OPPD’s Fort Calhoun Station Project Management Fundamentals PQD – PMFUND WO# 00615637-01 Brandon Miller Project Manager 1 Safety & Standards • Emergencies – Exits – Fire extinguishers – First aid / AED – Severe weather – Dial 7-7-7-7 • Silence electronics 2 Topics • Overview of Projects • International Standards for Projects • Project Behaviors • Project Scheduling • Earned Value Management • Project Communication Tools 3 Overview of Projects 4 What is a (Capital) project? • A capital project is any undertaking which requires the use of notable amounts of capital, both financial and labor, to undertake and complete. • Projects have a definitive beginning and end. • Decommissioning is a Capital Project 5 Decommissioning Funding Sources Site Restoration (OPPD Rate) Fuel Management (DOE Reimbursable) License Termination (NRC Regulated Fund: DCE) 6 Project Life Cycle Initiation Definition Development Planning Execution Closeout 7 Project Phases • • • • • • Initiation Definition Development Planning Execution Close Out 8 3 success factors to any Investor •Performance •Predictability •Transparency Progressive Elaboration • A project management technique in which the plan for the project is being continuously and constantly modified, detailed, and improved as newer and more improved sets of information becomes available to the team as the project unfolds and begins taking shape. 10 Project Organizations • • • • Project Management Project Controls Engineering Construction (Maintenance) 11 Areas of Project Controls • • • • • • • Scope Schedule Budget (Estimate) Cost Control Change Control Risk Management Reporting and Metrics Project Controls Activities • Progress the schedule • Input actuals (completion time and dates, enter costs and Timesheets) • Analyze data – Critical Path – Float – Forecast Project Controls Deliverables • • • • • Daily Schedule (2 week look-ahead) Metrics (Schedule/Cost Performance) POD Metrics Risk Registers Change Logs Integration / Transition System Abandon Fuel E WEEK ST, PM, CM Asbestos E-Week Schedule: E10/E4 - representation from project rep Cert – Overview of system health EP DSAR E-Week Schedule: E10/E4/Cert - resource and schedule integration to work week schedule, project rep involvement Train. Metrics • What is measured can be managed • Metrics should be designed to change a behavior of team members (or don’t bother) • No more than 20% of time should be put into the measurement and metrics of a projects (closer to 10%) 16 Month End Table 17 Month End Bubble Chart 18 Project Standards 19 AACE • Formed 1956 with 8500 members • Is the international standards for estimating and cost management • Has certifications for Project roles Certified Cost Professional (CCP), Certified Cost Technician (CCT), Certified Estimating Professional (CEP), Certified Forensic Claims Consultant (CFCC), Earned Value Professional (EVP), Decision and Risk Management Professional (DRMP), Certified Scheduling Technician (CST) and Planning & Scheduling Professional (PSP)… 20 AECE Estimating Class Standards 21 DCE 22 Project Management Institute • Founded in 1969 • 2.9M members • International recognized organization for Project standards • Has certifications for Project roles Project Management Professional, Program Management Professional, Risk Management Professional, Scheduling Professional… PMBOK 24 PMI Designations PMP Certification Requirements To apply for the PMP, you need to have either: •A secondary degree (high school diploma, associate’s degree, or the global equivalent) with at least five years of project management experience, with 7,500 hours leading and directing projects and 35 hours of project management education. OR •A four-year degree (bachelor’s degree or the global equivalent) and at least three years of project management experience, with 4,500 hours leading and directing projects and 35 hours of project management education. PMI Designations Project Scheduling Certification Requirements To apply for the PMI-SP, you need to have either: •A secondary degree (high school diploma, associate’s degree, or the global equivalent) with at least 5,000 hours of project scheduling experience and 40 hours of project scheduling education. OR •A four-year degree (bachelor’s or the global equivalent), with at least 3,500 hours of project scheduling experience and 30 hours of project scheduling education. •This is an overview of the requirements. For complete details regarding the PMI-SP eligibility requirements, please view the PMI-SP Handbook for further details PMI Designations Risk Management Certification Requirements To apply for the PMI-RMP, you need to have either: •A secondary degree (high school diploma, associate’s degree, or the global equivalent), with at least 4,500 hours of project risk management experience and 40 hours of project risk management education. OR •A four-year degree (bachelor’s degree or the global equivalent), with at least 3,000 hours of project risk management experience and 30 hours of project risk management education. Procedures The procedures are being updated to reflect : • PC-FC-01 Project Management (What/Why) • PC-FC-02 Project Controls (How) 28 Project Behaviors 29 Project Management Behaviors • • • • Focus Accountability Discipline Sense of Urgency Scheduling Behaviors Drives others to what is important • Ensures Critical Path is correct • Drives Critical Path through organization Cost behaviors Detailed and accurate • Ensures accuracy of costs incurred against plan • Analyzes costs to build better forecast model Risk Management • Project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on a project's objectives. • Not to be confused with Station Risk 33 Risk Behaviors Questioning Attitude, Organizes • Question plan: – What would happen if? – Could this impact? – What is the likelihood if? • Builds models to predict best and worst cases Change Management Change: Progressive Elaboration: 35 Change Behaviors • Listening to and looking for changes that have not been identified. • Disciplined to ensure change is reported/logged and implemented in correct systems: Schedule, Cost, Risk… 1, 2, 3… Project Negotiation 37 Negotiation • How to Inspire/Connect • Overcoming resistance • Bottom Line 38 Project Negotiation Project Managers negotiate for: • Resources • Priority • Physical Space • Budget Overcoming Resistance Resistance < Vision X First Steps X Disappointment 40 Bottom Line Bottom Line = Front Line 41 Project Scheduling 42 Project Schedules • • • • • • • Activity Types Relationships Levels Hammocks Risk Application Station Integration Float 6 Activity Types •Start Milestone •Finish Milestone •Level of Effort Management – Cost Capturing Definition Phase Disconnect Actuator •WBS Summary •Resource Dependent – Used in Operations and Maintenance not in projects Disconnect Actuator •Task Dependent – Used in Projects Task/Resource Dependant in Histograms Task Dependant * Resource Dependant Jan Feb Mar Apr May Jun Jul Aug Sep Jan •* Can be leveled through level loading Feb Mar Apr May Jun Jul Aug Sep Histogram Example Relationship Types • Start to Start • Finish to Finish • Finish to Start – Most Common Mobilize Crew Mobilize Crane Demob Crew Demob Crane Foundation Dry Frame House • Start to Finish – Never used Guard 1 shift Guard 2 Shift Work Week Management Methodology 48 Gate Gate Gate Work Week Management Methodology T-0 T-1 T-2 Execute Prepare Plan T-3+ Critical Path Methodology 50 Schedule Levels •Level 1 – Months to Years (Project Summary) •Level 2 – Weeks to Months (CD Phase Summary) •Level 3 – Days to Weeks (WBS Summary) •Level 4 – Hours to days (Project Activities) •Level 5 – Minutes to Hours (Outage Project Activities) Note: Projects will have their projects defined to Level 4/5 prior to execution. Schedule Levels Level 1 Project Definition Phase WBS Summary or LOE Level 2 Level 3 Level 4/5 Hammocks Level 4/5 • Tracked in Projects version of P6 only. • Reflects the steps within the Work Package. • Is Hammock to the Level 3. Level 3 Level 4/5 Hammocks Hammocks • • • Level of Effort will calculate duration based on predecessors and successors. Task Dependant is a resources loaded and duration dependant. The Level 3 activity will move/expand with the Hammock activities Level 3 Level of Effort (LOE) Level 5 Task Dependant Hammocks Adding Risk to schedules •Risk Milestones •Risk Incursion Tasks •Risk Mitigation •Risk Maintenance Reoccurring risk review tasks Train RM004: Mitigation task of the risk (resource loaded to add to base cost) RMS004: Risk Title RI004: Risk Incursion task (should only be resource loaded for modeling purposes) Recover Station Schedule • • Stations do not want full Project schedules to be loaded into Work Management as it clutters and confuses the system. Specific activities must be added where: – – – – Station support is required (Ops/Maintenance Crews) Clearance Orders are necessary Procurement events are realized General overview of Project performance Level 3 Level of Effort (LOE) Level 5 Task Dependant Project Schedule Specific activities to be added to the Station Schedule Float • Float: Duration of time for a project activities to be completed relative to intended (base lined) finish date (milestone) • Negative Float is when the project activities complete after (late) the intended finish date. Project Activities • Positive Float is when all project activities complete prior (early) to intended finish date. Project Activities Agile 58 Agile • Iterative or agile life cycles are composed of several iterations or incremental steps towards the completion of a project. Iterative approaches are frequently used in software development projects to promote velocity and adaptability since the benefit of iteration is that you can adjust as you go along rather than following a linear path. • One of the aims of an agile or iterative approach is to release benefits throughout the process rather than only at the end • Agile wants to leverage the best value using the least resources • Agile is Critical Path Method in a loop. Agile 60 Earned Value Management 61 Earned Value Analysis Reference Materials 1. 2. 3. 4. 5. 6. 7. Earned Value Analysis – Earned Value Analysis is a performance measurement technique that integrates cost, time, and scope on a project Earned Value – Planned Value (PV) – The figure illustrates a typical S-curve for the “Planned Value” (PV), the cumulative planned expenditure. In the early stages, expenditure is low, rising as contracts are issued, and materials purchased. In the later stages, the rate of expenditure slows during installation and commissioning Earned Value – Actual Cost (AC) – “Actual Cost” is the total of all project costs incurred to “Time Now” (also known as “Actual Time Expended”-ATE). These costs are recovered from time-sheet information, 3rd party invoices, material vouchers, etc. Earned Value – Progress (EV) – The final element required is a measure of the “Progress” or work achieved. This is termed “Earned Value” (EV), or “Progress”, but is also known as “Achieved Value” – The work achieved may be measured, or estimated. Completed tasks have an earned value of 100% of planned value, while tasks not started have zero earned value. Those tasks underway at ATE have earned value measured or estimated, and summed with completed tasks to give total EV Earned Value Indices – The data are combined in ratios giving Key Performance Indicators (KPI) of project performance. When work is proceeding to plan, or better, these ratios equal or are greater than 1. Conversely, unfavourable indices are less than 1 Schedule Performance Indices (SPI) – A “Schedule Performance Index” (SPI) is calculated in two ways; cost or time based. The cost-based SPI is part of traditional earned value analysis and the time-based SPI is used when forecasting the achieved work at intermediate time points, the remaining time to complete the project, or the total project time – SPI = EV / PV Cost Performance Index (CPI) – This index, also termed “productivity”, gives an indication of how well the budget is in terms of the work performed. A value greater than 1 is a healthy situation, but a value less than 1 means the project is over-spent – CPI = EV / AC Earned Value Analysis Reference Materials Basic Concepts Forecasting Time Budget at completion BAC Total planned cost for complete project Forecast Project Duration FPD PD / SPI time Actual Time Expended ATE Also known as time now FPD PD / SPI cost Project Duration PD Forecast Project Duration (alternate) Planned Value PV Plan scheduled and summed at Budget Values to period ATE BAC / CPI EV Progress calculated and summed at Budget Values to period ATE Forecast Cost at Completion FCC Earned Value Estimate at Completion EAC AC + (BAC – EV) / CPI Actual Cost AC Original Duration OD Actual costs summed to period ATE Project Performance Indices Cost Performance Index CPI EV / AC Schedule Performance Index (cost) SPI cost EV / PV Schedule Performance Index (time) SPI time OD / ATE Forecasting Cost Project Variances Schedule Variance (cost) SV cost EV – PV Schedule Variance (time) SV time OD – ATE Cost Variance CV EV – AC Estimated Variance at Completion EVAC BAC - EAC Earned Value S-Curve Project Communication Tools 66 Tools when talking projects • • • • • • 4 pillars of safety HU Tools SMART 5PT Developing Activity/Risk names Meeting Agendas 4 Pillars of Safety • • • • Industrial Nuclear Radiological Environmental 5 Alive HU Tools 1. Self/Peer Check (STAR) 2. Effective Communication – Use of Phonetic Alphabet – 3 Way Communication 3. Procedural Use and Adherence 4. Questioning Attitude 5. Pre-Job Briefings Applying SMART to schedules • • • • • Specific Measurable Attainable Relevant Timely 5PT – Getting information out • • • • • • Parts – Long Lead, vendors… People – Training, Qualifications… Package – WP, RWP, Confined… Permit – PA, Station, Confined… Plant – Drills, Weather, Outages… Tools – Rentals, Cranes, specialty… Must haves in Project Meeting Agendas • • • • • • • Safety/HU/Plant Status Schedule Risk Delays Opportunities Lessons Learned Recognition Developing Activity/Risk Name Pronoun – Verb – Noun •Field Tech draft work package •SF1 Crew weld 9ft pipe What goes in a Change Log •Funding changes •Schedule Changes •Scope Changes •Delays (SCR) •Risk Incursion(SCR) •Risk Mitigation(SCR) •Estimate values •Opportunities (SCR) 3 Methods to create Float 1.Lag in ties 2.Shorten Durations of Critical Path Tasks 3.Identify Parallel opportunities from Critical Path Tasks Questions bjmiller@oppd.com 76