Uploaded by Abdul Gayoom

Why It s So Expensive to Build Urban Rail in the U.S.

advertisement
Why It's So Expensive to Build
Urban Rail in the U.S.
1. ALON LEVY
JAN 26, 2018
It’s not just the Second Avenue Subway: Nearly all urban rail
projects in the U.S. cost much more than their European
counterparts.
In late December, The New York Times published a bombshell article by Brian Rosenthal
about high construction costs on the New York City subway. Doing painstaking investigative
work building on a set of numbers I blogged about in 2011, Rosenthal showed how, at $2.6
billion per mile, New York’s Second Avenue Subway broke records for its costs, and that all
of the reasons subway officials offered were excuses. The article documented poor
contracting practices, bad management, and union featherbedding. Unfortunately, what
Rosenthal portrays as a New York affliction is in fact a nationwide problem. The construction
costs of American rail transit are a multiple of such costs in peer countries, for both subways
and light-rail lines. Many U.S. lines that would be easy to justify economically if they cost as
much as in France or Sweden are marginal at current American costs. Every city that hopes to
expand its transit network should pay closer attention to best industry practices abroad if it
wants its investments to be cost-effective.
How much does rail cost?
The approximate range of underground rail construction costs in continental Europe and
Japan is between $100 million per mile, at the lowest end, and $1 billion at the highest. Most
subway lines cluster in the range of $200 million to $500 million per mile; in Amsterdam, a
six-mile subway line cost 3.1 billion Euros, or about $4 billion, after severe cost overruns,
delays, and damage to nearby buildings. The Second Avenue Subway is unique even in the
U.S. for its exceptionally high cost, but elsewhere, the picture is grim by European standards:
Line
Type
Cost
Length
Cost/mile
San Francisco Central Subway
Underground
$1.57
billion
1.7 miles
$920
million
Los Angeles Regional
Connector
Underground
$1.75
billion
1.9 miles
$920
million
Los Angeles Purple Line
Phases 1-2
Underground
$5.2 billion 6.5 miles
$800
million
BART to San Jose (proposed)
83%
Underground
$4.7 billion 6 miles
$780
million
Seattle U-Link
Underground
$1.8 billion 3 miles
$600
million
Honolulu Area Rapid Transit
Elevated
$10 billion
20 miles
$500
million
Boston Green Line Extension
Trench
$2.3 billion 4.7 miles
$490
million
Washington Metro Silver Line
Phase 2
Freeway median $2.8 billion
11.5
miles
$240
million
Atlanta I-20 East Heavy Rail
Freeway median $3.2 billion
19.2
miles
$170
million
It is hard to find exact international comparisons for subway lines running in the medians of
freeways. However, it should not be much more difficult to construct such lines than to build
light rail. Indeed, in the study for Atlanta’s I-20 East extension, there are options for light rail
and bus rapid transit, and the light rail option is only slightly cheaper than the heavy rail
option, at $140 million per mile.
Lists of light-rail lines built in France in recent years can be found on French
Wikipedia and Yonah Freemark’s The Transport Politic, and in articles in French media. The
cheaper lines cost about $40 million per mile, the more expensive ones about $100 million.
In the United States, most recent and in-progress light-rail lines cost more than $100 million
per mile. Two light-rail extensions in Minneapolis, the Blue Line Extension and
the Southwest LRT, cost $120 million and $130 million per mile, respectively. Dallas’
Orange Line light rail, 14 miles long, cost somewhere between $1.3 billion and $1.8 billion.
Portland’s Orange Line cost about $200 million per mile. Houston’s Green and Purple Lines
together cost $1.3 billion for about 10 miles of light rail.
The first Orange Line train carrying passengers across the new Tilikum Crossing bridge
in Portland in September 2015 (Timothy J. Gonzalez/AP)
Only a handful of American lines come in cheaper than $100 million per mile, the upper limit
for French light rail: For example, a light-rail extension in suburban Phoenix was recently
built for $65 million per mile.
Spending $900 million per mile on a subway, or $150 million per mile on light rail, may not
seem so outrageous compared to New York’s $2.6 billion per-mile subway. But there’s no
reason why building subways and light rail in sprawling cities should be as expensive as it is.
In Manhattan, the population density and utilities around Second Avenue make it comparable
to Paris, London, Berlin, and other older cities with large subway systems that have complex
tunnel networks. But San Jose has wide roads and little in the way of older infrastructure, so
it is better to compare it with suburban tunnels in Europe, which come near the low end of
construction costs. Among the American subway tunnels recently opened or under
construction, only the Central Subway in San Francisco, passing deep under the two-level
Market Street Subway, has a reason to be costly.
There’s no reason why building subways and light rail in sprawling cities should be as
expensive as it is.
In Stockholm, construction costs are generally low, but among its ongoing subway
extensions, the most suburban one (Barkarby) is the cheapest at about $150 million per mile;
an extension underwater (to Nacka) is about $220 million per mile, and a deep commuter rail
tunnel under the city center is about $400 million per mile. Based on the difference in costs
within Stockholm, it is likely that if other American cities built a project as complex as the
Second Avenue Subway, they would find themselves facing the same costs as the Second
Avenue Subway.
Cost per rider
The cost-per-mile metric is useful in measuring a city’s ability to build infrastructure
efficiently. However, by itself, it does not reveal whether rail investments are socially or
economically justified. In order to decide how cost-effective investment is, cities must
compare costs with benefits—in this case, ridership.
In New York, the Second Avenue Subway, which is only two miles long, is estimated to
eventually see 200,000 trips per day, and so far, it seems to be on track to achieving its
ridership projection. This is a high figure, achievable only in very dense neighborhoods. The
Second Avenue Subway serves segments of the Upper East Side that have among the highest
population-density levels in the developed world. With such high intensity of usage, the new
line is projected to cost $25,000 per daily rider. The cost-per-rider range for European
subways seems to be $10,000 to $25,000, so the Second Avenue Subway is not even an
outlier: Its extreme cost is balanced by very high ridership.
But in other American cities, there is no hope of balancing high cost with ridership in the
same way. Even relatively old cities such as Boston and San Francisco have extensive
suburban sprawl, and no neighborhood as dense as the Upper East Side.
Whereas the Second Avenue Subway will cost about $25,000 per rider if it meets projections,
Los Angeles’ Purple Line is expected to carry 150,000 riders across its three phases (and
some of this ridership comes from preexisting rather than new stations), which will come out
to about $45,000 per rider. Boston’s Green Line Extension is projected to get 52,000 daily
riders, making it about $45,000 per rider as well. But many American light-rail lines have
per-rider costs approaching $100,000.
A worker on the construction site of the T3 tramway line from Porte de la Chapelle to
Porte d’Asnieres in Paris in 2016. (Benoit Tessier/Reuters)
By contrast, Parisian tramways, which combine very high ridership and reasonable (though
not low) costs, are almost all cheaper than $10,000 per rider, with many around $5,000.
Parisian Metro extensions are more expensive, clustering around $10,000 per rider; these
balance higher investment costs with lower operating costs.
The Second Avenue Subway would be unbelievably cheap to build in Europe. Other
American lines would not be so cheap, but they could still be justifiable, with costs per rider
that fall within the European range. The budgets that American cities currently devote to the
odd line could fund entire networks of light rail and subway lines.
Why are costs so high?
In his exposé, Rosenthal talked about labor problems: severe overstaffing, with some workers
doing jobs that are no longer necessary, and wages well into six figures. These issues are not
exclusive to New York. A chapter in a textbook about megaproject construction states that
“as a result of existing union agreements covering the eastern seaboard area of the United
States, underground construction employs approximately four times the number of personnel
as in similar jobs in Asia, Australia, or Europe.” European subway construction uses union
labor, just like American construction, but the work rules that have accumulated over the
decades permit higher productivity and fewer workers doing each task.
But the problems are not just to do with labor. Working alongside active commuter or
intercity rail lines brings a slew of new requirements and regulations. The Green Line
Extension is notable for running in a trench next to a commuter rail line, and several Bostonarea rail activists told me that a key reason for its high cost is that construction is not
permitted to disturb commuter rail service. Another light rail line running alongside
commuter rail and Amtrak, San Diego’s Mid-Coast Trolley extension, costs $2.1 billion for
11 miles; by contrast, other light rail projects on San Diego’s wishlist are projected to cost
less, about $100 million per mile in 2010 dollars.
In California, the quality of contractors is to blame for some problems. The San Diego Union
Tribune ran an article in 2013 focusing on Tutor Perini, which has a pattern of submitting low
bids to win public construction contracts but then running over because of change orders and
courtroom battles, contributing to an average 40-percent cost overrun in the San Francisco
Bay Area.
The United States is not doomed to ineffective transit investment.
California’s contractor problem does not seem to be a national one. Jaime Garmendia, a
manager at Boston’s MBTA, said, “We would cease to do business with that contractor in a
heartbeat.” He put the Green Line Extension’s high cost down to poor project management.
Recent changes to the Green Line Extension support that diagnosis. After the transit agency
fired the contractor and hired a new general manager to oversee the project, it reduced the
budget to $2.3 billion from a previous $3 billion. Of the $2.3 billion price tag, only $1.1
billion is for actual construction, whereas much of the rest is sunk cost is due to the botched
earlier version of the extension.
What’s the solution?
Nearly all American urban rail projects cost much more than their European counterparts do.
The cheaper ones cost twice as much, and the more expensive ones about seven times as
much. The reasons for this are varied: Some arise from the character of the project (unique
regulations related to commuter rail), some from state rules (California’s problem with
contractors), and some from poor project management (Boston’s Green Line Extension).
Many of these problems are solvable upon a careful review of what it takes to build a new
subway or light-rail line. Boston’s experience in limiting its cost overrun is instructive, and
could prove to be a model for other cities. Modernizing work rules to avoid having many
redundant employees, as described in detail in Rosenthal's investigation, could also provide
savings. If cities overstaff tunnel construction by a factor of four, they could hire the same
number of workers to build four times as much tunnel and devote the cost savings to further
infrastructure improvements.
The United States is not doomed to ineffective transit investment. Since many of these
problems affect some cities but not others, there is scope for cities to learn best practices from
each other. Additionally, the U.S. can look at what other rich countries (such as France and
Sweden) do and copy what works. There is no iron curtain between the United States and
Western Europe—learning good rail-project management and procurement is well within the
grasp of a large urban transit agency. All it takes is the understanding that things are better
abroad, and a willingness to learn and do better.
Download