Asynchronous activity 4:
Write your name and section upon submitting your work
The AUS Company is planning to develop a new chemical process. They have identified the
following activities:
Activity
Description
A
B
C
D
E
F
G
H
I
J
Test method 1 for process
Test method 2 for process
Select the best method and refine the process
Complete initial preparation of production facilities
Train personnel
Develop final procedure manual
Run tests on the refined process
Adjust the production method
Set up complete production system
Run final tests
a.
b.
c.
d.
Immediate
Predecessor
--A, B
-D
D
C, E
F, G
F
H, I
t
16
11
5
12
2
4
2
2
4
2
Develop a project network showing all the data needed in a rectangular nodes (10 points)
Develop a Gantt Chart (20 points)
Do your work as neat as you can and make it organize as it can be (10 points)
Have your work pictured by cam scanner and attached it in MS Words Docs then send it to
our NEO LMS Class (10 points)