IDKK-AT-BYSCH-K00793-0001 Rev.B Schedule - October Report

advertisement
KEDUNG KERIS PROJECT
PT MEINDO ELANG INDAH
ID
Task Name
1
PROJECT SPAN
PROJECT SCHEDULE
LEAK DETECTION SENSING SYSTEM (LDSS)
Duration
Actual
Duration
% Complete
Start
Finish
99 days
22.12 days
22%
Wed 26‐09‐18 Mon 11‐02‐19
October 2018
November 2018
December 2018
January 2019
February 2019
20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20
2
Letter of Award
0 days
0 days
100%
Wed 26‐09‐18 Wed 26‐09‐18
3
Submission of Key Documents
1 day
1 day
100%
Fri 05‐10‐18
Fri 05‐10‐18
4
Milestone 1: 10%
0 days
0 days
100%
Fri 05‐10‐18
Fri 05‐10‐18
5
Kickoff Meeting
1 day
1 day
100%
Thu 11‐10‐18
Thu 11‐10‐18
6
Engineering (Critical Documents)
59 days
21.29 days
36%
Fri 05‐10‐18
Wed 26‐12‐18
0 days
0%
7
Issued for Approval
8
System Architecture
1 wk
1 wk
100%
Thu 11‐10‐18
Wed 17‐10‐18
9
Functional Design Specification
4 wks
0 wks
0%
Thu 08‐11‐18
Wed 05‐12‐18
10
General Arrangement Drawing
2 wks
2 wks
100%
Thu 11‐10‐18
Wed 24‐10‐18
11
Electrical Diagram
1 wk
1 wk
100%
Thu 11‐10‐18
Wed 17‐10‐18
12
Termination Diagram
1 wk
1 wk
100%
Thu 11‐10‐18
Wed 17‐10‐18
13
Handheld Datasheet
1 wk
1 wk
100%
Fri 05‐10‐18
Thu 11‐10‐18
14
Power Consumption List
1 wk
1 wk
100%
Fri 26‐10‐18
Thu 01‐11‐18
15
Issued for Construction
0 days
0%
16
System Architecture
1 wk
0 wks
0%
Thu 25‐10‐18
Wed 31‐10‐18
17
Functional Design Specification
1 wk
0 wks
0%
Thu 20‐12‐18
Wed 26‐12‐18
18
General Arrangement Drawing
1 wk
0 wks
0%
Thu 01‐11‐18
Wed 07‐11‐18
19
Electrical Diagram
1 wk
0 wks
0%
Thu 25‐10‐18
Wed 31‐10‐18
20
Termination Diagram
1 wk
0 wks
0%
Thu 25‐10‐18
Wed 31‐10‐18
21
FO Enclosure Datasheet
1 wk
0 wks
0%
Fri 19‐10‐18
Thu 25‐10‐18
22
Handheld Datasheet
1 wk
0 wks
0%
Fri 19‐10‐18
Thu 25‐10‐18
23
Power Consumption List
1 wk
0 wks
0%
Fri 09‐11‐18
Thu 15‐11‐18
99 days
13.66 days
14%
Wed 26‐09‐18 Mon 11‐02‐19
24
Procurement
25
FO Enclosure
2 wks
0 wks
0%
Fri 26‐10‐18
Thu 08‐11‐18
26
Handheld
2 wks
0 wks
0%
Fri 26‐10‐18
Thu 08‐11‐18
27
Cabinet & Accessories
8 wks
0 wks
0%
Thu 01‐11‐18
Wed 26‐12‐18
28
OptaSense Equipment
16 wks
4.8 wks
30%
Wed 26‐09‐18 Tue 15‐01‐19
29
FAT, Winfrith UK
1 day
0 days
0%
Wed 16‐01‐19 Wed 16‐01‐19
30
Punchlist Clearance & Packaging
1 wk
0 wks
0%
Thu 17‐01‐19
Wed 23‐01‐19
31
Delivery of OptaSense Equipment to KL 1 wk
0 wks
0%
Thu 24‐01‐19
Wed 30‐01‐19
32
Milestone 2: 15%
0 days
0 days
0%
Wed 30‐01‐19 Wed 30‐01‐19
33
Cabinet Assembly
4 wks
0 wks
0%
Thu 10‐01‐19
Wed 06‐02‐19
34
Cabinet Inspection, KL
1 day
0 days
0%
Thu 07‐02‐19
Thu 07‐02‐19
35
Packaging and Delivery, EXW‐KL
2 days
0 days
0%
Fri 08‐02‐19
Mon 11‐02‐19
36
Milestone 3: 55%
0 days
0 days
0%
Mon 11‐02‐19 Mon 11‐02‐19
PT ADVANCED TECHNOLOGY SOLUTION
IDKK-AT-BYSCH-K00793-0001
REV. B, ISSUED FOR INFORMATION
PAGE 1 OF 1
26-09
05-10
30-01
11-02
17 OCT 2018