ABSAL PAUL CONTRACTING INNOVATION LAB TARGET SCHEDULE 1 Absal Paul Contracting 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 22/Sep/19 29/Sep/19 8 Installation of Coffee Counter 22/Sep/19 29/Sep/19 8 Installation of glazing and entrance doors 22/Sep/19 29/Sep/19 8 Installation of floor finishes 29/Sep/19 3/Oct/19 5 Commissioning of MEP 29/Sep/19 3/Oct/19 5 Installation of LED feature display screen 29/Sep/19 3/Oct/19 5 Completion of glazing 29/Sep/19 3/Oct/19 5 Installation of furniture 29/Sep/19 3/Oct/19 5 Page 1 of 1 7/Oct/19 Installation of lighting 6/Oct/19 8 5/Oct/19 29/Sep/19 4/Oct/19 22/Sep/19 3/Oct/19 Commence glazing installation 2/Oct/19 8 1/Oct/19 Delivery of glazing 30/Sep/19 8 29/Sep/19 29/Sep/19 29/Sep/19 22/Sep/19 28/Sep/19 22/Sep/19 054 27/Sep/19 Delivery and commencement of glazing framework 26/Sep/19 8 25/Sep/19 8 22/Sep/19 24/Sep/19 22/Sep/19 15/Sep/19 23/Sep/19 15/Sep/19 Complete high level gypsum bulkheads 22/Sep/19 Complete feature wall installation 21/Sep/19 8 20/Sep/19 22/Sep/19 19/Sep/19 15/Sep/19 18/Sep/19 Install floor boxes and complete gypsum perimeter finish 17/Sep/19 8 16/Sep/19 Commence high level gypsum bulkheads 15/Sep/19 8 15/Sep/19 14/Sep/19 15/Sep/19 8/Sep/19 13/Sep/19 8/Sep/19 12/Sep/19 Commence feature wall / LED installation 11/Sep/19 8 9/Sep/19 8 15/Sep/19 10/Sep/19 15/Sep/19 8/Sep/19 8/Sep/19 8/Sep/19 Complete MEP at high level 7/Sep/19 Alter Scaffolding and complete spraying of soffit in black 6/Sep/19 Days 5/Sep/19 Finish 4/Sep/19 Start 3/Sep/19 Sno. 2/Sep/19 Level Project No 1/Sep/19 BANK ABC REFURBISHMENT Project Name 9/9/2019