IMU 3000 EMC Training
Ring, CWG, and EFT Overview
April 2020
Heather Darrah
Regulatory Engineer
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
Agenda – MV Testing with IMU 3000
1. Overview of Equipment
2. Combination Wave (Surge)
3. Ring Wave
4. Electrically Fast Transient (EFT)
5. Using the Software
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 2
IMU 3000 EMC Tester
• High Voltage (up to 8kV) Waveform Generator
• Test Capabilities
• CWG aka Surge
• Ring Wave
• Electrical Fast Transient (EFT)
• Voltage Dips (100% only)
• Programmable from touch screen
or laptop
• On-line or Signal Output
• 300VAC Max in (from wall power)
• Single Phase
• E-Stop for Equipment
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 3
IMU 3000 Panel Close Up
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 4
CDN-A-6-32 – Three Phase and High Voltage
• 600 VAC MAX
• 3 Phase
• Used with fuse box
• Not a generator
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 5
Three Phase Connection Example
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 6
Motor Set Up and Grounding
• Installed ground rod
• The entire top of the table is a ground plane
• MV Tests require running at load
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 7
Combination Wave (CWG or Surge)
• High voltage, high energy, short duration
• Simulate lightening strikes
• Only performed between motor power lines
• Per MV Test Plan
–
–
–
–
–
–
–
4 couplings (L1-PE, L2-PE,L1-L2, L1+L2 – PE)
4 Voltage levels (3KV, 4KV, 5KV, 6KV)
Positive and Negative Polarity (2)
Repeated twice
Random Phase Angle
Allow 1 minutes between hits
Total Time = 2*2*4*4 = 64 minutes long
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 8
Ring Wave
• High Voltage Oscillation
• Electrical network switching, breakdown of power supply circuits, or
lightning strikes
• Only performed between motor power lines
• Per MV Test Plan
–
–
–
–
–
–
–
–
4 couplings (L1-PE, L2-PE,L1-L2, L1+L2 – PE)
4 Voltage levels (3KV, 4KV, 5KV, 6KV)
Positive and Negative Polarity (2)
Repeated twice
Random Phase Angle
100kHz Wave frequency
Allow 1 minutes between hits
Total Time = 2*2*4*4 = 64 minutes long
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 9
Electrically Fast Transient (EFT) - Mains
• High Voltage, lower energy, greater frequency
• Switching transients occur by adding or removing loads from the system.
• Motor must be floating off ground plane
• Per MV Test Plan
–
–
–
–
–
2kV Power
15ms duration
2.5kHz and 5 kHz frequency
300ms period (120s total test time)
Couplings L, N, G, L+N, L+G, N+G, L1+N+G
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 10
Electrically Fast Transient (EFT) - Signal
• High Voltage, lower energy, greater frequency
• Switching transients occur by adding or removing loads
from the system.
• Motor should be externally grounded (not only power lines)
• Per MV Test Plan
–
–
–
–
1kV signal 15ms duration
2.5kHz and 5 kHz frequency
300ms period (120s total test time)
Use capacitive clamp around signal wires
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 11
Did We Pass?
• Requires human oversight
• Motor must remain in operable condition throughout test, without
experiencing permanent damage
• Motor can shut down after a hit, but must restart on it’s own
• IMU 3000 will not tell you this, but can provide
– Report of test conditions ran
– Ability to pause tests
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 12
Programming/Controlling Using the Laptop
• Remote Programming/Running - TEMA DEMO
• Individual tests can be arranged into sequence
• If you update an individual test it will not
automatically update in a sequence
• This method is effective if testing requirements
differ throughout the same test
• T1ppt@ch
• Limitations - cannot ramp voltage with polarity
changes
• https://www.emc-partner.com/emc-testsoftware?view=article&id=4998&catid=1185#do
wnload
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 13
Run Screen
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 14
The End
Creating a better tomorrow™…
©2019 Regal Beloit Corporation, Proprietary and Confidential
11/26/2018 │ 15
Download