Uploaded by young

STAGE FOR PJ 1.pdf

advertisement
05
Management of Design Process
KM STAGE(DEVELOPMENT ORDER)
BP STAGE(BUILDING PLAN)
TENDER STAGE
Drawing Process
15%
Drawing Process
25%
Drawing Process
40%
Payment Process
10%
Payment Process
10%
Payment Process
25%
Initial Design(Consultant)
BP Drawing (Consultant)
Tender Drawing (Consultant)
Design Feasibility & Workability Review
Specification Research
Technical Review (PMO Technical team)
Budget Review with Finance
Quantity Measurement (QS / PMO)
Tender Drawing & Final BQ
Approval Issues (Design/ Schedule/ Cost)
Coordination (Archi.+C&S+M&E+NSC)
Value Engineering(VE)
Permit (KM)
Permit (BP, GBI and etc)
Work with Consultant & Contractor
Completion
CCC STAGE
CP (Construction Phase)
Drawing Process
5%
Drawing Process
15%
Payment Process
5%
Payment Process
50%
Authority Matters (GBI/ CCC/ CPC)
Final Account
Tender Drawing (Consultant)
Reflection of Amendments
Site Work Evaluation
Work with Consultant & Contractor
Amendments according to Progress
Drawing Check and Feedback
Compiling As-Built Drawing and O&M
Shop Drawing Coordination
Variation Order (VO)
Management of Design Process
SD
[Schematic Design]
Process : 15%
ㆍInitial Design(Consultant)
ㆍDesign Feasibility &
Workability Review
ㆍBudget Review w/ Finance
ㆍApproval Issues
(Design/ Schedule/ Cost)
Completion
DD
[Design Development]
Process : 25%
ㆍImprove SD(Consultant)
ㆍSpecification Research
ㆍQuantity Measurement
ㆍCoordination w/ Consultant
ㆍPermittings
(KM, BP, GBI and Etc)
As-Built Dwg
Process : 5%
ㆍAuthority Matters
(GBI/ CCC/ CPC)
ㆍFinal Account
ㆍReflection of Amendments
ㆍWork w/ Consultant &
Contractor
ㆍDwg Check and Feedback
CD
[Construction Documents]
Process : 40%
ㆍImprove DD(Consultant)
ㆍTechnical Review and
Coordination
ㆍOrganize Bids
ㆍValue Engineering(VE)
ㆍWork w/ Consultant &
Contractor
CP
[Construction Phase]
Process : 15%
ㆍSite Work Evaluation
ㆍAny Amendments
ㆍShop Dwg Coordination
ㆍWork w/ Consultant &
Contractor
ㆍVariation Order(VO)
Download