partner function. For stock items, a reservation number will be generated by the system. Reservation number will have approval process as per the existing delegation of authority. Get the approval from the concerned authority. Business Blueprint Document Page 81 of 123 Maintenance Execution This is the next step in maintenance processing. Execution part involves, printing the Material Request, getting the material from warehouse, sending the technician to the site to carry out the maintenance activity. For stock items, a reservation number will be generated by the system (Similar to the existing MR number). Reservation number will have approval process as per the existing level of authority. Get the approval from the necessary authority. Print the reservation number and get the signature from the concerned person and handover it to warehouse. If the stock is available, Warehouse pDRCple will issue the material against the reservation number. For non stock item, a purchase requisition will be generated by PCD. This purchase requisition will have release strategy (approval process based on the existing level of authority). Further processing of purchase requisition will be done in MM. For more detail, please refer the document “Purchase requisition process (PRC01A)” For activities carried out internally, a confirmation number will be generated, which will be used for confirmation of the internal activity. For external activity, a purchase requisition will be triggered by the system. This purchase requisition will have release strategy (approval process based on the existing level of authority). Further processing of purchase requisition will be done in MM. For more detail, please refer the process “Purchase requisition process (PRC01A)” of MM to-be document. Print the work order/task list and execute the work. Confirmation Once the job is completed and quality is satisfactory, do the order confirmation. Confirmation involves: - Recording the actual time of the work performed by the internal manpower. This done through activity confirmation. - Recording the technical findings of maintenance activity on the notification. - Recording the measurement point/counter readings Business Blueprint Document Page 82 of 123 - Creation of the service entry sheet for the activity/service done by the external vendor and accept the service entry sheet. Further processing of service entry sheet will be done in MM. Completion This step involves completing the order from technical perspective and business perspective. • Technical completion of the order means, the work order is completed technically, i.e the work order is updated with all the details of the jobs carried out. The work order editing is no more after technical completion. System will set the work order status as ‘Technically complete’. Technical completion can be cancelled if required. Once the order is technically completed, system will schedule the next call date for the maintenance plan. • Settlement of the order refers to the transferring of the actual cost from order to receiving object. (In case of DRC, WBS is the receiving cost object). Settlement of the actual cost will be done either after the confirmation or after the technical completion. Order can be settled either partially or fully. • At the end of the financial year, close (business completion) the work order. System will set the order status as ‘Closed’. After the business closure no more cost will flow to the maintenance order. It is possible to reset the status. Business Blueprint Document Page 83 of 123 11.4 Configuration Data Order Type Order type Code Description Maintenance PM02 Routine Maintenance Number Range for Order type Number range Order Type From To Int/Ext 01 PM02 3000000 3999999 Internal Notification Type Notification type Code Description Maintenance RT Routine Maintenance Number Range for Notification Type Number range Notification type From To Internal/External 01 RT 3000000 3999999 Internal Priority Please refer the Preventive Maintenance Process. Same priority type would be used for Reactive Maintenance order too. Business Blueprint Document Page 84 of 123 11.5 RSI PROPOSAL Enhancement Following enhancements are required: Type Triggering point Description Workflow Work order status ‘Released’ A mail should be triggered to the person responsible on the work order Form Work order print out for FMD Maintenance person should be able to print the work order. Form Work order print out for TESD Maintenance person should be able to print the work order. Business Blueprint Document Page 85 of 123 12 Fleet Management (FLT01) 12.1 Definition Fleet objects include cars, trucks, ships, building machinery and transport containers. Fleet management refers to the entire life cycle management of the fleet i. e. staring from procurement till retirement of the fleet. 12.2 Process Overview (As Is) Currently, custom built software ‘Whitelink’ is being used for managing the fleet. This has the feature of movement tracking of the fleets, fuel card details, image view, monthly lease, warranty details, insurance details, asset disposal, fine entry, tyre replacement, certificate renewal, internal hiring and external hiring process and maintenance data of the fleets and equipments. This is stand alone software and not integrated with other departments. The processes covered in fleet management are Processing for new vehicle Receiving new vehicle Vehicle and Equipment Accident report and Repair Business Blueprint Document Page 86 of 123 12.3 Process Overview (To Be) Fleet management (FLT01) -Processing/Receiving New Vehicle TESD PCD Starrt Outside SAP Receive the request fro new vehicle Prepare request letter Get the approval from the executive management Available in pool of TESD? No Purchase requisition for Materials (PRC01A) Development Print Unit arrival form Equipment Master data Yes 1 Notification Create a Notification for quality inspection Development 2 Trigger an email to the quality inspection Development 5 3 Update the user assigned on the equipment master Comply with EO specification? Yes Development 4 END No Trigger an email to PCD Outside SAP Get it rectified by the supplier Roles 1, 2, 5 – Fleet services 3,4 – Quality Inspector Business Blueprint Document Page 87 of 123 12.3.1 Process Overview Description Processing for New Vehicle The following processes have to be handled outside RSI PROPOSAL. a. Initiating for the new vehicle b. Initial approval from HOD and DoTESD for the initiation request c. Getting the approval from the Executive management Once the request is approved by the executive management, following steps will be done on RSI PROPOSAL a. Check whether requested equipment is available in the pool from the equipment status b. If the equipment is not available in the pool, request for the creation of the asset master record to finance department. c. With reference to this asset, create a purchase requisition. The purchase requisition will have to be created against a internal order. If the internal order does not have enough budgets, system will not allow the user to save the purchase order. This purchase requisition will have approval process as per the existing authorization limit (Release strategy) d. Get the approval on purchase requisition from HOD and DoTESD. Inform the PCD on the request. e. PCD will arrange for leasing or procuring and get the quotation from the vendor. Hard copy of the quotation will be sent to TESD f. Get the approval from HOD and DoTESD on hard copy and forward it to PCD. g. PCD will create a service purchase order and arrange for leasing or procuring new vehicle/equipment. Receiving new vehicle a. Once the new vehicle is received, create an equipment master record and maintain all the details on the equipment master record. Create an inspection notification, with reference to this equipment and trigger an email from the Notification to Quality inspector, requesting for inspection b. Quality inspector will inspect the vehicle and enter all the technical findings on the Notification. If the quality is not as per the DRC specification, trigger an email to PCD. PCD will coordinate with the supplier for rectification of the defect. c. Once the quality is satisfactory, technically complete the notification. d. Fleet services will assign the fleet to employee/department. On the equipment master data, assign the partner function user/department e. To maintain the details of the Salik tag, a custom table would be provided, on which you will be able to maintain the Salik tag number, expiry date, Business Blueprint Document Page 88 of 123 Equipment movement tracking Since there is no standard process on RSI PROPOSAL to track the equipment as per the DRC requirement, this needs a development. There will a custom program to track the equipment status such as assignment of the equipment to the department, employee or project. Breakdown report For breakdown report, create breakdown notification. Enter the reference object (Equipment/Fleet). All the causes, objects parts, damage are maintained as catalogs in form of codes. Since all the fields required by DRC are not available on RSI PROPOSAL, there would be custom screen on the notification, where the required field would be maintained. Once the inspection is over, fill all the details on the notification. If the vehicle is to be scrapped, complete the notification and set the status of the equipment master record ‘Scrapped’ and set the deletion indicator. If the equipment/fleet is sold off, set the status ‘Sold’ and set the deletion indicator to equipment master record. If the equipment is to be repaired/serviced at work shop, trigger maintenance order from the notification and process the maintenance order. Business Blueprint Document Page 89 of 123 12.4 Configuration Data Notification Type Notification type Code Description Maintenance AR Accident Report Maintenance N1 Inspection Number Range for Notification Type Number range Notification type From To Internal/External 01 AR 4000000 4999999 Internal 02 N1 5000000 5999999 Internal 12.5 RSI PROPOSAL Enhancement Type Triggering point Description Workflow Quality Notification created A mail should be triggered to the person responsible on the Notification task. Form Quality Inspection Report Maintenance person should be able to print the quality inspection Form Accident report Maintenance person should be able to print the Accident report notification Enhancement Custom Screen Custom screen on Quality inspection notification Enhancement Custom screen Custom screen on Accident report Notification Work flow Assign task ‘Defective Product’ A mail would be triggered to PCD Enhancement Custom table User should be able to maintain the details of Salik Business Blueprint Document Page 90 of 123 tag, such as Salik card number etc. Business Blueprint Document Page 91 of 123 13 Fleet Hiring Process (FLT01B) 13.1 Definition Fleet hiring is the process, where in the equipment are sent to the project/facilities on chargeable basis. This hiring may be internal equipments or from the external supplier. 13.2 Process Overview (As Is) Currently, custom made software ‘Whitelink’ is being used for managing the hiring process and covers the following main processes a. Requisition b. Supplier enquiry c. Confirmation to supplier d. Internal hiring e. External hiring f. Requisition extension g. Off hiring Business Blueprint Document Page 92 of 123 13.3 Process Overview (To Be) Hiring of the Internal Fleet and Equipment (FLT01B) TESD Start 1 Requisition User/ requestor will create a requisition Development Development An auto mail will be triggered to the Hiring section Is available within EO External Yes 5 Confirm the requisition and assign the equipment to the requisition Development Development 6 An auto mail will be triggered to the Requisitioner and contact person Shipping document External Hiring (FLT01B) End 7 Create a shipping document 8 SD document Billing document Create the SD order 9 Create a Billing document End Roles: 1- User department 5, 8, 9 - Hiring section 7 – Fleet services Business Blueprint Document Page 93 of 123 Hiring of External Fleet and Equipment (FLT01B) TESD PCD FI/CO Start 1 Requisition User/ requestor will create a requisition Development An auto mail will be triggered to the Hiring section Is available within EO Yes No Internal Hiring (FLT01B) Reject the Requisition Development 2 Purchase Requisition Automatic Creation of PR Enquiry Create an enquiry from the PR Purchase Order (Confirmation to the to the supplier) 4 Create a Service Purchase order against the enquiry with reference to WBS element Outside SAP 5 Send a confirmation to the user Service entry sheet 7 End Outside SAP 6 Site person will maintain the time sheet of the equipment Vendor will bring invoice along with time sheet to PCD TESD will create a service entry sheet 8 Accept the service entry sheet Forward to Finance Invoice processing and vendor payment (FIN01B) End Roles: 1 – User Department 2,3, 4,5,7,8 – Hiring Section 6 – Site person End Business Blueprint Document Page 94 of 123 13.3.1 Process Description Internal hiring Internal rental stands for the rental within one company and comprises the rental of equipments to cost objects within one company code (projects, internal orders etc). “Time Based Equipments” is usually commissioned and shipped for a specific period of time to a specific location and is billed on a daily basis. The process for the internal equipment rental starts with a requisition note to be created by the requisitioning party, i.e. a site manager. In the requisition note the basic requirements are stated, like the equipment class needed (i.e. excavator), the time period, the location etc. The responsible equipment manager reviews the requisitions and therefore displays a list of existing requirements. He checks for available equipments and allocates them to the requisitioning party. Equipments can be transferred from the equipment pool to the recipient or from one recipient to another The use of equipments is invoiced and settled on a regular basis, usually once a month. All shipping documents in the settlement period are therefore grouped by recipients and transferred into billable orders by the system. These orders are then transferred into invoices (billing documents). The controlling objects of the recipient will be debited with the costs. 1. Report a requirement for the equipment/fleet. This is done through the requisition. Requester has to enter the basic requirements such as type of the equipment (Class), required start date/time and end date/time, quantity required. Recipient on the requisition represents the project site or a facility where the equipment should be delivered. While maintaining, recipient master data, maintain the name of contact person and the same can be accessible while creating a requisition. While saving the requisition, system will check for the budget on the WBS element assigned to the recipient. If the budget is not available on the WBS element, system will not allow the user to save the requisition. This is not a standard feature and will be achieved through enhancement. Once requisition is saved, system will assign an internal number. This is the reference number for further processing. 2. Allocate the equipment to request. During allocation of the equipment to the request, request can be changed. From the equipment list, list of the equipment available for use can be viewed. Confirm the request and assign the equipment number to the request. Upon saving the request, a confirmation mail will be triggered to the requestor and contact person. 3. Create a shipping document Business Blueprint Document Page 95 of 123 Shipping document is created with reference to the requisition. Once equipment is assigned to a demand, it has to be physically delivered to the location. This is done through shipping document. The shipping document will be used to move the equipment from the current location to the requested location. In ETM, a shipping document is not only used to represent the movement of equipment from one place to another, also acts as a documentation of the way the equipment is used in the various locations (“activity type”, i.e. “in operation”, “available for use”, “repair”). For off hiring create a shipping document with recipient as fleet services/hiring , with activity type ‘off hired’ which is the indication that equipment/fleet is in pool. 4. Settlement of the cost Create SD order To be able to settle/invoice the cost of the equipment for the period of time utilized, SD orders must be created. Create SD document with reference to the shipping document. During settlement, system takes the cost for the activity type ‘in operation’. The cost for the specific activity comes from the ETM catalogs. On the catalog, the original cost equipment, cost of maintenance, depreciation etc. will have to be maintained along with the formula to calculate the per hour cost of the equipment. The cost for per hour will have to be decided along with the FI/CO pDRCple, which will be done during the realization phase. Create a billing document Create a billing document with reference to the SD document. External hiring Hiring of external equipment will follow the standard RSI PROPOSAL service hiring. Each type of equipment would be created as service master record. The external hiring will follow the following steps: 3. 1. Receive the request from the user: Similar to internal hiring, for external hiring too, a requisition will have to be created by the designated user. An auto mail would be triggered to the hiring department upon saving the requisition. 2. Hiring section will check in the pool and other site, whether any internal equipment is available or not. If the internal equipment is available, the process ‘Internal hiring process’ would be followed. If the equipment is not available within DRC, ‘Reject’ the requisition. This rejection will trigger a purchase requisition automatically. This is not a standard RSI PROPOSAL functionality. This would be achieved through some custom development. Please refer MM document “Purchase requisition process (PRC01A)” for more details on purchase requisition. System will identify the Business Blueprint Document Page 96 of 123 relevant service master automatically based on the classification similar to the equipment. User has to validate the service master record in the PR. 4. Convert the purchase requisition into Request for quotation. Please refer the MM to-be documentation ‘Request for Quotation (PRC02A)’. However, there would be an enhancement on the enquiry to maintain the details like requisition number, from date to date and time. This enquiry has to be created vendor wise. Please refer MM process ‘Request for Quotation (PRC02A)’ 5. If the vendor /supplier do not respond or does not have the requested vehicle / equipment, create an enquiry on another vendor. Once you receive the reply from the supplier, send a confirmation mail to the user. 6. Once you receive the equipment at site from the supplier, create a purchase order. Please refer MM document process “Purchase order process (PRC03A) for more details on purchase order. This purchase order is the confirmation to the supplier and will be created with reference to the enquiry sent to the supplier. This confirmation document would be used for creation of service entry sheet and invoice processing of the supplier. 7. To track the status of the hired equipment: Each type of equipment would be created as Non-valuated materials. When you create purchase order, along with the service master record, maintain another line item per equipment type with respective material master. Make the goods receipt for the non valuated materials once the supplier delivers the equipment. When you make the goods receipt, enter the vehicle registration number as a serial number. In the back end system will generate one equipment number for each registration number with the status ‘ESTO- In Warehouse’, This is the indication that you have ‘hired’ the equipment. If DRC driver is assigned to the vehicle, update the partner function on the equipment master record. Once the Vehicle is taken back by the supplier, make the goods receipt reversal. This will set the status of the equipment as ‘AVLB-Available’. This is the indication that you have ‘off hired’ the equipment. For any other status of the equipment such as ‘breakdown’, replacement etc, will have to be set manually on the equipment master record. Fuel issued to the external hired equipment will have to be updated on measurement point. For this similar to internal the equipment, create measurement point for the external hired equipment. Fuel posting will be similar to that of for internal equipment. Business Blueprint Document Page 97 of 123 8. Time sheet for each equipment should be maintained by the site pDRCple. This has to be done outside RSI PROPOSAL. 9. Receive the invoice along with the time sheet and confirmation, create a service entry sheet. Accept the service entry sheet. Once the service entry sheet is accepted, accounting document would be created in the back ground by the system and the actual cost will be posted to the WBS element. Payment to the supplier would be made based on the accepted service entry sheet. For details on service entry sheet please refer the MM process “Service entry sheet process (WRH02A)”. 10. Forward the hard copy of the invoice to PCD 11. Further processing for payment will be done in MM and FI Urgent requests There is no separate process for urgent requests, as in the as-is process. All the request will follow the same process steps as mentioned above. In case of urgent request, hiring section has to create the requisition and process it. Extension request An email would be triggered to the requestor three day before the expiry date of the requisition requesting for either sending the extension for off hiring the equipment. This is not RSI PROPOSAL standard process and will be done through workflow For any extension, the request has to be created with reference to the original requisition number. When a requisition is created with reference to another requisition, all the data will be copied and these data can be edited before saving the requisition. Further processing of extension requisition is similar to normal requisition. Replacement of the equipment In case of replacement during a breakdown of equipment, hiring section should create a requisition and process it as normal requisition. There would be a separate activity type ‘replacement’ which is equivalent to ‘In operation’ activity, and will be used for settlement purpose. Business Blueprint Document Page 98 of 123 13.4 Configuration Data No specific configuration data for this process 13.5 RSI PROPOSAL Enhancement Type Triggering point Description Workflow Requisition created Mail to hiring section Workflow Requisition equipment internal Mail to the initiator and contact person Enhancement Triggering an enquiry from the requisition Once the user sets the status “rejected” a PR will have to be generated. Enhancement Maintaining the status for the external hired equipments For tracking of the external equipment status hired, ff hired, breakdown etc confirmed for Business Blueprint Document Page 99 of 123 14 Fuel Card Management (FLT01A) 14.1 Definition Fuel card management refers to the maintaining and tracking the fuel card, fuel card consumption etc. 14.2 Process Overview (As Is) There are mainly two types of fuel cards: Fuel cards assigned to Equipment and open fuel cards which are not assigned to any specific equipment. These fuel cards are procured from the supplier and this has specific validity date. Apart from fuel, DRC uses fuel vouchers also. These vouchers are procured from the supplier and issued to the user as and when request comes. Business Blueprint Document Page 100 of 123 14.3 Process Overview (To Be) Fuel Card Management (FLT01) TESD Start Outside SAP 1 Receive the fuel card from the supplier Development 3 Maintain the fuel card expiry date, vendor in the custom table 3 Maintain the fuel card number on the equipment master record Outside SAP 4 Receive the Monthly consumption report from the fuel card supplier, convert it to uploading format Development 5 Batch uploading of the supplier report to the system Automatic posting of fuel to a common cost center and updating of measurement point of the equipment End Roles: 1, 2 - Fleet Services 3 – Master data controller 4, 5 – Fuel Section Business Blueprint Document Page 101 of 123 Fuel Distribution by Tanker and from TESD Storage Tank (FLT01) TESD Start 1 Issue the fuel to the vehicle Outside SAP 2 Note down equipment number, run hours/kilometer reading Development 3 Batch uploading/Individual entry into the system Automatic posting of fuel to a common cost center and Updating of measurement point of the equipment End Roles: 1, 2 , 3 – Fuel section Business Blueprint Document Page 102 of 123 14.3.1 Process Description Fuel Card Management 1. Fuel Cards assigned to equipment/fleet a. All the fuel card numbers are maintained in the respective equipment master record. On the equipment master record there would be a provision to maintain the expiry date, supplier of the fuel card. b. There will be custom program to upload the fuel card report is received from the supplier, into RSI PROPOSAL. Run this program and give the flat file upload. Following data are required on the excel sheet to be uploaded. - Equipment registration number or Fuel card number - Date and time - Fuel consumption - Type of fuel (petrol, diesel etc) Fuel consumption should be measurement point on the equipment/ fleet master record. For each supplier one open purchase order will have to be created. While uploading the excel sheet in the custom screen, input ‘consolidated fuel quantity’ and ‘purchase order number’ for each supplier. In the back end, system will call a program which reads the data from the flat file/custom screen. Goods receipt (GRN) will be done against the purchase order and goods issue (GI) will be done to a common cost center. At the same time measurement document would be created for fuel consumption on the respective equipment master. 2. Open fuel card All the open fuel cards would be maintained as material master record. Whenever request comes for the open fuel card, issue the material to the common cost center; enter the recipient as equipment registration number. This you can track each open card issued to equipment/user. The process for posting the fuel consumption is similar to the fuel card assigned to equipment. Note: If an equipment has both open fuel card and permanent fuel card, you will not be able to distinguish the consumption on vehicle by fuel card type. Fuel Distribution by Tanker and by TESD Storage Tank The person who distributes, should get the following details a. Equipment number/registration number b. Quantity of the fuel Business Blueprint Document Page 103 of 123 c. Run hour/Kilometer reading Make the goods issue on RSI PROPOSAL with the above details. Fuel cost and quantity will be posted to a common cost center and equipment fuel consumption (quantity) will be updated. Fuel Voucher a. All the vouchers would be maintained as one material master record for each denomination with serial number. Whenever you receive the voucher post the goods as stock item. Procurement process is similar to any other material procurement. For details process on procurement please refer the MM document ‘Purchase requisition process (PRC01A)” b. When you get the request from the department, make a goods issue against the common fuel cost center. Enter the recipient as equipment registration number. c. Update the equipment measurement point. Approval for the Fuel issuance There is no approval system for fuel issue on the system. However, there would be a provision to print goods issue slip which will have to used for approval purpose. Fuel Procurement This process is similar to any other material procurement. Please refer the MM to-be document ‘Purchase requisition process for materials (PRC01A)’. Take the fuel storage tank level and the send a request through email to PCD for procuring the fuel. PCD will arrange for the procurement of the fuel. Business Blueprint Document Page 104 of 123 14.4 Configuration Data No specific configuration data 14.5 RSI PROPOSAL Enhancement The following enhancements are required to carry out this process Type Description Development A custom table to maintain the fuel card, expiry date and vendor User should be able to maintain the details of the fuel card number and expiry date along with the fuel card supplier code. Development Batch uploading of the fuel supply data. There would be one custom screen with different options to upload the fuel consumption 1. For Fuel card – User should input the fuel card number/registration number, fuel quantity, running hours/kilometers, date and time. 2. For open fuel card – User should input the fuel card number/registration number, fuel quantity, running hours/kilometers, date and time. 3. For fuel distribution – User should input the fuel card number/registration number, fuel quantity, running hours/kilometers, date and time. 4. Fuel voucher Business Blueprint Document Page 105 of 123 15 MiscellanDRCus Processes (MNT01E) 15.1 Definition MiscellanDRCus process covers those processes which are not a maintenance activity, but as a business process it is a part of the regular activity. 15.2 Process Overview (As Is) Followings are the various processes covered in as-is document Correspondence management – This is a part of Document Management System (DMS). Please refer the DMS document Client Satisfaction survey Client satisfaction Management Issuance of the tool AV SMATV Channel listing Assets and Scrap Disposal Procurement using Petty cash Asset control procedure Business Blueprint Document Page 106 of 123 15.3 Process Overview (To Be) Client Satisfaction survey FMD Start 1 Create Notification ‘Survey’ with reference to the service request notification for which survey to be carried out. Outside SAP 2 Carry out the survey Development 3 Update the Notification custom screen with inputs from the customer Start Business Blueprint Document Page 107 of 123 Notification 15.3.1 Process Description Client Satisfaction Survey Whenever the survey is to be carried out, trigger a ‘Survey’ Notification with reference to the original client service request notification. A custom screen would be provided on the Notification to enter the questionnaires. Carry out the actual survey. Once you get the feedback from the customer, update the Notification and close. Client satisfaction Management For client satisfaction management, there would be codes ‘Yes’ and ‘No’. Maintain the required client satisfaction management form through DMS module. While taking the print out of work order, take the print out of ‘survey form’ too. Once you get the signed form from the client, update the notification. Any comment from client if any has to be maintained as long text for each code. A report can be generated for each type of code ie with ‘yes’ and with ‘no’. Issuance of the tool Issuance of the tool will be done through HR master data. Object on Loan (Infotype 0040) would be created as ‘Tool Box’ and will be assigned to the HR master data. This ‘Tool Box’ will not have any details of the tools issued. This is just to have a record that a technician is having the ‘Tool box’. AV SMATV Channel listing For this process, card number can be maintained on the respective master data in the field ‘Inventory number’. This field is an open field and accepts both alphanumeric characters. For the procurement of the cards please refer the ‘Procurement of material process (PRC01A)’ Asset control procedure On RSI PROPOSAL there is no separate process as asset control procedure. The processes which covered in as – is document have been addressed already. • Acquisition of assets Acquisition of asset is part of procurement process. Any procurement of the facilities assets will follow the MM process ‘Procurement of material (PRC01A)’. Once the material is received, create an equipment master and update all the relevant data on the equipment master record. Business Blueprint Document Page 108 of 123 • Maintenance of assets For maintenance of facilities assets please refer the following maintenance processes: • 1. Preventive maintenance (MNT01A) 2. Reactive Maintenance (MNT01B) Facilities assets Tracking All the facilities assets movement will be tracked from the master data. There would be a provision to print the bar code. Whenever the equipment is moved from one facility to another, update the equipment master. System captures changes and details are available as ‘Action log’. In the ‘Action log’ a chronological change details are available. Assets and Scrap Disposal All the approval and processing should be done outside RSI PROPOSAL Once equipment/ fleet is disposed off or scrapped, set the user status accordingly and set the deletion indicator. Inform the FI pDRCple on the disposal of the asset. Finance pDRCple will make direct finance entry into the system and update the asset master data. Business Blueprint Document Page 109 of 123 15.4 Configuration data Notification Notification Type Code Description Maintenance SY Customer Survey Number range for Notification Notification Number range Internal/External SY 7000000-7999999 Internal 15.5 RSI PROPOSAL Enhancement Type Description Development A custom screen/table would be provided to maintain the questionnaire Business Blueprint Document Page 110 of 123 16 Procurement for Plant Maintenance 16.1 Definition Procurement for the plant maintenance and fleet management involves the procurement of material, assets, and external services. 16.2 Process Overview (As Is) 16.2.1 Process Overview Description Currently, DRC procures material, external services for various maintenance activities. For TESD following are the various procurement processes: - Spare parts procurement - Outsourced repair - Procuring boats and jet skies - Hiring /chartering of landing craft and passenger boats - Procurement using petty cash For FMD following are the various procurement processes - Temporary manpower hiring - Material Procurement - Supply and fix - Procurement using petty cash - Asset control procedure For LID following are the various procurement processes - Spare parts procurement - Procurement of external services - Procurement using petty cash 16.3 Process Overview (To Be) All the departments will have to follow the same Procurement Process. Procurement of the material and services: This has been explained in the respective maintenance processes. For detailed explanation please refer the following MM documents ‘Purchase requisition for material (PRC01A)’ Business Blueprint Document Page 111 of 123 Procurement of the Assets: Procurement of assets will be done trough the direct creation of purchase requisition with reference to an asset. All the process of procurement is similar to any other material procurement. ‘Purchase requisition for Services (PRC01A)’ Procurement using Petty cash All the petty cash process will be done in FI module and all the approval process will have to be done outside the RSI PROPOSAL system. Whenever the procurement is done through the petty cash, create a maintenance order (if the order does not exist) for the technical object (Functional location or equipment) for which the petty cash has been utilized. Hand over the maintenance order number and supporting bills to the petty cash clerk. Actual amount will be posted to the order directly in FI. Thus cost will be booked to respective equipment/functional location. 16.4 Configuration data Covered in MM to-be document. 16.5 RSI PROPOSAL Enhancement Covered in MM to-be document Business Blueprint Document Page 112 of 123 17 Budgeting for Plant Maintenance 17.1 Definition Budget is a forecast of an individual department’s income/expenses expected for some period in the future. Maintenance Budgeting is the process of anticipating the costs, and planning the expenditure of financial resources for the execution of the maintenance activity. 17.2 Process overview (As Is) Currently, a half yearly budget is prepared for each facility. Each section will prepare its budget and a consolidated budget will be prepared. Approval will be taken from the department directors and will be sent to the finance department. Finance department will distribute the budget. 17.3 Process overview (To Be) 17.3.1 Process Overview Description Expense Budget Expense budget planning, budgeting and control will be done through PS module (projects and WBS element) Each facility will have a WBS element at reactive maintenance and preventive maintenance level so that the budget is controlled at that level for each sections of the department. Whenever, a maintenance order is created, before releasing the order, WBS element should be maintained on the order. This creates a link between PM and PS modules thus control the budget. Planned values are checked, only if the value leads to the commitment. For details on the budget planning, distribution and structure of the project, please refer the PS module to-be document processes (Process ID PRJ02A, B, C and E and PRJ01B) Capital Budget Capital budget is used to control the capital expenditures. For plant maintenance, capital expenditures are mainly DRC asset procurement. Capital budgets are controlled through the Controlling Module (CO) internal orders. Please refer the ‘Capital budget process (FIN01A.4)’ of FI module. Business Blueprint Document Page 113 of 123 17.4 Configuration data Covered in PS to-be document 17.5 RSI PROPOSAL Enhancement Covered in PS to-be document Business Blueprint Document Page 114 of 123 18 Calibration Process (MNT01G) 18.1 Definition Test equipment is used in many companies for performing quality inspections. In order to ensure that the test equipment used always fulfils the defined performance criteria, most companies regularly test and calibrate their test equipment. Using the functions in the component Test Equipment Management, you can manage equipment data, plan and schedule inspections, and perform calibration inspections for the equipment. This process has the integration with Quality Management (QM) module. 18.2 Process overview (As Is) Currently, this process is not being followed. This is the requirement from the user department. A detailed procedure has been documented in as-is document. Following process from FMD department is covered in this to-be document: ‘Control of inspection, measuring and test equipment’ Business Blueprint Document Page 115 of 123 18.3 Process overview (To Be) Calibration Process (MNT01G) TESD/FMD/LID PCD Start 1 Create, Task list, maintenance plan 2 Schedule the maintenance Plan 3 B Auto triggering of maintenance order and/or Notification based on the scheduling data Maintenance Order 4 Inspection lot Release the order Development An auto mail would be triggered to Supervisor/ Engineer/Foreman Is material required No Yes Development 6 Material Reservation Slip Approval for the material reservation number 8 Print the material reservation number Purchase requisition for Materials (PRC01A) A Roles 1,2,4 – Maintenance Planner 8- Foreman/Engineer/Supervisor 6 – As per the delegation of authority Business Blueprint Document Page 116 of 123 FI/CO Calibration Process (MNT01G) TESD/FMD/LID PCD FI/CO A Job done by Internal/ External manpower? External Auto triggering of Purchase Requisition Purchase Requisition Purchase requisition for services (PRC01A) Internal Development 9 Print the Work order and task list Work order Print Outside SAP 10 Perform the job 9 Usage decision No Is accepted? Yes 11 WO Confirmation Confirmation Number Settlement Process 12 Technical completion B 13 Business completion End End Roles: 9, 11, 12 - Foreman/Engineer/Supervisor 10 – Technician 13 – Maintenance Planner Business Blueprint Document Page 117 of 123 18.3.1 Process Overview Description The calibration process is similar to the Preventive Maintenance process (MNT01A). Planning This is the first step in the preventive maintenance processing. This step involves creation of master data and maintenance plan etc. Check whether master data exists for technical object (equipment/fleet/functional location) on which you want to process the preventive maintenance. If the master data does not exist, create a master data for the technical objects and also create other master data such as such as maintenance item, task list and maintenance plan. On the task list maintain master inspection characters (MIC). MIC is the parameter for which the calibrations readings are recorded. If all the master data are available, schedule the maintenance plan. Scheduling of the maintenance plan refers to the starting of a maintenance plan. Based on the scheduling data on the maintenance plan, system give you list of planned date for the respective maintenance plan. Once the planned date is reached, system automatically triggers a maintenance order or maintenance notification depending on the call object set on the maintenance plan. Scheduling This is the second step in the Preventive Maintenance processing. This process involves releasing of the order and maintaining the settlement rule on the work order. All the orders triggered are available as list. From the list, you can select the order to be processed and go to order change mode. In the work order you can enter additional operations, components etc (apart from the task list attached) if required. For the equipment which is under warranty, you can see the details from the object information on the notification or order header. Release the maintenance order. - As soon as the work order is released an email will be triggered to the concerned engineer/supervisor/foreman. This is not a standard functionality of RSI PROPOSAL. This will be done through workflow. To trigger an email to the Business Blueprint Document Page 118 of 123 concerned person, ID of the responsible person should be maintained either on the equipment master record as partner function or on the maintenance order header as ‘person responsible’ - An Inspection lot would be created by the system automatically. Execution This is the next step in preventive maintenance processing. Execution part involves, printing the Material Request, getting the material from warehouse, sending the technician to the site to carry out the maintenance activity. For stock items, a reservation number will be generated by the system (Similar to the existing MR number). Reservation number will have approval process as per the existing level of authority. Get the approval from the necessary authority. Print the reservation number and get the signature from the concerned person and handover it to warehouse. If the stock is available, Warehouse pDRCple will issue the material against the reservation number. For non stock item, a purchase requisition will be generated by PCD. This purchase requisition will have release strategy (approval process based on the existing level of authority). Further processing of purchase requisition will be done in MM. For more detail, please refer the document “Purchase requisition process (PRC01A)” For activities carried out internally, a confirmation number will be generated, which will be used for confirmation of the internal activity. For external activity, a purchase requisition will be triggered by the system. This purchase requisition will have release strategy (approval process based on the existing level of authority). Further processing of purchase requisition will be done in MM. For more detail, please refer the process “Purchase requisition process (PRC01A)” of MM to-be document. Print the work order/task list and execute the work. Usage Decision Once the calibration process is carried out, enter the values for the inspection characters which are on the task list. If the calibration values are satisfactory, accept the usage decision. If the values are not satisfactory, reject the usage decision and carryout the rework. Business Blueprint Document Page 119 of 123 Note: Required quality parameters would be collected during realization phase. Confirmation During confirmation process, all the activities will have to be updated on the work order/Notification. Once the job is completed and quality is satisfactory, do the order confirmation. Confirmation involves: - Recording the actual time of the work performed by the internal manpower. - Recording the technical findings of maintenance activity on the notification. - Recording the measurement point/counter readings - Creation of the service entry sheet for the activity/service done by the external vendor and accept the service entry sheet. Further processing of service entry sheet will be done in MM. Completion This step involves completing the order from technical perspective and business perspective. • Technical completion of the order means, the work order is completed technically, i.e the work order is updated with all the details of the jobs carried out. The work order editing is no more after technical completion. System will set the work order status as ‘Technically complete’. Technical completion can be cancelled if required. Once the order is technically completed, system will schedule the next call date for the maintenance plan. • Settlement of the order refers to the transferring of the actual cost from order to receiving object. (In case of DRC, WBS is the receiving cost object). Settlement of the actual cost will be done either after the confirmation or after the technical completion. Order can be settled either partially or fully. • At the end of the financial year, close (business completion) the work order. System will set the order status as ‘Closed’. After the business closure no more cost will flow to the maintenance order. It is possible to reset the status. Business Blueprint Document Page 120 of 123 18.4 Configuration data Order type Order type Code Description Calibration PM05 Calibration order Number Range for Order Type Order Number Range Internal/External PM05 5000000-5999999 Internal 18.5 RSI PROPOSAL Enhancement Already covered in preventive maintenance and routine maintenance processes Business Blueprint Document Page 121 of 123 19 Issues and Gaps Issue Remarks BMS (Building Management system) should be integrated with RSI PROPOSAL. MBS integration with RSI PROPOSAL is not a part of scope of implementation. Barcode reading device should be integrated with RSI PROPOSAL Barcode reading interface and reading needs RSI PROPOSAL mobile infrastructure. Assets and scrap disposal – Currently, DRC has approval process with supporting documents (such as Image of assets, asset disposal forms etc), before disposing off any assets or scraps There is no standard process on RSI PROPOSAL to map this requirement. All the forms and images can be maintained on RSI PROPOSAL through DMS. For internal equipment, DRC wants to maintain the time sheet on RSI PROPOSAL Since all the equipments are charged on daily basis, time sheet has to be maintained outside RSI PROPOSAL. When a vehicle is used for multiple projects, where to book the fuel cost/cost of the equipment? Since it is very difficult to determine the exact WBS element/fuel quantity, it is advisable to book the cost to a specific cost center. This issue needs to be discussed with FI/CO If the employee exceeds approved quantity of fuel for a month, excess amount will be deducted from his salary – For this process DRC needs integration to HR There is standard process on RSI PROPOSAL. Hence this should be handled outside RSI PROPOSAL. For deduction of salary, inform HR department over email with the details. For the traffic fines, because of employee fault, the amount should be deducted from his salary - For this process DRC needs integration to HR There is standard process on RSI PROPOSAL. Hence this should be handled outside RSI PROPOSAL. For deduction of salary, inform HR department over email with the details. For the repair cost, which exceeds the insurance amount, should be deducted from employee salary There is standard process on RSI PROPOSAL. Hence this should be handled outside RSI PROPOSAL. For deduction of salary, inform HR department over email with the details. Business Blueprint Document Page 122 of 123 20 Reporting Requirements The following reporting requirement from DRC has been received. But analysis and feasibility of the same will be done during the realization phase. Standard RSI PROPOSAL report will be explained to the core team/super users after the first process work shop. S.No Reports Business Blueprint Document Page 123 of 123 Purpose of the report Priority