Design principles and Application for CBE 1 Task 1 1.1………………………………………………………………………P4-7 1.2………………………………………………………………………P8-10 1.3………………………………………………………………………P11-14 Task 2 2.1………………………………………………………………………P15-19 2.2………………………………………………………………………P20-23 2.3………………………………………………………………………P24-26 Task 3 3.1………………………………………………………………………P27-29 3.2………………………………………………………………………P30-32 3.3………………………………………………………………………P33-35 Task 4 4.1………………………………………………………………………P36-39 4.2………………………………………………………………………P40-43 4.3………………………………………………………………………P44-47 Task5 5.1………………………………………………………………………P48-51 5.2………………………………………………………………………P52-55 Reference……………………………………………………………….P56 Total number of words: 10,691 2 Introduction This project is large development at Lok Wo Shan, Sha Tin which is near to Wu Kai Sha Railway station. The whole project covering an area of 1,024,394 square feet will be November 2014 completed, It includes 25 towers which contain more 3000 units. Some of building can enjoy the sea view and watch Sui Kung country park view. 3 Task 1 1.1(P1.1) For P1.1, Discuss the planning phase or pre-contract period of construction project. The discussion must include the site investigation and sketch drawing during planning phase in this project. Answer: Pre-contract Process a. This is the period during which the need for the project, the ideas in terms size, function and appearance. b. They are formulated into plans that are capable of being used for the construction of a complete structure. c. Changes to the design will continue to occur throughout this period. Variations are also expected even after the work commenced on site. b1. Employer’s Brief a. On a traditional project the employer will first engage an engineer to work on the outline ideas for the project. b. In some case, the employer may decide to go straight to the contractor for a design and construct service. c. It is much more common to involve the contractor in the pre-contract design on building projects than it is on the civil engineering projects. d. Good up-to-date cost information is essential at this stage if the project is to be successful. The money available may be determined on the basic of the employer capital resources and funding ability. Possible alternative design solutions will need to be considered, along with the appropriate construction costs. b2. Site Investigation a. Assuming that the initial requirements can be agreed, the project moves towards a second stage. During this period, many of the aspects are examined to ascertain the viability of the project. A site survey and investigation should be carried out to 4 determine the nature of the ground and site conditions, and, where possible, to locate the proposed project in the advantageous position on the site. This advantageous position will consider the design restraints that may be present and the necessity to achieve and economic solution and value for money. b. Prior to the commencement of construction, it is necessary to conduct a site investigation. This generally entails drilling below the surface of the site to ascertain the nature and strength of the underlying soil or rock. The nature of the material on which a building is founded will determine the type, layout and size of foundation used. Therefore, a site investigation is necessary before design can be undertaken. c. Hong Kong is founded on dense granite, which provides a very strong foundation, but this may be overlaid by decomposed granite. Large areas of Hong Kong have been reclaimed from the sea and these areas will be compose of layers of fill material perhaps overlying sand or mud. Consequently, every project requires a thorough site investigation normally done by a specialist contracting firm, with the results interpreted by a civil or geotechnical engineer. Available from: https://www.keller.co.uk/sites/keller-uk/files/styles/image/public/2019-02/Lutoncfa-deep-foundations.JPG?itok=AXR1gt7S 5 d. Available from: https://www.nrdcs.com/images/pic6.jpg Most site investigation work will normally be completed in a separate contract before major construction work commences. The investigation is conducted under the supervision of competent personnel such as the engineer or an engineering geologist. The most common methods used are trial pits, borings, drillings and geophysical surveys. e. Bad ground conditions may have implications for the overall aspects of the design. This will inevitably increase construction will be considered. Once the outline design is approved, the scheme should be cost planned to ensure a balanced design that meets the overall requirements of the design brief. The Preliminary Site Investigation b3. Sketch design During this stage the engineer will be able to obtain outline planning approval and meet other statutory requirements regarding the project. There will previously have been discussions with the planners on the possibility of such a scheme being approved. Where necessary, the engineer will have consulted the structure and district plans to ensure at this early stage that the proposed development will not contravene these plans. The major planning problems will thus be solved. a. Construction The construction phase of the project brings the dream to life and demands rigor. It involves checking any document and drawing that the contractor puts forward and ensuring that works are carried out in conformity with the building contract. 6 b. Depending on the type of building contract the architect helps coordinate the works with the different trades, making sure that good common practice is respected, standard and regulations are followed. c. Tracking the project as per the schedule and also recording the delays in project due to un expected issues like strike, weather condition, material short supply etc. d. Keep a track of executed quantity against budgeted quantity. Any escalation in quantity & financial implications in budget to be highlighted to the client in time and getting approval. And maintaining Bills and Reports in proper filing system. 7 Task1 1.2(P1.2) For P1.2, Discuss the design phase or post-contract of construction project. The discussion must include the detail design, working drawing and brief tender discussion during the design phase in this project. Answer: Post-contract is depending on the pre-contract which involves the contract can be allowed for expects variations to occur. And it also mentions supervision, inspections, approvals and estimation. Post-contract Process 1) Construction a. The project should have been completely designed prior to release to the contractor for tendering purposes. Although the contract allows for and expects variations to occur, this should not provide an excuse for a design which only partly finished. b. One of the engineer’s main duties during this stage is to ensure that the contractor has all the information required for construction purposes. In addition, the engineer will be responsible for the smooth running of the works. c. As the work is carried out, the engineer’s role is largely that of a supervisor, ensuring that the contractor complies with all the requirements. During the construction of the works, the quantity surveyor will prepare the valuations for the interim certificate. Certificate is, however, entirely the responsibility of the engineer. It is preferable if the works can be re-measured and agreed soon after they have been completed. d. During the construction stage the responsibility falls on the engineer for the performance of a multitude of duties towards the realization of the project. e. These duties flow from both the service agreement he has entered into with the employer and from those imposed on him by the construction contract entered into between the employer and the contractor. f. The duties that the engineer has to perform in relation to the construction contract are obligations which, of course, in turn flow from the service agreement between the employer and the engineer. The obligations of the engineer towards the 8 employer during this stage for a project of a civil engineering nature may broadly be expressed as follows: g. Advising the employer on the preparation of the formal contract documents relation to the accepted tenders. h. Advising the employer of staff to be employed at site by the engineer (or the employer) for the supervision of the works. i. Preparation of working drawings, bar-bending schedules and other designs and details that are required for the due execution of the works. j. Examining the contractor’s proposals. k. Making such visits to site as the engineer considers necessary to satisfy himself as to the performance of any site staff appointed on the engineer’s advice and to satisfy himself that the works are executed generally in accordance with his designs and specifications and otherwise in accordance with good engineering practice. l. Giving all necessary instructions to the contracts. Such instructions should not significantly increase the cost of the works without prior approval from the employer, unless the circumstances were such that this was not possible. In the latter event the employer should be advised of any increases in cost as soon as it is practicable. As a matter of good practice the engineer should prepare and issue to the employer a revised estimate of the final capital cost every three months on works of any complexity. m. Performing any services which the engineer may be required to carry out under any contract for the execution of the works provided the engineer had initially approved such contracts. n. Providing the employer on completion of the works with such records and drawings as are reasonably necessary to operate and maintain the works in respect of the element of work supervised by the engineer. 9 o. Assisting the employer in settling disputes that may arise between him and the contractor, excepting litigation and arbitration, which are dealt with under a separate arrangement. p. All other duties imposed on the engineer by the construction contract entered into between the employer and the contractor. 2) Maintenance a. The project becomes officially complete when the engineer issues the certificate of substantial completion of the works. The contractor is responsible for making good any of his defects from this date for about 6 months or whatever period of time is stated in the appendix to the conditions of contract. b. The engineer should ensure that all defects are made good prior to the issue of the final certificate. The quantity surveyor during this period will prepare and agree the final account with the contractor’s surveyor or measurement engineer. At the commencement of the defects liability period, one-half of the retention is released to the contractor, with the other half being paid with the final certificate. Although the contractor is contractually responsible for work up to the end of this period, liability under common law will extend for a much longer period. Tender of construction involve characters as the follows: b1. Clients/employer b2. Contractor b3. Consultant b4. Engineers b5. Architect b6. Quantity surveyor b7. Suppliers else And the tender of document must include the following patterns: b8. Articles of agreement b9. Conditions of drawings b10. Specification b11. Bill of quantities 10 Task1 1.3(P1.3) For P1.3, Evaluate how the planning and design phase are coordinated and managed. It should include referencing to the terms and conditions specified in the contract documents. Answer: Coordinated and managed in the planning and design phase should be using tender. The usual contracts in construction projects are: a. b. c. d. e. Between the client and the consultants. Between consultants when one consultant acts as a subcontractor to the lead consultant. Between the client and the main contractor for the construction of the project. Between the main contractor and the subcontractors. Construction contracts consist of a number of contract documents which may include: e1. articles of agreement e2. conditions of contract e3. contract drawings e4. specification e5. bills of quantities. Articles of Agreement a. The articles of agreement are the formal contract signed by the parties which binds the contract documents together. b. the essence of the contract by stipulation the amount (the contract sum) that the employer (client) will pay the contractor for the contractor carrying out. c. Not all standard forms have bills of quantities as contract documents and in such cases, they would not be included in the articles of agreement. Instead, the bills of quantities would be replaced by a specification. Conditions of Contract a. The conditions of contract are the detailed provisions of the contract which seek to determine the obligations of both parties for all the many facets of construction projects and the actions to be taken on the occurrence of any of the many situations which may arise during a project. 11 b. Most importantly the conditions allocate the risk involved in the project between the parties. Upon signing the agreement the parties accept the risk enshrined whining the clauses. Contract Drawing a. b. The contract drawings have to be explicitly identified as such usually by their numbers and are normally listed in the specification or bill of quantities. The drawings will include the general arrangement drawings showing the site location, the position of the works on the site, means of access to the site, plans, elevations and sections. The level of detail of the drawings will vary between projects depending how much detail is in the specification or bill of quantities as together they have to identify what the contractor has to provide. Specification a. The specification is a detailed description of the work, materials and workmanship required for the project, and, which together with the contract drawings, identifies what is to be provided by the contractor. b. It is not usual to have both a specification and a bill of quantities as contract documents for a project. c. If a bill of quantities is used without a specification, the specification is in fact incorporated within the bill of quantities. d. The sequencing of the site operations. e. A method of construction to be adopted f. The details of any facilities to be offered to other contractors or subcontractors working on the site. Bill of Quantities a. A bill of quantities is a schedule of all the items of work required to complete the project. b. Usually the contractor who submits the lowest total process will be awarded the contract. The advantage of using a bill of quantities is that all the contractors are pricing exactly the same items and therefore directly comparable. c. In order to maintain consistency between the descriptions and the method of measurement of items in bills of quantities, documents are prepared using a standard method of measurement. For building work (as opposed to civil engineering), the Hong Kong Standard Method of Measurement for Building Works is currently used. 12 d. When a specification is used rather than a bill of quantities, each contractor competing for the job will prepare his own quantities since the type of information provided by bill of quantities is not available. e. A specification can be used as a contract document together with a bill of quantities. f. The contractor has agreed to construct the project in accordance with the drawings and specification, and the quantities in the bill of quantities are not guaranteed by the client. Alternatively, in such circumstances it may be that the conditions of contract require the whole of the work to be remeasured on completion and priced at the rates in the bill of quantities. g. Good tendering procedure a. Good tendering procedures will take into account the changes in the ways in which projects are procured. b. Use of a standard form or set of conditions, rather than one written solely on behalf of one of the parties to the contract. c. Six firms will be able to secure competition in prices. d. In preparing a short list of tenderers, the following should be considered: the firm’s financial standing and record d1. recent experience of constructing over similar contract periods d2. the general experience and reputation of the firm for similar project types d3. adequacy of the firm’s management d4. adequacy of capacity e. All tenderers must submit their tenders on the same basis. e1. Tender documents should be dispatched on the stated day. e2. Alternative offers based on alternative contract periods may be admitted if requested on the date of dispatch of the documents. e3. Standard conditions of contract should not be amended. e4. A time of day should be stated for receipt of tenders and tenders received late should be returned unopened. 13 f. The tender period will depend on the size and complexity of the job, but should not be less than 4 working weeks, i.e. 20 days. g. The priced bills must remain strictly confidential. h. Corrections must be initialed or confirmed in writing and the letter of acceptance must include a reference to this. i. If the tender under consideration exceeds the estimated cost, negotiations should take place with the tenderer to reduce the price. The quantity surveyor then normally produces reduction or addendum bills. 14 Task 2 2.1(P2.1) For P2.1, Examine the factor that affect the specification of materials. You must explain client requirement or constraints that affect specification of material in your selected contract. Answer: The execution of a construction project requires both design work and the carrying out of construction operations on the site. Traditionally, an employer who wished to have a project constructed would invariably commission an engineer to prepare drawings of surveyor to prepare documentation, such as bills of quantities, on which the contractor could prepare a price. Contractor selection a. Competition b. Negotiation This is the traditional and most popular method of awarding construction contracts. The arrangement is shown in Figure 1.1. In essence a number of firms of known reputation are selected by the design team to reputation are selected by the design team to submit a price. Employer Project Manager Engineer Contractor Other Consultants Sub-contractors Figure1.1 Project management relationship 15 The majority of contract documents state that the employer: a. is not bound to accept any tender b. may choose not to accept the lowest tender c. is not responsible for the cost involved in the preparation of a contractor’s tender The following have been identified as good practice: a. Use of a standard form or set of conditions, rather than one written solely on behalf of one of the parties to the contract. There are clear advantages to all parties in the knowledge that a standard procedure will be followed in inviting and accepting tenders. b. A limit should be placed on the number of firms invited to tender. Six firms will be able to secure competition in prices. The cost of preparing tenders is considerable and this has to be borne by the industry. c. In preparing a short list of tenderers, the following should be considered: c1. the firm’s financial standing and record c2. recent experience of constructing over similar contract periods c3. the general experience and reputation of the firm for similar project types c4. the general experience and reputation of the firm for similar project types c5. adequacy of capacity d. Each firm on the short list should be sent a preliminary enquiry to determine its willingness to tender. The enquiry should contain: d1. Job title d2. Names of employer and consultants d3. Location of site and general description of the works d4. Approximate cost range d5. Principal nominated subcontractors d6. Form of contract and any amendments d7. Procedure for correction of priced bills d8. Contract under seal or under hand d9. Anticipated date for possession d10. Contract period d11. Anticipated date for dispatch of tender documents d12. Length of tender period d13. Length of time tender must remain open for acceptance d14. Amount of liquidated damages 16 d15. Amount of bond d16. Amount of bond e. Once a contractor has confirmed an intention to tender that tender should be made. If circumstances arise which make it necessary to with draw, the engineer should be notified before the tender documents are issued or, at the latest, within 2 days thereafter. e1. The tender period will depend on the size and complexity of the job, but should not be less than 4 working weeks, i.e. 20 days. e2. If a tenderer submits a qualified tender, opportunity should be given to withdraw the qualification without amending the tender figure, e3. If a tenderer submits a qualified tender, opportunity should be given to withdraw the qualification without amending the tender figure. e4. Under English law, a tender may be withdrawn at any time before acceptance. e5. After tenders are opened all but the lowest three tenderers should be informed immediately. The lowest tenderer should be asked to submit a priced bill within 4 days. e6. After the contract has been signed, each tenderer should be supplied with a list of tender prices. e7. The priced bills must remain strictly confidential. e8. The tenderer should be notified and given the opportunity to confirm or withdraw the offer. If it is withdrawn, the next lowest tenderer is considered. e9. The tenderer should be given the opportunity of confirming the offer or correcting the errors. e10. Corrections must be initialed or confirmed in writing and the letter of acceptance must include a reference to this. The lowest tender should be accepted, after correction or confirmation, in accordance with the alternative chosen. e11. If the first alternative has been agreed upon and notified to all tenderers at the time of invitation to tender, the choice facing the tenderer should clearly be to confirm or withdraw. The employer may require a great deal of persuading to stand by the initial agreement in such circumstances. Open Competition a. With this method of contract procurement, the details of the proposed project are often advertised in the local and trade publications. b. This method has the advantage of allowing new contractors or contractors who are unknown to the design team the possibility of submitting a tender for consideration. 17 c. d. Unsuitable firms are removed from the list if the number of firms tendering becomes too large. Factors other than price must also be considered when assessing these tender bids, e. such as the firm which has submitted the lowest tender. They priced documents are checked for the reasonableness of the contractor’s rates and prices and the two parties then meet to negotiate an agreed price for the works. There is an absence of any competition or other restriction, other than the social acceptability of the price. It normally results in a tender sum that is higher than might otherwise have been obtained by using one of the previous procurement methods. Negotiation does, however, have particular applications where: e1. a business relationship exists between the employer and the contractor. e2. only one firm is capable of undertaking the work satisfactorily. e3. the contractor is already established on site (continuation contract) e4. an early start on site is required by the employer. e5. it is beneficial to bring the contractor in during the design stage to advise on constructional difficulties and how they might best be avoided. Design and construct (Design and Build) a. Design and construct projects aim to overcome the problem of the separation of the designing and constructing processes by providing for these two separate functions within a single organization. The single firm employed is frequently the contractor. The contractor may employ civil engineers as in-house designers or be responsible for directly employing a firm of consultants. The major difference is that instead of approaching a firm of engineering consultants, the employer briefs the contractor direct. b. The employer may choose to retain the services of an independent consultant to assess the contractor’s design, to monitor the work on site or to approve payments. c. A design evolved by the contractor is more likely to be suited to the needs of the latter’s organization and construction methodology and this should result in savings in both time and costs of construction. d. Should result in lower production costs on site and an overall shorter design and construction period, both of which should provide price savings to the employer. e. A further advantage to the employer is in the implied warranty of suitability because the contractor has provided the design as a part of the all-in service. The advantages claimed for a design and construct approach therefore include: a. The contractor is involved from the inception and is thus fully aware of all of the employer’s requirements. 18 b. c. The contractor is able to use specialized knowledge and methods of construction in evolving the design. It should be possible to reduce the time from inception to completion due to the d. telescoping of the various parts of the design and construction processes. There can be no claims for delays due to a lack of design information, since the e. contractor is in overall control. There is direct contact between the employer and the contractor. 19 Task 2 Task 2.2(P2.2) For P2.2, Examine the factors that affect the specification of building services. You must explain the impact of legislation on design of service installation and sustainable urban design. Answer: Green Code for Architecture a. The principles of the Building Research Establishment’s Environmental Assessment Method (BREEAM) are: Demolition and reconstruction only if reuse to adaptation or expansion of existing structures is uneconomical or impractical. b. Reduce the need for transport during demolition, refurbishment and construction and tightly control all processes to reduce noise, dust, vibration, pollution and waste. c. Make the most of the site. d. Design the building to minimize the cost of ownership and its impact on the environment over its life span by making it easily maintainable and by incorporating techniques and technologies for conserving energy and water and reducing emissions to land, water and air. e. Use the construction techniques which are indigenous to the area, learning from local traditions in materials and design. f. Build to the appropriate quality to last. The building life depends greatly on the form, surface treatment and the method of assembly of which of the materials used. g. Avoid using materials from non-renewable sources or which cannot be reused or recycled, especially in structures which have a short life. h. Avoid using materials from that cannot be reused or recycled or non-renewable sources, especially with short life spans in structures. 20 Green Building a. Measures for green buildings can be divided into four areas: a1. Reducing energy in use a2. Minimizing external pollution and environmental damage a3. Reducing embodied energy and resource depletion a4. Minimizing internal pollution and damage to health b. Green design emphasizes many new environmental resources and concerns for occupant health as below points: (Ray Kuruvilla George, 2006) b1. Reduce human exposure to harmful substances. b2. Save non-renewable energy and scarce materials. b3. Minimize the impact of energy and material life cycle on ecology. b4. Use renewable energy and materials collected sustainably. b5. Protect and restore local air, water, soil, flora and fauna. b6. Support pedestrians, bicycles, public transportation and other vehicles that substitute fossil fuels. Sustainable Design a. Long-term costs: economy cost, labor cost and environment cost. b. Sustainable design is the careful integration of architecture with structural, mechanical and electrical engineering. The Rocky Mountain Institute outlines five elements for sustainable design: (Rocky Mountain Institute, 1998) a. Planning and design should be thorough. Sustainable design is "front loaded" compared with traditional design. Early decisions have the greatest impact on energy efficiency, passive solar design, daylighting, and natural cooling. b. Sustainable design is more of a philosophy of building than a prescriptive building style. Sustainable buildings don't have any particular look or style. c. Sustainable buildings don't have to cost more. nor are they more complicated than traditional construction. d. Integrated design, that is design where each component is considered part of a greater whole, is critical to successful sustainable design. 21 e. Minimizing energy consumption and promoting human health should be the organizing principles of sustainable design. The other elements of design can be organized: energy saving architectural features, energy conserving building envelope, and energy-efficient and health-promoting mechanical, electrical, and plumbing systems. Understanding Place Sustainable design begins where we know each other. If we are sensitive to the nuances of a place, we can live without destroying it. Knowing the location helps determine design practices, such as the orientation of the building on the building, the protection of the natural environment, and the use of public transportation. Connecting with Nature Regardless of whether the design location is an inner city or a building in a more natural environment, the connection with nature can regenerate the designed environment. Effective design helps us understand our place in nature. Understanding Natural Processes There is no waste in nature. By-products of one organism become food for another. In other words, natural systems are made up of closed loops. By working with life processes, we respect the needs of all species. By regenerating processes rather than exhausting them, we become more active. Make natural cycles and processes visible, and reinvigorate the designed environment. Understanding Environmental Impact Sustainable design attempts to understand the impact of design on the environment by assessing the inherent energy and toxicity of the site, materials, and energy efficiency of the design, materials, and construction technologies. Negative environmental impacts can be mitigated through the use of sustainably harvested building materials and finishes, materials with low toxicity in manufacturing and installation, and recycling of building materials at the job site. Embracing Co-creative Design Processes Sustainable designers find it important to listen to every voice. Collaboration with system consultants, engineers, and other experts is carried out early in the design process, not after the fact. Designers are also listening to the voice of the local community. Designing diagrams for end users (community residents or office owners) has become standard practice. 22 Understanding People Sustainable design must take into account the broad cultures, races, religions and habits of the people who will use and live in the built environment. This requires keen awareness and compassion for the needs of people and communities. Example: Microclimate l Topography l Light-colored surfacing Site Design l Solar orientation l Pedestrian orientation Infrastructure Efficiency l Water supply and use l Wastewater collection Land-Use l Use density l Use mix Transportation l Integrate On-Site Energy Resources l Geothermal/Groundwater l Surface water Some of the tallest building in Hong Kong such as the Hong Kong and Shanghai Bank and the Bank of China have been constructed in structural steel. Available from: https://i.pinimg.com/474x/8d/f6/31/8df631889c1088b0fd68b3f19ed30532--normanfoster-architecture-drawings.jpg 23 Task 2 Task 2.3 (P2.3) For P2.3, Explain the financial implication of specifying materials and building services. You must explain three different types of financial implication in this contract. Answer: Finance a. The usual way of paying the contractor for the construction work is through monthly or stage payments. b. These payments help the contractor to offset the financial borrowing that is required to pay wages, salaries, goods, components and materials. The following are financial factors to consider: a. payments systems b. financial soundness of parties c. financial remedies d. contract funding Below table offers a checklist of questions to help to determine an appropriate contract strategy. 24 Type of contract a. Measurement Contracts allow seating to begin early before the design is completed, and make changes to the project relatively easy. However, due to the unknown engineering cost, some risks will inevitably be brought to customers. In fact, the client bears b. c. any unknown risk, and although this may cause the contractor to provide a competitive price, the level of customer uncertainty means that, except for civil engineering projects, measurement contracts are rarely signed. (Designing Building Wiki, 2017) Cost Reimbursement Price to be paid is determined on the basis pf the actual cost incurred by the contractor in carrying out the work, plus an agreed amount to cover overheads and profits. This arrangement is used where the requirement are only general terms according to the nature of work and the shortage of time. Re-measurement Employer can’t determine requirement is used and not even sufficiently for approximate quantities to be prepared. A set of preliminaries and preambles and a form of tender will also be needed. Term contractor is one 3 where contractor is in contract with the client for the entire contract period. For 3 year to execute any maintenance repair/for work where the extent of work is not yet known. It consists of a list of measured items with units of measurement stated against each, but with no quantities give. Jobbing order contract where a purchasing order or job order is raised to execute some simple work. Lump Sum contract a. The Lump Sum Contract can sometimes be called 'Stipulated Sum' and is the most basic form of agreement where the contractor/supplier agrees a fixed lump sum price to undertake all the specified contract works and the employer agrees to pay this price upon completion of works. b. The Schedule of Rates may be provided by the employer but quantities are usually binding upon the contract drawings and specifications. The Schedule of Rates can be used for payment purposes and the rates used for assessments of design changes and additional work. Advantages: a. Lower financial risk to Employer. b. Higher financial risk to Contractor. c. Minimum Owner supervision related to quality and schedule. 25 d. Contractor has higher incentive to achieve earlier completion and better performance. e. Contractor selection is relatively easy. Disadvantages: a. b. c. d. e. f. g. Changes difficult and costly. (but it usually is) Need to substantially complete design prior to bidding. Contractors tend to choose the lowest methods or materials are meet the specifications. Hard to build relationship. Each project is unique. Bidding expensive and lengthy. Contractors may include high contingency within each Schedule of Rate item The Construction Process The complexity of construction in Hong Kong is compounded by: a. The difficulty of sites and ground conditions. Hong Kong builds on sites which would not be considered for development in most other countries b. In time of high demand, there is variably a labor shortage and a restriction on importing labor c. The high speed of construction that is demanded by client, both public and private d. The congested of most sites due to high plot ratios. The logistics of site transport both horizontal and vertically are very difficult e. Heavy dependence on imported materials which can create uncertainty in delivery. Construction Costs The costs for the types of projects given below are averages based on fixed price competitive tenders and no more than rough guides. It must be understood that the actual cost of a building will depend upon the individual design and many other factor such as size, plan shape, height, location and specification. 26 Task 3 Task 3.1 For P3.1, Discuss the environmental factors that affect construction projects. You must discuss and specify any sustainable construction or sustainable development in this project. Answer: Sustainable Construction Sustainable construction is defined as the creation and responsible management of a healthy built environment based on resource efficient and ecological principles. a. Resource efficient and ecological consumption b. Minimizing non-renewable resource consumption c. Enhancing the natural environment d. Eliminating or minimizing the use of toxins According to an Organization for Economic Co-operation and Development (OECD) Project, “Sustainable building" can be defined as the building with the least impact on the building and the natural environment, including the building itself, its surroundings, and the wider regional and global environment. Sustainable building can be defined as a building practice that strives for overall quality (including social, economic and environmental performance) in a wide range of ways. Therefore, rational use of natural resources and proper management of building stock will help to save scarce resources, reduce energy consumption and improve environmental quality. (Raymond Wong wai-man, 2018) Sustainable building a. Sustainable building involves considering the entire life cycle of buildings, taking environmental quality, functional quality and future values into account. b. In strict quantity terms, the building and housing market is now saturated in most countries, and the demand for quality is growing in importance. c. Governments will be able to give a considerable impulse to sustainable buildings by encouraging these developments. The OECD project has identified five objectives for sustainable buildings: c1. Resource Efficiency c2. Energy Efficiency (including Greenhouse Gas Emissions Reduction) c3. Pollution Prevention (including Indoor Air Quality and Noise Abatement) c4. Harmonization with Environment (including Environmental Assessment) 27 c5. Integrated and Systemic Approaches (including Environmental Management System) Sustainable design principles a. economy of resources Ø energy, water, and material b. life cycle design Ø consider environmental quality, functional quality and future values humane design Ø reduce impact on nature Ø ensure human comfort and health c. Resource Efficiency a. combines the efficient use of both economic and ecological resources b. sustainable management of natural resources Ø conservation and sustainable use of biodiversity Ø the ‘ecosystem’ provides services (e.g. purification of water supplies by aquatic life-forms) Ø adoption of more sustainable patterns of production and consumption c. Aim Ø to reduce the demand and the costs for energy, water, and materials d. Results Ø monetary savings which benefit the local economy Ø reduced environmental impact Ø conservation of resources e. Integrated resources planning (IRP) & management f. Major factors Ø appropriate material selection Ø waste minimization Ø recycling of building materials Ø efficient use of water g. They also promote Ø increased durability of buildings Ø cyclical utilization of materials Environmental Architecture a. Healthful Interior Environment. Measures are to be taken to clean and revitalize interior air with filtration and plantings. b. Energy Efficiency. 28 c. d. e. Ensure that the building's use of energy is minimal. Environmental form. All possible measures should be taken to link the form and plan of the design to the site, area and climate. Good Design. Achieve an efficient, long lasting and elegant relationship of use areas, circulation. Ecologically Benign Materials. Use building materials and products that minimize destruction of the global environment. Use of Material a. The exterior colour theme of the building is in warm and the building and landscape are designed to be compatible and harmony with the adjacent public park. The material used are kept basic concrete; glazed tile; reconstituted stone; glass and steel. b. It’s the architect intenion to stick to materials we know to reuse and dispose of then expent with new potentially hazardous ones which have only been in use for a short time. c. The mternal partitions for office area are re-cycled light weight cement panels previously used as hoarding form and repectitive details minimize the use of additional timber formwork limber used inside the building are from sustainable sources. Electronic ballast are used to cut down power consumption of light fitting and non-CFC refrigerant has been adopted for air-cool chiller. Available from: https://greenbuildinginsider.com/6/importance-sustainable-building-practices 29 Task 3 Task 3.2 (P3.2) For P3.2, Evaluate environmentally responsible methods for disposing of waste materials. You must explain disposal of waste materials during construction process or disposal of waste materials during life of the building. Answer: Waste Management Strategies a. Waste prevention b. Recycling construction and demolition materials c. Architectural building material reuse (include adaptive reuse, reuse of recycled materials and conservative disassembly) d. Design for building material recovery (destruction, durability and adaptive reuse) Available from: https://www.cleantechloops.com/recycling-construction-wastes/ Important factors a. On-site collection & storage space b. Sorting & separation (paper, glass, plastic, metal Available from: https://www.sheltonmart.com.my/stainless-steel-bin/94-stainless-steel-recycle-bintriangle-4-in-1.html 30 Waste hierarchy a. Sustainable development b. Reduction c. d. On-site reuse On-site recovery e. f. g. Off-site reuse Off-site recovery Landfill Water Conservation Methods a. Leak detection & prevention b. Efficient fixture/appliances (e.g. low-flow toilets) c. Correct use of appliances (e.g. washing machine) d. Water use of landscaping & irrigation Green design issues a. Greywater reuse and rainwater recycling b. Composting toilets & wastewater treatment Available from: https://home.howstuffworks.com/green-living/composting-toilet1.htm Sources of solid waste a. Residential & commercial b. Industrial & agricultural c. Construction 31 Element of solid waste storage, collection a. Waste generation, on site storage, collection b. Transfer and transport c. d. Processing and recovery Disposal (e.g. landfill, incineration, composting) Available from: https://constructionreviewonline.com/2018/03/5-waste-management-tips-for-theconstruction-industry/ Recycling organic waste a. Make use of organic nutrients in garbage, human waste, and sewage a1. For growing crops/flowers in gardens a2. For feeding to farms (e.g. urban farming) b. Food gardens and city farmers Available from: https://penasdisposal.com/organic-recycling/ 32 Task 3 Task3.3 (P3.3) For P3.3 Evaluate environmentally responsible methods for promoting environmental efficiency. You must explain different form of construction or new and renewable sources or use of recycled material in this project. Available from: https://www.researchgate.net/profile/Sam_C_M_Hui/publication/252462829/figure/fi g1/AS:298235877969920@1448116382049/Building-life-cycle-and-sustainableconstruction.png Environmental Impact Assessment Environmental Impact Assessment (EIA) Is a process that identifies and assesses possible environmental impacts of a proposed project at an early stage of the planning process. The environmental impact assessment identifies measures that can be taken to avoid negative environmental impacts or reduce them to acceptable levels before processing them. Therefore, EIA represents a proactive approach to preventive environmental management and protection. Assessment Methodologies a. Life cycle energy audit a1. Initial embodied energy a2. Recurring embodied energy a3. Operational energy a4. Greenhouse gas assessment a5. Lighting, thermal and ventilation audit a6. Life cycle costing audit a7. Post occupancy evaluation 33 b. c. d. e. f. Preservation criteria b1. Species richness, abundance, diversity Ecological diversity b2. High number of endemic species & important pool b3. Habitat Three forms of biodiversity c1. Genetic c2. Species c3. Ecosystems Natural environment to protect d1. Grassland d2. Forest d3. Mangrove Impact of urban development e1. Direct species loss e2. Habitat destruction e3. Habitat destruction (pollution, decrease in size) due to disturbance, noise, light e4. Food wed disruption Impact of urban development f1. Avoidance: No development, Alternative f2. Reduction minimize impacts f3. Compensation (on site/offsite) f4. Habitat creation/restoration Design The client must awareness and goal setting: green vision, project goals & green design criteria. Unlike building projects, where the projects often determine the constructional methods to be used, civil engineering projects are heavily dependent upon particular contactor’s method of working. Try the best effort, to implicate the cost of the various solutions to determine that the cost remains on the target. The Principles of Sustainable Design: a. Understanding Place b. Connecting with Nature c. Understanding Natural Processes d. Understanding Environmental Impact e. Embracing Co-creative Design Processes f. Understanding People 34 Figure is a chart of the criteria, grouped by the affected building life-cycle phase. This chart helps compare the sustainable qualities of different materials used for the same purpose. The presence of one or more of these "green features" in a building material can assist in determining its relative sustainability. GREEN FEATURES Manufacturing Process (MP) Building Operations (BO) Water Management (WM) Waste Reduction (WR) Energy Efficiency (EE) Biodegradable (B) Pollution Prevention (P2) Water Treatment & Conservation (WTC) Recyclable (R) Recycled (RC) Nontoxic (NT) Reusable (RU) Embodied Energy Reduction (EER) Renewable Energy Source (RES) Others (O) Natural Materials (NM) Longer Life (LL) Different form of construction Curtain walling Many office and commercial buildings in Hong Kong are clad with curtain walling. Basically, a curtain wall is a thin layer (or skin) on the outside of a building which is supported from the structural frame of the building. Most curtain walls are made up(in part or in whole) of reflective glass. The reflective property of the glass is helpful in reducing thermal transfer, and reduces the cost of maintaining the building internal environment. Available from: https://www.reynaers.com/en/products/curtain-walls 35 Task 4 Task 4.1 (P4.1) For P4.1, Explain the roles and responsibilities of all parties involved in the planning and design phase. Answer: Client a. Define the extent of the project and the functions it is to perform b. Provide information required by the engineer during design and construction c. Obtain the necessary legal authority to allow the construction of the project d. Secure funding for the project and ensure that this is available at the appropriate times e. Acquire the necessary land for development An Engineer (Designer) The extent of professional service offered by the engineer is specified in agreement between him and the promoter. The engineer performs the feasibility study, design the works, prepares contract documents, ar4ranges the contract and supervises construction works. Organization for large project involving tunneling and bridgeworks 36 Senior Resident Engineer A senior resident engineer is usually appointed to head the whole site organization. Each section of works is then under the supervision of a resident engineer, supported by inspectors and works supervisors and so on. In some cases, specialists are required to reside on site depending on the nature of the works and the site conditions. Resident Engineer (RE) The resident engineer is an agent of the engineer. He may be and engineer seconded from the engineer’s office or may be recruited from an outside firm. In some cases he may be employed and paid by the promoter. Delegation of Power The resident engineer’s responsibilities are delegated by the engineer. Decisions made by the resident engineer have the same effect as if made by the engineer. The extent of delegation of the engineer’s power, and the duties of the resident engineer are listed in an appointment letter. himself. However, the engineer always has the final judgment. Assistant Resident Engineers Assistant resident engineers are assistants to the resident engineer in carrying out normal day-to-day business. Most of the assistant resident engineer’s duties are concerned with document preparation. This includes: a. re-designing of minor works b. report writing c. tests recording d. measurement of quantities e. keeping survey records with the assistance of the survey officer Duties of the Resident Engineer The main duty of the resident engineer is to see and check that the materials used, the workmanship employed and the works constructed by the contractor are in accordance with the specification and conditions of the contract. In addition, he has to ensure that the contractor has carried out the obligations required in the contract. 37 a. The actual extent of the resident engineer’s duty of course varies depending on the type of contract. In general, the main duties are grouped into the following sections: a1. Administration a2. to organize and assign duties to site staff and to ensure that all construction works are properly supervised. a3. to perform tests so as to ensure that the raw materials and the final product comply with specifications, both on site and at the place of manufacture; a4. to watch out for defected works and to ensure that appropriate remedial actions are proposed an taken by the contractor; a5. to examine the construction methods proposed by the contractor; a6. to examine the construction methods proposed by the contractor; a7. to redesign the works when it is necessary; a8. to check if sufficient materials of suitable quality are ordered and delivered to the site at the right times a9. assessment and payment a10. to assess and finally agree with the contractor on the quantity of work which is completed to specifications; a11. to check the day works, materials, etc. on site, so that based on the resident engineer’s recommendation, the engineer can certify payments. a12. Records a13. to keep a diary recording each stage of the history of construction and events on site such as visitors, accidents, stop of works, etc. The Inspector and the Works Supervisor The inspector’s main duty is to check the materials and workmanship provided by the contractor. In the past he was often a tradesman who got promoted by acquiring knowledge and experience of trades, materials and methods. Assistant Inspector of work They assist to the Inspector of work check the material and workmanship provided in the contractor. Works Supervisor The duty of a works supervisor is, by constant checking, to ensure that the contractor’s staff are constructing the work as specified in the contract by using the right amount of suitable materials. A works supervisor should have a basic technical training qualification and several years’ experience of detailed construction in a particular activity. 38 A works supervisor, who is responsible to the inspector, should spend most of his time outside the office observing and recording progress and production on the spot and ensuring that the contractor’s foreman gives proper instructions to the labor. 39 Task 4 Task 4.2 (P4.2) For P4.2, Explain the roles and responsibilities of all parties involved in the production phase. Answer: The contractor is a firm which undertakes to carry out construction work laid down in a contract signed between the contractor and the promoter (client). The client accepts the tender submitted by the contractor, the contractor will commence planning the provision of labour, materials and plant as required for the construction master programme. For large construction contracts (such as new town development involving a large number of bridge works and road works) in which different types of works are handled simultaneously, the previous organization chart no longer applies. Generally, it depends on the value of the contract, the duration of the contract, the location of the site, and the scope and complexity of the project. In small contracts, such as remedial work in slope protection, there is no diversity of work, and although the contractor may need to perform engineering and other administrative duties, it may be sufficient to have one person represent the contractor. Site Organization chart for large project 40 In a contractor’s site organization key personnel include: a. Site Agent a1. The main person in charge of the on-site representative contractor is the onsite agent. In some contractors, this position is called a project manager. a2. The qualification and experience of the site agent is always specified in the contract. a3. After the contractor receives the rejection notice, the engineer shall replace the on-site agent with another more capable agent. a4. As the site's chief administrator, the site agent is responsible for directing and controlling all construction projects. His main responsibility is to ensure that all work is performed as required by the contract. a5. The company's policy and the nature of the contract, agents can have the right to recruit necessary personnel, rent machinery and purchase materials. a6. Agents are usually experienced engineers in the construction of civil engineering projects. As the head of the construction team, he must be able to demonstrate his ability to organize and make informed decisions. a7. A good agent helps not only the contractor but also the engineer. Very often the site agent may discover omissions or errors in the contract drawings, which, if made known to the engineer early, could avoid delay and minimize extra cost for additional work. a8. For a large job, a deputy agent (sub agent) is sometimes appointed to assist the agent. Again, if the extent of the works is still too large, a number of sub-agents will be appointed to take direct control of specific areas of the job. b. Sub-agent b1. Assist the agent, a number of sub-agents will be appointed to take direct control of specific area of the job. Sometimes, a sub-agent may take up administrative functions. c. Site Engineer c1. The site engineer is responsible for the engineering aspect and in particular the accuracy of construction work. He has to check all information in the drawings issued by the engineer and to liaise with the foreman to plan the materials and plant requirement before work can begin. c2. The design of engineering work on site is also one of the site engineer’s duties. The engineering works include temporary works such as the construction of 41 approach bridges, falseworks, site drainage, alignment and layout of access roads. d. Plant manager d1. In modern construction projects the use of plant helps to speed up the completion time. The contractor’s head office usually determines the type and the number of plant to be used for a particular project. d2. It is also his job to have the plant available as stated in the construction programme proposed by the agent. He is kept informed of the long-term planning of the project and of short-term requirements. e. The Office Manager/clerk e1. The office manager is responsible for the efficient administration of nontechnical matters on site. The extent of the administration varies considerably depending on the location of the site and the complexity and service requirements of the works. His basic duty is to carry out the paper work such as issuing purchasing orders, arrangement payment of wages and dealing with all correspondence. f. General foreman f1. The general foreman is responsible for issuing instructions to section foremen and ensuring that the works are constructed according to the agent’s construction programme. He is the key person in controlling the execution of works by mobilizing the labour force as required. He spends some of his time visiting every part of the site every day. He has to advise the agent about the requirement of materials, the plant manager about the type of plant needed and the site engineer about the setting out and recording of the required lines and levels. f2. The general foreman usually has extensive practical knowledge in various construction skills. g. Quantity surveyor g1. During the course of construction, the contractor receives payment, usually on a monthly basis, according to the amount of work completed. The quantity surveyor measures this is meaning the quantity of completed site work. The amount of work must be agreed upon by the resident engineer’s staff. 42 g2. The quantity surveyor is also responsible for other duties such as preparing information about the financial state of the contract and dealing with matters in connection with costs, such as claims and extra work agreements. h. Land surveyor h1. Setting out works and making sure that works are constructed at correct levels are the responsibilities of the contractor. i. Ganger/Chainmen i1. Actually, who is carrying out such works of land surveyor. Theodolites, line tapes and steel tapes are essential tools for accurate surveying. 43 Task 4 Task 4.3 (P4.3) For P4.3, Evaluate the corporate and personal responsibilities of all parties involved in construction projects. You must evaluate current legislation applicable to each stage of this project (Planning, development, design, production). Answer: In HK, General Conditions of Contract (GCC) (clause 10 to 38). Contractor’s General Responsibilities (clause 10) Design responsibility a. Design b. Specification There is provision in the conditions of contract to cover permanent works designed by the contractor. The contractor is also not responsible for the adequacy of the temporary works designed by the engineer. The responsibility for most temporary works will be borne by the contractor. The provision of temporary works will be greatly influenced by the methods that the contractor chooses to carry out and complete the works. Contractor responsible for safety of site operations The contractor must be fully responsible for temporary or permanent works during the construction period. Performance Security It has become common today for employers to require performance bonds for construction contracts. This is to ensure that the contractor completes the works. The bond provides for a third party, often a bank, to provide the additional funds that may be required to complete a project in the event of the contractor becoming insolvent or for some other reason not completing the works. Under the Conditions of Contract the employer can request such a security for up to 10% of the tender total. This will be required within 28 days of the awarding of a contract to a contractor. The security for the bond must be provided in the Appendix to the Conditions of Contract. It is usual for the fees associated with a bond to be paid by the contractor, unless the contract provides otherwise. 44 A contractor may be prohibited from even tendering for a project where it is known either that it will not be possible to arrange a bond, or that it will be prohibitive in terms of its fee. Provision and interpretation of information (clause 11) a. b. Nature of ground, subsoil and hydrological conditions Pipes and cables in, on or over the ground This information will have been obtained by the employer through a site investigation prior to the design of the works. It is the contractor’s responsibility to correctly interpret this for the purpose of constructing the works. If the contractor is responsible for designing any part of the work, it must also be used. Basic and sufficiency of tender The contractor will therefore formulate the tender on the basis of: a. Information supplied to them from the employer b. Inspection of the site c. Examination of the contract documents d. Correctness and sufficiency of the rates and process in the bills of quantities which will cover all of the contractor’s obligations. Adverse Physical Conditions and Artificial Obstructions (clause 12) During the execution of the works the contractor may encounter physical conditions or artificial obstructions. If an experienced contractor cannot reasonably foresee these, the engineer should be notified in writing. These conditions exclude weather conditions and conditions due to bad weather. The use of this clause on major civil engineering works is common in the support of claims for additional expense. This is due in part because of the nature of civil engineering works and the fact that much of the work is at or below the ground level. More sophisticated means of determining the full extent of the ground conditions are constantly being brought in to use. Intention to claim At the time of writing to the engineer the contractor should state whether a contractual claim is to be made. The claim may be in the form of an additional payment (clause 52) or an extension of time (clause 44). 45 Measures being taken The contractor should also provide details to the engineer of any anticipated effects of the adverse physical condition. The contractor should also inform the engineer of the: a. b. c. Estimated costs involved Extent of anticipated delay Effects upon the works Action by Engineer The engineer should consider whether to a. Ask the contractor to investigate and report upon possible alternative measures that might be used together with their costs and timing b. Give written consent to the measures notified by the contractor c. Give the contractor written instructions on how the adverse physical condition is to be dealt with d. Suspend the works under clause 54 e. Issue a variation under clause 60 Conditions reasonably foreseeable The engineer may decide that the physical conditions or artificial obstructions could have been reasonably foreseen by an experienced contractor. Works to be to satisfaction of the engineer (clause 13) The materials, equipment, and labor provided by the contractor (clause 8) and the manner, speed, and speed of construction of the works are works and are performed in a manner acceptable to the engineer. (Ir David Y.K. Leung, 2010) Removal of contractor’s employees (clause 18) a. Misconduct b. Incompetence c. Negligence d. Failing in the performance of duties e. Failing to conform with particular provisions regarding safety f. Persisting in conduct which is prejudicial or health 46 Setting out (clause 19) The engineer is responsible for providing the contractor with all the information necessary for the contractor to set out the works. Safety and security (clause 20) The contractor shall give full consideration to the safety of all persons entitled to work on site during the entire project. Employer’s responsibilities The employer may employ other contractors or use a form of direct labour for certain aspects of the work (clause 31). 47 Task 5 Task 5.1 (P5.1) For P5.1, Discuss the modern technology available to designers, planners and builders. You must detail discuss the modern methods of construction or effect of design on this project. Answer: Intelligent building (IB) a. first coined in USA in early 1980s b. its definition/model is evolving b1. automated buildings (1981-85) b2. responsive buildings (1986-91) b3. effective buildings (1992-) c. development of IB c1. closely linked with computers and information technology (IT) c2. but, IB ≠ high-tech building Major IB features a. automatic reactions (adjust internal conditions) b. effective communication & IT management c. responsiveness to changes Integrated pyramid a. single function/dedicated systems b. multifunctional systems c. integrated systems d. computer integrated building IB in Europe study It turns out that Proved provides a responsive, effective and supportive intelligent environment in which organizations can achieve their business goals. Three main goals: a1. building management a2. space management a3. business management 48 An intelligent building does not make occupants seem stupid. a. maximizes the efficiency of its occupants and allows effective management of resource with minimum life costs. b. more responsive to user needs and has the ability to adapt to new technology or changes in the organizational structures. Intelligent and Green Available from: https://slidesplayer.com/slide/11396705/ Key issues for intelligent buildings a. site (access, local amenities, car parking) b. shell (thermal strategy, structure, floor layout) c. skin (services strategy, solar control) d. building services (HVAC, small power, cabling) e. information technology (communication, space f. management, network) Criteria: business value/benefits, efficiency and effectiveness Common objectives a. responsive (to user needs / to climate) b. efficient (building design & systems) c. effective (operation & management) d. better integration (with IT & within systems) 49 Trends a. smart buildings and Internet connectivity b. sustainability in business (quantifying the benefits) Smart & Green Building a. b. c. d. e. f. g. energy efficient use renewable energy green building materials low environmental impact responsive to climate/site responsive to user needs healthy environment Intelligent building Model Available services from: https://www.esdglobal.com/news/article/754-intelligent-building- Energy information system a. There is widespread recognition that there is often a large gap between building energy performance as designed, and measured post-occupancy energy consumption. b. EIS is the idea that building are complex, dynamic systems, and that realizing optimal energy performance requires higher-granularity data and more time analysis than can be gained monthly utility bills. 50 c. EIS are critically important because they can process data into actionable information and thereby serve as the information link between the primary actors who affect building energy efficiency d. EIS are broadly defined as performance monitoring software, data acquisition hardware, and communication systems used to store, analyze, and display building energy data. 51 Task 5 Task5.2 (P5.2) For P5.2, Evaluate the effect of technological advances on the various phases of construction projects. You must evaluate use of computer systems or development of new materials in this project. Answer: Intelligent Buildings are the centralized control of heating, ventilation and air conditioning, lighting and other systems of buildings through building management systems or Building Automation Systems (BAS). The goals of building automation are to improve occupant comfort, the efficient operation of building systems, reduce energy consumption and operating costs, and improve the useful life of utilities. Building automation is an example of a distributed control system-a computer network of electronic equipment designed to monitor and control machinery, safety, fire and flood safety, lighting (especially emergency lighting), HVAC and humidity control and ventilation systems in buildings. (Wiki, 2020) Intelligent Building at work Available from: https://electrical-engineering-portal.com/conceptual-model-of-smartgrid-framework-by-iec 52 Integrated Intelligent Engergy Saving Solution for Electrical System in Building Available from: http://takamulsystems.com/Solution%20Smart%20BMS.html Office space and commercial buildings a. Speculative offices (USA or European) b. Organizational/functional requirements c. Impact of IT and business strategy Major systems a. Building Automation System (BAS) b. Office Automation System (OAS) c. Communication Automation System (CAS) Typical features a. Building control & energy management b. Lighting management c. Addressable fire alarm d. Structured cabling e. Voice/data/image communication 53 f. g. h. Office automation Facility management & cad system Multi-function cardkeys Current and future development a. b. c. d. e. f. New ways of working More interaction More collaboration (physically or electronically) More individual autonomy More group spaces More shared spaces Intelligent Building at Home Available from: Platform.png https://onlinehubng.com/wp-content/uploads/2019/04/WebNMS- Present technology a. Phones and intercoms b. Home automation c. Video distribution (e.g. Tv) d. Video surveillance (e.g. Security) e. Structured wiring f. Home theater, game station 54 Future home a. home networking Home network today usually comprised of an Internet connection to the house, b. c. d. e. f. which links to a wireless router with which everything else to smartphone, Internet appliances They can seamlessly connect with each other rather than beings isolated. Interaction are achieved between home appliance and human being via terminal including mobile Webcam c1. IP webcam is based on an inexpensive ARM development board, which hosts its own web server to display the webcam feed. c2. The server has ability to either to a wired router or to act as a wireless access point in order for to connect and control its function via Wi-Fi enabled device. Video walls d1. Video wall is a special type of multiple computer monitors, video projectors or televisions, or overlapped to form a large screen. d2. Typical display technologies include LCD panels, Direct View LED arrays, hybrid projection screens, laser fluorescent displays, and rear projection. (Wiki, 2020) Home office Virtual clinic/hospital 55 Reference Task 2.2 Ray Kuruvilla George (2006) Science and Technology for Sustainable Development Rocky Mountain Institute (1998) Green Development: Integrating Ecology and Real Estate Task 2.3 Designing Building Wiki (2017) Measurement contracts [online] https://www.designingbuildings.co.uk/wiki/Measurement_contract Task 3.1 Mr Raymond Wong wai-man (2018) Green and Sustainable Buildings Design Criteria and Practices in Hong Kong [online]http://personal.cityu.edu.hk/bswmwong/contents/resources/city_env_studies/I ntroduction_of_Green_bldg_design_and_practises_in_HK.pdf Task 4.3 Ir David Y.K. Leung (2010) A Practical Approach to Conditions of Contact for Civil Engineering Works [online] https://hkupress.hku.hk/pro/con/367.pdf Task 5.2 Wiki, 2020, Building Automation [online] https://en.wikipedia.org/wiki/Building_automation Wiki, 2020, Video Wall [online] https://en.wikipedia.org/wiki/Video_wall 56