Critical Analysis of IS 1255-1983, reaffirmed 1996 for “Code of Practice for Installation and Maintenance of Power Cables up to and including 33 kV rating” “Stop hurting your extruded power cables! Do not perform DC high-potential test” Ravi Kumar Premjeet Nair Senior Application Engineer- Cable Infrastructure Megger India Pvt Ltd Kolkata, India Ravi.kumar@megger.com Product Manager- Cable Infrastructure Megger India Pvt Ltd Kochi, India Premjeet.nair@megger.com Abstract— Traditionally power cables, during installation or maintenance, are tested with a DC high voltage for its electrical strength as prescribed in IS 1255-1983, reaffirmed 1996. Modern extruded dielectric power cables such as XLPE have inherent space charge accumulation tendencies when subjected to a high voltage DC. The accumulated space charge leads to overstressing of insulation resulting in cable breakdown with high downtime and repair costs. As IS 1255-1983 is silent on the harmful effect of DC on XLPE cables, power companies in India are facing revenue losses as well as the quality of service to the consumer is affected. This paper analyses the demerits of IS 1255 and compares it with the other available test methods such as Very low frequency and Damped Alternating Current test, as well as condition assessment methods, such as Dissipation factor and Partial Discharge. A case study highlighting the advantages of newer test methods has been presented and a cost to benefit analysis is undertaken. Keywords—Power cables, XLPE, DC test, VLF test, DAC test, Partial Discharge test, Dissipation factor test, condition monitoring I. INTRODUCTION Power cables are arteries and veins of a power distribution network, it transports power from a transmission or distribution substation to another distribution substation or to a residential distribution transformer at a consumer premises. In a highly populated areas, underground power distribution network is the only option to provide electricity, it is also costlier than the overhead power distribution network. Underground cables constitute a major investment in electric power network. These cable networks are required to have a good life expectancy and high reliability. This article investigates into techniques for commissioning (or installation/acceptance) and maintenance tests on up to 33 kV rated power cables as described in IS 1255-1983 and, various other international practices based on IEEE field guides and IEC standard documents. II. HISTORY & EVOLUTION OF EXTRUDED POWER CABLES. First power cables were laid more than 90 years ago, since then the dielectric material used in the power cables to provide the desired voltage insulation has changed considerably. Cables of the older days were mainly oil filled laminated dielectrics, like Paper Insulated Lead Covered (PILC). Though, these cables were robust and immune to minor defects with high tolerance to partial discharge (PD), their performance was affected by defects such as leakage of fluid at gaskets or due to hole in outer sheath, ingress of moisture, waxing of fluid, dry or brittle paper, etc. One or more of these factors led to frequent breakdown of PILC cables requiring more maintenance and higher losses. In order to overcome the limitations of laminated cables, extruded polymeric dielectric cables such as Cross Linked Poly Ethelene(XLPE) were introduced in 1980s. Initial XLPE cables did overcame majority of the issues present in PILC cable, however it was found that XLPE cables had more susceptibility towards moisture ingress resulting into water trees, hence degradation of cable insulation was faster and service life expectancy was low. Modern XLPE cable are Tree retardant or TR-XLPE which have significantly improved the problem of water trees in it. Majority of the power cables used in India are of low and medium voltage category networks i.e. rated up to 33 kV. Recently, few power cables for transmission network up to 400kV are also being installed. India has a significant size of PILC cable installation majorly in metro cities, some of which are more than 40 years old, but majority of the cable installations are XLPE, as the number of XLPE installation in last twenty years has increased considerably. III. WHAT IS A HIGH VOLTAGE WITHSTAND TEST/ DIAGNOSTIC TEST? In a high voltage withstand test, a cable is subjected to a pre-determined voltage, for a pre-determined time. If cable survives the test voltage and duration it is taken into service, if it fails, it is then repaired and retested. A diagnostic test such as partial discharge or dissipation factor (Tan Delta), carried along with voltage with stand test or separately, provides additional useful information about the condition of insulation of cable. A partial discharge test would reveal the localised defects on the cable and its accessories such as joints and termination, so that corrective action can be taken. A Tan Delta test (on a service aged cable) would provide overall insulation quality so that cable or cable section replacement decision can be planned. IV. WHY TO PERFORM A HIGH VOLTAGE WITHSTAND/DIAGNOSTICS TEST? A. Manufacturing defects The newly manufactured cable may have certain defects like micro voids, protrusion, impurities or moisture in the insulation. Thus, it is important to carry out a high voltage withstand test of cable at site to verify the integrity of the cable insulation. B. Installation defects Improper handling of cable during installation will weaken the insulation and may create additional defects. Power cables comes in a standard length of 250m or 500m drum, so two or more power cables are joined to make a longer network. In order to connect the power cable within power network, terminations are installed at both end of the network. Creating joints and terminations is a manual process, subjected to human error during installation (Fig. 1 & 2). So, the quality of insulation of joint and termination need to be verified. Thus, before energising the power cable into service, it is very important to perform a high voltage withstand test. defects in the cable, rendering it to be unreliable. Thus, a periodic predictive maintenance test is also required to be carried out on power cables to assess the condition of insulation for carrying out corrective actions. D. Breakdown Lastly, if a cable insulation breakdown failure occurs in service, it is required to perform a voltage withstand test on the cable after repair work is done and before it is taken back into service again. In addition to the high voltage withstand test, if a diagnostics tests such as partial discharge measurement or Tan Delta measurement (on aged cables) is performed, it would reveal more valuable insights into quality of insulation of cable and its accessories (joints and terminations). V. HIGH VOLTAGE WITHSTAND TEST AS PER IS 1255: 1983 “IS 1255 recommends DC test on power cables after jointing and terminations are completed. The recommended values of test voltages are closer to 3 UO i.e. three times rated phase to earth voltage. It specifies a test duration of 5 minutes. DC test voltage for service aged cable is 1·5 times rated voltage or less depending on the age of cable, repair work or nature of jointing work carried out, etc.” [2]. VI. WHY DC IS DANGEROUS ON XLPE CABLE. In an extruded polymeric insulation, electrical charges such as electrons, holes or ions have a tendency to get electrostatically attracted to specific location within the insulation to form chemical bonds. These are known as space charges. It accumulates due to difference in the rate at which charge enters and leaves a region [3]. Applying a high DC voltage to a polymeric dielectric insulation for a longer duration, for e.g. 3 UO or 1.5 times rated voltage, for a duration of 5 minutes during a commissioning or maintenance test will create space charges. A cable may fail during reenergization if it is not completely discharged after a DC high voltage test, due to presence of trapped space charges, which have a longer discharge time constant [4]. It has been observed that after the DC test is conducted, these trapped space charge do not discharge even after 24 hours. IEC 60502-2: 2014 categorically warns that “a DC test may endanger the insulation system under test and recommends that where ever possible an AC test should be used” While IEEE 400.2: 2013 state that if an aged cross-linked polyethylene (XLPE) cable is exposed to high-voltage DC tests, then there are major negative issues affecting its integrity, after it is taken back into service. C. Service ageing Cable manufacturers as well as the field experiences suggests normal life expectancy of a cable to be around 40 to 50 years [1]. But, power cables in service withstands many stresses during its operation such as thermal stress, electrical over voltage and over current, moisture, etc. Combination of these factors reduces the insulation quality and creates many It is further observed that IEEE 1234-2019 unequivocally cautions that “some utility or industrial standards do not yet consider the potentially damaging effects of DC testing. It is not recommended to DC test on an extruded cable” In addition to space charge phenomena, it is also known that on extruded cables used in ac systems, DC test is not effective in detecting many forms of gross defects, e.g. voids, sharp cuts etc that may be present in a cable system that will otherwise be detected by other test voltage such as very low frequency (VLF) or at operating frequency [5] Acknowledging the above, it is worldwide well established that high voltage DC test is harmful as well as ineffective in some cases for extruded dielectric cables such as XLPE and it should not be carried out. VII. INTERNATIONAL STANDARD FOR HIGH VOLTAGE TEST ON EXTRUDED CABLES. Ideally, power cables should be tested with same power frequency ac at higher voltages as used in service for e.g. 50Hz ac. However, the charging current required for such test because of the inherent capacitance of longer length of concentric shielded cable, is very high and it requires a very large and bulky system to generate required charging current and power. So, the field testing is extremely challenging, inconvenient or not possible with 50Hz ac. Another option is to use AC resonant test systems which operates in frequency range from 20Hz to 300Hz but they are also extremely bulky and costly, so transportation is a challenge and it also requires a larger space and setup time at test site which is not feasible or desirable for a medium voltage cable. during commissioning test. It also recommends around 1.7 UO rms voltage for a duration of 30 minutes on a service aged cable. IEC differs in its recommendation as it suggest a 0.1Hz VLF test voltage of around 3 UO rms for a duration of 15 minutes. It also says that a lower voltage and/or shorter duration should be applied on a service aged cable depending on its age, history of breakdown and purpose of test. 0.1 Hz VLF test is the most popular choice with utilities across the worldwide. It must be noted that IEC 60502-2 recommends test frequency of 0.1Hz only. IEEE 400.2 also recommends test frequency 0.1 Hz but it also mentions that for longer circuits if the test kit doesn’t meet the required capacity then frequency may be reduced till 0.01Hz and test time need to increase suitably. However, it doesn’t suggest how much time to increase. Experience reveals that when a test is performed at a 0.01Hz frequency, the stress on cable is much lower than 0.1Hz test and it is not very effective, as it can miss out many significant defects present in the cable. 0.1 Hz VLF CR power sources due to their design has higher limit test capacitances than that of 0.1Hz VLF sine power sources. Hence it is possible to test considerably longer cable networks as compared to 0.1 Hz VLF sinusoidal without the need of reducing frequency. If no other test is possible then standard also mentions about possibility of testing with power frequency 50 Hz at nominal voltage UO for 24 hours. This is known as soak testing where a cable is charged under no load condition at rated nominal voltage for 24 hours, if cable survives then it is taken into service. However, this test method doesn’t take into account of the overvoltage stresses that a cable may encounter while in service. So cable behavior above rated operating voltage is unknown. Very Low Frequency (VLF) 0.1Hz ac voltage testing is an alternative method of test on a power cable. Moreover, it is also a portable and economical solution and onsite testing is possible with convenience. Unlike DC voltage, VLF test voltage continuously changes its polarity so it does not produce harmful space charges [6]. Also, at 0.1 Hz, the charging current required is only 1/500 of that at 50 Hz so it allows significantly smaller and more portable VLF power sources to test even longer lengths cable network. Two kind of VLF waveforms are described in both IEEE 400.2 as well as in IEC 60552 namely VLF cosine-rectangular waveform (VLF CR) and VLF sinusoidal waveform (VLF sine). In cosine rectangular electrical stress distribution is closer to the power frequency as the polarity reversal takes place around 8 msec (Fig 3.). While sinusoidal may have a very different stress distribution than that of power frequency. IEEE 400.2 recommends a 0.1Hz VLF test voltage of around 2 UO rms for minimum of 1 hour to be applied on a new cable VIII. DAMPED ALTERNATING CURRENT (DAC) TEST- A NONDESTRUCTIVE METHOD FOR CABLE TESTING AND DIAGNOSTICS. DAC voltage testing is one of the popular alternative methods of ac voltage testing and is applicable for a broad range of medium-voltage (MV), high-voltage (HV), and extra-highvoltage (EHV) cable types [7]. It is also a very convenient, portable and economical onsite test method. DAC voltages are generated by charging the cable to a predetermined voltage level and then discharging the capacitance of cable through a suitable inductance which in turns causes the damping of applied voltage. The frequency of DAC oscillation depends upon the value of HV inductor in the test equipment and the capacitance of the cable. Normally the frequency of a DAC test lies in between 20Hz to 500Hz [7]. Newly installed cable systems can be tested with 50 DAC excitations in monitored and/or non-monitored ways. Acceptable voltage level for a commissioning test is 2 UO. Cable systems in service or after repair or refurbishment, can be tested with 50 DAC excitations in a monitored and/or nonmonitored way but at a reduced voltage level, typically 1.7 UO [7]. rectangular voltage and, Dissipation Factor with the help of VLF sinusoidal waveforms. The protocol followed by company to carry out the test is described in Table 1. Table 1. Test protocol Since the frequency of a DAC high voltage test lies in between 20Hz to 500Hz, the test result is closer to that of a power frequency (50/60Hz) test, DAC test results are also relatable to that of a power frequency test (Fig.4) Cable Type New Old Tests performed Voltage withstand and Partial Discharge Voltage withstand, Partial Discharge and Tan Delta Voltage withstand test parameters Up to 2 UO rms voltage for 60 minutes Partial Discharge test parameters. From 0.5 UO to 2 UO in step of 0.2Uo Tan Delta test parameters Optional (At 0.5 UO UO, and 1.5 UO) Up to 1.6 Uo rms voltage for 30 minutes From 0.5 UO to 1.6 UO in step of 0.2 UO At 0.5 UO UO, and 1.5 UO Decision on the test results is taken as per guidelines described in Table 2. Table 2. Test result analysis guideline IX. WHY A DIAGNOSTIC TEST IS VERY IMPORTANT? A high voltage withstand test is a Go No-go test in which if the cable survives the duration of the test then it is taken into service, should the cable fail it is repaired and retested. In order to determine more information on condition of cable, diagnostic tests such as Dissipation Factor (Tan Delta) and partial discharge is performed which provide more insights into the nature of defects in cable, if any. Both IEEE and IEC standards suggests partial discharge and Tan Delta test to be carried out on a cable, during a high voltage withstand test or separately, at the time of commissioning, or during periodic/breakdown maintenance. While IS 1255 is silent about any field diagnostic test. Tan Delta is mostly carried out on a service aged cable, it provides insights into overall insulation condition of cable and can reveal information such as moisture, water trees or presence of wet joints so that cable or section replacement may be planned, while partial discharge is frequently carried out during commissioning test as well as maintenance test as it provides localised information about weak points such as voids, contamination or bad joints/ terminations etc so that corrective action can be taken. X. CASE STUDY A major petrochemical company in India has hundreds of power cable installed within its premises, majority of which are below 33kV. Most of the cables were installed in 1998 and are in their mid-service life. During installation the company had followed IS 1255 and only DC tests were conducted. As the cable started ageing, they felt the need of test and diagnostics methods as per international practices, in order to reduce their cable failure and to increase remaining life. Few years back they adopted testing methodology according to IEEE 400 series under which they now carry out VLF withstand test as well as partial discharge with cosine Test Result Cable occur insulation breakdown Cable survives test voltage and duration as well as partial discharge activities within limit Cable survives test voltage and duration but high partial discharge activities. Cable survives test voltage and duration with acceptable PD level but high Tan Delta values Action Cable is repaired and retested. Cable taken into service Partial Discharge spots are repaired, and PD test is reconducted. If possible, Tan Delta is performed on cable sections and cable replacement decision is taken accordingly. A 2.4 km, 33 kV rated XLPE cable (Fig. 5) feeding to a critical unit tripped, subsequently a joint failure was located at 240m in phase L3 while other two phases were healthy. The joint was repaired, and cable was tested with DAC voltage up to 1.6 UO rms (Phase to earth) for 30 minutes (Fig. 6). Cable successfully passed the withstand test but high-level of partial discharge was observed at the same joint of 240m. Tan Delta was also performed on the cable and the result were found to be within acceptable limit as per IEEE 400.2, indicating no presence of moisture in the cable. Results are summarized in table 3. Table 3. Tan Delta test result. Tan δ Values x 10-3 Phase 0.5 UO Stability UO L1 L2 L3 1.0 1.0 1.0 0 0 0 1.0 1.0 1.0 Stability 1.5 UO Stability 0 0 0 2.3 2.3 2.9 0 0 0 ∆ Tan δ 1.3 1.3 1.9 From the PD test result in Fig. 7. It was evident that the jointing work at L3 was not properly conducted, so decision was taken to open and rework on the joint with more supervision. Hence a possible in-service failure was averted with the help of a PD test. partial discharge or Dissipation factor diagnostics are added into VLF test sets, the costs will increase by another 50% [8]. Though, VLF & DAC test sets are relatively costlier than DC test sets but increase in reliability and life expectancy of cables, by use of proven VLF & DAC methods results into much larger savings in breakdown maintenance and replacement costs as well as downtime revenue losses. XII. CONCLUSION Recommendations of IS 1255 were valid and applicable on older PILC cable where DC test was acceptable. Technology progress has led to change in insulation materials of power cables, modern power cables are mostly XLPE upon which DC test is proven to be dangerous as well as ineffective and it is not recommended by international standards such as IEC & IEEE. Very Low Frequency (VLF) test and Damped Alternating Current (DAC) tests are two well proven, convenient and recommended technologies for high voltage test on XLPE power cables. It is high time Indian utilities migrates from DC test to VLF/DAC test as well as adopt diagnostic techniques such as partial discharge and Tan Delta measurements, which will reduce the failure of their vital cable assets as well as would enhance the quality of power supply to consumers. REFERENCES [1] [2] [3] XI. COST ANALYSIS DC test sets up to 60 kV which is required for a test on a 33kV power cable as per IS 1255 are a combination of a transformer and a rectifier, so they are very cheaply available. A sinusoidal VLF test set with 60 kV peak output would be in general two to three times costlier than a DC test set. A cosine rectangular VLF test set and Damped AC test sets with similar output would be 25% higher than a sinusoidal VLF test set. If [4] [5] [6] [7] [8] Central Electricity Authority of India (CEA): “Guidelines for use of Under Ground Cable System and overhead conductor system- 2018” IS 1255: 1983 reaffirmed 1996 “Code of Practice for Installation and Maintenance of Power Cables up to and including 33 kV rating” John C Fothergill “The Coming of Age of HVDC Extruded Power Cables” IEC 60502-2: 2014 “Standard for Power Cables with Extruded Insulation and their accessories.” IEEE 400.2- 2013: “Guide for Field Testing of Shielded Power Cable Systems using Very Low Frequency (VLF)” IEEE 400.3- 2006: “Guide for Partial Discharge Testing of Shielded Power Cable Systems in a Field Environment” IEEE 400.4- 2015 “Guide for Field Testing of Shielded Power Cable Systems rated 5kV and Above with Damped Alternating Current (DAC) Voltage” Megger.com