Defects Ratification cost Bulging tiles Item Description Unit Quantity Rate(RM) Amount (RM) F8 Removes and loosen the tile Fill in sand and floor patching compound in any low spot Retiled and replace damaged parts M2 0.36 52.23 52.23 RM RM Analysis of Price RM A)Removes and loosen the tile i) Labour Cost Unskilled worker RM12.70 x 1 hour x 0.36 4.57 B)Fill in sand and floor patching compound in any low spot i) Labour Cost Unskilled worker 7.31 RM20.30 x 1 hour x 0.36 C) Retiled and replace damaged parts i) Ceramic tiles 300mm x 300mm x 8mm i) Labour Cost Unskilled 30.00 worker/8hours x 1 hour RM82.80 /8 x 1 hour 10.35 40.35 52.23 Dampness Item F5 Description Unit Quantity Rate(RM) Amount (RM) Remove all debris, install new sealant, scrap the affected area, overall size 0.5m length x 0.7m width, paint the surface using undercoat and emulsion paint m² 0.35 160.51 160.51 Analysis of Price RM RM a) Remove all debris from the area i) Labour Cost Unskilled worker/8hours x 0.5 hour RM55/8 x 0.5 hour 3.44 b) Scrap the affected area i) Labour Cost Unskilled worker x 0.5hrs x 0.35m² RM4.30 x 0.5 hours x 0.35m² 0.75 c) Prepare the surface and paint one layer of undercoat paint on the surface i) Material Cost Nippon Vinilex 5400 Wall Sealer 5L ii) Labour Cost 105.00 RM Painter x 1.0hrs x 0.35m² 1.44 106.44 RM4.10 x 1.0hrs x 0.35m² d) Paint two layer of emulsion paint on the surface i) Material Cost 44.00 7 litre Colourland Paint Interior Colour Lite Emulsion Paint ii) Labour Cost Painter x 2.0 hour x 0.35m² RM8.40 x 2.0 hour x 0.35m² 5.88 49.88 160.51