I.D. Task Name 1. prepare drawings 2. identify tenants 3. develop prospectus 4. select G.C. 5. prepare permits 6. obtain permits 7. build mall 8. finalize contracts 9. tenants move in Duration 5w 6w 4w 3w 1w 4w 14w 12w 2w TASK Predecessor 1 1 1 5 4,6 2,3 7,8 Activities ID Pred. a Grow donor plants b a Cross & harvest F1 seeds c b Rear F1 plants d Procure chemicals, etc. e d, c Determine polar stage; plant F1 anthers for induction f Prepare aseptic growth room g e, f Plant calli; regenerate plants; screen for salt tolerance h g Screen plantlets in culture solution for salt tolerance i h Identify haploids; create diploids i Transfer plantlets to field for screening and seed production j k j Screen material at Network sites I k Select homozygous lines for agro-edaphic environments m I Test material in on-station trials n m Data analysis o n Nominate entries for National Screening Nursery p o Promote entries to National Trials q p Evaluate on-farm in farmers' fields r p Farmers' Field Days s q Release of cultivar by Variety Release Committees t s Overall analysis and report writing d1 p Dummy Estimates tm 20 5 12 20 10 12 8 5 5 12 20 20 20 8 20 40 . 20 4 8 12 Table 21.1 A List of the Activities Associated with an Inventory System Description Order hardware and software Shipment time Clarify manual procedures Design files Prepare site and install Design record shipment program Initialize vendor file Initialize customer file Initialize inventory file Write record shipment program Customize reports System test Train inventory manager Train sales clerks Train clerical personnel Train store manager 2 A Sample Problem for Finding Duration 2 5 1 4 1 1 1 1 1 1 1 1 1 2 0.5 1 Activity 1-2 2-5 3-12 4-7 5-7 6-10 7-8 8-9 9-10 10-11 11-12 12-13 13-14 13-16 14-16 15-16 the Critical Path and Critical Time Activity Predecessor Duration a — 5 days b — 4 c a 3 d a 4 e a 6 f b, c 4 g d 5 h d, e 6 i f 6 j g, h 4 Activity Description Optimistic Predecessors A Survey Site 4 B Excavation 15 A C Prepare Drawings 18 None D Soil Study 1 B E Prelim. Report 3 C, D F Approve Plans 1 E G Concrete Forms 9 F H Procure Steel 10 F I Order Cement 1 F J Deliver Gravel 5 G K Pour Concrete 14 H, I, J L Cure Concrete 2 K M Strength Test 2 L Find CPM A B C D E F G H I 10 5 8 12 15 3 10 4 2 A B B B,D C G,F H,E None