BATKINS INCORPORATED 30TH WEEKLY UPDATE APRIL 14, 2021 ST. LUKES MEDICAL CENTERCOLLEGE OF MEDICINE STRUCTURAL RETROFI TTI NG AND EXTERI OR REPAI NTI NG NTP D AT E D J U NE 2 6 , 2 0 2 0 PREPARED BY: KGHAPITA CHECKED BY: SDMLAYLO/RDSAPITANAN NOTED BY: LLCANTUBA/STLAGMAN PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 PROJECT OVERALL ACTIVITIES: EXTERIOR II. APPLICATION OF P.U. SEALANT AT CHB WALL (EXTERIOR) BATKINS INCORPORATED I & IX. I & IX. I & IX VII & VIII. I&IX. GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT FROM GROUND FLOOR TO TOP PARAPET. VII & VIII. USING NON-SHRINK MORTAR & APPLICATION OF MS300X-PLUS AT LEDGES (5TH FLOOR TO 12TH FLOOR), CONCRETE GUTTER INTERIOR III. APPLICATION OF PRESSURIZED EPOXY INJECTION FOR CRACKS ON INTERIOR RC WALL, COLUMNS & BEAMS. IV. GRAVITY EPOXY INJECTION (FLOOR SLAB) V. APPLICATION OF FIBRE-REINFORCED NON-SHRINK MORTAR AND STRUCTURAL CARBON FIBER AT COLUMNS, BEAM SOFFIT AND RC WALLS ON SPALLED OF CONCRETE. VI. APPLICATION OF FLEXIBLE HYDRAULIC MORTAR AT 12TH FLOOR SOFFIT FIRE EXIT STAIR (UNDERSLAB OF CONCRETE OVERHEAD TANK AT ROOFDECK) ACCOMPLISHED ACTIVITIES THIS WEEK 2 PROJECT SUBJECT : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : PROJECTED ACTUAL ACCOMPLISMENT BATKINS INCORPORATED (TO REFLECT BALANCE OF WORK PER ITEM III.) SUMMARY OF OVERALL ACTIVITIES ACCOMPLISHMENT BASED ON PERCENTAGE WEIGHT SCOPE OF WORK EXTERIOR II. APPLICATION OF P.U. SEALANT AT CHB WALL I&IX. GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT FROM GROUND FLOOR TO TOP PARAPET. VII & VIII. USING NON-SHRINK MORTAR & APPLICATION OF MS300X-PLUS AT LEDGES (5TH FLOOR TO 12TH FLOOR), CONCRETE GUTTER AFFECTED AREAS FRONT & REAR ELEVATION FRONT, REAR, RIGHT & LEFT ELEVATION LEDGES, PARAPET & CONCRETE GUTTER ESTIMATED BASE PERCENTAGE ACTUAL AREA or L.m. WEIGHT ACCOMPLISHMENT 2,200 L.m. 10.71% 10.71% 6,858 Sq.m. 60.71% 60.71% 991.38 Sq.m. 14.29% 14.29% 85.71% 85.71% 80 L.m. 6.25% 5.16% 134 L.m. 3.79% 3.79% 90 Sq.m. 2.46% 2.46% 25 Sq.m. 1.79% 1.79% 14.29% 100.00% 13.20% 98.91% SUBTOTAL INTERIOR III. PRESSURIZED EPOXY INJECTION FOR CRACKS ON INTERIOR RC WALL, COLUMNS & BEAMS. IV. GRAVITY EPOXY INJECTION (FLOOR SLAB) V. APPLICATION OF FIBRE-REINFORCED NON-SHRINK MORTAR AND STRUCTURAL CARBON FIBER AT COLUMNS, BEAM SOFFIT AND RC WALLS ON SPALLED OF CONCRETE. VI. APPLICATION OF FLEXIBLE HYDRAULIC MORTAR AT 12TH FLOOR SOFFIT FIRE EXIT STAIR (UNDERSLAB OF CONCRETE OVERHEAD TANK AT ROOFDECK) CRACKS AT BASEMENT TO PENTHOUSE 1ST TO 2ND FLOOR BASEMENT TO PENTHOUSE AT PARKING AREA AND STAIRS: 20 COLUMNS FROM GROUND TO 4TH FLOOR UNDER SLAB OF CONCRETE OVERHEAD TANK AT ROOFDECK SUBTOTAL TOTAL NOTE: BALANCE WORK ON INTERIOR: ITEM III.PRESSURIZED EPOXY INJECTION =1.09% AT 1OTH,11TH, AND 12TH FLOORS DUE TO UNAVAILABILITY OF AREAS PREPARED BY: MJRUTMACDER/SDMLAYLO NOTED BY: STL/LLC ACCOMPLISHMEN T BASED ON EXTERIOR AND INTERIOR 100% 92.37% PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED S CURVE BASED ON REVISED OVERALL ACTIVITIES ACCOMPLISHMENT FROM SEPTEMBER 7, 2020 – APRIL 14, 2021 SEPTEMBER 2020 OCTOBER 2020 NOVEMBER 2020 DECEMBER 2020 JANUARY 2021 FEBRUARY 2021 MARCH 2021 APRIL 2021 100% 94.62% 88.40% 90.54% 82.14% WEEK 30: PROJECTED 94.62% ACTUAL 90.54% 77.39% 73.85% 67.85% 62.10% 62.79% 61.38% 59.76% 55.43% 53.14% 57.43% 50.00% 48.07% 45.12% 42.98% 40.38% ACCOMPLISHMENT MONITORING 94.62% - 88.40% 6.22% 29.22% WEEK 30 (APRIL 14) WEEK 29 (APRIL 7) 7 DAYS ACCOMPLISHMENT (APRIL 8-14) 21.50% 14.94% 13.91% 11.43% 8.60% 8.92% 6.80% 0.20% 0.29% 1.16% 1.70% NOTE: THIS REVISED S-CURVE IS PRESENTED DUE TO START DATE DIFFERENCE OF INTERIOR (SEPTEMBER. 7 ,2020) AND EXTERIOR WORKS (NOVEMBER 5, 2020) RESPECTIVELY LINE CHART 4 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED SUMMARY OF WORKS FOR ACITIVITY II WITH ACCOMPLISHMENT UPDATE FROM NOVEMBER 5, 2020 – APRIL 14, 2021 ACTIVITY II: APPLICATION OF P.U. SEALANT WEEK 30 ELEVATION (WALL) ESTIMATED LI NEAR METER OF DISTRIBUTION (L.m.) % ACCOMPLI SHMENT % BALANCE % FRONT 1,100.00 L.m. 50.00% 50.00% 0.00% REAR 1,100.00 L.m. 50.00% 50.00% 0.00% TOTAL 2,200.00 L.m. 100% 100.00% 0.00% TABLE 2.0 5 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY II FRONT SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY II: APPLICATION OF P.U. SEALANT 100.00% WEEK 30 FRONT ELEVATION % LOCATION (REFER TO KEYPLAN) AREA = 1,100 L.m. FRONT ELEV. ITEM ACTUAL OVER TOTAL 1 1. Mob: Hauling of tools, materials and safety orientation. 5% 1.00 5.00% 2. Hauling and installation of jibs,manual gondola/fabricated steel and safety life lines. 10% 1.00 10.00% 3. Lay-out and identification of horizontal and vertical joints (between beams & CHB wall and between column & CHB wall) 15% 1.00 15.00% 4. Cutting and grinding of the identified horizontal & vertical joints at least 10-15mm WIDTH by 30-35mm depth. 20% 1.00 20.00% 5. Removal of dirt, dust and other laitance and installation of backing rod as bond breaker. 15% 1.00 15.00% 4. Straighten the edges of sealant to be applied. 10% 1.00 10.00% 3. Application of Polyurethane P.U. sealant (paintable P.U. sealant) 20% 1.00 20.00% 5. Punch listing, final cleaning, turn-over and pull-out 5% 1.00 5.00% 100% 8.00 100.00% TOTAL DONE ACTIVITY ONGOING ACTIVITY 6 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED SUMMARY OF WORKS FOR ACITIVITY I & IX WITH ACCOMPLISHMENT UPDATE FROM NOVEMBER 5, 2020 – APRIL 14, 2021 ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT WEEK 30 ELEVATI ON (WALL) ESTI M ATED AREA OF DI STRI BU TI ON (Sq.m.) % ACCOM PLI SHM ENT % BALANCE % FRONT 1,002 Sq.m. 14.61% 14.54% 0.07% RI GHT SI DE 2,326.50 Sq.m. 33.92% 33.75% 0.17% LEFT SI DE 2,461.20 Sq.m. 35.89% 35.53% 0.36% REAR 1,068.75 Sq.m. 15.58% 15.58% 0.00% TOTAL 6,858.45 Sq.m. 100% 99.40% 0.60% TABLE 2.0 7 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY I & IX FRONT SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT 99.50% WEEK 30 FRONT ELEVATION % LOCATION (REFER TO KEYPLAN) AREA = 1,002 Sq.m. FRONT ELEV. ITEM ACTUAL OVER TOTAL 1 1. Mob: Hauling of tools, materials and safety orientation. 5% 1.00 5.00% 2. Installation of jibs, motorized/manual gondola/fabricated steel ladder and safety lifelines. 5% 1.00 5.00% 15% 1.00 15.00% 5% 1.00 5.00% 35% 1.00 35.00% 5% 1.00 5.00% 5% 1.00 5.00% 5. Basecoat application of rubberized elastomeric paint with 100% fibermesh reinforcement. 10% 1.00 10.00% 6. Application of rubberized elastomeric paint (2 coats). 10% 1.00 10.00% 5% 0.90 4.50% 100% 9.90 99.50% 3. Surface preperation: 3.1 Grooving and grouting of cracks using fibre-reinforce non-shrink mortar with epoxy bonding. 3.2 Removal of unsound plastering and re-plastering using fiber-reinforced non-shrink mortar with epoxy bonding. 3.3 Grinding of the entire surface to remove the blistering/scalling and delaminated paint and to make an anchor pattern. 3.4 Final removal of dirt and dust. 4. Putty application on depressed areas and sealed horizontal & vertical joints. 7. Dismantling/transfer of motorized or manual gondola/fabricated steel ladder. 8. Punch listing, final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY ONGOING ACTIVITY 8 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY I & IX RIGHT SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT 99.50% WEEK 30 RIGHT SIDE ELEVATION % LOCATION (REFER TO KEYPLAN) AREA = 2, 326.50 Sq.m. ITEM RIGHT SIDE ELEV. ACTUAL OVER TOTAL 1 1. Mob: Hauling of tools, materials and safety orientation. 5% 0.5 1.00 5.00% 2. Installation of jibs, motorized/manual gondola/fabricated steel ladder and safety lifelines. 5% 0.5 1.00 5.00% 15% 0.5 1.00 15.00% 5% 0.5 1.00 5.00% 35% 0.5 1.00 35.00% 5% 0.5 1.00 5.00% 5% 0.5 1.00 5.00% 5. Basecoat application of rubberized elastomeric paint with 100% fibermesh reinforcement. 10% 0.5 1.00 10.00% 6. Application of rubberized elastomeric paint (2 coats). 10% 0.5 1.00 10.00% 5% 0.90 4.50% 100% 9.90 99.50% 3. Surface preperation: 3.1 Grooving and grouting of cracks using fibre-reinforce non-shrink mortar with epoxy bonding. 3.2 Removal of unsound plastering and re-plastering using fiber-reinforced non-shrink mortar with epoxy bonding. 3.3 Grinding of the entire surface to remove the blistering/scalling and delaminated paint and to make an anchor pattern. 3.4 Final removal of dirt and dust. 4. Putty application on depressed areas and sealed horizontal & vertical joints. 7. Dismantling/transfer of motorized or manual gondola/fabricated steel ladder. 8. Punch listing, final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY ONGOING ACTIVITY 9 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY I & IX LEFT SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT 99.00% WEEK 30 LEFT SIDE ELEVATION LOCATION (REFER TO KEYPLAN) AREA = 2,461.20 Sq.m. % ITEM LEFT SIDE ELEV. ACTUAL OVER TOTAL 1 1. Mob: Hauling of tools, materials and safety orientation. 5% 1.00 5.00% 2. Installation of jibs, motorized/manual gondola/fabricated steel ladder and safety lifelines. 5% 1.00 5.00% 3. Surface preperation: 3.1 Grooving and grouting of cracks using fibre-reinforce non-shrink mortar with epoxy bonding. 15% 1.00 15.00% 5% 1.00 5.00% 3.3 Grinding of the entire surface to remove the blistering/scalling and delaminated paint and to make an anchor pattern. 35% 1.00 35.00% 3.4 Final removal of dirt and dust. 5% 1.00 5.00% 4. Putty application on depressed areas and sealed horizontal & vertical joints. 5% 1.00 5.00% 5. Basecoat application of rubberized elastomeric paint with 100% fibermesh reinforcement. 10% 1.00 10.00% 6. Application of rubberized elastomeric paint (2 coats). 10% 0.95 9.50% 5% 0.90 4.50% 100% 9.85 99.00% 3.2 Removal of unsound plastering and re-plastering using fiber-reinforced non-shrink mortar with epoxy bonding. 7. Dismantling/transfer of motorized or manual gondola/fabricated steel ladder. 8. Punch listing, final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY ONGOING ACTIVITY 10 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY I & IX REAR SIDE ELEVATION FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY I & IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT REAR SIDE ELEVATION LOCATION (REFER TO KEYPLAN) AREA = 1,068.75 Sq.m. % ITEM 100.00% REAR ELEV. WEEK 30 ACTUAL OVER TOTAL 1 1. Mob: Hauling of tools, materials and safety orientation. 5% 1.00 5.00% 2. Installation of jibs, motorized/manual gondola/fabricated steel ladder and safety lifelines. 5% 1.00 5.00% 3. Surface preperation: 3.1 Grooving and grouting of cracks using fibre-reinforce non-shrink mortar with epoxy bonding. 15% 1.00 15.00% 5% 1.00 5.00% 3.3 Grinding of the entire surface to remove the blistering/scalling and delaminated paint and to make an anchor pattern. 35% 1.00 35.00% 3.4 Final removal of dirt and dust. 5% 1.00 5.00% 4. Putty application on depressed areas and sealed horizontal & vertical joints. 5% 1.00 5.00% 5. Basecoat application of rubberized elastomeric paint with 100% fibermesh reinforcement. 10% 1.00 10.00% 6. Application of rubberized elastomeric paint (2 coats). 10% 1.00 10.00% 5% 1.00 5.00% 10.00 100.00% 3.2 Removal of unsound plastering and re-plastering using fiber-reinforced non-shrink mortar with epoxy bonding. 7. Dismantling/transfer of motorized or manual gondola/fabricated steel ladder. 8. Punch listing, final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% 0.00 ONGOING ACTIVITY 11 PROJECT : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 SUBJECT PERIOD BATKINS INCORPORATED SUMMARY OF WORKS FOR ACTIVITY VII & VIII WITH ACCOMPLISHMENT UPDATE FROM NOVEMBER 5, 2020 – APRIL 14, 2021 ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) WEEK 30 CONCRETE ESTI MATED AREA OF GUTTER DI STRI BUTI ON (TOTAL (Sq.m.) AREA) FLOOR LEDGES (RI GH & LEFT SI DE) PARAPET WALL (TOTAL AREA) 5th FLOOR 2 0 0 6th FLOOR 2 0 7th FLOOR 2 8th FLOOR % ACCOMPLI SHMENT % BALANCE % 83.16 Sq.m. 8.94% 8.76% 0.18% 0 83.16 Sq.m. 8.94% 8.76% 0.18% 0 0 83.16 Sq.m. 8.94% 8.76% 0.18% 2 0 0 83.16 Sq.m. 8.94% 8.76% 0.18% 9th FLOOR 2 0 0 83.16 Sq.m. 8.94% 8.76% 0.18% 10th FLOOR 2 0 0 83.16 Sq.m. 8.94% 8.76% 0.18% 11th FLOOR 2 0 0 83.16 Sq.m. 8.94% 8.76% 0.18% 12th FLOOR 2 0 0 83.16 Sq.m. 8.94% 8.76% 0.18% ROOF DECK 2 1 1 264.64 Sq.m. 28.46% 27.89% 0.57% 929.92 Sq.m. 100% 98.00% 2.00% TOTAL TABLE 3.0 12 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 5TH FLOOR LEFT & RIGHT LEDGES FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) FIFTH FLOOR RIGHT & LEFT SIDE ELEV. LOCATION (REFER TO KEYPLAN) AREA= 83.16 Sq.m. 98.00% WEEK 30 % ITEM LEDGES ACTUAL OVER TOTAL RIGHT ELEV. LEFT ELEV. 1. Mob: Hauling of tools, materials and safety orientation. 5% 1 1 2 5.00% 2. Provision of barricades and safety precautins. 5% 1 1 2 5.00% 3. Surface preperation: 3.1 Chipping and grouting of perimeter pipe sleeves. 5% 1 1 2 5.00% 3.2 Determination of slope and slope correction by grinding. 20% 1 1 2 20.00% 3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any). 5% 1 1 2 5.00% 3.4 Grinding of the entire surface to make anchor pattern. 35% 1 1 2 35.00% 4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner. 10% 1 1 2 10.00% 5. Application of MS300X Polyurethane waterproofing (2 coats). 10% 1 1 2 10.00% 1.2 3.00% 0 0.00% 0 0.00% 17 98.00% 6. Installation of temporary socallo around the perimeter of pipe sleeve. 7. Flood testing for 24 hours. 5% 8. Final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% ONGOING ACTIVITY 13 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 6TH FLOOR LEFT & RIGHT LEDGES FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: 98.00% WEEK 30 ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) SIXTH FLOOR RIGHT & LEFT SIDE ELEV. LOCATION (REFER TO KEYPLAN) AREA= 83.16 Sq.m. % ITEM LEDGES ACTUAL OVER TOTAL RIGHT ELEV. LEFT ELEV. 1. Mob: Hauling of tools, materials and safety orientation. 5% 1 1 2 5.00% 2. Provision of barricades and safety precautins. 5% 1 1 2 5.00% 3. Surface preperation: 3.1 Chipping and grouting of perimeter pipe sleeves. 5% 1 1 2 5.00% 3.2 Determination of slope and slope correction by grinding. 20% 1 1 2 20.00% 3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any). 5% 1 1 2 5.00% 3.4 Grinding of the entire surface to make anchor pattern. 35% 1 1 2 35.00% 4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner. 10% 1 1 2 10.00% 5. Application of MS300X Polyurethane waterproofing (2 coats). 10% 1 1 2 10.00% 1.2 3.00% 0 0.00% 0 0.00% 17 98.00% 6. Installation of temporary socallo around the perimeter of pipe sleeve. 7. Flood testing for 24 hours. 5% 8. Final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% ONGOING ACTIVITY 14 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 7TH FLOOR LEFT & RIGHT LEDGES FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) SEVENTH FLOOR LOCATION (REFER TO KEYPLAN) AREA= 83.16 Sq.m. 98.00% WEEK 30 RIGHT & LEFT SIDE ELEV. % ITEM LEDGES ACTUAL OVER TOTAL RIGHT ELEV. LEFT ELEV. 1. Mob: Hauling of tools, materials and safety orientation. 5% 1 1 2 5.00% 2. Provision of barricades and safety precautins. 5% 1 1 2 5.00% 3. Surface preperation: 3.1 Chipping and grouting of perimeter pipe sleeves. 5% 1 1 2 5.00% 3.2 Determination of slope and slope correction by grinding. 20% 1 1 2 20.00% 3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any). 5% 1 1 2 5.00% 3.4 Grinding of the entire surface to make anchor pattern. 35% 1 1 2 35.00% 4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner. 10% 1 1 2 10.00% 5. Application of MS300X Polyurethane waterproofing (2 coats). 10% 1 1 2 10.00% 1 3.00% 0 0.00% 0 0.00% 17 98.00% 6. Installation of temporary socallo around the perimeter of pipe sleeve. 7. Flood testing for 24 hours. 5% 8. Final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% ONGOING ACTIVITY 15 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 8TH FLOOR LEFT & RIGHT LEDGES FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: 98.00% WEEK 30 ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) EIGHTH FLOOR RIGHT & LEFT SIDE ELEV. LOCATION (REFER TO KEYPLAN) AREA= 83.16 Sq.m. % ITEM LEDGES ACTUAL OVER TOTAL RIGHT ELEV. LEFT ELEV. 1. Mob: Hauling of tools, materials and safety orientation. 5% 1 1 2 5.00% 2. Provision of barricades and safety precautins. 5% 1 1 2 5.00% 3. Surface preperation: 3.1 Chipping and grouting of perimeter pipe sleeves. 5% 1 1 2 5.00% 3.2 Determination of slope and slope correction by grinding. 20% 1 1 2 20.00% 3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any). 5% 1 1 2 5.00% 3.4 Grinding of the entire surface to make anchor pattern. 35% 1 1 2 35.00% 4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner. 10% 1 1 2 10.00% 5. Application of MS300X Polyurethane waterproofing (2 coats). 10% 1 1 2 10.00% 1 3.00% 0 0.00% 0 0.00% 17 98.00% 6. Installation of temporary socallo around the perimeter of pipe sleeve. 7. Flood testing for 24 hours. 5% 8. Final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% ONGOING ACTIVITY 16 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 9TH FLOOR LEFT & RIGHT LEDGES FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) NINTH FLOOR RIGHT & LEFT SIDE ELEV. LOCATION (REFER TO KEYPLAN) AREA= 83.16 Sq.m. 98.00% WEEK 30 % ITEM LEDGES ACTUAL OVER TOTAL RIGHT ELEV. LEFT ELEV. 1. Mob: Hauling of tools, materials and safety orientation. 5% 1 1 2 5.00% 2. Provision of barricades and safety precautins. 5% 1 1 2 5.00% 3. Surface preperation: 3.1 Chipping and grouting of perimeter pipe sleeves. 5% 1 1 2 5.00% 3.2 Determination of slope and slope correction by grinding. 20% 1 1 2 20.00% 3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any). 5% 1 1 2 5.00% 3.4 Grinding of the entire surface to make anchor pattern. 35% 1 1 2 35.00% 4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner. 10% 1 1 2 10.00% 5. Application of MS300X Polyurethane waterproofing (2 coats). 10% 1 1 2 10.00% 1 3.00% 0 0.00% 0 0.00% 17 98.00% 6. Installation of temporary socallo around the perimeter of pipe sleeve. 7. Flood testing for 24 hours. 5% 8. Final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% ONGOING ACTIVITY 17 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 10TH FLOOR LEFT & RIGHT LEDGES FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: 98.00% WEEK 30 ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) TENTH FLOOR RIGHT & LEFT SIDE ELEV. LOCATION (REFER TO KEYPLAN) AREA= 83.16 Sq.m. % ITEM LEDGES ACTUAL OVER TOTAL RIGHT ELEV. LEFT ELEV. 1. Mob: Hauling of tools, materials and safety orientation. 5% 1 1 2 5.00% 2. Provision of barricades and safety precautins. 5% 1 1 2 5.00% 3. Surface preperation: 3.1 Chipping and grouting of perimeter pipe sleeves. 5% 1 1 2 5.00% 3.2 Determination of slope and slope correction by grinding. 20% 1 1 2 20.00% 3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any). 5% 1 1 2 5.00% 3.4 Grinding of the entire surface to make anchor pattern. 35% 1 1 2 35.00% 4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner. 10% 1 1 2 10.00% 5. Application of MS300X Polyurethane waterproofing (2 coats). 10% 1 1 2 10.00% 1.2 3.00% 0 0.00% 0 0.00% 17 98.00% 6. Installation of temporary socallo around the perimeter of pipe sleeve. 7. Flood testing for 24 hours. 5% 8. Final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% ONGOING ACTIVITY 18 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 11TH FLOOR LEFT & RIGHT LEDGES FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) ELEVENTH FLOOR RIGHT & LEFT SIDE ELEV. LOCATION (REFER TO KEYPLAN) AREA= 83.16 Sq.m. 98.00% WEEK 30 % ITEM LEDGES ACTUAL OVER TOTAL RIGHT ELEV. LEFT ELEV. 1. Mob: Hauling of tools, materials and safety orientation. 5% 1 1 2 5.00% 2. Provision of barricades and safety precautins. 5% 1 1 2 5.00% 3. Surface preperation: 3.1 Chipping and grouting of perimeter pipe sleeves. 5% 1 1 2 5.00% 3.2 Determination of slope and slope correction by grinding. 20% 1 1 2 20.00% 3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any). 5% 1 1 2 5.00% 3.4 Grinding of the entire surface to make anchor pattern. 35% 1 1 2 35.00% 4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner. 10% 1 1 2 10.00% 5. Application of MS300X Polyurethane waterproofing (2 coats). 10% 1 1 2 10.00% 1.2 3.00% 0 0.00% 0 0.00% 17 98.00% 6. Installation of temporary socallo around the perimeter of pipe sleeve. 7. Flood testing for 24 hours. 5% 8. Final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% ONGOING ACTIVITY 19 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII 12TH FLOOR LEFT & RIGHT LEDGES FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) TWELFTTH FLOOR RIGHT & LEFT SIDE ELEV. LOCATION (REFER TO KEYPLAN) AREA= 83.16 Sq.m. 98.00% WEEK 30 % ITEM LEDGES ACTUAL OVER TOTAL RIGHT ELEV. LEFT ELEV. 1. Mob: Hauling of tools, materials and safety orientation. 5% 1 1 2 5.00% 2. Provision of barricades and safety precautins. 5% 1 1 2 5.00% 3. Surface preperation: 3.1 Chipping and grouting of perimeter pipe sleeves. 5% 1 1 2 5.00% 3.2 Determination of slope and slope correction by grinding. 20% 1 1 2 20.00% 3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any). 5% 1 1 2 5.00% 3.4 Grinding of the entire surface to make anchor pattern. 35% 1 1 2 35.00% 4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner. 10% 1 1 2 10.00% 5. Application of MS300X Polyurethane waterproofing (2 coats). 10% 1 1 2 10.00% 1 3.00% 0 0.00% 0 0.00% 17 98.00% 6. Installation of temporary socallo around the perimeter of pipe sleeve. 7. Flood testing for 24 hours. 5% 8. Final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% ONGOING ACTIVITY 20 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED BAR CHART BASED ON ACCOMPLISHMENT OF ACTIVITY VII & VIII PENTHOUSE LEFT & RIGHT LEDGES FROM NOVEMBER 5, 2020 – APRIL 14, 2021 THIS WEEK: ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 Sq.m.) & MS300X-PLUS (650 Sq.m.) 98.00% WEEK 30 ROOF DECK ROOF DECK % LOCATION (REFER TO KEYPLAN) AREA = 181.48 Sq.m. CONCRETE GUTTER, AREA = 83.16 Sq.m. LEDGES RIGHT & LEFT SIDE ELEV. ITEM ACTUAL OVER TOTAL PARAPET WALL CONCRETE GUTTER 1 2 RIGHT ELEV. LEFT ELEV. LEDGES 1. Mob: Hauling of tools, materials and safety orientation. 5% 1 1 1 1 4 5.00% 2. Provision of barricades and safety precautins. 5% 1 1 1 1 4 5.00% 3. Surface preperation: 3.1 Chipping and grouting of perimeter pipe sleeves. 5% 1 1 1 1 4 5.00% 3.2 Determination of slope and slope correction by grinding. 20% 1 1 1 1 4 20.00% 3.3 Cutting/grooving of cracks and epoxy injection by gravity method (if any). 5% 1 1 1 1 4 5.00% 3.4 Grinding of the entire surface to make anchor pattern. 35% 1 1 1 1 4 35.00% 4. Primer application using LS P.U. Primer with fibermesh reinforcement along the perimeter corner. 10% 1 1 1 1 4 10.00% 5. Application of MS300X Polyurethane waterproofing (2 coats). 10% 1 1 4 10.00% 0.6 0.6 2.4 3.00% 0 0.00% 0 0.00% 34 98.00% 6. Installation of temporary socallo around the perimeter of pipe sleeve. 7. Flood testing for 24 hours. 1 0.6 1 0.6 5% 8. Final cleaning, turn-over and pull-out. TOTAL DONE ACTIVITY 100% 9% 9% 9% ONGOING ACTIVITY 21 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED FRONT ELEVATION 22 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 FRONT SIDE EXTERIOR WALL DURING PUTTY APPLICATION AND 1ST COAT TO TOP COAT APPLICATION OF ELASTOMERIC PAINT. BATKINS INCORPORATED FRONT SIDE EXTERIOR WALL AFTER PUTTY APPLICATION AND 1ST COAT TO TOP COAT APPLICATION OF ELASTOMERIC PAINT. FRONT EXTERIOR WALL ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT -DONE FOR PUTTY AND 1ST TO TOP COAT APPLICATION OF ELASTOMERIC PAINT. 23 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED FRONT SIDE EXTERIOR WALL (FRONT CANOPY) AFTER 1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH. FRONT EXTERIOR WALL ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT -DONE FOR PUTTY AND 1ST TO TOP COAT APPLICATION OF ELASTOMERIC PAINT. 24 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED LEGEND: 100% DONE FOR SURFACE PREP. 100% DONE PUTTY APPLICATION 100% DONE 1ST & TOP COAT APPLICATION FRONT ELEVATION (EXTERIOR WALL) ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT -DONE FOR PUTTY AND 1ST TO TOP COAT APPLICATION OF ELASTOMERIC PAINT. 25 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED LEGEND: 0% BALANCE. 100% DONE FOR SEALANT APPLICATION. FRONT ELEVATION (EXTERIOR WALL) ACTIVITY II. APPLICATION OF P.U. SEALANT AT CHB WALL (EXTERIOR) -DONE FOR P.U. SEALANT APPLICATION 26 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED RIGHT SIDE ELEVATION 27 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED LEGEND: 100% DONE FOR SURFACE PREP. 100% DONE PUTTY APPLICATION 100% DONE 1ST & TOP COAT APPLICATION RIGHT SIDE ELEVATION (EXTERIOR WALL) ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT 28 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED LEFT SIDE ELEVATION 29 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 LEFT SIDE (NEAR FRONT) EXTERIOR WALL DURING GRINDING WORKS AND PUTTY APPLICATION. BATKINS INCORPORATED LEFT SIDE (NEAR FRONT) EXTERIOR WALL AFTER PUTTY AND 1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH. LEFT SIDE EXTERIOR WALL ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT -ON-GOING PUTTY AND 1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH. 30 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 LEFT SIDE (NEAR FRONT) EXTERIOR WALL DURING GRINDING WORKS AND PUTTY APPLICATION. BATKINS INCORPORATED LEFT SIDE (NEAR FRONT) EXTERIOR WALL AFTER PUTTY AND 1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH. LEFT SIDE EXTERIOR WALL ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT -ON-GOING PUTTY AND 1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH. 31 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 LEFT SIDE (GROUND FLOOR) PARKING RAMP AFTER 1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH. BATKINS INCORPORATED LEFT SIDE (3RD FLOOR) PARKING RAMP AFTER 1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH. LEFT SIDE EXTERIOR WALL ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT -ON-GOING PUTTY AND 1ST COAT APPLICATION OF ELASTOMERIC PAINT WITH FIBERMESH. 32 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED LEGEND: 100% DONE FOR SURFACE PREP. 100% DONE PUTTY APPLICATION 95% DONE 1ST COAT APPLICATION WITH FIBERMESH 92% DONE TOP COAT APPLICATION ` LEFT SIDE ELEVATION (EXTERIOR WALL) ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT -ON-GOING 1ST COAT TO TOP COAT APPLICATION OF ELASTOMERIC PAINT. 33 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 LEFT SIDE PENTHOUSE AFTER TOP COAT APPLICATION OF MS300X PLUS. BATKINS INCORPORATED LEFT SIDE 12TH FLOOR AFTER TOP COAT APPLICATION OF MS300X PLUS. LEFT SIDE 7TH FLOOR AFTER TOP COAT APPLICATION OF MS300X PLUS. LEFT SIDE LEDGES ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.) -DONE FOR APPLICATION OF MS300X PLUS. 34 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 LEFT SIDE 6TH FLOOR AFTER TOP COAT APPLICATION OF MS300X PLUS. BATKINS INCORPORATED LEFT SIDE 5TH FLOOR AFTER TOP COAT APPLICATION OF MS300X PLUS. LEFT SIDE LEDGES ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.) -DONE FOR APPLICATION OF MS300X PLUS. 35 PROJECT SUBJECT PERIOD LEGEND: 100% 60% 60% : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED DONE FOR PRIMER APPLICATION. DONE FOR 1ST COAT MS300X APPLICATION DONE FOR TOP COAT MS300X APPLICATION PH 12TH 11TH 10TH 9TH 8TH 7TH 6TH 5TH LEFT SIDE ELEVATION (LEDGES) ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.) -DONE FOR BASE COAT APPLICATION. -ON GOING TOP COAT APPLICATION 36 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED REAR ELEVATION 37 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED I & IX. 100% DONE FOR SURFACE PREP. 100% DONE PUTTY APPLICATION 100% DONE TOP COAT APPLICATION REAR ELEVATION ACTIVITY I&IX: GEN. REQ. & APPPLICATION OF RUBBERIZED ELASTOMERIC PAINT WITH 100% FIBERMESH REINFORCEMENT 38 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED ROOF DECK 39 PROJECT SUBJECT PERIOD : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 BATKINS INCORPORATED ROOF DECK (ELEVATOR DECK) AFTER TOP COAT APPLICATION OF MS300X PLUS. ROOF DECK (ELEVATOR DECK) ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.) -DONE FOR TOP COAT APPLICATION OF MS300X PLUS. 40 PROJECT SUBJECT PERIOD LEGEND: : ST. LUKES MEDICAL CENTER – COLLEGE OF MEDICINE NTP DATED JUNE 26, 2020 : WORK IN PROGRESS (WEEK 30) : APRIL 8 - 14, 2021 100% 100% 100% BATKINS INCORPORATED DONE FOR PRIMER APPLICATION. DONE FOR 1ST COAT MS300X APPLICATION DONE FOR TOP COAT MS300X APPLICATION ROOF DECK (CONCRETE GUTTER, ELEVATOR AND STAIR DECK ) ACTIVITY VII & VIII: APPLICATION OF REPAIR NON-SHRINK MORTAR (341.38 SQ.M.) & MS300X-PLUS (650 SQ.M.) -DONE FOR MS300X P.U. APPLICATION 41 BATKINS INCORPORATED END OF PRESENTATION THANK YOU!!!