Uploaded by Eslam Allam

1MW ROOFTOP SOLAR PV POWER PLANT PERMIT

advertisement
LOCATION MAP
VICINITY MAP
BURDWAN, WB, INDIA
[email protected]
+91 8116401052
OM SAI SOLAR
CONSULTING
INNOVATIVE TYRES, HALOL, GUJARAT – UTILITY SCALE SOLAR PV POWER PLANT
GENERAL NOTES
4. CONTRACTOR TO VERIFY AND CHECK THE DIMENSIONS
AND DETAIL PRIOR TO THE START OF CONSTRUCTION. ANY
DISCREPANCY SHALL BE IMMEDIATELY REPORTED TO THE
ENGINEER FOR CLARIFICATIONANBD RESOLUTION.
NORMALIZED PRODUCTION PER INSTALLED kWp
(1000kWdc NOMINAL POWER)
DRAWING INDEX
SHEET NO.
1 OF 09
DWG NO.
T100
DESCRIPTION
ABBREVIATION
SHEET TITLE:
5. CONTRACTOR SHALL EXERCISE DUE CARE AND DILIGENCE
TO AVOID DAMAGE TO EXISTING UTILITIES, STRUCTURES OR
OTHER SITE IMPROVEMENTS NOT DESIGNATED TO BE
REMOVED OR MODIFIED. ANY DAMAGE TO EXISTING
IMPROVEMENTS NOT DESIGNATED TO BE REMOVED OR
MODIFIED SHALL BE RESTORED TO THEIR ORIGINAL
CONDITION OR BETTER.
Engineer:
I hereby certify that this drawing was prepared
by me or under my supervision
TITLE SHEET
Date
2 OF 09
G101
kWh/kWp/day
3 OF 09
S101
SITE LAYOUT
4 OF 09
E101
POWER ONE-LINE DIAGRAM (1)
E102
Issue
GENERAL NOTES
Date
5 OF 09
HALOL, GUJARAT, INDIA
PROJECT TITLE:
3. WORK SHALL BE PERFORMED IN ACCORDANCE WITH
APPLICABLE OSHA REGULATIONS.
TITLE SHEET
2. EXISTING UTILITIES SHALL REMAIN IN SERVICE AND IN
PLACE UNLESS NOTED OTHERWISE. INTERRUPTION OF
SERVICE SHALL BE KEPT TO A MINIMUM ANDONLY WITH
THE APPROVAL OF THE ENGINEER AND CONTRACTING
OFFICER.
INNOVATIVE TYRES –
1MW CAPTIVE SOLAR PV
POWER PLANT
1. THE CONTRACTOR SHALL OBTAIN ALL NECESSARY
PERMITS AND APPROVALS PRIOR TO STARTING ANY WORK.
POWER ONE-LINE DIAGRAM (2)
Marks
Revisions
DESIGNED BY
DRAWN BY:
CHECKED BY:
6 OF 09
E103
POWER ONE-LINE DIAGRAM (3)
7 OF 09
D101
SPV MODULE DATASHEET
8 OF 09
D102
SOLAR INVERTER DATASHEET
9 OF 09
L100
ELECTRICAL LABELS
SUPERVISED BY:
Drawing Number
T100
Scale:
Date:
AS SHOWN
MONTHS
02/06/2016
Sheet No.
01
OF
09
OM SAI SOLAR
CONSULTING
BURDWAN, WB, INDIA
[email protected]
+91 8116401052
GENERAL NOTES
GENERAL NOTES:
1.DO NOT SCALE DRAWINGS, IF UNABLE TO LOCATE DIMENSIONS FOR ANY ITEM OF WORK, CONSULT ARCHITECT/
ENGINEER FOR DIRECTIONS BEFORE PROCEEDING.
2.IN THE ABSENCE OF THE EXACT ROOF DIMENSIONS, THE DRAWING WILL BASED ON GOOGLE MAP, THEREFORE THESE
MAY NOT BE ACCURATE. CONTRACTOR ON SITE TO VERIFY ALL OBSTACLES ON THE ROOF AND ENSURE ALL REQUIRED
CLEARENCES WITH AUTHORITY HAVING JURISDICTION(S) PRIOR TO INSTALLATION, ORDERING MATERIAL OR
FABRICATION
3. CONTRACTOR SHALL OBTAIN ELECTRICAL AND OTHER PERMITS PRIOR TO INSTALLATION AND SHALL COORDINATE ALL
INSPECTIONS BY THE CITY INSPECTORS, TESTING/ COMMISSIONING BY THE UTILITY CO. AND ACCEPTANCE BY THE
CLIENT , AS NEEDED.
4.ROUTING OR RACEWAYS MATERIAL SHALL BE AT THE OPTION OF THE CONTRACTOR, WITHIN THE CODE, UNLESS
OTHERWISE NOTED AND SHALL BE COORDINATED WITH OTHER TRADES.
5. IF THE ROOF MATERIAL OR ROOF STRUCTURE IS NOT ADEQUATE FOR PV INSTALLATION, CALL ENGINEER PRIOR TO
INSATLL. THE CONTRACTOR IS RESPONSIBLE TO VERIFY THAT ROOF IS CAPABLE OF WITHSTANDING THE EXTRA WEIGHT.
6.WHENEVER A DISCREPANCY IN QUANTITY OF EQUIPMENT ARISES ON THE DRAWING OR SPECIFICATIONS, THE
CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING AND INSTALLING ALL MATERIAL AND SERVICES REQUIRED BY
STRICTEST CONDITIONS NOTED ON THE DRAWING OR IN THE SPECIFICATIONS TO ENSURE COMPLETE COMPLIANCE AND
LONGEVITY OF THE OPERABLE SYSTEM REQUIRED BY THE ARCHITECT/ENGINEER
7.THIS DESIGN IS FULLY BASED ON THE INFORMATION PROVIDED BY THE DEVELOPER, ANY MODIFICATIONS OR REMOVAL
OF THE LOGO OF THE EPC; "VARIETAS PROJECT MANAGERS & ENGINEERS" IS NOT ALLOWED AND WILL RENDER THIS
DESIGN VOID.
IEC 60068
ENVIRONMENTAL TESTING
IEC 60364-7-712
REQUIREMENTS FOR SPECIAL INSTALLATIONS OR LOCATIONS – SOLAR PHOTOVOLTAIC (PV) POWER SUPPLY SYSTEMS
IEC 60439-1
LOW VOLTAGE SWITCHGEAR & CONTROL GEAR ASSEMBLIES
IEC 60755
GENERAL REQUIREMENTS FOR RESIDUAL CURRENT – OPERATED PROTECTIVE DEVICES (OCPD)
IEC 61215
CRYSTALLINE SILICON TERRESTIAL PHOTOVOLTAIC (PV) MODULES – DESIGN QUALIFICATION AND TYPE APPROVAL
IEC 61683
EFFICIENCY MEASUREMENTS AND ENVIRONMENTAL TESTS OF POWER CONDITIONING UNITS (PCUs)
IEC 61701
PV MODULES TO BE USED IN A HIGHLY CORROSIVE ATMOSPHERE
IEC 61724
PHOTOVOLTAIC SYSTEM PERFORMANCE MONITORING – GUIDELINES FOR MEASUREMENT, DATA EXCHANGE AND ANALYSIS
IEC 61730
PART-2 : REQUIREMENTS FOR CONSTRUCTION & PART-2: REQUIREMENTS FOR TESTING, FOR SAFETY QUALIFICATION
IEC 62305
LIGHTING PROTECTION
IEC 62446
GRID CONNECTED PHOTOVOLTAIC SYSTEMS – MINIMUM REQUIREMENTS FOR SYSYTEM DOCUMENTATION, COMMISSIONING TESTS AND INSPECTION
IEC 62548
PHOTOVOLTAIC ARRAYS – DESIGN REQUIREMENTS
IEC 62109-1:2010
SAFETY OF POWER CONVERTERS FOR USE IN PHOTOVOLTAIC POWER SYSTEMS
IEC 62116
UTILITY-INTERCONNECTED PHOTOVOLTAIC INVERTERS – TEST PROCEDURE OF ISLANDING PREVENTION MEASURES
IEC 61727
PHOTOVOLTAIC SYSTEMS -CHARACTERISTICS OF THE UTILITY INTERFACES
IEC 61000
ELECTROMAGNETIC COMPATIBILITY (EMC)
IEC 62305
LIGHTNING PROTECTION STANDARD
IEC 61643-11
LOW VOLTAGE SURGE PROTECTIVE DEVICES – REQUIREMNETS & TESTS FOR SPDs IN PHOTOVOLTAIC APPLICATIONS
TUV 2 PfG 1169
TUV INTERNAL CABLE STANDARD
AS1319
SAFETY SIGNS FOR THE OCCUPATIONAL ENVIRONMENT
APPLICABLE JUNCTION BOX
STANDARDS
CREEPAGE DISTANCES AND CLEARANCES
IEC 60664
JUNTION BOXES
IEC 50548
DEGREES OF PROTECTION PROVIDED BY THE ENCLOSURES
IEC 60529
LOW VOLTAGE FUSES
IEC 60269
COPPER BUS BARS /TERMINAL BLOCKS HOUSED IN THE JUNCTION BOX WITH SUITABLE TERMINATION THREADS
IEC 62208
CHROMATED DIN RAIL
EN 60715
APPLICABLE SWITCHBOARD
LOW VOLTAGE AC SWITCHGEAR AND CONTROL GEARS SPECIFICATIONS
STANDARDS
IEC
60439
LOW VOLTAGE AC SWITCHGEAR AND CONTROL GEARS ASSEMBLIES
ICE 60947
IEC
GENERAL REQUIREMENTS FOR AC SWITCHGEAR & CONTROL GEAR VOLTAGE <1000V
IEC 60529
DEGREE OF PROTECTION FOR LOW VOLTAGE SWITCHGEAR & CONTROL ENCLOSURES
IEC 60404
ELECTROLYTIC COPPER / ALUMINIUM
IEC 62056
AC ELECTRIC METERS
IEC 60364
EARTHING
IEC 60947.2
DANGER NOTIC PALTES
IEC 60439
CIRCUIT BREAKERS VOLTAGE UP TO 1000V
IEC EN 60269-1
AIR BREAK SWITCHES/DISCOONECTS FOR VOLTAGES < 1000VAC & 1200VDC
IEC 60529
MAKING AND ARRANGEMENTS FOR SWITCHGGEAR, BUS BARS, MAIN CONNECTIONS
HALOL, GUJARAT, INDIA
ELECTRICAL INSTALLATIONS OF BUILDINGS
SHEET TITLE:
IEC 60050V (826)
PROJECT TITLE:
ELECTRICAL NOTES AND STANDARDS TO FOLLOW:
GENERAL NOTES
ELECTRICAL
9. ADEQUATE SPACING MUST BE MAINTAINED BETWEEN ANY PLUMBING/ SEWER VENTS EXTENDING THROUGH THE ROOF
AND UNDERSIDE OF THE PHOTOVOLTAIC PANELS (6'' MINIMUM RECOMMENDED).
INNOVATIVE TYRES –
1MW GRID CONNECTED
SOLAR PV POWER SYSTEM
8.THE WORKING CLEARANCE AROUND THE EXISTING ELECTRICAL EQUIPMENTS AS WELL AS THE NEW ELECTRICAL
EQUIPMENT WILL BE MAINTAINED IN ACCORDANCE WITH.
Engineer:
I hereby certify that this drawing was prepared
by me or under my supervision
Date
Date
Issue
Marks
Revisions
APPLICABLE STANDARDS FOR LOW
VOLTAGE AC CABLES
XLPE INSULATED PVC SHEATHED CABLES FOR WORKING VOLTAGES <1100V
IEC 60840
RECOMMENDED CABLE CURRENT RATINGS
IEC 60502
CONDUCTORS FOR INSULATED CABLES
IEC 60227, 60228
DESIGNED BY
DRAWN BY:
APPLICABLE
SP
30
LOCAL STANDARDS
NATIONAL ELECTRICAL CODES
IS 875
WIND LOADS ON BUILDINGS AND STRUCTURES
IS 2062: 1992
THE MOUNTING STRUCTURE STEEL
IS 2309
PROTECTION OF BUILDINGS AND ALLIED STRUCTURES AGAINST LIGHTING
IS 3043 – 1987
EACH ARRAY STRUCTUTRE OF THE PV YARD
IS 4759
GALVANIZATION OF THE MOUNTING STRUCTURE
CHECKED BY:
SUPERVISED BY:
Drawing Number
G101
Scale:
Date:
AS SHOWN
02/06/2016
Sheet No.
02
OF
09
STRING #G1, 20 MODULES
+
-
-
-
-
6 sq.mm PV WIRE
6 sq.mm
BARE COPPER
GROUNDING WIRE
RAIL
....
GROUNDING LUG
+
+
-
-
-
+
+
+
+
-
-
-
-
6
-
-
SHEET TITLE:
RAIL
....
GROUNDING LUG
+
11
-
BURDWAN, WB, INDIA
[email protected]
+91 8116401052
HALOL, GUJARAT, INDIA
+
PV to STRINGS
+
POWER ONE-LINE
DIAGRAM
-
+
INNOVATIVE TYRES –
1MW GRID CONNECTED
SOLAR PV POWER SYSTEM
1
6 sq.mm PV WIRE
PROJECT TITLE:
+
OM SAI SOLAR
CONSULTING
POWER ONE-LINE DIAGRAM
PV TO STRINGS
Engineer:
RAIL
....
I hereby certify that this drawing was prepared
by me or under my supervision
GROUNDING LUG
-
Date
16
-
-
-
RAIL
....
GROUNDING LUG
-
+
+
-
-
20
PV MODULE RATINGS @ STC
MODULE MFR: JINKO SOLAR
MODEL: JKM250P
VOC = 37.7V
VMP = 30.5V
ISC = 8.85A
IMP = 8.20A
Date
Issue
Marks
Revisions
DESIGNED BY
DRAWN BY:
CHECKED BY:
SUPERVISED BY:
Drawing Number
E101
Scale:
Date:
AS SHOWN
THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING
THE WORK AMONG THE VARIOUS TRADES AS NECESSARY TO
AVOID CONFICTS AND TO INSURE THE INSTALLATION OF ALL
WITHIN THE AVAILABLE SPACE.
02/06/2016
Sheet No.
04
OF
09
RAIL
GROUNDING LUG
#10 AWG THWN
MODULE/RACKING
EGC
STRING #B1, 20 MODULES
+
1 -
.... +
-
RAIL
GROUNDING LUG
+
1 -
.... +
-
.... +
-
+
.... +
-
-
+
.... +
-
RAIL
GROUNDING LUG
1-½" EMT
AC.2
DC.2
NEU
DC.1
G
21
#10 AWG THWN
MODULE/RACKING
EGC
DC.1
STRING #E1, 20 MODULES
1 -
CONDUIT
#10 AWG THWN
MODULE/RACKING
EGC
.... +
AC.1
CONDUIT
21
RAIL
GROUNDING
LUG
-
+
-
+- +- +- +- +- +- +- +- G
114" EMT
STRING #D1, 20 MODULES
1 -
MPPT
2
40A/3P
40A/3P
40A/3P
40A/3P
40A/3P
DC.1
RAIL
....
GROUNDING
LUG
-
+
-
MPPT
1
#10 AWG THWN
MODULE/RACKING
EGC
STRING #C1, 20 MODULES
+
-
DC DISC.
.... +
- 21
1- ¼ " EMT
.... +
-
21
#10 AWG THWN
MODULE/RACKING
EGC
CONDUIT
141" EMT
PV MODULE RATINGS @ STC
DC.2
MODULE MFR: ZINKO SOLAR
MODEL:
250Wp
VOC = 37.7V
VMP = 30.5V
ISC = 8.85A
IMP = 8.20A
"INV#2"
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT
& ARC-FUALT INTEREPTER
STRING #A2, 20 MODULES
STRING #B2, 20 MODULES
STRING #C2, 20 MODULES
STRING #D2, 20 MODULES
STRING #E2, 20 MODULES
PV INVERTER RATINGS
INVERTER MFR: INGETEAM
INVERTER MODEL:
24TL U M480
DC VOLT RATING
= 1000V
OPERATING VOLTAGE
=580-950V
DC MAX USABLE INPUT CURRENT:
PER MPPT
= 27A
PER INVERTER
= 54A
AC MAX RATED OUTPUT POWER = 24000W
= 29A
AC MAX OUTPUT CURRENT
"INV#3"
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT
& ARC-FUALT INTEREPTER
STRING #A3, 20 MODULES
STRING #B3, 20 MODULES
STRING #C3, 20 MODULES
STRING #D3, 20 MODULES
STRING #E3, 20 MODULES
"INV#4"
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT
HALOL, GUJARAT, INDIA
+
-
AC DISC.
DC.1
L1
L2
L3
N
G
CONDUIT
STRINGS TO INVERTER TO SUB-PANEL
-
(n)
200A 3P
(n)
20
POWER ONE-LINE
DIAGRAM
-
.... +
INNOVATIVE TYRES –
1MW GRID CONNECTED
SOLAR PV POWER SYSTEM
.... +
SHEET TITLE:
+
1 -
PROJECT TITLE:
+
-
NEW PV SUB-PANEL, "SP1"
200A BUS MINUMUM, 277/480V 4W
DC.1
STRING #A1 , 2 MODULES
BURDWAN, WB, INDIA
[email protected]
+91 8116401052
"INV#1"
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT
& ARC-FUALT INTEREPTER
OM SAI SOLAR
CONSULTING
POWER ONE-LINE DIAGRAM
STRINGS TO INVERTER TO SUB-PANEL
Engineer:
I hereby certify that this drawing was prepared
by me or under my supervision
& ARC-FUALT INTEREPTER
MIN WIRE SIZE = 29A * 125% = 36.25A
MIN (OCPD) = 40A, AVAILABLE (OCPD) =40A
STRING #A4, 20 MODULES
STRING #B4, 20 MODULES
STRING #C4, 20 MODULES
Date
STRING #D4, 20 MODULES
STRING #E4, 20 MODULES
Date
CIRCUIT DESCRIPTION
"INV#5"
INGETEAM 24TL-U-M480 WITH BOTH DC & AC DISCONNECT
& ARC-FUALT INTEREPTER
STRING #A5, 20 MODULES
STRING #B5, 20 MODULES
STRING #C5, 20 MODULES
STRING #D5, 20 MODULES
STRING #E5, 20 MODULES
CONDUCTOR SIZE/TYPE
CONDUIT SIZE*/QTY
1-WAY WIRE TRAVEL
VOLTAGE
@MAX POWER
CURRENT
@MAX POWER
VOLTAGE DROP (%)
(A)
(DC) SOLAR STRING
WIRING
2-CORE 6 sq.mm
FA
-
622 Vdc
8.53A
0.5%
(B)
(DC) STRING TO INVERTER (5
STRINGS)
(5) 2-CORE 6 sq.mm
(2) 1-¼ in
350 ft
622 Vdc
2*8.53A
0.5%
(C)
(AC) INVERTER TO
COMBINER BOX (5 INVERTERS)
(5) 4-CORE 16 sq.mm
(1) 1-¼ in
140 ft
480VAC
29A
0.80%
(D)
(AC) GEC GROUNDING
(1) BARE COPPER 10mm
(1) 1 in
65 ft
480VAC
-
-
(E)
(DC) GEC GROUNDING
(1) BARE COPPER 6mm
(1) ½ in
450 ft
622 Vdc
-
-
Issue
Marks
Revisions
DESIGNED BY
DRAWN BY:
CHECKED BY:
SUPERVISED BY:
Drawing Number
E102
*Please note that the size of the conduit calculated by considering 30% Fill Factor
Scale:
Date:
AS SHOWN
THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING
THE WORK AMONG THE VARIOUS TRADES AS NECESSARY TO
AVOID CONFICTS AND TO INSURE THE INSTALLATION OF ALL
WITHIN THE AVAILABLE SPACE.
02/06/2016
Sheet No.
05
OF
09
(n)
200A 3P
C#1, 20 SPV MODULES
D#1, 20 SPV MODULES
(n)
40A/3P
E#1, 20 SPV MODULES
CONDUIT
40A/3P
B#2, 20 SPV MODULES
1-½" EMT
40A/3P
40A/3P
40A/3P
A#2, 20 SPV MODULES
INV#2
AC.2
C#2, 20 SPV MODULES
NEU
BURDWAN, WB, INDIA
[email protected]
+91 8116401052
INV#1
OM SAI SOLAR
CONSULTING
B#1, 20 SPV MODULES
POWER ONE-LINE DIAGRAM
COMPLETE SOLAR PV SYSTEM
NEW PV SUB-PANEL, "SP1"
200A BUS MINUMUM, 277/480V 4W
A#1, 20 SPV MODULES
G
D#2, 20 SPV MODULES
E#2, 20 SPV MODULES
A#3, 20 SPV MODULES
B#3, 20 SPV MODULES
INV#3
NEW 1250kVA
TRANSFORMER#1
SECONDARY
PRIMARY
14kV Delta
480 Wye
C#3, 20 SPV MODULES
D#3, 20 SPV MODULES
X1
H1
E#3, 20 SPV MODULES
A#4, 20 SPV MODULES
H2
X2
X3
AC.2
E#4, 20 SPV MODULES
AC.2
G (n)
G
D#4, 20 SPV MODULES
A#5, 20 SPV MODULES
INV#5
PROJECT TITLE:
B#5, 20 SPV MODULES
C#5, 20 SPV MODULES
D#5, 20 SPV MODULES
AC SIDE COMBINER BOX
“CB1”
E#5, 20 SPV MODULES
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#6
NEW PV SUB-PANEL, "SP2"
200A BUS MINUMUM, 277/480V 4W
200A 3P
INPUT SIDE
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#7
M1
40A/3P
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#8
40A/3P
(e)
SWITCHBOARD 11000/440V 3PH
2500A BUS BAR
40A/3P
CONDUIT
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#9
OUTPUT SIDE
2" EMT
POINT OF CONNECTION
PER 690.64; 705.12(D)
200A 3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#10
SPLICES & TAPS PER 366.56
TOTAL STRING SIZE = 25kWp,
5x20 SPV
LOCKABLE & 120A, 11kV FUSED AC CIRCUIT BREAKER
INV#11
AUXILIARY
GUTTER
(3) POLARIS STACKED
CONNECTORS IPLDS
NEW PV SUB-PANEL, "SP3"
200A BUS MINUMUM, 277/480V 4W
AC.3
TOTAL STRING SIZE = 25kWp,
5x20 SPV
SHEET TITLE:
INPUT SIDE
INV#12
40A/3P
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#13
40A/3P
40A/3P
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#14
N
OUTPUT SIDE
G
LOADS
200A 3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#16
NEU
G
INV#15
NEW PV SUB-PANEL, "SP4"
200A BUS MINUMUM, 277/480V 4W
Engineer:
INPUT SIDE
TOTAL STRING SIZE = 25kWp,
5x20 SPV
3/4"
C-1#4
INV#17
40A/3P
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#18
40A/3P
40A/3P
G
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#19
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#20
INV#21
G
(e)
GROUND RODS 6'-0"
(2) 3/4" x 10'
APART TYPICAL
OUTPUT SIDE
200A 3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
POWER LINE
DIAGRAM
H3
C#4, 20 SPV MODULES
HALOL, GUJARAT, INDIA
H0
INV#4
INNOVATIVE TYRES –
1MW GRID CONNECTED
SOLAR PV POWER SYSTEM
B#4, 20 SPV MODULES
I hereby certify that this drawing was prepared
by me or under my supervision
Date
Date
NEW PV SUB-PANEL, "SP5"
200A BUS MINUMUM, 277/480V 4W
Issue
Marks
Revisions
INPUT SIDE
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#22
40A/3P
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#23
TOTAL STRING SIZE = 25kWp,
5x20 SPV
40A/3P
INV#31
40A/3P
INPUT SIDE
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#24
OUTPUT SIDE
TOTAL STRING SIZE = 25kWp,
5x20 SPV
40A/3P
DRAWN BY:
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#25
INV#33
40A/3P
40A/3P
CHECKED BY:
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#34
INV#26
NEW PV SUB-PANEL, "SP6"
200A BUS MINUMUM, 277/480V 4W
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#35
INPUT SIDE
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#27
TOTAL STRING SIZE = 25kWp,
5x20 SPV
40A/3P
INV#36
NEW PV SUB-PANEL, "SP8"
200A BUS MINUMUM, 277/480V 4W
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#28
INPUT SIDE
40A/3P
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#29
INV#37
40A/3P
40A/3P
OUTPUT SIDE
200A 3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#38
40A/3P
40A/3P
40A/3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#30
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#39
OUTPUT SIDE
200A 3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
INV#40
SUPERVISED BY:
OUTPUT SIDE
200A 3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
DESIGNED BY
INV#32
200A 3P
TOTAL STRING SIZE = 25kWp,
5x20 SPV
NEW PV SUB-PANEL, "SP7"
200A BUS MINUMUM, 277/480V 4W
ARRAY CONFIGURATION
No. of Inverters:40
Strings Per Inverter: 5
SPV Modules per String: 20
String Vmpp @STC: 615Vdc
String Impp @STC: 8.62A
Total Array Size: 1000kWdc
AC Output (@p.f=1) = 1000kVA
Drawing Number
E103
Scale:
Date:
AS SHOWN
02/06/2016
Sheet No.
06
OF
09
HALOL, GUJARAT, INDIA
SUGGESTED PV ARRAY LAYOUT
SITE LAYOUT
SHEET TITLE:
INNOVATIVE TYRES –
1MW GRID CONNECTED
SOLAR PV POWER SYSTEM
PROJECT TITLE:
OM SAI SOLAR
CONSULTING
WITH SUGGESTED PV ARRAY LAYOUT
BURDWAN, WB, INDIA
[email protected]
+91 8116401052
SITE LAYOUT
Engineer:
I hereby certify that this drawing was prepared
by me or under my supervision
Date
Date
Issue
Marks
Revisions
DESIGNED BY
DRAWN BY:
CHECKED BY:
SUPERVISED BY:
Drawing Number
S101
Scale:
Date:
AS SHOWN
THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING
THE WORK AMONG THE VARIOUS TRADES AS NECESSARY TO
AVOID CONFICTS AND TO INSURE THE INSTALLATION OF ALL
WITHIN THE AVAILABLE SPACE.
02/06/2016
Sheet No.
03
OF
09
INNOVATIVE TYRES –
1MW GRID CONNECTED
SOLAR PV POWER SYSTEM
DATASHEET –
SOLAR
PHOTO VOLTAIC
MODULE
HALOL, GUJARAT, INDIA
BURDWAN, WB, INDIA
[email protected]
+91 8116401052
PROJECT TITLE:
SHEET TITLE:
OM SAI SOLAR
CONSULTING
SOLAR PHOTOVOLTAIC MODULE – DATA SHEET
Engineer:
I hereby certify that this drawing was prepared
by me or under my supervision
Date
Date
Issue
Marks
Revisions
DESIGNED BY
DRAWN BY:
CHECKED BY:
SUPERVISED BY:
Drawing Number
D101
Scale:
Date:
AS SHOWN
02/06/2016
Sheet No.
07
OF
09
HALOL, GUJARAT, INDIA
BURDWAN, WB, INDIA
[email protected]
+91 8116401052
DATA SHEET –
SOLAR INVERTER
SHEET TITLE:
PROJECT TITLE:
INNOVATIVE TYRES –
1MW GRID CONNECTED
SOLAR PV POWER SYSTEM
OM SAI SOLAR
CONSULTING
SOLAR INVERTER – DATA SHEET
Engineer:
I hereby certify that this drawing was prepared
by me or under my supervision
Date
Date
Issue
Marks
Revisions
DESIGNED BY
DRAWN BY:
CHECKED BY:
SUPERVISED BY:
Drawing Number
D102
Scale:
Date:
AS SHOWN
02/06/2016
Sheet No.
08
OF
09
[email protected]
+91 8116401052
WB, INDIA
,
BURDWAN
LOCATION OF THIS LABEL IS ON THE AC DISCONNECT PLACED
BETWEEN COMBINER BOX AND TRANSFOMER
! DANGER
Arc flash and
shock hazard.
Appropriate PPE
required.
UTILITY AC DISCONNECT WARNING LABEL. 1
PER AC DISCONNECT AND ALL 3 AC LOAD
CENTERS.
UTILITY AC DISCONNECT OPERATING
SPECIFICATIONS. 1 PER AC DISCONNECT SITUATED
BETWEEN SUB-PANEL AND COMBINER BOX
LABEL FOR SYSTEM OWNER'S KWH GENERATION
METER; 1 PER OWNER METER.
LABEL FOR FACILITY NET GENERATION METER; 1
PER FACILITY GENERATION METER.
LABEL FOR ARC FLASH WARNING. 1 PER
ENERGIZED ENCLOSURE WITH ACCESS TO LIVE
PARTS.
,
PROJECT TITLE:
ONE PER INVERTER. NUMBER SEQUENTIALLY
UTILITY AC DISCONNECT
CAUTION LABEL
1000 VOLTS DC
UV RESISTANT, REFLECTIVE MARKINGS
REQUIRED ON ALL INTERIOR AND EXTERIOR DC
CONDUIT, RACEWAYS, ENCLOSURES, CABLE
ASSEMBLIES AND JUNCTION BOXES TO ALERT
FIRE SERVICE. MARKINGS SHALL BE PLACED
EVERY 10 FEET, AT TURNS, ADJACENT TO
PENETRATIONS, AT ALL DC COMBINER BOXES,
AND AT ALL DC JUNCTION BOXES. MARKING
CONTENT SHALL READ, "CAUTION: SOLAR
CIRCUIT" IN NON-BOLD ARIAL OR SIMILAR FONT
WITH 3/8" ALL CAPS WHITE LETTERING ON RED
BACKGROUND
LABELS
WARNING:
ELECTRIC SHOCK HAZARD, DO NOT
TOUCH TERMINALS. TERMINALS ON
BOTH THE LINE AND LOAD SIDES MAY
BE ENERGIZED IN TH OPEN POSITION
INV.XX
CONDUIT RUN FROM INVERTER TO POCC. (AS
NEEDED)
SHEET TITLE:
PHOTOVOLTAIC
AC DISCONNECT
CONDUIT RUN FROM SOURCE CIRCUT TO
INVERTER. (AS NEEDED)
SITE ADDRESS:
MIDC, HALOL, GUJARAT, INDIA
SOLAR PHOTOVOLTAIC
ARRAYLOCATION
LABEL FOR UTILITY AC DISCONNECT; 1 PER AC
DISCONNECT.
1000 kWdc
FACILITY NET
GENERATION METER
AC DISCONNECT RATINGS:
OPERATING CURRENT: 1600 AMPS
OPERATING VOLTAGE: 480 VOLTS AC
MAXIMUM CURRENT: 1000 AMPS/POLE
MAXIMUM VOLTAGE: 480 VOLTS AC
PROVIDES THE LOCATION OF THE SERVICE
DISCONNECTING MEANS AND THE
PHOTOVOLTAIC DISCONNECTING MEANS. THIS
PLAQUE SHALL BE APPLIED TO THE MAIN
SERVICE DISCONNECTING MEANS AND THE
PHOTOVOLTAIC DISCONNECTING MEANS; (2
TOTAL)
SYSTEM SIZE:
CAUTION
POWER TO THIS SERVICE IS ALSO
SUPPLIED FROM THE FOLLOWING
SOURCES WITH DISCONNECTS
LOCATED AS SHOWN
PHOTOVOLTAIC
AC DISCONNECT
INNOVATIVE TYRES, HALOL, GUJARAT
GRID-CONNECTED SOLAR PV SYSTEM
SYSTEM OWNER
GENERATION METER
LABEL AND MARKINGS LEGEND:
GENERAL NOTES FOR LABELS AND
MARKINGS:
PHOTOVOLTAIC
AC DISCONNECT
AC DISCONNECT RATINGS:
OPERATING CURRENT: 200 AMPS
OPERATING VOLTAGE: 480 VOLTS AC
MAXIMUM CURRENT: 1000 AMPS/POLE
MAXIMUM VOLTAGE: 480 VOLTS AC
208 VOLTS AC
1. LABELS AND MARKINGS SHALL BE APPLIED TO
THE APPROPRIATE COMPONENTS IN
ACCORDANCE WITH THE NEC.
2. SOLAR MODULES ARE SUPPLIED FROM THE
MANUFACTURER WITH MARKINGS PRE-APPLIED TO
MEET THE REQUIREMENTS OF THE NEC.
Engineer:
I hereby certify that this drawing was
prepared by me or under my supervision
3. NEXTRONEX AND SOLAR EDGE INVERTERS ARE
SUPPLIED FROM THE MANUFACTURER WITH THE
APPROPRIATE LABELS AND MARKINGS TO MEET
THE REQUIREMENTS OF THE NEC.
4. TEXT LABELS WILL BE ETCHED WITH WHITE
GRAPHICS ONTO 1/16" RED PLASTIC PLACARDS.
THE LABEL WILL BE MECHANICALLY ATTACHED TO
THE APPROPRIATE COMPONENT ENCLOSURES IN
CONSPICUOUS PLACES.
5. LABEL "A" WILL BE ETCHED WITH WHITE
GRAPHICS ONTO 1/16" RED PLASTIC PLACARD.
THE LABEL WILL BE EFFECTIVELY BONDED TO THE
EXISTING FACILITY SWITCHBOARD AND THE NEW
PHOTOVOLTAIC SYSTEM DISCONNECT.
Date
Issue
Date
Revisions
Marks
DESIGNED BY
DRAWN BY:
CHECKED BY:
SUPERVISED BY:
Drawing Number
L100
Date:
Scale:
AS SHOWN
Sheet No.
09
OF
09
02/06/2016