Uploaded by rafi_neerajan

348382184-Hse-Philosophy-Rev-b2-905

advertisement
LUNDIN MALAYSIA LIMITED
PROVISION OF BASIC ENGINEERING DESIGN SERVICES
FOR PHASE 2 AND PHASE 3 OF PM3 DEVELOPMENT
CONTRACT NO. : P98-016
HSE PHILOSOPHY
B2
B1
1
0
Rev.
26-Sep-00
15-Sep-00
04-Aug-00
21-Jun-00
Date
Design Basis – Final Issue
Design Basis – Final Issue
IDC
Preliminary
Description
FCM
FCM
FCM
FCM
By
TJ
TJ
NCL
NCL
Checked
Approved
Job No.
®
Engineers and Constructors
Protek Engineers Sdn Bhd
:
Client Approved
P98-016
Document No :
P2-GEN-L-PH-99-905
File name
:
HSE Philosophy
Page
:
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
CONTENTS
1
INTRODUCTION
4
1.1
Background
4
1.2
Purpose
4
1.3
Basis of Philosophy
5
1.3.1
General Approach
5
1.3.2
Strategies
5
1.3.3
Studies
5
1.3.4
Implementation
6
1.4
Legislation, Regulations, Codes & Standards
1.4.1
National Fire Protection Association Codes
1.4.2
Legislation / Statutory Requirements
1.4.3
Other Relevant Statutory Requirements
1.4.4
Other Related Documents
6
6
6
7
7
1.5
Definitions and Abbreviations
1.5.1
Definition of Terms
1.5.2
List of Abbreviations
7
7
8
2
9
SAFETY PHILOSOPHY
2.1
Design Criteria
9
2.2
Principles of Platform Layout
2.2.1
General
2.2.2
Utility & Accommodation Areas
2.2.3
Helideck
2.2.4
Combustion Equipment
2.2.5
Shutdown Valves
2.2.6
Hydrocarbon Pipework
2.2.7
Bridge Isolations
2.2.8
Bridge Lengths
9
9
10
10
11
11
11
11
11
2.3
11
Identification of Hazards
2.3.1
Hazard Identification
11
2.3.2
Hazard Investigation
12
2.4
Hazardous Area Classification
2.4.1
Hazardous Area
2.4.2
Non-Hazardous Area
2.5
12
12
13
Environmental Protection
13
2.5.1
Health and Safety of Personnel
13
2.5.2
Environment
14
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 1 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
2.6
Temporary Refuge (TR)
2.6.1
Ventilation Systems
2.6.2
Fire / Gas Dampers
14
15
15
2.7
16
3
Safety Studies
FIRE PROTECTION PHILOSOPHY
17
3.1
Introduction
17
3.2
Objectives
17
3.3
Background
17
3.4
Fire Zones
17
3.5
Fire Extinguishing
18
3.6
Reliability, Maintenance and Standards
3.6.1
Reliability
3.6.2
Maintenance
3.6.3
Standard of Equipment
18
18
18
18
3.7
Fire and Gas Detection System
18
3.8
Fire Water System
3.8.1
Deluge System
3.8.2
Fire Hydrant/Fire Hose Reel
3.8.3
Water/Monitor
18
19
20
20
3.9
20
Foam System
3.10
Dual Agent Skid
21
3.11
Fixed CO2 Extinguishing System
21
3.12
Fire Extinguishers
22
4
PASSIVE FIRE PROTECTION
24
4.1
Introduction
24
4.2
Firewall
24
4.3
Structural Fire Protection
24
4.4
Penetration of Firewall
24
4.5
Doors
25
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 2 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
5
GENERAL SECTION
26
5.1
Emergency Power
5.1.1
Emergency Power Supply
5.1.2
Uninterrupted Power Supply (UPS)
26
26
26
5.2
Emergency Communications
5.2.1
Centralization
5.2.2
Platform Alarms and Public Address System
26
26
27
5.3
Safety Equipment
28
5.4
Firemen Equipment
28
5.5
Helicopter Crash Equipment
29
5.6
Personnel Safety
5.6.1
Personnel Safety Equipment
5.6.2
Medical Facilities and First Aid Equipment
5.6.3
Lifting Appliances
5.6.4
Ladders
5.6.5
Doors
5.6.6
Guardrails
5.6.7
Toeboards
5.6.8
Stairs
5.6.9
Emergency Safety Showers & Eye Baths
29
29
29
29
30
30
30
30
30
30
5.7
31
Escape Routes & Platform Evacuation
5.8
Survival Equipment
5.8.1
Lifeboat
5.8.2
Lifeboat Location
5.8.3
Liferaft
5.8.4
Lifejackets
5.8.5
Workvest
5.8.6
Lifebuoys
32
32
32
32
33
33
33
5.9
34
Safety Signs and Notices
5.10 Navigational Aids
5.10.1 Fog Signals
5.10.2 Helicopter Visual Aids
5.11
Boat Landings/Sea Access from/to Platform
34
34
34
34
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 3 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
1
INTRODUCTION
1.1
Background
This document outlines the general Health Safety and Environment Philosophy to be adopted
for the detailed design of the Phase 2 and 3 of the PM-3 Development. The phase 2 and 3
developments comprise:
Phase 2
Installation of a Central Processing Platform (CPP) facility at Bunga Raya
(BR-A) with a bridge linked wellhead riser platform (BR-B), and a combined
wellhead platform for Bunga Seroja and Northwest Raya fields (BS-A). All
wellhead platforms will be tied into the CPP where the reservoir fluids will be
processed to meet a sales gas export specification and a stabilised oil
specification for export via shuttle tanker.
Phase 3
Installation of two wellhead platforms at East Bunga Kekwa-Cai Nuoc field
(BK-B and BK- C).
Sales gas will be exported via subsea pipeline to Malaysia and Vietnam. Stabilised crude oil
is exported via a floating storage and offloading (FSO) facility.
The HSE Philosophy documented herein is applicable to the CPP, BRB (WHRP) and satellite
platforms unless otherwise stated.
1.2
Purpose
The purpose of this philosophy document is to enable the identification of major hazards that
could lead to:
1.
2.
3.
4.
Injury to personnel,
Damage to facilities,
Loss of production, or
Pollution of the environment.
Once these hazards have been identified, the HSE objectives that will be adopted in the
design of the facilities will be specified. The subsequent designs shall be able to reduce the
risk to an acceptable level, by minimising the likelihood of adverse incidents and ensuring
that effective means are provided to minimise the consequences of adverse incidents.
The development of these HSE objectives and the subsequent design shall be based upon
established legislation, regulations, codes and standards and general good practice in the
industry.
This basic philosophy document shall be the preliminary background requirement and the
approach to be followed in the development of the detailed design in accordance with good
engineering practice for this new offshore installation complex.
The information contained in this document is of a general nature and is to be further
developed during detailed engineering phase.
The scope shall generally encompass hazard identification and assessments, consideration
of specific areas and technical requirements for active and passive fire protection and
detection system.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 4 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
1.3
Basis of Philosophy
1.3.1 The general approach to developing the HSE Philosophy is as follows:
1.
2.
3.
4.
5.
6.
Identify hazards to personnel, environment and assets
Analyse the identified hazards
Develop the philosophy for addressing the identified hazards
Selection of a strategy to deal with the hazard
Optimisation of design to minimise risks from the facilities
Provision of systems to manage and control hazardous events
1.3.2 Strategies for eliminating risk
Having established the various aspects that may put the personnel, the production
facilities and the environment at risk, it is the objective of this HSE philosophy to
identify the means, by which these aspects are to be eliminated, managed or
controlled.
The possible strategies to achieve this shall be:
1.
2.
3.
4.
5.
6.
Loss Prevention;
Fire Prevention;
Fire containment and prevention of escalation;
Protection of personnel;
Evacuation Escape and Rescue; and
Acceptance of consequential damage (Acceptability Criteria).
The approach adopted for the acceptance of consequential damage and all strategies listed
above shall be evaluated during the Quantative Risk Assessment (QRA) studies.
Hazard quantification shall identify the size, duration, release rate and intensity of all major
fire cases in the selection to generate the appropriate hazard management philosophy.
Generally, industry approved, methods/software shall be used.
1.3.3 Studies to determine potential causes of failure.
The potential causes of failure must be identified and the combination of design features
and operational procedures put together to address each one of the failures. The causes of
the failure can be identified by the Hazard Identification Study (HAZID). This shall be verified
by the Hazard and Operability Study (HAZOP) during detail design. The studies shall include
the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
Fire effects
Impact by vessel
Corrosion
Environmental effects
Breach of containment
Overpressure
Explosion
Isolation failure
Simultaneous production and drilling (SIPROD)
Contributing elements to failure should be identified and adequate preventive measures in
keeping with applicable codes and standards and normal operational procedures should be
embodied in the design.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 5 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
There are some hazardous events, such as uncontrolled riser failure, with potential to
overwhelm the installation should they occur. These can be classified as extreme accidental
events and the design to withstand these events, including the Temporary Refuge (TR)
design, may not prove cost beneficial in the balance of analysis.
The aim should be to reduce the risks from these events to within acceptable limits or to
levels As Low As Reasonably Practicable (ALARP).
1.3.4 Implementation of minimisation and control measures
The purpose and mode of implementation of the following minimisation and control
measures, developed from the design codes and other analysis techniques, shall be
investigated:
1.
2.
3.
4.
1.4
Inventory minimisation
Optimising the location of potential release
Control of gas and liquid releases
Control of fire spread
Legislation, Regulations, Codes & Standards
The philosophy and system design shall be in accordance with the current legislation and
mandatory provisions, if any.
The following sections present the documents that shall be used in the development of HSE
related designs and documents for this project.
1.4.1 National Fire Protection Association Codes
1.
2.
3.
4.
5.
6.
7.
8.
1.4.2
NFPA 10
NFPA 11
NFPA 12
NFPA 13
NFPA 14
NFPA 15
NFPA 17
NFPA 20
Portable Fire Extinguishers, 1998
Low-Expansion Foam, 1998
Carbon Dioxide Extinguishing Systems, 2000
Installation of Sprinkler Systems, 1999
Installation Of Standpipes and Hose Systems
Waterspray Fixed Systems 1996
Dry Chemical Extinguishing Systems 1998
Stationary fire Pumps for Fire Protection 1999
Legislation / Statutory Requirements
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Petroleum Mining Act, 1966
Occupational Safety & Health Act 1994
The Exclusive Economic Zone Act, 1984
Factories and Machinery Act 1967 (Act 139)
Factories and Machinery Regulation (Fencing of Machinery and Safety) 1970
Factories and Machinery Regulations (Safety, Health & Welfare) 1970
Factories and Machinery (Steam Boiler & Unfired Pressure Vessels)
Regulations, 1970
Factories and Machinery (Noise Exposure) Regulations, 1989
Atomic Energy Licensing Act, 1984
Radiation Protection (Basic Safety Standards) Regulations 1988
Radiation Protection (Licensing) Regulations 1984
Petroleum (Safety Measures) Act, 1984
Petroleum (Safety Measures) Transportation of Petroleum By Pipelines
Regulations 1985.
14. Environmental Legislation’s: HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 6 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
1.4.3
The Environmental Quality Act, 1974
The Environmental Quality (Amendment) Act, 1985
The Environmental Quality (Amendment) Act, 1998 (Act 1030)
The Environmental Quality (Clean Air) Regulations, 1978
The Environmental Quality (Sewage and Industrial Effluents) Regulations,
1979
The Environmental Quality (Prescribed Activities) (Environmental Impact
Assessment) Order, 1987
The Environmental Quality (Scheduled Wastes) Regulations, 1989
The Environmental Quality (Prescribed Premises)(Scheduled Wastes
Treatment and Disposal -Facilities) Regulations, 1989
The Environmental Quality (Licensing) Regulations, 1977
The Environmental Quality (Refrigerant Management) Regulations, 1999
The Environmental Quality (Halon Management) Regulations, 1999
The Environmental Quality Prescribed Activities (Open Burning) Order 2000
Other Relevant Statutory Requirements
1. Recommended Malaysian Air Quality Guidelines (not published)
2. Montreal Protocol
3. MARPOL 73/78 (The Convention For The Prevention of Pollution from Ships,
1973, Amended 1978)
4. Merchant Shipping Oil Pollution Act, 1994
5. Marine Water Quality Standards (Interim Guidelines)
6. Petronas Procedures for Production Operations (PPPO)
7. Helicopter Landing/Aviation authority requirements
8. Guidelines on "Radiological Monitoring For Oil & Gas Facilities Operators
Associated With Technologically Enhanced Naturally Occurring Radioactive
Materials (TENORM)", LEM/TEC/30 SEM.2, September 1996, Atomic Energy
Licensing Board
1.4.4
Other Related Documents
1. IMO-SOLAS-1983
2. IP Part 15
3. API 500
1.5
1.5.1
Safety of Life at Sea
Institute of Petroleum Model Code for Safety
Area Classification American Petroleum
Institute
Definitions and Abbreviations
Definition of Terms
Company
Lundin Malaysia Limited
Contractor
The Contractor is the party that carries out all or
part of the design, engineering, procurement,
purchasing, construction and commissioning for the
project.
Supplier
The Supplier is the party that manufactures,
supplies equipment and service including quality to
perform the duties specified by the Contractor, or
Company.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 7 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
1.5.2
List of Abbreviations
AHU
Air Handling Unit
ALARP
As Low As Reasonably Practicable
API
American Petroleum Institute
ASHRAE
American Society of Heating, Refrigeration, Air condition
Engineers
CP&EF
Central Processing & Export Facility
CPP
Central Processing Platform
DOE
Department of Environment
EERA
Escape Evacuation and Rescue Analysis
EIA
Environmental Impact Assessment
ESSA
Emergency Systems Survivability Analysis
FRC
Fast Rescue Craft
FEA
Fire and Explosion Analysis
HSE
Health, Safety and Environment
HVAC
Heating, Ventilating and Air Conditioning
HAZID
Hazard Identification Study
HAZOP
Hazard and Operability Study
IMO
International Maritime Organisation
IP
Institute of Petroleum
LEL
Lower Explosive Limit
LQ
Living Quarter
NFPA
National Fire Prevention Association
PFP
Passive Fire Protection
PRA
Preliminary Risk Analysis
QRA
Quantitative Risk Analysis
SDV
Shutdown Valve
SIA
Smoke Ingress Analysis
SIPROD
Simultaneous Production and Drilling
SOLAS
Safety of Life at Sea
TEMPSC
Totally Enclosed Motor Propelled Safety Craft
TR
Temporary Refuge
WHRP
Wellhead & Riser Platform (BRB)
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 8 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
2
SAFETY PHILOSOPHY
2.1
Design Criteria
The facilities will be designed in accordance with the safety standards required by Legislation
and the As Low As Reasonably Practicable (ALARP) risk principles. A third party specialist
safety contractor shall be engaged to carry out a Quantitative Risk Assessment (QRA) Study.
This study shall form the basis for the Contractor to verify the principles and the design with
the general objective of ensuring that the risk is reduced to satisfactory ALARP levels.
Other safety aspects will be incorporated into the design as dictated by the specifications
issued by COMPANY.
Where no standards exist to cover a specific aspect, the standards, procedures, and normal
good engineering practice shall be used.
The philosophy shall assume the occurrence of only one major incident at one time on the
basis that the design of the facility reduces the escalation of cascading events.
2.2
2.2.1
Principles of Platform Layout
General
This section covers the main features that shall be considered when laying out an
installation. Careful attention to equipment location can improve the safety,
access/egress and the efficient operation (operability) of the installation.
Due consideration shall be given to the location of process equipment, treatment
systems, utilities, the accommodation module and the helicopter landing deck, as
well as escape routes, life saving appliances and safety equipment, having regard to
the relevant hazards.
The first approach to layout is to grade each system according to the nature of the
hazard and then categorise the systems of similar grading as follows:
1.
2.
3.
4.
5.
Systems which have the potential to emit flammable material
Systems which may emit toxic gases
Systems which are a source of ignition
Systems which must be located in a safe area
Systems which are considered safe
Typically, sources of flammable material must be segregated from sources of
ignition and accommodation areas well separated from sources of flammable gas.
For this reason, a fire wall and/or a blast wall is required between the process areas
and the LQ, TR and utility areas. The exact requirement to be developed during the
detailed design phase in conjunction with the various studies given herein.
Although leaked hydrocarbon gas would normally be rapidly dispersed by wind and
buoyancy effects, for the duration of the leak gas jets/clouds within the flammable
limits may form within the area of the platform.
It is therefore necessary to clearly define the methodology to be used for the
determination of hazard zones for major gas leaks that are likely to result in gas
jets/clouds within the flammable limits. This methodology defined shall be applied
through a preliminary risk analysis exercise for all piping streams and equipment
containing hydrocarbon.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 9 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
A Flare Dispersion Study that examines flare flame-out conditions using the
prevailing wind direction, or vent dispersion study, should be conducted for the
maximum blowdown flowrate with expected process characteristic assumed.
A comprehensive hazard analysis must also be carried out to determine the fire
zones due to gas leaks from vessels and pipework. Such zones must be segrated by
bulkheads or decks or by distance such that the heat from a fire in one zone will not
propogate the emergency into another zone. The location of ESD valves to split the
systems must also be considered in the design and analysis.
Within fire zones, it shall be possible to suppress all ignition sources to prevent an
explosion when a flammable gas cloud is drifting towards them. A blast study shall
be conducted in conjunction with detailed design.
Depending on the nature and location of the ignition sources, the suppression shall
be:
1. Permanent, using “Ex” electrical equipment and heat generating pieces of
machinery suitable for use in explosive atmosphere,
2. Automatically controlled, when gas is suspected to drift toward or is detected
around the fire zone,
3. Manual locally controlled, when the available reaction time allows.
2.2.2
Utility & Accommodation Areas
The design shall locate non-hazardous areas to maximise safety with regard to the
prevalent wind direction. Utility areas are generally considered to be less hazardous
and are to be used as a “buffer” to segregate high risk areas from the
accommodations.
No hydrocarbon riser pipework should run under or within a horizontal distance of
100ft of a TR/LQ, central control room, fire pump, emergency power source, radio
room or other facilities essential to the safety of the installation in an emergency. If
the present distance, which conforms to this requirement, is maintained, then risers
will need no passive fire protection. This is to be confirmed during detailed design.
2.2.3
Helideck
The location of the helideck is governed by the following criteria:
1.
2.
3.
4.
5.
It must be a safe area
A clear approach angle of 210o is required
Structure induced turbulence should be minimised
The approach/take-off sector should be into the prevailing wind
Consideration should be given to the location and operability of the helideck
when designing/installing equipment exhausts
6. Drain gutters shall be bunded externally to the maximum height permitted by the
codes to prevent high winds carrying burning fuel of the deck
7. A safety net must be installed around the perimeter of the helideck
8. Compliance with Malaysian regulations
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 10 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
2.2.4
Combustion Equipment
2.2.5
Generally, combustion equipment and engines shall be located in non-hazardous
areas. If it is not possible to locate them in safe areas, mechanically ventilated
enclosures, along with fire and gas detection, are required to make the area safe.
Shutdown Valves
Riser/pipeline isolation valves shall be located directly below the lowest deck and, as
far as possible, are to be protected against fire and mechanical risks. Mere proximity
to other risers does not constitute a risk.
The location of shutdown valves on the topsides process shall be optimised in order
to sectionalise the process and minimise the inventory available to feed the release.
2.2.6
Hydrocarbon Pipework
Live hydrocarbon pipework must be located to minimise the risk of mechanical
damage by operations such as crane movement, drilling or workover. Flanges and
points of potential leakage shall be minimised in general.
Live hydrocarbon pipework shall be routed such that it does not pass through
confined or enclosed safe areas. Where routing through and open safe area is
unavoidable, live hydrocarbon pipework shall not have flanged or screwed
connections that affect the areas classification.
Liquid pipework shall not be routed through rooms containing electronic or electrical
systems.
2.2.7
Bridge Isolations
A means for isolating all hydrocarbon bridge crossings between the CPP and BRB
(WHRP) is required except for vents, flares or drains. This as a minimum shall
include for each line, a check valve on the receiving platform and an ESD valve on
the sending platform. In case of bi-directional flow an ESD valve shall be located on
each line on each platform.
2.2.8
Bridge Lengths
No restrictions are made on length of the bridge between the CPP and BRB (WHRP)
except as required by the safety studies. (The minimum bridge length is determined
by structural considerations).
2.3
2.3.1
Identification of Hazards
Hazard Identification
Hazards are identified with reference to the aforementioned documents. For a particular area
of the installation, the layout drawings are to define the type of equipment installed.
If the area contains process or utility systems, reference to the flowsheets provides
information on the nature of the hazards, e. g.:
1. Process conditions: pressure, flow, temperature
2. Composition:
flammable liquid or gas
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 11 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
Further reference to the P&ID provides the location of the sources of hazards including
vents, drains, flexible couplings or removable covers. In general, hydrocarbon equipment of
a high inventory, high pressure or high throughput is also considered to be hazardous.
2.3.2
Hazard Investigation
It is important to investigate how operations in an area may contribute to the risk. Such
operations may be:
1. The crane lifting of heavy items above wellheads or process/treatment equipment.
2. The venting of large quantities of hydrocarbon gas. Gas dispersion studies shall be
conducted on the vents at relevant hazard levels (LEL) to check the extent of
plumage. The hazard levels to be investigated should be selected based on the Gas
detection system set points.
3. For a case of simultaneous drilling or workover and production, the design shall
generally incorporate precautions to be implemented for the offshore installations
and the attending vessel during SIPROD.
4. Requirements for compliance with Health and Safety at Work regulations with
regards to chemical products and their handling shall be identified and addressed.
5. Emergency response plans shall be developed for manned and unmanned platforms
with due consideration to operations, evacuation, escape and rescue of personnel
using escape routes, liferafts, lifeboats, attendant vessels or helicopter. These plans
shall consider emergencies during drilling and workover activities in addition to those
during normal production. The emergency plan shall be developed based on the
major hazard scenarios assessed in the QRA and other safety studies.
2.4
2.4.1
Hazardous Area Classification
Hazardous Area
The electrical classification of areas shall be in accordance with IP 15 and applicable project
electrical documents. The molecular weight of the gas is considered between 21 and 46.
This is to be confirmed by the process stream data from the steady state simulation analysis.
For the purpose of hazardous area determination, the gas will be considered as “heavier
than air” because its density is more than 0.75 the density of air.
All hazardous areas will be given a zone classification depending on the degree of hazard.
The basis for area classification shall be in accordance with the definitions laid down in
Hazardous Area Classification (IP 15), i.e.
1. Zone 0
2. Zone 1
3. Zone 2
a zone in which a flammable gas/air mixture is continually present.
A zone in which a flammable gas/air mixture is likely to occur during normal
operations.
A zone in which a flammable gas/air mixture is unlikely to occur during
normal operations, and would only be of a short duration.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 12 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
2.4.2
Non-Hazardous Area
A non-hazardous or safe area can be defined as an area in which a flammable gas/air
mixture is not normally expected to be present and which can form part of a general
restricted area within the facility in which all operations (routine or unusual) are carried out.
Where non-hazardous areas are located within hazardous areas, pressurisation along with
airlock entrances with gas tight, self-closing doors shall be provided.
Further reference to area classification should be made to Hazardous Area Classification
Drawings to be prepared for this development.
By design, the following areas shall be defined as “non-hazardous” either by virtue of
location, ventilation or by over-pressurisation:
1.
2.
3.
4.
5.
6.
7.
Living Quarters (Level 1 & 2)
Control room
Switchgear room
Fire Pumps
Emergency Generator
General Utilities
Battery room (special consideration shall apply owing to battery venting and
possible H2 generation. Negative pressurisation shall be provided by means of
exhaust ventilation).
Careful consideration shall be given to the utility facilities regarding the layout. Care shall
be taken to segregate hazardous from non-hazardous equipment.
In hazardous areas all electrical equipment shall be certified for Gas Group IIA and
temperature class T3 as a minimum. Equipment operating in confirmed classified areas
shall have the necessary classification rating.
2.5
2.5.1
Environmental Protection
Health and Safety of Personnel
In the conduct of the Company’s activities, paramount importance is given to the health and
safety of personnel and to the safeguarding of the natural environment. Health, Safety and
Environmental (HSE) objectives, defined by the COMPANY, shall be implemented in all
stages of the development lifecycle.
The design shall uphold the HSE policy objectives in addition to other Statutory
Requirements, applicable by law or good practice in Malaysia, throughout the design life.
The aim shall be to identify all hazards and manage / minimise them in the most cost
effective manner in line with established procedures.
Relevant requirements shall be obtained from the Base EIA Study that has been developed
for this project and due consideration should be given to the hazards identified by the:
1. Environmental Impact Assessment For PM-3 Development Activities, Document. No.
K5877-RPT-01.
2. QRA Studies to be undertaken.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 13 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
3. Technical integrity achieved through a design based on a clear understanding of
technical, operational and material needs to achieve a facility that under specified
operating conditions, presents no foreseeable risk of failure endangering safety of
personnel, environment or asset values.
2.5.2
Environment
The environment must at all times be protected from contamination by solid, liquid and
gaseous effluents. Solids containing toxic substances and non biodegradable garbage shall
be taken ashore in containers. Effluent liquids containing hydrocarbons must pass through
separators to remove the hydrocarbons to an acceptable level prior to discharge overboard.
Liquid effluents should be checked for hydrocarbon and toxic levels. The threshold quantities
for gaseous discharge, liquid effluent and solid disposal are documented in the EIA report.
Care shall be taken to ensure that there is no possibility of contamination of fresh air intakes
for all wind directions and speeds.
Continuous venting/flaring shall be subject to the annual limits as per legislative requirements
and Petronas Procedures for Production Operations (PPPO). Noise limits to be adhered to
as per Malaysian/International limitation. These threshold levels are addressed in the EIA
report.
2.6
Temporary Refuge (TR)
A temporary refuge shall be provided on the CPP only. This section therefore refers only to
the CPP.
During an incident or pending their evacuation from the platform, personnel may take refuge
in an area regarded as a temporary refuge. For the TR to be effective, if must be able to
withstand the most severe external fire and explosion impact to which it may be reasonably
expected to be exposed. The environment within the TR must be provided with life support
requirements.
For this complex the TR shall be segregated from other areas by mean of a H60 firewall, the
effectiveness of which shall be evaluated by the QRA study. The TR shall comprise the
following:
1. LQ Level 1 & 2.
2. An area of Cellar Deck that consists of Mechanical & Instrument Workshops, Control &
Instrument Rooms.
3. An area of Cellar Deck that consists of MCC. & Switchgear room.
The HVAC System shall provide the ventilation requirement for the TR. Individual systems
are envisaged for the LQ (Level 1 & 2), Control & Instrument Rooms and Workshop areas.
To limit the load on emergency power requirement, each system shall be made up of an
outdoor pre-cooled air unit and main re-circulating air handling unit for space conditioning.
The pressurisation fan of the Diesel generator can be kept running even though the air
conditioning is shutdown due to loss of the turbine generator units.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 14 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
2.6.1
Ventilation Systems
Ventilation of external process areas shall be by natural ventilation. The platform
layout shall be optimised to allow maximum ventilation of process area via the
prevailing winds.
Ventilation systems for enclosed areas serving normally unmanned hazardous areas
shall be in accordance with ASHRAE.
Ventilation systems serving slight overpressure to safe enclosures or housing
equipment susceptible to sparking, shall be designed to provide the following as a
minimum:
1. Purging air to ensure safety of environment for equipment use.
2. Cooling for the removal of heat from equipment during operation.
3. Required overpressure of 50 Pa, which shall be maintained during a FIRE
MODE.
4. Necessary fresh air requirement to maintain a reasonable working environment.
Ventilation inlets and aspiration air intakes for internal combustion engines and gas
turbines shall be taken from a safe area (at least 3.0 m from a hazardous area).
In addition, inlet and exhaust openings shall be so segregated that cross
contamination of the ventilation from other areas is prevented.
The prevailing wind direction will be considered when siting gas vents, exhausts and
flares. Vented gas and exhaust gas shall be so situated as to be carried away
naturally downwind of the production station.
The flare and venting study shall assess the dispersion of flare radiation/vent gases
around the platform and the possibility for impairment of platform areas or cross
contamination of inlets.
An operating procedure for manual blackstart philosophy shall be prepared during
detailed design.
A separate ventilation and AHU system shall be provided for the TR and other safe
areas on the CPP.
2.6.2
Fire / Gas Dampers
Fire/gas dampers, as part of the HVAC System, shall be provided to isolate the
rooms (particularly the HVAC area) in the event of gas detection and to maintain the
integrity of fire walls.
All fire/gas dampers shall be operated by the HVAC control panel, via the Fire and
Gas System, to close automatically in the event of either gas or fire being detected.
Status of dampers to be individually displayed in the Control Room next to the Fire &
Gas Panel.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 15 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
2.7
Safety Studies
The following minimum safety studies are to be performed and documented during detailed
design:
1. Gas Dispersion Studies to determine the frequency of impairment of topside areas, if
any, and the likelihood of cross contamination of air intakes.
2. Flare Dispersion & Radiation Study to determine flammable gas concentrations during
flame-out conditions.
3. Noise Assessment Study to determine whether foreseeable noise levels are compliant
with the applicable Occupational Health legislation.
4. Quantitative Risk Analysis to confirm the findings of the hazardous area classifications
and the location of fire and gas detectors and other protective/preventive measures.
5. Hazard Identification (HAZID) at mid way stage of detailed engineering.
6. Detailed Engineering HAZOP study.
7. Quantitative Risk Analysis (QRA) to determine the risk levels on the installation;
8. Safety (HSE) Case, which shall document the safety, health and environmental
evaluations and decisions, made during the project design and shall reference the
philosophy, risks studies, environmental studies and all safety related documentation.
9. Exhaust and vent dispersion study
10. Blast and overpressure protection analysis
11. Acoustically induced vibration studies
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 16 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
3
FIRE PROTECTION PHILOSOPHY
3.1
Introduction
This section covers the philosophy for the fire protection systems of the CPP and BRBWHRP facilities.
The other satellite and BRB (WHRP) platforms are not normally manned. They are therefore
designed with minimum facilities and hence do not have the fixed fire protections systems
discussed below for use during normal operations. A fire water ringmain pipework is to be
installed on these platforms but is for use only during simultaneous production and drilling
(SIPROD) and will be fed from the drilling rig.
Only the discussion of portable fire protection systems is applicable to the BRB (WHRP) and
satellite platforms.
3.2
Objectives
The objectives of the fire protection design are as follows:
1. To ensure that an acceptable level of safety is achieved. The protection of personnel,
the installation and the environment, from fire and explosion is of primary importance.
2. To provide a basic concept on which the detailed design of the various safety systems
can be based.
3. To ensure that the supply of the firefighting equipment is adequate to meet the needs of
the design, and the appropriate statutory regulations.
3.3
Background
Major incidents often escalate from relatively minor occurrences involving the three elements
of the fire triangle, namely:
1. Fuel,
2. A source of ignition, and
3. A source of oxygen (air).
Exclude any of these elements and a fire will be avoided or extinguished, however if they are
all present, a fire will continue and may well escalate by involving further sources of fuel.
Thus, the basic requirements of the fire and gas detection and protection system are as
follows:
1. Detect this release of fuel/gas as rapidly as possible
2. Upon detection of a gas leak or fire, simultaneously:
a. Isolate the source of fuel/gas
b. Isolate sources of ignition
c. Attempt to disperse the fuel/gas
d. Apply extinguish ant (fire only)
e. Protect adjacent equipment to prevent escalation of the incident
f. Exclude air where possible
g. If the fuel source ignites, detect the fire as quickly as possible.
3.4
Fire Zones
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 17 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
The design of the fire protection systems assumes that only one major incident occurs at any
one time. To prevent incidents escalating beyond the capacity of the extinguishing systems,
as far as possible installations should be segregated into fire zones protected by fire resistant
bulkheads, the extremities of the platform and decks, or a combination of both. (refer to
Section 2.4).
3.5
Fire Extinguishing
The extinguishing medium must be suitable for the anticipated type of fire. Agents include
water, foam, dry powder and CO2. The advantages and limitations of each are detailed in
subsequent sections of this document. The compatibility of the various extinguishing means
must be considered.
3.6
Reliability, Maintenance and Standards
3.6.1
Reliability
The safety systems must have a high reliability level to ensure that they operate as
intended, when required, and to avoid spurious operation and consequential
disruption of production. To avoid human error, particularly during emergency
situations, automatic systems should be specified wherever possible. System
reliability is improved by ensuring complete autonomy, diversity, multiplicity and
redundancy as appropriate.
3.6.2
Maintenance
System should, where possible be self diagnostic so that the operator is immediately
informed of any faults. With built-in redundancy these should not affect operation of
the safety systems. Safety equipment should be readily accessible, easy to maintain
and spare parts should be readily available. Standardisation of equipment will
minimise the spare parts holding requirement.
3.6.3
Standard of Equipment
All fire and gas detection and protection systems will be in accordance with the
appropriate regulations and design codes. Equipment should be of an approved
design, suitable for the environmental conditions and for the design life of the
installation.
3.7
Fire and Gas Detection System
The fire and gas detection system is explained in detail in the Fire & Gas System Philosophy.
3.8
Fire Water System
The CPP shall be provided with fixed firewater system. Two normal operation (2 x 100 %)
fire pumps (1 standby) shall supply fire water to a ring main distribution system.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 18 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
Each firewater pump shall be complete with accessories and controls as detailed in NFPA 20
and shall be fitted with a diesel oil tank of sufficient capacity to make the pump available for
at least 8 hours. The proposed capacity should be confirmed during the detail design phase,
with a design discharge pressure sufficient to maintain a pressure of 7 barg at the helideck
monitor nozzles.
The sea/service water system pumps shall be utilized to maintain the firewater ring main
pressure at 10 barg. These pumps shall be of sufficient capacity to keep the ringmain
pressurised when two hose stations are in use. The purpose of their usage is primarily to
preclude frequent and unnecessary start up of the fire water pump engines (and
consequential wear and tear).
Provision for the manual selection of the duty firewater or sea/servoce water pumps shall be
made in the control room. Firewater P&ID drawings shall be developed to reflect this
conceptual design.
Firewater pumps shall be started automatically by:



Low ringmain pressure
Confirmed fire detection
Deluge valve discharge
Also, there shall be provision to start the pumps manually from:



CPP control room
Local pump controller
Helideck
Firewater pump stop shall be manual only, local to pumps. Confirmed gas detection in a
firewater pump area shall inhibit start of the pump but shall not stop the pump if it is already
running. The pumps shall have an overspeed trip to protect them from the ingestion of
flammable gas (rig saver). Fire detection in firewater pump area shall not stop or inhibit the
pump.
The firepumps start/stop and control logic shall be based on the requirement of NFPA 20 and
API 610 as a minimum and shall employ line pressures in addition to local and remote
means of starting.
The weekly test run of the Firewater pumps (required by NFPA) will be manually started.
The firewater pumps shall feed the following:



Firewater deluge
Hydrants and hose reels
Firewater monitors
The fire main network will be fully meshed and looped. Sectional isolating butterfly fire-safe
valves will be provided on the ring main and shall be positioned such that a maximum of one
automatic fire protection system and two hydrants may be isolated at one time.
All fire protection isolating valves on firewater ring main shall be locked in their operational
position; electrical supervision of their open/shut status will not be provided.
Maximum water velocity in the ring main shall be limited to 3 m/s.
3.8.1
Deluge System
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 19 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
Each deluge system shall be supplied from two different parts of the network. One
of the deluge valves shall be capable of being automatically actuated by fire
detection. The other one shall be local and manually operated. Manual local and
remote (control room) actuation shall be provided for automatic deluge valves
activation. The application design densities shall, as a minimum, comply with NFPA
15 and API requirements.
Valves and their control shall be located remotely from the areas protected.
A feed back signal shall be sent to control room when the system actuates.
Deluge isolating valves shall be normally open and locked open only.
Deluge nozzles shall be provided for complete water coverage on all surfaces and
shall have a water delivery pressure of 3 barg minimum. Rundown below the
hemisphere shall not be considered as acceptable coverage on horizontal vessels
greater than 1 m in diameter. In that case additional nozzles shall be provided below
the vessel.
Deluge nozzles shall not be installed higher than 3 m above the surface to be
protected.
3.8.2
Fire Hydrant/Fire Hose Reel
In addition to the fixed systems for fire extinguishing, a sufficient number of
strategically located hydrants, hose stations and fire hose reels shall be provided.
Fire hydrant/fire hose reels shall be provided in all areas except those containing
only electrical equipment.
Any place on the platform where a fire may occur shall be reached by at least two
water jets (from two sides) from outlets of the hydrant or fire hose reels.
The hydrants shall be arranged with two 2” 1/2 connections for fire hoses and
equipped with on/off ball valves.
The hose stations and related equipment shall be located as close to the hydrants as
practically possible.
In the outside areas (utility and process area) fire hydrant/hose stations with 2 @ 20
m length and 2” diameter and 2”1/2 hoses and fog/straight-jet nozzles shall be
provided. Hose connections shall be of instantaneous coupling. In process ares
with solid plate floors (as oppose to grating), the hose reel stations shall be dual
water and AFFF type.
The hose reels shall be used in confined areas (LQ). In these areas non-collapsing
hose reels containing 20m of 1”1/2 diameter hoses with fog/straight jet nozzle shall
be provided.
Hose reels shall be capable of applying a jet or a spray pattern at a minimum of 250
litres/min for cooling purposes and shall be able to cover the whole helideck
irrespective of wind direction.
3.8.3
Water/Monitor
Water monitors shall be provided on the bridge between CPP and BRB (WHRP) and
above the walkways and shall be capable of delivering 2000 l/m at 7 barg.
3.9
Foam System
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 20 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
Aqueous film forming foam (AFFF) capability shall be provided to enable extinction of
flammable liquid spill fires, and to give foam-making capability on the helideck and in CPP
process areas with solid plate decks.
3% AFFF concentrate, stored in pressure bladder tank, shall be used. The volume of the
bladder tank shall be sufficient to provide foam concentrate for a minimum of five minutes for
fighting spills/fires on the helideck at the delivery rates recommended by MHS.
Two AFFF foam/water monitors will be provided on either side of the helideck. Each will be
capable of giving minimum 50% coverage of the “prescribed area” based on an application
rate of 6L/min/m2.
The monitors will be designed for manual operation. They will be positioned outside of the
helicopter approach and landing area (210o zone), but positioned such that an operator has a
clear view of the helideck, when operating a monitor.
Water for these units shall be derived from the ring mains, at a minimum design pressure of
7 barg. Proportioners shall be fitted local to pressure tank, to give the correct induced foam
rate (3%).
3.10
Dual Agent Skid
Dual agents (chemical powder and premix water + AFFF) fire extinguishing skid,
permanently pressurised shall be provided on helideck protection on LQ. The extinguishing
agents will be powered by pressurised nitrogen and from combined dry chemical foam
branch pipe fitted with two independent triggers hose long enough to reach any point of the
helideck.
Each dual agent skid shall be provided with:
 Minimum 600l of AFFF solution
 Minimum 400 kg of dry chemical.
The inventories and delivery rates of these skids must comply with the requirements of the
MHS standards.
3.11
Fixed CO2 Extinguishing System
CO2 fixed system shall be designed in accordance with NFPA 12.
The primary use of this gaseous extinguishant is the protection of electrical equipment or
items that may be damaged by the application of water.
In all areas on the CPP where high inventories of electrical or electronic equipment are
housed, manual extinguishing system shall be provided.
Total flood CO2 fixed system with automatic activation will be installed in the turbine
enclosures only.
The Control and Instrument room shall only be provided with portable CO2 extinguishers
since these rooms will be continuously manned.
For automatic CO2 flooding, the system shall be activated by a confirmed coincidence
operation of fire detectors in the protected area. Manual activation shall be achieved from
the main control room, cylinder bank and from the entrances/exits of the protected area by
pull handle.
The CO2 cylinder bank shall be located outside the protected room. Each cylinder shall be
mounted on a permanent weight system for easy knowledge and viability of each system. If
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 21 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
CO2 cylinders are located in open area, they shall be placed inside GRP cabinets for
protection against environment.
Status of the CO2 system should be indicated at each entrance on CO2 status panel with a
pass switch and by pass alarm locally and in control room.
The operation of the system shall automatically close the ventilation dampers and turn off the
cooling fans of the protected area.
At all entrances of the protected area, warning notices shall be posted that the area is CO2
protected, and the system may be discharged. Visual (lights) and audible (klaxon) alarms
shall also be installed on the entrances to CO2 protected areas to indicate when CO2 has
been released.
Standardisation of CO2 cylinders and charges shall be required and spare cylinders set shall
be provided to allow replacement of any set.
3.12
Fire Extinguishers
The CPP and BRB (WHRP) shall be equipped with a sufficient number of suitable and
appropriately located portable fire extinguishers. The extinguishers shall at any time be
ready for use.
The extinguishers shall be easily accessible. The number and location must be considered
in each case. One extinguisher shall normally be located within a distance of 6 m.
The extinguishers are to be filled with the extinguishing agent best suited for fighting the
types of fire that are expected to occur in the area.
Portable dry chemical extinguishers are to be the first line of defence for fighting fires, as
they are satisfactory for type A, B and C fires. Only the one type of fire extinguisher shall be
used for process, utility office and living quarters. This is to ensure that personnel will not be
uncertain about which type to use in the case of fire. It also reduces replacement,
maintenance, inspection and training requirements.
50kg wheeled extinguishers should be placed to maximise coverage with a minimum of
repositioning. There should be a minimum of two in each major process area, and one in
any other areas with a large amount of equipment.
All corridors shall be equipped with a minimum of one hand extinguisher at each exit.
Portable extinguishers shall be provided for use on small fires, the types of extinguisher
should be as follows:


Dry powder (9kg portable and 50kg trolley unit)) - provided in process and utility areas
and at helideck
CO2 (10 kg) - electrical areas
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 22 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development


Dry Powder extinguishers (9 kg portable) in offices and living quarters.
Fixed CO2 snuffing system in galley hood.
All these extinguishers shall be specified for storage in marine atmosphere.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 23 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
4
PASSIVE FIRE PROTECTION
4.1
Introduction
Structural fire protection covers the provision of firewalls and protection for primary load
bearing structural members in hazard areas. Requirements for PFP shall be determined by
the radiation and heat profiles obtained from the QRA studies.
Structural fire protection is provided for the CPP facilities only. The satellite and BRB
(WHRP) platforms are not normally manned and are therefore designed with minimum
facilities and hence do not have structural fire protections systems discussed below.
4.2
Firewall
The objectives of firewalls are to prevent the passage of heat, smoke, flame and gases for a
sufficient period of time to: 


Enable the safe evacuation of personnel
Provide a safe haven for personnel
Ensure the operation of equipment required in an emergency
The temporary refuge (TR) shall be segregated from the rest of the CPP area by a H60 rated
firewall. The H class division firewalls are those divisions formed by bulkheads and decks
that comply with the following: 


4.3
They shall be constructed of steel or other equivalent material
They shall be suitably stiffened
They shall be so constructed as to be capable of preventing the passage of smoke and
flame to the end of the two-hour hydrocarbon fire test.
Structural Fire Protection
The objective of structural fire protection, if required, is only to prevent the collapse of critical
load bearing members, should they be involved in a fire situation, for a period long enough
for personnel to escape.
Critical load bearing structures are defined as follows: 

Primary steelworks in high risk areas where exposure to fire could rapidly cause collapse
of the installation
Secondary members in high risk areas that are exposed to fire could rapidly escalate the
incident.
The requirement for structural fire protection shall be evaluated and specified based on
safety studies to be undertaken during detailed design. Passive fire protection is only
required if studies to be performed during detailed design specify a requirement for it.
4.4
Penetration of Firewall
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 24 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
Penetration of firewalls (window, ducts, pipes, cables, etc.) shall be kept to a minimum and
any openings necessary for movement of penetrating pipes etc. should be reduced to the
absolute minimum required to allow the necessary movement while maintaining the stability,
integrity and insulation of the firewall. The sealing system shall have been demonstrated to
withstand fire tests relevant to the fire resistance rating of the wall, and sufficiently flexible to
accept limited movement.
4.5
Doors
All doors situated in fire rated walls shall maintain the rating of the wall of which they form
part. Additionally these doors shall be furnished with automatic door closures. All rated doors
shall have certifying body’s acceptance.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 25 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
5
GENERAL SECTION
5.1
Emergency Power
Emergency power generation shall be in accordance with the relevant specification. The vital
safety equipment such as pressurisation fans (for the HVAC system) and safety related
equipment should have a back up power supply from the emergency power system during a
hazardous incident.
5.1.1
Emergency Power Supply
Emergency Power Supply shall be fed by a diesel generator located within a safe
area on the CPP. The emergency power supply shall be separated from all potential
fires by a fire wall.
The day tank of diesel driven essential services generator shall have sufficient fuel to
enable the generator to run on “full-load” for a period of 24 hours.
5.1.2
Uninterrupted Power Supply (UPS)
Batteries shall be provided to maintain a source of power in the period between total
loss of power, and the emergency/blackstart generator start-up.
In case of main power total outage, and emergency supply, batteries will provide
power to the following systems:






ESD, Fire and Gas Detection system, for a period of 60 minutes minimum
Emergency lighting fixtures with integral batteries.
Alarm and public address system for a period of 60 minutes minimum
Helicopter landing deck lighting for a period of 30 minutes minimum with
switching on-off facility.
The emergency lighting installed in the LQ/TR and the process areas shall be
maintained at 50% of connected lighting load for TR and 30% for Process areas.
Emergency radio equipment for a period of 8 hours minimum
The batteries shall be housed in a “safe area” and separately ventilated, and
bounded by blast wall.
5.2
Emergency Communications
5.2.1
Centralization of communications
All emergency communication shall be centralised from the Radio Room located in the LQ or
TR. All requirements shall be as per Fire and Gas System Philosophy Document, relevant
system block diagrams and other relevant project documents. The Radio Room shall be
fitted with gas detection equipment in addition to continuous power supply availability even in
the event of power failure to the LQ or TR.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 26 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
5.2.2
Platform Alarms and Public Address System
The purpose of the general alarm is to raise the alarm in every part of the platform
by means of an audible, and where necessary in areas of high noise levels, visual
signals, distinct from other signals or alarms on the installation so that:


All personnel may be summoned to their muster areas
Personnel may be warned of the occurrence of specific emergencies, and so
enable immediate appropriate actions to be taken.
The general alarm system should be capable of providing an audible signal, or code
of signals distinct form other signals or alarms on every part of every platform
forming the CPP.
The resultant actions should be defined in the Emergency Procedures Manual
(Contingency Plan) and on the muster list. The design objectives are as follows:


To alert personnel wherever they may be
To provide a simple alarm code, which is not confusing and is easily
remembered. This code shall be consistent with the codes used on other
platforms in Malaysian waters and globally to avoid misunderstandings.
In areas of high noise level, conspicuous visual warning signals, e.g. bright, flashing
coloured lights (RED) shall be provided in addition to audible signals. In addition, the
audible alarm tones shall be a minimum of 5 dBa above the maximum noise in an
area that last for 30 seconds.
Care should be taken when positioning visual warnings signals to ensure that they
are not screened or hidden from view by equipment, machinery or structures, that
they are visible from all parts of the area covered and cannot be confused with any
other signals such as machinery control.
A public address system shall be provided to transmit clear verbal instructions to all
parts of the CPP and BRB (WHRP).
The public address system should be capable of permitting the clear annunciation of
the verbal order to abandon in case of emergency. Emergency verbal orders so
enunciated shall override any other routine use. The system should cover survival
craft launching and embarkation positions, in addition to those positions where
personnel are frequently present.
It shall be possible to override the alarms by an emergency verbal announcement.
A fault or accident to any part of the system should not render the system inoperable
elsewhere.
The alarm and P.A. system shall be provided with electrical power from the UPS.
Alarm and Public Address system shall be located in the Telecom Equipment Room
in the LQ. General Platform Alarm and Public Address (GPA/PA) System
Philosophy Document addresses the general requirements.
The gas/fire/general alarm of the production centre shall be operated automatically
or manually form the control room.
The requirements are explicit in the Fire & Gas Philosophy Document with system
requirements in the Fire & Gas System Block Diagram.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 27 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
5.3
Safety Equipment
The following minimum equipment shall be provided by the Contractor. The numbers of the
items listed below are given for guidance only and the specific number to be installed shall be
determined based on the platform manning level.
Equipment Item
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
5.4
Helicopter crash kit
Two helicopter fire suits etc.
Knotted ropes
Emergency eyewash and shower (near
chemical storage)
Stretcher
SCBA sets and breathing air compressor
10 min ELSA sets
Two hazardous area gas detectors (for
five different gases)
20 personal alarms
(LEL detection/CO2 gas detection)
Oxy viva resuscitation kit
Fully equipped
medical room
in
accommodation for site emergencies
Work vests in fibreglass box at stairs to
sea deck
Lifejackets for personnel transfer in
fibreglass box at base of crane
Personnel transfer basket for four
persons
Liferafts and lifebuoy
Equipment Requirement and
number Required
(CPP)
(BRB
Satellite
(WHRP)) Platforms











 (10 to 30)
 (10)


 (4)
 (4)

(10/10)
 (2/2)




 (4)






(20)
(20)
Fireman’s Equipment
Firemen equipment (2 boxes)shall be provided shall be provided on the CPP. The exact
contents of each set of equipment shall be based on the finalised manning level and platform
configuration/size. As an indication, each set should include:
1. Protective suit (bunker coats) complete with boots, gloves, hood and
helmet
2. A self-contained breathing apparatus
3. A portable battery operated lamp of three hours duration
4. A fireman’s axe
5. A safety harness and guidelines
6. A crowbar
7. A fire blanket
8. Spare air cylinders for breathing apparatus
Equipment should be used only by personnel trained in its use.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 28 of 35
4
4
2
2
2
2
1
1
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
5.5
Helicopter Crash Equipment
In the immediate vicinity of the helideck, all equipment for use in the event of an accident
involving a helicopter, as specified by MHS standards, should be stored in a cabinet. The
equipment should as a minimum include:
1.
2.
3.
4.
5.
6.
5.6
An aircraft type axe
A large axe
Hacksaw and blades
Grapple hook
Quick release knife
Crowbar and bolt cutters
Personnel Safety
This section covers the general safety of personnel on offshore installations and includes
such items as personal safety equipment, first aid equipment, sick bay and guarding of
machinery equipment.
5.6.1
Personnel Safety Equipment
Suitable safety helmets must be provided for every person on the installation.
Sufficient protective clothing (eye protectors, ear defenders, welding masks and
goggles, welding aprons, gloves, overalls, safety boots and shoes and breathing
apparatus) must be provided for all personnel engaged in operations where they are
exposed to risk of injury. All equipment provided must be kept clean and in a good
state of repair and condition, and be readily available for use when required by a
responsible person.
5.6.2
Medical Facilities and First Aid Equipment
In the LQ, a sick bay will be provided to be used solely for the purpose of medical
treatment and as a minimum shall be provided with the following, amongst others:
1. Patient alarm
2. Stretcher
3. Locked Cabinet
The sick bay shall be stocked with at least one first aid kit for each medically trained
person.
Sufficient suitable stretchers, at least one suitable for winching a sick or injured
person into a helicopter or vessel, and at least one collapsible stretcher suitable for
use in a confined space shall be provided.
5.6.3
Lifting Appliances
All lifting appliances and every item of lifting equipment shall be examined and tested
and all items shall be legibly marked with its safe working load. Certification of all
lifting appliances shall be undertaken by a third party.
Machinery Guarding and Heat Insulation. All exposed moving parts on all machinery
shall be suitably guarded to protect personnel from injury.
Guards and safety devices provided shall be well maintained and kept in position
whilst machinery is running.
All exposed parts of equipment having a skin temperature above 65C shall be
insulated or protected to avoid direct contact by personnel.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 29 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
5.6.4
Ladders
Fixed vertical ladders shall have a breadth of at least 350mm.
There shall be an unobstructed depth behind the rungs of at least 150mm. The
vertical distance between the rungs shall not be less than 250mm and not more than
350 mm. The rungs shall be evenly spaced for the entire ladder.
Maximum continuous ladder height shall be 9 m. Where the ladder height exceeds
this, rest landings shall be placed at a maximum of 6 metre intervals.
Starting at 2.5 metres from the base of the ladder, all ladders shall be provided with
safety cages. The safety cage shall extend to 1 m above the top of the ladder and
the distance form the rungs to the back of the cage shall be equal to 700 mm.
5.6.5
Doors
Doors shall have a free width of at least 750 mm and a clear height of at least 2050
mm. Doors shall generally be orientated so that they open in the direction of escape.
Doors on escape routes shall not be capable of being locked, and shall be provided
with self-illuminated signs.
5.6.6
Guardrails
The edge of any deck of walkway with a drop of 800 mm or more shall be provided
with a fixed guardrail, which shall be at least 1 m high, stanchions should be located
at maximum intervals of 1.5 m.
5.6.7
Toeboards
Any elevated decks or walkways shall be provided with toeboards, the height of
these shall be a minimum 100 mm. The opening between the deck/grating and the
toeboard shall not exceed 15mm. Details of the toeboards shall be proposed by
Contractor.
5.6.8
Stairs
Stairs should be provided where there is a height change of 450mm or more. Stair
edges shall have non-slip surfaces.
Stairs shall be constructed as to allow the easy transit of stretchers bearing a person
and shall be a minimum of 1.2m wide (same as the width of primary escape routes,
see Section 5.5).
5.6.9
Emergency Safety Showers & Eye Baths
In areas where personnel may come into contact with hazardous chemicals, there
shall be provided safety showers integral eye baths. Such units shall be 316
stainless steel continuously pressurised with fresh water. Such units shall include a
wide area filter to protect personnel’s eyes from foreign matter.
Safety eye baths shall be provided in all locations where hazardous chemicals can
be sprayed into the eyes of personnel. Such units shall be self contained distilled
water units with 10 minutes supply duration. Eye baths shall provide full face
bathing.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 30 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
Safety showers and eye baths shall:
1. Be treadle or push-plate operated
2. Be of 316 stainless steel and/or UV resistant plastic construction
3. Include in-built pressure and flow regulators.
Battery rooms shall also be provided with bottle-type eye baths.
5.7
Escape Routes & Platform Evacuation
In case of emergency the following shall be considered for platform evacuation:
1. Use of bridge linking CPP and BRB (WHRP)
2. Use of boat landing to the safety rescue vessel
3. Use of lifeboats/liferafts
4. Use of helicopter if feasible
Means of escape shall be provided from all enclosed and regularly manned areas of the
plant. A minimum of two escape routes shall be arranged from any area where a single
route would be in excess of five metres (5m) long and where more than 5 people are likely to
be grouped at the same time.
Primary escape routes shall not be obstructed in any way, and shall be on floors of solid
plate construction, and not on open grating.
All electrical switchroom doors shall be equipped with emergency quick opening device (antipanic bar).
Primary escape routes shall be 1.2 m wide and have clear headroom of 2.30 m. Doors on
escape routes shall open in the direction of escape.
External stairways of the accommodation area shall be 1.2 m wide. Other stairways to be
minimum 1.0 m wide. Landings shall be 1.5 m by 2.5 m minimum, to permit the handling of
stretchers.
Secondary escape routes shall be considered as the means of egress from inside modules
where primary routes do not exist. Secondary escape routes shall be 1.1 m wide and have
clear headroom of 2.30 m.
Escape routes shall be so constructed as to allow for easy transit and shall be clearly marked
and identified on the deck.
Rubber mats (mainly for electrical and switchgear room), non-slip plates, mesh type heat
shields (reflective) and all other safety provisions normal to basic permanently manned
platform requirements shall be identified and proposed for approval by the Company.
All means of access and egress shall be so constructed as to allow the easy transit of a
stretcher bearing personnel.
All means of access and egress shall be so constructed as to allow a person wearing selfcontained breathing apparatus to pass through without hindrance.
Passive and active fire protection shall be used if necessary on escape routes for the
protection of personnel against heat radiation.
All escape routes, lifeboat and liferaft stations and muster stations shall be adequately
illuminated by battery supplied emergency lighting and clearly identified by signs.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 31 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
5.8
Survival Equipment
Survival equipment shall be accordance with SOLAS and IMO requirements.
During basic design the survival equipment shall be designed on maximum manning level of:
1. 46 men maximum on CPP;
2. BRB (WHRP) and satellite platforms: normally unmanned.
The design shall allow for a total of 200% capacity. The exact number/capacity of survival
equipment is to be based on the finalised manning levels.
5.8.1
Lifeboat
The CPP, on which the LQ is situated, shall be provided with sufficient lifeboats to
accommodate 200% of the total number of persons planned to be present at the
same time. Lifeboats shall be davit launched, dual cabled, Totally Enclosed Motor
Propelled Survival Craft (TEMPSC).
The WHRP and the satellite platforms shall not be equipped with lifeboats but a
minimum level of survival equipment is to be provided in line with the specifications
for the CPP. In specifying survival equipment for these platforms, due consideration
should be given to the presence of the operations support vessel at the satellite
platforms at all times when they are manned.
The TEMPSC shall be stowed on approved type davits which shall be fitted with
electric winches to facilitate hoisting of the craft and located in “safe area”, i.e.
located as far as possible from any hazardous area.
The arrangement of the survival craft landing station and muster area shall be such
that it will not interfere with the operation of other lifesaving appliances or impede in
any way the prompt handling and marshalling of persons at the launching stations or
embarkation points. Survival craft shall be stowed so that they can be launched
safely in the shortest possible time.
The survival craft shall be located so as to ensure safe launching having particular
regard to the clearance from overhanging portions and side fittings of the installation
below the survival craft positions. A minimum of 3ft shall be provided between the
sides of the installation and davit launched survival craft when being lowered or
special deflection provisions shall be made to prevent damage or snagging during
raising and lowering.
Provisions shall be made at the platform legs at sea level, in areas near the
TEMPSC to minimise damage to it during launching.
5.8.2
Lifeboat Location
5.8.3
A minimum of 2 numbers of TEMPSC shall be provided at LQ level 1 on the CPP.
The exact requirements shall be confirmed by reference to the codes and standards
as well as by the QRA and other studies.
Liferaft
In addition to the above TEMPSC, all the CPP, BRB (WHRP) and satellite platforms
shall be provided liferafts at suitable locations including at the bridge ends of the
CPP and BRB (WHRP) platforms.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 32 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
All the above shall be located in a “safe area”, i.e. located as far as possible from
any hazardous area. They shall be distributed having regard to the number of
persons likely to be present on different areas at any time.
Appliances shall be stowed in such locations as to ensure safe launching in the
shortest possible time.
Liferafts shall be of 12 man capacity and shall afford a secondary means of
evacuating all the platforms. Liferafts shall be of the encapsulated “jettison” type
(rigid container) and shall automatically inflate when launched. Liferafts and
equipment shall be in accordance with SOLAS 1983. Certificate shall be provided.
Embarkation into jettison type liferaft shall be by means of knotted ropes, which shall
be located, adjacent to the liferafts stations.
Additional lifejackets shall be provided at each lifeboat and liferaft station.
5.8.4
Lifejackets
At the helicopter muster room/area, there shall be sufficient inflatable lifejackets
provided, equivalent to the largest operational helicopter for this field (probably
Sikorsky 61 aircraft) operating from the installation.
Lifejackets shall conform to the minimum requirements of SOLAS 1983. Quantities
and locations shall be determined by the POB, size and configuration of the
installation and shall be further defined in the Escape Route and Life Saving
Equipment drawings.
In specifying the requirements for lifejackets it must be borne in mind that the normal
practice in the region is for lifejackets to provided for each seat on board the
helicopter. If this practice is to be adopted for the PM3 phase 2 development then
no additional provision is required on the platform.
5.8.5
Workvest
One GRP container with a minimum of 20 workvest shall be located close to the
CPP boat landing, and one with four workvests at the head of the stairs to the boat
landing of each satellite platform. The exact number of workvests to be provided
shall be based on the finalised manning levels.
5.8.6
Lifebuoys
Lifebuoys shall be provided around all the CPP, BRB (WHRP) and satellite
platforms. Quantities and locations shall be further defined in the Escape Route and
Life Saving Equipment drawings.
Lifebuoys shall be located at lifeboat and liferaft stations and any other point deemed
necessary where they shall be either handrail or bulkhead mounted. They shall be
coloured “International Orange” and be suitably marked with the name of the
installation.
A length of buoyant line shall be attached to the lifebuoy and the other end securely
fastened to the installation. The length of line shall be twice the distance from the
mounting position to sea level at L.A.T.
In addition, 25% of the lifebuoys shall be equipped with water activated lights. At
strategic locations 25% of the lifebuoys shall also be equipped with smoke markers.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 33 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
5.9
Safety Signs and Notices
Graphic type signs shall be prominently displayed around the installation, identifying locations
of safety, firefighting and survival equipment etc. Legends for safety signs shall be in the
English and Bahasa Malaysia.
All operating instructions for lifeboats, liferafts and other safety equipment signs shall be in
English and Bahasa Malaysia.
Mimic form of Station Bills showing locations for major items of safety equipment and escape
routes shall be prominently displayed on all parts of the installation, and at each level of the
LQ.
On the inside of each cabin door shall be a floor plan of that level, giving the cabin occupants
directions to the muster points, escape routes to be taken and the disposition of fire and
safety equipment.
All directional signs shall be illuminated for up to 2 hours in an emergency.
Helideck markings shall be in accordance with relevant Civil Aviation Department and
COMPANY Specification Civil Aviation Department / SOLAS requirements.
Installation identification panels shall be positioned on two sides of the installation. The
panels shall display as a minimum the registered name of the installation. The legend should
be BLACK and be 1 (one) metre high on a YELLOW, retro-reflective background bearing the
names PM3 BUNGA RAYA.
5.10
Navigational Aids
Marine navigational aids and visual aids for helicopter operations shall be provided as per the
requirement of Local and International Legislation.
The marine navigational aids shall conform to the International Association of Lighthouse
Authorities recommendations.
Synchronised assemblies containing main white lights shall be installed on each corner of
the platforms. White lights should flash, emitting the Morse code letter “U” every 15 seconds
with minimum range at between 5 and 10 miles when the meteorological visibility is 10 miles.
5.10.1 Fog Signals
Fog signals and fog horns shall be installed as per the general Petronas
requirements and shall have as a minimum a range 2 mile.
The fog warning shall form the Morse letter “U” at a cycle of 30 seconds.
5.10.2 Helicopter Visual Aids
Helicopter visual aids including helideck lighting and obstruction lights shall be
provided as per the Department of Civil Aviation Regulations and the requirements of
International Legislation.
5.11
Boat Landings/Sea Access from/to Platform
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 34 of 35
Provision of Basic Engineering Design Services For Phase 2 and Phase 3 of PM3
Development
Design of boat landing shall take into account the sea/weather conditions and the
characteristics of the boats that will be used for personnel and the equipment transfer.
HSE Philosophy
Protek Engineers Sdn Bhd is a member of the JE Group
Page 35 of 35
Download