Uploaded by moham akh

IEEE-RTS-24

advertisement
The IEEE Reliability Test System
1
System Description
The 24 bus system [1] is illustrated in Figure 1. The slack bus of the system is node 13.
Figure 1: 24-bus power system – IEEE One Area RTS-96
1
1.1
Unit Data
Tables 1-3 present the generating units’ data of the power system. The generating units offer a single
block of energy, up and down reserve capacity. Table 1 provides the technical data of generating
units, Table 2 categorizes the units in different types and Table 3 provides the costs and initial state
of the generating units at the beginning of the scheduling horizon. The data is based on [1], [2], [3].
U nit
N ode
Unit 18
Unit 21
Unit 1
Unit 2
Unit15b
Unit 16
Unit 23a
Unit 23b
Unit 7
Unit 13
Unit 15a
Unit 22
18
21
1
2
15
16
23
23
7
13
15
22
Table 1: Technical Data of Generating Units
Pmax
Pmin
R+
R−
RU
RD
MW
MW
MW MW MW/min MW/min
400
400
152
152
155
155
310
350
350
591
60
300
100
100
30.4
30.4
54.25
54.25
108.5
140
75
206.85
12
300
0
0
40
40
30
30
60
40
70
180
60
0
0
0
40
40
30
30
60
40
70
180
60
0
6.67
6.67
2
2
3
3
3
4
7
3
1
5
6.67
6.67
2
2
3
3
3
4
7
3
1
5
UT
h
DT
h
1
1
8
8
8
8
8
8
8
12
4
0
1
1
4
4
8
8
8
8
8
10
2
0
Table 2: Unit Type
U nit T ype
U nit(s)
Nuclear
Coal/Stream
Coal/3 Stream
Oil/Stream
Hydro
U nit
18 21
1 2 15 16 23a
23b
7 13 15
22
Table 3: Costs and Initial State of Generating Units
C
Cu
Cd
Csu
Pini
Uini
$/MWh $/MW $/MW
$
MW
0/1
Unit 18
Unit 21
Unit 1
Unit 2
Unit15b
Unit 16
Unit 23a
Unit 23b
Unit 7
Unit 13
Unit 15a
Unit 22
5.47
5.47
13.32
13.32
10.52
10.52
10.52
10.89
20.70
20.93
26.11
0.00
0
0
15
15
16
16
17
16
10
8
7
0
0
0
14
14
14
14
16
14
9
7
5
0
2
0
0
1430.4
1430.4
312
312
624
2298
1725
3056.7
437
0
320
320
121.6
121.6
0
124
248
280
0
0
0
240
1
1
1
1
0
1
1
1
0
0
0
1
Tini
h
50
16
22
22
-2
10
10
50
-2
-1
-1
24
A positive Tini shows the time periods that the generating unit has been online at the beginning
of scheduling horizon. A negative one shows the time periods that the generating unit has been
offline at the beginning of scheduling horizon.
1.2
Load Data
In Figure 2, the load profile is illustrated. Table 4 provides the total system demand per hour and
Table 5 presents the node location of the loads, as well as load at each node as a percentage of the
total system demand. The load data is based on [2].
System Demand
3000
System Demand [MW]
2500
2000
1500
1000
500
0
5
10
15
20
Hours
Figure 2: System Demand Profile
Hour
1
2
3
4
5
6
7
8
9
10
11
12
Table 4: Load Profile
System Demand Hour System Demand
MW
MW
1598.252
1502.834
1431.270
1407.416
1407.416
1431.270
1765.233
2051.487
2266.178
2290.032
2290.032
2266.178
13
14
15
16
17
18
19
20
21
22
23
24
3
2266.178
2266.178
2218.469
2218.469
2361.596
2385.450
2385.450
2290.032
2170.760
1979.924
1741.379
1502.834
Table 5: Node Location and Distribution of the Total System Demand
Load
N ode % of system load
Load
N ode % of system load
Load
Load
Load
Load
Load
Load
Load
Load
Load
1.3
1
2
3
4
5
6
7
8
9
1
2
3
4
5
6
7
8
9
3.8
3.4
6.3
2.6
2.5
4.8
4.4
6
6.1
Load
Load
Load
Load
Load
Load
Load
Load
10
13
14
15
16
18
19
20
10
13
14
15
16
18
19
20
6.8
9.3
6.8
11.1
3.5
11.7
6.4
4.5
Transmission Lines
The transmission lines data is given in Table 6. The lines are characterized by the nodes that are
connected, as well as the reactance and the capacity of each line. The data is based on [2].
F rom
1
1
1
2
2
3
3
4
5
6
7
8
8
9
9
10
10
2
Table 6: Reactance and Capacity of Transmission Lines
T o Reactance Capacity F rom T o Reactance Capacity
p.u.
MVA
p.u.
MVA
2
3
5
4
6
9
24
9
10
10
8
9
10
11
12
11
12
0.0146
0.2253
0.0907
0.1356
0.205
0.1271
0.084
0.111
0.094
0.0642
0.0652
0.1762
0.1762
0.084
0.084
0.084
0.084
175
175
350
175
175
175
400
175
350
175
350
175
175
400
400
400
400
11
11
12
12
13
14
15
15
15
16
16
17
17
18
19
20
21
13
14
13
23
23
16
16
21
24
17
19
18
22
21
20
23
22
0.0488
0.0426
0.0488
0.0985
0.0884
0.0594
0.0172
0.0249
0.0529
0.0263
0.0234
0.0143
0.1069
0.0132
0.0203
0.0112
0.0692
500
500
500
500
500
500
500
1000
500
500
500
500
500
1000
1000
1000
500
Implementation Including Wind Power Production
It is recommended to include six wind farms at different locations throughout the grid. It is proposed
to locate the wind farms at 3, 5, 7, 16, 21 and 23 nodes. In this case, the capacity on the transmission
lines connecting the node pairs (15,21), (14,16) and (13,23) is reduced to 400 MW, 250 MW and
250 MW, respectively. This is done in order to introduce bottlenecks in the transmission system.
4
References
[1] C. Grigg, P. Wong, P. Albrecht, R. Allan, M. Bhavaraju, R. Billinton, Q. Chen, C. Fong, S.
Haddad, S. Kuruganty, et al. The IEEE Reliability Test System 1996. A report prepared by the
reliability test system task force of the application of probability methods subcommittee. IEEE
Transactions on Power Systems, 14(3): 1010-1020, 1999.
[2] A. J. Conejo, M. Carrion, J. M. Morales. Decision Making under Uncertainty in Electricity
Markets. Springer US, 2010.
[3] F. Bouffard, F. D. Galiana, A. J. Conejo. Market-Clearing with Stochastic Security Part II:
Case Studies. IEEE Transactions on Power Systems, 20(4): 1827-1835, 2005.
Nomenclature
C
Production cost
Cd
Downward reserve cost
Csu
Start up cost
Cu
Upward reserve cost
DT
Minimum down time of each generating unit
Pini
Power output of each generating unit at time 0
Pmax
Maximum output power of each generating unit
Pmin
Minimum output power of each generating unit
R+
Maximum reserve capacity of up regulation of each generating unit
R−
Minimum reserve capacity of up regulation of each generating unit
RD
Ramp down rate of each generating unit
RU
Ramp up rate of each generating unit
Tini
Number of hours of which the generating unit was in/out at the beginning of planning horizon
Uini
Stating whether the unit is online/offline at time 0
UT
Minimum up time of each generating unit
5
Download