Manager, Control Division – West . To: It is notified that we have completed the survey of the below titled project for status of its conformance to NG Mandatory Requirements of Energization and intimate that in accordance with inputs received from all concerned Transmission Divisions, the mentioned Facility/Equipment are Technically Acceptable from transmission side and may be energized as and when required in accordance with the Control Center Procedures and Regulations. For questions, if any, please contact Ahmad Saleh Al Zahrani at Phone 02-37642 or at e-mail ASMZahrani@se.com.sa Project Information Contract No. Project Title Installation of 110 KV UG cable for 110/13.8 KV UM Al Salam SS – construction of Um Al Salam SS S/S Name 4400005302 4400003333 WOA Jeddah Area Region Um Al Salam-2 SS - Al Adel BSP Equipment Name(s) / Number(s) As per SLD ☐ Equipment GIS Power Transformer Switch Gear Capacitor Bank AUX. Transformer Reactor Others ☒ Feeders ☐ ☐ ☐ ☐ ☐ ☐ Volt. Level KV Capacity Quantity Name Circuit Breaker - - - - - - - - - - - - - - - - - - - - - - - - - - - - - --- New/Existing Volt. Level KV OHL/UG From C.B # To C.B # Circuit- B New 110 KV UG Um Al Salam-2 SS E04 Al Adel BSP AD10 - - - - - - - - Need Operator 24 hours Project Take Over Division Yes ☐ Length KM TYPE OHL UG OHL UG NEW EXIS. - - 8.720 - No ☒ Project Take Over Division Manager Name Emad A. Bawajih Signature Permit Date Permit No. 13/03/2019 066 Note This Energization Permit shall stand null and void if said facility/equipment is not energized within 10 working days or any technical problem / safety hazard arises during energization of the said facility/equipment. All remaining PETS comments shall be cleared by Projects Division within scheduled time with intimation to PTD & concerned divisions. Control Division shall inform PTD after energization of equipment/facility. You can see the status of this project at the link http://rdd.web.com/pto/Project D S - N G - 6 2 7 0 - 001-12