RUNNING HEAD: CHAPTER 13 EXERCISES
WBS 8.4 Chapter 13 Exercises
Benjamin Srock
Fundamentals of Project Management
PMGT-501
Robert W. Erickson, Ph.D.
July 25, 2016
RUNNING HEAD: CHAPTER 13 EXERCISES
Benjamin Srock
PMGT 501
Chapter 13: Exercises 4 and 6
4.
Given the following project network, baseline, and status information, develop status
reports for periods 2, 4, 6, 8, and complete the performance indexes table. Calculate the EACf
and the VACf . Based on your data, what is your assessment of the current status of the project?
At completion?
Budget
$000
A
40
B
32
C
48
D
18
E
28
F
40
Total
206
Cumulative
ID
1
10
8
18
18
2
10
4
14
32
3
10
8
18
50
4
10
4
14
64
5
8
12
20
85
6
7
8
9
10
12
6
8
12
2
8
12
2
12
2
6
26
110
22
132
26
158
2
160
6
166
11
20
20
186
12
20
20
206
RUNNING HEAD: CHAPTER 13 EXERCISES
Status Report Ending Period 2
Task
A
B
Cumulative Totals
% Complete
75%
50%
($000)
EV
30
16
46
AC
25
12
37
PV
20
12
32
CV
5
4
9
EV
40
32
72
AC
35
24
59
PV
40
24
64
CV
5
8
13
EV
40
32
36
0
14
122
AC
35
24
24
0
10
93
PV
40
32
24
6
8
110
CV
5
8
12
0
4
29
EV
40
32
48
6
28
154
AC
35
24
32
20
20
131
PV
40
32
48
10
28
158
CV
5
8
16
-14
8
23
SV
0
0
0
-4
0
-4
AC
37
59
93
131
PV
32
64
110
158
SPI
1.44
1.13
1.11
0.97
CPI
1.24
1.22
1.31
1.18
PCI-B
22%
35%
59%
75%
Status Report Ending Period 4
Task
A
B
Cumulative Totals
% Complete
100%
100%
($000)
Status Report Ending Period 6
Task
A
B
C
D
E
Cumulative Totals
% Complete
100%
100%
75%
0%
50%
% Complete
100%
100%
100%
33%
100%
SV
0
8
8
($000)
Status Report Ending Period 8
Task
A
B
C
D
E
Cumulative Totals
SV
10
4
14
SV
0
0
12
-6
6
12
($000)
Performance Indexes Summary
Period
2
4
6
8
EV
46
72
122
154
EAC𝑓 =
(BAC − EV)
+ AC
EV
(AC)
EAC𝑓 =
(206 − 154)
+ 131
(154/131)
EAC𝑓 =
(52)
+ 131 = (44) + 131 = 𝟏𝟕𝟓
(1.18)
RUNNING HEAD: CHAPTER 13 EXERCISES
VAC𝑓 = (BAC − EAC𝑓 ) = (206 − 175) = 𝟑𝟏
Based on your data, what is your assessment of the current status of the project? At completion?
At the end of period 8, the project is 74.75% complete (EV/BAC) and $23,000 under budget. At
this point, the project should have amassed an actual cost of $154,000, when it actually cost
$131,000. This savings is a good sign as it indicates we are getting $1.18 worth of work for
every $1.00 we spend. Based on this current rate of operation, the project should come in
$31,000 under budget. The downside is that while there is a substantial savings, the project does
appear to be behind schedule.
6.
The following labor hours’ data have been collected for a nanotechnology project for
periods 1 through 6. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the
AC on the summary graph provided (or a similar one). Plot the SPI, CPI, and PCIB on the index
graph provided (or a similar one). What is your assessment of the project at the end of period 6?
Schedule Information
ACT/
WP
1
2
3
4
5
6
7
DUR
2
2
6
5
4
4
2
Total
ES
LF
SL
1
2
PV
0
2
0
20
10 10
2
7
3
24
2
11
3
30
2
7
0
25
4
11
3
16
7
11
0
20
11
13
0
10
Total PV by period 10 10
Cumulative PV by period 10 20
Baseline budget needs - labor hours (00)
3
16
5
10
31
51
4
8
5
10
23
74
5
10
2
4
16
90
6
3
2
4
9
99
7
2
1
4
7
106
8
9
10
11
12
13
5
4
5
5
6
4
14
120
5
125
6
131
4
135
5
5
140
5
5
145
14
RUNNING HEAD: CHAPTER 13 EXERCISES
Status Report Ending Period 1
Task
1
Cumulative Totals
($000)
% Complete
50%
EV
1000
1000
AC
500
500
PV
1000
1000
CV
500
500
EV
2000
2000
AC
1500
1500
PV
2000
2000
CV
500
500
EV
2000
0
300
500
2800
AC
1500
0
200
500
2200
PV
2000
1600
500
1000
5100
CV
500
0
100
0
600
EV
2000
1200
900
1000
5100
AC
1500
1000
800
1500
4800
PV
2000
2400
1000
2000
7400
($000)
CV
SV
500
0
200
-1200
100
-100
-500
-1000
300
-2300
EV
2000
2400
1500
1500
400
7400
AC
1500
2000
800
1500
400
6200
PV
2000
2400
2000
2200
400
9000
($000)
CV
SV
500
0
400
0
700
-500
0
-700
0
0
1600
-1200
EV
2000
2400
2400
2000
800
8800
AC
1500
2000
2100
1800
600
8000
PV
2000
2400
2300
2400
800
9900
($000)
CV
SV
500
0
400
0
300
100
200
-400
200
0
1600
-300
Status Report Ending Period 2
Task
1
Cumulative Totals
($000)
% Complete
100%
Status Report Ending Period 3
Task
1
2
3
4
Cumulative Totals
Status Report Ending Period 4
% Complete
100%
50%
30%
40%
Status Report Ending Period 5
Task
1
2
3
4
5
Cumulative Totals
% Complete
100%
100%
50%
60%
25%
Status Report Ending Period 6
Task
1
2
3
4
5
Cumulative Totals
% Complete
100%
100%
80%
80%
50%
Period
1
2
3
4
5
6
SPI
1.00
1.00
0.55
0.69
0.82
0.89
SV
0
0
($000)
% Complete
100%
0%
10%
20%
Task
1
2
3
4
Cumulative Totals
SV
0
0
CPI
2.00
1.33
1.27
1.06
1.19
1.10
PCI-B
7%
14%
19%
35%
51%
61%
SPI = EV/PV
CPI = EV/AC
PCIB = EV/BAC
SV
0
-1600
-200
-500
-2300
RUNNING HEAD: CHAPTER 13 EXERCISES
What is your assessment of the project at the end of period 6? It is important to first note the
critical path 1, 4, 6, & 7. At the completion of the 6th period, activity 4 should be completed but
is only 80% complete. Since the actual cost of activity 1 resulted in a savings of $500, perhaps
this savings can be utilized to crash this activity to get the project back on schedule. If nothing is
done, the project will not complete on time.