Today’s Agenda: Chapter 17 Project Close-Out Introduction: • Physical Close-out (C-O) • C-O is just as important as start-up • Client and designer satisfaction is paramount • Close-out of documentation • Close-out is defined in the contract • Can take up to a year, which delays receipt of retention Commissioning • Commissioning Spec Section? • Test and re-test • Simulate all four seasons, design days • Focus on MEP • Commissioning Agent: • Mechanical sub, or • Client in-house, or • 3rd Party • Cost can be up to 1% of construction Construction Close-out What Items are Included in Physical Close-out? • Punch list • Startup and Balance • Commissioning • Owner Training • Certificate of Substantial Completion • Certificate of Occupancy • Demobilization Punch list Process • Author? Participants? • How Many Punch lists? • Is the item a Punch list VS Change order VS Maintenance VS Incomplete? • Owner: GC to Pre-Punch • Owner: Punch, but not too soon • Active QC: Early Punch lists • Box 17.1 Box 17.1 Certificate of Substantial Completion • • • • • • • Read your Contract Architect’s Paper AIA G704, or Consensus, see text website Author? Ends LD’s, Starts Warranty Attach Punch list (how long of PL?) Tied to Final Pay Request Certificate of Occupancy (C of O) • • • • • City’s Paper, Box 17.2 Elevator Inspector is paramount Fire Marshall is paramount Partial or Interim or Temporary C of O Bond for uncompleted work: Ex: ___ Box 17.2 Occupancy Strategies • • • • • Joint Occupancy: Read your Contract Utility Bills by? Warranty VS Maintenance VS Punch list Clean-up by? Dumpsters by? Are Owner’s Contractors Union? Demobilization Activities: • Opposite of Mobilization • Did you estimate for either? • Remove Fence, Trailer, Temp Power, Sanikan, Clean Streets, Repair Sidewalks, And: ___ • Files into storage Contract Close-Out • • • • • Check the specs for requirements PM should take the lead As-Built Drawings: Red-Line or CAD? Operation and Maintenance Manuals (O&M) Warranties: One year, or more, or extended? Box 17.3 • (Final) Test Reports, including Balancing 11 Contract Close-Out, continued • Extra Materials (Locked-Up) % = __ Used for Change Orders? Punch List? • Permits (Signed-Off) • Close-Out Log, W7.1, Start = __ Submit this early as an early submittal for approval, Similar to submitting a Submittal Log or SOV for approval 12 Worksheet 17.1 LEED Close-out • Usually the LEED engineer or the PE, not necessarily the PM • Gather all paperwork associated with LEED compliance regarding materials used and recycling, et al • Owner adds their paper, along with input from the architect • Owner may have a LEED consultant who completes the LEED scorecard • Owner applies for LEED certificate and pays the fee • See also MOCP CH 5 PM Motivation for a Timely Close-out • Ends LDs • End sub claims • Begin warranty • Happy client • Minimize general condition costs • Submit and receive final pay request • Pay-off subs, happy subs • Receive retention ~ Fee! Financial Close-out Items All WRT Owner-GC and GC-Subs and Suppliers: • Final Change Orders • Final Subcontractor Modifications • Final Pay Request • Final and “Unconditional” Lien Releases: • GC and Subs, Prior CH 6 Example • Final Cost Accounting (Open Book) Audit • Union Affidavits • Final Retention Release Project Manager’s Close-out • As-built Estimate: Actual $ or Hours/Actual Qtys = Actual UPs • As-built Schedule • Final Fee Forecast • Owner Report Card/Incentive Fee • Input on Quality of Subs and Suppliers • PM Lessons Learned Warranty Management • Warranty usually for one year • Some subs (roof, elevator, glass) longer • Example sub warranty, Box 17.3 • Extended Warranty Agreement or Service Contracts • Warranty Service Requests, Box F17.4 • Warranty Response as Customer Service • On-site presence is 90% of the next job opportunity • Maintenance or Warranty Bond, Prior CH 2 Ex. 18 Recommended Extended Warranties and Maintenance Agreements, with: • • • • • • • Elevators Landscaping Process and Kitchen Equipment MEP Systems, Filters Fire Protection Low Voltage Systems: Security, Controls Others: __ Chapter 17, Project Close-Out, Summary • Construction and Document elements to C-O • PM and Superintendent roles • Good C-O = Happy Client (and designer) • Commissioning: by whom at what cost? • Punch lists • Certificate of Substantial Completion • Certificate of Occupancy Close-Out, Summary, continued • Owner Occupancy and GC De-Mob • Contractual Close-out • Activities: ___ • Financial Close-out • PM Close-out • Activities: ___ • Warranty Management • Review Questions: __