Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 Grand Stay Hotel- Floor No 43- Main Kitchen Renovation works CLIENT : Grand Stay Hotel PROJECT MANAGERS : Riwaq Projects Management MAIN CONTRACTOR : Helium MEP METHOD STATEMENT FOR SCREED WORKS 1|P age Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 TABLE OF CONTENTS 1. SCOPE OF WORK, METHODOLOGY 2. PROJECT ORGANIZATION FOR HEALTH AND SAFETY CONTROL 3. HEALTH AND SAFETY RISKS AND CONTROL 4. ACCESS AND EGRESS 5. LIGHTING 6. PLANT & EQUIPMENT 7. PERSONNEL TRAINING CERTIFICATION 8. HAZARDOUS MATERIAL / SUBSTANCE 9. WASTE MANAGEMENT 10. SPECIAL CONTROL MEASURES 11. APPENDIXES; A - CHECK LIST B - INSPECTION TEST PLAN C - RISK ASSESSMENT D- TDS 2|P age Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 PREFACE The purpose of this method statement is to establish, monitor and control all activities during Screed Works in accordance to the requirements prescribed in the drawings and project specifications. RIWAQ PROJECTS MANAGEMENT present this method statement for review and to notify those who involved in the construction to attain the consistency of work towards the common objectives. This Method statement is a controlled document and only the current revision number is valid and authorised. All necessary parties involved in the execution of this method will be competent and authorised for their respective roles and will be fully conversant with the contents of this document. Signed: Date: 18-Jan-2021 3|P age Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 1. SCOPE OF WORK, METHODOLOGY 1.1 SCOPE & OBJECTIVE This document details the methods and quality controls to be implemented in carrying out Screed Works within the scope of RIWAQ PROJECTS MANAGEMENT at ACT1|ACT2 Project. The method statement covers all activities related to the application of bonded screed. 1.2 DEFINITIONS AND ABBREVIATIONS DEFINITIONS Client Grand Stay Hotel Project Floor no 43 -Main kitchen renovation Project Manager Riwaq Projects Management Main Contractor Heluim MEP MUST Signifies a legal or statutory requirement MAY Signifies a feature which is discretionary SHALL Signifies a requirement made mandatory by this Method Statement 4|P age Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 ABBREVIATIONS QA - QUALITY ASSURANCE is the planning and organizing of a system or program to maintain a required level of quality or reliability. This includes auditing the system’s operation and related controls to assure that they are being executed properly and functioning as expected. Quality shall be assured by Contractor/Client. QC – QUALITY CONTROL is a part of Quality Assurance, implements the latter by examining physical characteristics and comparing them to established and acceptable Quality Documents as stated in the quality assurance program or plan Quality shall be controlled by Sub-Contractor in accordance with the Quality Documents. ITP INSPECTION & TEST PLAN means the document which contains sequence of activities in a process, highlights the applicable Quality Documents, and inspection criticalities. PAR - PREVENTIVE ACTION REQUEST means to eliminate the causes of a potential nonconformity or other potentially undesirable situation CAR - CORRECTIVE ACTION means to eliminate the causes of a detected nonconformity or other undesirable situation. QUALITY DOCUMENTS means drawings specification, procedure, record formats, codes and standards specified in the documents issued by the Contractor/Company to the Subcontractor. SITE means the place, designated by Client for further development, where the construction activities shall be carried out by Sub-contractor. PROCEDURE describes how a process is performed. TPI - Third Party Inspection 5|P age Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 1.3 CODES, STANDARDS & REFERENCES TYPE SPECIFICATIONS/CODES DOC REFERENCE Project Specification – General Specifications section Hand and Power Operated Tools - DM COCSP Chapter 21 Concrete and masonry - DM COCSP Chapter 10 HSE REQUIREMENT PPE - DM COCSP Chapter 4 All application Local Laws Regulations Technical Guidelines. 1.4 PLANT & EQUIPMENT REQUIREMENTS 1. 2. 3. 4. 5. 6. 7. 8. 9. Power Float – Petrol & Electrical Trowels Dabbling Bar Straight Edges Shovels Small Hand tools Hand held grinders Concrete grinder/polisher Reducer 6|P age Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 1.5 MATERIALS S. No. Material Details 1 Dry Mix Concrete – Screed 2 Bonding Agent 3 Edge Strip 4 Cement 5 Dust Proof Coating Material wherever applicable (Mapetop N AR6) 6 Crack Repair Material (Mapei: Eporip) 1.6 SEQUENCE OF WORKS 1. Prior to screeding 2. Bonded screed 3. Application 4. 1.7 Post screed DETAILED PROCEDURE Surface Preparation: The works shall be executed in accordance with the following methodology and sequence after ensuring that all the MEP services are laid and MEP clearance has obtained. Reference: ASTM C 150, Type I Project specification 03530 7|P age Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 Prior to Screeding works at Site Ensure that all materials and documentation have been approved in writing prior to commencement of any works. Pump locations and movement of truck mixers must be agreed with the main contractor logistic team on daily basis. For the floors from ground level to a maximum of 18 floors it may be possible to use our mobile concrete pump this will be dependent on how close we can get to the building and the number of podiums that are in place. Static vertical concrete lines will be placed by Cherry Tree Technical Services LLC after consultation about the location with the main contractor and Separate Logistic layout showing the routing shall be submitted for your approval in due course considering static line each floor that screed is required a 90-degree bend will be fitted to the pipe enabling us to tap into the line for each pour. Whether it is the mobile pump or the static line a reducer is connect to the pipe to allow us to connect our 63mm diameter, 20 metre length rubber hoses. The maximum amount of hoses to be used at one time should be 10. When using the static line, it should not be necessary to use more than 5 hoses at one time. The use of the flexible pipe will enable us to move in and out of rooms very quickly. Once screed has been completed all of the flexible hose will be removed and the static line recapped. Application of Bonding Agent at Dry Areas For Bonded screed ensure that the area (slab) is clean and free of dust. The floor areas to be screeded should have a texture to achieve sufficient bonding to the screed and within screed thickness/tolerance. The floor will be inspected by CTTS and ensure the requirement of scabbling to achieve sufficient key for the bonding of screed & submit inspection to consultant for approval along with a copy of MEP clearance. Upon obtaining approval from Consultant on the surface preparation bonding agent shall be applied by Mixing 3 parts water, 1 part bonding agent and 1part cement together and apply by using a broom to spread the mix to the entire areas that will be screeded. This process is repeated at every area before screed applied. It is very important to ensure that the bonding material does not dry out prior to the screed being poured and that screed should always be wet on wet with the bonding material. Laying of Screeding Works The Datum line shall be strictly followed as provided by Main Contractor and the drop for the final finishes given in writing. A laser level will then be used to transfer the levels around the area that are to be screeded. The screed will arrive by truck mixer form one of the approved read-mix suppliers, the delivery ticket will be checked against the approved mixed design to ensure that the correct grade, flowability & materials have been supplied. The screed will be continuously applied to the designated areas and continuously checked with the laser to ensure the correct levels are being maintained. The skilled masons will then use aluminium straight edges or dabbling bars of different sizes depending on area and space available to tamp the screed and give a suitable finish ready for power floating.(Polythene sheet shall be laid over the waterproofing in the wet area as per the approved shop drawings). 8|P age Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 Finishing/Power floating of Screed Works Float and trowel to finish the screed including all edges, using a power float. All screeds that are to receive ceramics, terrazzo and marble will be finished using a power float with a pan attached to give an orange peel effect. Screed that will receive carpet, vinyl and epoxy will be finished with power float blades leaving a smooth finish. Screed that will receive a Dust proof Coating Mapetop N AR6 shall be sprinkled at a rate of min.1.5kg/sqm before the Concrete starts to set, once Dust proof coating is observed the Moisture from the Screed then Power floating shall be carried out leaving a smooth finish. Once the power floating has been completed Polythene sheets will be laid across the screed to ensure correct curing or a curing agent will be applied. The screeded area will be open to foot traffic approximately 8 hours after power floating is completed. The screed should be cured for 2 days and no equipment or materials should be placed on the screed for at least 48 hours. 7 Days & 28 day Cubes to be made for each pour over 400m2/ as directed by the Consultant, these will be tested by a third party and all results issued to consultant for approval. Post Screeding and treatment of Construction/Movement Joint Within 48 hours saw cut joints will be made into the screed using a concrete road saw and/or hand- held grinders. The area will be cut into a maximum of 25m2 however this will be reduced where columns and other abutments i.e. doorways are situated as these are potential crack areas. The depth of the saw cut should be equal to one of the screed thickness but should never be less than 13mm. Cherry Tree Technical Services LLC will liaise with the main contractor on saw cuts so that any joints that are specifically required for the final finishing can be reflected through the screed. An inspection will be raised for Completion of Screeding works along with As-built level for Consultant approval. The screed finish will have a tolerance of 3mm over a 3m straight edge to check for any surface deviations, as per the project specification. Note: All procedures are in line with British Standards 8204-1 Rectification of Cracks on Screed: Major cracks can be treated with Crack filler material (MAPEI - EPORIP). 9|P age Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 1.8 ENVIRONMENTAL, SAFETY AND HEALTH 1.8.1 Activity Risk Assessment A risk assessment analysing potential risks and their mitigation measures is attached to this method statement in Appendix B. 1.8.2 HSE General Precautions & General Mitigation Measures/Controls Activity to be adequately supervised by competent staff (both Construction & HSE). All Personnel/Workforce involved in the activity to be inducted, and received the required training/competencies BEFORE commencing the activity. Engineer/Supervisor/Foremen In-Charge to conduct Daily Activity Briefing form, and discuss it with the workforce BEFORE commencing the activity (form and discussion to be in the language understood by the workforce) Required Permits/NOCs (including Permits to Work, as applicable) to be obtained ahead of time (BEFORE commencing the activity) (if any) All Plants/Machines/Vehicles/Equipment used in the activity to be pre-inspected and approved by the competent authorized personnel HSE Procedures relevant/applicable to the activity to be reviewed by the Engineer/Supervisor In-Charge, and specific precautions to be conveyed to the Foreman/Charge-Hand and Workforce through MS/RA briefing and other forms of communications. All Personnel/Workforce involved in the activity to fully comply with 5 point PPE requirement (Personal Protective Equipment) Use adequate and visible HSE signage, posters and board to promote awareness. Ensure adequate rest areas (welfare facilities) are accessible. Engineer/Supervisor/Foreman/Charge-Hand to be familiarized with Emergency Response Plan & Contact Numbers. Emergency contact numbers to be posted on site. Supply toilets and cool drinking water at the immediate area of the activities prior to commencement of works. The notifications of adverse weather conditions like high wind speed and TWL levels will be given to site construction. 1.9 ORGANISATIONAL RESPONSIBILITIES 10 | P a g e Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 1.9.1 Construction Manager Implement and maintain a successful completion of the work. Communicate this Method Statement to his subordinates. Provide his subordinates with the information they need to carry out their responsibilities. Enforce the application of this document once it is approved. Stop all unsafe work activities. Ensure the Health and Safety of the personnel on the site. Ensure that the requirements of the Project Specifications and relevant ITP is followed and implemented during construction Ensure requirements of tower crane installation is followed and implemented during construction. 1.9.2 HSE Manager Ensure Safe work procedures implemented and followed for each activity. Monitor in the implementation of this method statement. Provide required training. Regularly pay site visits to ensure that safety is being exercised at site as per requirement. Advise the Construction Manager for any intervention for safety procedures. Verify field activities are following the MS/RA and any new risks not previously identified are addressed and reflected in a revised/new MS/RA. Stop all unsafe work activities. 1.9.3 QC Manager Supervise of Quality Control activities involving all materials; undertake the more complex inspection and resolve technical and client issues on Quality Engineering. Assign QC Engineers and their monitoring all Site Inspection activities. Interpret codes, standards and project specifications to ensure contract requirements are met. Liaise with internal and external concerned parties to co-ordinate presence at inspections. Shall conduct inspections as per the Method Statement & ensure that all procedures in the Method Statement are implemented. Review and make recommendations for the continuing development and improvement of Inspection Test Plans and Quality Control Procedures / Method Statements specifically in relation to workmanship activities. Supervise of Quality Control activities involving all materials of tower. 1.9.4 Site Engineer Assist the section engineer in carrying out his responsibilities. Coordinate the work with the General Foreman. Directly monitor the construction activities at site. Implement the relevant ITP Ensure that the quality of the works meets the requirements of the Project Specifications, ITPs and QCPs Ensure that working areas are properly covered with work permits. Report on the spot of any non-conformance to the section engineer. Provide all necessary tools, equipment, and material required at site. Ensure that safety awareness at site is continuously maintained through JSTI and tool boxes talks. 11 | P a g e Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 Make sure that site personnel are adequately trained to do the job. Stop all unsafe work activities. 1.9.5 QC Engineer Maintain all quality records properly documented. Conduct inspections and monitor the required tests. Determining and reporting any non-conformance to M/S MACE / ARCH GROUP Manager. Ensuring that all personnel are fully aware with all the quality requirements and applications for all quality documents as relevant to their discipline. Ensuring appropriate supervision for all work activities enabling quality related operations to be effectively covered. Coordinate with the Independent Laboratory representative so that all tests are carried out as required by the specifications and records as per the Contractors Quality Control Plan. 1.9.6 Safety Officer Ensure that toolbox talks & DAB are conducted as per plan. Assist in the implementation of this Method Statement. Provide the required training for the site personnel involved. Monitor and advice to site supervisors all requirement for tools to maintain a safe working environment. Monitor the compliance with procedures with respect to equipment’s and related certification and permits. Stop all unsafe work activities. 1.9.7 Surveyor Execution of daily survey field tasks according to the procedures of the Survey Dept. Setting out and as-built of tasks provided by Senior Survey Engineer. Keeping the survey instruments and accessories in a good condition. Preparation of survey sketches and handing over of data. Handing over of set-out points or lines to responsible site engineer. Maintaining the Survey Monuments and Geodetic Network points. Control of subcontractor Surveyors daily work and data. 1.9.8 Subcontractor Ensure to follow Project Quality Plan and specifications strictly Execution of works as per approved drawings and specification Ensure to follow Project Safety plan 1.9.9 Permit to Works (PTW) Person Implement the requirements of the work where permit to work is required. Undertake restricted work (and general work) safely and in accordance with the PTW. Make sure equipment and area is safe before, during and on completion of the task. Seek immediate advice if circumstances or conditions change while undertaking work. Ensure that all tags and signs are prominently displayed so that others are aware. 2. PROJECT ORGANIZATION FOR HEALTH AND SAFETY CONTROL 12 | P a g e Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 Project Manager-HSE ManagerConstruction ManagerSite ManagerSite Engineer (Cherry Tree) Safety Officer 3. HEALTH AND SAFETY RISKS AND CONTROL All risk associated with the activity identified through sufficient and suitable risk assessment with control measures (Refer Risk Assessment) 4. ACCESS AND EGRESS Project Team will ensure that safe access and egress are provided at the work locations. Arrangements highlighted as per attached drawing. 5. LIGHTING Adequate lighting arrangements will be made available; Lux Level must be minimum 50. 6. EQUIPMENTS Equipment’s should be thoroughly inspected, tagged and colour coded. Manufactures certificates to be documented along with Third party certificates. Daily pre task inspections required and weekly check list to be recorded. 7. HAZARDOUS MATERIAL / SUBSTANCE Concrete 8. WASTE MANAGEMENT All concrete waste to be collected and disposed separately and do not mix with open soil. 9. SPECIAL CONTROL MEASURES Task specific PPEs should be worn by all masons involved in the task. Polythene sheets to be stored on designated area with adequate firefighting devices. Emergency procedures will be clearly briefed to all involved parties. 13 | P a g e Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 APPENDIX –A CHECK LIST 14 | P a g e Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 APPENDIX –B INSPECTION TEST PLAN (ITP) 15 | P a g e Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 APPENDIX –C RISK ASSESSMENT 16 | P a g e Document No. MST/021 Revision No. 0 Date: 18-Jan-2021 APPENDIX –D TDS 17 | P a g e