KIMANIS POWER PROJECT JOB SAFETY ANALYSIS Task / Job Description JSA No Type of JSA : / Functional Area: 275kV Kolopis switchyard : Erection of Steel Structure (Gantry and equipment) : JHA/KLPS/2013/ABB/02 New Prepared by : Name LUQMAN OSMAN Revised Purpose of JSA Position Company HSE SV ABB Reviewed by: 1 SHAH NAWAZ SAFETY ADVISOR 2 3 1. Approved for Submission: 1 ABB Signature : Non Routine Work Date / Routine Work Name Turnaround Environment Gas Release (HC / H2S) Spill or Loss of Dusty Off-Site Impact Signature Date 16.05.13 16.05.13 Reviewed by CTCI: 1 2 3 2. Approved by KPSB: 1 Signature I/C No. Date RISK RATING Potential Hazard Example for Specific Categories : Equipment Fire Damage (Physical) Loss of Production Explosion Other… Projects CTCI & KPSB Position Company Workers : I acknowledge receiving these instruction, understand the instruction, and fully comply with the JSA Name Comp Signature I/C No. Date Company Name any Worker Slip/ Trip/ Fall Struck/ Against Overhead Work Burn (Heat/ Chemical) Eye Injury Radiation Hazard Sharp Objects Back Injury Hazardous Chemical Containment Contacted by/ with Caught/ in/ on/ between Strains Electrical Hazard Specific Area: Severity: Extreme Multiple facilities, extensive damage or prolong loss of production > RM 200M High Single Fatality, major injury, > 1 lost Time Injury (LTI) major and loss of production (between RM 8M to RM 200M). Medium Major & minor injury loss of production (between RM 2 M to RM 8M) Low No injury, slight damage to equipment and no loss to production. Likelihood: High Probable, likely to occur (0-0.5 year). Medium Possible could occur (0.5-4 year). Low Remote, unlikely to occur (4-30 year). Page 1 of 9 Severity Low Med High Low Med High Extreme Low L L M Likelihood Med High L M M H H EX Mitigation Safe working practices OPP, PTW, HSEMS OPP, HSEMS, PTW, HSE awareness, Special procedure, HSE awareness, OSH program KIMANIS POWER PROJECT JOB SAFETY ANALYSIS Task / Job Description JSA No : Erection of Steel Structure (Gantry and equipment) : JHA/KLPS/2013/ABB/02 BASIC JOB STEP 1.0 Transportation of material to site POTENTIAL HAZARDS 1.1 Narrow road/ collision or topple Functional Area: 275kV Kolopis switchyard Who or What might be harmed (Person/Equip/ Env) Risk Rating Person/Equipment L Specific Area: CONTROLS 1.1.1 Ensure valid vehicle driving license 1.1.2 Observe proper traffic control and speed limit 1.1.3 Equipment or material should be properly Action Party Supervisor secure 1.2 Insecure instrument on vehicle Person/Equipment Page 2 of 9 L 1.1.4 Warning signs shall be erected as means of warning where applicable. 1.2.1 Properly secure the equipment and material 1.2.2 Ensure right position of the equipment and material is properly set on the vehicle 1.2.3 No person allowed to sit/present on the back of truck lorry Supervisor KIMANIS POWER PROJECT JOB SAFETY ANALYSIS Task / Job Description : Erection of Steel Structure (Gantry and equipment) JSA No : JHA/KLPS/2013/ABB/02 BASIC JOB STEP 2.0 Loading and unloading of POTENTIAL HAZARDS 2.1 Improper manual handling method Functional Area: 275kV Kolopis switchyard Who or What might be harmed (Person/Equip/ Env) Person (slip/trip) Risk Rating Person (falling from height/ falling object) M Person L L material 2.2 Falling load 2.3 Pinch Point / sharp edges CONTROLS 2.1.1 2.1.2 2.1.3 2.1.4 2.1.5 Person Page 3 of 9 M Action Party Supervisor Supervisor Supervisor 2.3.3 3.1 Pinch Point / sharp edges Toolbox briefing Proper manual handling method. Close supervision by Work Supervisor. Maintain good housekeeping Work related PPE to be worn. 2.2.1 Toolbox briefing – drop object and lifting 2.2.2 use tagline during lifting 2.2.3 provide signalman 2.2.4 Provide signages 2.2.5 Only competent operator are allowed to operate the crane 2.2.6 Crane functional test to be done before commencing the work 2.2.7 all lifting gear will be inspected before use 2.2.8 Will isolate the working area to ensure public safety 2.2.9 Work related PPE to be worn. 2.3.1 2.3.2 3.0 Preparing the foundation and material at respective Specific Area: Toolbox briefing – Pinch point. Using Proper PPE (hand glove/ long sleeve jacket) Proper handling method 3.1.1 Toolbox briefing – Pinch point. 3.1.2 Using Proper PPE (hand glove/ long sleeve Supervisor KIMANIS POWER PROJECT JOB SAFETY ANALYSIS Task / Job Description : Erection of Steel Structure (Gantry and equipment) JSA No : JHA/KLPS/2013/ABB/02 BASIC JOB STEP POTENTIAL HAZARDS Functional Area: 275kV Kolopis switchyard Who or What might be harmed (Person/Equip/ Env) Risk Rating Specific Area: CONTROLS Action Party jacket) installation point 3.2 Manual Handling. Person M 4.1 Pinch Point / sharp edges Person M 4.2 Sharp object Person M 4.0 Assembly of material Page 4 of 9 3.2.1 Ensure proper handling on tools before performing the job 3.2.2 Trained the workers correct way to lift material 3.2.3 Ensure all workers follow the correct procedure 3.2.4 Clearance of loose material 3.2.5 Post Signages as a way to increase awareness 4.1.1 Toolbox briefing – Pinch point. 4.1.2 Using Proper PPE (hand glove/ long sleeve jacket) Supervisor Supervisor Supervisor 4.2.1 Will install edge protector 4.2.2 Proper PPE to be worn 4.2.3 Put warning signages 4.2.4 Barricade all protrusion hazard KIMANIS POWER PROJECT JOB SAFETY ANALYSIS Task / Job Description : Erection of Steel Structure (Gantry and equipment) JSA No : JHA/KLPS/2013/ABB/02 BASIC JOB STEP 5.0 Installation of steel structure POTENTIAL HAZARDS Functional Area: 275kV Kolopis switchyard Who or What might be harmed (Person/Equip/ Env) 5.1 Falling load Person 5.2 Pinch Point / sharp edges Person Risk Rating M Person M Page 5 of 9 CONTROLS 5.2.1 Toolbox briefing – drop object and lifting 5.2.2 use tagline during lifting 5.2.3 provide signalman 5.2.4 Provide signages 5.2.5 Only competent operator are allowed to operate the crane 5.2.6 Crane functional test to be done before commencing the work 5.2.7 all lifting gear will be inspected before use 5.2.8 Will isolate the working area to ensure public safety 5.2.9 Work related PPE to be worn. Action Party Supervisor Supervisor M 5.3 Manual Handling. Specific Area: 5.2.1 5.2.2 5.2.3 Posting Warning Signage Toolbox briefing – Pinch point. Using Proper PPE (hand glove/ long sleeve jacket) 5.3.1 5.3.2 5.3.3 5.3.4 Toolbox briefing Proper manual handling method. Close supervision by Work Supervisor. Maintain good housekeeping Supervisor KIMANIS POWER PROJECT JOB SAFETY ANALYSIS Task / Job Description : Erection of Steel Structure (Gantry and equipment) JSA No : JHA/KLPS/2013/ABB/02 BASIC JOB STEP POTENTIAL HAZARDS Functional Area: 275kV Kolopis switchyard Who or What might be harmed (Person/Equip/ Env) Risk Rating M 5.4 Working at height 6.0 Bolt tightening and alignment work Person 6.1 Working at height (Bad weather) Person M Specific Area: CONTROLS 5.3.5 Work related PPE to be worn. 5.4.1 5.4.2 5.4.3 wear full body harness Close supervision by supervisor Provide suitable working platform 6.2.1 6.2.2 6.2.3 6.2.4 6.2.5 6.2.6 6.2.7 6.2.8 6.2.9 Toolbox briefing – Working at height Inspect safety harness before use Ensure workers are using correct tools Tight supervision from supervisor Use skylift to tighten the bolt Provide safe working platform Stop the work Outrigger fully extend Training of personnel 6.2 Pinch Point / sharp edges Action Party Supervisor Supervisor Person M 6.2.1 Posting Warning Signage 6.2.2 Toolbox briefing – Pinch point. 6.2.3 Using Proper PPE (hand glove/ long sleeve jacket) 6.3 Manual Handling. Person Page 6 of 9 6.1.1 Toolbox briefing KIMANIS POWER PROJECT JOB SAFETY ANALYSIS Task / Job Description : Erection of Steel Structure (Gantry and equipment) JSA No : JHA/KLPS/2013/ABB/02 BASIC JOB STEP POTENTIAL HAZARDS Functional Area: 275kV Kolopis switchyard Who or What might be harmed (Person/Equip/ Env) Risk Rating M 7.0 Housekeeping 7.1 Manual handling Person 7.2 Pinch Point / sharp edges Person Page 7 of 9 M M Specific Area: CONTROLS Action Party 6.1.2 6.1.3 6.1.4 6.1.5 Proper manual handling method. Close supervision by Work Supervisor. Maintain good housekeeping Work related PPE to be worn. Supervisor 7.1.1 7.1.2 7.1.3 7.1.4 7.1.5 Toolbox briefing Proper manual handling method. Close supervision by Work Supervisor. Maintain good housekeeping Work related PPE to be worn. 7.2.1 Posting Warning Signage 7.2.2 Toolbox briefing – Pinch point. 7.2.3 Using Proper PPE (hand glove/ long sleeve jacket) Supervisor Supervisor KIMANIS POWER PROJECT JOB SAFETY ANALYSIS Task / Job Description : Erection of Steel Structure (Gantry and equipment) JSA No : JHA/KLPS/2013/ABB/02 BASIC JOB STEP POTENTIAL HAZARDS 7.3 Slippery surfaces Functional Area: 275kV Kolopis switchyard Who or What might be harmed (Person/Equip/ Env) Risk Rating Person Specific Area: CONTROLS 6.1.1 6.1.2 Toolbox briefing Wear appropriate PPE M GENERAL NOTES Basic PPE (Safety Helmet @ Hard Hat, Safety Shoes, Safety Glass and Long Sleeve Jacket) shall be worn at all the time. Set up barricades around work area and display warning signs. All equipment / machinery to be inspected by CTCI before any work commences. All PTW and supporting permits must be valid before any works begins. On hearing of emergency siren, stop all works, machinery & source of ignition and walk on foot to the nearest muster point. Vehicle to exit immediately to designated parking area after delivery of material. No eating and resting on site. Use designated eating and resting area. All pressure gauges used must be calibrated and tagged with valid calibration sticker. All scaffolding must have a green "safe to use" tag before put into service. Page 8 of 9 Action Party Supervisor KIMANIS POWER PROJECT JOB SAFETY ANALYSIS Task / Job Description JSA No : Erection of Steel Structure (Gantry and equipment) : JHA/KLPS/2013/ABB/02 Functional Area: 275kV Kolopis switchyard Specific Area: Maintain good housekeeping daily at all the work places. Tool box talk specific on work instruction and briefing on hazards and control measures to be conducted before start of work. Page 9 of 9