Central View Office Building Project BREEAM+WELL tender requirements Prepared by BuildGreen Prepared for 13 November 2020 www.build-green.eu Central View Office Building Introduction I. General Information Central View office building aims to obtain BREEAM Outstanding - WELL Platinum certification according to BREEAM International New Construction 2016 version SD233 and WELL Building Standard version v2. The Client will undertake at his own cost a BREEAM - WELL assessment of the development which will be carried out by a licensed BREEAM International Assessor using evidence provided by the Contractor. 1. Building Research Establishment’s Environmental Assessment Method BREEAM (Building Research Establishment’s Environmental Assessment Method) is the established method of assessing, rating, and certifying the sustainability of buildings and is the UK and Europe leading and most widely used environmental assessment method. It sets the standard for best practice in sustainable design and has become the de facto measure used to describae a building’s environmental performance. The aims and objectives of BREEAM are: Aims of BREEAM •To mitigate the impacts of buildings on the environment •To enable buildings to be recognized according to their environmental benefits •To provide a credible, environmental label for buildings •To stimulate demand for sustainable buildings Objectives of BREEAM •To provide market recognition to low environmental impact buildings •To ensure best environmental practice is incorporated in buildings •To set criteria and standards surpassing those required by regulations and challenge the market to provide innovative solutions that minimize the environmental impact of buildings •To raise the awareness of owners, occupants, designers and operators of the benefits of buildings with a reduced impact on the environment •To allow organizations to demonstrate progress towards corporate environmental objectives Building projects are assessed at the design and post-construction stages using a system of environmental issues grouped within the following categories: •Management •Health and Well-Being •Energy •Transport •Water •Materials •Waste •Land use and Ecology www.build-green.eu 2 •Pollution The assessment of the building results in a final report and BRE Global BREEAM certificate detailing the performance of the assessed building against the environmental issues covered by the Standard. The building’s performance is expressed as a BREEAM rating of PASS, GOOD, VERY GOOD, EXCELLENT or OUTSTANDING. 2. The WELL Building Standard™ (WELL) The WELL Building StandardTM (WELL) is the first building standard to focus exclusively on the health and wellness of people in buildings. WELL is a performance-based system for measuring and certifying features of buildings that impact human health and wellbeing, through air, water, nourishment, light, fitness, comfort and mind. It marries best practices in design and construction with evidence-based medical and scientific research – harnessing buildings and communities as a vehicle to support human wellbeing. WELL values Equitable - Provides the greatest benefit to the largest number of people, inclusive of all demographic and economic groups and with special consideration to less advantaged or vulnerable populations. Global - Proposes interventions that are feasible, achievable and relevant across many applications throughout the world. WELL v2 offers regionally appropriate pathways for meeting health intents based on where projects are located. Evidence-based - Undergirded by strong, validated research leading to conclusions that can reasonably be accepted by the scientific community. Technically Robust - Draws upon industry best practices and proven strategies, offering consistency in findings across the relevant field or discipline. Customer Focused - Defines program requirements through a dynamic development process, with multiple opportunities for stakeholder engagement, and by tapping the expertise of established leaders in science, health, business, design and operations. Resilient - Responds to advances in scientific knowledge and technology, continuously adapting and integrating new findings in the field. BRE and the International WELL Building Institute™ (IWBI™) are collaborating to promote health and wellbeing in the design, construction and operation of buildings and fit-outs, internationally. To simplify the process for project teams pursuing both assessment methods, BRE and IWBI have worked together to compare performance requirements, harmonise evidence and identify opportunities to streamline the process of achieving dual certification. This work demonstrates the significant synergies between the two methods and the efficiencies that exist between their respective assessment and certification processes. It forms a part of an ongoing collaboration between BRE and IWBI to work together to harmonise their approach to health and wellbeing in the built environment across their standards, research programmes and services generally. www.build-green.eu 3 3. Requirements The present document represents a mandatory technical requirement for all project team members, in pursuance of the BREEAM - WELL certification of the Central View Office Project. If technical requirements herewith mentioned are more stringent or different than those of the design, the current document specification shall be applied. Note that considering that sustainability is not a sole responsibility of one team member, the entire team shall consider, respect, follow and implement the following requirements. a. BREEAM Requirements It is the BREEAM Assessor who determines the BREEAM rating and the assessment report is the formal record of an assessor's audit against the criteria defined in the Technical Manual for a BREEAM scheme. The BREEAM certificate issued by BRE Global provides assurance that the service provided by the assessor (that is, the process of producing the assessment report) has been conducted in accordance with the requirements of the scheme. The purpose of the certificate is therefore to give confidence to the client in the assessor's performance and processes in determining a BREEAM rating. The Contractor is obliged to achieve a minimum score of 85% which includes a built‐in contingency to manage the risks of non‐compliance or failure to provide adequate clarification in response to the BRE Quality Assurance process. The Contractor shall establish a unique point of contact for BREEAM who shall: • Coordinate the BREEAM efforts on behalf of the Contractor • Brief the Contractor project team • Ensure that all evidence submitted to the BREEAM Assessor is complete and clearly presented. • Work closely with the Client appointed BREEAM Assessor to manage the risk of noncompliance. • Inform the BREEAM Assessor of any project variations likely to affect the final BREEAM rating of the buildings. b. WELL Requirements It is the WELL Assessor who determines the WELL rating and the assessment report is the formal record of an assessor's audit against the criteria defined in the WELL Building Standard. The Contractor has to achieve a minimum score of 80 points which includes a built‐in contingency to manage the risks of non‐compliance or failure to provide adequate clarification in response to the WELL processes for reviewing the documentation and performance. The Contractor shall establish a unique point of contact for WELL who shall: • Coordinate the WELL efforts on behalf of the Contractor • Brief the Contractor project team • Ensure that all evidence submitted to the WELL Assessor is complete and clearly presented. • Work closely with the Client appointed WELL Assessor to manage the risk of noncompliance. www.build-green.eu 4 • Inform the WELL Assessor of any project variations likely to affect the final WELL rating of the buildings. The cost for all contractor design, procurement, works, documents, consultants, etc in relation to this subject shall be included in the tender price. The Contractor is provided below with summary requirements in relation to his obligations in respect of the targets. Evidence requirements The client representative (assessor or consultant) must be satisfied beyond reasonable doubt that the evidence gathered demonstrates unambiguous compliance with all relevant criteria defined in the BREEAM/ WELL scheme. All evidence must be appropriately referenced in the formal report produced by the assessor and made available on request from BRE Global Ltd and IWBI for quality assurance checks. Clear, ordered and well referenced evidence for each feature and criterion facilitates efficient quality assurance and certification. Evidence must demonstrate that ALL relevant criteria and sub‐criteria are achieved and where relevant, is provided to support compliance notes, definitions etc. Evidence should include a document header with the following details: • Project name • Document title • Company details • Author’s identity and role • Project phase • Date • Signature Relevant parts of the documentation shall be highlighted and translated into English. This document together with annex 1 should be used along with the following documents: 1. Technical Project (tender documentation) – parts related to BREEAM and WELL 2. BREEAM certification scorecard 3. WELL certification scorecard 4. BREEAM certification plan 5. BREEAM International New Construction Technical Manual SD233 1.0:2016 6. WELL Building Standard v2 Note: Please note that the whole team ( Design Team, Contractor) should read BREEAM&WELL requirements in line with National regulations. In case that there are some opposite requirements Design team/ Contractor should inform the client immediately. Every requirement listed in the document attached (annex 1) has BREEAM INC TM and IWBI reference. More detailed descriptions can be found in BREEAM Int NC and in WELL v2 Technical Manuals. www.build-green.eu 5 Coordination on site must be carried out in accordance with all relevant BREEAM and WELL standards and requirements and provided by the Contractor. Annex 1 – Central View Office_BREEAM-WELL Tender Requirements www.build-green.eu 6 CENTRAL VIEW - BREEAM - WELL REQUIREMENTS BREEAM 1. MAN Part MANAGEMENT 1. MAN Man 01 Sustainability champion (design) 1. MAN Man 01 Sustainability champion (monitoring progress) 1. MAN 1. MAN 1. MAN 1. MAN Man 03 Sustainability champion (construction) Man 02 Elemental life cycle cost (LCC) Man 02 Component level LCC plan Man 02 Capital cost reporting 1. MAN Man 03 National health and safety legislation 1. MAN Man 03 Environmental management 1. MAN Man 03 Considerate construction Requirements Action List A sustainability champion has been appointed to facilitate the setting and achievement of BREEAM performance targets for the project. The design stage sustainability champion is appointed to perform this role during the feasibility (Preparation and Brief) stage. The defined BREEAM performance targets have been formally agreed (see Relevant definitions) between the client and design or project team no later than the concept design work stage. To achieve this credit at the interim design stage assessment, the agreed BREEAM performance targets must be demonstrably achieved by the project design. This must be demonstrated via the BREEAM Assessor's design stage assessment report. The credit for sustainability champion (design) (criteria 9 to 11 ) has been achieved. A sustainability champion is appointed to monitor progress against the agreed BREEAM performance targets throughout the design process and formally report progress to the client and design team. The sustainability champion must attend key project and design team meetings during the concept design, developed design and technical design work stages (see Relevant definitions). Reporting must be carried out during and prior to completion of each stage, as a minimum. 5 A sustainability champion is appointed to monitor the project to ensure ongoing compliance with the relevant sustainability performance and process criteria, and therefore BREEAM targets, during the construction, handover and close out work stages. To do this the sustainability champion will ideally be site-based or will visit the site regularly to carry out spot checks, with the relevant authority to do so, and will require action to be taken to address shortcomings in compliance. The sustainability champion will monitor site activities with sufficient frequency (see compliance note CN3.3) to ensure that risks of non-compliance are minimised. They will report on progress at relevant project team meetings, including identifying potential areas of non-compliance and any action needed to mitigate. 6 The defined BREEAM performance target forms a requirement of the principal contractor's contract (see Man 01 Project brief and design: CN3.2 and Man 01 Project brief and design – Relevant definitions). 7 To achieve this credit at the final post-construction stage of assessment, the BREEAM-related performance target for the project must be demonstrably achieved by the project. This is demonstrated via the BREEAM Assessor's final postconstruction stage assessment report. BREEAM AP appointment letter (BGR draft) Contract with main contractor/design team Method statement (BGR draft) Time schedule for entire project- including design Minutes of Meetings 1 An outline, entire asset elemental LCC plan has been carried out at the Concept Design stage together with any design option appraisals in line with 'Buildings and constructed assets – Service life planning – Part 5: Life cycle costing ISO 156865:20081. 2 The outline LCC plan: 2.a Provides an indication of future replacement costs over a period of analysis as required by the client (e.g. 20, 30, 50 or 60 years) 2.b Includes service life, maintenance and operation cost estimates. 3 Demonstrate, using appropriate examples provided by the design team, how the elemental LCC plan has been used to influence building and systems design, and specification to minimise life cycle costs and maximise critical value. 4 A component level LCC options appraisal has been developed by the end of Process Stage 4 (equivalent to Technical Design Stage) in line with ISO 15686-5:2008, and includes the following component types (where present): 4.a Envelope, e.g. cladding, windows, or roofing 4.b Services, e.g. heat source, cooling source or controls 4.c Finishes, e.g. walls, floors or ceilings 4.d External spaces, e.g. alternative hard landscaping, boundary protection. 5 Demonstrate, using appropriate examples provided by the design team, how the component level LCC options appraisal has been used to influence building and systems design, and specification to minimise life cycle costs and maximise critical value. 6 Report the capital cost for the building , via the BREEAM Assessment Scoring and Reporting tool. Link Comments Responsibility Man 01 Project brief and design https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man01.htm %3FTocPath%3D5.0%2520Management%7C _____1 Sustainability champion have been asigned by client. Razvan Nica is BREEAM Accredited Profesional and comply with Sustainability Champion criteria. Project manager Architect BuildGreen Man 01 Project brief and design https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man01.htm %3FTocPath%3D5.0%2520Management%7C _____1 Sustainability champion have been asigned by client. Razvan Nica is BREEAM Accredited Profesional and comply with Sustainability Champion criteria. Project manager Architect BuildGreen Man 03 Responsible construction practices https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man03.htm %3FTocPath%3D5.0%2520Management%7C _____3 Main Contractor Project manager BuildGreen The costs for building elements for entire asset. It will be expressed as cost per square metre of gross internal floor area (GIFA) Man 02 Life cycle cost and service life planning https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man02.htm %3FTocPath%3D5.0%2520Management%7C _____2 This study will be conducted by Project manager BuildGreen. Input informations are BuildGreen required from the design & construction team. All component types to be installed Total cost of the project reported by the client Total cost of: envelope, services, finishes, external spaces Man 02 Life cycle cost and service life planning https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man02.htm %3FTocPath%3D5.0%2520Management%7C _____2 This study will be conducted by Project manager BuildGreen. Input informations are BuildGreen required from the design & construction team. Predicted capital costs The capital cost for the building includes the expenses related to the initial construction of the building: Construction, including preparatory works, materials, equipment and labour Site management Construction financing Insurance and taxes during construction Inspection and testing. Man 02 Life cycle cost and service life planning https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man02.htm %3FTocPath%3D5.0%2520Management%7C _____2 The reporting via BREEAM platform is BuildGreen responsibility. Team needs to provide relevant informations Project manager BuildGreen Man 03 Responsible construction practices https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man03.htm %3FTocPath%3D5.0%2520Management%7C _____3 The construction team have an ISO14001 and an occupational health and safety management system compliant with OHSAS 18001:2007 Main Contractor Man 03 Responsible construction practices https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man03.htm %3FTocPath%3D5.0%2520Management%7C _____3 Man 03 Responsible construction practices https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man03.htm %3FTocPath%3D5.0%2520Management%7C _____3 The construction team have an ISO14001 and an occupational health and safety management system compliant with OHSAS 18001:2008 Main Contractor 2 All national health and safety legislation and regulations for construction sites are considered and implemented during (refer to CN3.6): 2.a The design of the asset; to minimise health and safety risks 2.b Pre-construction work planning and organisation; to collate health and safety information from all relevant stakeholders (refer to Relevant definitions) 2.c Site set-up; to implement health and safety features 2.d Construction; to manage, monitor and report on the health and safety of construction site staff. 3 The principal contractor operates an environmental management system (EMS) covering their main operations. The EMS must be third party certified to ISO 14001/EMAS or an equivalent standard. 4 Implement best practice pollution prevention policies and procedures on site, demonstrated through the project team completing the checklist outlined in Table 9. To demonstrate compliance, not all actions need to be achieved; however the assessor and project team must demonstrate that the intent of each section (i.e. air quality) has been met. 9 BREEAM credits can be awarded as principal contractor achieves all items in each of the four sections within Checklist A1 Confirmation letter (BGR draft) AND the contractor's performance has been confirmed by independent assessment and verification. Main Contractor 1. MAN 2. HEA 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN Letter Of Assurances: => Contractor https://v2.wellcertified.com/wellv2/en/air/featur e/4 A letter to confirm that the fresh air is provided into the building in accordance with the criteria of the national best practice standard for ventialtion, the HVAC Systems are designed to incorporate suitable filtration to minimise external air pollution, as defined in EN 13779:2007, and that the building's air intakes are over 10m of horizontal distance from sources of external pollution The plan with the location of the CTAs from which the 10 m distance is to occur. A letter to confirm that the testing report confirm the required fresh air rates required Confirmation letter (BGR draft) Hea 02 Indoor Air Quality https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_02.htm%3FTo cPath%3D6.0%2520Health%2520and%2520 Wellbeing%7C_____2 Man 03 Responsible construction practices https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man03.htm %3FTocPath%3D5.0%2520Management%7C _____3 Main Contractor 1 There is a schedule of commissioning and testing that identifies the appropriate commissioning required for the scope of works. The schedule includes a suitable timescale for commissioning and recommissioning of building services and control systems, as well as testing and inspecting the building fabric. 2 The schedule will identify the appropriate standards that all commissioning activities will be conducted in accordance with. This will include national best practice commissioning codes or other appropriate standards, where applicable. Where a Man 04 Commissioning and building management system (BMS) is specified, refer to compliance note CN3.2 on BMS commissioning procedures. testing schedule and 3 An appropriate team member is appointed to monitor and programme pre-commissioning, commissioning and testing. responsibilities Where necessary, this will include recommissioning activities on behalf of the client. 4 The principal contractor accounts for the commissioning and testing programme, responsibilities and criteria within their budget and the main programme of works. The programme shall allow for the required time to complete all commissioning and testing activities prior to handover. Project budget. Programme of works. Appointment letter or commissioning responsibilities schedule. Relevant section or clauses of the building specification or contract. Main contractor's programme. Commissioning schedule. Man 04 Commisioning and handover https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man04.htm %3FTocPath%3D5.0%2520Management%7C _____4 Project Manager Main Contractor 5 The commissioning and testing schedule and responsibilities credit is achieved. 6 For complex building services and systems, a specialist commissioning manager is appointed during the design stage (by either the client or contractor) with responsibility for: Man 04 Commissioning 6.a Undertaking design reviews and giving advice on suitability for ease of commissioning building services 6.b Providing commissioning management input to construction programming and during installation stages 6.c Management of commissioning, performance testing and handover or post-handover stages. 6.d For simple building services, this role can be carried out by an appropriate project team member (see criterion 3 ), provided they are not involved in the general installation works for the building services systems. Option 1: Mechanically ventilated spaces For mechanically ventilated projects, one of the following requirements is met: • Newly installed ventilation systems are designed to meet the supply and exhaust rates set in one or more of the following ventilation guidelines, which must describe ventilation rates for at least 90% of the project area. The ventilation system is A03.1 Ensure Adequate Ventilation scheduled to be tested and balanced after project occupancy: • ASHRAE 62.1-2010 or any more recent versions (Ventilation Rate Procedure or IAQ Procedure) • ASHRAE 62.2-2016 • EN 16798-1 (for Category IV buildings) • AS 1668.2-2012 or any more recent version 10 A building user guide is developed, prior to handover for distribution to the building occupiers and premises managers (see Relevant definitions). A draft copy is developed and discussed with users first (where the building occupants are known) to ensure the guide is most appropriate and useful to potential users. 11 A training schedule is prepared for building occupiers or premises managers, timed appropriately around handover and proposed occupation plans, which includes the following content as a minimum: Man 04 Handover - Has a 11.a The design intent of the building Building User Guide been 11.b The available aftercare provision and aftercare team main contacts, including any scheduled seasonal commissioning developed prior to and post occupancy evaluation handover? 11.c Introduction to, and demonstration of, installed systems and key features, particularly BMSs, controls and their interfaces, to ensure they are fully conversant with the detailed operation of the building 11.d Introduction to the building user guide and other relevant building documentation, e.g. design data, technical guides, maintenance strategy, operations and maintenance (O&M) manual, commissioning records, log book etc. 11.e Maintenance requirements, including any maintenance contracts and regimes in place. To complete the commissioning Undertake design reviews and give advice on suitability for ease of commissioning; Provide commissioning management input to construction programming and during installation stages; To manage commissioning, performance testing and handover and posthandover stages Man 04 Commisioning and handover https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man04.htm %3FTocPath%3D5.0%2520Management%7C _____4 Project Manager Main Contractor Letter Of Assurances: => MEP & Contractor https://v2.wellcertified.com/wellv2/en/air/featur e/3 MEP Designer Main Contractor Man 04 Commisioning and handover BuildGreen will provide draft and https://www.breeam.com/BREEAMInt2016Sch review the final version emeDocument/#04_management/man04.htm %3FTocPath%3D5.0%2520Management%7C _____4 BuildGreen A04.1 Mitigate Construction Pollution Hea 02 Indoor air quality (IAQ) plan Man 03 Monitoring of site impacts For construction occurring after project registration, the following requirements are met: • Ducts are maintained per one of the below: • Ducts are sealed and protected from possible contamination during construction • Ducts are cleaned prior to installing registers, grills and diffusers. • If permanently installed ventilation system is operating during construction, filters must meet the following: • Media filters with a PM10 removal rating of at least 70% (e.g., MERV 8) are used to filter return air • All filters are replaced prior to occupancy • The project implements the following moisture and dust management procedures: • Carpets, acoustical ceiling panels, fabric wall coverings, insulation, upholstery and furnishings and other absorptive materials are stored separately in a designated area protected from moisture damage • All active areas of work are isolated from other spaces by sealed doorways or windows or through the use of temporary barriers • Walk-off mats are used at entryways to reduce the transfer of dirt and pollutants • Saws and similar tools use dust guards or collectors to capture generated dust 2 An indoor air quality plan has been produced and implemented, with the objective of facilitating a process that leads to design, specification and installation decisions and actions that minimise indoor air pollution during the design, construction and occupation of the building. The indoor air quality plan must consider the following: 2.a Removal of contaminant sources 2.b Dilution and control of contaminant sources 2.c Procedures for pre-occupancy flush out 2.d Third party testing and analysis 2.e Maintaining indoor air quality in-use 10 Responsibility has been assigned to an individual for monitoring, recording and reporting energy use, water consumption and transport data (where measured) resulting from all on site processes (and dedicated off-site monitoring) throughout the programme. To ensure the robust collection of information, this individual must have the appropriate authority and responsibility to request and access the data required. Where appointed, the sustainability champion could perform this role. Energy consumption 12 Monitor and record data of the site energy consumption in kWh (and where relevant, litres of fuel used) as a result of the use of construction plant, equipment (mobile and fixed) and site accommodation (as relevant to the project type). Water consumption 15 Monitor and record data on the principal constructor's and subcontractors' potable water consumption (m³) arising from the use of construction plant, equipment (mobile and fixed) and site accommodation (as relevant to the project type, see Compliance notes. 18 Monitor and record data on the transport movements and impacts resulting from delivery of the majority construction materials to the site and construction waste from the site. As a minimum this must cover: 18.a Transport of materials from the factory gate to the building site, including any transport, intermediate storage and distribution, see Relevant definitions. 18.b The scope of this monitoring must cover the following as a minimum: 18.b.i Materials used for major building elements, 18.b.ii Where within scope, ground works and landscaping materials. 18.c Transport of construction waste from the construction gate to waste disposal processing or the recovery centre gate. The scope of this monitoring must cover the construction waste groups outlined in the project's waste management plan Main Contractor The IAQ will be prepared by BuildGreen BuildGreen. Main contractor needs to implement it and report it accordingly. 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN W08.1 Provide Bathroom and Handwashing Accommodations N01.1 Ensure Fruit and Vegetable Availability N01.2 Promote Fruit and Vegetable Visibility N02.1 Provide Nutritional Information N02.2 Address Food Allergens N02.3 Label Sugar Content Option 1: Bathroom Accommodations Letter of Assurance – Designer The following requirements are met: • All bathrooms meet the following requirements: • Provide trash receptacles in stalls (in women’s and single-user bathrooms). If toilet paper cannot be flushed down toilets, trash receptacles must be placed in all bathroom stalls. • Provide sanitary pads, tampons and/or other menstrual products at no cost or subsidized by at least 50% (in women’s and single-user bathrooms). • Provide a hook, shelf or equivalent storage support in each toilet stall. • All occupants have access to at least one bathroom per floor that provides an accessible stall. • All occupants have access to at least one bathroom per floor that provides an infant changing table. • All regular occupants may request a syringe drop box at no cost, which the project places in one or more bathrooms based on occupant demand • All single-user bathrooms (if present) are open to all individuals with accompanying signage and at minimum one singleuser bathroom per floor (if present) meets the room and stall dimensions required by local accessibility code. • Floor drains are equipped with a self-primed liquid-seal trap Option 2: Family bathrooms For projects where the majority of occupants are visitors (e.g., shopping malls, airports, museums), family bathrooms are provided that meet the following requirements: • Accommodate expected demand by individuals in need of accompaniment or assistance in the bathroom (e.g., children, individuals with mental or physical disabilities) • Contain the following accommodations: • Changing table for infants. • Children’s toilet facilities or accommodations for child use of adult size toilet. • Children’s sinks or accommodations for child use of adult size sink (e.g., availability of stepstool). • Motion sensor lights. • Skid resistant floors. • Safety grab bars. • At least one designated location for bags (e.g., hook, shelf separate from changing table and sink). Option 3: Handwashing support The project provides, at minimum, the following in all sinks where handwashing is expected (e.g., bathrooms, break rooms and wellness rooms): If foods are sold or provided on a daily basis by (or under contract with) the project owner, each food outlet meets one of the Annotated Documents: following requirements: => Policy and/or Operations Schedule • The selection includes at least two varieties of fruits (containing no added sugar) and at least two varieties of non-fried vegetables • At least 50% of available food options are fruits (containing no added sugar) and/or non-fried vegetables. https://v2.wellcertified.com/wellv2/en/water/fe To be considered/ implemented in Architect ature/8 Building User Guide or Operational Manual https://v2.wellcertified.com/wellv2/en/nourish ment/feature/1 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Option 1: Fruit and vegetable promotion Letter of Assurance – Owner If foods are sold or provided on a daily basis by (or under contract with) the project owner, fruits and vegetables meet one of the following requirements: • Placed at eye-level or just below eye-level • Displayed on the countertop, table or other visible surface • Placed at point-of-sale or point-of-purchase • Placed at the end of aisles • Placed at the beginning of food service lines • Visible from the food outlet entrance If packaged foods and beverages, including items in vending machines and self-service bulk foods, are sold or provided on a Letter of Assurance – Owner daily basis by (or under contract with) the project owner, the following nutrition information is clearly displayed at point-ofdecision on packaging or adjacent signage: • Total calories per serving or package. • Macronutrient content (total protein, total fat and total carbohydrate) in weight and/or as a percent of the estimated daily requirements (daily values) per serving or package. • Total sugar content per serving or package. Option 1: Food allergy training Letter of Assurance – Owner If food is prepared on-site on a daily basis by (or under contract with) the project owner, the following requirements are met: • All food service staff (including managers, servers and kitchen staff) are offered annual food allergy training that covers, at a minimum, the following topics • Overview of food allergies • Anaphylaxis • Emergency response • Communications protocols • Reducing risk for cross-contact • Use of recipes and ingredient disclosure • Knowledge test • During hours of operation, at least one staff member with food allergy training within the past year is present to handle questions and special requests from individuals with food allergies. https://v2.wellcertified.com/wellv2/en/nourish ment/feature/1 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual https://v2.wellcertified.com/wellv2/en/nourish ment/feature/2 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual https://v2.wellcertified.com/wellv2/en/nourish ment/feature/2 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual For standard menu items sold or provided by (or under contract with) the project owner, one of the following requirements is met: • Standard menu items do not contain more than 25 g of sugar per serving. • The total sugar content for each standard menu item, as usually prepared and offered for sale, is clearly displayed at the point-of-decision on menus and menu boards (in addition to calories as required in Part 1 of this feature). • Standard menu items containing more than 25 g of sugar per serving are identified by an icon on menus and menu boards. An explanation of the icon and the health risks of high sugar intake is available at the point-of-decision https://v2.wellcertified.com/wellv2/en/nourish ment/feature/2 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Letter of Assurance – Owner 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN N04.1 Optimize Food Advertising Option 1: Food advertising If foods and beverages are sold or provided on a daily basis by (or under contract with) the project owner, the following requirements are met: • Sugar-sweetened beverages are not advertised or promoted • Deep-fried food options are not advertised or promoted • Deep-fried food options are not displayed under heat lamps. Option 2: Nutritional messaging All dedicated eating areas and points of sale contain at least two different instances of messaging that promote one of the following: • The consumption of fruits and vegetables • The consumption of drinking waterOption 2: Nutritional messaging All dedicated eating areas and points of sale contain at least two different instances of messaging that promote one of the following: • The consumption of fruits and vegetables • The consumption of drinking water If foods and beverages are sold or provided on a daily basis by (or under contract with) the project owner, the following requirements are met: • All standard menu items do not contain more than {{well-unit}}650 Cal|650 kCal{{/well-unit}}, or a version or portion of the standard menu item is available at a smaller size and lower cost for at least 50% of all standard menu items containing more than {{well-unit}}650 Cal|650 kCal{{/well-unit}}. • Where food is self-serve (e.g., buffet), dishware does not exceed the following sizes per occupant type: Letter of Assurance – Owner https://v2.wellcertified.com/wellv2/en/nourish ment/feature/4 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Letter of Assurance – Owner https://v2.wellcertified.com/wellv2/en/nourish ment/feature/6 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Annotated Documents: => Architectural Drawing => Policy Document https://v2.wellcertified.com/wellv2/en/nourish ment/feature/8 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Annotated Documents: => Policy Document https://v2.wellcertified.com/wellv2/en/nourish ment/feature/9 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Annotated Documents: => Letter of Assurance – Owner https://v2.wellcertified.com/wellv2/en/nourish ment/feature/9 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Letter Of Assurances: => Owner https://v2.wellcertified.com/wellv2/en/nourish ment/feature/10 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Annotated Documents: => Annotated Map Letter Of Assurances: => Owner https://v2.wellcertified.com/wellv2/en/nourish ment/feature/13 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual N06.1 Promote Healthy Portions Option 1: Dedicated eating space A dedicated eating space is located within a {{well-unit}}650 ft|200 m{{/well-unit}} walk distance of the project boundary and N08.1 Support Mindful meets the following requirements: Eating • Contains tables and chairs to accommodate at least 25% of regular occupants at peak occupancy. If multiple dedicated eating spaces are present, the combined seating space must accommodate at least 25% of regular occupants at peak occupancy. Meals sold or provided by (or under contract with) the project owner include main dish options that meet each of the following criteria: • Do not contain peanut. N09.1 Accommodate Special • Do not contain gluten. Diets • Do not contain dairy. • Do not contain egg. • Do not contain animal, seafood or dairy products. Foods and beverages sold or provided by (or under contract with) the project owner are clearly labeled at point-of-decision on packaging, menus or signage to indicate if they contain the following common food allergens: • Peanut • Fish • Shellfish N09.2 • Soy Label Food Allergens • Milk • Egg • Wheat • Tree nuts • Gluten The following supportive amenities are provided in a quantity that meets employee demand in at least one dedicated eating area within a {{well-unit}}650 ft|200 m{{/well-unit}} walk distance of the project boundary: • Cold storage. • Countertop surface. N10.1 Provide Meal Support • Sink and amenities for dish and hand washing. • Device for reheating food (e.g., toaster oven, microwave). • Dedicated cabinets or storage units available for employee use. • Reusable, non-plastic plates, bowls, cups and utensils, including spoons, forks and knives. • Cans/bins for garbage, recycling and/or compost. Option 1: Supportive environment The project is located within a {{well-unit}}0.25 mi|400 m{{/well-unit}} walk distance of one of the following: • Supermarket or store with a fresh fruit and vegetable section • Farmers' market that is open at least once a week and operates for at least four months of the year N13.1 Ensure Local Food Option 2: Supportive programming Access One of the following requirements is met: • The project serves as a distribution point for a community-based agriculture program that delivers fruits and vegetables to regular occupants at least twice a month for at least four months of the year • The project hosts the weekly sale of fruits and vegetables (e.g., fruit and vegetable carts or stands, mobile markets) for at 1. MAN Option 1: Supplemental lighting requirements The following requirements are met: • Occupants are provided supplemental lighting, the light fixtures provided increase the light level on the task surface to at least twice the recommended light levels based on the reference used to meet Feature L02: Visual Lighting Design, Part 1. • The supplemental light fixture is positioned to create minimal visual discomfort for the occupant or per manufacturer recommendations for installation. L09.2 Provide Supplemental • The supplemental light fixture is installed at least {{well-unit}}9 in|23 cm{{/well-unit}} from the front edge of the workstation Lighting or other work surface (horizontal distance) or per manufacturer's instructions. Option 2: Supplemental lighting availability The following requirements are met: • Supplemental light fixtures are provided to occupants upon request at no cost. Requests are fulfilled within eight weeks. • At least one supplemental light fixture is available to occupants for trial purposes. Annotated Documents: => Performance Test => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/light/feat To be considered/ implemented in Building Management/ Owner ure/9 Building User Guide or Operational Manual Option 1: Desktop computer monitors All computer monitors can be positioned by the user (monitor height, viewing angle, horizontal distance), through one or more of the following: • Monitors with built-in height and angle adjustment • Monitor stands or arms that allow height, angle and horizontal adjustment Option 2: Laptop computers All laptops meet one of the following requirements: • The laptop is paired with an external keyboard, mouse and stand such that the laptop screen can be positioned by the user (height, viewing angle, horizontal distance) • The laptop is used with an external monitor that meets Option 1 At least 25% of all workstations can be adjusted by the user for both seated and standing work, through one of the following: • Manual or electric height-adjustable work surfaces that provide users with the ability to customize workstation height at both seated and standing positions • Supplemental solutions (e.g., stand) that allow all or part of the work surface, monitor and primary input devices (e.g., keyboard, mouse) to be raised or lowered to seated or standing heights Annotated Documents: => Policy Document Letter Of Assurances: => Owner https://v2.wellcertified.com/wellv2/en/moveme To be considered/ implemented in Architect nt/feature/2 Building User Guide or Operational Manual Annotated Documents: => Policy Document Letter Of Assurances: => Owner https://v2.wellcertified.com/wellv2/en/moveme To be considered/ implemented in Architect nt/feature/2 Building User Guide or Operational Manual All seating at workstations can be adjusted by the user, including the following: • Seat height • Seat depth V02.3 • One additional adjustability requirement: Provide Chair Adjustability • Backrest height and lumbar support • Backrest angle • Armrest height and distance between armrests All workstations in which users are regularly required to stand for 50% or more of their working hours (e.g., assembly line station, hotel check-in counter, supermarket check-out counter) incorporate at least two of the following: V02.4 • Anti-fatigue mats, impact reducing flooring or a similar strategy Provide Support at Standing • Recessed toe space at least {{well-unit}}4 in|10 cm{{/well-unit}} depth and height.13 Workstations • A footrest or footrail • A leaning chair The following requirement is met: • All eligible employees receive an orientation (e.g., in-person training, interactive education, video or smartphone-based V02.5 education with competency verification) to workstations in the space covering, at minimum, the following: Provide Workstation • Ergonomic and adjustability features of a given workstation and their benefits. Orientation • Demonstration on how to make adjustments based on individual needs. • Available resources that can be used for future reference and where to access them. Option 1: Annual testing Conduct ongoing monitoring according to the following requirements: • The dry-bulb temperature, relative humidity, air speed (only for projects that use elevated air speed method) and mean radiant temperature are monitored in regularly occupied spaces at intervals no less than twice a year (including once in June, July or August and once in December, January or February), and results are submitted annually through the WELL digital T01.2 platform. Monitor Thermal Parameters • The number and location of sampling points comply with the requirements outlined in the Performance Verification Guidebook. Option 2: Continuous monitoring The following requirement is met: • Project meets Feature T06: Thermal Comfort Monitoring. A post-occupancy survey is administered at least twice a year, including once in June, July or August and once in December, A post-occupancy survey is administered at least twice a year, including once in June, July or August and once in December, January or February, at least six months after occupancy, which satisfies the following conditions: • All regular occupants are invited to participate in the anonymous survey, and responses are collected from the following number of respondents:<sup>1</sup> T02.1 Survey for Thermal • The survey includes an assessment of overall satisfaction with thermal performance and identification of thermal comfortComfort related issues in accordance with either:1. The sample survey in Appendix T1.2. Any pre-approved survey listed in Part 1: Administer Project Survey in Feature C03: Occupant Survey. • The results of the survey responses comply with one of the target satisfaction thresholds as specified in the table below: Annotated Documents: => Policy Document Letter Of Assurances: => Owner https://v2.wellcertified.com/wellv2/en/moveme To be considered/ implemented in Architect nt/feature/2 Building User Guide or Operational Manual Annotated Documents: => Policy Document Letter Of Assurances: => Owner https://v2.wellcertified.com/wellv2/en/moveme To be considered/ implemented in Architect nt/feature/2 Building User Guide or Operational Manual Annotated Documents: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/moveme To be considered/ implemented in BuildGreen nt/feature/2 Building User Guide or Operational Manual Annotated Documents: => On-going Data Report https://v2.wellcertified.com/wellv2/en/thermal %20comfort/feature/1 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/thermal %20comfort/feature/1 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual Annotated Documents: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/thermal %20comfort/feature/4 To be considered/ implemented in Building Management/ Owner Building User Guide or Operational Manual 1. MAN V02.1 Support Visual Ergonomics 1. MAN V02.2 Provide Height-Adjustable Work Surfaces 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN T04.3 Allow Flexible Dress Code The following requirement is met: • A flexible dress code policy is in place that allows regular occupants to dress for individual thermal preferences 1. MAN 1. MAN 1. MAN X11.2 Select Preferred Cleaning Products X11.1 Improve Cleaning Practices X08.1 Select Materials with Enhanced Chemical Restrictions 1. MAN M01.1 Promote Mental Health and Well-being 1. MAN M01.2 Promote Mental Health Literacy All cleaning, disinfection and sanitization products are specified in the cleaning plan and meet one of the following Annotated Documents: requirements: => Policy and/or Operations Schedule • Products are labeled as ‘low-hazard’ or ‘safer’ by an ISO 14024-compliant (Type 1) Ecolabel or by a third-party certification recognized by the local government where the project is located. Hazard criteria must be specific for the product classes within the scope of this feature. • The Safety Data Sheet (SDS) of each product discloses ingredients per EU Regulation 2015/83 (CLP) or California State Bill No. 25 and no ingredients listed in Section 3 of the SDS are classified as Category 1, 1A or 1B for the following Globally Harmonized Syste (GHS) codes and corresponding hazard statements: • H311 (toxic in contact with skin). • H312 (harmful in contact with skin). • H317 (may cause allergic skin reaction). Individual terpenes may be present up to a concentration of 0.5% in undiluted products. • H334 (may cause allergy or asthma symptoms or breathing difficulties if inhaled). • H340 (may cause genetic defects). • H350 (may cause cancer). • H360 (may damage fertility or the unborn child). • H372 (may causes damage to organs through prolonged or repeated exposure). • Products meet Feature X08 Materials Optimization. https://v2.wellcertified.com/wellv2/en/material To be considered/ implemented in Building Management/ Owner s/feature/11 Building User Guide or Operational Manual The project develops and implements a cleaning plan that meets the following requirements: • Details the following • Extent and frequency of cleaning. • Cleaning responsibilities of building occupants and cleaning staff. • Cleaning supplies available to building occupants and where they can be accessed. • Process to evaluate and document adherence to the cleaning plan. • Identifies the following: • Surfaces that require disinfection (e.g., high-touch surfaces). • Frequency and/or other thresholds (e.g., number of hours, number users of a space, results from a swab test) for disinfection. • Applicable governmental registration and directions of use (e.g., contact time and dilution rates) for disinfectants. • Other non-chemical tools used for disinfection, if any. • States the following documentation procedures • Record keeping practices for cleaning and disinfection activities. • The chain of communications with building occupants. • A system to log feedback from occupants and cleaning staff. • Specifies the following for cleaning materials and personal protection equipment (PPE): • PPE requirements for general cleaning and specialized tasks (e.g., disinfection or dilution or chemicals). • Color-coding for reusable and disposable cleaning cloths. • Separate cleaning of reusable cleaning materials from other clothing or products. • Includes the following precautions for storage of cleaning products: • An identifiable, fit-for-purpose storage space in accordance with the manufacturers’ directions; bleach stored away from other products. • Color-coding and labeling of any bleach-based and ammonia-based products, indicating they are not to be mixed with one another. • Specifies the following for cleaning tools and equipment: • HEPA rated filters for vacuum cleaners • If carpet and woven upholstery are present, the cleaning methodology (based on manufacturer’s recommendations), favoring hot water extraction if technically feasible. • Protocols for cleaning, maintenance and handling of waste accumulated in equipment (e.g., used vacuum cleaner bags). Option 1: Materials selection For at least 25 distinct permanently installed products (including flooring, insulation, wet-applied products, ceiling and wall assemblies and systems) and furniture, the following requirements are met: • Have ingredients inventoried to 100 ppm. • Meet one of the following: • Product is free of compounds listed in the Living Building Challenge’s Red List v.4.0.³ • Product meets the chemical thresholds in the Cradle to Cradle Basic Level Restricted Substances List, version 4 • Product does not contain compounds listed in REACH Restriction, Authorization and SHVC lists. • Product meets an optimization path listed under ‘Advanced Inventory &amp; Assessment’ in Option 2 of LEED v4.1 credit ‘Building Product Disclosure and Optimization - Material Ingredients’ Option 2: Future purchase of compliant products For projects with less than 25 distinct newly and permanently installed products (including flooring, insulation, wet-applied products, ceiling and wall assemblies and systems) and furniture, the following requirement is met: • Products purchased for future repair, renovation or replacement of building materials comply with chemical restrictions of Option 1 ‘Materials Selection’. The following requirements are met: • At least two of the following are available to all employees and students at no cost: • Education or awareness efforts on mental health and well-being, offered quarterly, either in-person or virtually (e.g., webcast on stress management, presentation on mindfulness, email on healthy sleep habits) • Trainings or courses related to mental health and well-being, offered annually, either in-person or virtually (e.g., Mental Health First Aid, stress management training) • Mindfulness or restorative programming, offered weekly, either in-person or virtually (e.g., ongoing access to guided mediation application, weekly yoga classes) • Policy that establishes healthy working hours, outlining the maximum hours to be worked per 24hour and seven-day period • Dedicated space for restoration and relaxation, with an accompanying policy permitting breaks during work or school hours • Annual communication (e.g., email, online module, in-person training) is provided to all regular occupants, and onboarding communications are provided to all new employees, specifically addressing all mental health and well-being benefits, resources and programs available through the project or organization. All employees are offered education and resources that address mental health literacy, including the following: a) Information about mental health and common mental health conditions, including, at minimum: causes, signs and symptoms of stress, depression, anxiety and substance abuse and addiction. b) Strategies for supporting personal mental health and well-being, covering, at minimum: regular self-care practices, positive coping skills, and behaviors that influence mental health and well-being (e.g., sleep, nutrition, physical activity). c) Local mental health organizations, self-help groups and help and crisis lines (call, text and chat). Annotated Documents: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/material To be considered/ implemented in Building Management/ Owner s/feature/11 Building User Guide or Operational Manual Annotated Documents: => Technical Document => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/material To be considered/ implemented in Building Management/ Owner s/feature/8 Building User Guide or Operational Manual Annotated Documents: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/mind/fea To be considered/ implemented in Building Management/ Owner ture/1 Building User Guide or Operational Manual Annotated Documents: => Educational Materials https://v2.wellcertified.com/wellv2/en/mind/fea To be considered/ implemented in BuildGreen ture/1 Building User Guide or Operational Manual 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN The project integrates the following throughout the space, including common circulation routes, shared seating areas and rooms (e.g., conference rooms, common spaces) and workstations (as applicable): • Natural materials, patterns, shapes, colors, images or sounds • At least one of the following: • Plants (e.g., potted plants, plant beds, plant walls) M02.1 Provide Connection to • Water (e.g., fountain) Nature • Nature views (e.g., outdoor views, simulated views) Annotated Documents: => Professional Narrative https://v2.wellcertified.com/wellv2/en/mind/fea To be considered/ implemented in Architect ture/2 Building User Guide or Operational Manual A clinical screening or self-assessment screening tool for common mental health conditions is made available to all employees and students at no cost and meets the following requirements: • Addresses, at minimum, stress, depression, anxiety and substance use. M03.1 Offer Mental Health • Provided confidentially, either in-person or virtually, through a licensed mental health professional, third party Screening organization, online screening or health insurance offering. • Includes directed feedback and/or guidance on interpretation of results and provides next steps for those who screen positive or at-risk Option 1: Substance use policy The following requirement is met: • A policy is in place regarding the use of alcohol and legal, recreational drugs on-site and is clearly communicated to all regular occupants Option 2: Substance use education Trainings (in the form of education seminars, workshops or classes) are offered at least once per year to regular occupants and meet the following requirements: • Address the following topics: M11.1 Offer Substance Use • Management of personal substance use, covering, at minimum, safe substance use habits, signs of dependency or Education addiction and short- and long-term health risks associated with substance misuse or addiction • Prescription opioid education, covering, at minimum, questions to ask at point of prescribing, safe use (e.g., storage, disposal, driving while using) and risks and signs of dependency or addiction • How to appropriately respond to a peer struggling with substance use, covering, at minimum, how to support a peer's recovery efforts and what to do in the case of relapse or a substance use emergency (e.g., withdrawal, overdose) • Provided in-person or virtually; in group or individual settings; through vendors, on-site staff, health insurance plans or programs, community groups or other qualified practitioners or programs (e.g., Mental Health First Aid) Annotated Documents: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/mind/fea To be considered/ implemented in Building Management/ Owner ture/3 Building User Guide or Operational Manual Annotated Documents: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/mind/fea To be considered/ implemented in Building Management/ Owner ture/11 Building User Guide or Operational Manual C01.1 Provide WELL Feature Guide Option 1: WELL feature guide Annotated Documents: A physical or digital WELL feature guide is prominently displayed and/or made widely available to all occupants, meeting the => Policy and/or Operations Schedule following requirements: • Describes the WELL features achieved by the project. • Explains how the WELL features achieved by the project impact occupant health, well-being and comfort and support the project’s health-oriented mission in Part 2: Provide Health-Oriented Mission in Feature C02: Integrative Design. Option 2: Communications The following requirement is met: • Quarterly communications (e.g., emails, modules, trainings) are sent to regular occupants, and onboarding communications are given to new employees (as applicable), about health resources, programs, amenities and policies available to them addressed by the WELL features achieved by the project. Option 1: Stakeholder charrette Early in the planning process, projects facilitate collaborative discussion with key stakeholders, including (as applicable): the owner, manager, facilities management team, architects, engineers, employees, occupants, residents, contractors and community members. The stakeholder discussion must address at minimum the following topics: • Health and well-being goals, including: • Occupant health and well-being needs. • The project’s objectives for health promotion to meet stakeholder needs. • Environmental and sustainability goals, including how the project will: C02.1 Facilitate Stakeholder • Reduce the project’s contribution to global climate change and promote a greener economy Charrette • Protect, enhance and restore water resources and ecosystem services • Promote sustainable material cycles • Enhance community through social equity and environmental justice.<sup>1 </sup> Option 2: Stakeholder orientation The following requirement is met: • Following project completion, tours of the space are made available to new employees during onboarding, and to all stakeholders - including at minimum (as applicable) the owner, manager, facilities management team, architects, engineers, employees, occupants, residents, contractors and community members - that communicate how planned or existing building operations, maintenance, programs and policies will support adherence to WELL. The project integrates design elements that address the following: • Celebration of culture (e.g., culture of occupants, workplace, surrounding community) M02.2 Provide Connection to • Celebration of place (e.g., local architecture, materials, flora, artists) Place • Integration of art • Human delight The project establishes a health-oriented mission that meets the following requirements: • Outlines the project’s objectives for health promotion • Connects supporting and improving occupant health to the organizational objectives or mission statement • Incorporates relevant project goals or strategies established during the stakeholder charrette. • Incorporates the ten WELL concepts: Air, Water, Nourishment, Light, Movement, Thermal Comfort, Sound, Materials, C02.2 Promote HealthMind and Community. Oriented Mission • Health-oriented mission is made available to all occupants and is detailed in the WELL Feature Guide established in Part 1: Provide WELL Feature Guide in Feature C01: Health and Wellness Promotion. https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in BuildGreen ty/feature/1 Building User Guide or Operational Manual Annotated Documents: => Professional Narrative https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in Building Management/ Owner ty/feature/2 Building User Guide or Operational Manual Annotated Documents: => Professional Narrative https://v2.wellcertified.com/wellv2/en/mind/fea To be considered/ implemented in Building Management/ Owner ture/2 Building User Guide or Operational Manual Annotated Documents: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in Building Management/ Owner ty/feature/2 Building User Guide or Operational Manual 1. MAN 1. MAN 1. MAN 1. MAN 1. MAN Option 1: Third-party survey For projects with ten or more eligible employees, the following requirement is met: • A survey is selected from one of the following pre-approved survey providers. More details may be found on IWBI's website (https://v2.wellcertified.com/resources/preapproved-programs). • Occupant Indoor Environmental Quality (IEQ) Survey<sup>TM</sup> from the Center for Built Environment at UC Berkeley. • Building Evaluation Survey Use Studies (BUS) Wellbeing Survey. • Sustainable and Healthy Environments (SHE) survey from the University of Sydney. • Space Performance Evaluation Questionnaire (SPEQ), High Performance Environments Lab (HiPE), University of Oregon. C04.1 Select Project Survey • Leesman Index. • Occupant Comfort &amp; Wellness Survey from the Institute for the Built Environment at Colorado State University. • Comfortmeter. • Healthy Building Index (HBI), from bba indoor environment &amp; DGMR. • Occupant Wellness Survey by Well Living Lab China. Option 2: Custom survey For projects with ten or more eligible employees, the following requirement is met: • A survey is created that covers the topics listed in Appendix C1. C04.2 Administer Survey and Report Results C05.1 Utilize Enhanced Survey Option 1: Survey administration The following requirements are met: • All eligible employees are invited to participate in the survey annually. Regular reminders are sent to eligible employees to complete the survey. • Survey protects all participant-identifying data through appropriate protective measures such as anonymous reporting and safe data storage. Any communication of results should be on an aggregated basis, such that no participant can be identified. • Analysis of responses is conducted by a qualified survey professional. Option 2: Result reporting Annually, the project submits the following through the WELL digital platform: • Project and survey data, including: • Total number of employees invited to complete the survey and number of employees who completed the survey. • Date survey started and finished. • Project location. • Project type. • Level of WELL Certification. • Sociodemographic information (age and gender at minimum). • Aggregated, anonymized survey results. Option 1: Enhanced survey administration For projects with ten or more eligible employees, the following requirements are met: • Meet Feature C04 Part 1 using Option 1. • Address at least one of the topics listed in Appendix C2 through at minimum three additional survey questions by working with one of the parties listed below. More details may be found on IWBI's website (https://v2.wellcertified.com/resources/preapproved-programs). • The pre-approved survey provider selected in Feature C04 Part 1. • BeWellLeadWell. • OHFB-Afriforte. • The Thrive XM Index. Option 2: Result analysis and reporting The project meets the following requirements: • Conduct enhanced analysis beyond descriptive statistics (e.g., correlations, inferential statistics such as multivariate analysis) of survey results. • Annually submit the following through the WELL digital platform: • Aggregated, anonymized survey results for the additional topics selected from Appendix C2. • Results of enhanced analysis. Option 1: Pre-occupancy survey administration The project meets the following requirement: • Administer a pre-occupancy survey using one of the following pre-approved survey providers and utilize the same provider in the post-occupancy survey in Feature C04 Part 1: • Occupant Indoor Environmental Quality (IEQ) Survey<sup>TM</sup> from the Center for Built Environment at UC Berkeley. C05.2 Utilize Pre- and Post• Building Evaluation Survey Use Studies (BUS) Wellbeing Survey. Occupancy Survey • Sustainable and Healthy Environments (SHE) survey from the University of Sydney. • Space Performance Evaluation Questionnaire (SPEQ), High Performance Environments Lab (HiPE), University of Oregon. • Leesman Index. • Occupant Comfort &amp; Wellness Survey from the Institute for the Built Environment at Colorado State University. • Comfortmeter. The project creates and implements a plan that addresses the following: C05.3 Implement Action • Aspirational satisfaction thresholds for post-occupancy survey responses. Plan • Strategies for improving unmet satisfaction thresholds. Annotated Documents: => Professional Narrative => Technical Document https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in BuildGreen ty/feature/4 Building User Guide or Operational Manual Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in Building Management/ Owner ty/feature/4 Building User Guide or Operational Manual Annotated Documents: => On-going Data Report => Technical Document https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in BuildGreen ty/feature/5 Building User Guide or Operational Manual Annotated Documents: => On-going Data Report => Technical Document https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in BuildGreen ty/feature/5 Building User Guide or Operational Manual Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in Building Management/ Owner ty/feature/5 Building User Guide or Operational Manual 1. MAN 1. MAN 1. MAN 1. MAN C07.1 Promote Culture of Health C07.2 Establish Health Promotion Leader W08.1 Provide Bathroom and Handwashing Accommodations C03.1 Develop Emergency Preparedness Plan Option 1: Health promotion strategies Annotated Documents: Occupant health and well-being is promoted through the following: => Policy and/or Operations Schedule • Monthly digital communications to employees and/or regular occupants (as applicable) that address the following: • Reinforce the project’s culture of health. • Market health promotion policies and programs. • Highlight stories from regular occupants (as applicable) who exemplify the project’s health culture. • Offer education (e.g., tips and resources created by the project or a third party) on at least two topics within the ten WELL concepts • Quarterly education sessions (e.g., workshops, lectures, seminars) that offer instruction on topics within the ten WELL concepts, covering at least two different concepts per year. Option 2: Health promotion coordinators One of the following is present: • Health promotion group that meets at least quarterly, is actively involved in planning and implementing health promotion programs and policies and seeks to cultivate a culture of health in the project • Paid mid- or senior-level employee that plans and implements health promotion programs. Health promotion must be part of their job description, requirements and/or performance expectationsProjects that meet Part 2 Health Promotion Leader automatically fulfill this requirement. https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in Building Management/ Owner ty/feature/7 Building User Guide or Operational Manual The following requirements are met: Annotated Documents: • Project has at least one dedicated executive-level employee whose primary responsibility is to plan and oversee => Policy and/or Operations Schedule strategies that promote the physical, mental and emotional health and well-being of all employees (e.g., Chief Wellness Officer). The individual must be employed at the executive (C-Suite) level or report directly to a member of the executive (CSuite) team. • Executive-level employee’s job description and performance expectations must include the following: • Established metrics or KPIs for promoting organizational health and well-being that are linked to employee’s performance evaluation. • At minimum annual reports by the employee on the progress of health promotion strategies and employee engagement to the executive (C-suite) team, Board of Directors and/or equivalent high-level stakeholders. • Executive-level employee is supported by at minimum one employee who helps plan and implement health promotion programs and policies. https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in Building Management/ Owner ty/feature/7 Building User Guide or Operational Manual Option 1: Bathroom Accommodations The following requirements are met: • All bathrooms meet the following requirements: • Provide trash receptacles in stalls (in women’s and single-user bathrooms). If toilet paper cannot be flushed down toilets, trash receptacles must be placed in all bathroom stalls. • Provide sanitary pads, tampons and/or other menstrual products at no cost or subsidized by at least 50% (in women’s and single-user bathrooms). • Provide a hook, shelf or equivalent storage support in each toilet stall. • All occupants have access to at least one bathroom per floor that provides an accessible stall. • All occupants have access to at least one bathroom per floor that provides an infant changing table. • All regular occupants may request a syringe drop box at no cost, which the project places in one or more bathrooms based on occupant demand • All single-user bathrooms (if present) are open to all individuals with accompanying signage and at minimum one singleuser bathroom per floor (if present) meets the room and stall dimensions required by local accessibility code. • Floor drains are equipped with a self-primed liquid-seal trap Option 2: Family bathrooms For projects where the majority of occupants are visitors (e.g., shopping malls, airports, museums), family bathrooms are provided that meet the following requirements: • Accommodate expected demand by individuals in need of accompaniment or assistance in the bathroom (e.g., children, individuals with mental or physical disabilities) • Contain the following accommodations: • Changing table for infants. • Children’s toilet facilities or accommodations for child use of adult size toilet. • Children’s sinks or accommodations for child use of adult size sink (e.g., availability of stepstool). • Motion sensor lights. • Skid resistant floors. • Safety grab bars. • At least one designated location for bags (e.g., hook, shelf separate from changing table and sink). Option 3: Handwashing support The project provides, at minimum, the following in all sinks where handwashing is expected (e.g., bathrooms, break rooms and wellness rooms): The following requirements are met: • A risk assessment is undertaken to address at minimum the following: • Identify project assets (e.g., employees, facilities). • Establish a pathway for occupants or groups who may be more vulnerable (e.g., older adults, people with disabilities, pregnant women, children) to confidentially identify specific needs they may have during an emergency • Evaluate potential impacts of relevant hazards and identify high-risk hazards. • Determine emergency management planning priorities. • An emergency management plan is in place outlining response in the case of emergency situations within the building or surrounding community, addressing at minimum the following hazards: • Natural (e.g., flood, tsunami, wildfire, earthquake, heatwave). • Fire. • Health (e.g., acute medical emergency, infectious disease pandemic). • Technological (e.g., power loss, chemical spill, explosion). • Human-caused (e.g., civil unrest, active shooter, terrorism). • The emergency management plan meets the following requirements: • Incorporates annual (at minimum) inventory and maintenance of building emergency response resources (e.g., first aid Letter Of Assurances: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/water/fe To be considered/ implemented in Architect ature/8 Building User Guide or Operational Manual Annotated Documents: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/communi To be considered/ implemented in Building Management/ Owner ty/feature/3 Building User Guide or Operational Manual 1. MAN 2. HEA 2. HEA 2. HEA 2. HEA I03.1 Offer WELL Educational Tours A01.5 Monitor Air Parameters https://v2.wellcertified.com/wellv2/en/innovatio To be considered/ implemented in BuildGreen n/feature/3 Building User Guide or Operational Manual Information about the air quality measured in Part 1 of this feature is made available to occupants as follows: Annotated Documents: • Data are presented through one of the following: => Letter of Assurance – Owner • Display screens prominently positioned at a height of {{well-unit}}3.6–5.6 ft|1.1–1.7 m{{/well-unit}} with at least one display per {{well-unit}}3500 f|325 {{/well-unit}} of regularly occupied space. • Hosted on a website or phone application accessible to occupants. Signs are present indicating where the data may be accessed at a density of at least one sign per {{well-unit}}3500 f|325 {{/well-unit}} of regularly occupied space. • Data presented include one of the following: • Concentrations of the parameters measured. • Qualitative results of air quality (e.g., colored-coded levels). https://v2.wellcertified.com/wellv2/en/air/featur To be considered/ implemented in Building Management/ Owner e/8 Building User Guide or Operational Manual A01. Fundamental Air Quality To be considered/ implemented in Building Management/ Owner https://v2.wellcertified.com/v2.4/en/air/feature/ Building User Guide or 1 Operational Manual A08.2 Promote Air Quality Awareness Option 1: Water quality pre-test Annotated Documents: For first-time registered projects, the following requirements are met: => Technical Document • The project pre-tests water at least one month before Performance Verification for the parameters below: => On-going Data Report • Turbidity. • Coliforms. • pH. • Total Dissolved Solids (TDS). • Total Chlorine. • Residual (free) chlorine. • Arsenic. • Lead. • Copper. • Nitrate • Benzene. • Sampling occurs at the following locations (with filters or other water treatment devices removed, if present): W05.1 Assess and Maintain • The water dispenser that is closest to the pipe that delivers water into the project. Drinking Water Quality • For projects with more than two floors, a drinking water dispenser on the highest floor and the drinking water dispenser located farthest from the location in requirement b(1) above to which the project has access. • For projects of 12 or more floors, one additional drinking water dispenser for every 10 floors. Option 2: Water quality monitoring The following requirements are met: • Piped water is delivered to drinking water dispensers. • Water is tested quarterly in drinking water dispensers and meets the following thresholds. If any sample exceeds these thresholds, remediation and re-testing occur within a month: • Turbidity is 1.0 NTU, FTU or FNU or less. • pH is between 6.5 and 9.0 (between 5.5 and 9 if a reverse osmosis system is installed at the point of use). • Total Dissolved Solids (TDS) are 500 mg/L or less. • Total Chlorine is 5 mg/L or less. • Residual (free) Chlorine is 5 mg/L or less. • Total Coliforms are not detected in a 100 ml sample. Testing is required only if residual chlorine is not detected. • Lead is 10 mg/L or less. Sampling frequency can be reduced to once per year if results are below detection limits in The following information is prominently displayed near sources of drinking water (or on a website available to occupants): Annotated Documents: • Water quality results from the most recent sampling, including date of testing and compliance with WELL thresholds. => Policy and/or Operations Schedule W05.2 Promote Drinking • If filters or other treatment units are in use, information about the treatment technologies and most recent date of device Water Transparency maintenance and/or filter cartridge replacement. 2. HEA L01.2 Promote Lighting Education 2. HEA WELLBEING 2. HEA The project provides free, public tours of the WELL Certified space. Tours are offered on a pre-determined schedule or upon request and meet the following requirements: • Offered at least six times per year. • Attended by at least 50 people per year. • Listed in the public directory of tours for WELL Certified spaces. • Include at least one destination per WELL concept. • Advertised through at least one publicly accessible channel (e.g., project website, signage, social media). The following requirements are met: Annotated Documents: • The pollutants listed in Parts 1-3 of this feature are monitored in regularly occupied spaces at intervals no longer than once => Operations Schedule per year, and the results are submitted annually through the WELL digital platform. • The number and location of sampling points for on-going monitoring complies with the requirements outlined in the Performance Verification Guidebook. Hea 01 Prerequisite https://v2.wellcertified.com/v2.4/en/water/featu To be considered/ implemented in Building Management/ Owner re/5 Building User Guide or Operational Manual https://v2.wellcertified.com/v2.4/en/water/featu To be considered/ implemented in re/5 Building User Guide or Operational Manual Projects provide educational resources on circadian rhythm, sleep hygiene, age-related increase in light requirements and/or Annotated Documents: importance of daylight exposure on circadian and mental health that meet at least two of the following requirements: => Educational Materials a) Educational signage is placed at high traffic points around the space. b) Newsletters or newsletter entries are issued to all occupants at least every quarter. c) At least two of the resources provided for Part 2: Health and Wellness Education of Feature C01: Health and Wellness Awareness cover information on circadian rhythm, sleep hygiene, age-related increase in light requirements and/or importance of daylight exposure to circadian and mental health. L01. Light Exposure and Education To be considered/ implemented in Architect https://v2.wellcertified.com/v2.4/en/light/featur Building User Guide or e/1 Operational Manual 1 All fluorescent and compact fluorescent lamps are fitted with high frequency ballasts. Hea 01 Visual Comfort https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_01_nc.htm%3 FTocPath%3D6.0%2520Health%2520and%2 520Wellbeing%7C_____1 A letter to confirm that all fluorescent and compact fluorescent lamps are fitted with high frequency ballasts. MEP Designer 2. HEA 2. HEA 2. HEA Hea 01 external lighting levels, zoning and control L01.1 Provide Indoor Light L02.1 Provide Visual Acuity 7Internal lighting in all relevant areas of the building is designed to provide an illuminance (lux) level appropriate to the tasks undertaken, accounting for building user concentration and comfort levels. This can be demonstrated through a lighting design strategy that provides illuminance levels in accordance with national best practice lighting guides (see CN3.10). 8The uniformity of illuminance due to electric lighting is as per the recommendation in the approved local standard. 9For areas where computer screens are regularly used, confirmation is required that the lighting has been designed to limit the potential for glare in accordance with a numerical glare limit specified within national best practice lighting guides . These should include: 9.aLimits to the luminance of the luminaires to avoid screen reflections. Manufacturers' data for the luminaires should be sought to confirm this 9.bFor uplighting, the recommendations refer to the luminance of the lit ceiling rather than the luminaire; a design team calculation is usually required to demonstrate this 9.cRecommendations for direct lighting, ceiling illuminance, and average wall illuminance. 10All external lighting located within the construction zone is designed to provide illuminance levels that enable users to perform outdoor visual tasks efficiently and accurately, especially during the night. To demonstrate this, external lighting provided is specified in accordance with EN 13201 series Road Lighting and EN 12464-2:2014 Light and lighting - Lighting of work places - Part 2: Outdoor work places. A letter to confirm that all external lighting located within the construction zone is designed to provide illuminance levels that enable users to perform outdoor visual tasks efficiently and accurately, especially during the night. Design drawings. Hea 01 Visual Comfort https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_01_nc.htm%3 FTocPath%3D6.0%2520Health%2520and%2 520Wellbeing%7C_____1 MEP Designer Option 1: Daylight simulation Annotated Documents: The project demonstrates, through computer simulations, that one of the following conditions are achieved: => Technical Document • Regularly occupied spaces achieve one of the following targets: • Common spaces that have unassigned seating for at least 15% of regular occupants at any given time achieve one of the following targets: Option 2: Interior layout One of the following requirements is met: • At least 30% of the regularly occupied area is within a {{well-unit}}20 ft|6 m{{/well-unit}} horizontal distance of envelope glazing in each floor and/or in each individual unit. • Common spaces have unassigned seating and can accommodate at least 15% of regular occupants at any given time. At least 70% of all seating in the spaces is within a {{well-unit}}16 ft|5 m{{/well-unit}} horizontal distance of envelope glazing. Option 3: Building design One of the following requirements is met: • The envelope glazing area is no less than 7% of the floor area for each floor level or individual unit. • The floor plate is no more than {{well-unit}}65 ft|20 m{{/well-unit}} between opposite walls that each have transparent envelope glazing, and there are no opaque obstructions higher than {{well-unit}}3.2 ft|1 m{{/well-unit}} within a {{well-unit}}20 ft|6 m{{/well-unit}} horizontal distance of the transparent envelope glazing. Option 4: Circadian lighting design The following requirement is met: • The project achieves at least one point in Feature L03: Circadian Lighting Design. https://v2.wellcertified.com/wellv2/en/light/feat ure/1 MEP Designer Option 1: Visual lighting design On-Site Assessment: The following requirements are met: => Technical Document • All indoor and outdoor spaces (including transition areas) comply with the illuminance thresholds specified in one of the => Letter of Assurance – Owner following lighting reference guidelines: 1. IES Lighting Handbook 10<sup>th</sup> Edition.³ 2. EN 12464-1: 2011 3. ISO 8995-1:2002(E) (CIE S 008/E:2001) 4. GB50034-2013 5. CIBSE SLL Code for Lighting • The illuminance thresholds take into consideration the tasks and the age groups of the occupants. Option 2: Predetermined light levels The following requirements are met: • More than 50% of the occupants are under the age of 65. • At least 90% of the project area is comprised of the following space types and meets the associated illuminance thresholds: • Offices and classrooms: minimum {{well-unit}}30 fc|320 lux{{/well-unit}} at task surface • Lobby, atrium and transition (including corridor and outdoor pathways): minimum {{well-unit}}10 fc|110 lux{{/well-unit}} at floor level • Storage spaces: minimum {{well-unit}}10 fc|110 lux{{/well-unit}} at floor level • Dining, Lounge and Restrooms: minimum {{well-unit}}10 fc|110 lux{{/well-unit}} at task surface https://v2.wellcertified.com/wellv2/en/light/feat ure/2 MEP Designer 2. HEA L04.1 Manage Glare from Electric Lighting 2. HEA L07.1 Balance Visual Lighting 2. HEA L07.1 / 1 Points Ensure Color Rendering Quality 2. HEA L07.2 / 1 Points Manage Flicker 2. HEA L06.1 Conduct Daylight Simulation 2. HEA L05.2 Integrate Solar Shading 2. HEA Hea 02 Ventilation 2. HEA A02.1 Prohibit Indoor Smoking 2. HEA A02.2 Prohibit Outdoor Smoking Option 1: Luminaire considerations Each luminaire meets one of the following requirements for regularly occupied spaces at light output representative of regular use conditions. Wall wash fixtures and concealed fixtures, installed as specified by manufacturer’s data, as well as decorative fixtures may be excluded from meeting these requirements: • 100% of light is emitted above the horizontal plane. • Classified with Unified Glare Rating (UGR) of 16 or lower. • Luminance that does not exceed 6,000 cd/ at any angle between 45 and 90 degrees from nadir. Option 2: Space considerations The following requirement is met in all regularly occupied spaces: • Unified Glare Rating (UGR) of 16 or lower. Option 1: Parameters for visual balance Ambient lighting in all regularly occupied spaces meets at least three of the following requirements: • Horizontal and vertical luminance contrast ratios for an ambient light system is no more than 10 between adjacent independently controlled zones. • Illuminance uniformity ratio of at least 1:2.5 (lowest light level: average light level) or 1:2.5 (average light level/minimum light level) is achieved on any horizontal task plane within a space. • Automatic changes in lighting characteristics, such as light levels, changes in color and distribution take place over a period of 10 minutes. • The Corelated Color Temperature (CCT) in each room for similar fixtures is consistent (±200 K) at any point of time. Option 2: Design for visual balance Lighting is designed by a lighting professional and takes into account the following considerations: • Luminance ratios on vertical and horizontal adjacent zones. • Illuminance uniformity on horizontal task planes. • Changes in lighting characteristics, such as light levels, changes in color and distribution. • Color temperature of lights used. All luminaires (except decorative fixtures, emergency lights and other special-purpose lighting) meet at least one of the following color rendering requirements. If tunable white lighting is used, the requirements are met at 1,000K intervals from the lower end (with a minimum of 2,700K) to the higher end (with a maximum of 5,000k): • CRI ≥90. • CRI ≥ 80 with R9 ≥ 50. • IES Rf ≥ 78, IES Rg ≥ 100, -1% ≤ IES Rcs,h1 ≤ 15%. All luminaires, in combination with the appropriate controls (except decorative lights, emergency lights and other specialpurpose lighting), used in regularly occupied spaces meet at least one of the following flicker requirements: • Classified as “reduced flicker operation” per California Title 24, when tested according to the requirements in Joint Appendix JA-10 • Recommended practices 1, 2 or 3 as defined by IEEE standard 1789-2015 LED • Pst LM ≤ 1.0 and SVM ≤ 1.6 for indoor applications per NEMA 77-2017<sup>11</sup> Letter Of Assurances: => Technical Document https://v2.wellcertified.com/wellv2/en/light/feat ure/4 MEP Designer Letter Of Assurances: => Professional Narrative https://v2.wellcertified.com/wellv2/en/light/feat ure/7 Architect Letter Of Assurances: => Technical Document https://v2.wellcertified.com/wellv2/en/light/feat ure/7 MEP Designer Letter Of Assurances: => Technical Document https://v2.wellcertified.com/wellv2/en/light/feat ure/7 MEP Designer The project demonstrates, through computer simulations, that the following conditions are achieved: • Regularly occupied spaces achieve one of the following targets: a) Average sDA300,50% is achieved for > 55% of regularly occupied floor area b)Average sDA300,50% is achieved for > 75% of regularly occupied floor area The following requirements are met in regularly occupied spaces: • All vertical transparent envelope glazing has shading that meet one of the following: Letter Of Assurances: => Technical Document https://v2.wellcertified.com/wellv2/en/light/feat ure/6 Architect Annotated Documents: => Policy and/or Operations Schedule https://v2.wellcertified.com/wellv2/en/light/feat ure/5 Architect Hea 02 Indoor Air Quality https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_02.htm%3FTo cPath%3D6.0%2520Health%2520and%2520 Wellbeing%7C_____2 MEP Designer https://v2.wellcertified.com/wellv2/en/air/featur e/2 Building Management/ Owner https://v2.wellcertified.com/wellv2/en/air/featur e/2 Architect The building has been designed to minimise the concentration and recirculation of pollutants in the building as follows: 4 Provide fresh air into the building in accordance with the criteria of the national best practice standard for ventilation. 5 The location of fresh air intakes are designed to minimise the entry of air pollutants into the building, as follows: 5.a In air-conditioned and mixed-mode buildings or spaces: 5.a.i The location of the building's air intakes and exhausts, in relation to each other and external sources of pollution, is designed in accordance with EN 13779:20071 Annex A2 (see CN3 for alternative methods of compliance). 7 Areas of the building subject to large and unpredictable or variable occupancy patterns have carbon dioxide (CO₂) or air quality sensors specified and: 7.a In mechanically ventilated buildings or spaces: sensors are linked to the mechanical ventilation system and provide demand-controlled ventilation to the space 7.b In naturally ventilated buildings or spaces: sensors either have the ability to alert the building owner or manager when CO₂ levels exceed the recommended set point, or are linked to controls with the ability to adjust the quantity of fresh air, i.e. automatic opening windows or roof vents. The following requirement is met: • Smoking and the use of e-cigarettes is prohibited in interior spaces within the project boundary Annotated Documents: => Policy and/or Operations Schedule Smoking and the use of e-cigarettes is prohibited in the following areas, with signage present to clearly communicate the ban: Letter of Assurance – Owner • Outdoors at ground level within {{well-unit}}25 ft|7.5 m{{/well-unit}} (or the maximum extent allowable by local codes) of all entrances, operable windows and building air intakes Signage is present to clearly communicate the ban. In outdoor areas within the project boundary that allow smoking (if any), signs are placed along walkways (not more than {{well-unit}}100 ft|30 m{{/well-unit}} between signs) that describe the hazards of smoking • On decks, patios, balconies, rooftops and other occupiable outdoor areas above ground level. 2. HEA 2. HEA 2. HEA A03.1 Ensure Adequate Ventilation A06.1 Increase Outdoor Air Supply A06.2 Improve Ventilation Effectiveness Option 1: Mechanically ventilated spaces For mechanically ventilated projects, one of the following requirements is met: • Newly installed ventilation systems are designed to meet the supply and exhaust rates set in one or more of the following ventilation guidelines, which must describe ventilation rates for at least 90% of the project area. The ventilation system is scheduled to be tested and balanced after project occupancy: • ASHRAE 62.1-2010 or any more recent versions (Ventilation Rate Procedure or IAQ Procedure) • ASHRAE 62.2-2016 • EN 16798-1 (for Category IV buildings) • AS 1668.2-2012 or any more recent version • CIBSE Guide A: Environmental Design, version 2007 or any more recent version • Existing ventilation systems have been tested and balanced to meet supply and exhaust rates set in one or more ventilation guidelines listed above within the last five years. Option 2: Naturally ventilated spaces For naturally ventilated projects with no mechanical ventilation, the following requirements are met: • One or more of the following design criteria, which must describe ventilation rates for at least 90% of the project area: • Natural Ventilation Procedure in ASHRAE 62.1-2010 or any more recent version • CIBSE AM10: Natural Ventilation in Non-Domestic Buildings (2005 or any more recent version) Section 2.4 – Natural ventilation strategies and Chapter 4 – Design Calculations • AS 1668.4-2012 or any more recent version • Any reference in Option 1, which describes natural ventilation procedures. • Vents and windows used to meet the ventilation requirements in one of the standards mentioned above are permanently open or have controls to prevent their closure during periods of occupancy. (Operable windows not used in ventilation calculations may be user operated.) • Outdoor air meets the following thresholds as an average for the previous year: • PM2.5 less than 15 μg/m³ • PM10 less than 30 μg/m³ Option 3: Naturally ventilated spaces in areas with elevated particulate matter For naturally ventilated projects with no mechanical ventilation, the following requirements are met: • One or more of the following design criteria, which must describe ventilation rates for at least 90% of the project area: • Natural Ventilation Procedure in ASHRAE 62.1-2010 or any more recent version • CIBSE AM10: Natural Ventilation in Non-Domestic Buildings (2005 or any more recent version) Section 2.4 – Natural Option 1: Increased air supply For mechanically ventilated projects, the following requirement is met in all occupiable spaces: • Exceed outdoor air supply rates described in ASHRAE 62.1-2010 by the percentages shown in the table below: Option 2: Demand control ventilation For mechanically ventilated projects, the following requirements are met in at least 90% of regularly occupied spaces: • A demand-controlled ventilation (DCV) system regulates the outdoor air ventilation rate to keep CO2 levels less than the thresholds specified in the table below, at the maximum intended occupancy: • Carbon dioxide is measured at the return air diffusers or in the breathing zone at least {{well-unit}}3.3 ft|1 m{{/well-unit}} away from doors, windows, air supply diffusers or occupants. At least one sensor is used for each occupancy zone (or per air handling unit, if a single zone is served by multiple air handling units). If the occupancy density/pattern/usage is substantially different in two adjacent areas, each area must be considered a separate zone. Option 3: Enhanced natural ventilation For naturally ventilated projects, the following requirement is met: • Implement an engineered natural ventilation system that is sufficient to keep CO2 levels in the breathing zone of all regularly occupied spaces below the specified thresholds at the maximum intended occupancies: Option 1: Displacement ventilation system The project uses a displacement ventilation system in at least 90% of regularly occupied spaces, with one of the following as a basis for design: • ASHRAE Guidelines RP-949 • ASHRAE 62.1-2019, "Stratified Air Distribution Systems (Section 6.2.1.2.1) • REHVA Guidebook No. 01 (Displacement Ventilation in non-industrial premises) Option 2: Personalized ventilation system For at least 50% of workstations, the following requirements are met: • Outdoor air is supplied in the breathing zone, with an airspeed of no greater than {{well-unit}}50 fpm|0.25 m/s{{/well-unit}} at the occupant's head • The return air diffusers are located more than {{well-unit}}9.8 ft|2.8 m{{/well-unit}} above the floor Option 1: Sensor requirements The following requirements are met: • The project deploys monitors that measure at least three of the following parameters: • PM2.5 or PM10 (accuracy 25% at 50 μg/m³). • Carbon dioxide (accuracy 10% at 750 ppm). • Carbon monoxide (accuracy 1 ppm at values between 0 and 10 ppm). • Ozone (accuracy 10 ppb at values between 0 and 100 ppb). • Nitrogen dioxide (accuracy 20 ppb at values between 0 and 100 ppb). • Total VOCs (accuracy 25% at 500 μg/m³). • Formaldehyde (accuracy 20 ppb at values between 0 and 100 ppb). • Monitors are sited at locations compliant with relevant parameters in the Performance Verification Guidebook. Monitor density is at least one sensor per {{well-unit}}3500 f|325 {{/well-unit}}. • Measurements are taken at intervals of no longer than 10 minutes for carbon dioxide and no longer than one hour for other pollutants. Option 2: Reporting & maintenance The following requirements are met: • Data are submitted annually through the WELL digital platform. • Monitors are recalibrated or replaced annually, and projects submit documentation attesting to their calibration or replacement annually through the WELL digital platform. Letter Of Assurances: =>Letter of Assurance – Engineer =>technical document https://v2.wellcertified.com/wellv2/en/air/featur e/3 MEP Designer Letter Of Assurances: =>Letter of Assurance – Engineer =>technical document https://v2.wellcertified.com/wellv2/en/air/featur e/6 MEP Designer Letter Of Assurances: => MEP https://v2.wellcertified.com/wellv2/en/air/featur e/6 MEP Designer Annotated Documents: => On-going Data Report https://v2.wellcertified.com/wellv2/en/air/featur e/8 MEP Designer https://v2.wellcertified.com/wellv2/en/air/featur e/11 MEP Designer 2. HEA A08.1 Install Indoor Air Monitors 2. HEA For all bathrooms, kitchens, rooms for cleaning and chemical storage, rooms with high-volume printers and copiers and high- Annotated Documents: humidity areas, the following requirements are met: => Technical Document A11.1 Manage Pollution and • Meet one of the following: Exhaust • Are separated from all adjacent regularly occupied spaces with self-closing doors and/or vestibules. • Are negatively pressurized compared with adjacent regularly occupied spaces. • Utilize exhaust fans such that the return air is vented outdoors and not recirculated 2. HEA 2. HEA 2. HEA 2. HEA 2. HEA 2. HEA 2. HEA 2. HEA Mechanically and Mixed-mode ventilated spaces The following requirement is met: a) Media filters are used in the ventilation system to filter outdoor air supplied to the space in accordance with thresholds specified in the table below: Annual Average Outdoor PM2.5 Threshold Minimum Air Filtration Level 16 μg/m³ or less MERV 8 or G4 17–18 μg/m³ MERV 10 or M5 19–23 μg/m³ MERV 12 or M6 A12.1 / 1 Points 24–39 μg/m³ MERV 14 or F8 Implement Particle Filtration 40–59 μg/m³ MERV 16 or E10 60 μg/m³ or greater MERV 16 preceded by MERV 8, or E10 preceded by G4 b) Filter is equipped with on-board pressure sensors or filter change indicator that signal when filter requires replacement. Evidence that the filter has been replaced according to manufacturer's recommendation is submitted annually through WELL Online. Option 2: Filter maintenance The following requirement is met: • Evidence that the filter has been replaced according to the manufacturer's recommendation is submitted annually through the WELL digital platform. The following requirement is met: • Project meets one of the below: • At least 75% of the regularly occupied spaces have operable windows that provide access to outdoor air A07.1 / 1 Points • For each floor, the openable window area is at least 4% of the net occupiable floor area Provide Operable Windows Hea 04 Thermal modelling T03.1 Provide Thermostat Control 1 Thermal modelling (or an analytical measurement or evaluation of the thermal comfort levels of the building) has been carried out using the predicted mean vote (PMV) and predicted percentage of dissatisfied (PPD) indices in accordance with ISO 7730:20051 taking full account of seasonal variations. 2 Local thermal comfort criteria have been used to determine the level of thermal comfort in the building, in particular internal winter and summer temperature ranges will be in line with the recommended comfort criteria within ISO 7730:2005, with no areas falling within the levels defined as representing local dissatisfaction. 3 Thermal comfort levels in occupied spaces meet the Category B requirements set out in Table A.1 of Annex A of ISO 7730:2005. During all standard occupied hours of the year, all regularly occupied spaces achieve thermal conditions representing Predicted Mean Vote (PMV) levels within +/- 0.5; PPD ≤ 10% (as per ASHRAE 55-2013, ISO 7730:2005 or EN 15251:2007). Annotated Documents: => On-going Data Report Letter Of Assurances: => MEP https://v2.wellcertified.com/wellv2/en/air/featur e/12 MEP Designer Letter Of Assurances: => Architect https://v2.wellcertified.com/wellv2/en/air/featur e/7 Architect A letter to confirm that you have used an analytical measurement and evaluation of the thermal comfort levels of the building using PMV and PPD indices in accordance with: EN ISO 7730:2005 Ergonomics of the thermal environment Technical HVAC Memo Technical thermostat sheets Plan with the location of thermostats Hea 04 Thermal comfort https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_04.htm%3FTo cPath%3D6.0%2520Health%2520and%2520 Wellbeing%7C_____4 BuildGreen https://v2.wellcertified.com/wellv2/en/thermal %20comfort/feature/3 MEP Designer Annotated Documents: => On-going Data Report => Policy Document Letter Of Assurances: => MEP https://v2.wellcertified.com/wellv2/en/thermal %20comfort/feature/6 MEP Designer Letter to confirm that the acoustician was appointed Hea 05 Acoustic performance https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_05.htm%3FTo cPath%3D6.0%2520Health%2520and%2520 Wellbeing%7C_____5 BuildGreen Hea 05 Acoustic performance https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_05.htm%3FTo cPath%3D6.0%2520Health%2520and%2520 Wellbeing%7C_____5 BuildGreen https://v2.wellcertified.com/wellv2/en/sound/fe ature/1 MEP Designer The following requirements are met for at least 90% of regularly occupied spaces: Letter Of Assurances: • Control over temperature in the space is available through either: 1. Thermostats present within the thermal zone. 2. A => MEP digital interface accessible to occupants on a computer or phone. • The maximum size of each thermal zone is {{well-unit}}650 ft²|60 m²{{/well-unit}} or 10 occupants, whichever is larger. • Projects earn points based on the number of thermal zones: • Temperature sensors are positioned at least {{well-unit}}3.3 ft|1 m{{/well-unit}} away from exterior walls, windows and doors, direct sunlight, air supply diffusers, mechanical fans, heaters or any other significant sources of heat or cold. Option 1: Thermal comfort monitors The project monitors dry-bulb temperature and relative humidity, satisfying the following requirements: • Sensors are located in occupiable areas; {{well-unit}}3.6-5.6 ft|1.1-1.7 m{{/well-unit}} above the floor; and at least {{wellunit}}3.3 ft|1 m{{/well-unit}} away from exterior walls, doors, direct sunlight, air supply/exhausts, mechanical fans, heaters or any other significant source of heat or cold. • A minimum of one sensor per {{well-unit}}3,500 f|325 {{/well-unit}} of occupiable floor area. • Measurements are taken at least once every 15 minutes. • Sensors comply with the Device Requirements listed in the WELL Performance Verification Guidebook. T06.1 / 1 Points Option 2: Reporting & maintenance Monitor Thermal The following requirements are met: Environment • Data are submitted annually through the WELL digital platform. • Sensors are recalibrated or replaced at least every three years and certificates attesting their calibration or replacement are submitted every three years through the WELL digital platform. Option 3: Environmental measures display Real-time display of dry-bulb temperature and relative humidity is made available to occupants through one of the following: • Display screens, with at least one screen located in each {{well-unit}}3,500 f|325 {{/well-unit}} zone of regularly occupied space. • A website or mobile application, with at least one sign located in each {{well-unit}}3,500 f|325 {{/well-unit}} zone of regularly occupied space, indicating where the data may be accessed. 1 A suitably qualified acoustician (SQA) (see Relevant definitions) is appointed by the client at the appropriate stage in the procurement process (but no later than completion of outline design) to provide early design advice on: 1.a External sources of noise impacting the chosen site Hea 05 Prerequisite 1.b Site layout and zoning of the building for good acoustics 1.c Acoustic requirements for users with special hearing and communication needs 1.d Acoustic treatment of different zones and façades. 2 All unoccupied spaces comply with the indoor ambient noise level targets as detailed in the more rigorous of criteria 2.a or 2.b: 2.a Indoor ambient noise level targets within national building regulations or other appropriate good practice standards 2.b Where national building regulations or good practice standards do not exist for the building type or do not provide indoor ambient noise targets, the indoor ambient noise levels comply with 'good practice' criteria levels outlined in Table 20 Hea 05 Indoor ambient noise 3 A SQA carries out ambient noise measurements to ensure that the relevant spaces achieve the required levels. Where the measurements identify that spaces do not meet the standards, remedial works are carried out and the measurements and sound insulation repeated to confirm that the levels are achieved prior to handover and occupation. 4. Sound insulation between acoustically sensitive rooms and other occupied areas comply with targets within national regulations or other appropriate good practice standards 5 The source and receive room sound pressure levels from which Dw is determined are measured in accordance with (EN) ISO 140-4:1998 and rated in accordance with (EN) ISO 717-1:1996. Measurements must be based on finished, but unfurnished rooms, accounting for, and to include the effect of, any carpets and acoustically absorbent ceilings specified. The project provides one of the following: • A plan developed by the project team and/or project owner that outlines acoustical solutions and a timeline for implementation with a focus on managing acoustical comfort, background noise, speech privacy, reverberation time and/or S01.2 Provide Acoustic impact noise within the project boundary. Design Plan • A detailed report from a professional in acoustics that describes existing conditions, recommended solutions and measurement results with a focus on managing background noise, speech privacy, reverberation time and/or impact noise within the project boundary. These measurements are not required to adhere to the Performance Verification Guidebook requirements for on-site testing. Annotated Documents: => Architectural Drawing => Professional Narrative 2. HEA 2. HEA The following requirements are met: Annotated Documents: • An annotated document is submitted and made available to occupants showing labeled zones throughout the project floor => Architectural Drawing S01.1 Label Acoustic Zones plan or similar schematic document as follows: • Loud zones: includes areas intended for loud equipment or activities (e.g., mechanical rooms, kitchens, fitness rooms, social spaces, recreational rooms, music rooms) • Quiet zones: includes areas intended for concentration, wellness, rest, study and/or privacy (e.g., restorative spaces, The following is achieved: On-Site Assessment: => Performance Test a) Background noise levels do not exceed the thresholds below: https://v2.wellcertified.com/wellv2/en/sound/fe ature/1 Architect https://v2.wellcertified.com/wellv2/en/sound/fe ature/2 Architect On-Site Assessment: => Performance Test https://v2.wellcertified.com/wellv2/en/sound/fe ature/4 Architect On-Site Assessment: => Performance Test Annotated Documents: => Design Specifications https://v2.wellcertified.com/wellv2/en/sound/fe Main contractor is responsible for Architect ature/3 treshold achievement. A pretesting is recommended Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/sound/fe ature/5 S05.1 Implement Sound Reducing Surfaces Spaces have ceiling finishes that meet the following specifications: a) Ceiling treatment meets the minimum NRC/ αw values described below: Space Type NRC/ αw Open Workspaces Enclosed Offices Dining Spaces 0.7 for at least 75% of available ceiling area Conference Rooms Classrooms 0.7 for at least 50% of available ceiling area a. Design drawings highlighting: i. All existing and proposed noise sensitive buildings local to, and within, the site boundary ii. Proposed sources of noise from the new development iii. Distance (m) from these buildings to the assessed development. b. The acoustician’s report confirming: i. The acoustician’s qualifications and professional status ii. Noise assessment in compliance with ISO 1996:2007 iii. Measurements based on installed and operating plant. iv. Compliance with the Pol 05 assessment criteria Pol 05 Noise Attenuation https://www.breeam.com/BREEAMInt2016Sch emeDocument/#12_pollution/pol05.htm%3FT ocPath%3D13.0%2520Pollution%7C_____5 Pol 05 Reduction of noise pollution 1 Where there are, or will be, no noise-sensitive areas or buildings within an 800m radius of the assessed site. OR 2 Alternatively, where the building does have noise-sensitive areas or buildings within an 800m radius of the site, one credit can be awarded as follows: 2.a Where a noise impact assessment has been carried out and the following noise levels measured or determined in accordance with the ISO 1996 series: 2.a.i Existing background noise levels at the nearest or most exposed noise-sensitive development to the proposed development or at a location where background conditions can be argued to be similar 2.a.ii The noise level resulting from the new noise source (see CN3.1). 3 The noise impact assessment must be carried out by a suitably qualified acoustic consultant holding a recognised acoustic qualification and membership of an appropriate professional body (see Relevant definitions). 4 The noise level from the proposed site or building, as measured in the locality of the nearest or most exposed noisesensitive development, is a difference no greater than +5dB during the day (07:00 to 23:00) and +3dB at night (23:00 to 07:00) compared to the background noise level. S02.1 Limit Background Noise Levels The following is achieved: a) Spaces meet the maximum RT(60) thresholds in the table below: 2. HEA S04.1 Achieve Reverberation Time Thresholds Option 1: Noise isolation class For walls that separate regularly occupied spaces the following requirements are met: • The project meets the following minimum Noise Isolation Class (NIC) or Weighted Difference Level (Dw) for each wall type, as applicable. If an interior wall meets multiple categories listed, use the highest NIC/Dw value listed. 6. MAT 6. MAT 9. POL S03.2 Achieve Sound Isolation at Walls Option 2: Speech privacy For walls that separate regularly occupied spaces the following requirements are met: • The sum of the measured Noise Isolation Class (NIC) or Weighted Difference Level (Dw) combined with the Noise Criteria Rating (NC) or A-weighted Sound Pressure Level (LAeq) within a room achieves the following minimum values, as applicable. If an interior wall meets multiple categories listed, use the highest value listed. Architect BuildGreen will make the report. BuildGreen The project team must provide the input information. To be discussed later in the process 2. HEA 2. HEA 2. HEA 2. HEA 2. HEA 2. HEA 2. HEA Hea 06 Safe access 1 Dedicated cycle lanes are provided which meet the following minimum width dimensions: 1.a Where pedestrian and cycle routes are shared, the minimum total width of the combined path is 3.0m 1.b Where the cycle lane is segregated from both the pedestrian route and carriageway, the minimum width of the cycle path is 2.0m and the pedestrian path is 1.5m 1.c Where the cycle route forms a part of the carriageway, the minimum width of the lane is 1.5m. 2 Dedicated cycle paths provide direct access from the site entrances to any cycle storage provided, without the need to deviate from the cycle path and, if relevant, connect to off-site cycle paths (or other appropriate safe route) where these run adjacent to the development’s site boundary. 3 Footpaths on site provide direct access from the site entrances to the building entrances and connect to public footpaths offsite (where existing), providing practical and convenient access to local transport nodes and other off-site amenities (where existing). 4 Where provided, drop-off areas are designed off, or adjoining, the access road and provide direct access to pedestrian footpaths, therefore avoiding the need for the pedestrian to cross vehicle access routes. 5 Dedicated pedestrian crossings are provided where pedestrian routes cross vehicle access routes, and appropriate traffic calming measures are in place to slow traffic down at these crossing points. 7 The lighting for access roads, pedestrian routes and cycle lanes is compliant with the external lighting criteria defined in Hea 01 Visual comfort, i.e. in accordance with the national best practice road lighting guide. Option 1: Building entry design The following requirements are met: • All regularly used entrances to the building that open to a pedestrian network include an entryway system composed of grilles, grates, slots or rollout mats or removable carpet tiles that are at least the width of the entrance and {{well-unit}}10 ft|3 m{{/well-unit}} long in the primary direction of travel (sum of indoor and outdoor length) • One of the below is in place to slow the movement of air from outdoors to indoors: • Building entry vestibule with two typically closed doorways. A09.1 Design Healthy • Revolving entrance doors. Entryways Option 2: Building entry maintenance Building entryway systems are cleaned, as follows: • Wet-cleaned at least once a week, or as instructed by manufacturer. • Vacuumed at least once a day, or as instructed by manufacturer. Option 3: Outdoor sport areas The following requirement is met: • All facilities adjacent to an outdoor sports field have a staging area that separates the playing field from other internal areas to capture moisture and debris 12 The building is designed to be fit for purpose, appropriate and accessible by all potential users. 13 An access strategy is developed in line with Checklist A3. The access strategy addresses, as a minimum, access to and throughout the development for all users, with particular emphasis on the following: 13.a Disabled users; addressing and proposing design solutions that remove obstacles that define disability Hea 06 Inclusive and 13.b People of different age groups, genders, ethnicity and fitness levels accessible design 13.c Parents with children (where appropriate to building use or type). 14 Facilities are provided for future building occupants and users (see Compliance notes) including, where relevant, facilities that can be shared and are accessible to members of the public or community without gaining uncontrolled access to other parts of the building (unless security processes and procedures prohibit this). 1 All water systems in the building are designed in compliance with the measures outlined in the relevant national health and safety best practice guides or regulations to minimise the risk of microbial contamination, e.g. legionellosis. Hea 09 Building services 2 Where humidification is required, a failsafe humidification system is provided. water systems: Minimising 3 A wholesome supply of accessible potable drinking water is supplied as follows in the permanently staffed areas: risk of contamination 3.a Point-of-use water coolers 3.b Provision in each staff kitchenette, or in a suitable location on each floor level, and in a staff canteen (if provided) Option 1: Legionella plan development The project provides a Legionella management plan that meets the following requirements: • Addresses hot water systems, cooling towers, decorative fountains and any other devices or spaces under control of the project where water is recirculated and aerosolized. • Includes the items listed below:³ • Determination of roles for Legionella management in the building, distinguishing those under project control from those that may be the responsibility of building management or other parties. • Water system inventory and process flow diagrams of systems within the project boundary. • Hazard analysis of water assets within the project boundary. If the project does not operate the building hot water supply system (e.g., boilers, heaters, pumps or hot water risers), then an explanation of the building-wide Legionella W03.1 management policies (if any) and how they influence risk is included. Implement Legionella • A list of monitoring actions for relevant variables (e.g., temperature or residual chlorine), performance limits Management Plan associated with these variables, and corrective actions when variables exceed such limits. • A list of critical control points (locations where actions to maintain relevant variables listed in (4) within performance limits are applied) within the project boundary. • Verification and validation procedures for evaluating the suitability and proper implementation of the management plan. A Legionella sampling schedule is included if projects have operational control over cooling towers and spas. • Protocols for documenting results of monitoring activities and corrective actions. If sampling for Legionella is planned, results are included. Option 2: Legionella plan implementation The following requirement is met: • Project submits annually through the WELL digital platform documentation of monitoring results, corrective actions and Legionella sample results (if any) as stated in the Legionella management plan. Water delivered to the project for human consumption meets the following thresholds: • Aluminum ≤ 0.2 mg/L • Chloride ≤ 250 mg/L • Copper ≤ 1 mg/L • Manganese ≤ 0.05 mg/L. • Iron ≤ 0.3 mg/L W04.1 Meet Thresholds for • Silver≤ 0.1 mg/L Drinking Water Taste • Sodium ≤ 270 mg/L.³ • Sulfate ≤ 250 mg/L • Sulfide ≤ 0.05 mg/L.³ • Zinc ≤5 mg/L • Total Dissolved Solids (TDS) ≤ 500 mg/L • Free Chlorine ≤ 1.25 mg/L Option 1: Water quality pre-test For first-time registered projects, the following requirements are met: W05.1 Assess and Maintain • The project pre-tests water at least one month before Performance Verification for the parameters below: Drinking Water Quality • Turbidity. • Coliforms. • pH. Design drawings (Architectural drawings for exterior- including access on site and offsite access) Letter of confirmation If the cycle storage is located in the basement, - architectural basement plan Hea 06 Accesibility https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_06.htm%3FTo cPath%3D6.0%2520Health%2520and%2520 Wellbeing%7C_____6 Architect Annotated Documents: => Commissioning Report Letter Of Assurances: => Owner https://v2.wellcertified.com/wellv2/en/air/featur e/9 Commissioning Manager Architect Hea 06 Accesibility https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_06.htm%3FTo cPath%3D6.0%2520Health%2520and%2520 Wellbeing%7C_____6 Architect Boiler technical data sheet, cooling towers Letter to confirm that all water systems in the building will be in compliance with the measures outlined in the relevant health and safety best practice guides to prevent legionella . Cold water supply diagram Hot water supply diagram - solar panel source( if exist) Annotated Documents: => Professional Narrative Hea 09 Water Quality https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_09.htm%3FTo cPath%3D6.0%2520Health%2520and%2520 Wellbeing%7C_____9 MEP Designer https://v2.wellcertified.com/wellv2/en/water/fe ature/3 Main Contractor/ Owner On-Site Assessment: => Performance Test https://v2.wellcertified.com/wellv2/en/water/fe Main contractor is responsible for Main Contractor/ Owner ature/4 treshold achievement. A pretesting is recommended Annotated Documents: => On-going Data Report => Technical Document https://v2.wellcertified.com/wellv2/en/water/fe Main contractor is responsible for ature/5 treshold achievement. A pretesting is recommended 2. HEA W05.2 Promote Drinking Water Transparency 2. HEA W06.1 / 1 Points Ensure Drinking Water Access 5. WAT W01.1 Verify Water Quality Indicators 5. WAT 5. WAT 5. WAT The following information is prominently displayed near sources of drinking water (or on a website available to occupants): • Water quality results from the most recent sampling, including date of testing and compliance with WELL thresholds. • If filters or other treatment units are in use, information about the treatment technologies and most recent date of device maintenance and/or filter cartridge replacement. Annotated Documents: => Policy and/or Operations Schedule Option 1: Dispenser availability Annotated Documents: The following requirements are met: => Architectural Drawing • At least one drinking water dispenser (minimum one per floor) is located within a {{well-unit}}100 ft|30 m{{/well-unit}} walk => Operations Schedule distance of all regularly occupied floor area and in all dining areas. • Water delivered by the dispensers is directly piped through the building’s water supply or is stored in containers designed for refilling. • All newly installed drinking water fountains are designed for water bottle-refilling. Option 2: Dispenser maintenance All drinking water dispensers meet the following requirement: • The mouthpieces/outlets, protective guards, aerators (if present), basins and touch points are cleaned on a daily basis. Water delivered to the project and intended for human contact (e.g., drinking, cooking and dishwashing, handwashing, showering or bathing) meets the following thresholds: • Turbidity is less than or equal to 1.0 NTU, FTU or FNU (nephelometric turbidity, formazin turbidity or formazin nephelometric units, respectively). • Coliforms are not detected in any 100 ml sample. The following requirements are met: • The project provides at least one drinking water dispenser, plus one drinking water dispenser per dwelling unit. • All drinking water dispensers provide water that meets the following parameters • Arsenic ≤ 0.01 mg/L. • Cadmium ≤ 0.003 mg/L. • Chromium (total) ≤ 0.05 mg/L. • Copper ≤ 2 mg/L. • Fluoride ≤ 1.5 mg/L. • Lead ≤ 0.01 mg/L. W02.1 Meet Chemical • Mercury (total) ≤ 0.006 mg/L. Thresholds • Nickel ≤ 0.07 mg/L. • Nitrate ≤ 50 mg/L as Nitrate (11 mg/L as Nitrogen). • Nitrite ≤ 3 mg/L as Nitrite (0.9 mg/L as Nitrogen). • Total chlorine ≤ 5 mg/L. • All drinking water dispensers provide water that meets the following parameters: • Residual (free) chlorine does not exceed 4 mg/L.³ • The concentration of total trihalomethanes (TTHM, sum of dibromochloromethane, bromodichloromethane, chloroform and bromoform) is 0.08 mg/L or less.³ • The concentration of haloacetic acids (HAA5, sum of chloroacetic, dichloroacetic, trichloroacetic, bromoacetic and dibromoacetic acids) is 0.06 mg/L or less.³ Option 1: Drinking water quality report The following requirements are met: • A municipal water quality report issued not more than one year before project registration covers at least two of the pesticides below. All reported pesticides comply with the following thresholds • Aldrin and Dieldrin (combined): 0.00003 mg/L or less. • Atrazine: 0.1 mg/L or less. • Carbofuran: 0.007 mg/L or less. • Chlordane: 0.0002 mg/L or less. • 2,4-Dichlorophenoxyacetic acid (2,4-D): 0.03 mg/L or less. • Dichlorodiphenyltrichloroethane (DDT) and metabolites: 0.001 mg/L or less. • Lindane: 0.002 mg/L or less. • Pentachlorophenol (PCP): 0.009 mg/L or less. • A municipal water quality report issued not more than one year before project registration contains concentrations of at least three of the organic contaminants below. All reported organic contaminants comply with the following thresholds W02.2 Meet Thresholds for • Benzene: 0.01 mg/L. Organics and Pesticides • Benzo[a]pyrene: 0.0007 mg/L. • Carbon tetrachloride: 0.004 mg/L. • 1,2-Dichloroethane: 0.03 mg/L. • Tetrachloroethene (Tetrachloroethylene): 0.04 mg/L. • Toluene: 0.7 mg/L. • Trichloroethene: 0.02 mg/L. • 2,4,6-Trichlorophenol: 0.2 mg/L. • Vinyl Chloride: 0.0003 mg/L. • Xylenes (o-, m- and p-): 0.5 mg/L. Option 2: On-site testing The following requirements are met: • All drinking water dispensers provide water that meets thresholds for at least two pesticides and three organic contaminants listed under ‘Drinking Water Quality Report’. • Water is tested by a professional demonstrated not to have a conflict of interest with the WELL project. Option 1: Drinking water quality report The following requirements are met: • The following water parameters are sampled at intervals of no less than once per year: • Turbidity. • pH. • Residual (free) chlorine. W03.1 Monitor Chemical • Total coliforms, only if residual chlorine is below detection limits. and Biological Water Quality • Any other water parameter found at 80% or above its threshold listed in W02 Part 1, as stated in the Final WELL Report or in subsequent annual sampling. Testing occurs only at the locations where parameters were found to be at 80% or above its threshold and testing takes place at least annually until the sample is below 80% of the threshold. • The number and location of sampling points for on-going monitoring complies with the requirements outlined in the Performance Verification Guidebook. • The water quality results are submitted annually through the WELL digital platform. https://v2.wellcertified.com/wellv2/en/water/fe Main contractor is responsible for ature/5 treshold achievement. A pretesting is recommended https://v2.wellcertified.com/wellv2/en/water/fe Main contractor is responsible for Architect ature/6 treshold achievement. A pretesting is recommended On-Site Assessment: => Performance Test https://v2.wellcertified.com/wellv2/en/water/fe Main contractor is responsible for Main Contractor/ Owner ature/1 treshold achievement. A pretesting is recommended On-Site Assessment: => Performance Test https://v2.wellcertified.com/wellv2/en/water/fe Main contractor is responsible for Main Contractor/ Owner ature/2 treshold achievement. A pretesting is recommended Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/water/fe To be considered/ implemented in Building Management/ Owner ature/2 Building User Guide or Operational Manual On-Site Assessment: => On-going Data Report https://v2.wellcertified.com/wellv2/en/water/fe Main contractor is responsible for Main Contractor ature/3 treshold achievement. A pretesting is recommended 2. HEA A01.1 Meet Thresholds for Particulate Matter 2. HEA A01.2 Meet Thresholds for Organic Gases 2. HEA A01.3 Meet Thresholds for Inorganic Gases 2. HEA A01.4 Meet Radon Threshold 2. HEA A01.5 Monitor Air Parameters 2. HEA A05.2 Meet Enhanced Thresholds for Organic Gases 2. HEA A05.3 Meet Enhanced Thresholds for Inorganic Gases 2. HEA 2. HEA 3. ENE Option 1: Acceptable thresholds The following thresholds are met in occupiable spaces: • PM2.5: 15 µg/m³ or lower • PM10: 50 µg/m³ or lower Option 2: Modified thresholds in polluted regions For projects where the annual average outdoor PM2.5 level is 35 µg/m³ or higher, the following thresholds are met: • PM2.5: 25 µg/m³ or lower • PM10: 50 µg/m³ or lower Option 3: Dynamic thresholds in polluted regions For projects where the annual average outdoor PM2.5 level is 35 µg/m³ or higher, the following thresholds are met: • PM2.5 less than or equal to 30% of the 24- or 48-hour average of outdoor levels on the day(s) of performance testing. • PM10 less than or equal to 30% of the 24- or 48-hour average of outdoor levels on the day(s) of performance testing. On-Site Assessment: => Performance Test =>Technical Document https://v2.wellcertified.com/wellv2/en/air/featur Main contractor is responsible for Main Contractor e/1 treshold achievement. A pretesting is recommended Option 1: Laboratory-based VOC tests The following thresholds are met in occupiable spaces: • Benzene (CAS 71-43-2): 10 µg/m³ or lower • Formaldehyde (CAS 50-00-0): 50 µg/m³ or lower • Toluene (CAS 108-88-3): 300 µg/m³ or lower Option 2: VOC monitoring The following requirements are met: • Sensors to measure total VOC at least once per hour (with accuracy 20 μg/m³ + 20% of reading at values between 150 and 2000 μg/m³) are installed with a density of at least one per every {{well-unit}}3,500 f|325 {{/well-unit}}. • Data covering at least the previous one month demonstrate total VOC levels of 500 µg/m³ or lower for at least 90% of regularly occupied hours for all sensors. The following thresholds are met in occupiable spaces: • Carbon monoxide: 10 µg/m³ [9 ppm] or lower • Ozone: 100 µg/m³ [51 ppb] or lower On-Site Assessment: => Performance Test =>Technical Document https://v2.wellcertified.com/wellv2/en/air/featur Main contractor is responsible for Main Contractor e/1 treshold achievement. A pretesting is recommended On-Site Assessment: => Performance Test =>Technical Document https://v2.wellcertified.com/wellv2/en/air/featur Main contractor is responsible for Main Contractor e/1 treshold achievement. A pretesting is recommended For regularly occupied spaces at or below grade, one of the following requirements is met: • The radon is 0.15 Bq/L [4 pCi/L] or lower, as tested by a professional demonstrated not to have a conflict of interest with the WELL project. One test is conducted per {{well-unit}}25,000 f|2300 {{/well-unit}} of regularly occupied space at or below grade. • All regularly occupied spaces at or below grade meet Feature A03, Part 1, Option 1. The following requirements are met: • The pollutants listed in Parts 1-3 of this feature are monitored in regularly occupied spaces at intervals no longer than once per year, and the results are submitted annually through the WELL digital platform. • The number and location of sampling points for on-going monitoring complies with the requirements outlined in the Performance Verification Guidebook. The following thresholds are met in occupiable spaces: • Acetaldehyde: 140 µg/m³ or lower • Acrylonitrile: 5 µg/m³ or lower • Benzene: 3 µg/m³ or lower • Caprolactam: 2.2 µg/m³ or lower • Formaldehyde: 9 µg/m³ or lower • Naphthalene: 9 µg/m³ or lower • Toluene: 300 µg/m³ or lower The following thresholds are met: • Carbon monoxide: 7 mg/m³ [6 ppm] or lower • Nitrogen dioxide: 40 µg/m³ [21 ppb] or lower At least one staircase is open to regular occupants, services all floors of the project and is aesthetically designed through the inclusion of at least two of the following on each floor: • Music • Artwork • Light levels of at least {{well-unit}}215 lux|20fc{{/well-unit}} when in use.7,18 • Windows or skylights that provide access to daylight • Natural design elements (e.g., plants, water features, images of nature) • Gamification Letter of Assurance – Owner Letter of Assurance – Engineer https://v2.wellcertified.com/wellv2/en/air/featur Main contractor is responsible for Main Contractor e/1 treshold achievement. A pretesting is recommended On-Site Assessment: => On-going Data Report https://v2.wellcertified.com/wellv2/en/air/featur Main contractor is responsible for Main Contractor e/1 treshold achievement. A pretesting is recommended On-Site Assessment: => Performance Test https://v2.wellcertified.com/wellv2/en/air/featur Main contractor is responsible for Main Contractor e/5 treshold achievement. A pretesting is recommended On-Site Assessment: => Performance Test https://v2.wellcertified.com/wellv2/en/air/featur Main contractor is responsible for Main Contractor e/5 treshold achievement. A pretesting is recommended https://v2.wellcertified.com/wellv2/en/moveme Recomandation in blue. Team Architect nt/feature/3 may decide to follow any other route Letter Of Assurances: => Owner V03.1 Design Aesthetic Staircases Option 1: Pedestrian-friendly streets At least one functional building entrance opens to a pedestrian network (i.e., streets where pedestrians travel, featuring at minimum sidewalks) and one of the following requirements is met: • The project is located in an area (zip or postal code) with a minimum Walk Score® of 70 • The project is located on a street with restricted vehicular traffic • Within a {{well-unit}}0.25 mi|400 m{{/well-unit}} walk distance of the project boundary, 90% of the total street length has continuous sidewalks present on both sides and two of the following: • At least eight existing use types are present within a {{well-unit}}0.25 mi|400 m{{/well-unit}} walk distance of the project boundary Uses and restrictions are defined in Appendix V1 V05.3 / 2 Points • There are speed limits of {{well-unit}}25 mph|40 kmh{{/well-unit}} or less and buffer protections Select Sites with Pedestrian along sidewalks (e.g., curb extension, bioswales, bike lane, parked cars, benches, trees, planters) Friendly Streets • Street segments intersect one another (excluding alleys) at least every {{well-unit}}260-330 ft|80100 m{{/well-unit}} Option 2: Pedestrian-friendly environment All exterior building walls (excluding alleys) incorporate some combination of the following design elements on the street level façade (i.e., first floor or first {{well-unit}}18 vertical ft|5.5 vertical m{{/well-unit}}, whichever is less): • Windows or glazing that provide transparency into the space • Overhangs such as canopies, awnings, eaves or shades • Murals or other artistic installations • Biophilic design elements (e.g., plants, water features, nature patterns, natural building materials) • Mixed building textures, colors and/or other design elements ENERGY Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/moveme nt/feature/5 BuildGreen Energy performance- Calculate the Energy Performance Ratio for International New Construction (EPRINC). Compare the EPRINC achieved with the benchmarks in Table 26 and award the corresponding number of BREEAM credits. 3. ENE 3. ENE 3. ENE 3. ENE 3. ENE 3. ENE a.As Built mechanical and architectural layouts b.Mechanical equipment technical sheets (where applicable): •Chillers/VRF/Split units/ Heat pumps •Gas boilers •Air Handling Units Ene 01 Use of approved •Cooling towers; dry coolers building energy calculation •Photovoltaic panels; Inverter software •Solar thermal panels c.Envelope elements U value •Exterior walls •Windows and skylights •Roof •Ground floor 1 Energy metering systems are installed that enable at least 90% of the estimated annual energy consumption of each fuel to Technical data: Energy meters; Gas, Thermal energy be assigned to the various end-use categories of energy-consuming systems (see Methodology ). Metering Energy Schemes, Natural Gas Supply, Convection Valves. 2 The energy-consuming systems in buildings with a gross internal area greater than 1,000m² are metered using an Screenshots of the BMS interface with energy consumption monitoring Ene 02 Sub-metering of appropriate energy monitoring and management system. A letter to confirm that will be installed a sub-meters system which will major energy-consuming 3 The systems in smaller buildings are metered either with an energy monitoring and management system or with separate facilitate the monitoring of in-use energy consumption. The system will systems accessible energy sub-meters with pulsed or other open protocol communication outputs, to enable future connection to an facilitate the monitoring of in-use energy consumption by tenant or end energy monitoring and management system (see Relevant definitions ). user. 4 The end energy-consuming uses are identifiable to the building users, for example through labelling or data outputs. 5 An accessible energy monitoring and management system or separate accessible energy sub-meters with pulsed or other open protocol communication outputs to enable future connection to an energy monitoring and management system are provided, covering a significant majority of the energy supply to tenanted areas or, in the case of single occupancy buildings, relevant function areas or departments within the building or unit. Ene 02 Sub-metering of high 5.a In most circumstances, sub-metering should be per floor, or per floor plate where there are multiple service risers, cores, energy load and tenancy or floor plates. areas 5.b It is possible to sub-meter per entire core or service riser, where the number of rooms served by the riser is less than the number of rooms on a typical floor (served by all risers). 5.c In the instance of a number of service risers that each serve a large number of rooms on each floor in high-rise building; sub-metering by ‘floor plate’ which would mean sub-metering each of the risers at each floor is preferable. 1 The building has been designed to operate without the need for external lighting (which includes on the building, signs and Technical Sheets of Exterior Lighting objects at entrances). Technical data sheet of the presence sensor OR alternatively, where the building does have external lighting, one credit can be awarded as follows: Exterior lighting plans 2 The average initial luminous efficacy of the external light fittings within the construction zone is not less than 60 luminaire Confirmation letter that the average initial luminous efficacy of the Ene 03 External lighting lumens per circuit Watt. external light fittings within the construction zone is not less than 60 3 All external light fittings are automatically controlled for prevention of operation during daylight hours and presence luminaire lumens per circuit Watt and All external light fittings are detection in areas of intermittent pedestrian traffic. automatically controlled for prevention of operation during daylight hours and presence detection in areas of intermittent pedestrian traffic. 1 The first credit within issue Hea 04 Thermal comfort has been achieved to demonstrate the building design can deliver Technical data: heat pumps, solar panels, etc. (if there is) appropriate thermal comfort levels in occupied spaces. HVAC Scheme 2 The project team carries out an analysis of the proposed building site during the Concept Design stage and identifies opportunities for the implementation of passive design solutions that reduce building energy demand (see CN3). Ene 04 Passive design 3 The building uses passive design measures to reduce the overall building energy demand, primary energy consumption or analysis CO₂ emissions by at least 5%, in line with the findings of the passive design analysis. 5 The passive design analysis, carried out under criterion 2 , includes an analysis of free cooling and identifies opportunities for the implementation of free cooling solutions. 6 The building is naturally ventilated or uses any combination of the free cooling strategies listed in CN3.1 1.a An analysis of the transport demand and usage patterns for the building has been carried out to determine the optimum A professional report/ study of transport analysis from the lifts number and size of lifts, escalators or moving walks manufacturer which will contain: 1.b The energy consumption has been estimated in accordance with ISO/DIS 25745 Energy performance of lifts, escalators 1. Energy calculation and classification for escalators, at least two types of and moving walks, Part 2: Energy calculation and classification for lifts (elevators) or Part 3: Energy calculation and system (for each transport type required). classification for escalators and moving walks, for one of the following: 2. For each lift, the following three energy efficient features are specified: 1.b.i At least two types of system (for each transport type required); OR a) The lifts operate in a standby condition during off-peak periods. For 1.b.ii An arrangement of systems (e.g. for lifts, hydraulic, traction, machine room-less lift (MRL)); OR example, the power side of the lift controller and other operating 1.b.iii A system strategy which is 'fit for purpose'. equipment such as lift car lighting, user displays and ventilation fans Ene 06 Energy consumption 1.c The use of regenerative drives should be considered, subject to the requirements in CN6 switch off when the lift has been idle for a prescribed length of time; 1.d The transport system with the lowest energy consumption is specified. b) The lift car lighting and display lighting provides an average lamp efficacy (across all fittings in the car) of >55 lamp lumens/circuit Watt c) The lift uses a drive controller capable of variable speed, variablevoltage, and variable-frequency (VVVF) control of the drive motor. 3. Where the use of regenerative drives is demonstrated to save energy, they are specified. 3. ENE Ene 06 Energy efficient features 4. TRA TRANSPORT 4. TRA 3For each lift, the following three energy efficient features are specified: 3.aThe lifts operate in a standby condition during off-peak periods. For example, the power side of the lift controller and other operating equipment such as lift car lighting, user displays and ventilation fans switch off when the lift has been idle for a prescribed length of time 3.bThe lift car lighting and display lighting provides an average lamp efficacy (across all fittings in the car) of >55 lamp lumens/circuit Watt 3.cThe lift uses a drive controller capable of variable speed, variable-voltage, and variable-frequency (VVVF) control of the drive motor. 4Where the use of regenerative drives is demonstrated to save energy, they are specified. Option 3 5 Electric recharging stations have been provided for at least 3% of the total car parking capacity for the building. Tra 03 Alternative modes of 6 The design team can demonstrate electric vehicles using these charging points will have lower CO₂ emissions than their transport petrol or diesel counterparts. Ene 01 Reduction of energy use and carbon BuildGreen will prepare the BuildGreen emissions modelling. The project team must https://www.breeam.com/BREEAMInt2016Sch provide the input information. emeDocument/#06_energy/ene01_nc.htm%3 FTocPath%3D7.0%2520Energy%7C_____1 Ene 02 Energy Monitoring https://www.breeam.com/BREEAMInt2016Sch emeDocument/#06_energy/ene02.htm%3FTo cPath%3D7.0%2520Energy%7C_____2 MEP Designer Ene 02 Energy Monitoring https://www.breeam.com/BREEAMInt2016Sch emeDocument/#06_energy/ene02.htm%3FTo cPath%3D7.0%2520Energy%7C_____2 MEP Designer Ene 03 External lighting https://www.breeam.com/BREEAMInt2016Sch emeDocument/#06_energy/ene03.htm%3FTo cPath%3D7.0%2520Energy%7C_____4 MEP Designer Ene 04 Low carbon design https://www.breeam.com/BREEAMInt2016Sch emeDocument/#06_energy/ene04.htm%3FTo cPath%3D7.0%2520Energy%7C_____5 MEP Designer Ene 06 Energy efficient transportation systems https://www.breeam.com/BREEAMInt2016Sch emeDocument/#06_energy/ene06.htm%3FTo cPath%3D7.0%2520Energy%7C_____7 Owner Technical lifts sheets Ene 06 Energy efficient transportation systems https://www.breeam.com/BREEAMInt2016Sch emeDocument/#06_energy/ene06.htm%3FTo cPath%3D7.0%2520Energy%7C_____7 Owner Technical sheets of electric charge stations A letter to confirm that the electric recharging stations will provide for at least 3% of the total car parking capacity for the building and that the electric vehicles which use the charging points will have lower CO2 emission than the cars which use petrol or diesel; An architectural plan with parking spaces for electric cars Tra 03 Alternative modes of transport https://www.breeam.com/BREEAMInt2016Sch emeDocument/#07_transport/tra03a_nc.htm% 3FTocPath%3D8.0%2520Transport%7C____ _3 Architect 4. TRA V04.1 / 2 Points Provide Bicycle Storage 4. TRA V04.2 Provide Showers, Lockers and Changing Facilities 4. TRA 4. TRA 5. WAT 5. WAT 5. WAT Option 1: Cycling network Letter Of Assurances: One of the following requirements is met: => Architect • The project is located in an area (zip or postal code) with a minimum Bike Score® of 50 • The project is located within a {{well-unit}}650 ft|200 m{{/well-unit}} walk distance of an existing cycling network that connects riders to at least 10 use types that are within a {{well-unit}}3 mi|4.8 km{{/well-unit}} cycling distance of the project boundary Uses and restrictions are defined in Appendix V2 • The project demonstrates existing plans for a cycling network that meets requirements a or b. Option 2: Bike parking The following requirements are met: • Bike parking is provided in the following quantities: • Short-term bike parking (e.g., public bike rack) is located within a {{well-unit}}100 ft|30 m{{/well-unit}} walk distance of a functional building entrance and can accommodate at least 2.5% of peak visitors (minimum of four spaces per building) • Long-term bike parking (e.g., bike room) is available within the project boundary and can accommodate at least 5% of regular occupants, excluding occupants under eight years old (minimum of four spaces per building) • The project provides access to basic bike maintenance tools (e.g., bike pump and patch kit) co-located with long-term bike parking or quarterly on-site bike maintenance services. The following requirements are met: • Showers with changing facilities are available in a quantity listed below within a {{well-unit}}650 ft|200 m{{/well-unit}} walk distance of the project boundary • At least five lockers are available for every shower. Lockers are co-located with shower facilities. The building's car parking capacity is compared to the maximum car parking capacity benchmarks in Table 36 and the relevant number of credits awarded. For most building types, except those where stated, the benchmarks vary according to the building's public transport Tra 04 Car parking capacity Accessibility Index (AI; determined in accordance with BREEAM issue Tra 01 Public transport accessibility). Therefore, for these building types the AI must be determined prior to assessing this issue. This is required to ensure that the building’s car parking capacity is relative to the development's accessibility to the public transport network. At least one of the following outdoor physical activity spaces is within a {{well-unit}}0.25 mi|400 m{{/well-unit}} walk distance of the project boundary and available at no cost to regular occupants: • Green space (e.g., park, walking/biking trail). V08.2 Provide Outdoor • Blue space (e.g., swimming area). Physical Activity Space • Recreational field or court. • Fitness zone that includes all-weather fitness equipment. • For projects with child occupants, play space geared toward children (e.g., playground). WATER 1 An assessment of the efficiency of the building's domestic water-consuming components is undertaken using the BREEAM Wat 01 calculator. 2 The water consumption (L/person/day) for the assessed building is compared against a baseline performance and BREEAM credits awarded based upon Table 38. 3 The efficiency of the following 'domestic-scale' water-consuming components must be included in the assessment (where specified): 3.a WCs 3.b Urinals 3.c Taps (wash hand basins and where specified kitchen taps and waste disposal unit) Wat 01 Water consumption 3.d Showers 3.e Baths 3.f Dishwashers (domestic and commercial-sized) 3.g Washing machines (domestic and commercial or industrial sized). The BREEAM Wat 01 calculator defines the building types and activity areas for which the above components must be assessed. 4 Where a greywater or rainwater system is specified, its yield (L/person/day) is used to offset non-potable water demand from components that would otherwise be supplied using potable water. 5 Any greywater systems must be specified and installed in compliance with the national best practice standard. 1 The specification of a water meter on the mains water supply to each building; this includes instances where water is supplied via a borehole or other private source. 2 Water-consuming plant or building areas, consuming 10% or more of the building's total water demand, are either fitted with easily accessible sub-meters or have water monitoring equipment integral to the plant or area (see Compliance notes). 3 Each meter (main and sub) has a pulsed or other open protocol communication output to enable connection to an Wat 02 Water monitoring appropriate utility monitoring and management system, e.g. a building management system (BMS), for the monitoring of water consumption (see Relevant definitions). 4 If the site on which the building is located has an existing BMS, managed by the same occupier or owner (as the new building), the pulsed or digital water meters for the new building must be connected to the existing BMS (see Relevant definitions). 1 The design team has identified all water demands from uses other than domestic-scale drinking and sanitary use components, e.g. swimming pools, vehicle wash and irrigation equipment (see Relevant definitions). 2 Systems or processes have been identified to reduce the water demand, and demonstrate, through either good practice design or specification, a meaningful reduction in the total water demand of the building.The following are some examples of solutions deemed to satisfy compliance for a number of different building types or functions (where the water demand for that function is one of the significant contributors in the building). 5. WAT Wat 04 Water efficient equipment Drip-fed subsurface irrigation incorporating soil moisture sensors. The irrigation control should be zoned to permit variable irrigation to different planting assemblages. Reclaimed or recovered water from a rainwater collection or waste water recovery system with appropriate storage, i.e. greywater collection from building functions or processes that use potable water, e.g. vehicle wash, sanitary facilities, irrigation etc. External landscaping and planting that relies solely on precipitation, during all seasons of the year. All planting specified is restricted to contextually appropriate species that thrive without irrigation and will continue to do so in those conditions likely as a result of climate change, i.e. typically warmer and drier conditions. https://v2.wellcertified.com/wellv2/en/moveme nt/feature/4 Architect Letter Of Assurances: Technical Document https://v2.wellcertified.com/wellv2/en/moveme nt/feature/4 Architect An architectural site plan with the parking spaces An architectural plan with the parking spaces located in the basement(s) level(s) A letter to confirm the number of building occupants and the number of the car parking capacity Tra 04 Maximum Car Parking Capacity https://www.breeam.com/BREEAMInt2016Sch emeDocument/#07_transport/tra04.htm%3FT ocPath%3D8.0%2520Transport%7C_____5 Architect Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/moveme Recomandation in blue. Team nt/feature/8 may decide to follow any other option. BuildGreen Technical data: washing basin, urinal, toilet, shower, Letter to confirm that through the design is aimed to reduce the consumption of potable water for sanitary use from all sources using water efficient components and that the amount of potable water consumed through taps, urinals, WCS and showers will be lower than the standard specifications demanded by national standards for these types of consumers Wat 01 Water consumption BuildGreen will prepare the report. MEP Designer https://www.breeam.com/BREEAMInt2016Sch The project team must provide the emeDocument/#08_water/wat01_nc.htm%3FT input information. ocPath%3D9.0%2520Water%7C_____1 Cold water supply rising diagram Main water meter technical sheets Letter to confirm that the water meter on the mains water supply will be provided for the building and that the design will include water meters record water consumption for each floor, that no main water consumption plan which uses more than 10% of total water demand of building is provided for the building, that each sub meter has a pulsed output, connected at BMS Wat 02 Water monitoring https://www.breeam.com/BREEAMInt2016Sch emeDocument/#08_water/wat02.htm%3FToc Path%3D9.0%2520Water%7C_____2 MEP Designer To describe the sytems or processes which sanitary designer had identified to reduce the water demand Design drawings (where necessary) e.g.greywater collection from building functions or processes that use potable water, vehicle wash, sanitary facilities, irrigation Manufacturer's product details( where necessary) Wat 04 Water efficient equipment https://www.breeam.com/BREEAMInt2016Sch emeDocument/#08_water/wat04.htm%3FToc Path%3D9.0%2520Water%7C_____4 MEP Designer Flow control devices that regulate the supply of water to each WC area or facility according to demand are installed (and therefore minimise water leaks and wastage from sanitary fittings). 5. WAT 5. WAT Wat 03 Flow control device W07.2 Design Interiors for Moisture Management 5. WAT W08.3 Support Effective Handwashing 6. MAT MATERIALS 6. MAT 6. MAT 6. MAT 6. MAT 6. MAT 6. MAT 6. MAT Mat 01 Life cycle impacts Mat 01 Environmental product declarations (EPD) Mat 03 Prerequisite 1A leak detection system which is capable of detecting a major water leak on the mains water supply within the building and between the building and the utilities' water meter is installed. The leak detection system must be: 1.aA permanent automated water leak detection system that alerts the building occupants to the leak OR an inbuilt automated diagnostic procedure for detecting leaks 1.bActivated when the flow of water passing through the water meter or data logger is at a flow rate above a preset maximum for a preset period of time 1.cAble to identify different flow and therefore leakage rates, e.g. continuous, high or low level, over set time periods 1.dProgrammable to suit the owner's or occupiers' water consumption criteria 1.eWhere applicable, designed to avoid false alarms caused by normal operation of large water-consuming plant such as chillers. Option 1: Condensation and liquid water management The project implements measures to manage moisture in interior spaces that address, at a minimum, the following:³ • Protection of moisture-sensitive building materials and selection of moisture-resistant materials or finishes in surfaces likely to be exposed to liquid water (e.g., finished floors) or that may absorb moisture such as interior sheathing in basements, areas at or below grade, bathrooms, janitorial rooms or kitchens. • Condensation on cold surfaces such as basements, slab-on-grade floors, the inside of exterior walls and glazing. Option 2: Water leak control in fixtures The following requirements are met: • All hard-piped fixtures, such as toilets, dishwashers, icemakers, water treatment devices and clothes washers, have a labeled, readily accessible single-throw manual shut-off (governed or activated per use) or automatic shut-off at point-ofconnection. • All installed water treatment devices have a waste line fixed in-place, equipped with a backflow preventor. All sinks where handwashing is expected (e.g., kitchens, bathrooms, break rooms and wellness rooms), meet the following requirements: • The faucet design prevents the water column from flowing directly into the drain or a sink drain stopper is installed • Water does not splash outside the sink when the faucet is fully open. • Newly installed sinks meet the following design parameters: • The sink basin is at least {{well-unit}}9 inches|23 cm{{/well-unit}} in width and length. • The water column from the sink to the basin is at least {{well-unit}}6 inches|15 cm{{/well-unit}} in length (measured along flow of water, even if at an angle). • The water column is at least {{well-unit}}3 inches|7.5 cm{{/well-unit}} away from any edge of the sink. 1 The project uses a life cycle assessment (LCA) tool to measure the life cycle environmental impact of the building elements. 2 The LCA includes at least the mandatory building elements indicated in the 'Materials assessment scope' section of the BREEAM International Mat 01 calculator (where present in the building). Technical sheets for selenoid valve and sensor Cold water supply rising diagram A letter to confirm that the design is made to reduce the risk of leakage in the water distribution network and is including the installation of shut-off valves in the water supply, the selenoid valves system will be installed on the water supply, to each toilet area in the building Water supply diagram containing the leak detection system for each toilet area Wat 03 Leak Detection https://www.breeam.com/BREEAMInt2016Sch emeDocument/#08_water/wat03.htm%3FToc Path%3D9.0%2520Water%7C_____3 MEP Designer Letter Of Assurances: => MEP https://v2.wellcertified.com/wellv2/en/water/fe ature/7 MEP Designer Letter Of Assurances: => Architect https://v2.wellcertified.com/wellv2/en/water/fe ature/8 Architect • The faucet design prevents the water A letter to confirm that will be used at leat 5 products which are coverd by • Water does not splash outside the sink a verified Environmental Product Declaration(EPD) when the faucet is fully open. The list of quantities of materials used for construction Architecture sections plans BuildGreen will prepare the report. BuildGreen The project team must provide the input information. 5 Where a range of at least five products specified at Design Stage (DS) and installed by Post-Construction Stage (PCS) are EPD (Environmental Product Declaration) Certificate for at least 5 of the • Newly installed sinks meet the following covered by verified EPD (see CN3.2). following categories: design parameters: 1. Timber or timber-based products 2. Concrete or cementitious 3. Metal 4. Stone or aggregate 5. Clay-based 6. Gypsum 7. Glass 8. Plastics, polymers, resins, paint, other chemicals, bituminous 9. Animal fibre, skin, cellulose fibers 10. Other 1 All timber and timber-based products used on the project are Legally harvested and traded timber. Letter to confirm that all the timber and timber-based products used on the • The sink basin is at least {{well-unit}}9 Note: For other construction products there are no prerequisite requirements at this stage. project will be legally harvested and traded timber or have a FSC and inches|23 cm{{/well-unit}} in width and length. COC; FSC certificate for wood (wooden doors, OSB, floating floor) 2 By the end of concept design stage, the client or developer has a documented policy and procedure that sets out procurement requirements for all suppliers and trades to adhere to relating to the responsible sourcing of construction products (see CN3). Mat 03 Sustainable 3 The documented policy and procedure must be disseminated to all relevant internal and external personnel, and included procurement plan within the construction contract to ensure that they are enforceable on the assessed project. 4 The documented policy and procedure must encourage the specification of products with responsible sourcing certification over similar products without certification. 5 The available responsible sourcing credits (refer to Table 42) can be awarded where the applicable construction products (refer to Table 43) are responsibly sourced in accordance with the BREEAM methodology, as defined in the Methodology Mat 03 Responsible sourcing section. of construction products A sustainable procurement plan A confirmation letter that the sustainable procurement plan is disseminated and is included in the construction contract For each material used, need to complete a MAF( Material Approval Form) BES 6001 /FSC/ ISO 14001 certificates for: concrete, reinforcement steel, carpentry + glass (interior and exterior), finishes (false ceiling, raised floor, carpet, sandstone, faience), gypsum board, BCA, brick, bituminous membranes 1 The building incorporates suitable durability and protection measures, or designed features or solutions to prevent damage Architectural building plans and materials used to vulnerable parts of the internal and external building and landscaping elements. This must include, but is not necessarily Exterior plans of the building containing the measures which will be taken limited to: to prevent damage to building elements with markings: kick plates for 1.a Protection from the effects of high pedestrian traffic in main entrances, public areas and thoroughfares (corridors, lifts, doors; entrance mats; durable floor finishes (eg sandstone); door stops; Mat 05 Protecting vulnerable stairs, doors etc.) steel doors; barriers; bolards, etc. parts of the building from 1.b Protection against any internal vehicular or trolley movement within 1m of the internal building fabric in storage, delivery, Interior plans containing the measures which will be taken to prevent damage corridor and kitchen areas damage to building elements with markings: kick plates for doors; 1.c Protection against, or prevention from, any potential vehicular collision where vehicular parking and manoeuvring occurs entrance mats; durable floor finishes (eg sandstone); door stops; steel within 1m of the building façade for all car parking areas and within 2m for all delivery areas. doors; barriers; bolards, etc. Confirmation letter 2 The relevant parts of the building incorporate appropriate design and specification measures to limit material degradation Mat 05 Protecting exposed due to environmental factors (see Methodology for the process to assess this criterion). parts of the building from See Table 45 for a list of applicable elements, environmental factors and material degradation effects to consider. material degradation Main Contractor Main Contractor • The water column from the sink to the BuildGreen will provide draft and basin is at least {{well-unit}}6 inches|15 review the final version cm{{/well-unit}} in length (measured along flow of water, even if at an angle). BuildGreen • The water column is at least {{wellunit}}3 inches|7.5 cm{{/well-unit}} away from any edge of the sink. Main Contractor Mat 05 Designing for durability and resilience https://www.breeam.com/BREEAMInt2016Sch emeDocument/#09_material/mat05.htm%3FT ocPath%3D10.0%2520Materials%7C_____5 Architect Mat 05 Designing for durability and resilience https://www.breeam.com/BREEAMInt2016Sch emeDocument/#09_material/mat05.htm%3FT ocPath%3D10.0%2520Materials%7C_____5 Architect 6. MAT 2. HEA 6. MAT 6. MAT 6. MAT 6. MAT Mat 06 Material efficiency Hea 02 Prerequisite X01.2 Restrict Mercury X01.3 Restrict Lead X02.2 Manage Lead Paint Hazards X02.3 Manage Polychlorinated Biphenyl (PCB) Hazards 1 Opportunities have been identified, and appropriate measures investigated and implemented, to optimise the more efficient use of materials in building design, procurement, construction, maintenance and end of life. 2 The above is carried out by the design or construction team in consultation with the relevant parties (see CN3) at each of the following project work stages: 2.aPreparation and Brief 2.bConcept Design 2.cDeveloped Design 2.dTechnical Design 2.eConstruction. 1 Materials containing asbestos are prohibited from being specified and used within the building. A letter to confirm that the design will avoid materials which contain asbestos Technical sheets of the finishes - paint, wood, OSB, carpet, raised floor, floor adhesives, etc. (if the products were selected) The following requirements are met: • Newly installed fluorescent and sodium lamps, if present, meet one of the following: • RoHS restrictions • The following specifications • Newly installed fire alarms, meters, sensors, relays, thermostats and load break switches meet one of the following: • RoHS restrictions • Products contain no more than 0.1% (1000 ppm) of mercury by weight. Option 1: Paints and electronics The following requirements are met: • Newly installed fire alarms, meters, sensors, relays, thermostats and load break switches meet one of the following: • RoHS restrictions • Products contain no more than 0.01% (100 ppm) of lead by weight. • Newly installed paints applied as finishes within the project boundary meet at least one of the following criteria: • Paints have a lead concentration of 100 ppm (0.1%) by weight or below. • Paints have no added lead carbonates and lead sulfates. • Paints are deemed free of lead or with no added lead by an ISO 14024-compliant (Type 1) Ecolabel, or a voluntary third-party certification program recognized by the local government where the project is located. • Paints meet Feature X08: Materials Optimization. Option 2: Drinking water pipes, fittings and solder Pipes, fixtures, fittings and solder newly installed or applied within the project boundary intended for drinking water distribution and delivery meet at least one of the following: • The product is approved for use with drinking water by a local government authority or by a government-authorized certification body. • The product has a weighted wetted average of 0.25% of lead or less, verified by a third party, or is labeled as ANSI/NSF 372-compliant. Option 1: Identify lead paint hazards For existing buildings constructed or renovated before the enactment of laws banning lead-containing paints for use in interior walls, one of the following requirements is met: • If local laws mandate full removal of lead paint before occupancy of the space, project demonstrates that risk has been addressed by providing relevant legal documentation, such as approved certificates of occupancy or remediation reports submitted to relevant authorities. • An on-site investigation of the space to determine the presence of any lead-based hazards in paint, dust and soil is conducted. The investigation must be performed by a certified inspector or a qualified professional where no local regulations apply and address the following: • An inventory of locations of potential sources and sinks of lead-containing materials, where lead-containing paint may be present. • Confirmation of lead hazards through in-situ test results by x-ray fluorescence (XRF) or by laboratory analyses of paint chip and/or surface dusts. Surface dust is considered a hazard if its lead loading is more than {{well-unit}}6.5 µg/f|0.07 mg/{{/well-unit}} of the collection area if sampled from floors or over {{well-unit}}65 µg/f|0.7 mg/{{/well-unit}} for dust on interior window sills Paints having over 0.5% of lead by weight or {{well-unit}}930 µg/f|10,000 mg/{{/well-unit}} of applied area and bare soil containing over 400 ppm of lead by weight are also considered lead hazards Lower thresholds mandated by local regulations prevail for terms of hazard assessment. Option 2: Lead action plan If lead is found in the investigation, a certified inspector (or a qualified professional where no local regulations apply) implements an action plan that contains the following: • Notification of remediation work to occupants and transient populations in the surrounding spaces, and restriction of access to work areas during remediation. • If paints are mechanically removed, measures are taken to minimize the formation and spread of dusts during the remediation process and to ensure adequate respiratory and skin protection for workers. • A re-inspection schedule that includes visual assessments and dust testing, if any lead-containing paints are left in place and are subject to stabilization (i.e., painted over with products to prevent chipping or degradation) or enclosure, at least once every three years. • Post-remediation clearance, confirming that the lead loading in dust is below the levels deemed hazardous. For buildings constructed or last renovated before the institution of any applicable laws banning or restricting PCBs, or buildings undergoing renovation work that disturbs (i.e., partially or fully removing) materials likely to contain PCBs such as caulking, fluorescent light ballasts and capacitors of appliances fabricated before 1980, the following requirements are met: • An inspection strategy for assessing PCB-related risks is implemented and contains the following: • Determination of locations where materials potentially containing PCBs may be disturbed. • If caulk is to be disturbed or removed, analysis of the presumably PCB-containing material following protocols mandated by local laws or, in absence of local laws, by any applicable US EP or ISO testing methods. • If PCBs are found in disturbed materials, an action plan is implemented and contains the following: • Notification of remedial work to relevant authorities and building occupants. • Preventative measures against the spread of PCB-containing dusts and human exposure during remediation activities, including restricting access for those not involved in the work. • Protective measures for workers, including chemical-resistant gloves, clothing protection, goggles and respirators. • Waste handling that minimizes the spread of contaminated debris and safe disposal of PCB-containing waste in locations allowed by applicable local regulations. https://www.breeam.com/BREEAMInt2016Sch emeDocument/#09_material/mat06.htm%3FT ocPath%3D10.0%2520Materials%7C_____6 Architect Hea 02 Indoor Air Quality https://www.breeam.com/BREEAMInt2016Sch emeDocument/#05_health/hea_02.htm%3FTo cPath%3D6.0%2520Health%2520and%2520 Wellbeing%7C_____2 https://v2.wellcertified.com/wellv2/en/material s/feature/1 Architect Letter Of Assurances: => Architect => MEP Technical Document https://v2.wellcertified.com/wellv2/en/material s/feature/1 Architect MEP Designer Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/material s/feature/2 Main Contractor Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/material s/feature/2 Main Contractor Letter Of Assurances: => Architect => MEP =>Restrict Mercury Architect MEP Designer 6. MAT 6. MAT X03.2 Manage Lead Hazards X02.1 Manage Asbestos Hazards 6. MAT X05.1 Select Compliant Interior Furnishings 6. MAT Man 03 Legally harvested and traded timber 6. MAT X05.2 Select Compliant Architectural and Interior Products The project addresses lead hazards through the following: • The top {{well-unit}}0.6 in|1.5 cm{{/well-unit}} layer in all existing outdoor bare soil (outside the building envelope, postconstruction, not covered by grass, vegetation or other landscaping including mulch covered soil) is tested for lead. Each continuous area of bare soil is sampled at least once. If the lead concentration of any sample surpasses 400 ppm by weight then the following is performed: • A second set of samples is taken at {{well-unit}}6 in|15 cm{{/well-unit}}, {{well-unit}}12 in|30 cm{{/well-unit}}, {{wellunit}}18 in|45 cm{{/well-unit}} and {{well-unit}}24 in|60 cm{{/well-unit}} deep • If these samples are above 400 ppm by weight, soil is replaced with soil from another source to the extent of the deepest sample found above this threshold. • Lead in artificial turf fibers is assessed as follows • If lead concentration of synthetic turf fibers is unknown, test a sample of fibers to determine the lead concentration using an EPA, ISO or locally accepted protocol. Option 1: Asbestos risk assessment For existing buildings constructed or last renovated before the enactment of laws banning the installation of asbestoscontaining materials, and for buildings located where there is no local asbestos phase-out regulation, one of the following requirements is met: • Project for which all asbestos has been removed in a prior renovation demonstrates that occupancy of the space is legally allowed. • An investigation of the project space is conducted by an inspector certified under local regulation or a qualified professional with demonstrable experience where no local regulations apply. The investigation must provide the following, at minimum: • A list of locations where presumed asbestos containing materials (PACM) were found. • Confirmation of the presence of asbestos is performed through Polarized Light Microscopy (PLM) or Transmission Electron Microscopy (TEM) testing. The sample number and location follow applicable laws or recommendations of the inspector conducting the assessment. Materials having over 1% of asbestos are considered ACM. If analytical confirmation is not available or possible, all PACM are considered asbestos-containing materials (ACM). Option 2: Asbestos action plan If asbestos-containing materials (ACM) were found per the above, an action plan that contains the following is implemented: • Notification of any works to relevant authorities and persons living, working or transiting in the vicinity of the building or space. • Preventative measures against the formation and spread of asbestos fibers in the air during remedial work. • Measures taken for workers’ protection during remediation activities, including but not limited to skin and respiratory protection. • If ACM are being removed, activities are carried out for proper handling of ACM waste, including: wetting of all removed ACM, care in transportation to prevent crumbling, sealing and leak-tight transportation, proper labeling and final disposal in locations allowed by applicable laws and permits. • Post-remediation clearance forfixtures occupancy confirmation by testing of fibers in air using phase contrast microscopy (PCM) Option 1: Furniture, millwork and At least 50% by cost of newly installed furniture, millwork and fixtures (minimum 10 distinct products), as defined in Appendix X1, meet one of the following requirements: • Textiles (i.e., fabrics including upholstery) and plastics in products contain 100 ppm (0.01%) by weight or less of the below compounds and chemical classes, unless higher amounts are mandated by local codes. For assessing compliance of a product, all pieces of each of the two material categories (textiles, plastics) are grouped together and each material category is assessed independently against the 100 ppm threshold: • Halogenated flame retardants (HFR). • Polyfluoroalkyl substances (PFAS). • Lead. • Cadmium. • Mercury. • Do not contain textiles and plastic. Option 2: Electrical and electronic products All newly installed electrical and electronic products, as specified in Appendix X1, meet the following requirement: • Products are compliant with RoHS restrictions. Annotated Documents: => Professional Narrative https://v2.wellcertified.com/wellv2/en/material s/feature/3 Architect Annotated Documents: => Technical Document https://v2.wellcertified.com/wellv2/en/material s/feature/2 BuildGreen Annotated Documents: => Technical Document Letter of Assurance – Contractor https://v2.wellcertified.com/wellv2/en/material s/feature/5 Architect Man 03 Responsible construction practices https://www.breeam.com/BREEAMInt2016Sch emeDocument/#04_management/man03.htm %3FTocPath%3D5.0%2520Management%7C _____3 https://v2.wellcertified.com/wellv2/en/material s/feature/5 Main Contractor 1 All timber and timber-based products used during the construction process of the project are 'Legally harvested and traded timber' (see Relevant definitions). At least 50% by cost of newly installed products under the classes listed below, as defined by Appendix X1 (minimum 10 distinct products), meet the following requirements, unless higher amounts are mandated by local code: • Flooring products contain 100 ppm (0.01%) by weight or less of the following: • Halogenated flame retardants (HFR). • Polyfluoroalkyl substances (PFAS). • Orthophthalates. • Insulation products, including thermal and acoustic insulation in walls, ceilings, ducts, tubes and pipes, contain 100 ppm (0.01%) by weight or less of halogenated flame retardants (HFR). • Ceiling and wall panels contain 100 ppm (0.01%) by weight or less of the following: • Halogenated flame retardants (HFR). • Orthophthalates. • Plastic plumbing contains 100 ppm (0.01%) by weight or less of orthophthalates. Annotated Documents: => Technical Document Letter of Assurance – Contractor Architect 6. MAT 6. MAT 7. WST 7. WST 7. WST 7. WST 7. WST 8. LE X06.2 Restrict VOC Emissions from Furniture, Architectural and Interior Products Products within one or more categories and corresponding thresholds in Table 1 meet one of the following compliance Annotated Documents: requirements, earning points as shown in Table 2: Table 1:Table 2: => Technical Document • Tested per methods and VOC emission thresholds established in one of the following: Letter of Assurance – Contractor • California Department of Public Health (CDPH) Standard Method v1.2. • AgBB • European Union LCI VOC threshold following EN 16516-1:2018 testing methods. • ANSI/BIFMA e3-2014, sections 7.6.1 or 7.6.2 (Furniture). • Made exclusively with one or a combination of (without organic additives): metal, untreated wood, glass, ceramic or stone. • If custom-made or refurbished, wet-applied and wood-based materials used in fabrication or refurbishing meet the following: • All paints, coatings, sealants and adhesives applied to the product are verified as low-VOC emitting by one of the applicable standards listed in Part 1. • All composite wood panels, including medium-density fiberboard, plywood and particle wood panels meet the ‘Formaldehyde emissions evaluation’ criterium of the ‘Low-Emitting Materials’ credit of the LEED v4.1 standard or meet one of the following: US EPA TSCA Title VI, Europe E1, Japan Four-star. • Installed for at least 6 months before project registration or manufactured and unmodified at least one year before project registration. Newly installed interior wet-applied paints, coatings, adhesives, sealants and finished poured floorings used inside the Annotated Documents: building envelope (minimum 10 distinct products or applied to at least 10% of project area) meet the following: => Technical Document • All products are tested by a third-party laboratory to meet testing methods and thresholds established in one of the Letter of Assurance – Contractor following standards and/or regulations for VOC content: • SCAQMD Rule 1168 (Adhesives and Sealants, 2017). • GB 33372-2020 (Adhesives). • 2019 CARB SCM for Architectural Coatings X06.1 Limit VOCs from Wet• EU Ecolabel for indoor and outdoor paints and varnishes. Applied Products • HJ 2537-2014 (Paints). • Any other standard listed in the ‘VOC content evaluation’ section of the ‘Low-Emitting Materials’ credit of the LEED v4.1 standard • At least 75% of products (by surface area or volume) are tested by a third-party laboratory to meet testing methods and thresholds established in one of the following standards and/or regulations for VOC emissions: • California Department of Public Health (CDPH) Standard Method v1.2. • AgBB • European Union LCI VOC threshold following EN 16516-1:2018 testing methods. WASTE 1 Where appropriate targets for the amount of non-hazardous and hazardous waste produced on site are set in m3 of waste The name of the designated person to monitor waste generated on the per 100m² or tonnes of waste per 100m². site 2 Procedures are in place to minimise non-hazardous and hazardous waste in line with the targets. Plan with site organization during the construction 3 The amount of site construction waste created is being monitored and targets regularly reviewed. Estimate of the amount of waste and how to recycle and transport waste 4 The design or site management team has nominated an individual responsible for implementing the above. on site 5 A pre-demolition audit of any existing buildings, structures or hard surfaces is completed to determine if refurbishment or The amount of waste will be reported monthly by each contractor reuse is feasible and, if not, to maximise the recovery of material from demolition for subsequent use, prioritising high grade A copy of the pre-demolition audit( where relevant) or a letter to confirm or value applications. The audit must cover: that the site had no structure/ construction before, so no demolition has Wst 01 Construction waste 5.a Identification of the key refurbishment and demolition materials been required. reduction 5.b Potential applications and any related issues for the reuse and recycling of the key refurbishment and demolition Identifying reclamation and reuse potential both on site and off-site materials. Local and national material valuation 6 Using the collated data, report the amount of waste generated per 100m² (gross internal floor area) in m³ (where volume is Segregation recommendations actual volume of waste, not bulk volume) or tonnes from the construction process via the BREEAM scoring and reporting tool. Environmental quantification. 7 Criteria 1 to 6 (where applicable) are achieved. 8 Procedures are in place for sorting, reusing and recycling construction waste into at least five defined waste groups (see Table 48) either on site or off-site through a licensed external contractor. Wst 03 Operational waste Wst 06 Functional adaptability X09.1 Implement a Waste Management Plan ECOLOGY 1 Dedicated space is provided for the segregation and storage of operational recyclable waste volumes generated by the assessed building or unit, its occupants and activities. This space must be: 1.a Clearly labelled, to assist with segregation, storage and collection of the recyclable waste streams 1.b Accessible to building occupants or facilities operators for the deposit of materials and collections by waste management contractors 1.c Of a capacity appropriate to the building type, size, number of units (if relevant) and predicted volumes of waste that will arise from daily or weekly operational activities and occupancy rates. 2 Where the consistent generation in volume of the appropriate operational waste streams is likely to exist, e.g. large amounts of packaging or compostable waste generated by the building's use and operation, the following facilities are provided: 2.a Static waste compactors or balers; situated in a service area or dedicated waste management space 2.b Vessels for composting suitable organic waste resulting from the building's daily operation and use; OR adequate space for storing segregated food waste and compostable organic material prior to collection and delivery to an alternative composting facility 2.c Where organic waste is to be stored or composted on site, a tap is provided adjacent to or within the facility for cleaning and hygiene purposes. 1 A building-specific functional adaptation strategy study has been undertaken by the client and design team by completion of the concept design which includes recommendations for measures to be incorporated to facilitate future adaptation. 2 Functional adaptation measures (see examples in Table 49) have been implemented in the design by completion of the technical design in accordance with the functional adaptation strategy recommendations, where practical and cost effective. Omissions have been justified in writing to the assessor. The plan with the location of dedicated space The plan with the accessibility for waste management contractors A letter to confirm that a dedicated space will provide for the segregation and storage of operational recyclable waste volumes generated by the building( and the volume) and which type of materials will able to be recycled For all batteries, pesticides, lamps that may contain mercury, other mercury-containing equipment (including thermostats and Annotated Documents: thermometers) and electrical and electronic equipmen present or expected to be present within the project during the => Policy and/or Operations Schedule building operations, a waste management plan that contains the following is developed and implemented: • Identification of roles, responsibilities and vendors for implementing the plan • Identification of the sources of waste, estimation of rates of generation and strategies to minimize waste generation • Strategies for waste collection. Each of the categorized wastes is separately contained in clearly labeled receptacles and removed from the building within one year • Protocols for cleaning spills of mercury (including broken fluorescent lamp tubes), pesticides and battery electrolyte fluid, including sealed containment of residues, as applicable • Protocols to track, measure and report waste stream flows • Protocols for off-site shipment of wastes. https://v2.wellcertified.com/wellv2/en/material s/feature/6 Architect https://v2.wellcertified.com/wellv2/en/material s/feature/6 Architect Wst 01 Construction Waste Management https://www.breeam.com/BREEAMInt2016Sch emeDocument/#10_waste/wst01_nc.htm%3F TocPath%3D11.0%2520Waste%7C_____1 Main contractor has to produce Main Contractor evidence with the amount of site construction waste created, has to monitor the waste and make sure that the targets are regularly reviewed. BGR will provide an excel file for site waste monitoring. BGR will make a report based on this data Wst 03 Operational waste https://www.breeam.com/BREEAMInt2016Sch emeDocument/#10_waste/wst03a.htm%3FTo cPath%3D11.0%2520Waste%7C_____3 Architect Wst 06 Functional adaptability https://www.breeam.com/BREEAMInt2016Sch emeDocument/#10_waste/wst06.htm%3FToc Path%3D11.0%2520Waste%7C_____7 BuildGreen https://v2.wellcertified.com/wellv2/en/material s/feature/9 Main Contractor 8. LE 8. LE 8. LE 8. LE 8. LE 8. LE 9. POL 9. POL 9. POL 1. The Contractor will appoint a biodiversity champion to make sure that the ecological value of the site survey, conducted by the Consultant prior to the commencement of site activities, will be uphold in the construction stage. 2. All existing features of ecological value within the assessment zone and site boundary area are adequately protected from damage during clearance, site preparation and construction activities. 3. In all cases, the Contractor is required to construct ecological protection recommended by the Ecologist, prior to any preliminary site construction or preparation works (e.g. clearing of the site or erection of temporary site facilities). 1 A SQE has been appointed by the client or their project representative no later than the conclusion of the design brief, i.e. the ecologist is appointed at the beginning of Concept Design stage. 2 The SQE has provided an ecology report with appropriate ecological recommendations (see Relevant definitions) for the LE 04 Ecologist's report and enhancement of the site's ecology at Concept Design stage. The report is based on a site visit or survey by the SQE (see recommendations also CN2.1). 3 All recommendations within the ecology report for enhancement of site ecology have been, or will be, implemented in the final design and build. 1 Where a SQE is appointed prior to commencement of activities on site and they confirm that all relevant EU, local and national regulations or legislation requirements relating to the protection and enhancement of ecology have been complied with during the design and construction process. 2 Where a landscape and habitat management plan, appropriate to the site (including impacts of the building both during construction and in operation), is produced covering at least the first five years after project completion. This is to be handed LE 05 Long term impact on over to the building owner or occupants and includes: 2.a Management of any protected features on site biodiversity 2.b Management of any new, existing or enhanced habitats 2.c A reference to any current or future legislation requirements (local, national or regional) that apply to the site regarding the protection of species and habitats (and where applicable refer to biodiversity action strategies or action plans) 2.d Confirmation from the SQE that all relevant aspects of ecology are included within the plan. 3 Where additional measures to improve the assessed site's long term biodiversity are adopted, according to Table 53. Construction zone Plan https://www.breeam.com/BREEAMInt2016Sch emeDocument/#11_landuse/le02.htm%3FToc Path%3D12.0%2520Land%2520Use%2520an d%2520Ecology%7C_____2 BuildGreen Design Landscape Plan LE 04 Enhancing Site Ecology https://www.breeam.com/BREEAMInt2016Sch emeDocument/#11_landuse/le04.htm%3FToc Path%3D12.0%2520Land%2520Use%2520an d%2520Ecology%7C_____4 SQE has been appointed by BuildGreen BuildGreen and the recomandation incorporated in the design. Confirmation letter (BGR draft) Landscape and Habitat Management Plan LE 05 Long term impact on biodiversity https://www.breeam.com/BREEAMInt2016Sch emeDocument/#11_landuse/le05.htm%3FToc Path%3D12.0%2520Land%2520Use%2520an d%2520Ecology%7C_____5 Landscape and Habitat BuildGreen Management Plan will be produce by SQE based on the final plant selection LE 02 Ecological value of site and protection of ecological features X10.1 Manage Pests M09.1 Provide Nature Access Indoors M09.2 Provide Nature Access Outdoors A management plan for pest control based on integrated pest management (IPM) principles is implemented for all indoor and Annotated Documents: outdoor spaces, addressing the following: => Policy and/or Operations Schedule • Plan contains the following elements • List of roles and responsibilities for the program development, implementation, maintenance and education. • Pest management objectives, including protocols for identification of pests and metrics of progress. • Design and operational measures to prevent conditions that may attract pests. • Pest tolerance thresholds and control strategies (including methods and response times) for when tolerance thresholds are exceeded, attending to the safety of the applicator, the occupants and the environment. • Records of pest monitoring data, pest events, pesticide applications, control actions and emergency responses. • For pesticide application (periodic or emergency) within the project, the plan includes the following provisions • Paper or digital notification to all building occupants on the protocol for pesticide use. • Notification to all building occupants at least 24-hours prior to pesticide application, and signage posted at the site of application at least 24-hours prior to application until at least 24 hours after application. • Notifications include the pesticide name, registration number, treatment location and date of application and applicator. If emergency pesticide application is needed, information on the type of emergency or reason for unplanned use. The project provides a combination of indoor plants (e.g., potted plants, plant beds, plant walls), water feature(s) and/or Technical Document view(s) comprising of natural areas, such as green spaces (e.g., park, forest) or blue spaces (e.g., ocean, lake) that meet a combination of the following requirements: • Within direct line of sight of at least 75% of all workstations and seats within conference rooms, lecture halls or classrooms. • Within {{well-unit}}33 ft|10 m{{/well-unit}} of all workstations and seats within conference rooms, lecture halls or classrooms. https://v2.wellcertified.com/wellv2/en/material s/feature/10 Building Management/ Owner Option 1: Outdoor nature Technical Document One of the following requirements is met: • Outdoor nature access facilitated by the conditions below: • Outdoor space of an area of at least 5% of the project interior area must be accessible to all regular occupants. • At least 70% of the accessible outdoor space as viewed from above must include plants or natural elements, including tree canopies. • Nearby nature access facilitated by the conditions below: • At least one green space or blue space is within a {{well-unit}}650 ft|200 m{{/well-unit}} walk distance from the project boundary and available to all regular occupants during open hours of the space(s). • Green spaces must be a minimum of {{well-unit}}1.2 acre|0.5 hectare{{/well-unit}} Option 2: Outdoor nature access The following requirement is met: • Occupants are encouraged to access outdoor nature (e.g., presence of signage or maps to outdoor nature, availability of breaks during the workday to go visit outdoor nature). https://v2.wellcertified.com/wellv2/en/mind/fea Recomandation in blue. Team ture/9 may decide to follow any other option. Architect 2 All systems (with electric compressors) must comply with the requirements of EN 378:2008+A2:20121 (parts 2 and 3) or ISO 5149:20142 and where refrigeration systems containing ammonia are installed, the Institute of Refrigeration Ammonia Refrigeration Systems Code of Practice3 Pol 01 Impact of refrigerants https://www.breeam.com/BREEAMInt2016Sch emeDocument/#12_pollution/pol01.htm%3FT ocPath%3D13.0%2520Pollution%7C_____1 MEP Designer Pol 01 Impact of refrigerants https://www.breeam.com/BREEAMInt2016Sch emeDocument/#12_pollution/pol01.htm%3FT ocPath%3D13.0%2520Pollution%7C_____1 MEP Designer https://v2.wellcertified.com/wellv2/en/mind/fea ture/9 POLLUTION Pol 01 Prerequisite Pol 01 Impact of refrigerant 6 Where the systems using refrigerants have Direct Effect Life Cycle CO₂ equivalent emissions (DELC CO₂ₑ) of ≤ 1000 kg CO₂ₑ/kW cooling or heating capacity. Chiller Technical Data Sheet The specifications of the refrigerant leakage detection system A letter to confirm that HVAC design will aim to reduce the level of greenhouse gas emissions airising from the leakage of refrigerants used to heat or cool the building 9. POL 9. POL 9. POL 9. POL 9. POL 9. POL 9. POL Pol 01 Impact of refrigerant Pol 02 NOx emissions A10.1 Manage Combustion 7Where systems using refrigerants have a permanent automated refrigerant leak detection system installed; OR where an inbuilt automated diagnostic procedure for detecting leakage is installed. In all instances a robust and tested refrigerant leak detection system must be installed and must be capable of continuously monitoring for leaks. 8The system must be capable of automatically isolating and containing the remaining refrigerant charge in response to a leak detection incident Where the plant installed to meet the building's delivered heating and hot water demand has, under normal operating Burner technical sheet, boiler conditions, a NOx emission level (measured on a dry basis at 0% excess O₂) as follows: NOx Emission levels for heating and hot water (mg/kWh) ≤ 40 mg/kWh Pol 01 Impact of refrigerants https://www.breeam.com/BREEAMInt2016Sch emeDocument/#12_pollution/pol01.htm%3FT ocPath%3D13.0%2520Pollution%7C_____2 MEP Designer Pol 02 NOx emissions https://www.breeam.com/BREEAMInt2016Sch emeDocument/#12_pollution/pol02.htm%3FT ocPath%3D13.0%2520Pollution%7C_____2 MEP Designer Option 1: Appliance and heater combustion ban The following requirement is met: • Combustion-based fireplaces, stoves, space heaters, ranges and ovens are not used in occupiable spaces Option 2: Low-emission combustion sources Equipment used in the project for heating, cooling, water heating, process heating or power generation (including back-up, if used for more than 200 hours per year) within the building or project site meet some combination of the following requirements: • Comply with California’s South Coast Air Quality Management District emission rules for pollution • Are electric. • Are supplied by district heating or cooling. Option 3: Engine exhaust reduction The following requirement is met: • Vehicle engine idling for more than 30 seconds is prohibited in all pick-up, drop-off and parking areas at the building site controlled by the project. "No idling" signage is present at these locations indicating this rule. https://v2.wellcertified.com/wellv2/en/air/featur e/10 MEP Designer 1Where a site-specific flood risk assessment (FRA) confirms the development is situated in a flood zone that is defined as having a low annual probability of flooding (in accordance with current best practice national planning guidance). The FRA Pol 03 Flood resilience - Low must take all current and future sources of flooding into consideration (see CN3.2). flood risk Letter Of Assurances: => Owner & MEP Pol 03 Surface water run off BuildGreen will make the report https://www.breeam.com/BREEAMInt2016Sch based on the information that the emeDocument/#12_pollution/pol03_nc.htm%3 project team has to provide FTocPath%3D13.0%2520Pollution%7C_____ 3 4 An appropriate consultant is appointed to carry out, demonstrate or confirm the development's compliance with the 1. CV for the Sanitary Designer responsbile person (must include previous Pol 03 Surface water run off following criteria: experiences in the domain and relevant diplomas) https://www.breeam.com/BREEAMInt2016Sch 5 Where drainage measures are specified to ensure that the peak rate of run-off from the site to the watercourses (natural or 2. Consultant's report containing all information necessary to demonstrate emeDocument/#12_pollution/pol03_nc.htm%3 municipal) is no greater for the developed site than it was for the pre-development site. This should comply at the 1-year and compliance with the requirements. FTocPath%3D13.0%2520Pollution%7C_____ 100-year return period events. 3 6 Relevant maintenance agreements for the ownership, long term operation and maintenance of all specified sustainable drainage systems (SuDS) are in place. 7 Calculations include an allowance for climate change; this should be made in accordance with current best practice planning guidance (see Relevant definitions ). 8 Where flooding of property will not occur in the event of local drainage system failure (caused either by extreme rainfall or a lack of maintenance); AND EITHER 9 Drainage design measures are specified to ensure that the post-development run-off volume, over the development lifetime, is no greater than it would have been prior to the assessed site's development for the 100-year 6-hour event, including an allowance for climate change (see criterion 14 ). Pol 03 Surface water run-off 10 Any additional predicted volume of run-off for this event is prevented from leaving the site by using infiltration or other SuDS techniques. OR (only where criteria 9 and 10 for this credit cannot be achieved): 11 Justification from the appropriate consultant indicating why the above criteria cannot be achieved, i.e. where infiltration or other SuDS techniques are not technically viable options. 12 Drainage design measures are specified to ensure that the post-development peak rate of run-off is reduced to the limiting discharge. The limiting discharge is defined as the highest flow rate from the following options: 12.a The pre-development 1-year peak flow rate; OR 12.b The mean annual flow rate Qbar; OR 12.c 2L/s/ha. Note that for the 1-year peak flow rate the 1-year return period event criterion applies (as described in the peak run-off criteria above). 13 Relevant maintenance agreements for the ownership, long term operation and maintenance of all specified SuDS are in place. 14 For either option, above calculations must include an allowance for climate change; this should be made in accordance with current best practice planning guidance. 17 There is no discharge from the developed site for rainfall up to 5mm (confirmed by the appropriate consultant). 1. Confirmation letter (BGR Draft) Pol 03 Surface water run off 18 In areas with a low-risk source of watercourse pollution, an appropriate level of pollution prevention treatment is provided, 2. Sanitary plans and schemes with the petrol/oil/grease separators and https://www.breeam.com/BREEAMInt2016Sch using appropriate SuDS techniques. their location on site plus the location of the retention tank(s). emeDocument/#12_pollution/pol03_nc.htm%3 19 Where there is a high risk of contamination or spillage of substances such as petrol and oil (see CN3.17), separators (or 3. Technical sheet for petrol/oil separator FTocPath%3D13.0%2520Pollution%7C_____ an equivalent system) are installed in surface water drainage systems. 3 Pol 03 Minimising 20 Where the building has chemical or liquid gas storage areas, a means of containment is fitted to the site drainage system watercourse pollution (i.e. shut-off valves) to prevent the escape of chemicals to natural watercourses (in the event of a spillage or bunding failure). 21 A comprehensive and up-to-date drainage plan of the site will be made available for the building or site occupiers. 22 Relevant maintenance agreements for the ownership, long term operation and maintenance of all specified SuDS must be in place. Pol 04 Reduction of night time light pollution 1 Where external obtrusive lighting has been eliminated through effective design that removes the need for external lighting without adversely affecting the safety and security of the site and its users. OR alternatively, where the building does have external lighting, one credit can be awarded as follows: 2 All external lighting (except for safety and security lighting) can be automatically switched off between 23:00 and 07:00. 3 Illuminated advertisements, where specified comply with: 3.a The maximum luminance (CD/m²) outlined in Table 60 (please refer to Additional information for a definition of the different zones) 3.b In Zone E1 (see Table 60) the maximum luminance value shall be zero post-curfew. 4 If safety or security lighting is provided and will be used between 23:00 and 07:00: 4.a Safety and security lighting complies with the lower levels of lighting recommended during these hours in accordance with CIE 150-2003 and CIE 126-1997, for example by using an automatic switch to reduce the lighting levels at 23:00 or earlier. 1. Drainage system layouts and schemes 2. Technical memo with sanitary installations description Technical sheet for crepuscular sensor Dialux report for exterior lighting A letter to confirm that the external lighting strategy will be designed in compliance with the limits set for technical parameters in section 2.7 of CIE 150-2003and table 2 of CIE 126-1997. The maximum luminance(CD/m2) will comply with the illuminated area(m2) for the the area where the building is located and that the all external lighting( except for safety and security lighting, as well as illuminated advertisments) will be automatically switched off between 23:00 and 07:00 and will be controlled by BMS. Pol 04 Reduction of night time light pollution https://www.breeam.com/BREEAMInt2016Sch emeDocument/#12_pollution/pol04.htm%3FT ocPath%3D13.0%2520Pollution%7C_____4 MEP Designer MEP Designer MEP Designer MEP Designer