End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Project Sarthak SAP Implementation at PDIL User Manual Module: Project SYSTEM USER PROCEDURE MANUAL Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 1 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 TABLE OF CONTENTS Getting Started ............................................................................................................................... 4 1.0 Create Non Chargeable Project ......................................................................................... 14 2.0 Create Non Chargeable WBS Structure ............................................................................. 18 3.0 Display Non Chargeable Project Structure ........................................................................ 23 4.0 Create Network And Activities For Non Chargeable Project ............................................ 25 5.0 Update the Project Status as Reviewed ............................................................................ 29 6.0 Update the Project Status as Approved ............................................................................ 31 7.0 Inputs Received from Concerned Departments................................................................. 34 8.0 Create Chargeable Project ................................................................................................. 38 9.0 Change Operative Structure .............................................................................................. 41 10.0 Display Operative Structure ........................................................................................... 48 11.0 Project Builder ................................................................................................................. 50 12.0 Scheduling ....................................................................................................................... 56 13.0 Attach text to Project elements ...................................................................................... 60 14.0 Update the Project Status as Request for Validation .................................................... 63 15.0 Update the Project Status as Validation Completed ..................................................... 65 16.0 Man Hours & ResourcePlanning..................................................................................... 67 17.0 Cost Plan for Materials or Services................................................................................. 72 18.0 Budgeting ........................................................................................................................ 77 19.0 Budget Supplement, Return and Transfer ..................................................................... 80 20.0 Update the Project Status as Budgeted ......................................................................... 83 21.0 Update the Project Status as Reviewed by Finance ...................................................... 85 22.0 Activity Confirmation ...................................................................................................... 88 23.0 Milestone Confirmation assigned to a WBS Element .................................................... 90 24.0 Milestone Confirmation assigned to an Activity ........................................................... 91 25.0 Cross Application Time Sheet ......................................................................................... 93 Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 2 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 26.0 Progress Calculation ....................................................................................................... 98 27.0 SETTLEMENT .................................................................................................................. 101 28.0 Update the System Status of a WBS Element to Technically Closed(TECO) ............... 106 29.0 Update the System Status of a WBS Element to Closed(CLSD) ................................... 107 Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 3 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Getting Started LOG ON: Select SAP Log in Icon On PC Desktop & press enter key or double click, Or follow the menu path as shown in following screen: Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 4 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 The following screen will appear. Select Server and click on Log on icon Logging onto the SAP R/3 system Last changed on: (DD/MM/YYYY) Sap R/3 systems are client systems. The client enables you to run several business operations at the same time in one SAP R/3 system. Client is, in organizational terms, an independent unit in the system. Clients have their own data environment and therefore their own user master and transaction data, assigned user master records and chart off accounts and specific customizing parameters. So that you log on to SAP R/3 system, you must have a master record created for you for corresponding client. For reasons of access protection, you must enter a password when you log onto the sap system. The system does not display the password you enter. Last changed by: Version: Page: 5 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 SAP R/3 system is available in several languages. Use the language input field to select the logon language for each session. You can place your own text on the initial screen Elements of the screen layout Last changed on: (DD/MM/YYYY) Command Field: Use command field (hidden as default) to go to applications directly by entering the transaction code. Standard Tool Bar: the push buttons in the standard tool bar are found on every screen in an SAP R/3 system. Any push buttons that cannot be used in a particular application are grayed out. If you place your cursor on a push button for a while the system displays a quick info text that explains the push button function. The Application Tool bar: shows which functions are available in the current application. A Tab page: provides a clearer overview of several information screens Status bar: the status bar displays information on the current system status, for example. Warning or error messages Menu bar: the menus shown here depend on which application you are working in. Title bar: the title bar displays the functions that are available for the user. Last changed by: Version: Page: 6 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Checkboxes: checkboxes enable you to select several options simultaneously within a group. Radio Buttons: allow you to choose exactly one item form a selection. The below shown screen gives you a detail explanation. Menu bar Standard toolbar Title bar Comman d Application toolbar Tab Page Input Fields Check boxes, Radio Buttons Status bar Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 7 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 SAP Easy Access Sap easy access is the standard entry screen displayed after the logon. You navigate through the system using the tree structure. You are greeted by your logo in the right-hand part of the window Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 8 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Selecting Functions You can call functions in the system as follows o Menu Option o Favourites o Entry in the SAP easy Access menu “/n” ends the current session “/i” delets the current session “/oCV01N” opens a new session and branches out to the transaction specified (CV01N) By entering “ search_sap_menu” in the command field, you can display menu paths for the desired SAP transaction. Command Field Menu SAP easy Access and Favorite List Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 9 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Field help : F1 and F4 Use F1 to display an explanation of fields, menus, functions and messages. F1 Help also provides technical information on the relevant field. F1 Help Last changed on: (DD/MM/YYYY) Use F4 to display possible inputs . you can also access F4 help for a selected field using the button immediately to the right of that field. Last changed by: Version: Page: 10 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 F4 help User – Specific Personalization Last changed on: (DD/MM/YYYY) The end user has many possibilities for personalizing the system. For example as shown in the screen below. Last changed by: Version: Page: 11 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 SAP – Symbols or icons Button Keyboard Shortcut Description Enter Key Enter/Continue Ctrl + Page Up Ctrl + S Save to database Page Up F3 Back Page Down Last changed on: (DD/MM/YYYY) Last changed by: Button Keyboard Shortcut Version: Description First page Previous page Next page Page: 12 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Shift + F3 Exit System Task Ctrl + Page Down F12 Cancel None Ctrl + P Print None Ctrl + F Find F1 Ctrl + G Find next Alt + F12 Last changed on: (DD/MM/YYYY) Last changed by: Last page Create New session Create shortcut on Desktop F1 Help Version: Customize Local Layout Page: 13 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 1.0 Create Non Chargeable Project Trigger: Once a Enquiry is approved for further execution, the Non Chargeable Project structure to be created in the system. The Project structure thus created will be used to record inputs from concerned department to create quotation. BUSINESS PROCESS PROCEDURE OVERVIEW The person responsible for the project creates the project definition, WBS elements in the system Output - Results Project created Comments Non Charegable project is created Procedural Steps Access transaction by: Via Menus Project System > Project > Special Maintenance Functions >Work break down system > Create CJ01 Via Transaction Code Create Project definition and Work break down structure : Field Name Description R/O/C User Action and Values Project Definition Project Profile Enter a unique project definition ID R Enter the relevant project profile( NCP01 – PDIL Non Chargeable Project Profile) (Note: On above table, in column “R/O/C”: “R” = Required, “O” = Optional, “C” = Conditional) Last changed on: (DD/MM/YYYY) Enter the project definition ID Enter the project profile Commen ts Last changed by: R Version: Page: 14 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Tips and Tricks: There are two ways to create a project either from an existing operative project or from the standard project. In the template area enter the project definition or the standard project to copy data into the new project. Click Last changed on: (DD/MM/YYYY) to find the current open number Last changed by: Version: Page: 15 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Click Project System ECC 6.0 Abhinay Gautam 01/12/2010 to find the proposed open number subsequently click to use the new open project ID. Press Enter Enter information on screen “Create Project Definition” as mentioned in below table: Field Name Project Definition Description Person Responsibl e Business Area Plant Last changed on: (DD/MM/YYYY) or click on Project Definition Description R/O/C User Action and Values Commen ts Enter the project definition description R Enter the project description for the required project Enter the Project Manager as Person Responsible R Enter the Project Manager as Person Responsible Enter the business area R Enter the plant O Choose from the dropdown the required business area Choose from the dropdown the Last changed by: Version: Page: 16 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Start Date Finish Date Fcst Finish Date(F) Profit Center Project System ECC 6.0 Abhinay Gautam 01/12/2010 Enter the start date of the project Enter Finish Date as last date of quotation submission Enter the finish date as last to receive inputs from department Enter the profit center required plant Enter the start date of the project R R Enter Finish Date as last date of quotation submission Choose from the dropdown R R Choose from the dropdown the required profit center Maintain Project details in tab ‘Customer Enhancement’ at project level. Make the required changes in the project save Last changed on: (DD/MM/YYYY) Last changed by: and to exit. Version: Page: 17 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 2.0 Create Non Chargeable WBS Structure Trigger: Once a project is identified for planning and execution, the same needs to be created as a project structure in the system. The Project structure thus created needs to be changed project during its execution. BUSINESS PROCESS PROCEDURE OVERVIEW The person responsible for the project edits and changes the WBS elements in the system Output – Results Project edited and changed Comments WBS elements have been changed during execution Access transaction by: Via Menus Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > Change CJ02 Via Transaction Code Enter the Project Definition / WBS Element detail on screen ‘Change Project: Initial Screen’ Create WBS element on screen “Change Project: WBS element overview” o Create Two WBS elements at level 1 – One for Inputs required from Concerned department and other for manhours booking. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 18 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: o Project System ECC 6.0 Abhinay Gautam 01/12/2010 Further structure shall be created under these two WBS elements as required. Level Enter the level in the project hierarchy R WBS Element Planning Element Enter the WBS element unique ID Check or uncheck the check box R Account Check or uncheck the check O Last changed on: (DD/MM/YYYY) Last changed by: O Enter the level of the WBS element. Enter only one WBS element at level 1. All other WBS elements should be entered below this on levels viz. 2,3,4,5. Enter WBS element ID as per the project coding mask. Check the ‘PE’ box wherever cost planning has to be carried out. If the box is not checked system will not allow cost planning at that level Check the ‘Acct’ box wherever Version: Page: 19 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Assignment box Billing Element Check or uncheck the check box O Company Code Enter The company Code R Profit Centre Enter The profit centre R network / activities or actual cost has to be booked Check the ‘Bill’ box wherever Enquiry/Quotation has to be assigned Choose from the dropdown the required company code for the WBS element PDIL Company Code – 1000 Non PDIL Company Code - 9000 Choose from the dropdown the required profit centr for the WBS element Non PDIL Profit centre - 10009000 Business Area Enter the business area O Choose from the dropdown the required business area for the WBS element i.e. only if the Business area is different than the business area as defined in the project definition Plant Enter the plant O Choose from the dropdown the required plant for the WBS element i.e. only if the plant is different than the plant as defined in the project definition Maintain operative indicators 1) Planning Element: 2) Account assignment element: 3) Billing: Last changed on: (DD/MM/YYYY) Last changed by: To allow planning in WBS elements To allow actual and commitment postings To allow assignment to sales & billing documents Version: Page: 20 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Maintain settlement rule for WBS element: Select WBS element then Goto > Edit>Cost> Settlement rule Enter information on screen “Maintain Settlement Rule – Overview” as specified in table below: Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 21 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Field Name CAT Settlement receiver % Settlement type Project System ECC 6.0 Abhinay Gautam 01/12/2010 Description Enter the settlement Category Enter the settlement receiver R/O/C R User Action and Values Enter settlement category R Enter the settlement receiver Enter the percentage Enter the settlement Type R R Enter the percentage Enter the settlement Type Maintain Project details in tab ‘Customer Enhancement’ at project level. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 22 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Make the required changes in the project save and to exit. 3.0 Display Non Chargeable Project Structure Trigger: Once a project is created, same needs to be displayed for specific users. BUSINESS PROCESS PROCEDURE OVERVIEW Project to be displayed only to specific users for information purpose Output – Results Project displayed Comments Access transaction by: Via Menus Via Transaction Code Last changed on: (DD/MM/YYYY) Last changed by: Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > Display CJ03 Version: Page: 23 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Display Project definition and Work break down structure : Field Description R/O/ User Action and Values Comme Name C nts Project Enter the project R Enter the project definition Definition definition ID (Note: On above table, in column “R/O/C”: “R” = Required, “O” = Optional, “C” = Conditional) Press Display the project and Last changed on: (DD/MM/YYYY) to display WBS elements or to display project definition. to exit. Last changed by: Version: Page: 24 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 4.0 Create Network And Activities For Non Chargeable Project BUSINESS PROCESS PROCEDURE OVERVIEW To complete the project structure viz. Network and Activities from one transaction by the user responsible. Output – Results Project is created/ changed Comments Access transaction by: Via Menus Via Transaction Code Click under project. Last changed on: (DD/MM/YYYY) Project System > Project > Project Builder CJ20N to open the project already created. System saves the last five projects processed . By double clicking on them one can open the Last changed by: Version: Page: 25 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 By clicking Last 5 project processed in CJ20N can be viewed at bottom corner of the screen. new projects can also be CREATED. Create Network and Internal activity: In the project builder from the templates area click and select the Network and activities , drag and drop it to the relevant WBS element where the Network and activities needs to be attached. Maintain required information while creating networks as follows: Description Plant – Plan to be maintained as per inputs required from required location MRP Controller – To be maintained as per the departments Create Network activities by dragging(as shown in above screenshot) from the templates area Network, Activities viz. Intenal activity, Cost activity to the required WBS element/Network. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 26 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Intenal activity can be created to receive information in form of Manhours, Mandays, Mantrips as specified in table below: Field Name Description R/O/C Activ Desc Work Activity number Description Work involved in the activity O R O Unit Unit of work R Work Work center C Plan Acti Plant Activity type O O Last changed on: (DD/MM/YYYY) Last changed by: User Action and Values Assigned by user Amount of work - to be entered by concerned departments when project is transmitted fot inputs. Unit of measure of the work quantity like HR(Hours), Day(Mandays), TRP(Mantrip) Work center number, needed to link to activities coming from a cost center Comment s Work to be entered by concerned departments when project is transmitted fot inputs. Work center to be assigned department eise Can overwrite default plant The activities as defined in CC planning Version: Page: 27 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Cost activity to be created to receive inputs in form of amount and information to be entered as specified in table below: Field Name Description R/O/C User Action and Values Desc Amount Description Costs in the activity R O Name of activity The planned cost amount to be entered by concerned departments when project is transmitted fot inputs. Cost Cost Element R Account charged for activity Last changed on: (DD/MM/YYYY) Last changed by: Version: Comment s Amount to be entered by concerned department s when project is transmitted fot inputs. Page: 28 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 5.0 Update the Project Status as Reviewed When Project structure is created and saved by BD department will trigger an intimation to competent authority to review and set the project structure to “20 -REVW” - Reviewed Menu path Transaction Logistics Project system Project Special Maintenance function WBS Change CJ02 Enter the Project No. Press Enter. Select level 1 WBS elements only on WBS overview screen and change user status to REVW Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 29 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click on Project Defintion Click on Check the Status Profile. Select the relevant status REVW Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 30 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Click on Back Click on Save. Project System ECC 6.0 Abhinay Gautam 01/12/2010 & Check the new status 6.0 Update the Project Status as Approved When Project structure is reviewed will trigger an intimation to competent authority to approve and set the project structure to “30 -APRV” - Approved Menu path Transaction Logistics Project system Project Special Maintenance function WBS Change CJ02 Enter the Project No. Press Enter. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 31 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Select level 1 WBS elements only on WBS overview screen and change user status to APRV Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 32 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click on Project Defintion Click on Check the Status Profile. Select the relevant status APRV Click on Back Click on Save. Once Non chargeable Project status is set to approved the BD can Transmit the project to & Check the new status concerned department for inputs by changing Project and WBS status to TRNS “Transmitted to department” by following the same steps as given above. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 33 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 7.0 Inputs Received from Concerned Departments BUSINESS PROCESS PROCEDURE OVERVIEW To furnish the inputs required to create quotation by BD department Output – Results Project is created/ changed Comments Access transaction by: Via Menus Via Transaction Code Project System > Project > Project Builder CJ20N Click to open the project for which input needs to be furnished. System saves the last five projects processed under . By double clicking on them one can open the project. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 34 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 A pop up will appear on screen, Enter the WBS element received in the mail and press Enter Select internal activity and enter the following information: 1. Manhours(HR) 2. Mandays(Day) 3. Manmonth(Mon) 4. Mantrip(TRP) Direct Amount to be entered in cost activity as shown below: Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 35 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Select WBS elements and change user status where inputs are given and can be submitted back to BD. Click on Change status to “50 - SUBM” - Inputs Submitted Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 36 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Click on Back Click on Save. Project System ECC 6.0 Abhinay Gautam 01/12/2010 & Check the new status **When quotation is submitted to client, Change the user status to ‘60- QUOT Quotation Submitted’ for all WBS elements and at project level as well. This will restrict further creation of quotation for the that project. **If Job is Awarded then settle all cost to costcenter and change project status to 70-YAWD and close the project. ** If Job is Not Awarded then settle all cost to costcenter and change project status to 80NAWD and close the project. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 37 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 8.0 Create Chargeable Project Trigger: Once a project is identified for planning and execution, the same needs to be created as a project structure in the system. The Project structure thus created will be used to monitor the progress of the project during its execution. BUSINESS PROCESS PROCEDURE OVERVIEW The person responsible for the project creates the project definition, WBS elements in the system Output - Results Project created Comments Operative project is created Procedural Steps Access transaction by: Via Menus Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > Create CJ06 Via Transaction Code Create Project definition and Work break down structure : Field Name Description R/O/C User Action and Values Commen ts Project Enter the project definition R Enter a unique project definition Definition ID ID Project Enter the project profile R Enter the relevant project profile Profile (Note: On above table, in column “R/O/C”: “R” = Required, “O” = Optional, “C” = Conditional) Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 38 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Tips and Tricks: There are two ways to create a project either from an existing operative project or from the standard project. In the template area enter the project definition or the standard project to copy data into the new project. Click Last changed on: (DD/MM/YYYY) to find the current open number Last changed by: Version: Page: 39 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Click to find the proposed open number subsequently click open project ID. to use the new Enter information on screen “Create Project Definition” as mentioned in below table: Field Name Project System ECC 6.0 Abhinay Gautam 01/12/2010 Description R/O/C User Action and Values Commen ts Project Definition Description Basic Data Business Area Plant Enter the project definition description R Enter the project description for the required project Enter the business area R Enter the plant O Location Enter project location O Profit Center Enter the profit center O Choose from the dropdown the required business area Choose from the dropdown the required plant Choose from the dropdown the location Choose from the dropdown the required profit center Make the required changes in the project save Last changed on: (DD/MM/YYYY) Last changed by: and to exit. Version: Page: 40 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 9.0 Change Operative Structure Trigger: Once a project is identified for planning and execution, the same needs to be created as a project structure in the system. The Project structure thus created needs to be changed project during its execution. BUSINESS PROCESS PROCEDURE OVERVIEW The person responsible for the project edits and changes the WBS elements in the system Output – Results Project edited and changed Comments WBS elements have been changed during execution Access transaction by: Via Menus Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > Change CJ02 Via Transaction Code Change Project definition and Work break down structure : Field Name Description R/O/C User Action and Values Commen ts Project Enter the project definition R Enter the project definition Definition ID Project Enter the project profile O Enter the WBS element to be Profile changed (Note: On above table, in column “R/O/C”: “R” = Required, “O” = Optional, “C” = Conditional) Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 41 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Enter the WBS Element detail by clicking on and create WBS elements Level Enter the level in the project hierarchy R WBS Element Planning Element Enter the WBS element unique ID Check or uncheck the check box R Last changed on: (DD/MM/YYYY) Last changed by: O Enter the level of the WBS element. Enter only one WBS element at level 1. All other WBS elements should be entered below this on levels viz. 2,3,4,5. Enter WBS element ID as per the project coding mask. Check the ‘PE’ box wherever cost planning has to be carried out. If the box is not checked system will not allow cost planning at that Version: Page: 42 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Account Assignment Check or uncheck the check box O Billing Element Check or uncheck the check box O Business Area Enter the business area O Plant Enter the plant O level Check the ‘Acct’ box wherever network / activities or actual cost has to be booked Check the ‘Bill’ box wherever revenue or sales document has to be assigned Choose from the dropdown the required business area for the WBS element i.e. only if the Business area is different than the business area as defined in the project definition Choose from the dropdown the required plant for the WBS element i.e. only if the plant is different than the plant as defined in the project definition Maintain operative indicators 1) Planning Element: 2) Account assignment element: 3) Billing: Last changed on: (DD/MM/YYYY) Last changed by: To allow planning in WBS elements To allow actual and commitment postings To allow assignment to sales & billing documents Version: Page: 43 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Date planning for WBS Elements: Select the WBS element and from the menu select > Details > WBS detail screen Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 44 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Field Name Project System ECC 6.0 Abhinay Gautam 01/12/2010 Description R/O/C User Action and Values Bsc Start Bsc Fin Fcst Strt Enter the basic start date Enter the basic finish date Enter the forecast start date O O O Enter the basic start date Enter the basic finish date Enter the forecast start date Fcst Fin Enter the forecast finish date O Enter the forecast finish date Act Start Enter the actual start date O Enter the actual start date Act Fin Enter the actual finish date O Enter the actual finish date Commen ts Usually during execution stage Usually during execution stage Only after WBS is released Only after WBS released Maintain Progress Version and Calculation methods in WBS elements and network activities. Maintain following details in Progress tab POC weight Progress version Meth. Plan and Meth. Act. Plan method is required here and Actual method shall be considered same as plan method. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 45 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Maintain settlement rule for WBS element: Select WBS element then Goto > Edit>Cost> Settlement rule Enter information on screen “Maintain Settlement Rule – Overview” as specified in table below: Field Name CAT Settlement receiver % Settlement type Last changed on: (DD/MM/YYYY) Description Enter the settlement Category Enter the settlement receiver R/O/C R User Action and Values Enter settlement category R Enter the settlement receiver Enter the percentage Enter the settlement Type R R Enter the percentage Enter the settlement Type Last changed by: Version: Page: 46 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Maintain Project details in tab ‘Customer Enhancement’ at project level. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 47 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: 10.0 Project System ECC 6.0 Abhinay Gautam 01/12/2010 Make the required changes in the project save and to exit. Display Operative Structure Trigger: Once a project is identified for planning and execution, same needs to be displayed for specific users. BUSINESS PROCESS PROCEDURE OVERVIEW Project to be displayed only to specific users for information purpose Output – Results Project displayed Comments Access transaction by: Via Menus Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > Display CJ03 Via Transaction Code Display Project definition and Work break down structure : Field Name Last changed on: (DD/MM/YYYY) Description Last changed by: R/O/C User Action and Values Version: Commen Page: 48 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 ts Project Enter the project definition R Enter the project definition Definition ID Project Enter the project profile O Enter the WBS element to be Profile changed (Note: On above table, in column “R/O/C”: “R” = Required, “O” = Optional, “C” = Conditional) Press Display the project and Last changed on: (DD/MM/YYYY) to display WBS elements or to display project definition. to exit. Last changed by: Version: Page: 49 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 11.0 Project Builder Trigger: Project builder is one stop tool to maintain and create the project structure. Network activities can be easily assigned to different WBS elements here simply by dragging & dropping the activity to the required WBS element. It can be noted here that it is much easier to create WBS elements in T.Code CJ01. Hence, it is up to the user’s convenience to use which ever transaction he’s comfortable with to attain the same result. In project builder on can create and change the project structure viz. WBS elements, network and activities by dragging and dropping the individual objects from the templates area. Project planning board in the project builder gives the users among other functionalities scheduling and confirming activities. BUSINESS PROCESS PROCEDURE OVERVIEW To create the entire project viz. Project definition, WBS Elements, Network and Activities from one transaction by the user responsible. Output – Results Project is created/ changed and scheduled Comments Procedural Steps Access transaction by: Via Menus Via Transaction Code Last changed on: (DD/MM/YYYY) Project System > Project > Project Builder CJ20N Last changed by: Version: Page: 50 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Click under project. By clicking Last changed on: (DD/MM/YYYY) Project System ECC 6.0 Abhinay Gautam 01/12/2010 to open the project already created. System saves the last five projects processed . By double clicking on them one can open the new projects can be CREATED. Last changed by: Version: Page: 51 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Create WBS Elements, Network and Internal activity: In the project builder from the templates area click and select the Network and activities , drag and drop it to the relevant WBS element where the Network and activities needs to be attached. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 52 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Drag and drop from the templates area the WBS element, Network and Internal Activity to the required project definition/WBS element/Network. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 53 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Create Milestone: In the project builder from the templates area click and select the Milestone drag and drop it to the relevant WBS element or activity where the milestone needs to be attached. Field Name Description R/O/C User Action and Values Commen ts Milestone description Trend Analysis Enter milestone description R Check the selection box O Basic Fix Date Fcst Fixed date Enter the date O Enter the milestone description for the WBS element Select the Check box to enable the milestone in milestone trend analysis Enter the basic fixed date Enter the forecasted date O Enter the date Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 54 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Actual date Enter the actual date O Perc of Compl. Enter the percentage of completion O Enter the actual date after the WBS/ activity has been released. Enter the percentage of completion periodically to update progress Enter Milestone description and select usage from drop down list: Maintain milestone offset to schedule with respect to activities: Maintain Progress and Billing percentage for milestones Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 55 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Maintain following checkboxes Progress analysis – If milestone is relevant for progress calulation Sales document date – If milestone is relevant billing 12.0 Scheduling Access transaction by: Menu path Transaction Project System > Project > Project Builder CJ20N Enter the Project number Select Project and expand structure Select a network and Click on Last changed on: (DD/MM/YYYY) Last changed by: to enter relationship between the activities. Version: Page: 56 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Select an activity and click on change Click to manually connect the activities in either Finish to Start, Start to Start, Start to Finish or Finish to Finish. Last changed on: (DD/MM/YYYY) Last changed by: to enter duration of an activity. Version: Page: 57 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Double Click on the relationship arrow Go Project definition by clicking Last changed on: (DD/MM/YYYY) Last changed by: to change or display the relationship to select Bottom up planning in the ‘Scheduling scenario’ Version: Page: 58 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click on or from the menu > Goto > Project Planning Board to schedule the project Select all WBS and activities and click on Save Result: The project is scheduled and saved. Last changed on: (DD/MM/YYYY) to schedule the project. the project. Last changed by: Version: Page: 59 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: 13.0 Project System ECC 6.0 Abhinay Gautam 01/12/2010 Attach text to Project elements To add long text to the WBS element go to T.Code CJ02 the WBS detail screen or double click on the WBS description to enter the WBS long text. Long text tab page To attach text to activity, go to project builder T.Code: CJ20N Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 60 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click Enter document type, description and press enter to enter detail text Last changed on: (DD/MM/YYYY) to up load PS text Last changed by: Version: Page: 61 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 To up load PS text to WBS element follow the similar steps as above. Attach document to WBS Click to Last changed on: (DD/MM/YYYY) attach document to WBS element Last changed by: Version: Page: 62 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 From the dropdown select the document type and in the ‘document’ field from the dropdown select the document to upload. Press enter and save 14.0 to exit. Update the Project Status as Request for Validation Menu path Transaction Logistics Project system Project Special Maintenance function WBS Change CJ02 Enter the Project No. Press Enter. Select level 1 WBS elements only on WBS overview screen and change user status to REFV Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 63 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click on Project Defintion Click on Check the Status Profile. Select the relevant status REFV Click on Back Last changed on: (DD/MM/YYYY) & Check the new status Last changed by: Version: Page: 64 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: 15.0 Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click on Save. Update the Project Status as Validation Completed Menu path Transaction Logistics Project system Project Special Maintenance function WBS Change CJ02 Enter the WBS Element No. Press Enter. Select the WBS Element. Click on details Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 65 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click on Check the Status Profile. Select the relevant status. Click on Back & Check the new status Similarly change the status of other WBS Elements. Click on Save. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 66 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: 16.0 Project System ECC 6.0 Abhinay Gautam 01/12/2010 Man Hours & ResourcePlanning Trigger: A new project is adopted. The project manager must then plan out the expected Manhours, Costs and Manpower to execute the project’s tasks. Business Process Procedure Overview This document describes how to enter a project manhour and cost plan . And how to assign resources to project. Input – Required Fields Project Definition/WBS Element Field Value/Comments A valid project must be created and set to allow planning (based on the operative indicator which allows planning for each WBS element and the planning profile). Output - Results A Project Plan Comments Access transaction by: Via Menus Logistics >Project System>Financials>Planning>Costs in WBS>Overall values>Change Via Transaction Code CJ20N Enter CJ20n on Transaction bar and select green button Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 67 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Click on Open Last changed on: (DD/MM/YYYY) Project System ECC 6.0 Abhinay Gautam 01/12/2010 and enter project definition for which you wish enter controlled Man hours. Last changed by: Version: Page: 68 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Select Network activity where controlled manhours needs to be planned and enter information in the fields as specified below. Field Name Description R/O/C User Action and Values Work centre Work centre Value R Enter department work center for which you want to enter controlled man hours Work Man hours R Activity Type Activity type value R Enter controlled man hours for the department Enter activity type to calculate the cost for each hour. Comments You need to enter a work center as per department (Note: On above table, in column “R/O/C” ; “R” = Required, “O” = Optional, “C” = Conditional) Click on the left green arrow Last changed on: (DD/MM/YYYY) Last changed by: or the Save icon to complete. Version: Page: 69 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Resource Planning : Select Network Activity Select Persons from the list and enter estimated work hours. Last changed on: (DD/MM/YYYY) Last changed by: and navigate to tab “Person Assignment” Version: Page: 70 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Click on the Save Project System ECC 6.0 Abhinay Gautam 01/12/2010 icon to complete. **Note : Tab “Person Assignment” only takes effec if “Work Centre” and “Hours” are entered in Network Activity. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 71 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 17.0 Cost Plan for Materials or Services Access transaction by: Via Menus Logistics >Project System>Financials>Planning>Costs in WBS>Overall values>Change CJ20N Via Transaction Code On screen “Project Builder” : Initial Screen”, open Add cost activity from template and enter plan amount. Last changed on: (DD/MM/YYYY) Last changed by: project to plan estimated cost. Version: Page: 72 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 To plan units such as materials, internal labor hours, and miscellaneous text items, click on the button Last changed on: (DD/MM/YYYY) for ‘Unit costing’. Enter information in the field as specified in table below. Last changed by: Version: Page: 73 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Field Name Description Project System ECC 6.0 Abhinay Gautam 01/12/2010 R/O/C Costing Variant Copy from:Base plan object Costing Variant R Base Planning Object O Copy from: WBS element Copy from: Fiscal year Version WBS element O User Action and Values Enter a valid cost variant key or leave the default value Enter an existing base planning object Fiscal year O Enter a WBS’s cost estimate to copy from Enter a plan year to copy from Plan Version O Enter a plan version to copy from Commen ts The existing planned units on this base planning object will be copied into this new project unit plan. Click on the enter key to continue with unit planing. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 74 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 On screen “Create Unit Cost Estimate: List Screen 1”, enter information in the fields as specified in the table below: Field Name Item Category Resource Plant/Activity Purchasing Organization Quantity Units L Description Price-total Price unit Last changed on: (DD/MM/YYYY) Description Item Category defined the type of cost you will plan: e.g. internal activity, materials, services, text items….etc. The resource code or value relative to the item category you selected (e.g. material number, a service number, a cost center…etc) Plant or activity type of the planned resource R/O/C** R User Action and Values Enter the appropriate item category for the type of expense you will plan. R Enter the correct resource relative to the category of expense you chose in the prior step. O Purchasing Organization O Quantity of planned units Unit of Measure Item Category Description of the planned unit Price based on one unit of measure Number of units to which price refers R O O O O O Enter the plant or the activity (depending on the item category). Of the planned resource. Enter the purchasing organization responsible for this planned item. Enter the planned quantity Enter the appropriate unit of measure Flags an item for subsequent processing Enter a description if desired The total cost per unit The quantity for this unit price Last changed by: Version: Comments Page: 75 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Cost Element Project System ECC 6.0 Abhinay Gautam 01/12/2010 O Enter a valid cost element for this expense Work Center Portion of costs to be treated as fixed costs Work Center O Plant Formula Plant Cost Formula O O Enter a valid work center if appropriate for this item category Enter a valid plant Enter a valid cost formula Origin Group Price-fixed Cost Element that this cost will be tracked against **Note that the values and requirements of each column will vary based on the item category. In some cases data may not be required or data may default from master records. Click on the left green arrow Last changed on: (DD/MM/YYYY) Last changed by: or the Save icon to return to overall annual planning. Version: Page: 76 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 18.0 Budgeting Access transaction by: Via Menus Alternative menu path Via Transaction Code Logistics >Project System>Financials>Budgeting>Original Budget>Change Accounting>Project System> Financials>Budgeting>Original Budget>Change CJ30 On screen “Change Original Budget: Initial Screen”, enter information in the fields as specified in the table below: To enter overall budget values, on the screen “Change Original Budget: WBS Element Overview” enter information in the fields as specified below and save Last changed on: (DD/MM/YYYY) Last changed by: Version: . Page: 77 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 In case of assigning budget based on planned cost – goto menu EDIT-> Copy view -> Planned total Click on Back Last changed on: (DD/MM/YYYY) and save Last changed by: Version: Page: 78 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Field Name Proj. Def. Description Project Definition Timeframe Project System ECC 6.0 Abhinay Gautam 01/12/2010 R/O/C User Action and Values C No entry O Entered selected fiscal year Original Budget Timeframe for budget view (overall or fiscal year). Budget amount O Enter the total budget value by WBS element. Current budget Current budget, C Distributed Distributed budget C Distributable Distributable budget C Assigned Planned Total Previous Year Assigned budget Planned cost total Previous year C C C Cumulative Remainder Cumulative budget Remainder C C Release Release C Comprised of the original budget as a amended by supplements, returns, transfers, and some other types of budget Displays total of current budget for subordinate objects Difference between current budget and distributed budget Comprised of commitment and actual postings Total plan cost value Annual budget values for the previous fiscal year Cumulative annual budget values Difference between overall plan value and cumulative value Budget amount released Click save icon to save budget data. Comments Annual view should be completed first. Since budgets tend to follow a top-down strategy, the amounts at the top level of the project should be greater than or equal to the sum of the lower level WBS elements. The system has a check feature to advise you when this is not the case Note that it is necessary to scroll right to view all of the above fields and columns. If budget amounts are entered for lower level WBS elements, the Edit>Total Up feature will total up to the higher level WBS element. Miscellaneous options To work with availability control follow the menu paths: Extras>Availability Control> Info To see if availability control is activated Extras>Availability Control>Activate To activate availability control for this project Extras>Availability Control>Reference To review project actual charges in relation to available budget. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 79 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 19.0 Budget Supplement, Return and Transfer Trigger: Internally approved increase in project funding. Business Process Procedure Overview This document describes how to modify the project budget with a funding supplement, Return or Transfer. A supplement to a project (versus a supplement in a project) will add the budget increase to all levels of the project’s hierarchy. Thus the entire project’s budget is increased. The distributed and distributable proportions from higher to lower level WBS elements remain unchanged. A supplement may be made to either the overall or the annual budget levels. This entry will create an audit trail of all changes to the original budget. Input – Required Fields Project Definition/WBS Element Field Value/Comments A valid project must be created and set to allow budgeting (based on a budget profile). Access transaction by: Via Menus Logistics >Project System>Financials>Budgeting>Supplement>To Project Via Transaction Code CJ36, CJ35, CJ34 On screen “Post Supplement: Initial Screen”, enter information in the fields as specified in the table below: Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 80 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Field Name Description Project System ECC 6.0 Abhinay Gautam 01/12/2010 R/O/C Document Date Receiver Year Document Date R Receiver Year O Overall values too Overall Values O Long Text Text Text Text (Free) O O User Action and Values Commen ts Enter the posting date of this budget change Enter the year to which the budget increase will be applied. If you enter a year in the initial screen, this serves as a default value in the entry screen. Tick on to update the overall Your budget in addition to the annual selection budget on the initial screen serves as a default in the entry screen. Select from a list of standard text types Enter a description of the budget change (Note: On above table, in column “R/O/C” ; “R” = Required, “O” = Optional, “C” = Conditional) Click on the ‘Overview’ or ‘Enter’ button. On screen “Post Supplement: List Screen”, enter information in the fields as specified in the table below: Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 81 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Field Name Receiver WBS Description WBS element R/O/C R Amount Supplement Amount R Currency Transaction Currency O Re… Receiver Year for Budge increase Overall Values Updated (yes or no) O Overall O User Action and Values Enter the WBS element that is receiving the budget supplement or increase. Comments All higher level WBS elements will also receive increase. Enter the amount by which you want to increase the project’s budget Enter the type of currency for Default will this budget amount be controlling area currency. Enter the year to which the budget increase will be applied. Tick this button ‘on’ to update the overall budget in addition to the annual budget (Note: On above table, in column “R/O/C” ; “R” = Required, “O” = Optional, “C” = Conditional) Click on the Similar steps to be followed for Budget return and Budget transfer using transactions CJ34, CJ35. respectively. Last changed on: (DD/MM/YYYY) Save icon to complete. Last changed by: Version: Page: 82 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 20.0 Update the Project Status as Budgeted Menu path Transaction Logistics Project system Project Special Maintenance function WBS Change CJ02 Enter the Project No. Press Enter. Click on Project Defintion Click on Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 83 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Check the Status Profile. Select the relevant status BUDG, to trigger a work flow to Finance Click on Back & Check the new status Click on Save . Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 84 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 21.0 Update the Project Status as Reviewed by Finance Once Finance validates the WBS element master data the user status is set to 50 – RWFB – ‘Reviewed by Finance’ by Finance. Only after this user status has been set can the WBS element be released to execution. Finance will check following parameters before putting user status ‘RWFB’: a) Organization Structure b) Operative Indicators such as planning element, account assignment element c) Settlement rules Menu path Transaction Logistics Project system Project Special Maintenance function WBS Change CJ02 Enter the Project No. Press Enter. Select level 1 WBS elements only on WBS overview screen and select Goto > Edit> User Status>Set & Pass On to ‘RWFB’ Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 85 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Select status ‘RWFB’ from the status list. Now click on Project Defintion Click on Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 86 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Check the Status Profile. Select the relevant status ’50 - RWBF’ Click on Back Click on Save Last changed on: (DD/MM/YYYY) & Check the new status . Last changed by: Version: Page: 87 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 22.0 Activity Confirmation Access Transaction By: Menu path Transaction Logistics Project System Project builder CJ20N Go to the Activity Overview on the Header Details screen of the Network :- Go to the tab for Int. Processing as shown below and select the internal activity Click on the Confirmation icon on the lower part of the screen Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 88 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 On the Next screen carry out the following steps for Partial Confirmation of the Activity:Enter activity completion percentage in field Processing %. Press Enter. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 89 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click on the “Back” button. Save the Network. Click on Final Confirmation and Completed Indicators for Full and Final Confirmation by repeating the above steps for the same activity Click on Back icon Click on Save (Ctrl+S) 23.0 Milestone Confirmation assigned to a WBS Element Access by transaction Menu path Transaction Logistics Project system Project Special Maintenance function WBS Change CJ02 Enter the WBS Element No. and press Enter (Refer Fig. below) Go to WBS Element Overview. Select the WBS Element. Click on Milestone Overview. Select the Row of a Milestone & Click on details Enter the Actual Date. Click on Back. Click on Save (Ctrl+S) Last changed on: (DD/MM/YYYY) . Last changed by: Version: Page: 90 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: 24.0 Project System ECC 6.0 Abhinay Gautam 01/12/2010 Milestone Confirmation assigned to an Activity Access by Transaction Menu path Transaction Logistics Project system Project builder CJ20N Enter the Network no. and press Enter (Refer Fig. below) Go to Activity Overview. Select the relevant Activity and confirm by entering Processing % and go back. After confirmation, system will show a pop up to confirm milestones attached to network activity Click on “Yes” and system will show another pop up with all milestones and milestones those are scheduled and needs to be confrimed with activity confirmation are already populated with actual date and can be changed if required. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 91 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Click on Back Click on Save (Ctrl+S) Last changed on: (DD/MM/YYYY) Project System ECC 6.0 Abhinay Gautam 01/12/2010 . Last changed by: Version: Page: 92 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 25.0 Cross Application Time Sheet Trigger: Timekeepers, employees and/or managers need to maintain employee time sheets. In SAP, time sheets are maintained using CATS (Cross-Application Time Sheets). Business Process Procedure Overview This document describes the business process procedure for maintaining time sheet data. Project Managers, Enigineers, HOD’s and/or input data into time sheets via the CATS screen. Time data is stored in the CATS database and is available for reporting. Tips and Tricks Enter times (F5) icon allows you to access the specified “Time Sheet: Data Entry View” Settings (F7) icon allows you to modify your Data entry profile settings (i.e. General, Time, Persons, Worklist, Default, Checks, Cost accounting variant, and Workflow) Input – Required Fields (Required fields for all steps in the business process procedure above.) Data entry profile Personnel number Key date Output - Results (Results or expected outcome.) Depends on the profile setup. A time sheet in Data Entry View will be displayed. Field Value/Comments The data entry profile determines the method of data entry, the layout of the data entry screen, and the following factors: o Whether times can be entered for individual employees or for groups of employees o Whether time sheet data is entered on a daily, weekly or monthly basis o Whether or not the data entered is subject to approval The personnel number is the only feature within a client that is unique to an employee. You have to enter a personnel number before you can display and maintain an employee's master data and time data. The Key date field will not be displayed until backing out of the “Time Sheet: Data Entry View.” Comments (Any comments that pertain to the required fields.) The field selections displayed on the time sheet are determined during profile configuration in the IMG. Procedural Steps Access transaction by: Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 93 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Via Menus Project System ECC 6.0 Abhinay Gautam 01/12/2010 (R/3 Menu Path) Logistics -> Project System -> Progress -> Confirmation -> Time Sheet -> Time Data -> Enter Accounting -> Project System -> Progress -> Confirmation -> Time Sheet -> Time Data -> Enter Via Transaction Code CAT2 On the screen “Time Sheet: Initial Screen,” enter information in the fields as specified in the table below: Field Name Data entry profile Personnel number Last changed on: (DD/MM/YYYY) Description R/O/C The data entry profile determines the method of data entry, the layout of the data entry screen, and the following factors: o Whether times can be entered for individual employees or for groups of employees o Which data can be maintained (confirmations, services, etc.) o Whether time sheet data is entered on a daily, weekly or monthly basis o Whether or not the data entered is subject to approval The personnel number is the only feature within a client that is unique to an employee. You have to enter a personnel number before you can display and R Use the matchcode to search for the Data entry profile R Use the matchcode to search for employee Personnel numbers Last changed by: User Action and Values Version: Comments Page: 94 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Key date Project System ECC 6.0 Abhinay Gautam 01/12/2010 maintain an employee's master data and time data. The Key date field will not be displayed until backing out of the “Time Sheet: Data Entry View.” R (Note: On the above table, in column “R/O/C;” “R” = Required, “O” = Optional and “C” = Conditional) On the screen “Time Sheet: Data Entry View,” enter information into the fields. Please note that the fields vary according to the Data entry profile that you have selected. Select following fields on data entry view Task Type - BER(Time sheet) Task level - P1 (PDIL) Task Component: - Normal Hours, Overtime, Tour Hours While on this screen, you can perform various functions. For example under the Edit Menu, you can Insert lines (Ctrl + F4), Delete lines (Shift + F2), Copy lines (F5), Split lines (Ctrl + F3), and create New lines (Ctrl +F5). Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 95 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Moreover, you can Select all (Shift + F7), Deselect all (Shift + F8), Sort ascending (Ctrl + F8), Sort descending (Ctrl + F9), Check entries (Ctrl + F6), and Reset entries (Ctrl + F11 Also from this screen, you can view detailed time data, display the time data in various views (Data Entry, Release, and Variable), Check the log, etc. To release time sheet, select option Release View and then select line and click on icon Release Once time sheet is released, a mail will trigger to HOD for approval. Go to SAP inbox and click on Last changed on: (DD/MM/YYYY) Last changed by: , this will display approval dash board for released hours Version: Page: 96 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Select line items need to be approved and click on Last changed on: (DD/MM/YYYY) Last changed by: and save Version: . Page: 97 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 26.0 Progress Calculation Access transaction by: Via Menus Accounting>Project System>Logistics>Project System>Progress > Progress determination Via Transaction Code CNE1, CNE5 On screen “Project Progress”, enter information in the fields aspecified in the table below: Field Name Project Definition Description Project Definition R/O/C R User Action and Values Enter a valid Project Definition value for ehich progress to be calculated WBS element WBS element R Enter a valid WBS element Last changed on: (DD/MM/YYYY) Last changed by: Version: Comments You only have to enter a project definition, a WBS element, OR a networkbut not all. Page: 98 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Network With hierarchy Network R Option to include sub-tree WBS O elements in the settlement posting Enter a valid Network Click on the ‘With hierarchy’ button if you want all lower level WBS elements to also be considered for progress calulation. Progress version to be entered 100 Progress Version With orders Enter progress version R O Click this option on if you would like all related orders also be considered for progress calculation Toperiod Fiscal Year Option to include orders linked to the Project in the settlement posting Period of project progress Fiscal year of project progress R R Test run Run is test mode (Yes or No) O Enter the period of project progress. Enter the fiscal year of the project project progress To run in test mode, leave the default button for ‘Test run’ on. To perform the actual posting, remove the test run flag. It is recommend ed to run in test mode first. Click on the ‘Execute’ button. After execution, the system will display below screen with information regarding selected data, processing options and category of no. of objects processed. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 99 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Once Progress is calculated then go to transaction ‘CNE5’ to display the report for progresss calculated: Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 100 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 27.0 SETTLEMENT Trigger: The settlement is run manually for a single project, a WBS element, or network. Business Process Procedure Overview The organization’s business process requires that project charges be settled. This process may be part of a month-end accounting close or run as frequently as desired. A project manager or a project analyst can choose an individual project/WBS/Network to settle which will cause a posting of revenue and/or expense from the project to another receiving object. Input – Required Fields Project/WBS/Network Field Value/Comments An project object must be created and must be set to allow settlement (correct status and a settlement rule established). Output - Results Settled Costs Comments For example, in capital projects, the project costs for the period would be settled to an assets under construction (nondepreciating assets), or transferred to the balance sheet. Costs can be settled to other objects such as cost centers, depending on the type of project, organizational structure and configuration. Tips and Tricks It is recommended to first run most settlement in test mode with the detail list option selected. This should give you a detailed list of any items which need to be changed or corrected before actual settlement can run successfully. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 101 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Access transaction by: Via Menus Accounting>Project System>Financials>Period-end Closing>Single Functions>Settlement>Individual Processing Via Transaction Code CJ88 On screen “Actual Settlement: Project/WBS element/network”, enter information in the fields as specified in the table below: Enter Project and select fileds as shown above. Then execute Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 102 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Actual Settlement: Project/WBS element/network Field Name Project Definition Description Project Definition WBS element Network With hierarchy WBS element Network Option to include sub-tree WBS elements in the settlement posting R R O With orders Option to include orders linked to the Project in the settlement posting Period of revenue and expenses on the project to be settled Fiscal year of revenue and expenses on the project to be settled The type of settlement that will be performed. Fiscal period into which the settlement transaction should be posted The value date for settlements to an asset. Run is test mode (Yes or No) O Detail list Settlement run to produce a detailed log (Yes or No) O Check transaction data Process to check whether data is available to settle with this run. O Settlement period Fiscal Year Processing type Posting Period Asset Value Date Test run R/O/C R R R R R O O User Action and Values Enter a valid Project Definition value to be settlement Comments You only have to enter a project definition, a WBS element, OR a networkbut not all. Enter a valid WBS element Enter a valid Network Click on the ‘With hierarchy’ button if you want all lower level WBS elements to also get settled. Click this option on if you would like all related orders to be settled. Enter the period of project revenues and expenses you would like to settle. Enter the fiscal year of the project charges that you would like to settle. Select from the list of valid processing types. Enter the posting period that settlement will post to. Enter the value date (if desired) for a project which is settling to an asset. To run in test mode, leave the default button for ‘Test run’ on. To perform the actual posting, remove the test run flag. It is recommended to run in test mode first. Tick on the ‘Detail list’ button if you would like a detailed log of the test or actual settlement run. Tick this button if you would like the system to perform a check on available data to be settled on the project. Click on the ‘Execute’ button. From the log screen, click on the ‘Details’ button to review settled data. Double chick on a settled object to review detail or select the Sender or Receiver buttons on the top of the screen. Left green arrow to exit. (Note: On above table, in column “R/O/C” ; “R” = Required, “O” = Optional, “C” = Conditional) Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 103 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 After execution system will display below screen with information regarding selected data, processing options and no.of objects settled Select detail list Last changed on: (DD/MM/YYYY) to view the settled objects(Sender and Receiver) and amount. Last changed by: Version: Page: 104 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 To display accounting documents, place cursor on line item and select accounting documents Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 105 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 28.0 Update the System Status of a WBS Element to Technically Closed(TECO) Menu path Transaction Logistics Project System Project Special Maintenance FunctionsWork Break Down Structure (WBS)Change CJ02 Enter the WBS Element No. Press Enter. Select the WBS Element. Go to Menu to Menu Bar Edit Option Status Technically Completed (Refer Fig. below) This will change the System Status to Technically Competed. Check the status Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 106 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click on Save. ** Same steps to be followed to TECO Network and Activites in transaction CJ20N. 29.0 Update the System Status of a WBS Element to Closed(CLSD) Menu path Transaction Logistics Project System Project Special Maintenance FunctionsWork Break Down Structure (WBS)Change CJ02 Enter the WBS Element No. Press Enter. Select the WBS Element. Go to Menu to Menu Bar Edit Option Status Closed (Refer Fig. below) This will change the System Status from Technically Competed to Closed Check the status Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 107 of 108 End User Manual Title: Project Sarthak Module: Release: Created by: Created on: Project System ECC 6.0 Abhinay Gautam 01/12/2010 Click on Save. ** Same steps to be followed to CLOSE(CLSD) Network and Activites in transaction CJ20N. Last changed on: (DD/MM/YYYY) Last changed by: Version: Page: 108 of 108