LUNDIN MALAYSIA LIMITED PROVISION OF BASIC ENGINEERING DESIGN SERVICES FOR PHASE 2 AND PHASE 3 OF PM3 DEVELOPMENT CONTRACT NO. : P98-016 HSE PHILOSOPHY B2 B1 1 0 Rev. 26-Sep-00 15-Sep-00 04-Aug-00 21-Jun-00 Date Design Basis – Final Issue Design Basis – Final Issue IDC Preliminary Description FCM FCM FCM FCM By TJ TJ NCL NCL Checked Approved Job No. ® Engineers and Constructors Protek Engineers Sdn Bhd : Client Approved P98-016 Document No : P2-GEN-L-PH-99-905 File name : HSE Philosophy Page : Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development CONTENTS 1 INTRODUCTION 4 1.1 Background 4 1.2 Purpose 4 1.3 Basis of Philosophy 5 1.3.1 General Approach 5 1.3.2 Strategies 5 1.3.3 Studies 5 1.3.4 Implementation 6 1.4 Legislation, Regulations, Codes & Standards 1.4.1 National Fire Protection Association Codes 1.4.2 Legislation / Statutory Requirements 1.4.3 Other Relevant Statutory Requirements 1.4.4 Other Related Documents 6 6 6 7 7 1.5 Definitions and Abbreviations 1.5.1 Definition of Terms 1.5.2 List of Abbreviations 7 7 8 2 9 SAFETY PHILOSOPHY 2.1 Design Criteria 9 2.2 Principles of Platform Layout 2.2.1 General 2.2.2 Utility & Accommodation Areas 2.2.3 Helideck 2.2.4 Combustion Equipment 2.2.5 Shutdown Valves 2.2.6 Hydrocarbon Pipework 2.2.7 Bridge Isolations 2.2.8 Bridge Lengths 9 9 10 10 11 11 11 11 11 2.3 11 Identification of Hazards 2.3.1 Hazard Identification 11 2.3.2 Hazard Investigation 12 2.4 Hazardous Area Classification 2.4.1 Hazardous Area 2.4.2 Non-Hazardous Area 2.5 12 12 13 Environmental Protection 13 2.5.1 Health and Safety of Personnel 13 2.5.2 Environment 14 HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 1 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 2.6 Temporary Refuge (TR) 2.6.1 Ventilation Systems 2.6.2 Fire / Gas Dampers 14 15 15 2.7 16 3 Safety Studies FIRE PROTECTION PHILOSOPHY 17 3.1 Introduction 17 3.2 Objectives 17 3.3 Background 17 3.4 Fire Zones 17 3.5 Fire Extinguishing 18 3.6 Reliability, Maintenance and Standards 3.6.1 Reliability 3.6.2 Maintenance 3.6.3 Standard of Equipment 18 18 18 18 3.7 Fire and Gas Detection System 18 3.8 Fire Water System 3.8.1 Deluge System 3.8.2 Fire Hydrant/Fire Hose Reel 3.8.3 Water/Monitor 18 19 20 20 3.9 20 Foam System 3.10 Dual Agent Skid 21 3.11 Fixed CO2 Extinguishing System 21 3.12 Fire Extinguishers 22 4 PASSIVE FIRE PROTECTION 24 4.1 Introduction 24 4.2 Firewall 24 4.3 Structural Fire Protection 24 4.4 Penetration of Firewall 24 4.5 Doors 25 HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 2 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 5 GENERAL SECTION 26 5.1 Emergency Power 5.1.1 Emergency Power Supply 5.1.2 Uninterrupted Power Supply (UPS) 26 26 26 5.2 Emergency Communications 5.2.1 Centralization 5.2.2 Platform Alarms and Public Address System 26 26 27 5.3 Safety Equipment 28 5.4 Firemen Equipment 28 5.5 Helicopter Crash Equipment 29 5.6 Personnel Safety 5.6.1 Personnel Safety Equipment 5.6.2 Medical Facilities and First Aid Equipment 5.6.3 Lifting Appliances 5.6.4 Ladders 5.6.5 Doors 5.6.6 Guardrails 5.6.7 Toeboards 5.6.8 Stairs 5.6.9 Emergency Safety Showers & Eye Baths 29 29 29 29 30 30 30 30 30 30 5.7 31 Escape Routes & Platform Evacuation 5.8 Survival Equipment 5.8.1 Lifeboat 5.8.2 Lifeboat Location 5.8.3 Liferaft 5.8.4 Lifejackets 5.8.5 Workvest 5.8.6 Lifebuoys 32 32 32 32 33 33 33 5.9 34 Safety Signs and Notices 5.10 Navigational Aids 5.10.1 Fog Signals 5.10.2 Helicopter Visual Aids 5.11 Boat Landings/Sea Access from/to Platform 34 34 34 34 HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 3 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 1 INTRODUCTION 1.1 Background This document outlines the general Health Safety and Environment Philosophy to be adopted for the detailed design of the Phase 2 and 3 of the PM-3 Development. The phase 2 and 3 developments comprise: Phase 2 Installation of a Central Processing Platform (CPP) facility at Bunga Raya (BR-A) with a bridge linked wellhead riser platform (BR-B), and a combined wellhead platform for Bunga Seroja and Northwest Raya fields (BS-A). All wellhead platforms will be tied into the CPP where the reservoir fluids will be processed to meet a sales gas export specification and a stabilised oil specification for export via shuttle tanker. Phase 3 Installation of two wellhead platforms at East Bunga Kekwa-Cai Nuoc field (BK-B and BK- C). Sales gas will be exported via subsea pipeline to Malaysia and Vietnam. Stabilised crude oil is exported via a floating storage and offloading (FSO) facility. The HSE Philosophy documented herein is applicable to the CPP, BRB (WHRP) and satellite platforms unless otherwise stated. 1.2 Purpose The purpose of this philosophy document is to enable the identification of major hazards that could lead to: 1. 2. 3. 4. Injury to personnel, Damage to facilities, Loss of production, or Pollution of the environment. Once these hazards have been identified, the HSE objectives that will be adopted in the design of the facilities will be specified. The subsequent designs shall be able to reduce the risk to an acceptable level, by minimising the likelihood of adverse incidents and ensuring that effective means are provided to minimise the consequences of adverse incidents. The development of these HSE objectives and the subsequent design shall be based upon established legislation, regulations, codes and standards and general good practice in the industry. This basic philosophy document shall be the preliminary background requirement and the approach to be followed in the development of the detailed design in accordance with good engineering practice for this new offshore installation complex. The information contained in this document is of a general nature and is to be further developed during detailed engineering phase. The scope shall generally encompass hazard identification and assessments, consideration of specific areas and technical requirements for active and passive fire protection and detection system. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 4 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 1.3 Basis of Philosophy 1.3.1 The general approach to developing the HSE Philosophy is as follows: 1. 2. 3. 4. 5. 6. Identify hazards to personnel, environment and assets Analyse the identified hazards Develop the philosophy for addressing the identified hazards Selection of a strategy to deal with the hazard Optimisation of design to minimise risks from the facilities Provision of systems to manage and control hazardous events 1.3.2 Strategies for eliminating risk Having established the various aspects that may put the personnel, the production facilities and the environment at risk, it is the objective of this HSE philosophy to identify the means, by which these aspects are to be eliminated, managed or controlled. The possible strategies to achieve this shall be: 1. 2. 3. 4. 5. 6. Loss Prevention; Fire Prevention; Fire containment and prevention of escalation; Protection of personnel; Evacuation Escape and Rescue; and Acceptance of consequential damage (Acceptability Criteria). The approach adopted for the acceptance of consequential damage and all strategies listed above shall be evaluated during the Quantative Risk Assessment (QRA) studies. Hazard quantification shall identify the size, duration, release rate and intensity of all major fire cases in the selection to generate the appropriate hazard management philosophy. Generally, industry approved, methods/software shall be used. 1.3.3 Studies to determine potential causes of failure. The potential causes of failure must be identified and the combination of design features and operational procedures put together to address each one of the failures. The causes of the failure can be identified by the Hazard Identification Study (HAZID). This shall be verified by the Hazard and Operability Study (HAZOP) during detail design. The studies shall include the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. Fire effects Impact by vessel Corrosion Environmental effects Breach of containment Overpressure Explosion Isolation failure Simultaneous production and drilling (SIPROD) Contributing elements to failure should be identified and adequate preventive measures in keeping with applicable codes and standards and normal operational procedures should be embodied in the design. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 5 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development There are some hazardous events, such as uncontrolled riser failure, with potential to overwhelm the installation should they occur. These can be classified as extreme accidental events and the design to withstand these events, including the Temporary Refuge (TR) design, may not prove cost beneficial in the balance of analysis. The aim should be to reduce the risks from these events to within acceptable limits or to levels As Low As Reasonably Practicable (ALARP). 1.3.4 Implementation of minimisation and control measures The purpose and mode of implementation of the following minimisation and control measures, developed from the design codes and other analysis techniques, shall be investigated: 1. 2. 3. 4. 1.4 Inventory minimisation Optimising the location of potential release Control of gas and liquid releases Control of fire spread Legislation, Regulations, Codes & Standards The philosophy and system design shall be in accordance with the current legislation and mandatory provisions, if any. The following sections present the documents that shall be used in the development of HSE related designs and documents for this project. 1.4.1 National Fire Protection Association Codes 1. 2. 3. 4. 5. 6. 7. 8. 1.4.2 NFPA 10 NFPA 11 NFPA 12 NFPA 13 NFPA 14 NFPA 15 NFPA 17 NFPA 20 Portable Fire Extinguishers, 1998 Low-Expansion Foam, 1998 Carbon Dioxide Extinguishing Systems, 2000 Installation of Sprinkler Systems, 1999 Installation Of Standpipes and Hose Systems Waterspray Fixed Systems 1996 Dry Chemical Extinguishing Systems 1998 Stationary fire Pumps for Fire Protection 1999 Legislation / Statutory Requirements 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Petroleum Mining Act, 1966 Occupational Safety & Health Act 1994 The Exclusive Economic Zone Act, 1984 Factories and Machinery Act 1967 (Act 139) Factories and Machinery Regulation (Fencing of Machinery and Safety) 1970 Factories and Machinery Regulations (Safety, Health & Welfare) 1970 Factories and Machinery (Steam Boiler & Unfired Pressure Vessels) Regulations, 1970 Factories and Machinery (Noise Exposure) Regulations, 1989 Atomic Energy Licensing Act, 1984 Radiation Protection (Basic Safety Standards) Regulations 1988 Radiation Protection (Licensing) Regulations 1984 Petroleum (Safety Measures) Act, 1984 Petroleum (Safety Measures) Transportation of Petroleum By Pipelines Regulations 1985. 14. Environmental Legislation’s: HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 6 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development a. b. c. d. e. f. g. h. i. j. k. l. 1.4.3 The Environmental Quality Act, 1974 The Environmental Quality (Amendment) Act, 1985 The Environmental Quality (Amendment) Act, 1998 (Act 1030) The Environmental Quality (Clean Air) Regulations, 1978 The Environmental Quality (Sewage and Industrial Effluents) Regulations, 1979 The Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order, 1987 The Environmental Quality (Scheduled Wastes) Regulations, 1989 The Environmental Quality (Prescribed Premises)(Scheduled Wastes Treatment and Disposal -Facilities) Regulations, 1989 The Environmental Quality (Licensing) Regulations, 1977 The Environmental Quality (Refrigerant Management) Regulations, 1999 The Environmental Quality (Halon Management) Regulations, 1999 The Environmental Quality Prescribed Activities (Open Burning) Order 2000 Other Relevant Statutory Requirements 1. Recommended Malaysian Air Quality Guidelines (not published) 2. Montreal Protocol 3. MARPOL 73/78 (The Convention For The Prevention of Pollution from Ships, 1973, Amended 1978) 4. Merchant Shipping Oil Pollution Act, 1994 5. Marine Water Quality Standards (Interim Guidelines) 6. Petronas Procedures for Production Operations (PPPO) 7. Helicopter Landing/Aviation authority requirements 8. Guidelines on "Radiological Monitoring For Oil & Gas Facilities Operators Associated With Technologically Enhanced Naturally Occurring Radioactive Materials (TENORM)", LEM/TEC/30 SEM.2, September 1996, Atomic Energy Licensing Board 1.4.4 Other Related Documents 1. IMO-SOLAS-1983 2. IP Part 15 3. API 500 1.5 1.5.1 Safety of Life at Sea Institute of Petroleum Model Code for Safety Area Classification American Petroleum Institute Definitions and Abbreviations Definition of Terms Company Lundin Malaysia Limited Contractor The Contractor is the party that carries out all or part of the design, engineering, procurement, purchasing, construction and commissioning for the project. Supplier The Supplier is the party that manufactures, supplies equipment and service including quality to perform the duties specified by the Contractor, or Company. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 7 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 1.5.2 List of Abbreviations AHU Air Handling Unit ALARP As Low As Reasonably Practicable API American Petroleum Institute ASHRAE American Society of Heating, Refrigeration, Air condition Engineers CP&EF Central Processing & Export Facility CPP Central Processing Platform DOE Department of Environment EERA Escape Evacuation and Rescue Analysis EIA Environmental Impact Assessment ESSA Emergency Systems Survivability Analysis FRC Fast Rescue Craft FEA Fire and Explosion Analysis HSE Health, Safety and Environment HVAC Heating, Ventilating and Air Conditioning HAZID Hazard Identification Study HAZOP Hazard and Operability Study IMO International Maritime Organisation IP Institute of Petroleum LEL Lower Explosive Limit LQ Living Quarter NFPA National Fire Prevention Association PFP Passive Fire Protection PRA Preliminary Risk Analysis QRA Quantitative Risk Analysis SDV Shutdown Valve SIA Smoke Ingress Analysis SIPROD Simultaneous Production and Drilling SOLAS Safety of Life at Sea TEMPSC Totally Enclosed Motor Propelled Safety Craft TR Temporary Refuge WHRP Wellhead & Riser Platform (BRB) HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 8 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 2 SAFETY PHILOSOPHY 2.1 Design Criteria The facilities will be designed in accordance with the safety standards required by Legislation and the As Low As Reasonably Practicable (ALARP) risk principles. A third party specialist safety contractor shall be engaged to carry out a Quantitative Risk Assessment (QRA) Study. This study shall form the basis for the Contractor to verify the principles and the design with the general objective of ensuring that the risk is reduced to satisfactory ALARP levels. Other safety aspects will be incorporated into the design as dictated by the specifications issued by COMPANY. Where no standards exist to cover a specific aspect, the standards, procedures, and normal good engineering practice shall be used. The philosophy shall assume the occurrence of only one major incident at one time on the basis that the design of the facility reduces the escalation of cascading events. 2.2 2.2.1 Principles of Platform Layout General This section covers the main features that shall be considered when laying out an installation. Careful attention to equipment location can improve the safety, access/egress and the efficient operation (operability) of the installation. Due consideration shall be given to the location of process equipment, treatment systems, utilities, the accommodation module and the helicopter landing deck, as well as escape routes, life saving appliances and safety equipment, having regard to the relevant hazards. The first approach to layout is to grade each system according to the nature of the hazard and then categorise the systems of similar grading as follows: 1. 2. 3. 4. 5. Systems which have the potential to emit flammable material Systems which may emit toxic gases Systems which are a source of ignition Systems which must be located in a safe area Systems which are considered safe Typically, sources of flammable material must be segregated from sources of ignition and accommodation areas well separated from sources of flammable gas. For this reason, a fire wall and/or a blast wall is required between the process areas and the LQ, TR and utility areas. The exact requirement to be developed during the detailed design phase in conjunction with the various studies given herein. Although leaked hydrocarbon gas would normally be rapidly dispersed by wind and buoyancy effects, for the duration of the leak gas jets/clouds within the flammable limits may form within the area of the platform. It is therefore necessary to clearly define the methodology to be used for the determination of hazard zones for major gas leaks that are likely to result in gas jets/clouds within the flammable limits. This methodology defined shall be applied through a preliminary risk analysis exercise for all piping streams and equipment containing hydrocarbon. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 9 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development A Flare Dispersion Study that examines flare flame-out conditions using the prevailing wind direction, or vent dispersion study, should be conducted for the maximum blowdown flowrate with expected process characteristic assumed. A comprehensive hazard analysis must also be carried out to determine the fire zones due to gas leaks from vessels and pipework. Such zones must be segrated by bulkheads or decks or by distance such that the heat from a fire in one zone will not propogate the emergency into another zone. The location of ESD valves to split the systems must also be considered in the design and analysis. Within fire zones, it shall be possible to suppress all ignition sources to prevent an explosion when a flammable gas cloud is drifting towards them. A blast study shall be conducted in conjunction with detailed design. Depending on the nature and location of the ignition sources, the suppression shall be: 1. Permanent, using “Ex” electrical equipment and heat generating pieces of machinery suitable for use in explosive atmosphere, 2. Automatically controlled, when gas is suspected to drift toward or is detected around the fire zone, 3. Manual locally controlled, when the available reaction time allows. 2.2.2 Utility & Accommodation Areas The design shall locate non-hazardous areas to maximise safety with regard to the prevalent wind direction. Utility areas are generally considered to be less hazardous and are to be used as a “buffer” to segregate high risk areas from the accommodations. No hydrocarbon riser pipework should run under or within a horizontal distance of 100ft of a TR/LQ, central control room, fire pump, emergency power source, radio room or other facilities essential to the safety of the installation in an emergency. If the present distance, which conforms to this requirement, is maintained, then risers will need no passive fire protection. This is to be confirmed during detailed design. 2.2.3 Helideck The location of the helideck is governed by the following criteria: 1. 2. 3. 4. 5. It must be a safe area A clear approach angle of 210o is required Structure induced turbulence should be minimised The approach/take-off sector should be into the prevailing wind Consideration should be given to the location and operability of the helideck when designing/installing equipment exhausts 6. Drain gutters shall be bunded externally to the maximum height permitted by the codes to prevent high winds carrying burning fuel of the deck 7. A safety net must be installed around the perimeter of the helideck 8. Compliance with Malaysian regulations HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 10 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 2.2.4 Combustion Equipment 2.2.5 Generally, combustion equipment and engines shall be located in non-hazardous areas. If it is not possible to locate them in safe areas, mechanically ventilated enclosures, along with fire and gas detection, are required to make the area safe. Shutdown Valves Riser/pipeline isolation valves shall be located directly below the lowest deck and, as far as possible, are to be protected against fire and mechanical risks. Mere proximity to other risers does not constitute a risk. The location of shutdown valves on the topsides process shall be optimised in order to sectionalise the process and minimise the inventory available to feed the release. 2.2.6 Hydrocarbon Pipework Live hydrocarbon pipework must be located to minimise the risk of mechanical damage by operations such as crane movement, drilling or workover. Flanges and points of potential leakage shall be minimised in general. Live hydrocarbon pipework shall be routed such that it does not pass through confined or enclosed safe areas. Where routing through and open safe area is unavoidable, live hydrocarbon pipework shall not have flanged or screwed connections that affect the areas classification. Liquid pipework shall not be routed through rooms containing electronic or electrical systems. 2.2.7 Bridge Isolations A means for isolating all hydrocarbon bridge crossings between the CPP and BRB (WHRP) is required except for vents, flares or drains. This as a minimum shall include for each line, a check valve on the receiving platform and an ESD valve on the sending platform. In case of bi-directional flow an ESD valve shall be located on each line on each platform. 2.2.8 Bridge Lengths No restrictions are made on length of the bridge between the CPP and BRB (WHRP) except as required by the safety studies. (The minimum bridge length is determined by structural considerations). 2.3 2.3.1 Identification of Hazards Hazard Identification Hazards are identified with reference to the aforementioned documents. For a particular area of the installation, the layout drawings are to define the type of equipment installed. If the area contains process or utility systems, reference to the flowsheets provides information on the nature of the hazards, e. g.: 1. Process conditions: pressure, flow, temperature 2. Composition: flammable liquid or gas HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 11 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development Further reference to the P&ID provides the location of the sources of hazards including vents, drains, flexible couplings or removable covers. In general, hydrocarbon equipment of a high inventory, high pressure or high throughput is also considered to be hazardous. 2.3.2 Hazard Investigation It is important to investigate how operations in an area may contribute to the risk. Such operations may be: 1. The crane lifting of heavy items above wellheads or process/treatment equipment. 2. The venting of large quantities of hydrocarbon gas. Gas dispersion studies shall be conducted on the vents at relevant hazard levels (LEL) to check the extent of plumage. The hazard levels to be investigated should be selected based on the Gas detection system set points. 3. For a case of simultaneous drilling or workover and production, the design shall generally incorporate precautions to be implemented for the offshore installations and the attending vessel during SIPROD. 4. Requirements for compliance with Health and Safety at Work regulations with regards to chemical products and their handling shall be identified and addressed. 5. Emergency response plans shall be developed for manned and unmanned platforms with due consideration to operations, evacuation, escape and rescue of personnel using escape routes, liferafts, lifeboats, attendant vessels or helicopter. These plans shall consider emergencies during drilling and workover activities in addition to those during normal production. The emergency plan shall be developed based on the major hazard scenarios assessed in the QRA and other safety studies. 2.4 2.4.1 Hazardous Area Classification Hazardous Area The electrical classification of areas shall be in accordance with IP 15 and applicable project electrical documents. The molecular weight of the gas is considered between 21 and 46. This is to be confirmed by the process stream data from the steady state simulation analysis. For the purpose of hazardous area determination, the gas will be considered as “heavier than air” because its density is more than 0.75 the density of air. All hazardous areas will be given a zone classification depending on the degree of hazard. The basis for area classification shall be in accordance with the definitions laid down in Hazardous Area Classification (IP 15), i.e. 1. Zone 0 2. Zone 1 3. Zone 2 a zone in which a flammable gas/air mixture is continually present. A zone in which a flammable gas/air mixture is likely to occur during normal operations. A zone in which a flammable gas/air mixture is unlikely to occur during normal operations, and would only be of a short duration. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 12 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 2.4.2 Non-Hazardous Area A non-hazardous or safe area can be defined as an area in which a flammable gas/air mixture is not normally expected to be present and which can form part of a general restricted area within the facility in which all operations (routine or unusual) are carried out. Where non-hazardous areas are located within hazardous areas, pressurisation along with airlock entrances with gas tight, self-closing doors shall be provided. Further reference to area classification should be made to Hazardous Area Classification Drawings to be prepared for this development. By design, the following areas shall be defined as “non-hazardous” either by virtue of location, ventilation or by over-pressurisation: 1. 2. 3. 4. 5. 6. 7. Living Quarters (Level 1 & 2) Control room Switchgear room Fire Pumps Emergency Generator General Utilities Battery room (special consideration shall apply owing to battery venting and possible H2 generation. Negative pressurisation shall be provided by means of exhaust ventilation). Careful consideration shall be given to the utility facilities regarding the layout. Care shall be taken to segregate hazardous from non-hazardous equipment. In hazardous areas all electrical equipment shall be certified for Gas Group IIA and temperature class T3 as a minimum. Equipment operating in confirmed classified areas shall have the necessary classification rating. 2.5 2.5.1 Environmental Protection Health and Safety of Personnel In the conduct of the Company’s activities, paramount importance is given to the health and safety of personnel and to the safeguarding of the natural environment. Health, Safety and Environmental (HSE) objectives, defined by the COMPANY, shall be implemented in all stages of the development lifecycle. The design shall uphold the HSE policy objectives in addition to other Statutory Requirements, applicable by law or good practice in Malaysia, throughout the design life. The aim shall be to identify all hazards and manage / minimise them in the most cost effective manner in line with established procedures. Relevant requirements shall be obtained from the Base EIA Study that has been developed for this project and due consideration should be given to the hazards identified by the: 1. Environmental Impact Assessment For PM-3 Development Activities, Document. No. K5877-RPT-01. 2. QRA Studies to be undertaken. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 13 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 3. Technical integrity achieved through a design based on a clear understanding of technical, operational and material needs to achieve a facility that under specified operating conditions, presents no foreseeable risk of failure endangering safety of personnel, environment or asset values. 2.5.2 Environment The environment must at all times be protected from contamination by solid, liquid and gaseous effluents. Solids containing toxic substances and non biodegradable garbage shall be taken ashore in containers. Effluent liquids containing hydrocarbons must pass through separators to remove the hydrocarbons to an acceptable level prior to discharge overboard. Liquid effluents should be checked for hydrocarbon and toxic levels. The threshold quantities for gaseous discharge, liquid effluent and solid disposal are documented in the EIA report. Care shall be taken to ensure that there is no possibility of contamination of fresh air intakes for all wind directions and speeds. Continuous venting/flaring shall be subject to the annual limits as per legislative requirements and Petronas Procedures for Production Operations (PPPO). Noise limits to be adhered to as per Malaysian/International limitation. These threshold levels are addressed in the EIA report. 2.6 Temporary Refuge (TR) A temporary refuge shall be provided on the CPP only. This section therefore refers only to the CPP. During an incident or pending their evacuation from the platform, personnel may take refuge in an area regarded as a temporary refuge. For the TR to be effective, if must be able to withstand the most severe external fire and explosion impact to which it may be reasonably expected to be exposed. The environment within the TR must be provided with life support requirements. For this complex the TR shall be segregated from other areas by mean of a H60 firewall, the effectiveness of which shall be evaluated by the QRA study. The TR shall comprise the following: 1. LQ Level 1 & 2. 2. An area of Cellar Deck that consists of Mechanical & Instrument Workshops, Control & Instrument Rooms. 3. An area of Cellar Deck that consists of MCC. & Switchgear room. The HVAC System shall provide the ventilation requirement for the TR. Individual systems are envisaged for the LQ (Level 1 & 2), Control & Instrument Rooms and Workshop areas. To limit the load on emergency power requirement, each system shall be made up of an outdoor pre-cooled air unit and main re-circulating air handling unit for space conditioning. The pressurisation fan of the Diesel generator can be kept running even though the air conditioning is shutdown due to loss of the turbine generator units. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 14 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 2.6.1 Ventilation Systems Ventilation of external process areas shall be by natural ventilation. The platform layout shall be optimised to allow maximum ventilation of process area via the prevailing winds. Ventilation systems for enclosed areas serving normally unmanned hazardous areas shall be in accordance with ASHRAE. Ventilation systems serving slight overpressure to safe enclosures or housing equipment susceptible to sparking, shall be designed to provide the following as a minimum: 1. Purging air to ensure safety of environment for equipment use. 2. Cooling for the removal of heat from equipment during operation. 3. Required overpressure of 50 Pa, which shall be maintained during a FIRE MODE. 4. Necessary fresh air requirement to maintain a reasonable working environment. Ventilation inlets and aspiration air intakes for internal combustion engines and gas turbines shall be taken from a safe area (at least 3.0 m from a hazardous area). In addition, inlet and exhaust openings shall be so segregated that cross contamination of the ventilation from other areas is prevented. The prevailing wind direction will be considered when siting gas vents, exhausts and flares. Vented gas and exhaust gas shall be so situated as to be carried away naturally downwind of the production station. The flare and venting study shall assess the dispersion of flare radiation/vent gases around the platform and the possibility for impairment of platform areas or cross contamination of inlets. An operating procedure for manual blackstart philosophy shall be prepared during detailed design. A separate ventilation and AHU system shall be provided for the TR and other safe areas on the CPP. 2.6.2 Fire / Gas Dampers Fire/gas dampers, as part of the HVAC System, shall be provided to isolate the rooms (particularly the HVAC area) in the event of gas detection and to maintain the integrity of fire walls. All fire/gas dampers shall be operated by the HVAC control panel, via the Fire and Gas System, to close automatically in the event of either gas or fire being detected. Status of dampers to be individually displayed in the Control Room next to the Fire & Gas Panel. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 15 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 2.7 Safety Studies The following minimum safety studies are to be performed and documented during detailed design: 1. Gas Dispersion Studies to determine the frequency of impairment of topside areas, if any, and the likelihood of cross contamination of air intakes. 2. Flare Dispersion & Radiation Study to determine flammable gas concentrations during flame-out conditions. 3. Noise Assessment Study to determine whether foreseeable noise levels are compliant with the applicable Occupational Health legislation. 4. Quantitative Risk Analysis to confirm the findings of the hazardous area classifications and the location of fire and gas detectors and other protective/preventive measures. 5. Hazard Identification (HAZID) at mid way stage of detailed engineering. 6. Detailed Engineering HAZOP study. 7. Quantitative Risk Analysis (QRA) to determine the risk levels on the installation; 8. Safety (HSE) Case, which shall document the safety, health and environmental evaluations and decisions, made during the project design and shall reference the philosophy, risks studies, environmental studies and all safety related documentation. 9. Exhaust and vent dispersion study 10. Blast and overpressure protection analysis 11. Acoustically induced vibration studies HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 16 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 3 FIRE PROTECTION PHILOSOPHY 3.1 Introduction This section covers the philosophy for the fire protection systems of the CPP and BRBWHRP facilities. The other satellite and BRB (WHRP) platforms are not normally manned. They are therefore designed with minimum facilities and hence do not have the fixed fire protections systems discussed below for use during normal operations. A fire water ringmain pipework is to be installed on these platforms but is for use only during simultaneous production and drilling (SIPROD) and will be fed from the drilling rig. Only the discussion of portable fire protection systems is applicable to the BRB (WHRP) and satellite platforms. 3.2 Objectives The objectives of the fire protection design are as follows: 1. To ensure that an acceptable level of safety is achieved. The protection of personnel, the installation and the environment, from fire and explosion is of primary importance. 2. To provide a basic concept on which the detailed design of the various safety systems can be based. 3. To ensure that the supply of the firefighting equipment is adequate to meet the needs of the design, and the appropriate statutory regulations. 3.3 Background Major incidents often escalate from relatively minor occurrences involving the three elements of the fire triangle, namely: 1. Fuel, 2. A source of ignition, and 3. A source of oxygen (air). Exclude any of these elements and a fire will be avoided or extinguished, however if they are all present, a fire will continue and may well escalate by involving further sources of fuel. Thus, the basic requirements of the fire and gas detection and protection system are as follows: 1. Detect this release of fuel/gas as rapidly as possible 2. Upon detection of a gas leak or fire, simultaneously: a. Isolate the source of fuel/gas b. Isolate sources of ignition c. Attempt to disperse the fuel/gas d. Apply extinguish ant (fire only) e. Protect adjacent equipment to prevent escalation of the incident f. Exclude air where possible g. If the fuel source ignites, detect the fire as quickly as possible. 3.4 Fire Zones HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 17 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development The design of the fire protection systems assumes that only one major incident occurs at any one time. To prevent incidents escalating beyond the capacity of the extinguishing systems, as far as possible installations should be segregated into fire zones protected by fire resistant bulkheads, the extremities of the platform and decks, or a combination of both. (refer to Section 2.4). 3.5 Fire Extinguishing The extinguishing medium must be suitable for the anticipated type of fire. Agents include water, foam, dry powder and CO2. The advantages and limitations of each are detailed in subsequent sections of this document. The compatibility of the various extinguishing means must be considered. 3.6 Reliability, Maintenance and Standards 3.6.1 Reliability The safety systems must have a high reliability level to ensure that they operate as intended, when required, and to avoid spurious operation and consequential disruption of production. To avoid human error, particularly during emergency situations, automatic systems should be specified wherever possible. System reliability is improved by ensuring complete autonomy, diversity, multiplicity and redundancy as appropriate. 3.6.2 Maintenance System should, where possible be self diagnostic so that the operator is immediately informed of any faults. With built-in redundancy these should not affect operation of the safety systems. Safety equipment should be readily accessible, easy to maintain and spare parts should be readily available. Standardisation of equipment will minimise the spare parts holding requirement. 3.6.3 Standard of Equipment All fire and gas detection and protection systems will be in accordance with the appropriate regulations and design codes. Equipment should be of an approved design, suitable for the environmental conditions and for the design life of the installation. 3.7 Fire and Gas Detection System The fire and gas detection system is explained in detail in the Fire & Gas System Philosophy. 3.8 Fire Water System The CPP shall be provided with fixed firewater system. Two normal operation (2 x 100 %) fire pumps (1 standby) shall supply fire water to a ring main distribution system. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 18 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development Each firewater pump shall be complete with accessories and controls as detailed in NFPA 20 and shall be fitted with a diesel oil tank of sufficient capacity to make the pump available for at least 8 hours. The proposed capacity should be confirmed during the detail design phase, with a design discharge pressure sufficient to maintain a pressure of 7 barg at the helideck monitor nozzles. The sea/service water system pumps shall be utilized to maintain the firewater ring main pressure at 10 barg. These pumps shall be of sufficient capacity to keep the ringmain pressurised when two hose stations are in use. The purpose of their usage is primarily to preclude frequent and unnecessary start up of the fire water pump engines (and consequential wear and tear). Provision for the manual selection of the duty firewater or sea/servoce water pumps shall be made in the control room. Firewater P&ID drawings shall be developed to reflect this conceptual design. Firewater pumps shall be started automatically by: Low ringmain pressure Confirmed fire detection Deluge valve discharge Also, there shall be provision to start the pumps manually from: CPP control room Local pump controller Helideck Firewater pump stop shall be manual only, local to pumps. Confirmed gas detection in a firewater pump area shall inhibit start of the pump but shall not stop the pump if it is already running. The pumps shall have an overspeed trip to protect them from the ingestion of flammable gas (rig saver). Fire detection in firewater pump area shall not stop or inhibit the pump. The firepumps start/stop and control logic shall be based on the requirement of NFPA 20 and API 610 as a minimum and shall employ line pressures in addition to local and remote means of starting. The weekly test run of the Firewater pumps (required by NFPA) will be manually started. The firewater pumps shall feed the following: Firewater deluge Hydrants and hose reels Firewater monitors The fire main network will be fully meshed and looped. Sectional isolating butterfly fire-safe valves will be provided on the ring main and shall be positioned such that a maximum of one automatic fire protection system and two hydrants may be isolated at one time. All fire protection isolating valves on firewater ring main shall be locked in their operational position; electrical supervision of their open/shut status will not be provided. Maximum water velocity in the ring main shall be limited to 3 m/s. 3.8.1 Deluge System HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 19 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development Each deluge system shall be supplied from two different parts of the network. One of the deluge valves shall be capable of being automatically actuated by fire detection. The other one shall be local and manually operated. Manual local and remote (control room) actuation shall be provided for automatic deluge valves activation. The application design densities shall, as a minimum, comply with NFPA 15 and API requirements. Valves and their control shall be located remotely from the areas protected. A feed back signal shall be sent to control room when the system actuates. Deluge isolating valves shall be normally open and locked open only. Deluge nozzles shall be provided for complete water coverage on all surfaces and shall have a water delivery pressure of 3 barg minimum. Rundown below the hemisphere shall not be considered as acceptable coverage on horizontal vessels greater than 1 m in diameter. In that case additional nozzles shall be provided below the vessel. Deluge nozzles shall not be installed higher than 3 m above the surface to be protected. 3.8.2 Fire Hydrant/Fire Hose Reel In addition to the fixed systems for fire extinguishing, a sufficient number of strategically located hydrants, hose stations and fire hose reels shall be provided. Fire hydrant/fire hose reels shall be provided in all areas except those containing only electrical equipment. Any place on the platform where a fire may occur shall be reached by at least two water jets (from two sides) from outlets of the hydrant or fire hose reels. The hydrants shall be arranged with two 2” 1/2 connections for fire hoses and equipped with on/off ball valves. The hose stations and related equipment shall be located as close to the hydrants as practically possible. In the outside areas (utility and process area) fire hydrant/hose stations with 2 @ 20 m length and 2” diameter and 2”1/2 hoses and fog/straight-jet nozzles shall be provided. Hose connections shall be of instantaneous coupling. In process ares with solid plate floors (as oppose to grating), the hose reel stations shall be dual water and AFFF type. The hose reels shall be used in confined areas (LQ). In these areas non-collapsing hose reels containing 20m of 1”1/2 diameter hoses with fog/straight jet nozzle shall be provided. Hose reels shall be capable of applying a jet or a spray pattern at a minimum of 250 litres/min for cooling purposes and shall be able to cover the whole helideck irrespective of wind direction. 3.8.3 Water/Monitor Water monitors shall be provided on the bridge between CPP and BRB (WHRP) and above the walkways and shall be capable of delivering 2000 l/m at 7 barg. 3.9 Foam System HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 20 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development Aqueous film forming foam (AFFF) capability shall be provided to enable extinction of flammable liquid spill fires, and to give foam-making capability on the helideck and in CPP process areas with solid plate decks. 3% AFFF concentrate, stored in pressure bladder tank, shall be used. The volume of the bladder tank shall be sufficient to provide foam concentrate for a minimum of five minutes for fighting spills/fires on the helideck at the delivery rates recommended by MHS. Two AFFF foam/water monitors will be provided on either side of the helideck. Each will be capable of giving minimum 50% coverage of the “prescribed area” based on an application rate of 6L/min/m2. The monitors will be designed for manual operation. They will be positioned outside of the helicopter approach and landing area (210o zone), but positioned such that an operator has a clear view of the helideck, when operating a monitor. Water for these units shall be derived from the ring mains, at a minimum design pressure of 7 barg. Proportioners shall be fitted local to pressure tank, to give the correct induced foam rate (3%). 3.10 Dual Agent Skid Dual agents (chemical powder and premix water + AFFF) fire extinguishing skid, permanently pressurised shall be provided on helideck protection on LQ. The extinguishing agents will be powered by pressurised nitrogen and from combined dry chemical foam branch pipe fitted with two independent triggers hose long enough to reach any point of the helideck. Each dual agent skid shall be provided with: Minimum 600l of AFFF solution Minimum 400 kg of dry chemical. The inventories and delivery rates of these skids must comply with the requirements of the MHS standards. 3.11 Fixed CO2 Extinguishing System CO2 fixed system shall be designed in accordance with NFPA 12. The primary use of this gaseous extinguishant is the protection of electrical equipment or items that may be damaged by the application of water. In all areas on the CPP where high inventories of electrical or electronic equipment are housed, manual extinguishing system shall be provided. Total flood CO2 fixed system with automatic activation will be installed in the turbine enclosures only. The Control and Instrument room shall only be provided with portable CO2 extinguishers since these rooms will be continuously manned. For automatic CO2 flooding, the system shall be activated by a confirmed coincidence operation of fire detectors in the protected area. Manual activation shall be achieved from the main control room, cylinder bank and from the entrances/exits of the protected area by pull handle. The CO2 cylinder bank shall be located outside the protected room. Each cylinder shall be mounted on a permanent weight system for easy knowledge and viability of each system. If HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 21 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development CO2 cylinders are located in open area, they shall be placed inside GRP cabinets for protection against environment. Status of the CO2 system should be indicated at each entrance on CO2 status panel with a pass switch and by pass alarm locally and in control room. The operation of the system shall automatically close the ventilation dampers and turn off the cooling fans of the protected area. At all entrances of the protected area, warning notices shall be posted that the area is CO2 protected, and the system may be discharged. Visual (lights) and audible (klaxon) alarms shall also be installed on the entrances to CO2 protected areas to indicate when CO2 has been released. Standardisation of CO2 cylinders and charges shall be required and spare cylinders set shall be provided to allow replacement of any set. 3.12 Fire Extinguishers The CPP and BRB (WHRP) shall be equipped with a sufficient number of suitable and appropriately located portable fire extinguishers. The extinguishers shall at any time be ready for use. The extinguishers shall be easily accessible. The number and location must be considered in each case. One extinguisher shall normally be located within a distance of 6 m. The extinguishers are to be filled with the extinguishing agent best suited for fighting the types of fire that are expected to occur in the area. Portable dry chemical extinguishers are to be the first line of defence for fighting fires, as they are satisfactory for type A, B and C fires. Only the one type of fire extinguisher shall be used for process, utility office and living quarters. This is to ensure that personnel will not be uncertain about which type to use in the case of fire. It also reduces replacement, maintenance, inspection and training requirements. 50kg wheeled extinguishers should be placed to maximise coverage with a minimum of repositioning. There should be a minimum of two in each major process area, and one in any other areas with a large amount of equipment. All corridors shall be equipped with a minimum of one hand extinguisher at each exit. Portable extinguishers shall be provided for use on small fires, the types of extinguisher should be as follows: Dry powder (9kg portable and 50kg trolley unit)) - provided in process and utility areas and at helideck CO2 (10 kg) - electrical areas HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 22 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development Dry Powder extinguishers (9 kg portable) in offices and living quarters. Fixed CO2 snuffing system in galley hood. All these extinguishers shall be specified for storage in marine atmosphere. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 23 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 4 PASSIVE FIRE PROTECTION 4.1 Introduction Structural fire protection covers the provision of firewalls and protection for primary load bearing structural members in hazard areas. Requirements for PFP shall be determined by the radiation and heat profiles obtained from the QRA studies. Structural fire protection is provided for the CPP facilities only. The satellite and BRB (WHRP) platforms are not normally manned and are therefore designed with minimum facilities and hence do not have structural fire protections systems discussed below. 4.2 Firewall The objectives of firewalls are to prevent the passage of heat, smoke, flame and gases for a sufficient period of time to: Enable the safe evacuation of personnel Provide a safe haven for personnel Ensure the operation of equipment required in an emergency The temporary refuge (TR) shall be segregated from the rest of the CPP area by a H60 rated firewall. The H class division firewalls are those divisions formed by bulkheads and decks that comply with the following: 4.3 They shall be constructed of steel or other equivalent material They shall be suitably stiffened They shall be so constructed as to be capable of preventing the passage of smoke and flame to the end of the two-hour hydrocarbon fire test. Structural Fire Protection The objective of structural fire protection, if required, is only to prevent the collapse of critical load bearing members, should they be involved in a fire situation, for a period long enough for personnel to escape. Critical load bearing structures are defined as follows: Primary steelworks in high risk areas where exposure to fire could rapidly cause collapse of the installation Secondary members in high risk areas that are exposed to fire could rapidly escalate the incident. The requirement for structural fire protection shall be evaluated and specified based on safety studies to be undertaken during detailed design. Passive fire protection is only required if studies to be performed during detailed design specify a requirement for it. 4.4 Penetration of Firewall HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 24 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development Penetration of firewalls (window, ducts, pipes, cables, etc.) shall be kept to a minimum and any openings necessary for movement of penetrating pipes etc. should be reduced to the absolute minimum required to allow the necessary movement while maintaining the stability, integrity and insulation of the firewall. The sealing system shall have been demonstrated to withstand fire tests relevant to the fire resistance rating of the wall, and sufficiently flexible to accept limited movement. 4.5 Doors All doors situated in fire rated walls shall maintain the rating of the wall of which they form part. Additionally these doors shall be furnished with automatic door closures. All rated doors shall have certifying body’s acceptance. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 25 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 5 GENERAL SECTION 5.1 Emergency Power Emergency power generation shall be in accordance with the relevant specification. The vital safety equipment such as pressurisation fans (for the HVAC system) and safety related equipment should have a back up power supply from the emergency power system during a hazardous incident. 5.1.1 Emergency Power Supply Emergency Power Supply shall be fed by a diesel generator located within a safe area on the CPP. The emergency power supply shall be separated from all potential fires by a fire wall. The day tank of diesel driven essential services generator shall have sufficient fuel to enable the generator to run on “full-load” for a period of 24 hours. 5.1.2 Uninterrupted Power Supply (UPS) Batteries shall be provided to maintain a source of power in the period between total loss of power, and the emergency/blackstart generator start-up. In case of main power total outage, and emergency supply, batteries will provide power to the following systems: ESD, Fire and Gas Detection system, for a period of 60 minutes minimum Emergency lighting fixtures with integral batteries. Alarm and public address system for a period of 60 minutes minimum Helicopter landing deck lighting for a period of 30 minutes minimum with switching on-off facility. The emergency lighting installed in the LQ/TR and the process areas shall be maintained at 50% of connected lighting load for TR and 30% for Process areas. Emergency radio equipment for a period of 8 hours minimum The batteries shall be housed in a “safe area” and separately ventilated, and bounded by blast wall. 5.2 Emergency Communications 5.2.1 Centralization of communications All emergency communication shall be centralised from the Radio Room located in the LQ or TR. All requirements shall be as per Fire and Gas System Philosophy Document, relevant system block diagrams and other relevant project documents. The Radio Room shall be fitted with gas detection equipment in addition to continuous power supply availability even in the event of power failure to the LQ or TR. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 26 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 5.2.2 Platform Alarms and Public Address System The purpose of the general alarm is to raise the alarm in every part of the platform by means of an audible, and where necessary in areas of high noise levels, visual signals, distinct from other signals or alarms on the installation so that: All personnel may be summoned to their muster areas Personnel may be warned of the occurrence of specific emergencies, and so enable immediate appropriate actions to be taken. The general alarm system should be capable of providing an audible signal, or code of signals distinct form other signals or alarms on every part of every platform forming the CPP. The resultant actions should be defined in the Emergency Procedures Manual (Contingency Plan) and on the muster list. The design objectives are as follows: To alert personnel wherever they may be To provide a simple alarm code, which is not confusing and is easily remembered. This code shall be consistent with the codes used on other platforms in Malaysian waters and globally to avoid misunderstandings. In areas of high noise level, conspicuous visual warning signals, e.g. bright, flashing coloured lights (RED) shall be provided in addition to audible signals. In addition, the audible alarm tones shall be a minimum of 5 dBa above the maximum noise in an area that last for 30 seconds. Care should be taken when positioning visual warnings signals to ensure that they are not screened or hidden from view by equipment, machinery or structures, that they are visible from all parts of the area covered and cannot be confused with any other signals such as machinery control. A public address system shall be provided to transmit clear verbal instructions to all parts of the CPP and BRB (WHRP). The public address system should be capable of permitting the clear annunciation of the verbal order to abandon in case of emergency. Emergency verbal orders so enunciated shall override any other routine use. The system should cover survival craft launching and embarkation positions, in addition to those positions where personnel are frequently present. It shall be possible to override the alarms by an emergency verbal announcement. A fault or accident to any part of the system should not render the system inoperable elsewhere. The alarm and P.A. system shall be provided with electrical power from the UPS. Alarm and Public Address system shall be located in the Telecom Equipment Room in the LQ. General Platform Alarm and Public Address (GPA/PA) System Philosophy Document addresses the general requirements. The gas/fire/general alarm of the production centre shall be operated automatically or manually form the control room. The requirements are explicit in the Fire & Gas Philosophy Document with system requirements in the Fire & Gas System Block Diagram. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 27 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 5.3 Safety Equipment The following minimum equipment shall be provided by the Contractor. The numbers of the items listed below are given for guidance only and the specific number to be installed shall be determined based on the platform manning level. Equipment Item 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 5.4 Helicopter crash kit Two helicopter fire suits etc. Knotted ropes Emergency eyewash and shower (near chemical storage) Stretcher SCBA sets and breathing air compressor 10 min ELSA sets Two hazardous area gas detectors (for five different gases) 20 personal alarms (LEL detection/CO2 gas detection) Oxy viva resuscitation kit Fully equipped medical room in accommodation for site emergencies Work vests in fibreglass box at stairs to sea deck Lifejackets for personnel transfer in fibreglass box at base of crane Personnel transfer basket for four persons Liferafts and lifebuoy Equipment Requirement and number Required (CPP) (BRB Satellite (WHRP)) Platforms (10 to 30) (10) (4) (4) (10/10) (2/2) (4) (20) (20) Fireman’s Equipment Firemen equipment (2 boxes)shall be provided shall be provided on the CPP. The exact contents of each set of equipment shall be based on the finalised manning level and platform configuration/size. As an indication, each set should include: 1. Protective suit (bunker coats) complete with boots, gloves, hood and helmet 2. A self-contained breathing apparatus 3. A portable battery operated lamp of three hours duration 4. A fireman’s axe 5. A safety harness and guidelines 6. A crowbar 7. A fire blanket 8. Spare air cylinders for breathing apparatus Equipment should be used only by personnel trained in its use. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 28 of 35 4 4 2 2 2 2 1 1 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 5.5 Helicopter Crash Equipment In the immediate vicinity of the helideck, all equipment for use in the event of an accident involving a helicopter, as specified by MHS standards, should be stored in a cabinet. The equipment should as a minimum include: 1. 2. 3. 4. 5. 6. 5.6 An aircraft type axe A large axe Hacksaw and blades Grapple hook Quick release knife Crowbar and bolt cutters Personnel Safety This section covers the general safety of personnel on offshore installations and includes such items as personal safety equipment, first aid equipment, sick bay and guarding of machinery equipment. 5.6.1 Personnel Safety Equipment Suitable safety helmets must be provided for every person on the installation. Sufficient protective clothing (eye protectors, ear defenders, welding masks and goggles, welding aprons, gloves, overalls, safety boots and shoes and breathing apparatus) must be provided for all personnel engaged in operations where they are exposed to risk of injury. All equipment provided must be kept clean and in a good state of repair and condition, and be readily available for use when required by a responsible person. 5.6.2 Medical Facilities and First Aid Equipment In the LQ, a sick bay will be provided to be used solely for the purpose of medical treatment and as a minimum shall be provided with the following, amongst others: 1. Patient alarm 2. Stretcher 3. Locked Cabinet The sick bay shall be stocked with at least one first aid kit for each medically trained person. Sufficient suitable stretchers, at least one suitable for winching a sick or injured person into a helicopter or vessel, and at least one collapsible stretcher suitable for use in a confined space shall be provided. 5.6.3 Lifting Appliances All lifting appliances and every item of lifting equipment shall be examined and tested and all items shall be legibly marked with its safe working load. Certification of all lifting appliances shall be undertaken by a third party. Machinery Guarding and Heat Insulation. All exposed moving parts on all machinery shall be suitably guarded to protect personnel from injury. Guards and safety devices provided shall be well maintained and kept in position whilst machinery is running. All exposed parts of equipment having a skin temperature above 65C shall be insulated or protected to avoid direct contact by personnel. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 29 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 5.6.4 Ladders Fixed vertical ladders shall have a breadth of at least 350mm. There shall be an unobstructed depth behind the rungs of at least 150mm. The vertical distance between the rungs shall not be less than 250mm and not more than 350 mm. The rungs shall be evenly spaced for the entire ladder. Maximum continuous ladder height shall be 9 m. Where the ladder height exceeds this, rest landings shall be placed at a maximum of 6 metre intervals. Starting at 2.5 metres from the base of the ladder, all ladders shall be provided with safety cages. The safety cage shall extend to 1 m above the top of the ladder and the distance form the rungs to the back of the cage shall be equal to 700 mm. 5.6.5 Doors Doors shall have a free width of at least 750 mm and a clear height of at least 2050 mm. Doors shall generally be orientated so that they open in the direction of escape. Doors on escape routes shall not be capable of being locked, and shall be provided with self-illuminated signs. 5.6.6 Guardrails The edge of any deck of walkway with a drop of 800 mm or more shall be provided with a fixed guardrail, which shall be at least 1 m high, stanchions should be located at maximum intervals of 1.5 m. 5.6.7 Toeboards Any elevated decks or walkways shall be provided with toeboards, the height of these shall be a minimum 100 mm. The opening between the deck/grating and the toeboard shall not exceed 15mm. Details of the toeboards shall be proposed by Contractor. 5.6.8 Stairs Stairs should be provided where there is a height change of 450mm or more. Stair edges shall have non-slip surfaces. Stairs shall be constructed as to allow the easy transit of stretchers bearing a person and shall be a minimum of 1.2m wide (same as the width of primary escape routes, see Section 5.5). 5.6.9 Emergency Safety Showers & Eye Baths In areas where personnel may come into contact with hazardous chemicals, there shall be provided safety showers integral eye baths. Such units shall be 316 stainless steel continuously pressurised with fresh water. Such units shall include a wide area filter to protect personnel’s eyes from foreign matter. Safety eye baths shall be provided in all locations where hazardous chemicals can be sprayed into the eyes of personnel. Such units shall be self contained distilled water units with 10 minutes supply duration. Eye baths shall provide full face bathing. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 30 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development Safety showers and eye baths shall: 1. Be treadle or push-plate operated 2. Be of 316 stainless steel and/or UV resistant plastic construction 3. Include in-built pressure and flow regulators. Battery rooms shall also be provided with bottle-type eye baths. 5.7 Escape Routes & Platform Evacuation In case of emergency the following shall be considered for platform evacuation: 1. Use of bridge linking CPP and BRB (WHRP) 2. Use of boat landing to the safety rescue vessel 3. Use of lifeboats/liferafts 4. Use of helicopter if feasible Means of escape shall be provided from all enclosed and regularly manned areas of the plant. A minimum of two escape routes shall be arranged from any area where a single route would be in excess of five metres (5m) long and where more than 5 people are likely to be grouped at the same time. Primary escape routes shall not be obstructed in any way, and shall be on floors of solid plate construction, and not on open grating. All electrical switchroom doors shall be equipped with emergency quick opening device (antipanic bar). Primary escape routes shall be 1.2 m wide and have clear headroom of 2.30 m. Doors on escape routes shall open in the direction of escape. External stairways of the accommodation area shall be 1.2 m wide. Other stairways to be minimum 1.0 m wide. Landings shall be 1.5 m by 2.5 m minimum, to permit the handling of stretchers. Secondary escape routes shall be considered as the means of egress from inside modules where primary routes do not exist. Secondary escape routes shall be 1.1 m wide and have clear headroom of 2.30 m. Escape routes shall be so constructed as to allow for easy transit and shall be clearly marked and identified on the deck. Rubber mats (mainly for electrical and switchgear room), non-slip plates, mesh type heat shields (reflective) and all other safety provisions normal to basic permanently manned platform requirements shall be identified and proposed for approval by the Company. All means of access and egress shall be so constructed as to allow the easy transit of a stretcher bearing personnel. All means of access and egress shall be so constructed as to allow a person wearing selfcontained breathing apparatus to pass through without hindrance. Passive and active fire protection shall be used if necessary on escape routes for the protection of personnel against heat radiation. All escape routes, lifeboat and liferaft stations and muster stations shall be adequately illuminated by battery supplied emergency lighting and clearly identified by signs. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 31 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 5.8 Survival Equipment Survival equipment shall be accordance with SOLAS and IMO requirements. During basic design the survival equipment shall be designed on maximum manning level of: 1. 46 men maximum on CPP; 2. BRB (WHRP) and satellite platforms: normally unmanned. The design shall allow for a total of 200% capacity. The exact number/capacity of survival equipment is to be based on the finalised manning levels. 5.8.1 Lifeboat The CPP, on which the LQ is situated, shall be provided with sufficient lifeboats to accommodate 200% of the total number of persons planned to be present at the same time. Lifeboats shall be davit launched, dual cabled, Totally Enclosed Motor Propelled Survival Craft (TEMPSC). The WHRP and the satellite platforms shall not be equipped with lifeboats but a minimum level of survival equipment is to be provided in line with the specifications for the CPP. In specifying survival equipment for these platforms, due consideration should be given to the presence of the operations support vessel at the satellite platforms at all times when they are manned. The TEMPSC shall be stowed on approved type davits which shall be fitted with electric winches to facilitate hoisting of the craft and located in “safe area”, i.e. located as far as possible from any hazardous area. The arrangement of the survival craft landing station and muster area shall be such that it will not interfere with the operation of other lifesaving appliances or impede in any way the prompt handling and marshalling of persons at the launching stations or embarkation points. Survival craft shall be stowed so that they can be launched safely in the shortest possible time. The survival craft shall be located so as to ensure safe launching having particular regard to the clearance from overhanging portions and side fittings of the installation below the survival craft positions. A minimum of 3ft shall be provided between the sides of the installation and davit launched survival craft when being lowered or special deflection provisions shall be made to prevent damage or snagging during raising and lowering. Provisions shall be made at the platform legs at sea level, in areas near the TEMPSC to minimise damage to it during launching. 5.8.2 Lifeboat Location 5.8.3 A minimum of 2 numbers of TEMPSC shall be provided at LQ level 1 on the CPP. The exact requirements shall be confirmed by reference to the codes and standards as well as by the QRA and other studies. Liferaft In addition to the above TEMPSC, all the CPP, BRB (WHRP) and satellite platforms shall be provided liferafts at suitable locations including at the bridge ends of the CPP and BRB (WHRP) platforms. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 32 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development All the above shall be located in a “safe area”, i.e. located as far as possible from any hazardous area. They shall be distributed having regard to the number of persons likely to be present on different areas at any time. Appliances shall be stowed in such locations as to ensure safe launching in the shortest possible time. Liferafts shall be of 12 man capacity and shall afford a secondary means of evacuating all the platforms. Liferafts shall be of the encapsulated “jettison” type (rigid container) and shall automatically inflate when launched. Liferafts and equipment shall be in accordance with SOLAS 1983. Certificate shall be provided. Embarkation into jettison type liferaft shall be by means of knotted ropes, which shall be located, adjacent to the liferafts stations. Additional lifejackets shall be provided at each lifeboat and liferaft station. 5.8.4 Lifejackets At the helicopter muster room/area, there shall be sufficient inflatable lifejackets provided, equivalent to the largest operational helicopter for this field (probably Sikorsky 61 aircraft) operating from the installation. Lifejackets shall conform to the minimum requirements of SOLAS 1983. Quantities and locations shall be determined by the POB, size and configuration of the installation and shall be further defined in the Escape Route and Life Saving Equipment drawings. In specifying the requirements for lifejackets it must be borne in mind that the normal practice in the region is for lifejackets to provided for each seat on board the helicopter. If this practice is to be adopted for the PM3 phase 2 development then no additional provision is required on the platform. 5.8.5 Workvest One GRP container with a minimum of 20 workvest shall be located close to the CPP boat landing, and one with four workvests at the head of the stairs to the boat landing of each satellite platform. The exact number of workvests to be provided shall be based on the finalised manning levels. 5.8.6 Lifebuoys Lifebuoys shall be provided around all the CPP, BRB (WHRP) and satellite platforms. Quantities and locations shall be further defined in the Escape Route and Life Saving Equipment drawings. Lifebuoys shall be located at lifeboat and liferaft stations and any other point deemed necessary where they shall be either handrail or bulkhead mounted. They shall be coloured “International Orange” and be suitably marked with the name of the installation. A length of buoyant line shall be attached to the lifebuoy and the other end securely fastened to the installation. The length of line shall be twice the distance from the mounting position to sea level at L.A.T. In addition, 25% of the lifebuoys shall be equipped with water activated lights. At strategic locations 25% of the lifebuoys shall also be equipped with smoke markers. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 33 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development 5.9 Safety Signs and Notices Graphic type signs shall be prominently displayed around the installation, identifying locations of safety, firefighting and survival equipment etc. Legends for safety signs shall be in the English and Bahasa Malaysia. All operating instructions for lifeboats, liferafts and other safety equipment signs shall be in English and Bahasa Malaysia. Mimic form of Station Bills showing locations for major items of safety equipment and escape routes shall be prominently displayed on all parts of the installation, and at each level of the LQ. On the inside of each cabin door shall be a floor plan of that level, giving the cabin occupants directions to the muster points, escape routes to be taken and the disposition of fire and safety equipment. All directional signs shall be illuminated for up to 2 hours in an emergency. Helideck markings shall be in accordance with relevant Civil Aviation Department and COMPANY Specification Civil Aviation Department / SOLAS requirements. Installation identification panels shall be positioned on two sides of the installation. The panels shall display as a minimum the registered name of the installation. The legend should be BLACK and be 1 (one) metre high on a YELLOW, retro-reflective background bearing the names PM3 BUNGA RAYA. 5.10 Navigational Aids Marine navigational aids and visual aids for helicopter operations shall be provided as per the requirement of Local and International Legislation. The marine navigational aids shall conform to the International Association of Lighthouse Authorities recommendations. Synchronised assemblies containing main white lights shall be installed on each corner of the platforms. White lights should flash, emitting the Morse code letter “U” every 15 seconds with minimum range at between 5 and 10 miles when the meteorological visibility is 10 miles. 5.10.1 Fog Signals Fog signals and fog horns shall be installed as per the general Petronas requirements and shall have as a minimum a range 2 mile. The fog warning shall form the Morse letter “U” at a cycle of 30 seconds. 5.10.2 Helicopter Visual Aids Helicopter visual aids including helideck lighting and obstruction lights shall be provided as per the Department of Civil Aviation Regulations and the requirements of International Legislation. 5.11 Boat Landings/Sea Access from/to Platform HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 34 of 35 Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3 Development Design of boat landing shall take into account the sea/weather conditions and the characteristics of the boats that will be used for personnel and the equipment transfer. HSE Philosophy Protek Engineers Sdn Bhd is a member of the JE Group Page 35 of 35