Project Planning and Scheduling – Assignment Course Code: PMD 911 Course Instructor: Eng. Abeer Youssef Time Management 1) Solution: 1|Page Hassan Badr,17125907 Project Planning and Scheduling – Assignment Course Code: PMD 911 Course Instructor: Eng. Abeer Youssef 2) Solution: 2|Page Hassan Badr,17125907 Project Planning and Scheduling – Assignment Course Code: PMD 911 Course Instructor: Eng. Abeer Youssef 1) Given three durations for each activity (a, m, b) in weeks for the shown AOA network: 3|Page Hassan Badr,17125907 Project Planning and Scheduling – Assignment Course Code: PMD 911 Course Instructor: Eng. Abeer Youssef Solution: Activity 1-2 1-3 1-4 2-5 3-6 4-6 4-8 5-7 6-9 7-9 8-9 4|Page a 2 4 1 1 4 8 5 2 12 3 3 m 2 5 3 2 7 10 6 3 13 3 5 b 3 10 4 2 12 13 7 4 14 4 5 De=(a+4m+b)/6 2017 5.67 2.83 1.83 7.33 10.17 6 3 13 3.17 4.67 (b-a)/6 0.17 1 0.5 0.17 1.33 0.83 0.33 0.33 0.33 0.17 0.33 Hassan Badr,17125907 Project Planning and Scheduling – Assignment Course Code: PMD 911 Course Instructor: Eng. Abeer Youssef Required: 1- What is the probability of finishing the project in 26 weeks? 2- What is the probability of finishing the project in the period from 24 to 28 weeks? 3- What is the probability of reaching milestone 7 in 6 weeks? 4- What is the probability of finishing activity (4-8) in 10 weeks? 5- What is the probability of starting activity (6-9) in 11 weeks? 5|Page Hassan Badr,17125907 Project Planning and Scheduling – Assignment Course Code: PMD 911 Course Instructor: Eng. Abeer Youssef 6|Page Hassan Badr,17125907