Schedule for WiFi system and cabling system renovation for The Landmark
ID
Task name
Assignee
Dur.
Description
W 1 W 2 W 3 W 4 W 5 W 6 W 7 W 8 W 9 W 10 W 11W 12
MT WT F MT WT F MT WT F MT WT F MT WT F MT WT F MT WT F MT WT F MT WT F MT WT F MT WT F MT WT F
1
2
3
3
3.1
3.2
3.2
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
5
7
8
9
9.1
9.2
9.3
9.4
9.5
9.6
10
11
12
Hardware Order
Materials Order
Materials Delivery
Cabling Fiber Optic
SR to F.10
F.11 & F.12
F.13 & F.14
Cabling Data Cable
SR to G's AP Location
F.10
F.11
F.12
F.13
F.14
G, RT, & Gym
AP, Sw, & Ctr Config
Staging Deployment
Hardware Delivery
AP Installation
F.10
F.11
F.12
F.13
F.14
G, RT, & Gym
Labeling
Handover & Training
UAT Signing
Admin: 1 per
Admin: 1 per
Infra: 2 pers
Infra
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Wansi: 3 pers
Wansi: 1 per
Wansi: 2 pers
Infra
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
Infra: 5 pers
PM
PM
40 days Ordering hardware from Aruba Vietnam.
8 days Ordering cable and materials for cabling.
1 day Deliver cable and materials to The Landmark.
1 day
1 day
1 day
Cabling fiber optic cable from SR to F.10
Cabling fiber optic cable from F.10 to F.11&F.12
Cabling fiber optic cable from F.10 to F.13&F.14
1 day
5 days
5 days
5 days
5 days
5 days
3 days
1 day
2 day
1 day
Cabling data cable from SR to G's Aps
Cabling data cable from F.10's Sw to Aps
Cabling data cable from F.11's Sw to Aps
Cabling data cable from F.12's Sw to Aps
Cabling data cable from F.13's Sw to Aps
Cabling data cable from F.14's Sw to Aps
Cabling data cable from nearest Sw to Aps
Configure Aps, Sws, and Ctr at NetNam's office
Deploy a staging system at NetNam's office
Deliver the hardware to the Landmark
2 day
2 day
2 day
2 day
2 day
1 day
1 day
1 day
1 day
Install Aps at F.10
Install Aps at F.11
Install Aps at F.12
Install Aps at F.13
Install Aps at F.14
Install Aps at G, RT and gym
Labeling all devices and cable.
Handover the system, documents, and training.
Sign the UAT and finish the project.
Legend:
SR = Server room
G = Ground Floor
F = Floor
RT = Rooftop
AP = Access Point
Sw = Switch
Ctr = Controller
Admin = Administration team of NetNam.
Inf = Infrastructure team of NetNam.
PM = Project manager from NetNam.
Per = Person
Note:
The working time is from 9:00 a.m to 5:00 p.m.
Sunday and Saturday are not working day.