Pre-cutover Cutover Post Cutover Communications Plan Cutover plan... Mid Servers point to Prod - Few days before CMDB Go Live Cloud Discovery point to Prod - Azure schedule per subscription Integrations point to Prod - Crowdstrike ready for Paul to test, AD / Single Sign On ready, WPP CMDB - Functional Testing cycle Data Load Discovery data & config WPP CMDB CIs (Integration, Non discovery)- As soon as tested by Paul Crowdstrike (Integration, Non discovery) - As soon as tested by Paul CWB Data (Services data) - dependent on solution being agreed (18 Dec) Technical Services data - Can be loaded in advance, plug install required Groups & Group members, Roles - Can be loaded as soon as data confirmed (target groups) Tactical CMDB (Non discovery) - Deltas from Discovered + Crowdstrike + WPP CIs, CSDM attributes - Can be loaded once Technical Service, Groups etc (target groups) Foundation data (location data) - Can be loaded in advance once validated in Test Prod Code Release Mid Servers - 1 Day Prod Validation