FACTORY ACCEPTENCE TEST (FAT) Name Role/Title Owner Reviewer Approver LIST OF CHECKING ITEMS FOR TEST Sign: FAT Date: 1. 3D model(Tekla model) (i) J – Bolt model(Both Ash yard & Coal Yard) (ii) Assembled model (Both Ash & Coal Yard) (iii) Final Layout model (Both Ash & Coal Yard) (iv) Joint detail of XG (v) Joint detail of ZC (vi) 80x80x5 L angle grid (Cladding fixing detail) (vii) Plate 19 Joint detail (Coal Yard) (viii) Plate 18 Joint detail (Coal Yard) (ix) Plate 24 Joint detail (Ash yard) (x) Doubler plate joint detail (Both Ash and Coal yard) (xi) Corner assembled drawing 2. J bolt (Final product of Coal Yard) (i) Bolt total length (ii) Bolt diameter (iii) Plate dimension(LxW and thickness) (iv) Galvanized thickness 3. Assembled Structure (Ash Yard) (i) Length of total structure with angle bracing (ii) Visually inspected of welding (iii) Visually inspected the 4.5m span assembled structure 4. Assembled Structure (Coal Yard) (i) Length of total structure with angle bracing (ii) Visually inspected the Plate no 19 joint detail 5. Galvanize factory (i) Visit the galvanize factory (ii) Measured the galvanized thickness of sample LIST OF REFERENCE DOCUMENTATION Sign: Date: 1. Fabrication drawings 2. Welder Qualification Certificate 3. CE Certification 4. ISO/SGS certification 5. Measuring Tool Calibration report VALIDATION APPROVAL Approved FAT Sign : Sign : Date : Date : FAT Reject Tests to be performed may be adjusted as applicable 1. Checked the J bolt assembled 3D model for both Coal Yard and Ash yard 2. Checked the assembled 3D model of both Coal and Ash yard 3. Checked the Final layout drawing 4. Checked joint detail of XG 5. Checked joint detail of ZC 6. Checked the cladding sheet fixing detail (80x80x5 L angle grid) 7. Checked the plate 19 joint detail (Coal Yard) 8. Checked the plate 18 joint detail (Coal Yard) Summary Findings Passed Not N/A Passed 9. Checked the plate 24 joint detail (Ash Yard) 10. Checked the Doubler plate joint detail for Butt welding (Ash yard) 11. Checked the corner assembled drawing of Coal Yard 12. Checked the J bolts total length of coal yard (According Drawing no. DJL1 and MDJ2) 13.Checked the J bolt diameter of coal yard (According Drawing no. DJLI and MDJ2) 14.Checked the J bolt bottom plate dimension Length, Width and Thickness (According Drawing no. DJL1 and MDJ2) 15.Checked the galvanized thickness of J bots 16.Checked the Total length of Ash yard structure with angle bracing (According Assembled Drawing no. 01) 17.Checked the quality of welding visually (Ash Yard) 18.Visually inspected the 4.5m span assembled structure(Ash Yard) 19.Checked the Total length of Coal Yard structure with angle bracing (According Assembled Drawing no.02) 20. Visually inspected the plate no 19 joint detail 21.Visited the galvanized factory 22.Checked the galvanized thickness of sample DETAIL FINDING APPROVAL Check the Fabricated structure complies with the fabrication drawings FAT Approved Rejected Sign: Sign: Date: Date: Tests to be performed may be adjusted as applicable 1. Client requested to add washer plate to Joint 2 & 4 before visiting the factory. After visiting the factory checked that plate location and related joint detail from the Tekla model. N/A Remark Approved 2. Client requested to add extra 100x100x6 angle iron for Ash yard structure. After coming for factory visit checked that detail of Tekla model and fabricated structure. N/A Remark Approved 3. Client requested to change the double angle joint detail for both Coal and Ash yard instead of welding use the nut and bolt joint for same arrangement. N/A Remark Approved Additional remarks 4. …………………………………………………………………………………............. Approved 5. …………………………………………………………………………………………… Approved 6. …………………………………………………………………………………………… Approved 7. …………………………………………………………………………………………… Approved 8. …………………………………………………………………………………………… Approved 9. …………………………………………………………………………………………… Approved 10. ………………………………………………………………………………………….. Approved FAT PUNCH LIST Any incomplete works or nonconformities shall be recorded on the FAT punch list and categorized as follows. (a) Ongoing rectification during FAT (b) FAT to be repeated (c) Modifications to be made after FAT (d) Remaining work to be rectified i.e. at site Item 1 2 3 4 5 6 7 Description Responsible Type Complete