2011 International Conference on Electrical Engineering and Informatics 17-19 July 2011, Bandung, Indonesia E14 - 5 Through Fault Current Monitoring System to Predict the Degradation of Transformer Withstand Capability H. Maryono#1, H.I. Septiyani#2, M. Muhlis #3, M.N. Nugraha#4 # PT PLN (Persero) P3B Jawa Bali West Jawa Regional Offices - Maintenance Department Jl. M. Toha km 04 Cigereleng, Bandung – Indonesia 40255 1 hendrik.m@pln-jawa-bali.co.id henny.ika@pln-jawa-bali.co.id 3 muhlis@pln-jawa-bali.co.id 4 n.nugraha@pln-jawa-bali.co.id 2 Abstract— PLN P3B Jawa Bali is a unit that responsible for managing and operating the transmission system in Jawa and Bali area. For this utility, power transformer is one of the equipments that has important role in the transmission system, therefore various efforts have been done to prevent transformer failures. To prevent unexpected transformer failure, the condition assessment of distribution transformers is done. Distribution transformer failure analysis has been done as the early stage of the assessment. The results of the analysis indicate that faults on 20 kV feeders are the main root cause of the damage on distribution transformer (150/20 kV and 70/20 kV). Some references also mentioned that the transformer failures caused by 20 kV feeder faults are highly affected by the fault currents and duration. Therefore, this paper will presents about the development of the through fault current (TFC) monitoring system to predict the degradation of transformer withstand capability and its application on distribution transformers 150/20 kV 60 MVA. This system consists of TFC logger, PC concentrator and web based database system. TFC logger will record the fault current and duration that exceed the normal current on the transformer and then send the data to the server. The cumulative TFC data will be used to predict the degradation of transformer withstand capability. Keywords— Through fault current, transformer withstand capability, TFC monitoring system I. INTRODUCTION PLN P3B Jawa Bali is a unit that responsible for managing and operating the transmission system in Jawa and Bali area. For this utility, power transformer is one of the equipment that has important role in transmission system. Therefore, various efforts have been done to prevent transformer failures. Distribution transformer failure analysis has been conducted as a part of transformer condition assessment. The results showed that the faults on 20 kV feeders are the main root cause of transformer failures in P3B Jawa Bali [1]. References [2,3,4] also mention that through fault currents produce mechanical and electrical stress which can cause a weakening of winding clamping pressure, movement of conductors, insulation damage and changes in winding structure. These stresses are strongly affected by the fault current and duration. Therefore, this paper presents a TFC monitoring system to predict the degradation of transformer withstand capability and its application on the distribution transformers 150/20 kV 60 MVA. TFC monitoring system is used to record the fault current and duration which exceed the overload current. This data is sent to the server and used to predict the transformer withstand capability. TFC data on transformers 150/20 kV 60 MVA in Cigereleng and Fajarsurya substations will also be presented. Some assumptions are needed for predicting the remaining withstand capability of the transformer, therefore it is difficult to get the accurate value. However, by using the TFC monitoring system, fault current and duration can be monitored and used as a basis for possible corrective actions. II. TRANSFORMER WITHSTAND CAPABILITY When the fault occurs, current which flows through the transformer exceeds the transformer overload current (see Fig. 1). This current causes electrical and mechanical stress on the transformer. These stresses can cause a weakening of winding clamping pressure, movement of conductors, insulation damage and changes in winding structure. 20 kV Fig. 1, Through fault current 978-1-4577-0752-0/11/$26.00 ©2011 IEEE Authorized licensed use limited to: Universidad Nacional de Colombia (UNAL). Downloaded on February 17,2021 at 20:30:13 UTC from IEEE Xplore. Restrictions apply. E14 - 5 Based on the IEC 60076-5, distribution transformers should be able to withstand maximum short circuit current for 2 seconds. Reference [3] mention that the degradation of transformer withstand capability can be predicted using equation (1). ………………………………………..(1) transformer remaining withstand capability and as a basis to conduct the possible corrective actions. A. The Architecture of TFC Monitoring System The architecture of TFC monitoring system can be seen in Fig. 4. This system consists of three main components. There are TFC logger, PC concentrator and server. Where: I = Short circuit current t = Duration k = Constant During the operation, transformer withstand capability always be decreased as shown in Fig. 2. This degradation can be caused by thermal and chemical stress, etc. Fig 4, Architecture of TFC monitoring system TFC Logger TFC logger is a device mounted on the secondary side of distribution transformer to monitor the current flowing through that transformer. When the current exceeds the setting value (transformer overload current) the logger will record the fault current and duration, and then transmit them to the PC concentrator via wireless communication. Fig.2, Stress withstand capability over transformer lifetime Transformer withstand capability will be decreased quickly if exposed to through fault current (see Fig. 3). This figure shows that the first two faults reduce the withstand capability significantly, and then the transformer could not withstand the force of the third fault. Fig. 3, Stress withstand capability with through fault current III. TFC MONITORING SYSTEM TFC monitoring system can be used as one detection of transformer condition. The system current and duration and then store the data into server. The cumulative of t are used to of the early record fault the database predict the PC Concentrator PC concentrator is used to collect and pass the data to the server. By using TFC driver installed on the PC concentrator, the users can change the instrument settings and access the data in TFC logger. Server On the server, there is a web-based database application. This server collects all data TFC and then predict the transformer remaining withstand capability. This server is equipped with an early warning system that can send a short message when the cumulative TFC reach a limit value. This setting limit is adjustable. B. Transformer 150/20 kV 60 MVA in Fajarsurya S/S The failure of distribution transformer 150/20 kV 60 MVA at Fajarsurya substation occurred in 2010. This transformer failed when the short circuit occurred on the 20 kV feeder. Sudden pressure relay initiated CBs to open and localize the fault. Based on the disturbance recorder, the fault currents that flow through RST windings were 1267.5 A, 3990A and T 3325 A respectively. Electrical tests have been done to investigate the failed transformer. The results of SFRA and dc resistance tests showed that S phase winding is open. Further investigation has been done to inspect internal condition of the transformer. The results of internal inspection showed that S phase winding elongated as shown in Fig. 5. It was supposed that the S-phase 978-1-4577-0752-0/11/$26.00 ©2011 IEEE Authorized licensed use limited to: Universidad Nacional de Colombia (UNAL). Downloaded on February 17,2021 at 20:30:13 UTC from IEEE Xplore. Restrictions apply. E14 - 5 winding was no longer able to resist axial force f caused by the last fault. transformer since 2009. The through fault currents and can be seen inn Fig. 7 ~ 8 respectively. cumulative of Fig 7, Through faault currents data Cumulative TFC on Tran nsformer 150/20 kV 60 MVA Cigereleng S/S S in 2009 - 2010 80 Cumulative I2t (kA2.s) 70 Fig 5, Failed transformer Based on the operation record book, it was w known that the failed transformer experienced high numbeer of 20 kV feeder faults. The cumulative of t during 2009-22010 can be seen in Fig. 6 as follow. Cumulative TFC on Trx 150/20 kV V 60 MVA Fajarsurya S/S in 2009-201 10 70 Cumulative I2t (kA2.s) 60 50 40 30 60 50 40 30 20 10 0 I2t phase R I2tt phase S I2t phase T Fig 8, Cumulative TFC on Transformer 150/20 kV 60 MVA in Cigereleng substaation By using the cumulative of , remaining withstand capability of the transformer caan be predicted as shown in Fig 9. These curves are calculateed under assumption that the initial withstand capability of thhe transformer in 2009 is 0.9 x k, where 2 . The through fault currents will reduce the initial withstannd capability. Figure 9 shows that the R-phase winding suffeer a higher stress than another phases. 20 Remaining withstand capability 10 0 I2t phase R I2t phase S I phase T I2t Fig 6, Cumulative TFC on Transformer 150/20 kV 60 6 MVA in Fajarsurya substation Based on the inspection result and cumuulative TFC, it is supposed that mechanical stress on the S-phase S winding is higher than the other phases during the 20099-2010. Remaining withstand capability 375 365 355 345 335 325 315 305 295 285 275 R-phase winding C. Transformer 150/20 kV 60 MVA in Cigeereleng S/S Transformer 60 MVA 150/20 kV in Ciggereleng substation operated since 1994. This transformer is one o of transformers which experience high number of faults on 20 kV feeder. Therefore, TFC monitoring system has been installed in this S-phaase winding T-phase winding Fig. 9, Remaining withstand capability 978-1-4577-0752-0/11/$26.00 ©2011 IEEE Authorized licensed use limited to: Universidad Nacional de Colombia (UNAL). Downloaded on February 17,2021 at 20:30:13 UTC from IEEE Xplore. Restrictions apply. E14 - 5 IV. CONCLUSIONS Transformer failure at Fajarsurya substation show that the TFCs can cause the changes in winding structure and open circuit. By using TFC Monitoring System, the fault current and duration can be recorded for predicting the remaining withstand capability of transformer. Some assumptions are needed to predict the remaining withstand capability, so it is difficult to obtain the accurate withstand capability. However, by using this system, the fault current and duration can monitored as a basis for taking possible corrective actions. ACKNOWLEDGMENT We would like to thanks to the Management of PLN P3B Jawa Bali and all contributors who have supported us for developing this TFC Monitoring System. REFERENCES [1] [2] [3] [4] [5] [6] N. Ukhita A. W., A.P. Purnomoadi, A. Susilo, E. Yuliastuti dan A. Pharmatrisanti, Failure Analysis on Power Transformers 60 MVA 150/20 kV, Proceedings of the International Conference on Electrical Engineering and Informatics, Institut Teknologi Bandung, Indonesia June 17-19, 2007. Anita Oommen, A Case Study Evaluation of the Causes for the Premature Failure of Transformer on the Escom Transmission Network, Study Committee B5 Colloquium CIGRE, Canada, 14-16 September 2005. Roy Moxley and Armando Guzman, Transformer Maintenance Interval Management, Schweitzer Engineering Laboratories, Inc., 2005. R.P.P smeets, L.H.te Paske, T. Fogelberg, Short Circuit Withstand Capability of Large Power Transformers. IEC, Power Transformer – Ability to withstand short circuit, IEC 60076-5, 2000. IEEE Guide for Transformer Through Fault Current Duration, IEEE C57.109-1995. 978-1-4577-0752-0/11/$26.00 ©2011 IEEE Authorized licensed use limited to: Universidad Nacional de Colombia (UNAL). Downloaded on February 17,2021 at 20:30:13 UTC from IEEE Xplore. Restrictions apply.