Engineering Safety: Going Lower - Reducing Risk, Enhancing Projects Howard Thompson – February 2013 AMEC Brownfield Projects & Operations Management - Technical Safety Manager AMEC Europe – Head of Engineering Assurance & Governance 1 Outline of Presentation Explore some of the trends that influence Engineering Safety Explore some of the limitations of Hazard & Risk Management as an approach to Engineering Safety Outline the principles of an Inherently Safer approach Consider the organisational implications in developing an Inherently Safer approach to Engineering Safety 2 In the Beginning ... ... low sensitivity to Consequences or the Likelihood of them! 3 More Recently ... The Hoover Dam: 112 people died during construction Attitudes to Hazards and Risks are constantly evolving 4 Trends in Occupational Safety 4 API Bayer BP 3 Chevron Texaco Concawe ConocoPhillips 2 Dow DuPont ExxonMobil OMV 1 Shell Trend Line 05 20 03 20 01 20 99 19 97 19 95 19 93 0 19 Incidents per 200,000 work hours 5 5 Unrevealed Safety Issues • Despite improving HSE Performance indicators, the Texas City refinery suffered a major event in May 2005 … and a second event two months later … OSHA Recordable Incident Frequency (RIF) Texas City refinery: From 1.73 (1999) to 0.64 (2004) API US refining average: 0.84 (2004) BP Global: 0.53 (2004) • Occupational safety data can give misleading indications of ‘design’ or ‘process’ safety performance • ‘Process’ or ‘Design’ Safety was not widely measured in 2005, however, indicators of hardware safety issues are more widely recorded and assessed now … although there are many more Lagging indicators in use than Leading ones! 6 Texas City 7 Trends in Refinery Damages Incident costs - $ per 1000bbls refinery capacity corrected to 2000 prices 25.00 Raw data 20.00 5-year average 15.00 Linear (5-year average) 10.00 5.00 20 00 19 98 19 96 19 94 19 92 19 90 19 88 19 86 19 84 19 82 19 80 19 78 19 76 19 74 19 72 19 70 19 68 19 66 0.00 19 64 Damage $/1000 bbl refinery production at 2000 prices 30.00 8 Trends Increased and increasing public risk aversion Reducing regulatory tolerance Increased damages where legal action ensues Increased focus on occupational safety and statistics Increasing focus on ‘technical’ safety and statistics Increased Management of Change (MoC) challenges – Through the life of modern engineered facilities and products – Due to evolution in stakeholder organisations – Changing operational requirements 9 An Increasing Complex world … Nimrod 2006 After an Air-to-Air Refuelling (AAR), the plane caught fire Experienced crew acted with calmness, bravery and professionalism, and in accordance with training, but could not control the fire Aircraft exploded All 14 on board died Why Did it Happen? Fuel vent pipes and couplings No 7 Fuel tank ↓ ← Cross-Feed – Supplementary Cooling Pack Duct (HOT) Airframe anti-icing pipe → ←────── Fuel pipes – refuel and feed Uninsulated Bellows Why Did it Happen? Probable cause was fuel coming into contact with extremely hot surfaces; an overflow due to the Air to Air Refuelling, ignited by the cross-feed / Supplementary Cooling Pack (SCP) duct, which could be at up to 400ºC, and was not properly insulated Major design flaws: Original fitting of cross-feed duct Addition of SCP AAR modification Why Did it Happen? Fuel pipe / vent coupling seals sourced from new supplier Couplings not to original specification – Although thought to be by the procurement function Fuel pipe / vent couplings known to be unreliable by maintenance teams –This information never fed back to the design or safety case teams Why Did it Happen? A number of previous incidents and warning signs ignored Safety case existed but contained significant errors Widespread assumption that Nimrod was “safe anyway” after 30 years of successful flights Safety case became a “tick-box” exercise Missed key dangers, should have been the best opportunity to prevent the accident Financial pressures and cuts led to there being distraction from safety as an overriding priority Hazard and Risk Management ... A crucial ... LIMITED ... contributor to safety! 15 Hazard and Risk Management Paradigm What could happen? How often? How bad? So what? What do I do? 16 Hazard and Risk Management Risk Analysis Hazard Identification Frequency Analysis Risk Assessment Risk Management Consequence Analysis Evaluation of Hazard & Risk Manage Risk Residual Risk 17 Event Sequences A corner stone of the Hazard & Risk Management Paradigm is the concept of Event Sequence The idea is that all event sequences are identified in the analysis, or covered within some more general event sequence A key limitation is the issue of foresee-ability What is foreseeable? Is it really possible to foresee all categories of event The case law is demanding engineers and experts are expected to foresee relatively remote events The O&G industry regulator is not as demanding as for example the Nuclear industry regulator in these matters 18 Underlying techniques of Hazard and Risk Management Process REQUIRED – The Hierarchical use of controls and barriers REQUIRED – The Demonstration of ALARP ALARP - As Low As Reasonably Practicable 19 Safe? “ “ We identified the Hazards and ensured there were adequate Safeguards, consistent with the ALARP principle N.b. ... The cost emphasis of ALARP ... an encouragement to add safeguards until increased benefits through risk reduction can not be justified Some North Sea Events The SEA GEM 27th December 1965 – 13 Lost Mineral Workings (Offshore Installations) Act 1971 The ALEXANDER KEILLAND 27th March 1980 – 123 Lost Norway – Created a clear source of Authority for Abandonment The sister rig the Henrik Ibsen also got into difficulty a few months later The PIPER ALPHA July 1988 – 167 Lost Mineral Workings (Offshore Installations) Act 1971 21 The SEA GEM – The First Rig to Find Hydrocarbons in the NS The Alexander Keilland Semi Sub Drilling Rig Adjacent to a Production Platform Alexander Keilland – Structural Arrangement 24 Piper Alpha Metocean Conditions - Foreseeable ? The Ocean Ranger – Capsized off Newfoundland February 1982 – 84 lost Ocean Ranger with Draupner Wave shown for comparison 1 – The Draupner wave 59 ft / 18 m 2 – Location of unprotected portlight 28 ft / 8.5 m 3 – Location of the ballast control room 26 How Can We Make It Safer ? “ “ So what can we do differently? Inherently Safer Design The concept supports the view that the achievement of safe operations requires that HAZARDS are addressed during concept development and all subsequent phases of System, Structure, or Equipment design AND IMPLEMENTATION The intent of Inherently Safer Design is to eliminate a hazard completely or reduce its magnitude significantly Thereby eliminating / reducing the need for safety systems and procedures Furthermore, this hazard elimination or reduction should be accomplished by means that are inherent in the design and process and thus permanent and inseparable from them 28 Principles of Inherent Safety Eliminate Simplify Minimise Inherent Safety Principles Moderate Substitute 29 Examples - Minimise Minimise storage of hazardous gases, liquids and solids Minimise inventory by phase change (liquid instead of gas) Eliminate raw materials, process intermediates or by-products Just-in-time deliveries of hazardous materials Hazardous materials removed or properly disposed of when no longer needed Hazardous tasks (e.g. working at height or above water, lifting operations) combined to minimise the number of trips Need for awkward postures and repetitive motions minimised 30 Examples - Substitute Substitute a less toxic, less flammable or less reactive substance –Raw materials, process intermediates, by-products, utilities etc. –Use of water-based product in place of solvent- or oil-based product Alternative way of moving product or equipment in order to eliminate human strain Allergenic materials, products and equipment replaced with nonallergenic alternatives Gas Gas Hot Oil Hot Water 31 Examples - Moderate Reduce potential releases by lower operating conditions (P, T) – Process system operating conditions – New / replacement equipment that operate at lower Speed, P or T Dilute hazardous substances to reduce hazard potential Storage of hazardous gases, liquids and solids as far as way as possible in order to eliminate risk to people, environment and asset Segregation of hazardous equipment / units to prevent escalation Relocate facility to limit transportation of hazardous substances New / replacement equipment that produces less noise or vibration 32 Examples - Simplify Simplify and / or reduce - connections, elbows, bends, joints, small bore fittings Separate single complex multipurpose vessel with several simpler processing steps and vessels Equipment designed to minimize the possibility of an operating or maintenance error Minimise number of process trains Reactors designed / modified to eliminate auxiliary equipment (e.g. blender) Eliminate or arrange equipment to simplify material handling Ergonomically designed workplace 33 Examples of Equipment Level ISD in Brownfield & Operations Development 1 • Replace flammable hydraulic fluids with water-based equivalents • Replace oil-filled switchgear with vacuum-insulated equivalent • Replace Ex instrumentation with intrinsically safe equivalents • Use low toxicity oils to replace PCBs in transformers • Use low smoke, zero halogen, cable insulation • Use PFP coatings that resist water ingress so avoid Corrosion Under Insulation 34 Examples of Equipment Level ISD in Brownfield & Operations Development 2 • Arrange equipment layout to minimise restrictions on explosion venting • Arrange “Deluge on Gas” where advantageous to minimise explosion overpressures • Arrange beam detection to replace or supplement point F&G detectors • Position acoustic leak detectors to supplement gas detection for high pressure gas systems • Position hand rails at all locations where there would be unguarded height, if equipment was removed for service • Position pipe work, including flanges and rodding points, so that service leaks will be caught, and not by operators! 35 Inherently Safer Design – Why Bother? Helps us to achieve safer operations, both in terms of day to day safety, and importantly ... –In avoiding low likelihood high consequence events –Through the elimination and reduction of hazards and unrevealed system vulnerabilities Reduced number of Engineered Safeguards Reduced Complexity Reduced component and vessel sizes Reduced energy consumption Inherently Safer Designs have reduced CAPEX and OPEX and are easier to operate and maintain! 36 A Case Study ... An Example of how Design without the application of ISD results in unrevealed vulnerabilities Mumbai High How the cook cut his finger ... and the platform fell into the sea ... 37 Mumbai High North (27 July 2005) 38 Mumbai High North – Background Mumbai High Field was discovered in 1974 and is located in the Arabian Sea 160 km west of the Mumbai coast The field is divided into the north and south blocks, operated by the state-owned Oil & Natural Gas Corporation (ONGC) Four platforms linked by bridges: – NA small wellhead platform (1976) – MHF residential platform (1978) – MHN processing platform (1981) – MHW additional processing platform Complex imported fluids from 11 other satellite WHPs and exported oil to shore via pipelines, as well as processing gas for gas lift operations The seven-storey high MHN platform had 5 gas export risers and 10 fluid import risers situated outside the platform jacket 39 Mumbai High North – Sequence of Events (1) Noble Charlie Yester jack-up was undertaking drilling operations in the field The Samudra Suraksha was working in the field supporting diving operations A cook onboard the Samudra cut off the tips of two fingers Monsoon conditions onshore had grounded helicopters The cook was transferred from the Samudra to the Mumbai High platform complex by crane lift for medical treatment 40 Mumbai High North – Sequence of Events (2) While approaching the platform the Samudra experienced problems with its computer-assisted azimuth thrusters and was brought in stern-first under manual control Strong swells pushed the Samudra towards the platform, causing the helideck at the rear of vessel to strike and damage one or more gas export risers – the resultant leak ignited The close proximity of other risers and lack of fire protection caused further riser failure - the fire engulfed the Samudra and heat radiation caused severe damage to the Noble Charlie Yester jack-up Emergency shutdown valves were in place at the end of the risers which were up to 12 km long - riser failure caused large amounts of gas to be uncontrollably released 41 Mumbai High North (27 July 2005) 42 Mumbai High North (27 July 2005) 43 Mumbai High North – Aftermath The seven-storey high processing Platform collapsed after around two hours, leaving only the stump of its jacket above sea level The Sumadra suffered extensive fire damage and was towed away from scene but later sank on 01 Aug 2005, about 18 km off the Mumbai coast A total of 384 personnel were on board the platform and jack-up at the time of the accident … 22 reported dead (only) Significant problems were reported with the abandonment of all the installations involved, only 2 of 8 lifeboats and 1 of 10 life rafts were launched 44 How could a better design have avoided this disaster or reduce its impact? Would it be possible to eliminate the hazard altogether? • Position risers inside jacket structure • Location of boat landing on lee side of platform • Larger separation distance between platforms • Subsea Isolation Valves to reduce hydrocarbon inventory during release • Relocation and fire proofing of risers to prevent escalation • Improved availability of evacuation means 45 Inherently Safer Design – How do we do it? Establish an ISD Culture Develop processes that support specific structured ISD events 46 Inherently Safer Design – How do we do it? Establish an ISD culture within the organisation –Driven from the top –Involvement of all technical and project personnel –Roll-out progressively – presentations, posters, pilot events –Establish processes and guidance for their use Ensure every project has planned ISD events in every phase –Including each phase of Implementation –Measure ISD uptake performance across all projects –Sustain awareness and interest ensure all new starts involved and encourage champions 47 Success or Failure of ISD – Some Factors All engineers and project personnel provided with ISD Awareness training as part of Induction Ownership - ISD is not owned by HSSE or Technical / Process Safety personnel but by All engineering and project personnel Operations personnel should be involved in all ISD workshop / study events The language of ISD should be sustained in each project, ISD features should be captured and presented in appropriate media Often “ISD design features” do not receive the credit and attention they should, or are only known amongst a few – ISD design features should be acknowledged and shared with a wider audience 48 Putting it all together ... Inherently Safer Design Residual Risk Control (Hazard & Risk Management Process) 49 Integrating ISD & Existing Safety Processes 50 AMEC Several Years On – A Summary of Findings Encourage Each Project ... To have, and to communicate, a clear systematic process Definitions and Terms of Reference shared in advance with all workshop participants and stakeholders Create an ISD Register at the earliest time and maintain through all phases Expect to identify some possibilities that will not be actionable until a future phase, register needs to keep track of these Develop and maintain an ISD culture, make ISD wins visible to the team as a whole 51 An ISD Workshop Process SET ISD GOALS IDENTIFY HAZARDS BRAINSTORM OPTIONS INITIAL REDUCTION OF OPTIONS Reject options that clearly cannot meet the goals IDENTIFY AND UNDERSTAND THE SPECIFIC HAZARDS AND RISKS OF REMAINING OPTIONS DEVELOP EACH REMAINING OPTION FOR SELECTION •Eliminate hazards •Confirm that it will be practical to manage the residual hazards SELECT / REJECT OPTION No •Meets goals? •Meets economic criteria? •Possible to manage residual risks with defined protection layers and an aim of continuous risk reduction? If multiple iterations fail to deliver a suitable outcome Final No Yes DEVELOP SELECTED OPTION •Meets goals •Minimise risks from residual hazards •Define minimum design standards/limits •Conduct risk management activities RECOMMEND DISCONTINUING DEVELOPMENT 52 ISD Goals - Examples of High Level Goals LAYOUT EXAMPLES Minimise explosion overpressure potential Minimise frequency of occurrence of explosion overpressures Minimise escalation potential from fire and explosion events Minimise vulnerability of Emergency Escape and Rescue systems to fire and explosion; including Temporary Refuge PROCESS EXAMPLES Maximise simplicity of plant Minimise hydrocarbon inventories and pressures Minimise leak potential Maximise integrity of containment envelope from internal and external loadings and hazards High level goals require to be pursued through the development of low level goals with the involvement of each and every technical discipline contributing to the project 53 An ISD Register 54 An ISD Output Bridge length set to optimise separation between Process and Well Bay areas and the Temporary Refuge Minimal inventory fuel gas for GTs Both jackets designed for a minimum Reserve Strength (RSR) of 2.5 Diverse Fire Pump locations Designed so as to minimise HP / LP interfaces 55 Strategy for Hazard Management UK HSE (OTH 96 521) Identify Hazards Understand /Assess Hazards Inherently Safer Design (ISD) Avoid Hazards Reduce Severity Reduce Likelihood Segregate / Reduce Impact Additional Engineering Controls Apply Passive Safeguards Apply Active Safeguards Apply Procedural Safeguards Risks ALARP No Yes OK 56 In Summary Attitudes to safety continue to evolve and pose engineering project stakeholders ever greater safety challenges The ‘traditional’ Hazard and Risk Management’ paradigm is imperfect and further steps are now required to meet modern challenges Inherently Safer Design (ISD) consists of straightforward principals that can be widely applied ISD when integrated with Hazard and Risk Management changes the emphasis on how safety is driven within design and planning processes This change of emphasis is not only beneficial to safety but to other project and operational parameters including cost and maintenance burden 57 That’s all for now ... ? Hindenberg