Flat plate/pipe column structure for low-and medium-rise buldings Those hard-to-manage columns can be hidden in the partitions of an architectural layout BY FREDERICK P. WIESINGER AND EUGENE P. HOLLAND, WIESINGER-HOLLAND LTD., STRUCTURAL ENGINEERS, CHICAGO, ILLINOIS he structural procedure described here was devised as a solution to the difficult task of fitting columns into the architectural layout of low- and medium-rise reinforced concrete buildings. It consists of a thin reinforced concrete flat plate supported on pipe columns and has been used successfully by the authors in countless apartments in the Chicago area. Traditionally, low-rise apartment buildings of two to five stories have been constructed of ordinary building materials—wood stud interior walls, wood joists and exterior masonry walls. The much debated four-plus-one buildings allowed by the city of Chicago have been built with these materials for years, as have thousands of these buildings in the suburban areas. Precast voided concrete planks bearing on masonry walls, with topping to provide a level floor surface are also extensively used, and unless the architect or developer accepts the joint lines between planks, a ceiling is also required. Needless to say, the cost of this structure far exceeds the cost of o rd i n a ry construction, thereby requiring the developer to reduce his T profit margin. Bar joists with a concrete slab and ceiling are sometimes used but appear to be in the same cost category as the voided plank construction. The spring and summer of 1968 saw a tremendous leap in the cost of lumber. Architects, contractors and developers began searching for less costly altern a t i ve s. The flat plate/pipe column idea seemed worthy of investigation, and the Dana Point Apartments in Arlington Heights, Illinois (a $15,000,000 fourand five-story development) offered an excellent opportunity for contractors and subcontractors to try new procedures. The data presented here describe some of those used. An obvious starting point for the flat plate/pipe column scheme is the three-and-five-eighths-inches space available in the interior of a standard partition because it restricts the column size to nominal three-inch pipe, with three and onehalf-inches outside diameter. Such columns can be located without causing bulges, and it is not necessary to place them into closets and c o rn e r s. Thus they can be placed relatively close to one another. Consequently, the largest necessary span is usually determined by the width of the living room. Preliminary calculations for the Dana Point development indicated that the loads would be within the capacity of the pipe columns. Compared to conventional flat plate construction, smaller spans lead to a thinner slab and to reduction in reinforcing. Article 2101 (e) of ACI 318-63 specifies at least fiveinch thickness, for which a maximum span of 15 or 16 feet is feasi- Figure 1 Pipe Columns Figure 2 I-beam capital Figure 3 Sleeve extends through slab to receive the column above. ble. Furthermore, it is clear that the support size required by peripheral shear in the slab can readily be obtained by welding a head on top of the column. The structure for Dana Point I is a five-inch thick cast-in-place reinforced concrete flat plate, supported on pipe columns with I-beam column capitals three and one-half inches wide, six inches deep and two feet long below the slab (Figure 1). The columns vary from threeinch diameter standard to extra heavy pipe entirely within the conventional partitions, as do the capitals (Figure 2). The partitions provide the necessary fire protection for both columns and capitals. A sleeve is welded to the top of the capital. This extends through the slab to receive the column above ( Fi g u re 3). The slab is reinforced in accordance with the requirements of the American Concrete Institute Code, utilizing a uniform mat of welded wire fabric in the bottom of the slab, with supplemental bottom reinforcing bars where re q u i re d . The top reinforcing is conventional and consists of reinforcing bars. The exterior masonry walls are loadbearing as well as resistant to lateral f o rc e s. Floor covering (carpet and tile) is applied directly to the slab. The underside of the slab is painted. At Dana Point, the contractor elected to place the columns from the deck above by simply dropping them through slots cut in the deck into the sleeves below. The original intention was to weld the columns to the sleeves but when the cost became known it was decided that the only reason for the welding would be long-standing engineering custom. The weld was omitted and gravity alone does the job. After the forms for holes, plumbing sleeves and such were in place, the deck was covered with the bottom mat. Electrical conduits were put in place next, followed by the top reinforcement. Concrete was placed in the usual fashion. Additional advantages devised With the successful completion of the first phase of Dana Point, the advantages of the flat plate/pipe column became apparent to other developers. Because of this growth in interest, the authors’ firm was prompted to study further the various parameters of the procedure and arrive at variations that not only fit the different types of architecture but also facilitate construction and offer further reduction in costs. Experience with building the loadbearing walls, which required a great deal of coordination and field control as well as use of highstrength masonry materials, led to providing pipe columns in the exterior walls. The exterior masonry enclosure, acting as infilled shear panels between the columns, provided the lateral bracing. Bracing A further technique was the use of scattered braced bents. Steel pipe Kbracing (Figure 4), located in the partitions between columns, provides the braced-bent action. The bents must be placed at varying locations at each floor level to avoid the accumulation of wind compression and tension forces in the columns supporting the braced panels. It developed that it is possible to base the design on the criterion of never allowing more force on the column due to wind than the amount that can be absorbed by the 33 percent increase in allowable stresses for wind. Simple formulas have been developed that determine the number of bays per floor that must be braced to accomplish this. For example, for a six-story building there is a single-K brace needed on the ground floor for e ve ry 40 linear feet of wind exposure, one for every 45 feet on the second floor, and gradual increases to one for every 126 feet on the floor below the top floor. Reinforcement The speed and ease with which the bottom reinforcement (welded wire fabric and supplemental bars) could be placed pointed up the slow and laborious procedure for setting the top reinforcement, which, on the first buildings, consisted entirely of bars. Attempts at using welded wire fabric for top re i n f o rc e m e n t proved to be uneconomical initially because of the ACI Code requirement for providing middle strip negative reinforcement (Figure 5). The most efficient way to place welded wire fabric in this location is to extend the top re i n f o rc e m e n t from over the column heads to the middle strip areas. Although this allows for simplified setting, the total amount of welded wire fabric is increased considerably, thus increasing cost. This factor led to the study of eliminating the top steel in the middle strip areas and providing for the total negative moment by increasing the reinforcement over the column head. Such departures from the standard methods specified in the ACI Code, and indeed from the standard practice, could be justified only on the basis of thorough, detailed analysis, research, and expensive tests. The Portland Cement Association committed the necessary test funds, expertise and manpower. The results of the tests were subsequently reported. * They proved conclusively that for apartment loading with short spans and thin slabs the middle strip negative moment area can be left entirely without reinforcement. Thus on subsequent projects the top reinforcement consisted entirely of a piece of welded wire fabric combined with a few reinforcing bars over the columns (Figure 6). This arrangement proved to be most economical and convenient. In-slab shearhead devised The below-slab shearhead as discussed proved to be somewhat of a nuisance, due to the fact that columns located adjacent to a doorway required a soffit to enclose the head. The possibility also existed that the shearhead would be misori* Cardenas, Alex E.; Kaar, Paul H., “Field Test of a Flat-Plate Structure,” ACI Journal, January 1971, pp. 50-59. ented with respect to the partition. To counter this problem, an in-slab shearhead was devised (Figure 7) and has been used in most of the later developments. Figure 4 Steel pipe K-bracing Random placement of columns Other considerations re q u i re d d i f f e rent kinds of innova t i o n s. It became apparent, for instance, that on some projects it is not desirable to locate columns on a grid p a t t e rn. Ra t h e r, they must be placed in a completely scattered or random fashion. This situation is not cove red by the ACI Code and thus special design pro c e d u re s were developed. Cost comparisons Sixteen projects totaling over four million square feet have been constructed with the above described p ro c e d u re s. Detailed cost comparisons made by the developers for s e ve ral sizes of bays have been updated to the latter part of 1971 (Figure 8). While it is hardly possible to generalize, it can be concluded that costs with the flat plate/pipe column method are presently about fifty cents per square foot more than o rd i n a ry (wood) construction. A number of developers decided that superior quality, lower maintenance costs, improved sound transmission p ro p e rt i e s, and reduced fire insurance rates are worth the cost differential, even where local building codes allow ordinary construction. On the other hand, when the comparison was made with any of the other building types, such as voided slab, bar joist or conventional flat plate, the flat plate/pipe column method proved to be the more economical, in the majority of cases, if no more than one- or two-hour fire rating is required. For more than two-hour ratings, the cost of fireproofing may tip the balance in the direction of concrete columns. In such cases, precast or cast-in-place columns have been used, keeping in mind the fact that the economic advantages of the method presented in this article are due, to a significant extent, to the use of thin slab FLAT PLATE TOP REINFORCEMENT Figure 5 Top reinforcement at column head and between columns ACI Code Figure 6 Top reinforcement at column head only Wiesinger-Holland Figure 7 IN-SLAB SHEARHEAD Figure 8 FLAT-PLATE COLUMN STRUCTURAL COST COMPARISON Structural cost per square foot of supported slab. Includes footings, slab on grade, pipe columns, wind bracing, and structural slabs. Does not include land, fees or general contractors’ overhead and profit. Transfer for parking not considered. reinforcement as described. The same consideration is applied to buildings that are too tall for pipe columns to support the loads. Most recent innovations Fu rther innovations in the flat plate/pipe column method are now being utilized. On-site precast s l a b s, apartment size or slightly smaller, are being lifted to form the apartment floors. The slabs for another thre e - s t o ry, twe l ve - u n i t building are supported on bearing walls. The change from the bearing wall to the pipe column type of support will be made on two projects now in the design stage. Sixs t o ry, one hundred-unit apartments in a Chicago suburb and t h re e - s t o ry, twe n t y-unit apartments in New York will utilize special multiple-purpose inserts that function as a lifting device as well as the column connector. Developers are projecting a minimum fifty cents per square foot savings by use of the on-site precast slabs. The large size panels allow all joints to fall at the partition lines, thus elim- inating the need for topping, and also eliminating the problems connected with joinery. Casting of the panels stacked on top of one another will save the expense of forming and shoring and is expected to lead to economies in field labor and materials handling—eve n when measured against the cost of erection. PUBLICATION #C720380 Copyright © 1972, The Aberdeen Group All rights reserved