APAC Service Operations HSE Health & Safety Management System Title: Working at Height Group Document: Group Reference Standard – Work at Height – Fall Protection Document Reference: APC-HSE-HSMS-00539 Date of Issue: 12 Jul 2019 Process Owner: APAC Service Operations HSE Process Writer: Ashwin Bhosale & Nisar Shaikh Process Approver: Sian Petigny 1.0 Objective Sodexo is committed to protect Sodexo employees (including contractors, visitors, and clients that may be affected by our performed maintenance work activities) wherever Work at Height (WaH) activities are identified in order to minimise the risk of potential injury to persons or potential impact and damage to the surrounding environment. This document describes the process for working safely at heights (at or above 1.8m) where there is a risk of an individual(s) falling from one level to another, when conducting work on machinery, equipment or other installations, or where individuals are working within 1.8m of a live edge or brittle surface; including any potential for dropped objects impacting personnel below. Examples of work at height include; roof work, working from cradles, accessing ceilings and lighting fitments, and access to other high areas inside and outside buildings. Work at height considerations also apply where a worker could fall into dangerous machinery or materials, regardless of the height of the work being performed. Work at ground level can also be hazardous where there is the potential to fall below ground, for example into excavations, inspection chambers and pits. 2.0 Scope This process applies to all APAC sites and compliance with its requirements is mandatory for all scope of services rendered by Sodexo and its contracted services. This process shall also be applied in accordance with applicable local legal requirements. If Sodexo is required to adopt and/or use (by contractual agreement) client’s methodology and/or form (e.g. Risk Assessment, Job Safety Analysis, Job Hazard Analysis), this is to be agreed upon and documented in the HSE Interface Document (APC-HSE-FORM-00550b). When required, Local Operating Process (LOP) is to be developed. Regardless, client is responsible to provide related training with refresher frequency arranged for Sodexo affected team. Where there is a more stringent height limit, i.e. less than 1.8m (e.g. this process against client or applicable national, state, and local legal requirements), the more stringent requirement shall be followed. Such cases shall also be defined in the LOP to be developed. 1/8 – APC-HSE-HSMS-00539 Version 1 / Date of Issue 12 Jul 2019 3.0 Responsibilities Regional and Local Management Team Regional and local management team are responsible for ensuring that this process is followed on site and that there is access to a competent operational resource allocated to each site/ contract in order to meet and implement the requirements in this document, as well as applicable local or international legal requirements. APAC Regional HSE Team Supporting the management team in the implementation of this process within the organisation To promote and cascade this process across the region through the respective Territory Team(s) Ensure that this process is reviewed at regular interval, kept current and all references are relevant/valid, including all related documents Territory HSE Team (Includes In-Contract & Site HSE) Will facilitate the deployment of this process including relevant guidelines, tools and forms at site Allocate / provide training in accordance with the training needs analysis and/or training matrix for the appointed resources to be able to carry out work Conduct random checks during announced or unannounced site visits, inspections or audits to ensure that this process is being followed by the site(s) and to confirm compliance Ensure that this process is in compliance with applicable local requirements Regional and Local FM Team Provide technical knowledge and support to the local / site team, across all territory or business activities (e.g. FM services or food services) in the development of risk assessments (RA), Safe System of Work (SSW), etc. associated with WaH tasks to be done onsite Conduct review of contractor method statements, qualifications, etc. to ensure that subcontracted work will be carried out in accordance with this process and Sodexo’s Permit to Work (PTW) process Prescribe additional control measures necessary to ensure the WaH task shall be carried out and completed safely in accordance with this process Site Manager / Lead Ensure that a detailed RA is completed for all WaH tasks in order to identify appropriate controls to mitigate or reduce the risk, in consultation with Qualified Authorized Person(s), and appropriate SMEs Making sure that any WaH equipment (e.g. mechanical aids or PPE) identified in the RA are used and implemented as required Ensure that the appointed operational competent resource (i.e. Qualified Authorized Person) trains the affected employees in accordance to the WaH SSW Ensure that the PTW Process (in accordance with APC-HSE-HSMS-00532) is implemented for WaH tasks Ensure that all employees who are required to carry out WaH as part of their tasks are provided with the necessary training, which may include but not limited to: general awareness, Sodexo internal WaH training, training from supplier of WaH equipment, etc. 2/8 – APC-HSE-HSMS-00539 Version 1 / Date of Issue 12 Jul 2019 If a Qualified Authorized Person for WaH is not available on site, reach out to Local FM Team for appropriate support In the event of the Qualified Authorized Persons (responsible person) Site Manager will take on the role of Permit Issuer – in accordance with PTW process Ensure that this process is implemented and enforced on contractors who perform WaH tasks Ensure that any HSE concerns regarding a client appointed contractor is brought to the attention of the client at the earliest possible opportunity Qualified Authorized Person1 for WaH (includes Supervisor, Team Lead, etc. leading the work team) Understand Sodexo RA, PTW and WaH processes Support the Site Manager (if not the same person) to issue WaH permits and ensure requirements of this process is implemented on site Attend the required internal and external trainings Train Qualified Person/s in the SSW of a specific WaH activity Qualified Person2 (includes Workers and Standby Person) Attend WAH related training (internal or external) Comply with the SSW and RA of affected WAH activity Perform pre-checks of WaH equipment and WaH control measures when appointed by Qualified Authorized Person Understand the SSW as trained by the Qualified Authorized Person and comply with the SSW requirements while performing the work. 4.0 What you need to do 4.1 Requirements before performing Working at Height 4.1.1 Ensure Appropriate Risk Assessment is in Place and Implemented All potential WaH activity shall have detailed risk assessments. Control measures to protect against fall hazards will be selected in accordance with the hierarchy of controls. The most protective control measures will be used wherever feasible to eliminate potential fall exposure. The RA shall be carried out considering these potentials: Wherever practicable, the need to eliminate the need to WaH shall be identified as part of the risk assessment process. This could include carrying out the work on the ground or from a solid structure such as a work platform which is secured by hard barricading (e.g. platform with guard rails, toe boards etc.) 1 A Qualified Authorised Person is a Qualified Person with additional training and experience, and has a good understanding of the plant, equipment, building or site in order to understand the process or task being undertaken and associated controls, and verify the required precautions have been effectively applied. This individual is responsible for developing and implementing safe work processes; preparing or approving work permits; approving the selection and use of work equipment and clothing; and verifying that safety equipment chosen by the Qualified Person for specific tasks is appropriate. 2 Person or persons that are locally qualified and registered in accordance with the local legislation as appropriate, and have been assessed by the Authorizing Engineer as sufficiently competent. They are responsible for adhering to all the requirements detailed in the Group Standard as well as the local safe work process. 3/8 – APC-HSE-HSMS-00539 Version 1 / Date of Issue 12 Jul 2019 If applicable, minimize the distance or impact of a potential fall Minimize risk by providing information, instruction or training to applicable workers Use fall prevention, fall protection or fall arrest equipment (whichever is applicable) Regardless of the height where work is being done, Point-of-Work Risk Assessment (i.e. 3 Checks for Safety, Working at Height Safety Nets Card, or Dynamic Risk Assessment) shall be completed and the appropriate SSW followed. The table below provides examples of possible hazards and risk factors associated with a WaH activity and control measures that may be implemented to manage such hazards and risks. This list is not exhaustive and only provided to serve as reference in conducting WaH RAs. Hazards On fragile roofing While using access equipment On unstable or uneven surfaces Near an unprotected edge or opening In adverse weather or environmental conditions (e.g. low visibility, extreme temperatures etc.) With tools or objects that may fall Near overhead power lines or sources of hazardous energy 4.1.2 Risk Factors Medical and physical fitness of the person conducting the task Work area condition (e.g. quality of the work surface, lighting and/or ventilation conditions, etc.) Adverse weather conditions Number of personnel who may be at risk Location of the work area, including locations of access/egress routes Type of work to be carried out Work practices in use Scheduling of work, including time and duration of work Type of plant, machinery or equipment to be used Competence, training and experience of the people carrying out the work Being struck by a moving or falling object, tools or equipment during the work Simultaneous operations within the vicinity of the work at height Control Measures Eliminating the hazard i.e. working on the ground where possible If work at heights is unavoidable, secure the elevated work area with a passive fall prevention barrier system, such as guardrails Being medically and physically fit for the task Substituting a work method or process with one less hazardous i.e. using walkways for access instead of a ladder Modifying the system of work or equipment i.e. using scaffolding Adopting work positioning systems such as scissor lifts or MEWPs Providing additional controls i.e. adopting administrative controls such as permit to work, SSW, so the time or conditions of exposure to the risk is reduced Using personal protective equipment i.e. fall-arrest or fall restraint equipment Safe Systems of Work (SSW) In Place SSWs shall be developed in consultation with Qualified Authorized Person(s) who shall be supported by relevant SMEs (e.g. HSE and FM). The SSWs shall be based on good industry practice, local requirements, or manufacturer recommendations. The SSW shall be developed based on the following recommendations and using a riskbased approach [e.g. based on Risk Assessment process] and include consideration of: The situation under which the SSW is to be developed The means and sequence by which the safe access will be achieved The checks that are to be performed prior to the commencement of work 4/8 – APC-HSE-HSMS-00539 Version 1 / Date of Issue 12 Jul 2019 The specific fall protection and personal protective equipment (PPE) required Whether or not a Permit to Work (Working at height) is required, based on the results of the risk assessment The title/positions of persons authorised to perform work and issue permits (if required) in relation to the work to be done Any other special requirements. SSW should usually come and be issued in the form of a proper operations document format, however, if unavailable, site team could also make use of the SSW section as available in the detailed risk assessment for the same purpose. All controls identified in the SSW shall be in place before work commences. The Qualified Authorized Person for WaH in each territory will jointly develop, together with other SMEs, the local procedures (SOP) and conduct the necessary relevant training to employees who will carry out the work. A register of WaH SSWs (Refer to APC-HSE-FORM-00539a), including the names of the Qualified Authorized Person(s) who have undergone training, shall be maintained by the Site Manager in accordance with appropriate FM SME recommendations. 4.2 Performing the Work at Height under an Approved WaH PTW Upon completion of the requirements of the PTW, Responsible Person shall apply a WaH PTW from the Permit Issuer (Sample permit provided in Appendix). Note that in some situations, the Qualified Authorized Person(s) conducting the work may also be the Permit Holder. In such cases, the Site Manager shall take on the role of the Permit Issuer. For the case of Sodexo direct contractors, Qualified Authorized Person (if appointed) shall take on the role of the Permit Issuer. The approved Working at Height Permit shall be displayed in the area where the work is being undertaken. All working at height shall be conducted in strict accordance to the SSW and/or Risk Assessment and (if applicable) the Working at Height Permit conditions. If a Working at Height Permit is required and has been issued, the Responsible Person (i.e. the Permit Holder) must also monitor the work to ensure that all the controls and other precautions described in the Permit are being followed. If any breaches to the conditions or controls required under the Working at Height Permit occur, the Permit Holder must immediately stop the work and notify the authorised Permit Issuer. Work can only recommence upon formal approval of the Permit Issuer, including reissuing the Working at Height Permit. 4.3 Completion and Cancellation of Permit After completing the WaH activity or task, the Permit Holder shall conduct an inspection before closing-down (securing) and leaving the work site. This inspection shall include a check that all the work has been satisfactorily completed and all persons, equipment, tools and instruments have been withdrawn. 5/8 – APC-HSE-HSMS-00539 Version 1 / Date of Issue 12 Jul 2019 The post work inspection shall also ensure that the work area is in a condition that will allow it to be safely secured before any associated plant or equipment can be reinstated or brought back into service e.g. all barricades and signs have been removed, temporary road closures or deviations removed, isolations removed, etc. Consequently the Permit Issuer, after agreeing with the Permit Holder on the completion of work, shall cancel the WaH PTW to confirm that the work area/equipment is returned to a safe status with no hazards remaining in respect of these works; and that all personnel, work equipment and materials have been withdrawn as appropriate. 5.0 Training and Competence WaH Permit Issuer shall be appointed by the Site Manager (in consultation with the Regional SMEs as necessary) to issue WaH Permits. Such appointment shall be documented in the APC-HSE-FORM-00532d - Authorised Permit Issuer Appointment Form. WaH Permit Issuers shall undergo related internal and external WaH training. Alternatively if specialised work is required at a height of 1.8m or more, a suitably trained and competent contractor shall be engaged to conduct work at heights providing they hold the appropriate competencies and/or licences. In such cases, the Site Manager shall ensure that contractors are supervised at all times while WaH is being performed. Site Manager shall ensure related internal and external training is provided to Qualified Persons to make sure they are capable and competent to perform the WAH activity. Qualified Person(s) shall be trained and assessed to ensure that: They have sufficient skills and knowledge to apply safe working practices when working at height They have demonstrated a responsible attitude towards safe work practices They understand applicable site SSWs relating to the working at height they are authorised to conduct They have demonstrated an understanding and have sufficient skill to identify work requirements, assess and install equipment, perform work at height and clean work area(s) Prior to their appointment, the following personnel involved in WaH task shall undergo the required initial and appropriate refresher trainings as defined below. Refresher trainings are recommended to be at least every two years unless local requirements require more frequent. Trainees Trainer Training Method Training Records Site Employees, Site manager, Qualified Authorized Person, Qualified Person, Permit Issuer, SME, etc. and all other employees involved in the performance and implementation of WaH activities, including the use of WaH PTW Internal – to introduce the Sodexo WaH process and WaH PTW System Induction (Refer WAH Training guidance) Maintained at site Permit Issuer, SMEs, Qualified Authorized Person; Qualified Person doing WaH External - Suitably recognised training organisation – as required based on client or local legal Induction & Practical Maintained at site 6/8 – APC-HSE-HSMS-00539 Version 1 / Date of Issue 12 Jul 2019 Trainees Trainer Training Method Training Records requirements Where WaH activities are to be performed by contractors, the contractor company shall provide records of personnel qualification, competency and appropriate training to the Site Manager as part of the approval process for WaH permit. 6.0 Record Keeping Site Manager/Lead (or his/ her appointed person) is responsible to ensure the following are kept up to date, relevant and available at their site: Work at height Risk Assessments and Safe Systems of Work Work at height Permit to work Relevant internal and external training. Applicable certifications, operation manuals, service logs and any other documents / records related for WaH equipment Applicable licenses / certifications of relevant personnel 7.0 Revision Table Version No Revision Date 1 12 Jul 2019 7/8 – APC-HSE-HSMS-00539 Version 1 / Date of Issue 12 Jul 2019 Revision Description New Document Appendix 8/8 – APC-HSE-HSMS-00539 Version 1 / Date of Issue 12 Jul 2019