Overall assessment on flexible pavement maintenance activities along North South Expressway Northern Region: From Alor Setar KM51.40 to Sungai Petani KM 107.90 Cite as: AIP Conference Proceedings 2020, 020023 (2018); https://doi.org/10.1063/1.5062649 Published Online: 05 October 2018 A. Albar, M. H. Osman, Z. Dollah, A. A. Musir, and N. Z. Roslan ARTICLES YOU MAY BE INTERESTED IN The falling weight deflectometer (FWD) for characterization bonding state of subgrade AIP Conference Proceedings 2020, 020022 (2018); https://doi.org/10.1063/1.5062648 The improvements on the pedestrian sidewalk towards supporting world class city in Malaysia AIP Conference Proceedings 2020, 020024 (2018); https://doi.org/10.1063/1.5062650 Evaluation of rutting resistance of dense graded asphaltic concrete with nanosilica modified binder AIP Conference Proceedings 2020, 020025 (2018); https://doi.org/10.1063/1.5062651 AIP Conference Proceedings 2020, 020023 (2018); https://doi.org/10.1063/1.5062649 © 2018 Author(s). 2020, 020023 Overall Assessment on Flexible Pavement Maintenance Activities along North South Expressway Northern Region : From Alor Setar KM51.40 to Sungai Petani KM 107.90 A. Albar1, a) , M. H. Osman1 , Z. Dollah1, A. A. Musir1 and N. Z. Roslan1 1 Faculty of Civil Engineering, Universiti Teknologi MARA Cawangan Pulau Pinang, 13500 Permatang Pauh, Pulau Pinang, Malaysia a anizaalbar@ppinang.uitm.edu.my Abstract. The purpose of this study is to establish the complete assessment of flexible pavement maintenance activities carried out from Sungai Petani KM107.90 to Alor Setar KM51.40, Section N2,North South Expressway Northern Region. The assessment includes the visual inspection to determine the rating criteria for each defect found on the flexible pavement and the determination of proper rehabilitation work along Section N2 by referring to Inspection Manual for Pavement Maintenance Management System – PLUS Bhd and OPUS NMM NRO and Buku Panduan Pemeriksaan Penyelenggaraan Bulanan Lebuhraya- Lembaga Lebuhraya Malaysia (LLM). Quality Assurance and Quality Control (QA/QC) practice also been incorporated throughout the assessment as listed in Method Statement in Work Order and Standard Specification for Road Works JKR/SPJ/2008-S4 Fexible Pavement. It is including before, during and after rehabilitation work is implemented. From the visual inspection, cracking recorded the highest percentage of the defect found on north bound with 32%, while south bound recorded as 44%. Both are categorized in rating C condition which require repairs for user comfort which mill and pave method been chosen for repairing works after considering several factors; such as optimum time and cost. A good assessment at defected area will increase the life span of the pavement and minimize the overall maintenance cost. INTRODUCTION Flexible pavement contains several layers of natural granular material which consists of subgrade layer, sub-base layer, base layer and waterproof bituminous surface layers. The purpose for these different layers is to reduce the transmitted stress caused by traffic loading so it will not exceed bearing capacity of the sub-grade [1]. According to Razali and Zakaria [2], modes of pavement distress that are commonly found in Malaysia are including top-down cracking, reflection crack, rutting and lack of macrotexture. Several conditions have been identified as the possible causes of the defects occurred on the road. Axle loading and climatic conditions are the major parameter to design flexible pavement. Other than that, traffic loading, thickness of pavement and low quality of construction also contribute to the problem. It is agreed by Behiry [3] that heavy vehicle will cause severe deterioration and it will lead to the decreasing of the life span of the road pavement. On the other hand, road damage is also caused by lack of monitoring by the authorities on the construction site or during overhaul the way to control the quality of construction. Jain. et. al [1] added that the pavement networks must be managed, not simply maintained and the task of managing pavements must be completely systematic and objective achieveable. Thus, the cooperation from all organizations are important to mitigate this problem. This is the main reason of the rehabilitation work and Quality Assurance / Quality Control (QA/QC) becomes top priority to increase the life span of the road. Jain et. al [1] mentioned that the main objective of pavement maintenance and rehabilitation system is to provide a technical tool to maintain roads at preferred serviceability levels. Since pavements deteriorate in time, it is necessary to maintain and rehabilitate them to provide minimum desired service to its user and save the valuable assets. The method of rehabilitation works that commonly implemented on North South Expressway includes reinstatement or mill and pave, overlays, overlays with pre-treatment, structural overlay and regulating. Any Advances in Civil Engineering and Science Technology AIP Conf. Proc. 2020, 020023-1–020023-7; https://doi.org/10.1063/1.5062649 Published by AIP Publishing. 978-0-7354-1738-0/$30.00 020023-1 preventive maintenance shall be carried out effectively at the beginning stage to avoid further failure that would affect the cost of repairs. STUDY BACKGROUND Section N2 is a 50km length expressway traversing across most paddy fields in northern area in Malaysia which stretched from Alor Setar Selatan KM51.40 to Sungai Petani Selatan KM107.90. Since its completion, one of the latest technology been implemented on the flexible pavement in year 2013 to alleviate soft ground problems at KM56.05-KM55.40 along Pendang-Alor Setar Selatan. The reinforce concrete raft with 300mm thick as treatment design to replace the existing Dense Bituminous Macadam (DBM) and Asphaltic Concrete Wearing Course (ACWC). Then the ACWC is overlaid on top of the newly completed RC rafts. The deterioration of the new or repaired flexible pavement is relatively caused by traffic stress and environment. The severity of the traffic loads and the variability of road materials might affect the rate of deterioration. Before any rehabilitation work is carried out, a proper assessment shall be performed to identify the pavement distress and its possible causes. Despite of many options of rehabilitation methods and techniques, an appropriate and right choice of assessment technique and rehabilitation work are very important to ensure that the serviceability requirements of the expressway are adequate and thus minimising the need for regular repaving works to maintain the road profile. Pursuant to the above, this study is perform to assess the flexible pavement maintenance activities along Section N2, North South Expressway Northern Region including identifying type of pavement distress and method of rehabilitation works being implemented as well as the QA/QC throughout the pavement maintenance activities. METHODOLOGY Assessment of the pavement distress was carried-out using the surface condition inspection form modified based on the assessment guide available in [4]. Over 50km length according to its bound directions (North bound and South bound) and lanes (slow lane and fast lane) are assessed for the condition of the pavement. The criteria that been assessed including the type, degree and extent of the pavement defect for every 500m segment from the slowmoving vehicles travelling on the pavement shoulder. Table 1 shows the rating criteria in determining the severity of the pavement defect. While the degree and extent of pavement defects are presented in Table 2 and Table 3 respectively. TABLE 1. Pavement Defect Rating Criteria Rating A: Damage which disturb the traffic B: Damage which requires immediate repairs. C: Damage which required repairs for user comfort. Description Required high priority repairs, immediate attention required due to the traffic safety needs. Moderate priority repairs, attention required due to heavy damage. Less priority repairs, scheduled maintenance or minor damage or further investigation and assessment work is required. TABLE 2. Degree of Pavement Defect Degree 0 1 2 3 4 Severity Slight Between slight and warning Warning Between warning and severe Description No distress visible Slight- No attention required immediately Between slight and warning Distress is distinct. Starting of secondary defect Between warning and severe 020023-2 TABLE 3. Extent of Pavement Defect Extent 1 2 3 4 5 Description Isolated (seldom) occurence Intermittent (scattered) occurrence, over parts of the segment length Intermittent (scattered) occurrence, over most of the segment length More frequent occurrence over a major portion of the segment Extensive occurence As to address the defects detected during the inspection, the rehabilitation works on flexible pavements are carried out. The type of treatment and common condition of use are indicated in Table 4. TABLE 4. Treatment Type and Condition of Use Treatment Reinstatement Overlays Overlays with pre-treatment Structural overlay Regulating Type of Works Mill and replace to the required depth Overlay of 50mm ACWC with localized patching if required Pre-treatment of existing pavement layers to the required depth and application of 50mm overlays across all lanes Pre-treatment of existing pavement layers including base treatment to the required depth and application of overlays across all lanes to the required thickness Regulating of undulation at identified areas using asphalt concrete materials Condition of Use Cracks, rutting Surface cracks / failure Cracks, rutting Severe cracks, severe rutting Depression, undulation Quality assurance and quality control (QA/QC) are carried out before, during and after the rehabilitation work. Before commencing of rehabilitaion work, mix design, plant trial including crusher and premixt plant, and laboratory testing are conducted such as Binder and Grading test, Marshall test, Immersion Index and Draindown test. All testing should comply with the specification highlighted in [5]. Besides that, the QA/QC inspection also performed during the rehabilitation process to ensure all works are done as described in Method of Statement in Work Order (WO). Another stages of laboratory testing then been conducted after the rehabilitation work including Maximum Specific Gravity by using Rice Method and determination of density of asphalt cored sample. RESULT AND DISCUSSION From the visual inspection on flexible pavement along Section N2 for North Bound and South Bound, most of the stretch are rated as rating C which require repairs for user comfort. However, it is less priority repairs, where scheduled maintenance or further investigation and assessment work are required. Only few segments are recorded as degree 2 which the most defect found is cracking between slight and warning sign of the severity. In addition, the extension of cracking defect is scattered occurrence over most of the segment length. Other defects detected are patching, potholes, raveling, rutting and bleeding. Table 5 shows the frequencies of pavement distresses found for North Bound and South Bound. 020023-3 TABLE 5. Frequency of Pavement Defects along Section N2 North Bound Frequency Percentage % 16 22 6 8 2 2 6 8 10 14 18 24 16 22 0 0 16 22 74 100 Type of Defects Alligator cracking Longitudinal cracking Block cracking Ravelling Rutting Potholes Patching Bleeding Alligator cracking Total South Bound Frequency Percentage % 14 26 8 14 2 4 4 7 2 4 10 19 12 22 2 4 14 26 54 100 Cracking defect which consist of alligator, longitudinal and block cracking recorded as the most common defect found whith 32% for North Bound and 44% for South Bound. Cracking of road pavement surfaces can happen in a wide variety of patterns, ranging from isolated single crack to an interconnected pattern extending over the entire pavement surface. It can be seen in Figure 1 on distribution of pavement defect for both bounds. While Figure 2 shows the photos of common defects found on the flexible pavement along Section N2. The defect problems are closely related to soil condition beneath the pavement as the passage is crossing the paddy field. It is worsened by repetitive and heavy vehicles travel along this section which caused more impact to the pavement layers. (a) (b) FIGURE 1. Distribution of Pavement Defects on (a) North Bound; (b) South Bound (a) (b) (c) (d) (g) (h) (i) (j) (e ) (k ) (f) (l) FIGURE 2. Common defects found on flexible pavement along Section N2 (a) Longitudinal crack ; (b) Transverse crack ; (c) Alligator crack ; (d) Block crack ; (e) Severe cracking ; (f) Ravelling and rutting ; (g) Multiple patches ; (h) Undulating ; (i) Bleeding ; (j) Shoving ; (k) Polishing ; (l) Potholes 020023-4 The most suitable rehabilitation work to repair the significant defect after considering the optimum cost, time and suitability for a long-term engineering solution is reinstatement which involving mill and replace to the required depth. The rehabilitation works that been inspected located at KM84.10 to KM84.30, North Bound, Section N2, North South Expressway Northern Region as shown in Figure 3. The milling work process are performed at site by referring to [6]. Major pavement works involved are milling, paving and compacting. FIGURE 3. Rehabilitation works process consists of milling, dipping, cleaning milled area, spraying tack coat, paving, and compacting pavement layer. In addition, the quality assurance and quality control (QA/QC) activities been done before, during and after the repairing works. Before commencing of rehabilitation work, few laboratory tests were conducted in laboratory on premix by referring to [5]. All results are tabulated in Table 6 and meet the specification limit. The need of conducting test on bituminous material are to ensure the pavement can withstand the heavy traffic loads act upon it and its life span can be prolonged. TABLE 6. QA/QC Laboratory Testing Before Rehabilitation Works Laboratory Testing Binder & Grading Marshal Immersion in 30 minutes Immersion in 24 hours Draindown Stability Flow Bearing Capacity Stability Flow Bearing Capacity Stability Flow Bearing Capacity Laboratory Result 5.44% 1377.6 kg 2.95 mm 467 kg/mm Specification Limit 5.14% - 5.74% >750 kg 2 mm – 4 mm >320 kg/mm 1398.8 kg 3.00 mm 466.3 kg/mm > 750 kg 2 mm – 4 mm >320 kg/mm 1324.4 kg 2.80 mm 473 kg/mm > 750 kg 2 mm – 4 mm >320 kg/mm 0.02% <0.3% Where as during rehabilitation work, it is necessary to monitor every process to ensure the compliancy of design and pavement work as stated in method statement for each approved Work Order (WO) prepared by UEM Edgenta. The QA/QC involved is shown in Figure 4. 020023-5 (a) (b) (c) (d) (e) (f) FIGURE 4. QA/QC process during rehabilitation work (a) Dipping process of milled area; (b) Cleaning of milled area; (c) Spraying of tack coat uniformly; (d) Checking the temperature of premix; (e) Monitoring rolling pattern of tandem roller; (f) Monitoring rolling pattern for pneumatic tyre roller. After rehabilitation work, bituminous mix sample is taken from the site and went throughthe laboratory testing to determine its quality. These testing are conducted to obtain a good and economical blend of bituminous mix design through several trial mixes. Moreover, the suitable designed bituminous mix will have a great strength to withstand heavy traffic loads under climatic conditions and fulfil the pavement surface characteristics. Tests involved are binder & grading, maximum specific gravity, marshall test and density of asphalt cored sample and the results are tabulated in Table 7. TABLE 7. QA/QC Laboratory Testing After Rehabilitation Works Laboratory Testing Binder & Grading Stability Marshal Flow Bearing Capacity Maximum Specific Gravity Density of asphalt cored sample Laboratory Result 5.43% 1401 kg 2.95 mm 475 kg/mm 2.44 99% Specification Limit 5.14% - 5.74% >750 kg 2 mm – 4 mm >320 kg/mm 2.44 – 2.70 99% - 100% CONCLUSION It can be concluded that the overall assessment on flexible pavement maintenance from Sg Petani KM107.90 to Alor Setar KM51.40 North South Expressway Northern Region is successfully conducted. The following conclusions are highlighted from this study: 1. The most common defect found on flexible pavement along the stretch was cracking which consists of alligator, longitudinal and block cracking. It is because section N2 is surrounded by paddy field which will cause the development of cracking defect due to weak subgrade layer. 2. Reinstatement which involves mill and pave works been choose as a rehabilitation methods and techniques to ensure that the serviceability requirements of the expressway are adequate and thus minimising the need for regular repaving works to maintain the road profile. 3. QA/QC activities are successfully implemented before, during and after the rehabilitation works by site supervision and monitoring as well as through laboratory testing. All results meet the specification limit by Standard Specification for Road Works JKR/SPJ/2008-S4 Flexible Pavement established by Public Work Department (JKR). ACKNOWLEDGEMENT The authors would like to acknowledge Universiti Teknologi MARA (UiTM) for financial support in this research work. 020023-6 REFERENCES 1. 2. 3. 4. 5. 6. S. Jain, Y.P. Joshi and S.S. Golia. Design of rigid and flexible pavements by various methods and their cost analysis of each method, International Journal of Engineering Research and Applications, Vol. 3, No.5,pp119123. (2013) R. Razali and S. Zakaria. Improving road durability using modified asphalt in Malaysia: How it works?, International Journal of Pavements Conference, Sao Paulo, Brazil, pp1-8. (2013) A.E.M. Behiry. Fatigue and rutting lives in flexible pavement, Ain Shams Engineering Journal, Vol. 3, No.4, pp 367-374. (2012) PLUS Bhd and OPUS NMM NRO. Inspection manual for pavement maintenance management system. (2000) Jabatan Kerja Raya. Standard specification for road works. JKR/SPJ/2008-S4 Flexible pavement. (2008) UEM Edgenta. Method of statement for proposed pavement rehabilitation and associated works from KM84.10 to KM84.30 north bound, section N2, North South Expressway. (2017) 020023-7