Process Safety Management System Audit Terms of Reference Document No. SR-65-19-01 ToR - PSM Audit REV DATE DESCRIPTION PREPARED A 18/11/2019 Issued for comments MSA 2 CHECKED APPROVED SR-65-19-01 ToR - PSM Audit TABLE OF CONTENTS 1.0 INTRODUCTION .......................................................................................................... 4 2.0 SCOPE ........................................................................................................................ 5 3.0 OBJECTIVE .................................................................................................................. 6 4.0 AUDIT APPROACH ...................................................................................................... 7 5.0 ELEMENT WISE AUDIT APPROACH ............................................................................ 11 3 SR-65-19-01 ToR - PSM Audit 1.0 INTRODUCTION As part of continuous improvement process, Hub Power Services Limited (HPSL) has engaged M/S Shepherd Risk to assist them in carrying out audit of Process Safety Management system across the company head office and operations. Muhammad Saim, Senior consultant, Process Safety will assist HPSL, HPSL will dedicate a team of Process Safety & HSE personnel for audit. This document gives a brief outline of Audit Terms and methodology that will be adopted. HPSL is requested to prepare for audit accordingly. 4 SR-65-19-01 ToR - PSM Audit 2.0 SCOPE Scope of audit activities will cover HPSL Head office and 3 Plant sites: 1. Hub Power Plant. 2. Narowal energy Limited (NEL) 3. New Bong Escape Power Plant (NBE), Laraib Energy 5 SR-65-19-01 ToR - PSM Audit 3.0 OBJECTIVE Process Safety Management system is the application of management systems to protect life of people, the environment and the property from catastrophic events resulting from loss of control over processes. There are three key aspects of Process Safety Management: Technical Integrity; Design Integrity and Operating Integrity Objective of a Process Safety Management Audit is to assess the effectiveness of Safety Management System and Culture at HPSL in managing Design Integrity, Technical Integrity and Operations Integrity. Process Safety Managem ent Operating Integrity The impact of a change in design integrity (standard, design concept, etc.) can take 5 to 10 years, before positive change is seen. Example: team decides to change the design standard for a process vessel. From now on, no block valves are allowed in the vent lines anymore. This change will only show it benefit many years after the first vessel has been designed and put into operation. The impact of technical integrity can be anywhere between 1 and 5 years. Example, the company can decide to remove all block valves after process vessels across the whole facility. This will take a while to get budget, plant shutdowns, do the work, etc. The impact of operational integrity can be (almost) immediate. Example, the company can send out Standing Order that from now on all block valves are identified and placed in locked-open after each process vessel. 6 SR-65-19-01 ToR - PSM Audit 4.0 AUDIT APPROACH Audit will be carried out based on: OSHA 29-CFR-1910 Audit Guidelines AIChE, CCPS Guidelines for PSM Audit Energy Institute PSM Audit guidelines Since HPSL activities do not directly involve hazardous chemical process (not directly involved with chemical, petrochemical or refining industry) hence OSHA PSM 29.CFR.1910 is not fully applicable to HPSL operations, however, OSHA 29.CFR.1910.269 Occupational Safety and Health Standard for Electric Power Generation, Transmission, and Distribution are directly applicable. Therefore the audit will primarily be based on OSHA.29.CFR.1910.269. Focus of the audit activities will be to assess whether the way organization is currently operating is good enough in terms of Process Safety Management, identify strengths and weaknesses and suggest actions to bridge the gaps to ensure that organization is meeting industry best practices. Overall audit process will be in three main steps: 1. Pre-Audit Activities 2. Audit Activities 3. Post Audit Activities Audit activities will be based on site visit, interviews & discussions and document reviews. Audit team will use experience and judgement in assessing the Process Safety Performance aided by checklist and questionnaire. In addition to focusing on Process Safety Management System Elements, the audit team will carry out a Safety Perception Survey based on an employee & contractor interviews and feedback. Scope and activities of each of the three steps is detailed below: 7 SR-65-19-01 ToR - PSM Audit 1 - Pre_ audit Activities Lead Muhammad Saim - Consultant HPSL Saleem Qureshi Kick Off Meeting Who: Muhammad Saim + HPSL Core Team Venue: HPSL Head office Date: TBA Estimated duration: 4 hrs. 8 Introductions & objective setting Finalize audit Plan - Dates & Locations, allocate resources Prepare onsite agenda - Element wise audit plan Review & finalize audit questionnaire Gather background information: o Previous Audit Report. A copy of the previous audit report o Action Plan. Status report on the resolution of previous audit exceptions Regulatory Requirements. Copies of applicable local regulations o Corporate Policies. Copies of applicable corporate policies, standards, and guidelines o Facility Policy Manuals and Plans. Copy of tables of contents from current facility safety manuals, emergency plans, and other documents covering policies, procedures, and reporting requirements o Facility Organization. Current facility organization chart annotated to illustrate line and staff responsibility for all process safety areas under review, and to identify key contact people o Facility Layout. Maps or diagrams to illustrate location of different operations and of process safety and control system components Process o Descriptions: Discussion of process operations, flows, chemicals and control systems. o Reports. Copies of selected process safety status reports, self-audits, or other applicable reports o Incident Reports. Investigation reports for recent episodic incidents SR-65-19-01 ToR - PSM Audit 2 - Audit Activities Corporate Level Audit Lead: Muhammad Saim Opening Meeting with Management & Leadership Individual Interviews - Senior Management/Team Leaders Corporate Policies Commitment to Process Safety & Objectives Top Process Safety Risks & Action Plans PSM Element wise assessment Arrive at site Opening Meeting with Site Management o Introductions - All o Audit Objectives & Plan - Consultant o Site Briefing - Site Manager Audit Activities - Team split as per element wise audit plan o Site visit o Interviews Managers, Supervisors, Operators, Technicians, Labor, Contractors etc. o Documentation & Data Review Audit Team meeting - notes compilation Close out meeting with site management Support: Saleem Qureshi Location: HPSL Head office Date: TBA Estimated duration: 1 Day Site Audit Lead: Muhammad Saim + Saleem Qureshi Support: HPSL Audit Team Location: Plant Sites - Hub, NLE, NBE Date: TBA Estimated duration: 1.5 Day each site 3- Post Audit Activities Compilation of Audit Findings Participants: Audit Team Location: HPSL Head office Date: TBA Estimated duration: 4 hrs. 9 Share Element wise Audit Findings - Strengths, Weaknesses, Observations Submit element wise report and checklist to consultant Element wise rating SR-65-19-01 ToR - PSM Audit Audit Report 10 Draft Report HPSL Comments on Draft Report Final Report & Presentation SR-65-19-01 ToR - PSM Audit 5.0 ELEMENT WISE AUDIT APPROACH Table below lists key aspects of audit against each element: Element Management Commitment Management Leadership & Commitment Policies & Principles Integrated Organization Structure Line Management Key Audit Aspects Are the PSM Policies, Objectives and Goals defined and communicated by senior management & leadership to entire organisation effectively, this includes contractors? Does the Leadership demonstrate commitment to PSM Objectives & Goals by providing adequate resources (manpower, finance, time)? Are PSM KPIs defined, measured and steered at leadership levels? Are employee benefits (e.g. annual increment, bonus) linked to PSM KPIs? Is the PSM organisation (e.g. HSE) independent of site management influences i.e. reporting directly to senior leadership vs. reporting to site manager? Are competencies of core PSM / HSE positions defined? Are competent and experienced personnel appointed on all approved PSM/HSE positions? Is there a system in place to collect and maintain necessary Process Safety Information? Does a system exist to ensure that data are accurate, reliable, and up-to-date, and that process safety information is available to all personnel who need to have access to it? Accountability & Responsibility Goals, Objectives, & Plans Technology Safety Personnel 11 Process Safety Information SR-65-19-01 ToR - PSM Audit Is there a program in place and executed for Process Hazard & risk Analysis? Are the risk tolerability criteria defined? Are all risks within ALARP or acceptable limits? Are applicable PHRA tools and techniques clearly defined and procedures and mythologies documented? Are competencies for leading and participating in PHRA techniques defined and developed within organization? Is there a plan in place for periodic execution of PHRAs and is being followed? Is there a system in place for monitoring timely implementation of recommendations from PHRAs? How are delays and deferments in implementation of PHRA recommendations handled, does the management declare it an incident (API 754) Is there are system in place for periodic review and update of operating procedures? Are all operating procedure current and updated? Reflecting latest PSI and PHRAs? Are operating procedures covering all modes of operation, including normal, shutdown & startup and emergency? Process Hazard & Risk Analysis Operating Procedures & Practices 12 SR-65-19-01 ToR - PSM Audit Are safe upper and lower operating limits defined? Is there a system in place for managing changes - facility, technology and Personnel? Does the Change Management procedure define type of changes covered under the subject? Does the change management procedure define the need for PHRAs as applicable to the change? Management of Change Pre Start-up Safety Review Is there a documented procedure in place for Pre-Start-up Safety Reviews? Has the company defined international standards, guidelines, and industry practices for Design, Fabrication, Procurement and installation of critical equipment? Facilities Has the company defined inspection & testing requirements for fabrication, installation and maintenance? Are procedures for inspection and maintenance well defined? Electrical & Mechanical Integrity Has the company adopted RBI, RCM based maintenance plans? Are Safety Critical Elements and Activities listed and performance standards included, proof test intervals, and proof test procedures defined, documented and followed? Are maintenance and inspection personnel well trained/certified in relevant tasks? Is there any overdue maintenance of any Safety Critical Equipment? Quality Assurance 13 Are quality assurance requirements for SR-65-19-01 ToR - PSM Audit design, procurement, fabrication and installation defined and documented? How are process safety training objectives set? At what level of the organization is this done? How frequently is this assessment made, and by whom? At what level of the organization does this training take place? Training & Performance Who is assigned primary responsibility for the training? How is input provided from other groups to ensure that integration of a specific subject into the overall training program will be correct? After development of the training materials, who has the responsibility and authority for validating the completeness and accuracy of the materials? Has the validation actually taken place? Are training records maintained? Available? Are contractors involved in every aspect of PSM Program and necessary trainings given? Contractors Are contractor workers competency defined, and assessed? Is contractor work force aware of their contribution, and responsibilities towards PSM? Incident Investigation Is there a procedure/guideline in place for incident reporting and investigation? Are there any trained incident investigators 14 SR-65-19-01 ToR - PSM Audit in the organisation? Are lessons from incident investigations shared with all including employees and contractors? Are comprehensive Emergency Response Plans in place? Is ER organisation defined and known to all including employees, contractors and govt agencies? Emergency Planning & Response Area ER plans based on scenarios identified and assessed in PHRA studies? Are adequate resources required to execute ER plan, should an undesirable event occurs, available? How are govt and external agencies involved in ER planning? Are trainings, testing and drills on ER plan conducted regularly? 15 SR-65-19-01 ToR - PSM Audit Annexure I PSM Audit Questionnaire (will be given later) 16 SR-65-19-01 ToR - PSM Audit Annexure II Safety Perception Audit Check list (will be given later) 17 SR-65-19-01 ToR - PSM Audit