Uploaded by BATKINS INC

April 08-14 2021 30TH WEEKLY REPORT

advertisement
BATKINS INCORPORATED
30TH WEEKLY UPDATE
APRIL 14, 2021
ST. LUKES MEDICAL CENTERCOLLEGE OF MEDICINE
STRUCTURAL RETROFI TTI NG AND EXTERI OR REPAI NTI NG
NTP D AT E D J U NE 2 6 , 2 0 2 0
PREPARED BY: KGHAPITA
CHECKED BY: SDMLAYLO/RDSAPITANAN
NOTED BY: LLCANTUBA/STLAGMAN
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
PROJECT OVERALL ACTIVITIES:
EXTERIOR
II. APPLICATION OF P.U. SEALANT AT CHB WALL (EXTERIOR)
BATKINS INCORPORATED
I & IX.
I & IX.
I & IX
VII & VIII.
I&IX. GEN. REQ. & APPPLICATION OF RUBBERIZED
ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
FROM GROUND FLOOR TO TOP PARAPET.
VII & VIII. USING NON-SHRINK MORTAR & APPLICATION OF
MS300X-PLUS AT LEDGES (5TH FLOOR TO 12TH FLOOR),
CONCRETE GUTTER
INTERIOR
III. APPLICATION OF PRESSURIZED EPOXY INJECTION FOR
CRACKS ON INTERIOR RC WALL, COLUMNS & BEAMS.
IV. GRAVITY EPOXY INJECTION (FLOOR SLAB)
V. APPLICATION OF FIBRE-REINFORCED NON-SHRINK
MORTAR AND STRUCTURAL CARBON FIBER AT COLUMNS,
BEAM SOFFIT AND RC WALLS ON SPALLED OF CONCRETE.
VI. APPLICATION OF FLEXIBLE HYDRAULIC MORTAR AT 12TH
FLOOR SOFFIT FIRE EXIT STAIR (UNDERSLAB OF CONCRETE
OVERHEAD TANK AT ROOFDECK)
ACCOMPLISHED ACTIVITIES THIS WEEK
2
PROJECT
SUBJECT
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: PROJECTED ACTUAL ACCOMPLISMENT
BATKINS INCORPORATED
(TO REFLECT BALANCE OF WORK PER ITEM III.)
SUMMARY OF OVERALL ACTIVITIES ACCOMPLISHMENT BASED ON PERCENTAGE WEIGHT
SCOPE OF WORK
EXTERIOR
II. APPLICATION OF P.U. SEALANT AT CHB WALL
I&IX. GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100%
FIBERMESH REINFORCEMENT FROM GROUND FLOOR TO TOP PARAPET.
VII & VIII. USING NON-SHRINK MORTAR & APPLICATION OF MS300X-PLUS AT LEDGES
(5TH FLOOR TO 12TH FLOOR), CONCRETE GUTTER
AFFECTED AREAS
FRONT & REAR ELEVATION
FRONT, REAR, RIGHT & LEFT
ELEVATION
LEDGES, PARAPET & CONCRETE
GUTTER
ESTIMATED BASE PERCENTAGE
ACTUAL
AREA or L.m.
WEIGHT
ACCOMPLISHMENT
2,200 L.m.
10.71%
10.71%
6,858 Sq.m.
60.71%
60.71%
991.38 Sq.m.
14.29%
14.29%
85.71%
85.71%
80 L.m.
6.25%
5.16%
134 L.m.
3.79%
3.79%
90 Sq.m.
2.46%
2.46%
25 Sq.m.
1.79%
1.79%
14.29%
100.00%
13.20%
98.91%
SUBTOTAL
INTERIOR
III. PRESSURIZED EPOXY INJECTION FOR CRACKS ON INTERIOR RC WALL,
COLUMNS & BEAMS.
IV. GRAVITY EPOXY INJECTION (FLOOR SLAB)
V. APPLICATION OF FIBRE-REINFORCED NON-SHRINK MORTAR AND STRUCTURAL
CARBON FIBER AT COLUMNS, BEAM SOFFIT AND RC WALLS ON SPALLED OF
CONCRETE.
VI. APPLICATION OF FLEXIBLE HYDRAULIC MORTAR AT 12TH FLOOR SOFFIT FIRE EXIT
STAIR (UNDERSLAB OF CONCRETE OVERHEAD TANK AT ROOFDECK)
CRACKS AT BASEMENT TO
PENTHOUSE
1ST TO 2ND FLOOR
BASEMENT TO PENTHOUSE AT
PARKING AREA AND STAIRS: 20
COLUMNS FROM GROUND TO
4TH FLOOR
UNDER SLAB OF CONCRETE
OVERHEAD TANK AT ROOFDECK
SUBTOTAL
TOTAL
NOTE: BALANCE WORK ON INTERIOR:
ITEM III.PRESSURIZED EPOXY INJECTION =1.09%
AT 1OTH,11TH, AND 12TH FLOORS DUE TO
UNAVAILABILITY OF AREAS
PREPARED BY: MJRUTMACDER/SDMLAYLO
NOTED BY: STL/LLC
ACCOMPLISHMEN
T BASED ON
EXTERIOR AND
INTERIOR
100%
92.37%
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
S CURVE BASED ON REVISED OVERALL ACTIVITIES ACCOMPLISHMENT
FROM SEPTEMBER 7, 2020 – APRIL 14, 2021
SEPTEMBER 2020
OCTOBER 2020
NOVEMBER 2020
DECEMBER 2020
JANUARY 2021
FEBRUARY 2021
MARCH 2021
APRIL 2021
100%
94.62%
88.40%
90.54%
82.14%
WEEK 30:
PROJECTED
94.62%
ACTUAL
90.54%
77.39%
73.85%
67.85%
62.10% 62.79%
61.38%
59.76%
55.43%
53.14%
57.43%
50.00%
48.07%
45.12%
42.98%
40.38%
ACCOMPLISHMENT MONITORING
94.62%
- 88.40%
6.22%
29.22%
WEEK 30 (APRIL 14)
WEEK 29 (APRIL 7)
7 DAYS ACCOMPLISHMENT
(APRIL 8-14)
21.50%
14.94%
13.91%
11.43%
8.60% 8.92%
6.80%
0.20% 0.29% 1.16% 1.70%
NOTE: THIS REVISED S-CURVE IS PRESENTED DUE TO START DATE DIFFERENCE OF INTERIOR
(SEPTEMBER. 7 ,2020) AND EXTERIOR WORKS (NOVEMBER 5, 2020) RESPECTIVELY
LINE CHART
4
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
SUMMARY OF WORKS FOR ACITIVITY II WITH ACCOMPLISHMENT UPDATE FROM NOVEMBER 5, 2020 – APRIL 14, 2021
ACTIVITY II: APPLICATION OF P.U. SEALANT
WEEK 30
ELEVATION
(WALL)
ESTIMATED LI NEAR METER OF
DISTRIBUTION
(L.m.)
%
ACCOMPLI SHMENT
%
BALANCE
%
FRONT
1,100.00 L.m.
50.00%
50.00%
0.00%
REAR
1,100.00 L.m.
50.00%
50.00%
0.00%
TOTAL
2,200.00 L.m.
100%
100.00%
0.00%
TABLE 2.0
5
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY II FRONT SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY II: APPLICATION OF P.U. SEALANT
100.00% WEEK 30
FRONT ELEVATION
%
LOCATION (REFER TO KEYPLAN)
AREA = 1,100 L.m.
FRONT
ELEV.
ITEM
ACTUAL OVER TOTAL
1
1. Mob: Hauling of tools, materials and safety orientation.
5%
1.00
5.00%
2. Hauling and installation of jibs,manual gondola/fabricated steel and safety life lines.
10%
1.00
10.00%
3. Lay-out and identification of horizontal and vertical joints (between beams & CHB wall and between column & CHB wall)
15%
1.00
15.00%
4. Cutting and grinding of the identified horizontal & vertical joints at least 10-15mm WIDTH by 30-35mm depth.
20%
1.00
20.00%
5. Removal of dirt, dust and other laitance and installation of backing rod as bond breaker.
15%
1.00
15.00%
4. Straighten the edges of sealant to be applied.
10%
1.00
10.00%
3. Application of Polyurethane P.U. sealant (paintable P.U. sealant)
20%
1.00
20.00%
5. Punch listing, final cleaning, turn-over and pull-out
5%
1.00
5.00%
100%
8.00
100.00%
TOTAL
DONE ACTIVITY
ONGOING ACTIVITY
6
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
SUMMARY OF WORKS FOR ACITIVITY I & IX WITH ACCOMPLISHMENT UPDATE FROM NOVEMBER 5, 2020 – APRIL 14, 2021
ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT
WITH 100% FIBERMESH REINFORCEMENT
WEEK 30
ELEVATI ON
(WALL)
ESTI M ATED AREA OF
DI STRI BU TI ON
(Sq.m.)
%
ACCOM PLI SHM ENT
%
BALANCE
%
FRONT
1,002 Sq.m.
14.61%
14.54%
0.07%
RI GHT SI DE
2,326.50 Sq.m.
33.92%
33.75%
0.17%
LEFT SI DE
2,461.20 Sq.m.
35.89%
35.53%
0.36%
REAR
1,068.75 Sq.m.
15.58%
15.58%
0.00%
TOTAL
6,858.45 Sq.m.
100%
99.40%
0.60%
TABLE 2.0
7
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY I & IX FRONT SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
99.50% WEEK 30
FRONT ELEVATION
%
LOCATION (REFER TO KEYPLAN)
AREA = 1,002 Sq.m.
FRONT
ELEV.
ITEM
ACTUAL OVER TOTAL
1
1. Mob: Hauling of tools, materials and safety orientation.
5%
1.00
5.00%
2. Installation of jibs, motorized/manual gondola/fabricated steel ladder and safety lifelines.
5%
1.00
5.00%
15%
1.00
15.00%
5%
1.00
5.00%
35%
1.00
35.00%
5%
1.00
5.00%
5%
1.00
5.00%
5. Basecoat application of rubberized elastomeric paint with 100% fibermesh reinforcement.
10%
1.00
10.00%
6. Application of rubberized elastomeric paint (2 coats).
10%
1.00
10.00%
5%
0.90
4.50%
100%
9.90
99.50%
3. Surface preperation:
3.1 Grooving and grouting of cracks using fibre-reinforce non-shrink mortar with epoxy bonding.
3.2 Removal of unsound plastering and re-plastering using fiber-reinforced non-shrink mortar with epoxy bonding.
3.3 Grinding of the entire surface to remove the blistering/scalling and delaminated paint and to make an anchor pattern.
3.4 Final removal of dirt and dust.
4. Putty application on depressed areas and sealed horizontal & vertical joints.
7. Dismantling/transfer of motorized or manual gondola/fabricated steel ladder.
8. Punch listing, final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
ONGOING ACTIVITY
8
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY I & IX RIGHT SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
99.50% WEEK 30
RIGHT SIDE ELEVATION
%
LOCATION (REFER TO KEYPLAN)
AREA = 2, 326.50 Sq.m.
ITEM
RIGHT SIDE
ELEV.
ACTUAL OVER TOTAL
1
1. Mob: Hauling of tools, materials and safety orientation.
5%
0.5
1.00
5.00%
2. Installation of jibs, motorized/manual gondola/fabricated steel ladder and safety lifelines.
5%
0.5
1.00
5.00%
15%
0.5
1.00
15.00%
5%
0.5
1.00
5.00%
35%
0.5
1.00
35.00%
5%
0.5
1.00
5.00%
5%
0.5
1.00
5.00%
5. Basecoat application of rubberized elastomeric paint with 100% fibermesh reinforcement.
10%
0.5
1.00
10.00%
6. Application of rubberized elastomeric paint (2 coats).
10%
0.5
1.00
10.00%
5%
0.90
4.50%
100%
9.90
99.50%
3. Surface preperation:
3.1 Grooving and grouting of cracks using fibre-reinforce non-shrink mortar with epoxy bonding.
3.2 Removal of unsound plastering and re-plastering using fiber-reinforced non-shrink mortar with epoxy bonding.
3.3 Grinding of the entire surface to remove the blistering/scalling and delaminated paint and to make an anchor pattern.
3.4 Final removal of dirt and dust.
4. Putty application on depressed areas and sealed horizontal & vertical joints.
7. Dismantling/transfer of motorized or manual gondola/fabricated steel ladder.
8. Punch listing, final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
ONGOING ACTIVITY
9
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY I & IX LEFT SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
99.00% WEEK 30
LEFT SIDE ELEVATION
LOCATION (REFER TO KEYPLAN)
AREA = 2,461.20 Sq.m.
%
ITEM
LEFT
SIDE
ELEV.
ACTUAL OVER TOTAL
1
1. Mob: Hauling of tools, materials and safety orientation.
5%
1.00
5.00%
2. Installation of jibs, motorized/manual gondola/fabricated steel ladder and safety lifelines.
5%
1.00
5.00%
3. Surface preperation:
3.1 Grooving and grouting of cracks using fibre-reinforce non-shrink mortar with epoxy bonding.
15%
1.00
15.00%
5%
1.00
5.00%
3.3 Grinding of the entire surface to remove the blistering/scalling and delaminated paint and to make an anchor pattern. 35%
1.00
35.00%
3.4 Final removal of dirt and dust.
5%
1.00
5.00%
4. Putty application on depressed areas and sealed horizontal & vertical joints.
5%
1.00
5.00%
5. Basecoat application of rubberized elastomeric paint with 100% fibermesh reinforcement.
10%
1.00
10.00%
6. Application of rubberized elastomeric paint (2 coats).
10%
0.95
9.50%
5%
0.90
4.50%
100%
9.85
99.00%
3.2 Removal of unsound plastering and re-plastering using fiber-reinforced non-shrink mortar with epoxy bonding.
7. Dismantling/transfer of motorized or manual gondola/fabricated steel ladder.
8. Punch listing, final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
ONGOING ACTIVITY
10
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY I & IX REAR SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
REAR SIDE ELEVATION
LOCATION (REFER TO KEYPLAN)
AREA = 1,068.75 Sq.m.
%
ITEM
100.00%
REAR
ELEV.
WEEK 30
ACTUAL OVER TOTAL
1
1. Mob: Hauling of tools, materials and safety orientation.
5%
1.00
5.00%
2. Installation of jibs, motorized/manual gondola/fabricated steel ladder and safety lifelines.
5%
1.00
5.00%
3. Surface preperation:
3.1 Grooving and grouting of cracks using fibre-reinforce non-shrink mortar with epoxy bonding.
15%
1.00
15.00%
5%
1.00
5.00%
3.3 Grinding of the entire surface to remove the blistering/scalling and delaminated paint and to make an anchor pattern. 35%
1.00
35.00%
3.4 Final removal of dirt and dust.
5%
1.00
5.00%
4. Putty application on depressed areas and sealed horizontal & vertical joints.
5%
1.00
5.00%
5. Basecoat application of rubberized elastomeric paint with 100% fibermesh reinforcement.
10%
1.00
10.00%
6. Application of rubberized elastomeric paint (2 coats).
10%
1.00
10.00%
5%
1.00
5.00%
10.00
100.00%
3.2 Removal of unsound plastering and re-plastering using fiber-reinforced non-shrink mortar with epoxy bonding.
7. Dismantling/transfer of motorized or manual gondola/fabricated steel ladder.
8. Punch listing, final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
0.00
ONGOING ACTIVITY
11
PROJECT
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
SUBJECT
PERIOD
BATKINS INCORPORATED
SUMMARY OF WORKS FOR ACTIVITY VII & VIII WITH ACCOMPLISHMENT UPDATE FROM NOVEMBER 5, 2020 – APRIL 14, 2021
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
WEEK 30
CONCRETE
ESTI MATED AREA OF
GUTTER
DI STRI BUTI ON
(TOTAL
(Sq.m.)
AREA)
FLOOR
LEDGES
(RI GH & LEFT
SI DE)
PARAPET
WALL
(TOTAL AREA)
5th FLOOR
2
0
0
6th FLOOR
2
0
7th FLOOR
2
8th FLOOR
%
ACCOMPLI SHMENT
%
BALANCE
%
83.16 Sq.m.
8.94%
8.76%
0.18%
0
83.16 Sq.m.
8.94%
8.76%
0.18%
0
0
83.16 Sq.m.
8.94%
8.76%
0.18%
2
0
0
83.16 Sq.m.
8.94%
8.76%
0.18%
9th FLOOR
2
0
0
83.16 Sq.m.
8.94%
8.76%
0.18%
10th FLOOR
2
0
0
83.16 Sq.m.
8.94%
8.76%
0.18%
11th FLOOR
2
0
0
83.16 Sq.m.
8.94%
8.76%
0.18%
12th FLOOR
2
0
0
83.16 Sq.m.
8.94%
8.76%
0.18%
ROOF DECK
2
1
1
264.64 Sq.m.
28.46%
27.89%
0.57%
929.92 Sq.m.
100%
98.00%
2.00%
TOTAL
TABLE 3.0
12
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 5TH FLOOR LEFT & RIGHT LEDGES
FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
FIFTH FLOOR
RIGHT & LEFT SIDE ELEV.
LOCATION (REFER TO KEYPLAN)
AREA= 83.16 Sq.m.
98.00% WEEK 30
%
ITEM
LEDGES
ACTUAL OVER TOTAL
RIGHT
ELEV.
LEFT
ELEV.
1. Mob: Hauling of tools, materials and safety orientation.
5%
1
1
2
5.00%
2. Provision of barricades and safety precautins.
5%
1
1
2
5.00%
3. Surface preperation:
3.1 Chipping and grouting of perimeter pipe sleeves.
5%
1
1
2
5.00%
3.2 Determination of slope and slope correction by grinding.
20%
1
1
2
20.00%
3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any).
5%
1
1
2
5.00%
3.4 Grinding of the entire surface to make anchor pattern.
35%
1
1
2
35.00%
4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner.
10%
1
1
2
10.00%
5. Application of MS300X Polyurethane waterproofing (2 coats).
10%
1
1
2
10.00%
1.2
3.00%
0
0.00%
0
0.00%
17
98.00%
6. Installation of temporary socallo around the perimeter of pipe sleeve.
7. Flood testing for 24 hours.
5%
8. Final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
ONGOING ACTIVITY
13
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 6TH FLOOR LEFT & RIGHT LEDGES
FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
98.00% WEEK 30
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
SIXTH FLOOR
RIGHT & LEFT SIDE ELEV.
LOCATION (REFER TO KEYPLAN)
AREA= 83.16 Sq.m.
%
ITEM
LEDGES
ACTUAL OVER TOTAL
RIGHT
ELEV.
LEFT
ELEV.
1. Mob: Hauling of tools, materials and safety orientation.
5%
1
1
2
5.00%
2. Provision of barricades and safety precautins.
5%
1
1
2
5.00%
3. Surface preperation:
3.1 Chipping and grouting of perimeter pipe sleeves.
5%
1
1
2
5.00%
3.2 Determination of slope and slope correction by grinding.
20%
1
1
2
20.00%
3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any).
5%
1
1
2
5.00%
3.4 Grinding of the entire surface to make anchor pattern.
35%
1
1
2
35.00%
4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner.
10%
1
1
2
10.00%
5. Application of MS300X Polyurethane waterproofing (2 coats).
10%
1
1
2
10.00%
1.2
3.00%
0
0.00%
0
0.00%
17
98.00%
6. Installation of temporary socallo around the perimeter of pipe sleeve.
7. Flood testing for 24 hours.
5%
8. Final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
ONGOING ACTIVITY
14
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 7TH FLOOR LEFT & RIGHT LEDGES
FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
SEVENTH FLOOR
LOCATION (REFER TO KEYPLAN)
AREA= 83.16 Sq.m.
98.00% WEEK 30
RIGHT & LEFT SIDE ELEV.
%
ITEM
LEDGES
ACTUAL OVER TOTAL
RIGHT
ELEV.
LEFT
ELEV.
1. Mob: Hauling of tools, materials and safety orientation.
5%
1
1
2
5.00%
2. Provision of barricades and safety precautins.
5%
1
1
2
5.00%
3. Surface preperation:
3.1 Chipping and grouting of perimeter pipe sleeves.
5%
1
1
2
5.00%
3.2 Determination of slope and slope correction by grinding.
20%
1
1
2
20.00%
3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any).
5%
1
1
2
5.00%
3.4 Grinding of the entire surface to make anchor pattern.
35%
1
1
2
35.00%
4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner.
10%
1
1
2
10.00%
5. Application of MS300X Polyurethane waterproofing (2 coats).
10%
1
1
2
10.00%
1
3.00%
0
0.00%
0
0.00%
17
98.00%
6. Installation of temporary socallo around the perimeter of pipe sleeve.
7. Flood testing for 24 hours.
5%
8. Final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
ONGOING ACTIVITY
15
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 8TH FLOOR LEFT & RIGHT LEDGES
FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
98.00% WEEK 30
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
EIGHTH FLOOR
RIGHT & LEFT SIDE ELEV.
LOCATION (REFER TO KEYPLAN)
AREA= 83.16 Sq.m.
%
ITEM
LEDGES
ACTUAL OVER TOTAL
RIGHT
ELEV.
LEFT
ELEV.
1. Mob: Hauling of tools, materials and safety orientation.
5%
1
1
2
5.00%
2. Provision of barricades and safety precautins.
5%
1
1
2
5.00%
3. Surface preperation:
3.1 Chipping and grouting of perimeter pipe sleeves.
5%
1
1
2
5.00%
3.2 Determination of slope and slope correction by grinding.
20%
1
1
2
20.00%
3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any).
5%
1
1
2
5.00%
3.4 Grinding of the entire surface to make anchor pattern.
35%
1
1
2
35.00%
4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner.
10%
1
1
2
10.00%
5. Application of MS300X Polyurethane waterproofing (2 coats).
10%
1
1
2
10.00%
1
3.00%
0
0.00%
0
0.00%
17
98.00%
6. Installation of temporary socallo around the perimeter of pipe sleeve.
7. Flood testing for 24 hours.
5%
8. Final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
ONGOING ACTIVITY
16
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 9TH FLOOR LEFT & RIGHT LEDGES
FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
NINTH FLOOR
RIGHT & LEFT SIDE ELEV.
LOCATION (REFER TO KEYPLAN)
AREA= 83.16 Sq.m.
98.00% WEEK 30
%
ITEM
LEDGES
ACTUAL OVER TOTAL
RIGHT
ELEV.
LEFT
ELEV.
1. Mob: Hauling of tools, materials and safety orientation.
5%
1
1
2
5.00%
2. Provision of barricades and safety precautins.
5%
1
1
2
5.00%
3. Surface preperation:
3.1 Chipping and grouting of perimeter pipe sleeves.
5%
1
1
2
5.00%
3.2 Determination of slope and slope correction by grinding.
20%
1
1
2
20.00%
3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any).
5%
1
1
2
5.00%
3.4 Grinding of the entire surface to make anchor pattern.
35%
1
1
2
35.00%
4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner.
10%
1
1
2
10.00%
5. Application of MS300X Polyurethane waterproofing (2 coats).
10%
1
1
2
10.00%
1
3.00%
0
0.00%
0
0.00%
17
98.00%
6. Installation of temporary socallo around the perimeter of pipe sleeve.
7. Flood testing for 24 hours.
5%
8. Final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
ONGOING ACTIVITY
17
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 10TH FLOOR LEFT & RIGHT LEDGES
FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
98.00% WEEK 30
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
TENTH FLOOR
RIGHT & LEFT SIDE ELEV.
LOCATION (REFER TO KEYPLAN)
AREA= 83.16 Sq.m.
%
ITEM
LEDGES
ACTUAL OVER TOTAL
RIGHT
ELEV.
LEFT
ELEV.
1. Mob: Hauling of tools, materials and safety orientation.
5%
1
1
2
5.00%
2. Provision of barricades and safety precautins.
5%
1
1
2
5.00%
3. Surface preperation:
3.1 Chipping and grouting of perimeter pipe sleeves.
5%
1
1
2
5.00%
3.2 Determination of slope and slope correction by grinding.
20%
1
1
2
20.00%
3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any).
5%
1
1
2
5.00%
3.4 Grinding of the entire surface to make anchor pattern.
35%
1
1
2
35.00%
4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner.
10%
1
1
2
10.00%
5. Application of MS300X Polyurethane waterproofing (2 coats).
10%
1
1
2
10.00%
1.2
3.00%
0
0.00%
0
0.00%
17
98.00%
6. Installation of temporary socallo around the perimeter of pipe sleeve.
7. Flood testing for 24 hours.
5%
8. Final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
ONGOING ACTIVITY
18
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 11TH FLOOR LEFT & RIGHT LEDGES
FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
ELEVENTH FLOOR
RIGHT & LEFT SIDE ELEV.
LOCATION (REFER TO KEYPLAN)
AREA= 83.16 Sq.m.
98.00% WEEK 30
%
ITEM
LEDGES
ACTUAL OVER TOTAL
RIGHT
ELEV.
LEFT
ELEV.
1. Mob: Hauling of tools, materials and safety orientation.
5%
1
1
2
5.00%
2. Provision of barricades and safety precautins.
5%
1
1
2
5.00%
3. Surface preperation:
3.1 Chipping and grouting of perimeter pipe sleeves.
5%
1
1
2
5.00%
3.2 Determination of slope and slope correction by grinding.
20%
1
1
2
20.00%
3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any).
5%
1
1
2
5.00%
3.4 Grinding of the entire surface to make anchor pattern.
35%
1
1
2
35.00%
4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner.
10%
1
1
2
10.00%
5. Application of MS300X Polyurethane waterproofing (2 coats).
10%
1
1
2
10.00%
1.2
3.00%
0
0.00%
0
0.00%
17
98.00%
6. Installation of temporary socallo around the perimeter of pipe sleeve.
7. Flood testing for 24 hours.
5%
8. Final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
ONGOING ACTIVITY
19
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 12TH FLOOR LEFT & RIGHT LEDGES
FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
TWELFTTH FLOOR
RIGHT & LEFT SIDE ELEV.
LOCATION (REFER TO KEYPLAN)
AREA= 83.16 Sq.m.
98.00% WEEK 30
%
ITEM
LEDGES
ACTUAL OVER TOTAL
RIGHT
ELEV.
LEFT
ELEV.
1. Mob: Hauling of tools, materials and safety orientation.
5%
1
1
2
5.00%
2. Provision of barricades and safety precautins.
5%
1
1
2
5.00%
3. Surface preperation:
3.1 Chipping and grouting of perimeter pipe sleeves.
5%
1
1
2
5.00%
3.2 Determination of slope and slope correction by grinding.
20%
1
1
2
20.00%
3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any).
5%
1
1
2
5.00%
3.4 Grinding of the entire surface to make anchor pattern.
35%
1
1
2
35.00%
4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner.
10%
1
1
2
10.00%
5. Application of MS300X Polyurethane waterproofing (2 coats).
10%
1
1
2
10.00%
1
3.00%
0
0.00%
0
0.00%
17
98.00%
6. Installation of temporary socallo around the perimeter of pipe sleeve.
7. Flood testing for 24 hours.
5%
8. Final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
ONGOING ACTIVITY
20
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII PENTHOUSE LEFT & RIGHT LEDGES
FROM NOVEMBER 5, 2020 – APRIL 14, 2021
THIS WEEK:
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.)
98.00% WEEK 30
ROOF DECK
ROOF DECK
%
LOCATION (REFER TO KEYPLAN)
AREA = 181.48 Sq.m. CONCRETE GUTTER, AREA = 83.16 Sq.m. LEDGES
RIGHT & LEFT SIDE
ELEV.
ITEM
ACTUAL OVER TOTAL
PARAPET
WALL
CONCRETE
GUTTER
1
2
RIGHT
ELEV.
LEFT
ELEV.
LEDGES
1. Mob: Hauling of tools, materials and safety orientation.
5%
1
1
1
1
4
5.00%
2. Provision of barricades and safety precautins.
5%
1
1
1
1
4
5.00%
3. Surface preperation:
3.1 Chipping and grouting of perimeter pipe sleeves.
5%
1
1
1
1
4
5.00%
3.2 Determination of slope and slope correction by grinding.
20%
1
1
1
1
4
20.00%
3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any).
5%
1
1
1
1
4
5.00%
3.4 Grinding of the entire surface to make anchor pattern.
35%
1
1
1
1
4
35.00%
4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner.
10%
1
1
1
1
4
10.00%
5. Application of MS300X Polyurethane waterproofing (2 coats).
10%
1
1
4
10.00%
0.6
0.6
2.4
3.00%
0
0.00%
0
0.00%
34
98.00%
6. Installation of temporary socallo around the perimeter of pipe sleeve.
7. Flood testing for 24 hours.
1
0.6
1
0.6
5%
8. Final cleaning, turn-over and pull-out.
TOTAL
DONE ACTIVITY
100%
9%
9%
9%
ONGOING ACTIVITY
21
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
FRONT
ELEVATION
22
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
FRONT SIDE EXTERIOR WALL DURING PUTTY APPLICATION AND 1ST
COAT TO TOP COAT APPLICATION OF ELASTOMERIC PAINT.
BATKINS INCORPORATED
FRONT SIDE EXTERIOR WALL AFTER PUTTY APPLICATION AND 1ST
COAT TO TOP COAT APPLICATION OF ELASTOMERIC PAINT.
FRONT EXTERIOR WALL
ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
-DONE FOR PUTTY AND 1ST TO TOP COAT
APPLICATION OF ELASTOMERIC PAINT.
23
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
FRONT SIDE EXTERIOR WALL (FRONT CANOPY) AFTER 1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH.
FRONT EXTERIOR WALL
ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
-DONE FOR PUTTY AND 1ST TO TOP COAT
APPLICATION OF ELASTOMERIC PAINT.
24
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
LEGEND:
100% DONE FOR SURFACE PREP.
100% DONE PUTTY APPLICATION
100% DONE 1ST & TOP COAT APPLICATION
FRONT ELEVATION (EXTERIOR WALL)
ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
-DONE FOR PUTTY AND 1ST TO TOP COAT
APPLICATION OF ELASTOMERIC PAINT.
25
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
LEGEND:
0% BALANCE.
100% DONE FOR SEALANT APPLICATION.
FRONT ELEVATION (EXTERIOR WALL)
ACTIVITY II. APPLICATION OF P.U. SEALANT AT CHB WALL (EXTERIOR)
-DONE FOR P.U. SEALANT APPLICATION
26
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
RIGHT SIDE
ELEVATION
27
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
LEGEND:
100% DONE FOR SURFACE PREP.
100% DONE PUTTY APPLICATION
100% DONE 1ST & TOP COAT APPLICATION
RIGHT SIDE ELEVATION (EXTERIOR WALL)
ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
28
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
LEFT SIDE
ELEVATION
29
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
LEFT SIDE (NEAR FRONT) EXTERIOR WALL DURING
GRINDING WORKS AND PUTTY APPLICATION.
BATKINS INCORPORATED
LEFT SIDE (NEAR FRONT) EXTERIOR WALL AFTER PUTTY AND
1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH
FIBERMESH.
LEFT SIDE EXTERIOR WALL
ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
-ON-GOING PUTTY AND 1ST COAT APPLICATION OF
ELASTOMERIC PAINT WITH FIBERMESH.
30
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
LEFT SIDE (NEAR FRONT) EXTERIOR WALL DURING
GRINDING WORKS AND PUTTY APPLICATION.
BATKINS INCORPORATED
LEFT SIDE (NEAR FRONT) EXTERIOR WALL AFTER PUTTY AND
1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH
FIBERMESH.
LEFT SIDE EXTERIOR WALL
ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
-ON-GOING PUTTY AND 1ST COAT APPLICATION OF
ELASTOMERIC PAINT WITH FIBERMESH.
31
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
LEFT SIDE (GROUND FLOOR) PARKING RAMP AFTER 1ST COAT
APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH.
BATKINS INCORPORATED
LEFT SIDE (3RD FLOOR) PARKING RAMP AFTER 1ST COAT
APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH.
LEFT SIDE EXTERIOR WALL
ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
-ON-GOING PUTTY AND 1ST COAT APPLICATION OF
ELASTOMERIC PAINT WITH FIBERMESH.
32
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
LEGEND:
100% DONE FOR SURFACE PREP.
100% DONE PUTTY APPLICATION
95% DONE 1ST COAT APPLICATION WITH
FIBERMESH
92% DONE TOP COAT APPLICATION
`
LEFT SIDE ELEVATION (EXTERIOR WALL)
ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
-ON-GOING 1ST COAT TO TOP COAT APPLICATION
OF ELASTOMERIC PAINT.
33
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
LEFT SIDE PENTHOUSE AFTER TOP COAT
APPLICATION OF MS300X PLUS.
BATKINS INCORPORATED
LEFT SIDE 12TH FLOOR AFTER TOP COAT
APPLICATION OF MS300X PLUS.
LEFT SIDE 7TH FLOOR AFTER TOP COAT
APPLICATION OF MS300X PLUS.
LEFT SIDE LEDGES
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.)
-DONE FOR APPLICATION OF MS300X PLUS.
34
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
LEFT SIDE 6TH FLOOR AFTER TOP COAT
APPLICATION OF MS300X PLUS.
BATKINS INCORPORATED
LEFT SIDE 5TH FLOOR AFTER TOP COAT
APPLICATION OF MS300X PLUS.
LEFT SIDE LEDGES
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.)
-DONE FOR APPLICATION OF MS300X PLUS.
35
PROJECT
SUBJECT
PERIOD
LEGEND:
100%
60%
60%
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
DONE FOR PRIMER APPLICATION.
DONE FOR 1ST COAT MS300X APPLICATION
DONE FOR TOP COAT MS300X APPLICATION
PH
12TH
11TH
10TH
9TH
8TH
7TH
6TH
5TH
LEFT SIDE ELEVATION (LEDGES)
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.)
-DONE FOR BASE COAT APPLICATION.
-ON GOING TOP COAT APPLICATION
36
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
REAR ELEVATION
37
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
I & IX.
100%
DONE FOR
SURFACE PREP.
100%
DONE PUTTY
APPLICATION
100%
DONE TOP COAT
APPLICATION
REAR ELEVATION
ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT
38
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
ROOF DECK
39
PROJECT
SUBJECT
PERIOD
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
BATKINS INCORPORATED
ROOF DECK (ELEVATOR DECK) AFTER TOP COAT APPLICATION OF MS300X PLUS.
ROOF DECK (ELEVATOR DECK)
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.)
-DONE FOR TOP COAT APPLICATION OF MS300X PLUS.
40
PROJECT
SUBJECT
PERIOD
LEGEND:
: ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE
NTP DATED JUNE 26, 2020
: WORK IN PROGRESS (WEEK 30)
: APRIL 8 - 14, 2021
100%
100%
100%
BATKINS INCORPORATED
DONE FOR PRIMER APPLICATION.
DONE FOR 1ST COAT MS300X APPLICATION
DONE FOR TOP COAT MS300X APPLICATION
ROOF DECK (CONCRETE GUTTER, ELEVATOR AND STAIR DECK )
ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.)
-DONE FOR MS300X P.U. APPLICATION
41
BATKINS INCORPORATED
END OF
PRESENTATION
THANK YOU!!!
Download