Uploaded by Alexey Samokhin

Audiovisual-Systems-Performance-Verification-10-2013

advertisement
ANSI/INFOCOMM 10:2013
Audiovisual Systems
Performance Verification
ANSI/INFOCOMM 10:2013
ANSI/INFOCOMM 10:2013
Audiovisual Systems Performance Verification
InfoComm International Standard
ICS 33.160
2013-12-20
Abstract
This Standard provides a framework and supporting processes for determining elements of an
audiovisual system that need to be verified; the timing of that verification within the project delivery
cycle; a process for determining verification metrics, and reporting procedures. Consultants,
integrators, manufacturers, technology support staff, owners, third-party commissioning agents, and
architects who have verification processes in place can integrate those existing processes into the
framework this Standard provides, adding customized items to those already defined in the Standard.
Keywords
audio, audio performance, audio system, audio/video performance, audiovisual integration,
audiovisual system, AV operations, AV system installation, AV system serviceability, cable labeling,
cable management, cable termination, contrast ratio, control, control performance, documentation,
electrical, evaluation, information technology (IT), measurement, metrics, network, PoE, procedures,
verification, video, video performance, visual system, wireless microphone, wireless system operation
Disclaimer
The application of this Standard is strictly voluntary. InfoComm International recommends its use but
does not assume responsibility for misinterpretation or misapplication. InfoComm International does
not assume liability for disputes resulting from the non-conformance to this Standard. Conformance
does not imply certification of a system.
Copyright
®
© 2013 by InfoComm International . This Standard may not be reproduced in whole or in part in any
form for sale, promotion, or any commercial purpose, or any purpose not falling within the provisions
of the U.S. Copyright Act of 1976, without prior written permission of the publisher. For permission,
address a request to the Director of Standards, InfoComm International.
© 2013 by InfoComm International®
Licensed to purchaser. Single user license only. Copying and networking prohibited.
ISBN: 978-0-939718-36-8
ANSI/INFOCOMM 10:2013
2013-12-20
Foreword
This Standard provides a framework and supporting processes for determining elements of an
audiovisual system that need to be verified, the timing of that verification within the project delivery
cycle, a process for determining verification metrics, and reporting procedures.
As audiovisual systems have increased in complexity, the chances of misconfiguration, improper
installation, and failure to conform to project requirements increase. Managing expectations and
verifying conformance with stated project requirements of audiovisual (AV) systems is the major goal
of this Standard. While many organizations have internal processes and verification procedures, there
is an industry-wide need to utilize project documentation along with this Standard to identify elements
within an AV system that require measurement and verification. Use of this Standard supports a
comprehensive, systematic, and practical approach to verifying performance of AV systems.
This Standard requires that project documentation has been created for the project being verified.
Documentation will vary from project to project and the standard does not prescribe the nature and
extent of the project documentation. Conformance to the Standard is not possible without project
documentation.
This Standard assumes that a project owner’s operational specifications have been established in the
system/project documentation.
This Standard does not provide a “one size fits all” verification pathway, but a means to enable the
user of the Standard to develop a project-specific list of system performance verification items based
on performance requirements defined in the project’s documentation. Being able to assess the
performance of the audiovisual system based on what was defined in the project’s documentation
should reduce dissatisfaction at the end of the project.
Using the Standard, consultants, integrators, manufacturers, technology support staff, owners, thirdparty commissioning agents, and architects who have system performance verification processes in
place can integrate those existing processes into the framework this Standard provides, adding
customized items to those already defined in the Standard.
Benefits of using this Standard are not limited to but include:
 Ability to streamline verification tests and reporting;
 Providing a verifiable outcome;
 Creating a common language between all parties;
 Aligning outcome and performance expectations at an early stage in the project;
 Creating reporting that completes the project documentation; and
 Reducing project risk through early identification of problems, thereby reducing the
likelihood of remedial work.
This Standard should be used in conjunction with ANSI/INFOCOMM 2M-2010 Standard Guide for
Audiovisual Systems Design and Coordination Processes as well as other relevant performance
standards.
About InfoComm International
®
InfoComm International is the leading non-profit association serving the professional AV
communications industry worldwide. Founded in 1939, the association offers industry expertise and
market research serving press and others seeking information about the industry. Through activities
that include trade shows, education, certification, government relations, outreach, and information
services, InfoComm promotes the industry and enhances members’ ability to conduct business
successfully and competently. InfoComm International is the ANSI Accredited Standards Developer
(ASD) dedicated to the dissemination of the knowledge of audiovisual systems performance
parameters.
© 2013 by InfoComm International®
Page ii
ANSI/INFOCOMM 10:2013
2013-12-20
About ANSI
The American National Standards Institute, Inc. (ANSI) is the national coordinator of voluntary
standards development and the clearinghouse in the United States for information on national and
international standards. An American National Standard implies a consensus of those substantially
concerned with its scope and provisions. Consensus is established when, in the judgment of the
ANSI Board of Standards Review, substantial agreement has been reached by directly and materially
affected interests. Substantial agreement means much more than a simple majority, but not
necessarily unanimity. Consensus requires that all views and objections be considered and that a
concerted effort be made toward their resolution. The use of an American National Standard is
completely voluntary. Its existence does not in any respect preclude anyone, whether he or she has
approved the standard or not, from manufacturing, marketing, purchasing, or using products,
processes, or procedures not conforming to the standard.
InfoComm International Standards Development
InfoComm International maintains a Standards Steering Committee that provides oversight to the
standards development task groups responsible for specific standards. The Steering Committee
reports to the InfoComm International Board of Directors, whose approval is required before
standards may be submitted to ANSI.
© 2013 by InfoComm International®
Page iii
ANSI/INFOCOMM 10:2013
2013-12-20
InfoComm International Standards Program Developers
At the time of this Standard’s development and approval, contributors’ names and affiliations are as
shown:
Audiovisual Systems Performance Verification Standard Task Group
Matthew Silverman, CTS, PMP, George Mason University, Moderator
John Bailey, CTS-D, CTS-I, Whitlock
Jason Brameld, BSc (Hons) ARCS, MInstSCE, PTS Consulting, LLP
Greg Bronson, CTS-D, Cornell University
Paul Depperschmidt, CTS, Cisco
Richard Derbyshire, CTS, Shen Milsom & Wilke, LLC
Dan Doolen, MS, ISF-C, CQT, University of Illinois
Tristan Gfrerer, Google, CTS, BEng (Hons)
Mike Izatt, CTS-D, Spectrum Engineers, Inc.
Thomas Kopin, CTS, ISF-C, Kramer Electronics USA
Richard Morrison, CTS, Prince2, CPEng, BE (Computer Systems), Norman Disney & Young
Mike Quinn, BEng, CEng, MIET, CTS-D
InfoComm International Standards Steering Committee
Matthew Silverman, CTS, PMP, George Mason University, Chair
Jason Antinori, CTS-D, TELUS
David Barnett, CTS-D, The Sextant Group
Michael Bialas, CVE, ITIL, Anadarko Petroleum Corporation
Jason Brameld, BSc (Hons) ARCS, MInstSCE, PTS Consulting, LLP
Joy Caspar, CTS, Real Time Services
Richard Derbyshire, CTS, Shen Milsom & Wilke, LLC
Ratnesh Javeri, CTS-D, Innovative Systems & Solutions Pvt. Ltd.
Jeffrey Lipp, CTS-D, Lipp AV Design, Inc.
Peter Pekurar, Christie Digital Systems USA, Inc.
Peter Swanson, CTS, AMX Australia
Read Wineland, CTS, Biamp
InfoComm International Staff
David Labuskes, CTS, RCDD (Executive Director and CEO)
Joseph Bocchiaro III, Ph.D., CStd, CTS-D, CTS-I, ISF-C (Vice President of Standards and Industry
Innovations)
Aron Abrams (Standards Resources Coordinator)
Jessica Drennon (Standards Development Coordinator)
Ann E. Brigida, CTS, AStd (Director of Standards)
The task group would like to thank the following organizations for providing documentation samples:
Compass Group
George Mason University
Northeastern University
proAV, UK
Pro AV Solutions, Australia
Providence University
PTS Consulting Partners LLP
Sharp’s Audio Visual, Canada
Whitlock
© 2013 by InfoComm International®
Page iv
ANSI/INFOCOMM 10:2013
2013-12-20
Table of Contents
Abstract ............................................................................................................................................. i
Keywords .......................................................................................................................................... i
Disclaimer ......................................................................................................................................... i
Copyright ........................................................................................................................................... i
Foreword ...........................................................................................................................................ii
About InfoComm International ..........................................................................................................ii
About ANSI ...................................................................................................................................... iii
InfoComm International Standards Development ............................................................................ iii
InfoComm International Standards Program Developers ................................................................iv
1
2
3
4
5
6
7
Scope, Purpose, and Application ............................................................................................. 7
1.1
Scope................................................................................................................................. 7
1.2
Purpose ............................................................................................................................. 7
1.3
Application ......................................................................................................................... 7
1.4
Exceptions ......................................................................................................................... 8
Referenced Publications ........................................................................................................... 9
2.1
Normative References ....................................................................................................... 9
2.2
Informative References ..................................................................................................... 9
Definitions ............................................................................................................................... 10
3.1
Abbreviations ................................................................................................................... 10
3.2
Definitions ........................................................................................................................ 10
Verification Framework ........................................................................................................... 11
4.1
Overview .......................................................................................................................... 11
4.2
Implementation ................................................................................................................ 11
Verification Item Selection Process Group ............................................................................. 12
5.1
Overview .......................................................................................................................... 12
5.2
Implementation ................................................................................................................ 13
5.3
Reference Verification Items ........................................................................................... 13
5.4
Functional Categories...................................................................................................... 14
5.5
Verification Phases and Milestones ................................................................................ 16
5.6
Verification Phases Implementation ................................................................................ 17
Verification Metric Selection Process Group .......................................................................... 17
6.1
Overview .......................................................................................................................... 17
6.2
Selection Process Implementation .................................................................................. 17
Performance Verification Process Group ............................................................................... 19
7.1
8
Implementation ................................................................................................................ 19
Verification Reporting Process Group .................................................................................... 19
8.1
Overview .......................................................................................................................... 20
8.2
Reporting Format and Implementation ............................................................................ 20
© 2013 by InfoComm International®
Page v
ANSI/INFOCOMM 10:2013
2013-12-20
9
Reference Verification Items by Functional Category and Verification Phase ....................... 22
9.1
Audio System Performance Reference Verification Items .............................................. 22
9.2
Video System Performance Reference Verification Items .............................................. 25
9.3
Audio/Video System Performance Reference Verification Items .................................... 27
9.4
Cable Management, Termination, and Labeling Reference Verification Items ............... 28
9.5
Control Performance Reference Verification Items ......................................................... 30
9.6
System and Record Documentation Reference Verification Items ................................. 31
9.7
Electrical Reference Verification Items............................................................................ 33
9.8
Information Technology Reference Verification Items .................................................... 34
9.9
Operations and Support Reference Verification Items .................................................... 36
9.10
Physical Environment Reference Verification Items .................................................... 37
9.11
Physical Installation Reference Verification Items ....................................................... 38
9.12
Serviceability Reference Verification Items ................................................................. 40
9.13
Wireless Reference Verification Items ......................................................................... 40
10
Acknowledgment of Conformance to the Standard ............................................................ 41
11
Annexes .............................................................................................................................. 42
11.1
Annex 1: Master List of Reference Verification Items by Verification Phase .............. 42
11.2
Annex 2: Table of Figures ............................................................................................ 49
11.3
Annex 3: Bibliography .................................................................................................. 50
© 2013 by InfoComm International®
Page vi
ANSI/INFOCOMM 10:2013
2013-12-20
1
Scope, Purpose, and Application
1.1
Scope
1.1.1
This Standard provides a comprehensive evaluation framework and associated processes
to verify functionality and performance of an audiovisual system in accordance with the
system’s project documentation. The Standard identifies the timing of verification; a list of
reference items to be considered, delineated by their function as related to the system; a
process for determining verification metrics; and reporting procedures.
1.1.2
This Standard identifies audiovisual system performance-evaluation requirements for the
following 13 functional categories:
Audio Performance
Video Performance
Audio/Video Performance
Cable Management, Termination, and Labeling
Control Performance
Electrical
Information Technology
Operations and Support
Physical Environment
Physical Installation
Serviceability
Wireless
System and Record Documentation
1.2
1.2.1
1.3
Purpose
The purpose of this Standard is to provide a framework for the verification and reporting of
the performance of an audiovisual system based on the requirements specified in the
system’s project documentation. The Standard defines 160 potential verification items; a
process for determining which items are germane to the project and a way to incorporate
additional items; a process for defining the evaluation metrics for verification; a process for
verifying the items; and a process for how and when to report those results.
Application
1.3.1
This Standard can be utilized by all parties involved in the audiovisual system installation
process including consultants, integrators, manufacturers, technology support staff,
owners, third-party commissioning agents, and architects to verify the performance of
audiovisual systems throughout the integration process.
1.3.2
Planning for the use of this Standard should begin with the project’s initiation. The
framework provided by this Standard should be integrated into the project’s project
management and/or quality management processes. For organizations that have existing
project management and/or quality management programs, the framework provided by this
Standard can be integrated into existing processes. Conformance to the Standard shall
require that all requirements of the Standard are included; this Standard does not provide
for partial conformance.
© 2013 by InfoComm International®
Page 7
ANSI/INFOCOMM 10:2013
2013-12-20
1.3.3
This Standard is aligned with ISO 21500:2012:Guidance on project management, where
the activities of this Standard take place within the Implementing, Controlling, and Closing
process groups. The Standard is aligned with ANSI/INFOCOMM 2M-2010, Standard
Guide for Audiovisual Design and Coordination Processes, where the activities of the
Standard take place within the construction phase. For projects where it is known that this
Standard is being implemented at project initiation, it is recommended that users of this
Standard begin planning for conformance to the Standard at that time.
Figure 1 – Illustration of Implementation Phases
1.3.4
1.4
This Standard can be applied to any size (scope and/or value) audiovisual system as long
as its project documentation clearly cites (and completes) a project-specific verification list
during initiation and then subsequently documents verification through the project phases.
Exceptions
1.4.1
Specific measurement metrics
This Standard does not provide measurement metrics for any defined reference
verification items in Section 9. Metrics (beyond pass/fail) should be determined by
following the process in section 6.2 of this Standard.
1.4.2
Measurement methodology
This Standard does not prescribe any specific methodology for achieving the required
metrics. Comparable measurement techniques and methods exist in many cases, and the
user of this Standard shall choose a method by using the metrics selection process
hierarchy as defined in Section 7 of this Standard once a project-specific reference
verification item is identified.
1.4.3
This Standard does not include prescription for corrective action.
1.4.4
In addition, this document is not designed as a technical training manual or roadmap for
specific actions. It is expected that all parties using this Standard have or will obtain the
necessary training and experience through other means.
© 2013 by InfoComm International®
Page 8
ANSI/INFOCOMM 10:2013
2013-12-20
2
Referenced Publications
2.1
2.1.1
2.2
2.2.1
Normative References
There are no normative references for this Standard.
Informative References
The following publications contain information that supports the design and application of
this Standard, but are not required provisions of the Standard:
American National Standards Institute. 2005. ANSI E1.8-2005 Entertainment Technology –
Loudspeaker Enclosures Intended for Overhead Suspension – Classification, Manufacture
and Structural Testing. New York, NY: American National Standards Institute.
rd
Churcher, David. 2012. BSRIA Design Framework for Building Services. 3 ed. Berkshire,
UK: The Building Services Research and Information Association.
InfoComm International®. 2009. ANSI/INFOCOMM 1M-2009 Audio Coverage Uniformity in
Enclosed Listener Areas. Fairfax, VA: InfoComm International®.
InfoComm International®. 2010. ANSI/INFOCOMM 2M-2010 Standard Guide for
Audiovisual Design and Coordination Processes. Fairfax, VA: InfoComm International®.
InfoComm International®. 2011. ANSI/INFOCOMM 3M-2011 Projected Image System
Contrast Ratio. Fairfax, VA: InfoComm International®.
InfoComm International®. 2012. ANSI/INFOCOMM 4:2012 Audiovisual Systems Energy
Management. Fairfax, VA: InfoComm International®.
InfoComm International®. 2009. AV Installation Handbook. 2
International®.
nd
ed. Fairfax, VA: InfoComm
InfoComm International®. 2012. AV Implementation Handbook. Fairfax, VA: InfoComm
International®.
International Organization for Standardization. 2012. ISO 21500:2012 Guidance on project
management. Geneva, Switzerland: International Organization for Standardization.
Royal Institute of British Architects. 2007. RIBA Outline Plan of Work. London, UK: RIBA
Publishing.
Schluter, Bob. 2002-2010. Controlling the Temperature Inside Equipment Racks. Fairfield,
NJ: Middle Atlantic Products.
© 2013 by InfoComm International®
Page 9
ANSI/INFOCOMM 10:2013
2013-12-20
3
Definitions
As used in this document, “shall” and “must” denote mandatory provisions of the Standard.
“Should” denotes a provision that is recommended, but not mandatory.
For the purposes of this Standard, the following definitions and abbreviations apply:
3.1
Abbreviations
3.2
Definitions
AHJ
AV
DSP
EDID
HDCP
ID
IP
IEEE
IEEE 802
IT
OEM
PDF
QoS
PoE
SPL
SSID
TX
UPS
Authority Having Jurisdiction
Audiovisual
Digital Signal Processing
Extended Display Identification Data
High-bandwidth Digital Content Protection
Identification (alternative: remove abbreviation in body text)
Internet Protocol
Institute of Electrical and Electronics Engineers
Wired and Wireless Ethernet Standards Suite
Information Technology
Original Equipment Manufacturer
Adobe™ Portable Document Format
Quality of Service
Power over Ethernet
Sound Pressure Level
Service Set Identification
Transmit
Uninterruptable Power Supply
Battery Management Plan: Documented plan for how batteries for battery powered
devices will be recharged or replaced.
Divisible Space: A single program space which can be divided into multiple program
spaces through the use of movable walls.
Endpoint: A source (e.g., computer, microphone, camera) or receiver (e.g., projector,
display, recorder) device at a terminal point in the signal flow of an audiovisual system.
Invasive: References a test procedure type, which requires special configuration of the
systems and their configuration to enable the test to be completed outside of normal
operating procedures.
Metric: A criterion or set of criteria stated in quantifiable terms.
Midpoint: A device within an audiovisual system (e.g., matrix switch, distribution amplifier,
DSP, signal converter) through which an audiovisual signal from a source is routed to a
receiver.
Non-invasive: References a test procedure, which can be applied without any changes to
the systems and/or configuration and is unlikely to affect another part of the system.
Owner: A person or organization contracting the completion of the audiovisual system.
Project Documentation: A group of documents specific to the project being verified that
define scope, resources, and schedule. These documents contain all governance,
contractual, process, and technical information related to the project being verified.
© 2013 by InfoComm International®
Page 10
ANSI/INFOCOMM 10:2013
2013-12-20
Record Documentation: Documentation that provides a record of the audiovisual system
installation details at the completion of the project. This may include system schematics,
equipment schedules, location drawings, etc. Record documentation is usually passed to
the owner on completion to enable the system to be maintained.
Regulatory Authority: The municipal, local, county, state, national, or international
authority that has governance over the geographic location in which the system is being
installed. May also be defined as Authority Having Jurisdiction (AHJ).
System Verifier: The person using this Standard to verify an audiovisual system’s
performance.
User-facing Controls: Controls (e.g., knobs, buttons, switches) that are readily accessible
by the user of the AV system that are not part of the defined user interface of the system.
Verifier – see System Verifier
4
Verification Framework
4.1
4.1.1
Overview
This Standard provides a customizable methodology that yields project-specific
performance verification reporting for an audiovisual system. While there is an overarching
methodology for the framework, there is no “one size fits all” approach when it comes to
system performance verification. This framework is intended to be used with existing
project and quality management processes implemented by the organization. Additionally,
existing organizational verification processes can be adapted to be in conformance with
the Standard.
Verification Item
Selection Process
Group
Verification Metrics
Selection Process
Group
Performance
Verification Process
Group
Verification
Reporting Process
Group
Figure 2 – Framework Process Groups
4.2
Implementation
4.2.1
Implementation of the Standard requires that project documentation shall exist. If project
documentation does not exist, then it shall be created prior to the application of this
framework.
4.2.2
ANSI/INFOCOMM 2M-2010, Standard Guide for Audiovisual System Design and
Coordination Processes, provides descriptions for audiovisual system project
documentation and can be used as a guideline for creating project-specific documentation.
4.2.3
This Standard and ANSI/INFOCOMM 2M-2010 are complementary and not mutually
exclusive.
© 2013 by InfoComm International®
Page 11
ANSI/INFOCOMM 10:2013
2013-12-20
4.2.4
Users of this Standard shall create a project-specific verification report at verification
phases utilizing the processes outlined in this Standard. Workflow for the application of the
Standard can be subdivided into four sequential process groups:
4.2.4.1 Verification Item Selection Process Group
The first group defines the process for selection of verification items that
are germane to the system. Selection is based on the performance
requirements as defined in the project documentation. All reference
verification items included in the reference verification list in this Standard
may not be applicable to project-specific performance requirements.
Additionally, the Standard provides for the ability to include project-specific
verification items not defined in this Standard but defined by performance
requirements in the project documentation.
4.2.4.2 Verification Metrics Selection Process Group
The second group defines the process for selection of project-specific
verification metrics for each item selected as defined in 4.2.4.1. The
specific verification metric shall be based on the stated requirements in
the project documentation and determined using relevant sources
identified by the process outlined in this section.
4.2.4.3 Performance Verification Process Group
The third group defines the process for completing the performance
verification for the project. Performance verification shall occur multiple
times throughout the project. During this process, testing of performance
and conformance with metrics as defined in 4.2.4.2 will occur.
4.2.4.4 Verification Reporting Process Group
The fourth group defines the process for issuance of a verification report
based on the outcome of the system’s performance. Reports shall be
issued multiple times during the project to provide the most up to date
verification information as the project progresses. The verifier shall be
required to acknowledge conformance to the Standard with each report
issued.
5
5.1
Verification Item Selection Process Group
Overview
This process, as noted in 4.2.4.1, defines the means that will be utilized to determine
which reference verification items will be included within the project-specific verification.
The items selected serve as the basis for establishing metrics (4.2.4.2) and verifying the
system’s performance.
Verification Item
Selection Process
Group
Verification Metrics
Selection Process
Group
© 2013 by InfoComm International®
Page 12
Performance
Verification Process
Group
Verification Reporting
Process Group
ANSI/INFOCOMM 10:2013
2013-12-20
Figure 3 – Verification Item Selection Process in the Systems Performance Verification Process
Flow
5.2
Implementation
5.2.1
The system verifier shall be responsible for conducting this process in consultation with all
applicable stakeholders for the project.
5.2.2
Verification items shall be selected based on the information and requirements defined in
the project documentation.
5.2.3
In all cases, items mandated by regulatory requirements shall be included.
5.2.4
The Standard provides a reference list of 160 potential verification items. Verification items
are organized by both functional categories and verification phases. The functional
categories group verification items by system function. The verification phases identify at
what point in a project verification should take place. Certain items identified as reference
verification items require verification during multiple verification phases.
5.2.5
The reference verification items provided shall not be regarded as an exhaustive list when
a project’s documentation outlines the need for additional specific requirements or an
organization’s processes require additional items. Provisions are made to include these
additional verification items in the project-specific verification process and reporting.
5.2.6
To determine which verification items are required:
1) Review regulatory requirements relating to the audiovisual system (e.g.,
requirements for the system to respond to an emergency condition), identify
applicable reference verification list items, and include these items on the projectspecific verification item list.
2) Review project documentation to determine specific performance requirements,
identify applicable reference verification list items, and include these items on the
project-specific verification item list.
3) Review manufacturer-provided information for equipment on the project, identify
applicable reference verification list items, and include these items on the projectspecific verification item list.
4) Review remaining reference verification list items, identify all additional applicable
verification list items which were not included in the project documentation but are
necessary to ensure the system performs as specified and include these items on
the project-specific verification item list.
5) Identify any specific client-/owner-required tests not already covered and include
these items on the project-specific verification item list.
5.2.7
The above process shall be applied for each system on the project.
5.2.8
A separate verification list shall be completed for each system.
5.2.9
All reference verification items in the Standard shall be included in verification reports.
Items identified as not applicable (N/A) shall be listed either in sequence or as a list at the
end of the verification report.
5.3
5.3.1
Reference Verification Items
Overview
This Standard defines 160 reference verification items that exist within 13 functional
categories, four verification phases, and two milestones. Although each reference
© 2013 by InfoComm International®
Page 13
ANSI/INFOCOMM 10:2013
2013-12-20
verification item exists within only one functional category, some items are included in
multiple verification phases. A comprehensive reference verification list has been provided;
however, specific projects may include systems, technology, or functional requirements
that require additional verification items. Users of the Standard may add customized
verification items to the items identified during the Verification Item Selection Process (see
4.2.4.1) and include additional tests that exceed items required in each functional
category. A complete list of reference verification items identified by functional category
and verification phase is found in Section 11.
5.3.2
Implementation
5.3.2.1 For consistency, users of this Standard shall maintain the exact numbering scheme for
verification items as defined in this Standard.
5.3.2.2 For applications that require project-specific verification items, those items shall be
numbered as PROJ-XXX where XXX is the incremental number of each additional projectspecific item, numerically starting with 100 (i.e., PROJ-100).
5.4
Functional Categories
5.4.1
Audio System Performance
Verification items within this category verify the audio system’s performance, stability, and
conformance to requirements provided within project documentation. Project-specific
verification items that address capture, transformation, or reproduction of program audio or
voice; audio signal management; acoustic environment; and loudspeaker operations shall
be listed in this section.
5.4.2
Video System Performance
Verification items within this category verify the video system’s performance, stability, and
conformance to requirements provided within project documentation. Project-specific
verification items that address capture, transformation, or reproduction of video; video
signal management; and camera operations shall be listed in this section.
5.4.3
Audio/Video System Performance
Verification items within this category verify linked audio and video system elements that
cannot be separated due to their functional requirements. These items verify performance,
stability, and conformance to requirements provided within project documentation. Projectspecific verification items that address linked audio and video system elements shall be
listed in this section.
5.4.4
Cable Management, Termination, and Labeling
Verification items within this category verify the workmanship for installation and
management of all systems’ cabling, labels, and connections conformance to requirements
provided within project documentation. Project-specific verification items that address site
cabling, rack cabling, furniture cabling, and loose cables shall be listed in this section.
The functional categories are defined as follows:
In this context, “cable” refers to all cabling including fiber and copper (e.g., twisted pair,
multicore, coaxial).
5.4.5
Control System Performance
Verification items within this category verify the control system’s performance, usability,
stability, and conformance to requirements provided within project documentation. Projectspecific verification items that address system communications, interface and control
devices, mobile device integration, external system integration (e.g., life safety, security,
environmental), automated system functions, and user interface operations shall be listed
in this section.
© 2013 by InfoComm International®
Page 14
ANSI/INFOCOMM 10:2013
2013-12-20
5.4.6
System and Record Documentation
Verification items within this category verify that the system’s project-specific record
documentation has been completed. Any documentation should be delivered in electronic
format wherever possible and practical. Project-specific verification items that address
drawings and specifications, test reports, manuals, and acceptance reports shall be listed
in this section.
5.4.7
Electrical
Verification items within this category verify the system’s interaction with mains voltage
distribution and DC power distribution within the system are in conformance with the
regulatory authority and project documentation. Project-specific verification items that
address power distribution, monitoring, and sequencing shall be listed in this section.
This category specifically excludes testing of the building’s fixed electrical installation,
which is deemed the responsibility of others as defined in the project documentation or by
regulatory authority.
5.4.8
Information Technology
Verification items within this category verify the Information Technology elements of the
system perform, provide stability, and conform to requirements provided within project
documentation. Project-specific verification items that address network integration and
performance, IT systems integration, IT security, unified communications, and software
licensing shall be listed in this section.
This category specifically excludes testing of the owner’s information technology systems
unless specified in the project documentation.
5.4.9
Operations and Support
Verification items within this category verify that operational planning and handover of
elements of the system have been conducted and conform to requirements provided within
project documentation. Project-specific verification items that support planning for
operations or address handover elements shall be listed in this section.
5.4.10 Physical Environment
Verification items within this category verify that built elements that interact with a system
perform and conform to requirements provided within project documentation. Projectspecific verification items that address structural reinforcement, lighting, enclosures,
finishes, and other built elements shall be listed in this section.
5.4.11 Physical Installation
Verification items within this category verify that the workmanship for installation of all the
equipment within the system except cabling conforms to requirements provided within
project documentation. Project-specific verification items that address containment,
installation, security, and equipment cleanliness shall be listed in this section.
5.4.12 Serviceability
Verification items within this category verify that the system is serviceable in conformance
with the requirements provided within project documentation. Project-specific verification
items that address system accessibility, access panels, and rack clearance shall be listed
in this section.
5.4.13 Wireless
Verification items within this category verify that all aspects of wireless audio, video, and
control systems perform and conform to the requirements provided within project
documentation. Project-specific verification items that address radio frequency, infrared,
Bluetooth®, Digital Enhanced Cordless Telephony (DECT), and proprietary wireless
systems shall be listed in this section.
© 2013 by InfoComm International®
Page 15
ANSI/INFOCOMM 10:2013
2013-12-20
5.5
Verification Phases and Milestones
Figure 4 – Verification Phases and Milestones
The verification phases and milestones are defined as follows:
5.5.1
Pre-Integration
Verification items that take place prior to systems integration. These items will generally
verify existing conditions or coordinated trades activities required for AV system installation
(e.g., device enclosures, backing/blocking/framing).
5.5.2
Systems Integration
Verification items that take place while the audiovisual system(s) is/are being integrated or
built, including off-site and on-site work. These items will generally verify proper operation
or configuration so that the system can function (e.g., equipment mounted level and plumb,
phantom power, termination stress, AV rack thermal gradient performance).
5.5.3
Post-Integration
Verification items that take place after the audiovisual system(s) has been completed.
These items will generally verify system performance against verification metrics as
defined in the project documentation (e.g., projected image contrast ratio, audio and video
recording, control system automated functions).
5.5.3.1 Substantial/Practical Completion
Verification milestone that indicates conditional acceptance of the project has been
issued by the owner or owner's representative, acknowledging that the project or a
designated portion is substantially/practically complete and ready for use by the
owner, however some requirements and/or deliverables defined in the project
documentation may not be complete. This milestone occurs at the end of the postintegration verification phase.
5.5.4
Closeout
Verification items involved with closing out the project. These items will generally be
related to documenting the As-Built/As-Is status of the system(s) and transfer of system
software, among other (e.g., control system test reporting, As-Built drawings complete,
warranties) items.
5.5.4.1 Final Acceptance
Verification milestone that acceptance of the project has been issued by the owner
or owner's representative, acknowledging that the project is 100% complete and
all required deliverables, services, verification lists, testing, verification, and
signoffs have been received, and all requirements defined in the project
documentation have been satisfied and completed that occur at the completion of
the closeout verification phase. No further project activity will take place after this
milestone is verified.
© 2013 by InfoComm International®
Page 16
ANSI/INFOCOMM 10:2013
2013-12-20
5.6
Verification Phases Implementation
5.6.1
Certain verification items may need verification at multiple times during a project.
5.6.2
The reference verification items provided in this Standard define the verification phases at
which those items should be tested. Where additional items are added on a projectspecific basis, these shall also be allocated a verification phase.
6
Verification Metric Selection Process Group
Verification Item
Selection Process
Group
Verification
Metrics Selection
Process Group
Performance
Verification
Process Group
Verification
Reporting Process
Group
Figure 5 – Verification Metrics Selection Process Group
6.1
Overview
6.1.1
Once the verification items have been identified, each item shall require a pass/fail
verification.
6.1.2
There are 16 (out of 160) specific verification items identified in this Standard that require a
measurement in addition to pass/fail to validate performance. These verification items are
identified in Section 9 item descriptions. The item descriptions include a sentence that
reads, “This verification item shall require a metric to be verified.”
6.1.3
There are 11 (out of 160) specific verification items identified in this Standard that it is
recommended include a measurement in addition to pass/fail to validate performance.
These verification items are identified in Section 9 in the reference verification list item
descriptions. The item descriptions include a sentence that reads, “This verification item
should require a metric to be verified.”
6.1.4
This Standard does not identify the method or measure beyond pass/fail; this should be
identified and defined by the user of the Standard.
6.2
6.2.1
Selection Process Implementation
Each project-specific verification item that has been identified and requires a metric in
addition to pass/fail shall follow this selection process:
1) Review client/owner’s key priorities – in terms of cost, quality, time, functionality, and
performance.
2) Start with the best-case metrics for the given type of installation (e.g., general
meeting room, boardroom, video conferencing, stadium).
3) Review metrics with owner, building designers and/or equipment manufacturers to
confirm that best-case metrics are achievable.
4) Modify metrics to suit project and define target metrics for the project.
© 2013 by InfoComm International®
Page 17
ANSI/INFOCOMM 10:2013
2013-12-20
Figure 6 – Verification Metric Selection Factors
6.2.2
The sources of information that shall be referenced are indicated in order of importance in
Figure 7 – Hierarchy of Metric Selection. In the case of conflict or variance between
requirements, the higher listed item shall take precedence.
6.2.3
In all cases, regulatory authority requirements shall be adhered to.
Regulatory Requirements
Project Documentation
National and International
Standards
Manufacturer
Documentation
Standard Guide
Other ‘Best Practices’
Documentation
Figure 7 – Hierarchy of Metric Selection
© 2013 by InfoComm International®
Page 18
ANSI/INFOCOMM 10:2013
2013-12-20
6.2.4
7
In many instances, best-case metrics may not be achievable as part of a system
installation due to the existing or planned building environment. When conflict exists
between the building environment and best-case metrics for the audiovisual system, a
discussion should take place between the system verifier and the owner to determine an
agreeable metric.
Performance Verification Process Group
Verification Item
Selection Process
Group
Verification Metrics
Selection Process
Group
Performance
Verification Process
Group
Verification
Reporting Process
Group
Figure 8 – Systems Performance Verification Process Group Flow
7.1
Implementation
7.1.1
This process shall be followed for performance verification in accordance with project
documentation:
1) Prepare
a. Identify parties responsible for verification and stakeholders who wish to be
involved in the process.
b. Identify when verification is to be performed.
c. Identify invasive and non-invasive test procedures.
d. Define methods of measurement and test equipment.
2) Execute
a. Confirm system availability and provide notice prior to performing
verification.
b. Perform verification.
8
Verification Reporting Process Group
Verification Item
Selection Process
Group
Verification Metrics
Selection Process
Group
Performance
Verification Process
Group
Figure 9 – Verification Reporting Process Group Flow
© 2013 by InfoComm International®
Page 19
Verification
Reporting Process
Group
ANSI/INFOCOMM 10:2013
2013-12-20
8.1
Overview
8.1.1
The system verifier shall provide reporting to the client/owner and/or the contractually
identified stakeholder(s) throughout all verification phases of the project. At a minimum, the
system verifier shall issue reports at the end of the pre-integration, integration, post
integration, and closeout verification phases.
8.1.2
If project reports are issued only once per verification phase, the reports shall include the
results of all project-specific verification items for that verification phase in a completed and
documented manner to be considered in conformance with this Standard.
8.1.3
Reports may be issued multiple times per verification phase based on project
requirements. When considered together, the reports shall include results of all projectspecific verification items for that verification phase in a completed and documented
manner to be considered in conformance with this Standard.
8.1.4
If an event (e.g., change order, remediation work, audiovisual system design changes,
building design changes, program scope change) causes a project-specific verification
item to be verified additional times, the system verifier shall reissue the verification report
for all project-specific verification items that have been verified again.
8.1.5
At the conclusion of the project, the system verifier shall issue a verification report for the
final acceptance milestone. This report shall be cumulative and contain all required report
elements and the results of all project-specific verification items that have been verified in
all verification phases of the project. After the final acceptance report has been issued, no
further reports shall be issued. This report shall be organized by the sequential verification
phases.
8.2
Reporting Format and Implementation
8.2.1
The format of the report shall be either printed, electronic, or both. Electronically formatted
reports shall be issued in a format that prevents subsequent editing.
8.2.2
Each issuance of the verification report shall include the following:
8.2.2.1 Report Header
1)
2)
3)
4)
5)
Project name
Name of system verifier
Date of issuance of report
Verification phase covered by report
To whom the report is being issued
8.2.2.2 Project-specific verification items from the verification phase covered by
the report
1) Verification item number
2) Verification item name
3) Verification item-defined metric (e.g., visual inspection, measure image
contrast ratio of 7:1, SPL at least-favored listener measured at 80 dBSPL)
4) Verification item measurement result (if required – see section 6.1)
5) Verification item pass/fail result
6) Name of the verifier/party completing item
7) Date of the verification
8) Notes and comments (if necessary)
© 2013 by InfoComm International®
Page 20
ANSI/INFOCOMM 10:2013
2013-12-20
8.2.2.3 List of reference verification items not verified on this project for the
verification phase covered by the report
8.2.2.4 Signed acknowledgment of conformance to the Standard as required in
Section 10
8.2.3
The reports shall organize the verification items in the same categorical order as they are
presented in the Standard. Verification items shall be ordered according to the following
hierarchy:
1) Functional category
2) Item number
8.2.4
Optional elements may be included in the reporting that are required for the project. Items
such as report version numbers, traceability, item descriptions, recommendations for
remedial actions, and change logs may be included at the discretion of the system verifier
or as required by project documentation.
8.2.5
In the event that the project is suspended or delayed indefinitely, a report shall be issued
noting that the process cannot be continued, and all relevant and supporting files that are
used to track, monitor, and/or note the verification process and status shall be transferred
to the owner for future use.
© 2013 by InfoComm International®
Page 21
ANSI/INFOCOMM 10:2013
2013-12-20
9
Reference Verification Items by Functional Category and Verification
Phase
9.1
Audio System Performance Reference Verification Items
AP-100
AP-101
AP-102
AP-103
AP-104
AP-105
AP-106
AP-107
AP-108
AP-109
AP-110
AP-111
AP-112
AP-113
AP-114
AP-115
AP-116
AP-117
AP-118
AP-119
AP-120
AP-121
AP-122
AP-123
AP-124
AP-125
AP-126
AP-127
AP-128
AP-129
AP-130
AP-131
Emergency Muting
Loudspeaker Zoning
Alignment of Multiple Audio Source Levels
Audio Buzz and Rattles
Audio Routes
AV Room Reverberation Time
DSP Programming
Loudspeaker Physical Alignment
Loudspeaker Polarity
Loudspeaker Time Alignment
Phantom Power
Loudspeaker Transformer Tap Setting
Acoustical Ambient Noise
Assistive Listening Devices
Audio Coverage in Listener Areas
Audio Dynamics
Audio Level Exceeds Background Noise Level
System Electronic Frequency Response
Audio System Equalization for Spectral Balance
Audio System Latency
Audio System Speech Reproduction at Listener
Positions
Audio System Total Harmonic Distortion
Conferencing Audio Levels
Conferencing Echo Suppression Performance
Loudspeaker Impedance
Microphone Physical Alignment and Placement
Microphone Gain Before Feedback
Microphone Level Alignment
Multi-channel Loudspeaker System Output
Sound Masking
Audio Reinforcement System Headroom
Audio System Signal-to-Noise Ratio
© 2013 by InfoComm International®
Page 22
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
9.1.1














Audio System Performance Reference Verification Item Numbers and Descriptions
AP-100 – Emergency Muting
o Verify that any required muting or operational change of the installed sound
system(s) has been made in accordance with local regulations in the event of a life
safety or similar emergency.
AP-101 – Loudspeaker Zoning
o Verify that loudspeaker zones are wired as defined in the project documentation.
AP-102 – Alignment of Multiple Audio Source Levels
o Verify calibration of permanent audio system inputs such that the difference
between any input signal level after the first common gain adjustment meets the
requirements of the project documentation. This verification item should require a
metric to be verified.
AP-103 – Audio Buzz and Rattles
o Verify that no audible noise caused by improper installation of any equipment
provided in completed system(s) is present.
AP-104 – Audio Routes
o Verify that all audio routes are tested from endpoint to endpoint via the appropriate
midpoint(s) for operation and routing as defined in the project documentation.
AP-105 – AV Room Reverberation Time
o Verify reverberation time meets the requirement defined in the project
documentation. This verification item shall require a metric to be verified.
AP-106 – DSP Programming
o Verify that all DSP-based products have been programmed as defined in the
project documentation.
AP-107 – Loudspeaker Physical Alignment
o Verify that loudspeakers are placed and aimed as defined in the project
documentation.
AP-108 – Loudspeaker Polarity
o Verify that all loudspeakers have correct polarity as defined in the project
documentation.
AP-109 – Loudspeaker Time Alignment
o Verify that loudspeaker time alignment performs as defined in the project
documentation. This verification item shall require a metric to be verified.
AP-110 – Phantom Power
o Verify that phantom power is provided at the correct voltage and correct locations
as defined in the project documentation.
AP-111 – Loudspeaker Transformer Tap Setting
o Verify the loudspeaker transformer tap setting in constant voltage systems is as
defined in the project documentation.
AP-112 – Acoustical Ambient Noise
o Verify that the background acoustic noise levels within audiovisual spaces are
within the required limits as detailed in the project documentation. This test is
specifically related to ambient noise levels and not audio system quiescent noise,
which is tested separately. This verification item shall require a metric to be
verified.
AP-113 – Assistive Listening Devices
o Verify that all devices that are part of the assistive listening system have been
tested as a complete end-to-end personal listening system. Verify that the
assistive listening system complies with regulatory requirements and adheres to
project documentation. This verification item should require a metric to be verified.
© 2013 by InfoComm International®
Page 23
ANSI/INFOCOMM 10:2013
2013-12-20













AP-114 – Audio Coverage in Listener Areas
o Verify that coverage of the audio systems in listener areas meets the performance
requirements as defined in the project documentation. ANSI/INFOCOMM 1M2009, Audio Coverage Uniformity in Enclosed Listener Areas should be used.
Perform separate tests for all independent systems within the project, including but
not limited to program sound, speech reinforcement, and show relay. This
verification item should require a metric to be verified.
AP-115 – Audio Dynamics
o Verify use of audio dynamics, including but not limited to noise compensation,
automatic gain control, gating, feedback suppression, compression, limiting,
delays, and levelers meets the requirements defined in the project documentation.
AP-116 – Audio Level Exceeds Background Noise Level
o Verify that the audio level provided by the installed audio system exceeds the
background noise level as defined in the project documentation. This verification
item shall require a metric to be verified.
AP-117 – System Electronic Frequency Response
o Verify that the electronic frequency response of the audio system is as defined in
the project documentation. This verification item shall require a metric to be
verified.
AP-118 – Audio System Equalization for Spectral Balance
o Verify that the audio system equalization is in accordance with the acoustic
response curves as defined in the project documentation. This verification item
shall require a metric to be verified.
AP-119 – Audio System Latency
o Verify that audio system latency meets requirements defined in the project
documentation. This verification item shall require a metric to be verified.
AP-120 – Audio System Speech Reproduction at Listener Positions
o Verify that the audio system provides speech reproduction (intelligibility) as
defined in the project documentation. This verification item should require a metric
to be verified.
AP-121 – Audio System Total Harmonic Distortion
o Verify that the total harmonic distortion of the installed audio system is as defined
in the project documentation. This verification item shall require a metric to be
verified.
AP-122 – Conferencing Audio Levels
o Verify that in a conferencing audio application, the incoming and outgoing audio
levels are checked and adjusted in the system as defined in the project
documentation. This verification item should require a metric to be verified.
AP-123 – Conferencing Echo Suppression Performance
o Verify that a system with conferencing capability performs at nominal operating
levels in a full duplex mode with echo and latency performance as defined in the
project documentation.
AP-124 – Loudspeaker Impedance
o Verify that all loudspeaker circuits have the correct impedance as defined in the
project documentation. This verification item should require a metric to be verified.
AP-125 – Microphone Physical Alignment and Placement
o Verify proper alignment and placement of microphones in the system as defined in
the project documentation.
AP-126 – Microphone Gain Before Feedback
o Verify that the speech reinforcement system is operating without feedback and at
audio levels as defined in the project documentation. This verification item shall
require a metric to be verified.
© 2013 by InfoComm International®
Page 24
ANSI/INFOCOMM 10:2013
2013-12-20





9.2
AP-127 – Microphone Level Alignment
o Verify calibration of microphone inputs so that the difference between any input
signal level after the first common gain adjustment meets the requirements of the
project documentation. This verification item should require a metric to be verified.
AP-128 – Multi-channel Loudspeaker System Output
o Verify that the audio outputs of a multi-channel loudspeaker system are assigned
correctly to designated outputs as defined in the project documentation.
AP-129 – Sound Masking
o Verify that audio system sound-pressure levels and equalization are adjusted to
the level of sound masking as defined in the project documentation. This
verification item shall require a metric to be verified.
AP-130 – Audio Reinforcement System Headroom
o Verify that the audio system is capable of performing above nominal operating
levels without distortion as defined in the project documentation. This verification
item shall require a metric to be verified.
AP-131 – Audio System Signal-to-Noise Ratio
o Verify audio system electrical signal-to-noise ratio meets the minimum levels
defined in the project documentation. This verification item should require a metric
to be verified.
Video System Performance Reference Verification Items
VP-100
VP-101
VP-102
VP-103
VP-104
VP-105
VP-106
VP-107
VP-108
VP-109
VP-110
VP-111
9.2.1


EDID Management Plan
HDCP Management Plan
Projected Display Physical Alignment
Video System Pixel Failure Tolerance
Image Geometry
Displayed Image Performance
Colorimetry
Multiple Resolution Performance of Video Displays
Projected Display Brightness Uniformity
Projected Image Contrast Ratio
Test Video Routes
Video Camera Image and Operation
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Video System Performance Verification Item Numbers and Descriptions
VP-100 – EDID Management Plan
o Verify that the EDID (Extended Display Identification Data) management plan has
been implemented as defined in the project documentation.
VP-101 – HDCP Management Plan
o Verify that the HDCP (High-bandwidth Digital Content Protection) management
plan has been implemented as defined in the project documentation.
© 2013 by InfoComm International®
Page 25
ANSI/INFOCOMM 10:2013
2013-12-20










VP-102 – Projected Display Physical Alignment
o Verify that the combined installation of projector and screen provides a displayed
image that is correctly aligned to the active projection screen surface without
misalignment unless an alternative condition is specified in the project
documentation.
VP-103 – Video System Pixel Failure Tolerance
o Verify that all displayed images do not have pixel failures (bright or dead pixels)
that exceed the requirements of the project documentation or the manufacturer’s
specifications. This verification item shall require a metric to be verified.
VP-104 – Image Geometry
o Verify that all displayed images are correctly focused, have the correct image
geometry and are free from distortion (e.g., stretching, keystone,
barrel/pincushion). Any requirements for projection mapping or image shaping to
unusual surfaces should be validated in accordance with the requirements of the
project documentation.
VP-105 – Displayed Image Performance
o Verify that the components of the displayed image system(s) (projection or directview) perform(s) as required with relation to image size, viewing angles, sight
lines, viewer locations and/or any other requirements as defined in the project
documentation.
VP-106 – Colorimetry
o Verify calibration of all video displays to ensure they display colors uniformly to a
common reference standard as defined in the project documentation.
VP-107 – Multiple Resolution Performance of Video Displays
o Verify that the system(s) accurately displays all resolutions required by project
documentation on all displays within the system (i.e., no pixel shift, no geometric
distortion, no artifacts from scaling, letterboxing, pillarboxing, or windowboxing).
VP-108 – Projected Display Brightness Uniformity
o Verify that the combined installation of projector and screen provides a display to
the viewer that meets the requirements of the project documentation. This
verification item shall require a metric to be verified.
VP-109 – Projected Image Contrast Ratio
o Verify that the system conforms to the appropriate viewing category as defined in
the project documentation. The testing methodology in ANSI/INFOCOMM 3M2011 shall be used. The projected image contrast ratio shall be measured for all
projected images within the system. This verification item shall require a metric to
be verified.
VP-110 – Test Video Routes
o Verify that all video routes are tested from endpoint to endpoint via the appropriate
midpoint(s) for operation and routing required by the project documentation.
VP-111 – Video Camera Image and Operation
o Verify that cameras, lenses, and pan/tilt systems operate as defined in the project
documentation. Inspect the camera image through the full lens operation.
© 2013 by InfoComm International®
Page 26
ANSI/INFOCOMM 10:2013
2013-12-20
9.3
Audio/Video System Performance Reference Verification Items
AVP-100
AVP-101
AVP-102
AVP-103
AVP-104
AVP-105
9.3.1






Emergency Communications
Genlocking (Video Synchronization)
Audio and Video Recording
Audio/Video Sync
Radio Frequency Television Distribution
Source Testing
X
X
X
X
X
X
X
X
Audio/Video System Performance Reference Verification Item Numbers and Descriptions
AVP-100 – Emergency Communications
o Verify that emergency communications systems properly receive inputs and
information from other systems (including but not limited to life safety systems,
security systems, and weather notifications), deliver appropriate notifications to
target audiences, comply with regulatory requirements, and adhere to
requirements defined in the project documentation.
AVP-101 – Genlocking (Video Synchronization)
o Verify that the video synchronization of the system is performing as defined in the
project documentation.
AVP-102 – Audio and Video Recording
o Verify that audio and video signals are being routed to the recording device(s) and
that the recording device(s) is operating correctly, as defined in the project
documentation.
AVP-103 – Audio/Video Sync
o Verify that audio/video synchronization is maintained to ensure the proper time
alignment of signals during playback at the point of user experience or
transmission as defined in the project documentation. This verification item should
require a metric to be verified.
AVP-104 – Radio Frequency Television Distribution
o Verify that the radio frequency and satellite intermediate frequency distribution
systems provide all services to all endpoints as defined in the project
documentation. This verification item shall require a metric to be verified.
AVP-105 – Source Testing
o Verify that the signal produced by a source typical of what will be used in normal
operation of the system is routed through the system to applicable endpoints and
produces the performance as defined in the project documentation. A test
generator shall not be used for this verification item.
© 2013 by InfoComm International®
Page 27
ANSI/INFOCOMM 10:2013
2013-12-20
9.4
Cable Management, Termination, and Labeling Reference Verification Items
CABL-100
CABL-101
CABL-102
CABL-103
CABL-104
CABL-105
CABL-106
CABL-107
CABL-108
CABL-109
CABL-110
CABL-111
CABL-112
CABL-113
CABL-114
CABL-115
CABL-116
9.4.1




Cable Bend Radius
AV Connector Plate Input and Output Labeling
AV Connector Seating
AV Connector Verification
AV Equipment Power Cable Management
AV System Cable Labeling
Cable Separation
Cable Supports
Cable Ties
Cables Bundled by Type
Cables Dressed
Patch Panel Configuration
Patch Panel Labeling
Termination Stress
AV Connector Plate Consistent Labeling
AV System Cabling Verification
Cable Length Required for Serviceability
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Cable Management, Termination, and Labeling Verification Item Numbers and
Descriptions
CABL-100 – Cable Bend Radius
o Verify that cables are not bent beyond their minimum bend radius as specified in
cable data sheet in order to maintain signal integrity as defined in the project
documentation. Project documentation may state a larger radius to allow for a
safety margin.
CABL-101 – AV Connector Plate Input and Output Labeling
o Verify that all AV connector plate inputs and outputs are labeled as defined in the
project documentation.
CABL-102 – AV Connector Seating
o Verify that all AV connectors are correctly keyed, seated, and latched to respective
connection points as defined in the project documentation. Conditions where
physical parameters exceed the connector's ability to maintain full seating should
be resolved as defined in the project documentation.
CABL-103 – AV Connector Verification
o Verify that all AV cable terminations are made securely and meet the
recommendations of the connector and cable manufacturer(s), published
standards, and requirements defined in the project documentation.
© 2013 by InfoComm International®
Page 28
ANSI/INFOCOMM 10:2013
2013-12-20













CABL-104 – AV Equipment Power Cable Management
o Verify that all AV equipment power cables are managed as defined in the project
documentation. Verify that cables are managed in a uniform and acceptable
manner so as not to compromise safety/OEM warranty, AV signal quality, and/or
future field service.
CABL-105 – AV System Cable Labeling
o Verify that all AV system cables are identified by a unique ID as defined in the
project documentation. Verify that this unique ID is displayed permanently at both
ends of the cable, is legible, and is positioned where it can be seen without undue
disturbance.
CABL-106 – Cable Separation
o Verify that both site and rack cables have appropriate separation according to
signal type and level as defined in the project documentation.
CABL-107 – Cable Supports
o Verify that all cables are supported throughout their lengths as defined in the
project documentation.
CABL-108 – Cable Ties
o Verify that, where appropriate, cable ties are used to secure the cables, are
correctly tensioned, and that the correct type of cable tie(s) is used as defined in
the project documentation.
CABL-109 – Cables Bundled by Type
o Verify that cables are only bundled together when their construction, signal type,
and signal level are compatible and will not cause measureable crosstalk or
interference between cables.
CABL-110 – Cables Dressed
o Verify that cables are dressed to ensure that all rack and site cables are installed
to provide serviceability, safety, and aesthetics as defined in the project
documentation.
CABL-111 – Patch Panel Configuration
o Verify that all patch panels have been correctly wired and configured as defined in
the project documentation.
CABL-112 – Patch Panel Labeling
o Verify that all patch panels have been labeled as defined in the project
documentation. Verify that all labeling is machine-printed, consistent, durable,
accurate, and legible.
CABL-113 – Termination Stress
o Verify that all cable terminations have been completed and adequately supported
to minimize stress on the termination point and/or connector.
CABL-114 – AV Connector Plate Consistent Labeling
o Verify that AV connector plates have consistent labeling throughout the project as
defined in the project documentation.
CABL-115 – AV System Cabling Verification
o Verify that all cabling is the correct type and routed correctly from point to point as
defined in the project documentation.
CABL-116 – Cable Length Required for Serviceability
o Verify that sufficient cabling is available so the device can be placed in a
serviceable location as defined in the project documentation.
© 2013 by InfoComm International®
Page 29
ANSI/INFOCOMM 10:2013
2013-12-20
9.5
Control Performance Reference Verification Items
CON-100
CON-101
CON-102
CON-103
CON-104
CON-105
CON-106
9.5.1







Control System Communications
Interfacing and Control of External Devices and Systems
Mobile Device Integration
System Response to Emergency Conditions
Control System Automated Functions
Control System User Interface Performance
Control System Response Time
X
X
X
X
X
X
X
X
X
X
X
Control Performance Reference Verification Item Numbers and Descriptions
CON-100 – Control System Communications
o Verify that all control communications are tested from endpoint to endpoint via the
appropriate midpoint(s) for operation and functionality as defined in the project
documentation.
CON-101 – Interfacing and Control of External Devices and Systems
o Verify that AV control system interfaces to and from control systems provided by
others conform to requirements as defined in the project documentation.
CON-102 – Mobile Device Integration
o Verify that mobile devices that are to be supported are integrated and operating as
defined in the project documentation.
CON-103 – System Response to Emergency Condition(s)
o Verify that any required response of the installed audiovisual system(s) in the
event of a life safety or similar emergency operates in accordance with local
regulations and as defined in the project documentation. This item specifically
excludes sound system response to an emergency condition, which is covered
under item AP-100, Emergency Muting.
CON-104 – Control System Automated Functions
o Verify that all time-dependent or automated functions executed by the control
system conform to requirements as defined in project documentation.
CON-105 – Control System User Interface Performance
o Verify that the control system is implemented in a manner consistent with the
requirements as defined in the project documentation.
CON-106 – Control System Response Time
o Verify that the control system provides the user response time and maximum
latency defined in the project documentation. This verification item should require
a metric to be verified.
© 2013 by InfoComm International®
Page 30
ANSI/INFOCOMM 10:2013
2013-12-20
9.6
System and Record Documentation Reference Verification Items
DOC-100
DOC-101
DOC-102
DOC-103
DOC-104
DOC-105
DOC-106
DOC-107
DOC-108
DOC-109
DOC-110
DOC-111
DOC-112
DOC-113
DOC-114
DOC-115
DOC-116
DOC-117
DOC-118
DOC-119
DOC-120
Final Inventory of AV Equipment
Approval of Samples
Delivered Product Against Samples
Wireless Frequency Licensing
Consultant’s Testing
General Contractor’s Testing
Integrator’s Testing
Manufacturer’s Testing
Owner’s Testing
Third-Party Testing
Substantial/Practical Completion
As-Built Drawings Complete
Audio System Test Reporting
Control System Test Reporting
Final Commissioning Report and System Turnover
Required Closeout Documentation
Software Licensing
User Manuals
Video System Test Reporting
Warranties
Final Acceptance
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
9.6.1
System and Record Documentation Reference Verification Item Numbers and Descriptions

DOC-100 – Final Inventory of AV Equipment
o Verify that all equipment has been delivered as defined in the project
documentation.
DOC-101 – Approval of Samples
o Verify that samples of all equipment to be used as defined in the project
documentation have been submitted for approval.
DOC-102 – Delivered Product Against Samples
o Where samples of products have been required for approval, verify that the
products that are delivered are the same and of the same quality.
DOC-103 – Wireless Frequency Licensing
o Verify that the correct and valid wireless frequency licensing permits have been
obtained for legal operation of the system.
DOC-104 – Consultant’s Testing
o Verify that any consultant’s testing requirements defined in the project
documentation have been performed and approved.




© 2013 by InfoComm International®
Page 31
ANSI/INFOCOMM 10:2013
2013-12-20















DOC-105 – General Contractor’s Testing
o Verify that any general contractor’s testing requirements defined in the project
documentation have been performed and approved.
DOC-106 – Integrator’s Testing
o Verify that any integrator’s testing requirements have been performed and
approved as defined in the project documentation.
DOC-107 – Manufacturer’s Testing
o Verify that any manufacturer’s testing requirements defined in the project
documentation have been performed and approved.
DOC-108 – Owner’s Testing
o Verify that any owner’s testing requirements defined in the project documentation
have been performed and approved.
DOC-109 – Third-Party Testing
o Verify that any third-party testing requirements have been performed and
approved as defined in the project documentation.
DOC-110 – Substantial/Practical Completion
o Verify that a conditional acceptance of the project has been issued by the owner or
owner’s representative, acknowledging that the project or a designated portion is
substantially/practically complete and ready for use by the owner, however some
requirements and/or deliverables defined in the project documentation may not be
complete.
DOC-111 – As-Built Drawings Complete
o Verify that a complete set of accurate as-built drawings indicating all AV devices,
AV device locations, mounting details, system wiring and cabling interconnects,
and all other details has been provided as defined in the project documentation.
DOC-112 – Audio System Test Reporting
o Verify that the audio system test report has been completed and issued as defined
in the project documentation.
DOC-113 – Control System Test Reporting
o Verify that the control system test report has been completed and issued as
defined in the project documentation.
DOC-114 – Final Commissioning Report and System Turnover
o Verify that the final commissioning report has been completed, issued to the
proper entity, and accepted as defined in the project documentation.
DOC-115 – Required Closeout Documentation
o Verify that a complete set of as-built system documentation has been provided as
defined in the project documentation.
DOC-116 – Software Licensing
o Verify that the usage and ownership rights have been assigned as defined in the
project documentation.
DOC-117 – User Manuals
o Verify that manufacturer’s user manuals are delivered to the owner in a format
defined in the project documentation (e.g., binders, PDFs), or dispose of the
manuals in a responsible manner (recycling) if the owner specifies that they do not
wish to receive the manuals.
o Integrator- or programmer-created manuals and documentation shall be delivered
to the owner in a format defined in the project documentation.
DOC-118 – Video System Test Reporting
o Verify that the video system test report has been completed and issued as defined
in the project documentation.
DOC-119 – Warranties
o Verify that all warranties are activated and that all warranty details have been
passed to the owner as defined in the project documentation.
© 2013 by InfoComm International®
Page 32
ANSI/INFOCOMM 10:2013
2013-12-20

9.7
DOC-120 – Final Acceptance
o Verify that a final acceptance of the project has been issued by the owner or
owner’s representative, acknowledging that the project is 100% complete, that all
required deliverables, services, project-specific verification lists, testing,
verification and signoffs have been received, and that all requirements defined in
the project documentation have been satisfied and completed.
Electrical Reference Verification Items
ELEC-100
ELEC-101
ELEC-102
ELEC-103
ELEC-104
ELEC-105
ELEC-106
ELEC-107
ELEC-108
9.7.1






AV Equipment Connected to Proper Circuit
Grounding/Earthing
Mains Voltage Sub-Distribution Integrity
Power Sources
Power Sequencing
UPS Operation
DC Power Distribution
Power Loss Recovery
Power Monitoring
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Electrical Reference Verification Item Numbers and Descriptions
ELEC-100 – AV Equipment Connected to Proper Circuit
o Verify that all AV equipment is powered from the designated power circuit and
outlet as defined in the project documentation. No additional (non-AV) equipment
should be connected unless permitted in the project documentation.
ELEC-101 – Grounding/Earthing
o Verify that all elements of the AV system are correctly bonded to an electrical
ground/earth in accordance with the requirements of the regulatory authority and
as defined in the project documentation.
ELEC-102 – Mains Voltage Sub-Distribution Integrity
o Verify that all electrical sub-distribution systems provided by the AV contractor in
equipment racks, furniture, and similar structures meet local regulatory
requirements for electrical integrity.
ELEC-103 – Power Sources
o Verify that the sources of mains voltage AC power to be used for the supply of AV
equipment are correct as defined in the project documentation and have been
tested to the outlet in accordance with local electrical standards.
ELEC-104 – Power Sequencing
o Verify that the power sequencing of devices is correct as defined in the project
documentation.
ELEC-105 – UPS Operation
o Verify that the uninterruptible power supply (UPS) is performing to the
specifications as defined in the project documentation.
© 2013 by InfoComm International®
Page 33
ANSI/INFOCOMM 10:2013
2013-12-20



IT-100
IT-101
IT-102
IT-103
IT-104
IT-105
IT-106
IT-107
IT-108
IT-109
IT-110
IT-111
IT-112
IT-113
IT-114
IT-115
IT-116
9.8.1

Content Delivery Network
IEEE 802 Wireless Security
Network Bandwidth
Network QoS (Quality of Service)
Network Security
Telephony
Unified Communications
AV IP Address Scheme
IEEE 802 Wireless Networks
PoE (Power over Ethernet)
Network Topology
Application Integration
Enterprise Management Tools
Identity Management
Network Performance Under Full Functional Load
Remote Access
Remote Management
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Closeout
Post-Integration
Systems
Integration
Information Technology Reference Verification Items
Pre-Integration
9.8
ELEC-106 – DC Power Distribution
o Verify that all DC powered devices are receiving the proper voltage and current for
normal operation.
ELEC-107 – Power Loss Recovery
o Verify that the AV systems resume normal operation on the restoration of power
following a hard electrical power outage. Power loss recovery shall include
verification of the resumption state on power recovery. Resumption state shall be
the control system start-up condition/start page (where applicable) and resetting all
devices to a known state as defined in the project documentation.
ELEC-108 – Power Monitoring
o Verify power-monitoring equipment is working and reporting as defined in the
project documentation. Power-monitoring equipment should be verified with a
known electrical load where possible. If power-monitoring data is being collected
for an energy management system, connectivity with the system should be
verified.
Information Technology Verification Item Numbers and Descriptions
IT-100 – Content Delivery Network
o Verify that the content delivery network (e.g., digital signage) is in place and
provides the required connectivity for the required audio, video, and control
systems.
o Verify that all required content licensing has been acquired.
© 2013 by InfoComm International®
Page 34
ANSI/INFOCOMM 10:2013
2013-12-20













IT-101 – IEEE 802 Wireless Security
o Verify that the wireless network is protected in accordance with the client/owner’s
information security policies from unauthorized access and provides the required
connectivity for the audio, video, and control systems.
IT-102 – Network Bandwidth
o Verify that the required network bandwidth is available for control, audio, video,
and data as part of either a shared or a dedicated audiovisual network.
IT-103 – Network QoS (Quality of Service)
o Verify that the required Quality of Service (QoS) is in place for audio, video, and
data as part of either a shared network or a dedicated audiovisual network.
IT-104 – Network Security
o Verify that the shared or dedicated network is secure as defined in the project
documentation and accessible to suit the required audio, video, and control
systems.
IT-105 – Telephony
o Verify that any required telephony connections to the AV system are in place and
connectivity is verified.
IT-106 – Unified Communications
o Verify that any connections to IT-based unified communication applications that
will interface with the AV system have been planned for and integrated.
IT-107 – AV IP Address Scheme
o Verify and document that all network-connected equipment has the correct IP
address, subnet mask, hostname, and gateway configuration as defined in the
project documentation.
IT-108 – IEEE 802 Wireless Networks
o Verify that the wireless network configuration is correct and valid (e.g., channel
no., SSID, TX power) in defined areas of use as defined in the project
documentation.
o Verify that there is adequate channel separation between any client wireless
networks that are required to co-exist in the same area.
IT-109 – PoE (Power over Ethernet)
o Verify that PoE (Power over Ethernet) devices are supplied with correct power
required for normal device operation.
o Verify under normal operations that the switch providing PoE has the capacity to
power all of the devices that are connected to it.
IT-110 – Network Topology
o Verify that the network for audio, video, and control is of a suitable topology to
support the services to be delivered as defined in the project documentation.
IT-111 – Application Integration
o Verify that the audiovisual and control systems have been integrated and have
been fully configured with headend software, including monitoring and asset
management; databases; web-based front ends; digital signage software and
systems; content generation and distribution platforms; and appliances as defined
in the project documentation.
IT-112 – Enterprise Management Tools
o Verify that enterprise management tools such as central monitoring client/server or
web-based applications have been installed and connected to all systems they are
required to monitor or control as specified in the project documentation.
IT-113 – Identity Management
o Verify that all systems-authentication credentials are configured correctly. Any
temporary credential used during system installation and commissioning should be
removed.
o User and group authentication and authorization are verified based on the
requirements from the project documentation. Connectivity with the central
directory, database, or other identity authority should be verified.
© 2013 by InfoComm International®
Page 35
ANSI/INFOCOMM 10:2013
2013-12-20



9.9
IT-114 – Network Performance Under Full Functional Load
o Verify that the network can provide the required operational performance to carry
control, audio, video, and data under production load and at times of peak
production load (refer to IT-102 Network Bandwidth).
IT-115 – Remote Access
o Verify that remote access to AV and IT systems are configured as defined in the
project documentation.
IT-116 – Remote Management
o Verify that remote management tools such as virtual touch panels, internal web
applications, or manufacturer’s applications are configured and functional as
required by the project documentation and/or manufacturer’s specification.
Operations and Support Reference Verification Items
OP-100
OP-101
OP-102
OP-103
9.9.1




Software
Battery Management Plan
Content Management Plan
System Content Provided
X
X
X
X
X
X
X
Operations and Support Reference Verification Item Numbers and Descriptions
OP-100 – Software
o Verify that all control programming code, DSP configuration files, and any other
associated software have been provided as defined in the project documentation.
OP-101 – Battery Management Plan
o Verify that a battery management plan has been completed and supplied to the
owner in the project documentation package.
OP-102 – Content Management Plan
o Verify there is a plan for managing the content to be delivered by the audiovisual
systems, including the means to create content and update content when new
information needs to be conveyed.
OP-103 – System Content Provided
o Verify that any owner, vendor, or third-party-produced system content that is
required for operations as defined in the project documentation has been supplied,
loaded, and tested in the completed AV system.
© 2013 by InfoComm International®
Page 36
ANSI/INFOCOMM 10:2013
2013-12-20
9.10 Physical Environment Reference Verification Items
PHYSE-100
PHYSE-101
PHYSE-102
PHYSE-103
PHYSE-104
PHYSE-105
PHYSE-106
PHYSE-107
PHYSE-108
PHYSE-109
PHYSE-110
PHYSE-111
PHYSE-112
PHYSE-113
PHYSE-114
Divisible Spaces
Human Factors, Usability, and Ergonomics
Lighting
Vibration
Backing/Blocking/Framing
Clean Building Handover
Coordinated Construction Elements
Device Enclosures
Finishes
Floor Boxes/Wall Boxes/Ceiling Boxes
HVAC Commissioned
HVAC Operations
Structural Mounting
Protection of Installed Equipment
Accessibility
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
9.10.1 Physical Environment Verification Item Numbers and Descriptions






PHYSE-100 – Divisible Spaces
o Verify that the divisible spaces provide the functionality defined in the project
documentation.
PHYSE-101 – Human Factors, Usability, and Ergonomics
o Verify that ergonomics and usability elements for audience and system users are
installed and configured as defined in the project documentation.
PHYSE-102 – Lighting
o Verify that the lighting systems are suitable for each type of application (e.g., video
conferencing, presentation, broadcast, performance) as defined in the project
documentation. This verification item should require a metric to be verified.
PHYSE-103 – Vibration
o Verify that the physical environment is suitable for the intended audiovisual
systems in relation to all sources of vibration affecting stability of equipment such
as videoconferencing cameras, document cameras, and fixed screen and
projector locations.
PHYSE-104 – Backing/Blocking/Framing
o Verify that installed backing, blocking, and framing meets project documentation
requirements and industry standards for installation means and methods.
PHYSE-105 – Clean Building Handover
o Verify that the area is clean, free of dust, and suitable for equipment installation
and that no further work is planned that will release contaminants into any AV
equipment area.
o Verify that the area released is isolated from any areas not yet released.
© 2013 by InfoComm International®
Page 37
ANSI/INFOCOMM 10:2013
2013-12-20









PHYSE-106 – Coordinated Construction Elements
o Verify that the elements (including but not limited to spatial requirements and
building services) required by the AV system that are coordinated with other
disciplines have been provided as defined in the project documentation.
PHYSE-107 – Device Enclosures
o Verify that device enclosures accommodate the intended device and that all
necessary environmental controls (e.g., heating, cooling, humidity) are
incorporated into the enclosure as defined in the project documentation.
PHYSE-108 – Finishes
o Verify AV equipment, furniture, fixtures, and accessories against the project
documentation.
PHYSE-109 – Floor Boxes/Wall Boxes/Ceiling Boxes
o Verify that installed floor, wall, and ceiling boxes meet project documentation and
regulatory authority requirements.
PHYSE-110 – HVAC Commissioned
o Verify the HVAC system has been tested and balanced prior to completing
verification items AP-112 and AP-116.
PHYSE-111 – HVAC Operations
o Verify the HVAC system has begun continuous operations in advance of
equipment operations.
PHYSE-112 – Structural Mounting
o Verify configuration and compatibility of structural accommodations and all
mounting hardware based on the intended application. All equipment mounting
hardware shall be installed in the manner specified by the hardware manufacturer.
PHYSE-113 – Protection of Installed Equipment
o Verify that all elements of the AV system are free of damage.
PHYSE-114 – Accessibility
o Verify that all systems are accessible in accordance with regulatory requirements.
9.11 Physical Installation Reference Verification Items
PHYSI-100
PHYSI-101
PHYSI-102
PHYSI-103
PHYSI-104
PHYSI-105
PHYSI-106
PHYSI-107
PHYSI-108
PHYSI-109
PHYSI-110
PHYSI-111
Cable Containment/Conduit
AV Rack Air Flow and Temperature Performance
Equipment Security
AV Equipment Labeling
Plumb and Level/Square
Site Security
AV Equipment Located Per Project Documentation
AV Rack Cleanliness
Non-End-User Controls Protection
Optical Components Cleanliness
Handling of Accessories Otherwise Undefined
Turnover of Accessory System Elements
© 2013 by InfoComm International®
Page 38
X
X
X
X
X
X
X
X
X
X
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
9.11.1 Physical Installation Reference Verification Item Numbers and Descriptions











PHYSI-100 – Cable Containment/Conduit
o Verify that installed containment/conduit capacity and routes meet project
documentation requirements, industry standards, and regulatory requirements for
installation means and methods.
o Verify that installed containment/conduit is serviceable and free of contaminants.
PHYSI-101 – AV Rack Air Flow and Temperature Performance
o Verify that the AV rack(s) provides the air flow as required in the project
documentation.
o Verify that the temperature in the AV rack has been measured and is within
tolerances defined by manufacturers’ guidelines and the project documentation.
This verification item shall require a metric to be verified.
PHYSI-102 – Equipment Security
o Verify that equipment is secured as defined in the project documentation.
o Verify that all security systems, devices, and manufacturer security accessories
are installed and verified to be operating as defined in project documentation.
o Verify that keyed devices have been keyed as defined in the project
documentation and devices requiring configuration have been configured as
defined in the project documentation and are verified to be operating within
specification.
PHYSI-103 – AV Equipment Labeling
o Verify that all AV equipment has been labeled in accordance with the requirements
of the project documentation. All labeling must be consistent, durable, accurate,
and visible without dismantling of sub-assemblies.
PHYSI-104 – Plumb and Level/Square
o Verify that all AV equipment has been installed, aligned, or angled correctly as
defined in the project documentation. Level and plumb are the default requirement
unless particular angles or other alignments are defined in the project
documentation.
PHYSI-105 – Site Security
o Verify that all elements of the AV system are free from loss, damage, or
tampering.
PHYSI-106 – AV Equipment Location
o Verify that AV equipment is installed at the location and/or in the rack or enclosure
as defined in the project documentation. Equipment is installed per the elevation or
other specification provided by the project documentation or the manufacturer’s
specification.
PHYSI-107 – AV Rack Cleanliness
o Verify that all components installed in AV equipment racks are free from dirt, dust,
water, or any other element that would compromise the performance and/or
longevity of the AV system.
PHYSI-108 – Non-End-User Controls Protection
o Verify that installed items with user-facing controls that are not intended for enduser access have been covered, disabled, or otherwise secured to prevent enduser operation.
PHYSI-109 – Optical Components Cleanliness
o Verify that all optical components, such as lenses and mirrors, are free from dirt,
dust, damage, or markings that would compromise the optical performance of
those system components.
PHYSI-110 – Handling of Accessories Otherwise Undefined
o Verify that all items that are pre-packaged with primary system equipment but
have no documented/planned use in the AV system(s) are managed in
accordance with the project documentation.
© 2013 by InfoComm International®
Page 39
ANSI/INFOCOMM 10:2013
2013-12-20

PHYSI-111 – Turnover of Accessory System Elements
o Verify that any equipment that may be considered portable and/or otherwise not
specifically incorporated into the installed AV system(s) has been set up,
configured, and tested.
9.12 Serviceability Reference Verification Items
SERV-100
SERV-101
SERV-102
SERV-103
Access Panels
Ability to Maintain and Service Equipment
Input and Output Panel Accessibility
Rack Clearance
X
X
X
X
X
9.12.1 Serviceability Reference Verification Item Numbers and Descriptions




SERV-100 – Access Panels
o Verify that any access panels that have been installed to provide access to any
type of AV equipment are properly sized and positioned as detailed in the project
documentation.
SERV-101 – Ability to Maintain and Service Equipment
o Verify that all equipment is accessible and capable of being maintained, serviced,
cleaned, or adjusted as necessary.
o Verify that all equipment requiring regular cleaning or maintenance is accessible
without requirement for special equipment or tools that would disrupt the normal
use of the facility and systems therein.
SERV-102 – Input and Output Panel Accessibility
o Verify that all input and output panels are accessible and meet all requirements for
user access and placement.
SERV-103 – Rack Clearance
o Verify rack placement and use for physical stability in accordance with the project
documentation and regulatory authority.
9.13 Wireless Reference Verification Items
WL-100
WL-101
WL-102
WL-103
Wireless Audio Systems Operation
Wireless Control Systems Operation
Wireless Coordination
Wireless Video Systems Operation
© 2013 by InfoComm International®
Page 40
X
X
X
X
X
X
X
X
X
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
9.13.1 Wireless Reference Verification Item Numbers and Descriptions




WL-100 – Wireless Audio Systems Operation
o Verify that the operation of wireless audio systems (RF and IR) is as defined in the
project documentation.
WL-101 – Wireless Control Systems Operation
o Verify that the operation of wireless control systems (RF and IR) is as defined in
the project documentation.
WL-102 – Wireless Coordination
o Verify that the environment is suitable for the required wireless services (RF and
IR) to provide audio, video, and control, and can be implemented for the required
number of channels as defined in the project documentation.
WL-103 – Wireless Video Systems Operation
o Verify that the operation of wireless video systems (RF and IR) is as defined in the
project documentation.
10 Acknowledgment of Conformance to the Standard
Acknowledgment of conformance to the Standard shall include a written statement,
authored and signed by the system verifier, stating that all requirements of this Standard
have been completed, the date of completion, and that the handover of the completed,
verified system is finalized.
An example of this acknowledgment statement:
The system verifier acknowledges that the performance of this audiovisual system has
been verified in conformance with all required processes and contains all required
elements as documented within INFOCOMM 10:2013 Audiovisual Systems Performance
Verification.
_____________________________________
System Verifier
Date
© 2013 by InfoComm International®
Page 41
ANSI/INFOCOMM 10:2013
2013-12-20
11 Annexes
The provisions in the annexes that accompany this Standard are not mandatory and are
included for purposes of clarification, illustration, or general information.
11.1 Annex 1: Master List of Reference Verification Items by Verification Phase
This annex provides master list of all 13 functional category reference verification items by
verification phase.
Audio System Performance Reference Verification Items by Verification Phase
AP-100
AP-101
AP-102
AP-103
AP-104
AP-105
AP-106
AP-107
AP-108
AP-109
AP-110
AP-111
AP-112
AP-113
AP-114
AP-115
AP-116
AP-117
AP-118
AP-119
AP-120
AP-121
AP-122
AP-123
AP-124
AP-125
AP-126
AP-127
AP-128
AP-129
AP-130
AP-131
Emergency Muting
Loudspeaker Zoning
Alignment of Multiple Audio Source Levels
Audio Buzz and Rattles
Audio Routes
AV Room Reverberation Time
DSP Programming
Loudspeaker Physical Alignment
Loudspeaker Polarity
Loudspeaker Time Alignment
Phantom Power
Loudspeaker Transformer Tap Setting
Acoustical Ambient Noise
Assistive Listening Devices
Audio Coverage in Listener Areas
Audio Dynamics
Audio Level Exceeds Background Noise Level
System Electronic Frequency Response
Audio System Equalization for Spectral Balance
Audio System Latency
Audio System Speech Reproduction at Listener
Positions
Audio System Total Harmonic Distortion
Conferencing Audio Far-Side Level Adjust
Conferencing Echo Suppression Performance
Loudspeaker Impedance
Microphone Physical Alignment and Placement
Microphone Gain Before Feedback
Microphone Level Alignment
Multi-Channel Loudspeaker System Output
Sound Masking
Audio Reinforcement System Headroom
Audio System Signal-to-Noise Ratio
© 2013 by InfoComm International®
Page 42
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
Video System Performance Verification Items by Verification Phase
VP-100
VP-101
VP-102
VP-103
VP-104
VP-105
VP-106
VP-107
VP-108
VP-109
VP-110
VP-111
EDID Management Plan
HDCP Management Plan
Projected Display Physical Alignment
Video System Pixel Failure Tolerance
Image Geometry
Displayed Image Performance
Colorimetry
Multiple Resolution Performance of Video Displays
Projected Display Brightness Uniformity
Projected Image Contrast Ratio
Test Video Routes
Video Camera Image and Operation
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Audio/Video System Performance Verification Items by Verification Phase
AVP-100
AVP-101
AVP-102
AVP-103
AVP-104
AVP-105
Emergency Communications
Genlocking (Video Synchronization)
Audio and Video Recording
Audio/Video Sync
Radio Frequency Television Distribution
Source Testing
© 2013 by InfoComm International®
Page 43
X
X
X
X
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
Cable Management, Termination, and Labeling Reference Verification Items by Verification
Phase
CABL-100
CABL-101
CABL-102
CABL-103
CABL-104
CABL-105
CABL-106
CABL-107
CABL-108
CABL-109
CABL-110
CABL-111
CABL-112
CABL-113
CABL-114
CABL-115
CABL-116
Cable Bend Radius
AV Connector Plate Input and Output Labeling
AV Connector Seating
AV Connector Verification
AV Equipment Power Cable Management
AV System Cable Labeling
Cable Separation
Cable Supports
Cable Ties
Cables Bundled by Type
Cables Dressed
Patch Panel Configuration
Patch Panel Labeling
Termination Stress
AV Connector Plate Consistent Labeling
AV System Cabling Verification
Cable Length Required for Serviceability
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Control Reference Verification Items by Verification Phase
CON-100
CON-101
CON-102
CON-103
CON-104
CON-105
CON-106
Control System Communications
Interfacing and Control of External Devices and Systems
Mobile Device Integration
System Response to Emergency Condition
Control System Automated Functions
Control System User Interface Performance
Control System Response Time
© 2013 by InfoComm International®
Page 44
X
X
X
X
X
X
X
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
System and Record Documentation Reference Verification Items by Verification Phase
DOC-100
DOC-101
DOC-102
DOC-103
DOC-104
DOC-105
DOC-106
DOC-107
DOC-108
DOC-109
DOC-110
DOC-111
DOC-112
DOC-113
DOC-114
DOC-115
DOC-116
DOC-117
DOC-118
DOC-119
DOC-120
Final Inventory of AV Equipment
Approval of Samples
Delivered Product Against Samples
Wireless Frequency Licensing
Consultant’s Testing
General Contractor’s Testing
Integrator’s Testing
Manufacturer’s Testing
Owner’s Testing
Third-Party Testing
Substantial/Practical Completion
As-Built Drawings Complete
Audio System Test Reporting
Control System Test Reporting
Final Commissioning Report and System Turnover
Required Closeout Documentation
Software Licensing
User Manuals
Video System Test Reporting
Warranties
Final Acceptance
X
X
X
X
X
X
X
X
X
X
X
X
X
Electrical Reference Verification Items by Verification Phase
ELEC-100
ELEC-101
ELEC-102
ELEC-103
ELEC-104
ELEC-105
ELEC-106
ELEC-107
ELEC-108
AV Equipment Connected to Proper Circuit
Grounding/Earthing
Mains Voltage Sub-Distribution Integrity
Power Sources
Power Sequencing
UPS Operation
DC Power Distribution
Power Loss Recovery
Power Monitoring
X
X
X
X
X
X
X
X
X
X
X
X
Information Technology Reference Verification Items by Verification Phase
© 2013 by InfoComm International®
Page 45
X
X
X
X
X
X
X
X
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
IT-100
IT-101
IT-102
IT-103
IT-104
IT-105
IT-106
IT-107
IT-108
IT-109
IT-110
IT-111
IT-112
IT-113
IT-114
IT-115
IT-116
Content Delivery Network
IEEE 802 Wireless Security
Network Bandwidth
Network QoS (Quality of Service)
Network Security
Telephony
Unified Communications
AV IP Address Scheme
IEEE 802 Wireless Networks
PoE (Power over Ethernet)
Network Topology
Application Integration
Enterprise Management Tools
Identity Management
Network Performance Under Full Functional Load
Remote Access
Remote Management
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Operations and Support Reference Verification Items by Verification Phase
OP-100
OP-101
OP-102
OP-103
Software
Battery Management Plan
Content Management Plan
System Content Provided
© 2013 by InfoComm International®
X
X
X
Page 46
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
Physical Environment Reference Verification Items by Verification Phase
PHYSE-100
PHYSE-101
PHYSE-102
PHYSE-103
PHYSE-104
PHYSE-105
PHYSE-106
PHYSE-107
PHYSE-108
PHYSE-109
PHYSE-110
PHYSE-111
PHYSE-112
PHYSE-113
PHYSE-114
Divisible Spaces
Human Factors, Usability, and Ergonomics
Lighting
Vibration
Backing/Blocking/Framing
Clean Building Handover
Coordinated Construction Elements
Device Enclosures
Finishes
Floor Boxes/Wall Boxes/Ceiling Boxes
HVAC Commissioned
HVAC Operations
Structural Mounting
Protection of Installed Equipment
Accessibility
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Physical Installation Reference Verification Items by Verification Phase
PHYSI-100
PHYSI-101
PHYSI-102
PHYSI-103
PHYSI-104
PHYSI-105
PHYSI-106
PHYSI-107
PHYSI-108
PHYSI-109
PHYSI-110
PHYSI-111
Cable Containment/Conduit
AV Rack Air Flow and Temperature Performance
Equipment Security
AV Equipment Labeling
Plumb and Level/Square
Site Security
AV Equipment Located Per Project Documentation
AV Rack Cleanliness
Non-End-User Controls Protection
Optical Components Cleanliness
Handling of Accessories Otherwise Undefined
Turnover of Accessory System Elements
© 2013 by InfoComm International®
Page 47
X
X
X
X
X
X
X
X
X
X
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
Serviceability Reference Verification Items by Verification Phase
SERV-100
SERV-101
SERV-102
SERV-103
Access Panels
Ability to Maintain and Service Equipment
Input and Output Panel Accessibility
Rack Clearance
X
X
X
X
X
Wireless Reference Verification Items by Verification Phase
WL-100
WL-101
WL-102
WL-103
Wireless Audio Systems Operation
Wireless Control Systems Operation
Wireless Coordination
Wireless Video Systems Operation
© 2013 by InfoComm International®
Page 48
X
X
X
X
X
X
X
X
X
X
X
X
ANSI/INFOCOMM 10:2013
2013-12-20
11.2 Annex 2: Table of Figures
FIGURE 1
FIGURE 2
FIGURE 3
FIGURE 4
FIGURE 5
FIGURE 6
FIGURE 7
FIGURE 8
FIGURE 9
ILLUSTRATION OF IMPLEMENTATION PHASES............................................................................................. 8
FRAMEWORK PROCESS GROUPS .......................................................................................................... 11
VERIFICATION ITEM SELECTION PROCESS IN THE SYSTEMS PERFORMANCE VERIFICATION PROCESS FLOW .. 12
VERIFICATION PHASES ......................................................................................................................... 16
VERIFICATION METRIC SELECTION PROCESS GROUP .............................................................................. 17
VERIFICATION METRIC SELECTION FACTORS .......................................................................................... 18
HIERARCHY OF METRIC SELECTION ....................................................................................................... 18
SYSTEMS PERFORMANCE VERIFICATION PROCESS GROUP FLOW ............................................................ 19
VERIFICATION REPORTING PROCESS GROUP FLOW ................................................................................ 19
© 2013 by InfoComm International®
Page 49
ANSI/INFOCOMM 10:2013
2013-12-20
11.3 Annex 3: Bibliography
The AIA (American Institute of Architects). Terminology: As-Built Drawings, Record Drawings,
Measured Drawings. AIA BP 11.02.04. 2007.
http://www.aia.org/aiaucmp/groups/secure/documents/document/aiap026835.pdf.
Audio Engineering Society. AES Standard for Audio Applications of Networks - High-performance
Streaming Audio-Over-IP Interoperability. AES67-2013. New York: Audio Engineering Society,
2013.
BICSI and InfoComm International. AV Design Reference Manual. Tampa, FL and Fairfax, VA: BICSI
and InfoComm International, 2006.
Department for Education and Skills. Acoustic Design of Schools: A Design Guide. Building Bulletin
93. London: Department for Education and Skills, 2013.
Dilaura, David L., Kevin W. Houser, Richard G. Mistrick, and Gary R. Steffy, eds. The Lighting
Handbook: Reference and Application. 10th ed. Salem, MA: Illuminating Engineering Society of
North America, 2011.
Cisco Systems, Inc. Cisco TelePresence Room Design Guide. San Jose: Cisco Systems, Inc., 2012.
IEC (International Electrotechnical Commission). Sound System Equipment – Part 16: Objective
Rating of Speech Intelligibility by Speech Transmission Index. 4th ed. IEC 60269-16. Geneva: IEC,
2011.
InfoComm International. ACU Field Guide. Fairfax, VA: InfoComm International, 2011.
———. Audio Coverage Uniformity in Enclosed Listener Areas. ANSI/INFOCOMM 1M-2009.
Fairfax, VA: InfoComm International, 2009.
———. Audiovisual Best Practices: The Design and Integration Process for the AV and
Construction Industries. Fairfax, VA: InfoComm International, 2005.
———. Audiovisual Systems Energy Management. ANSI/INFOCOMM 4: 2012. Fairfax, VA:
InfoComm International, 2012.
———. AV Implementation Handbook. Fairfax, VA: InfoComm International, 2012.
———. AV Installation Handbook. 2nd Ed. Fairfax, VA: InfoComm International, 2009.
———. Dashboard for Controls Design Guide: A Guide for the Creation of Touchpanel Control
Interfaces for AV Systems. Fairfax, VA: InfoComm International, 2005.
———. Design Guidelines for ACU. Fairfax, VA: InfoComm International, 2012.
———. Projected Image System Contrast Ratio. ANSI/INFOCOMM 3M-2011. Fairfax, VA:
InfoComm International, 2011.
———. Standard Guide for Audiovisual Design and Coordination Processes. ANSI/INFOCOMM
2M-2010. Fairfax, VA: InfoComm International, 2010.
ISO (International Organization for Standardization). Acoustics — Measurement of Room Acoustic
Parameters — Part 2: Reverberation Time in Ordinary Rooms. ISO 3382-2. Geneva: ISO, 2008.
———. Quality Management Systems – Fundamentals and Vocabulary. 3rd ed. ISO9000. Geneva:
ISO, 2005.
© 2013 by InfoComm International®
Page 50
ANSI/INFOCOMM 10:2013
2013-12-20
Jeffreys, Greg. Specifying and Assessing Projected Image Quality. Bromham, UK: Paradigm
Audiovisual Ltd., 2005. (Revised 2006).
Maltese, Mario. AV 9000: Defining Quality in Engineered Audio Visual Systems. Raleigh, NC:
AQAV, 2012.
———. Association for Quality in AV Technology (AQAV) AV9000:2011 Standard. Raleigh, NC:
AQAV, 2011. (Revised 2013).
National Fire Protection Association (NFPA). Standard for National Fire Alarm and Signaling Code.
NFPA 72. Quincy, MA: NFPA, 2013.
Standards Australia. Australian / New Zealand Standard: Acoustics – Measurement of the
reverberation time in rooms. AS/NZS 2460. Sydney: Standards Australia, 2002.
———. Australian / New Zealand Standard: Acoustics – Recommended design sound levels and
reverberation times for building interiors. AS/NZS 2107. Sydney: Standards Australia, 2000.
———. Australian / New Zealand Standard: Coaxial cable and optical fibre systems for the RF
distribution of analog and digital television and sound signals in single and multiple dwelling
installations. AS/NZS 1367. Sydney: Standards Australia, 2007.
© 2013 by InfoComm International®
Page 51
ANSI/INFOCOMM 10:2013
2013-12-20
APPROVAL VERIFICATION
Matthew Silverman, CTS, PMP
Chair
InfoComm International
Standards Steering Committee
© 2013 by InfoComm International®
Ann E. Brigida, CTS, AStd
Director of Standards
InfoComm International
Page 52
Download
Study collections