NEW ERA UNIVERSITY 9 Central Ave, New Era, Quezon City, 1107 Metro Manila Department of Architecture and Engineering CE 213 – 18 ENGINEERING UTILITIES SCHEDULE: TUESDAY / 10: 00 AM – 1:00 PM ACUZAR, JUDEL JHOANNA MARIE G. 2BSCE-1 January 12, 2021 QUIZ # 3 A. FROM THE FOLLOWING FIGURE, FIND THE MATERIALS REQUIRED FOR ITS CONSTRUCTION FIGURE 1 2.00 M 3.00 M 4.00 M 4.50 M C 1 C 3 C 2 FLOOR LINE CHB FOOTING 4.00 M DETAILS : 2.50 M C 4 11.00 M C 5 3.00 M 0.50 M 5.00 M A. CHB SIZE = 15 X 20 X 40 CHB FOOTING: THICKNESS =0.20 m WIDTH = 0.30 m B. COLUMNS COLUMN LENGTH C1 C2 C3 C4 C5 5.0 9.0 11.0 9.0 3.5 FOOTINGS WIDTH LENGTH 0.50 0.60 0.50 0.60 0.50 0.60 0.50 0.60 0.50 0.60 THICKNESS 0.25 0.25 0.25 0.25 0.25 C. PLASTERING BOTH SIDES OF THE FIREWALL : THICKNESS = 12 mm January 12, 2021 1 NEW ERA UNIVERSITY 9 Central Ave, New Era, Quezon City, 1107 Metro Manila Department of Architecture and Engineering REQUIREMENTS: 1. Compute the total quantity of CHB and its Mortar : cement and sand , Class B Mixture 2. Compute the total Concrete for CHB footing : Cement, Gravel and Sand. Class B mixture. 3. Compute the total Concrete for the columns and footings. Class B mixture Cement, gravel, and sand. 4. Compute for the total cement and sand for the plastering works. TOTAL QUANTITY OF CHB AND ITS MORTAR: CEMENT AND SAND, CLASS B MIXTURE • SOLVING FOR TOTAL QUANTITY OF CHB β’ Knowing the total area π¨πππ π¨: 4π π¨ = 4π ∗ 5π π¨ = 20 π π. π. 5π π¨πππ π©: π¨ = (9π + 11π/2) ∗ 11π 11π 9π π¨ = 110 π π. π. 11π π¨πππ πͺ: 6π 3.5π π¨ = (6π + 3.5π/2) ∗ 5π π¨ = 23.75π π. π. 5π πΊππππππππ ππ π¨πππ: ππ ππ. π. +πππ ππ. π. +ππ. ππππ. π π¨πππ = πππ. ππ ππ. π. January 12, 2021 2 NEW ERA UNIVERSITY 9 Central Ave, New Era, Quezon City, 1107 Metro Manila Department of Architecture and Engineering Getting Total Quantity of CHB: 1 sq. m = 12.5 CHB 153.75 sq. m * 12.5 CHB CHB= 1921.875 pieces or 1922 pieces Getting Total Quantity of Mortar: 1 sq.m = 1.018 bags oof cement 153.75 sq. m * 1.018 bags of cement Cement = 156.5175 or 157 bags of cement Getting Total Quantity of Mortar: 1 sq. m = 0.0844 cu. m 153.75 sq. m * 0.844 cu. m Sand = 12.9765 cu. m or 13 cu. m of sand Getting total concrete of CHB footing (Class B mixture): 0.20m * 20m * 0.30m = 1.2 cu.m 1.2 cu. m * 7.5 = 9 bags of cement 1.2 cu. m * 0.5 = 0.6 cu.m of sand 1.2 cu. m * 1.0 = 1.2 cu.m of gravel January 12, 2021 3 NEW ERA UNIVERSITY 9 Central Ave, New Era, Quezon City, 1107 Metro Manila Department of Architecture and Engineering Getting total concrete of columns and footing (Class B mixture): C1= 0.60 * 0.60 * 5 = 1.8 cu.m C2= 0.60 * 0.60 * 9 = 3.24 cu.m C3= 0.60 * 0.60 * 11= 3.96 cu.m C4= 0.60 * 0.60 * 9 = 3.24 cu.m C5= 0.60 * 0.60 * 3.5 = 1.26 cu.m Volume for posts V= c1 + c2 + c3 + c4 +c5 = 13.5 cu. m Volume for footings V= 0.60 * 0.60 * 0.25 = 0.09 cu.m *5 V= 0.45 cu.m Summation of volume V= 13.5 + 0.45 = 13.95 cu.m Volume of concrete: 13.95 * 7.5 = 104.625 or 105 bags of cement 13.95 * 0.5 = 6.975 or 7 cu.m of sand 13.95 * 1.0 = 13.95 cu. m of gravel Getting total cement and sand for plastering works ( Class B mixture): CLASS B = 1:3 12mm = 0.144 153.75 * 0.144 = 22.14 or 22 bags of cement 153.75 * 0.012 = 1.845 or 2 cu. m of sand January 12, 2021 4 NEW ERA UNIVERSITY 9 Central Ave, New Era, Quezon City, 1107 Metro Manila Department of Architecture and Engineering January 12, 2021 5