EMM 5618 MANUFACTURING PROJECT MANAGEMENT LECTURER : ASSOC.PROF. IR. DR. NAWAL ASWAN ABDUL JALIL Title: Supply, Delivery, Installation, Testing & Commissioning of Air- Cond & Mechanical Services for MEDICAL CITY HOSPITAL. 1234- Thaer Zuhair AbdulRazaq Wajdi A. Noor Zaid Mohammed Abdulsattar Mohamed Ibrahim . GS45260 GS47683 GS45291 GS44108 PRESENTATION OUTLINE • INTRODUCTION • WBS & Activity • Problem statement: – Normal condition – Limited resources. – Reduce the duration. INTRODUCTION • Company name: NOOR AL-HUDA COMPANY • Location: Iraq- Baghdad • Objectives: – To complete project within duration given (18 month). – To define duration of project based on current company situation which are resources constrain. – To define the possibility of reducing project duration as per request by client. • Start date: 2/1/2012 • Duration given to complete: 18Months • Request to complete the project early- 16Months Project Selection Project (A) Project (B) Project (C) Construct new PHCC Rehabilitation woeks for A/C system for Medical Ibn Al Haitham hospital City Hospital Project name Project location Mousle Basrah Baghdad Required rate of return (k) 20% 20% 20% Period (t) 18 Months 18 Months 18 Months Initial investment (I) USD 3000000 USD 2250000 USD 1120000 Total profits USD 600000 USD 450000 USD 224000 As we see above, the required rate of return and period of work are same for the three project, therefore the company managers decided to select project (C) for the reasons below: (1) Required skilled workers are already under duty. (2) Financial liquidity for the company is not good. (3) The total profits of project (C) is commensurate with the total investment. (4) The company executes many similar projects of project (C). WBS 1. AC & MV FOR MCC(100%) USD 1,120,000 1.1 AIR COND (60%) USD 6,72,000 1.1.1 DESIGN (5%) USD 56,000 1.2 MECH VENT (40%) USD 448,000 1.1.2 SELECTION & CONFIRMATION (55%) USD 616,000 1.2.1 DESIGN (5%) USD 56,000 1.2.2 SELECTION & CONFIRMATION (35%) USD 392,000 WBS [Cont from 1.1.2] 1.1.2 SELECTION & CONFIRMATION (55%) USD 616,000 1.1.2.1 CASSETTE (5%) USD 56,000 1.1.2.2 FAN COIL (13%) USD 145,600 1.1.2.3 AHU (15%) USD 168,000 1.1.2.4 AIR COOLED CHILLER (9%) USD 100,800 1.1.2.5 PUMP (4%) USD 44,800 1.1.2.6 COOLING TOWER (9%) USD 100,800 WBS [Cont from 1.2.2] 1.2.2 SELECTION & CONFIRMATION (35%) USD 392,000 1.2.2.1 EXHAUST AIR FAN (19%) USD 212,800 1.2.2.2 FRESH AIR (16%) USD 179,200 OBS Activity 1-NORMAL CONDITION • The project network is the tool used for planning, scheduling, and monitoring project progress. • The network is developed from the information collected for the WBS and is a graphic flow chart of the project job plan. • The network is the framework for the project information system that will be used by the project managers to make decisions concerning project time, cost, and performance •Critical path analysis used to schedule the activities in a project. •Activity in Critical Path cannot be delay because any delay of an activity in critical path will means that the whole project will be delay. •C.P.= 1,3,4,6,12,14,19,17,26,27,29,30,32,33,34.= 363 days •Critical path analysis used to schedule the activities in a project. •Activity in Critical Path cannot be delay because any delay of an activity in critical path will means that the whole project will be delay. •C.P.= 1,3,4,6,12,14,19,17,26,27,29,30,32,33,34.= 363 days •Critical path analysis used to schedule the activities in a project. •Activity in Critical Path cannot be delay because any delay of an activity in critical path will means that the whole project will be delay. •C.P.= 1,3,4,6,12,14,19,17,26,27,29,30,32,33,34.= 363 days •Critical path analysis used to schedule the activities in a project. •Activity in Critical Path cannot be delay because any delay of an activity in critical path will means that the whole project will be delay. •C.P.= 1,3,4,6,12,14,19,17,26,27,29,30,32,33,34.= 363 days LIMITED RESOURCES RESOURCES ENGINEER DRAFTER AC ELEC PLUMBER ADMIN SUPERVISOR NORMAL CONDITION 2 1 15 9 10 1 8 LIMITED RESOURCES 2 1 12 8 8 1 6 Task Name Letter of award Priliminaries Planning, design and shop drawing preparation Submission to client approval Bill of Quantity Purchasing Delivery- Chillers Delivery-Pumps Delivery-Cooling Tower Delivery-Air Handling Unit and Fan Coil Unit Delivery-Mechanical Ventilation Fan Site survey and setting out Duct work Pipe work Electrical work Ducting insulation Pipe jacketing Installation of grille and diffuser Installation of valve and fitting Installation of control panel and main switch board Installation of AHU & FCU Installation of MV Fan Installation of Pump Installation of Chillers Installation of Cooling Tower T&C-Pipe pressure test T&C-Water balancing T&C- Air balancing Major equipment testing Bomba inspection As-built drawing preparation Operation and manual preparation Handing over inspection with end user Finish Milestone Free Slack Free Slack (Resources constrain) (Normal condition) 0 days 0 days 0 days 0 days 9 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 98.2 days 133.2 days 138.2 days 153.2 days 123.2 days 116.2 days 0 days 0 days 68.2 days 0 days 0 days 3 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 9 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 90 days 155 days 155 days 210 days 150 days 180 days 0 days 0 days 60 days 0 days 0 days 3 days 0 days 0 days 0 days Due to resources constrain. Normal condition Limited resources Normal condition Limited resources Critical path : normal condition = limited resources C.P.= 1,3,4,6,12,14,19,17,26,27,29,30,32,33,34.= 371.2 days CRASHING Cost-Duration Information Activity TIME Slope Normal Max .Crash A1 Letter of Award 1 0 A2 Preliminaries 7 2 USD2500 /day 30 0 USD3000 /week A3 Planning, design and shop drawing preparation - A4 Submission to client approval 14 0 USD3000 /week A5 Bill of Quantity 5 0 USD2500 /day A6 Purchasing 5 2 USD1250 /day A7 Chillers 90 0 USD3750 /week A8 Pumps 30 0 USD3750 /week A9 Cooling Tower 60 0 USD3750 /week A10 Air Handling Unit and Fan Coil Unit 60 0 USD3750 /week A11 Mechanical Ventilation Fan 60 0 USD3750 /week A12 Site survey and setting out 5 2 USD2500 /day A13 Duct work 120 0 USD4250 /week A14 Pipe work 120 0 USD4250 /week A15 Electrical work 120 0 USD4250 /week A16 Ducting insulation 30 0 USD4250 /week Cost-Duration Information Summary Cost by Duration Duration COST Direct Indirect Total 363 USD779258.75 USD344250 USD1123508.75 362 USD780533.75 USD342125 USD1122658.75 361 USD781808.75 USD340000 USD1121808.75 360 USD783083.75 USD337875 USD1120958.75 359 USD784358.75 USD335750 USD1120108.75 358 USD785633.75 USD333635 USD1119258.75 357 USD786908.75 USD331500 USD1118408.75 356 USD788183.75 USD329375 USD1117558.75 355 USD789458.75 USD327350 USD1116708.75 354 USD790733.75 USD325125 USD1115858.75 353 USD792008.75 USD323000 USD1115008.75 352 USD793283.75 USD320875 USD1114158.75 351 USD 795408.75 USD 318750 USD 1114158.75 350 USD 797533.75 USD 316625 USD 1114158.75 342 USD 800508.75 USD 299625 USD 1100133.75 334 USD 803483.75 USD282625 USD 1086108.75 333 USD 807733.75 USD 280500 USD 1088233.75 332 USD 811983.75 USD 278375 USD 1090358.75 331 USD 816233.75 USD 276250 USD 1092483.75 330 USD 820483.75 USD 274125 USD 1094608.75 DIRECT COST + INDIRECT COST = TOTAL COST Project Cost-Duration Graph 1200000 1000000 800000 600000 400000 200000 0 325 330 335 Direct cost 340 345 Indirect cost 350 Total cost 355 360 365 CONCLUSION - Within 18 months which is on June 2013, with current condition of NOOR AL-HUDA COMPANY resources, they can achieve the expected time. - But due to request of client that they want the project to be complete on April 2013 (16 months), only by crashing some activity will fulfill client request. - outsourcing for certain work in the project. the advantages of outsourcing is company can reduce cost, besides overhead cost also can be eliminate since the company no longer has to internally maintain the contract services. - By outsourcing, the company has flexibility, where they no longer constrained by their own resources but can pursue a wide range of project combining their resources with talents of other companies. This will give advantages to small company like NOOR AL-HUDA COMPANY to go global with foreign partners.