METHOD STATEMENT & RISK ASSESMENT ROBERTSBRIDGE COMMUNITY COLLEGE PROJECT NUMBER – G14/46395 PROJECT MANAGER – Geoff Field RISK ASSESSMENT & METHOD STATEMENT Job Number G14/46395 Contract/ Site name Robertsbridge Community College, Knelle Road, Robertsbridge, TN32 5EA. Site Location As Above Work/Tasks to be carried out :- Construction of New Parking Bays & Concrete Hardstanding Contractors Project Manager Geoff Field Revision Date 07753-850726 geoff@hailshamroadways.co. uk Contact Mobile E.mail Client Robertsbridge Community College Address Knelle Road, Robertsbridge, TN32 5EA. Contact Details Tony Hougham Contact Mobile E.mail Dates/times the work will be carried out :Start Date 28/7/2014 Duration of works 10 Days Normal Working Hours Between 8.00am - 6.00pm Page 2 of 19 21/7/2014 ahougham@robertsbridge.org.uk RISK ASSESSMENT & METHOD STATEMENT RISK ASSESSMENTS a) Generic Risk Assessments - See Appendix D b) Site Specific Operations What is the Activity What is the Hazard Who is at Risk Hazard Effect 1–5 (A) Prob 1–3 (B) Risk What Control Measures Need to be put in Place (A x B) Residual Hazard 1–5 (A) Residual Prob. 1–3 (B) Residu al Risk (A x B) Delivering machinery Trips and falls operatives 2 3 6 Ensure unloading takes place in a controlled manner with a banksman 2 1 2 Entering the works area Trips and falls Members of the public 2 2 4 Ensure signs are in place to warn pedestrians 2 1 2 Delivering materials Trips and falls operatives 2 2 4 Ensure unloading takes place in a controlled manner with a banksman 2 1 2 Excavating Above Tree Roots Damaging Roots Trees 5 3 15 5 1 5 Excavating Above Tree Roots Damaging Roots Trees 5 3 15 Ensure that all excavations are watched by banksman to ensure no damage to roots Hand dig areas above tree roots 5 1 5 Circulation of Risk Assessment (to be signed) Name of Assessor Date of assessment Site Foreman Operative Geoff Field 21/7/2014 Foreman See attached list Page 3 of 19 Client Other HAZARD EFFECT 5 4 3 2 1 Fatality Major injury / illness More than 3 days off work Minor injury Near miss PROBABILITY 3 2 1 Very likely to occur Likely to occur Unlikely to occur RISK RATING SYSTEM +12 Very High Risk 8-12 High Risk Find alternative method; if necessary involving CDM Coordinator and Design Team. If possible use alternative method. If not, implement further control measures Method Statement sections below must be completed. 4-6 Medium Risk Control measures needed. 1-3 Low Risk No further action needed. RISK ASSESSMENT & METHOD STATEMENT COSHH assessment Summary of details below:Type of materials Is a COSHH assessment required? x Manufacturer Coated macadam Bitumen Tack Coat Attached COSHH Sheet Tarmac See Appendix B Colas See Appendix B Permit to work required?:Permit type :- Yes /No Hot Works no Confined space no Access no Planning only no Work on or near electrical equipment no Yes Location on site Additional Details Page 5 of 19 Details when used No RISK ASSESSMENT & METHOD STATEMENT Detail any personal protective equipment required (PPE):PPE item Yes /No Type Details when used - Safety Footwear Yes Steel toecap with mid sole protection safety boots All times on site Head Protection Yes Only helmets to BS 5240 or EN 397 less than 3 years old will be worn. Safety helmets will be worn by all our operatives at all times, in specified locations Hi-Vis Clothing Yes Class 1 At all times on site Gloves, include type Weather Protection Eye Protection Yes Leather At all times on site Yes Water Resistant When necessary Yes Glasses At all times on site Ear Protection Yes Full ear defender When operating machinery Full body safety harness Respiratory Protection No No FFP1 FFP2 Detail any safety equipment that will be required:- Page 6 of 19 FFP3 RISK ASSESSMENT & METHOD STATEMENT Noise assessment Is a noise assessment required? Full details below:Type of Name of machine machine Area of use: Ear protection requirements and type: Atlas Copco 85 In the open air Ear Defenders Tandem vib roller Spin Cutter BOMAG 85 In the open air Ear defenders Stihl 85 In the open air Ear Defenders WACKER 85 In the open air Ear Defenders Marini 85 In the open air Ear Defenders Paving Machine Vibration assessment Full details below: Type of machine Name of machine Is a vibration assessment required? Atlas Copco tba 45minutes per person Vibrating plate WACKER tba 45minutes per person Manual handling assessment Is a manual assessment required Full details of all items over 20 kgs as follows:Weight Yes No No no Vibration level Exposure limit and control measure m/ sec ² Compressor Material/ equipment No dB (A) max. at source Compressor Vibrating plate Yes Amount Dimensions Control measure Additional Details No items in excess of 20kg to be lifted by individual operatives Page 7 of 19 Yes RISK ASSESSMENT & METHOD STATEMENT Detailed sequence of work operations in a logical order See Appendix A for relevant drawings/sketches and/or technical information if required. SITE INDUCTION Ensure that a site induction is carried out with all site personnel prior to the works commencing To ensure that all works are carried out in accordance with the requirements of the attached risk assessments Ensure that all risk assessments have been discussed and that emergency and fire procedures are in place Ensure that all site personnel are familiar with the safe use of plant to be used Ensure that site plant has been appropriately maintained and is fit for use GENERAL SITE APPRAISEL Before commencement of works, ensure that the site is ‘walked’ by the operatives to familiarise themselves with its terrain Remove any obvious hazards and the like. Carry out visual check for both overhead and underground services Cable Avoidance Tool is to be used prior to works to establish locations of underground services Check for lose and damaged branches and remove as required Check ground conditions are suitable for safe working THE WORKS Parking Bays Away From Tree Roots To excavate area 290mm below required finish levels and dispose of all arisings on site. To supply and lay new 255 x 125mm HB kerbs on concrete bed and haunch. To supply and fit 2 no. new 900 x 450mm diameter plastic road gullies with 425 x 425mm cast iron gratings. To connect to existing drainage with 10mm diameter plastic pipe. To supply and lay 200mm depth of granular sub-base, 60mm depth of AC 20 dense binder 100/150 asphalt and 30mm depth of AC 10 close surface 100/150 asphalt consolidated. Parking Bays Above Tree Roots To carefully excavate BY HAND DIGGING existing turf to an approximate depth of 50mm and dispose of all arisings. To exacavate for new kerbing BY HAND DIGGING and dispose of all arisings. To supply and lay new 2600mmx120mmx200mm railway sleepers and secure with new 600mmx50mmx50mm wooden pegs. To supply and lay 200mm depth of Type 3 granular sub-base, 60mm depth of AC 20 open binder 100/150 asphalt and 30mm depth of AC 10 open surface 100/150 asphalt consolidated. Footpath Above Tree Roots To carefully excavate BY HAND DIGGING existing turf to an approximate depth of 50mm and dispose of all arisings on site. To excavate for new kerbing BY HAND DIGGING and dispose of all arisings on site. To supply and lay new 150x25mm tanalised timber Page 8 of 19 RISK ASSESSMENT & METHOD STATEMENT edging board and secure with 600mmx50mmx50mm wooden pegs. To supply and lay 150mm depth of Type 3 granular sub-base, 45mm depth of AC 20 open binder 100/150 asphalt and 20mm depth of AC 6 open surface 100/150 asphalt consolidated. Bike Shelter Base NO EXCAVATION TO BE CARRIED OUT. To supply and lay 100mm depth of granular sub-base. To supply and fit shuttering. To supply and lay polythene membrane, a single layer of A142 reinforcing mesh and 150mm depth of C30 concrete. 7.2.1 To avoid damage to tree roots, existing ground levels should be retained within the RPA. Intrusion into soil (other than for piling) within the RPA is generally not acceptable, and topsoil within it should be retained in situ. However, limited manual excavation within the RPA might be acceptable, subject to justification. Such excavation should be undertaken carefully, using hand-held tools and preferably by compressed air soil displacement. NOTE Due to the demands that manual excavation places on a development project, and limitations arising from health and safety considerations, it is not realistic to plan for excavation using hand-held tools where there is a need for trench shoring or grading the sides of the excavation to a stable angle of repose. 7.2.2 Roots, whilst exposed, should immediately be wrapped or covered to prevent desiccation and to protect them from rapid temperature changes. Any wrapping should be removed prior to backfilling, which should take place as soon as possible. 7.2.3 Roots smaller than 25 mm diameter may be pruned back, making a clean cut with a suitable sharp tool (e.g. bypass secateurs or handsaw), except where they occur in clumps. Roots occurring in clumps or of 25 mm diameter and over should be severed only following consultation with an arboriculturist, as such roots might be essential to the tree’s health and stability. 7.2.4 Prior to backfilling, retained roots should be surrounded with topsoil or encompassed sharp sand (builders’ sand should not be used because of its high salt content, which is toxic to tree roots), or other loose inert granular fill, before soil or other suitable material is replaced. This material should be free of contaminants and other foreign objects potentially injurious to tree roots. Page 9 of 19 RISK ASSESSMENT & METHOD STATEMENT Resources Number of operatives anticipated to be on site to carry out the work safely:- 3 Plant, equipment to be used Inspection/certification requirements – See appendix C Van Tandem roller Wacker plate 3T Excavator 3T Dumper 16T Grab Lorry Materials to be used 255mm x 125mm HB Kerbs 150mm x 50mm BN Kerbs C20 Concrete Type 1 Granular Sub Base Type 3 Granular Sub Base AC 20 dense binder 100/150 AC 20 OPEN binder 100/150 AC 10 close surface 100/150 AC 10 OPEN surface 100/150 Page 10 of 19 RISK ASSESSMENT & METHOD STATEMENT Details of access and egress to work areas:All access to site to be gained from KnelleRoad. Arrangements for delivery, stacking, storing and movement on site of plant/ materials:Delivery Materials delivered and retained on trucks until required Stacking & Storage Stored on delivery vehicles Movement of plant/Materials On specified Haul routes and Under supervision of a banksman Protection needed for any site visitors:Yes Other employees x PPE Required Yes Hi Vis No No x Hard Hat Yes Client Personnel x No x Yes No Yes Members of the public Hi Vis Hi Vis Hi Vis Hard Hat Hard Hat Ear Defenders x Ear Defenders Ear Defenders Gloves x Gloves Gloves Safety Glasses x Safety Glasses Safety Glasses Safety Boots x Safety Boots Safety Boots Dust Masks Dust Masks Page 11 of 19 Dust Masks No x Yes No RISK ASSESSMENT & METHOD STATEMENT Is site specific signage required? Signage:Full details below:Information – Yes No x None X Specific detailed description of safe working at heights/prevention of falls:Hierarchy for managing and selecting equipment for work at height. Selected Equipment Details of use, also give reasons Equipment To be Not why equipment is not used. N/A Detail of work at height used Suitable X 2 MEWPS Scissor lifts, cherry pickers etc. Scaffolding/ Fixed Guardrails 3 Stepladders X 4 Ladders X 5 Safety Harness / Safety Lines. X 1 X None X Specific detailed description of safe working at depths not exceeding 5m:Hierarchy for managing and selecting equipment for work at depth. Selected Equipment Details of use, also give reasons a. Equipment To be Not why equipment is not used. N/A Detail of work at depths not exceeding 5m used Suitable 1 Safety Harness / Safety Lines. X 2 Gas Detection X 3 Ladders X 4 5 Page 12 of 19 RISK ASSESSMENT & METHOD STATEMENT Environmental controls details Ensure that any fauna and natural wildlife is not unnecessarily disturbed by the works Description of clearance of waste from site including waste transfer procedures:Excavated materials to be loaded on to tipper and taken to a licenced waste facility Site Welfare Toilet and hand washing facility are available on site Description of emergency/rescue and fire procedures. Ensure that any formal Fire Procedures explained at site induction are adhered to- For out of hours emergency contact:First name Surname Geoff Field Contact Number 07753-850726 Who will be the on-site First Aider:First name Surname Nick Honeysett Training course/date July 2013 Page 13 of 19 RISK ASSESSMENT & METHOD STATEMENT Nearest Accident and Emergency Hospital CONQUEST HOSPITAL The Ridge, St Leonards on Sea, Hastings, TN37 7RD. 01424-755255 Competent person/supervision/training/procedures:Duties of supervisor/foreman (name if known at this stage) To act as Company Foreman/representative to carry out works as instructed and specified First name Surname Training/ level of competence Nick Honeysett Foreman Name and contact details of Health and Safety Officer/Manager or Consultant (Must include qualifications/ membership of professional H&S body) Name Contact details Qualifications/membership of professional H&S body Bryan Sheldon 0845-2268393 Page 14 of 19 MIOSH, MIIRSM RISK ASSESSMENT & METHOD STATEMENT Names of all operatives involved in this operation:NB. To be completed by all operatives involved in the works after Site Supervisor has explained the contents. First Name Surname Job title Signature Rev No Date Nick Honeysett Foreman 21/7/2014 David Dann Skilled Operative 21/7/2014 Dave Seymour Skilled Operative 21/7/2014 Name of competent person/s who prepared this method statement:Name Job title Signature Geoff Field Managing Director Page 15 of 19 Date 15/7/2014 RISK ASSESSMENT & METHOD STATEMENT APPENDIX A Site Drawings Technical Information Page 16 of 19 RISK ASSESSMENT & METHOD STATEMENT APPENDIX B COSHH Details – (Carried in Foreman Pack) Page 17 of 19 RISK ASSESSMENT & METHOD STATEMENT APPENDIX C Plant Inspection / Certification Page 18 of 19 RISK ASSESSMENT & METHOD STATEMENT APPENDIX D Generic Risk Assessments – (Carried in Foreman Pack) Page 19 of 19