Project:
ai BANK EL Haram
ARCHITECTURE WORKS
Item
No.
Description
RAISED FLOORS
7.9.
Section -1-: GENERAL REQUIREMENTS:
Supplying and installing 600X600x40mm raised floor calcium sulphate tiles produced by
"MERO", or similar for the IT room, with total height including pedestals from 100mm to
400mm made of high density and high performance chipboard core 38-40mm thickness, 4
sides banding in PVC/ABS trim protection, galvanized steel sheet base. Complete work
including all accessories, stringer is connected to pedestal head with screws, gluing the
pedestal to the RC slab using approved epoxy clue, surface preparation, painting the room
floor using antistatic paint material to be approved by the Consultant.
7.10.
7.11.1
7.11.2
Quantity
m2
12
ml
80
m2
90
m2
15
Rate EGP.
Amount EGP.
PVC Skirting
Supplying and installing approved PVC skirting 700mm height to match with the above
Raised floor,Vinel tiles. Complete work including cutting, placing, proper fixation to the walls
using approved bonding material, neat joining with the Raised floor, ...etc.material to be
approved by the Consultant.
7.11.
Unit
CARPET TILES
Supplying and installing Environmental Friendly carpet tiles 500 *500 MM for customer
service and manger room from(Milliken) code (FXN44-47 Mocha) Antibacterial with
approval color as per the Code ,. Completed work including cutting, placing,using approved
gluing material,…etc. which should making necessary opening for floor boxes whenever
requested or directed by the Engineer,Different samples must be submitted for review and
approval prior of starting the delivery and installation works.
All specified as per Square Meter
DITTO as above but for premier room from(Milliken) code (FXA169-05-27 Boom)
All specified as per Square Meter
16
Project:
ai BANK EL Haram
ARCHITECTURE WORKS
Item
No.
Description
7.12. CARPET Skirting
Section -1-: GENERAL REQUIREMENTS:
Supplying and installing approved PVC skirting Covered with Carpet 50mm height to match
with the above Carpet tiles. Complete work including cutting, placing, proper fixation to the
walls using approved bonding material, neat joining with the Raised floor, ...etc.material to
be approved by the Consultant.
7.13.
Unit
Quantity
ml
25
m2
5
m2
160
Rate EGP.
Amount EGP.
INTERLOCK SIDEWALK PAVE
Supplying & installing for outside sidwalk (street side) heavy duty interlock pre-cast concrete
pave 80mm thick red & grey colour shape as per approved sample produced by
"EUROPEAN", "TECHNOC-CRETE" or similar. The interlock shall be laid on lean concrete bed
150mm thickness class (fcu 250kg/cm2) on well compacted 50mm clean sand bed complete
works including lean concrete layer, sand bed, leveling alignment, filling the joints, ....etc.
Data sheets, and various samples must be submitted for review and approval prior of
commencing the Works.
All specified as per Square Meter
Section 8:- CLADDING & WALL TILING WORKS
8.1.
DRY WALL PARTITION
Supplying and erecting dry wall partitions produced by "KNAUF", "LAFARGE" or approved
similar 100mm thick. full height extending from floor slab to the underside of the above
floor slab for various rooms complete as shown on relevant drawing and in the hereinafter
specifications:
1). Made of fire rated (90 min) gypsum boards F(DF) face panels 12mm thick with
acoustic insulation- high density rock wool 100kg/m3 - to fill completely the
space between the gypsum boards. Joints between boards shall be completely
concealed in order after being painted to visually appear as a solid masonry wall.
2).
The panels shall be fastened to the studs by means of hardened steel clips with
prongs embedded into the panel long edges and screwed on the studs; clips shall
be fixed to the adjacent panel and slid between the first panel and the stud
structure clips shall be placed at a distance not exceeding 400mm.
3).
The boards must provide - at least - one hour fire rating.
4). The partitions should not expose any screws on panels.
5).
The scope of work includes providing the necessary stiffening of substructure for
the cable routing and the hanging of the boards, providing the necessary
opening and box -outs for electrical fittings (lighting and power switches)
6). Complete sound insulation by using foam tapes to seal all the penetrations to
maintain the sound integrity.
7). Workshop drawings and a proto-type sample of a dry wall panel including its
fixation accessories must be submitted for review and approval prior of
commencing the Works.
All specified as per Square Meter