Uploaded by rayan rahman

Mid-Term Question

advertisement
Bangladesh University of Professionals (BUP)
Faculty of Business Studies
Dept. of Business Administration in Accounting & Information Systems
Course: Management Accounting (ACT- 4101)
Mid-Term Examination (January-June: 2021)
Time: 1 Hour
Total Marks: 20
(Answer all the Questions)
1. In all respects, Company A and Company B are identical except that Company A’s costs (2)
are mostly variable, whereas Company B’s costs are mostly fixed. When sales increase,
which company will tend to realize the greatest increase in profits? Explain.
2. A company manufactures and sells a single product which has the following cost and (5)
selling price structure.
Particular
Tk/unit
Tk/unit
Selling Price
120
Direct Material
22
Direct Labor
36
Variable Overhead
14
Fixed Overhead
12
84
Profit per unit
36
The fixed overhead absorption rate is based on the normal capacity of 2,000 units per
month. Assume that the same amount is spent each month on fixed overheads.
Budgeted sales for next month are 2,200 units.
You are required to calculate:
i.
Breakeven point, in sales units per month.
ii. The margin of safety and interpret the result.
iii. The sales required to achieve profit of Tk. 96,000 in a month.
iv.
Degree of operating leverage.
v.
Estimated percentage increase and decrease in net operating income of a 10%
increase in sales and a 5% decrease in sales.
3. QLM company produces two products, A and B, the production costs of which are
shown below:
Particular
A (Tk.)
B (Tk.)
Direct Materials
10
10
Direct Labor
5
9
Variable Overhead
5
9
Fixed Overhead
5
9
Fixed overhead is absorbed on the basis of direct labor cost.
(5)
The products pass through two processes, Y and Z, with associated labor cost of Tk. 10
per direct labor hour in each. The direct labor time taken associated with the two
products for these processes is shown below:
Process
Y
Z
Product A
10 mins
20 mins
Product B
39 mins
15 mins
Selling prices are set by the market. The current market price for product A is Tk.65 and
that for B, Tk. 52. At these prices, the market will absorb as many units of A and B as
the company can produce. The ability of the company to produce A and B is limited by
the capacity to process the products through Y and Z. The company operates a two-shift
system, giving 16 working hours per day. Process Z is a single process line and 2 hours
in each shift will be downtime. Process Y can process two units simultaneously, although
this doubles the requirement for direct labor. Process Y can operate for the full 16 hours
each day.
Requirement:
What production plan should the company follow in order to maximize profits?
4. Jamuna Ltd. provides a range of project management services to clients, ranging from (8)
one-off design of buildings to overall development, and ongoing supervision in
completion of structures. As it is a service company it incurs only labour and overhead
costs.
The following budgeted information is available for the year ahead of Jamuna Ltd.
Cost Pool
Design Costs
Planning Costs
Supervision Costs
Sundry Completion Costs
Cost Driver
Number of drafts of Project
Number of Planning Meetings
Number of Site Visits
Secretarial Support Labour Hours
Technical Labour Costs
Secretarial Support Labour Costs
Technical Labour Hours
Secretarial Support Labour Hours
Number of drafts of Projects
Total Site Visits
Number of Planning Meetings
Tk. 245,000
Tk. 162,015
1,960
9,258
378
560
250
Details relating to two jobs undertaken by Jamuna are as follows:
Particulars
Contract Price Agreed
Technical Labour Hours
Secretarial Support Labour Hours
Number of drafts of Project
ABC
Tk. 10,000
50
67
5
XYZ
Tk. 10,000
45
49
7
Tk.
18,333
32,170
42,084
25,202
Site Visits
Planning Meetings
15
6
30
10
Calculate the total cost of the two jobs using Activity Based Costing approach.
Download