MEDIA RELEASE: Friday, April 28, 2006, 4:30 p.m. REGIONAL MUNICIPALITY OF WATERLOO PLANNING AND WORKS COMMITTEE AGENDA Tuesday, May 2, 2006 9:00 A.M. Council Chamber 2nd Floor, Regional Administration Building 150 Frederick Street, Kitchener, Ontario 1. DECLARATIONS OF PECUNIARY INTEREST UNDER THE MUNICIPAL CONFLICT OF INTEREST ACT 2. DELEGATIONS a) Rosemary Kittel-McCormick, St. Agatha re: Gerber Road 3. REPORTS – TRANSPORTATION AND ENVIRONMENTAL SERVICES DESIGN AND CONSTRUCTION a) E-06-040.1, Ira Needles Boulevard, Stage 3, Victoria Street to South of Erb Street, Review of Two-Lane Cross Section Alternatives that will Facilitate Future Road Widening to Four Lanes 1 b) E-06-051, Gerber Road Improvements, Nafziger Road to Moser-Young Road, Wellesley and Wilmot Townships - Approval of Roadway Improvements and Approval of Speed Limit Changes 14 TRANSPORTATION c) E-06-054, Roundabout at the Intersection of Regional Road #17 (Ament Line) and Regional Road #10 (Herrgott Road), in the Township of Wellesley 29 d) E-06-057, Roundabout Education Program 31 e) E-06-058, Ontario’s Millennium Partnership Funding Agreement for the Region of Waterloo International Airport Servicing and Land Development Project 38 f) CR-RS-06-025, Disposal of Easement Interest, Nafziger Road, Township of Wilmot 41 g) CR-RS-06-027, Authorization to Expropriate Permanent Easements (2nd Report) Along Shantz Station Road, Township of Woolwich, Relating to Region of Waterloo International Airport Requirements 45 WASTE MANAGEMENT h) E-05-103.1, Food Waste Organics Pilot Project Update Document Number: 266174 Document Name: P&W AGENDA - MAY 2 2006 49 Agenda -2- May 2, 2006 i) E-06-047, Waste Management Education Program 58 j) E-06-056, Waterloo Landfill Monitoring Program Update 61 k) CR-RS-06-026, Hydro Corridor Relocation, Waterloo Landfill Site 65 WATER SERVICES l) E-06-039, Water Supply Update 68 m) E-06-033, Consultant Selection for the Water Supply Strategy Update 75 TRANSIT SERVICES n) E-05-099.3, GRT Fleet Maintenance Update 80 JOINT REPORT o) P-06-054, Housing Incentives and Funding Resource Guide (Distributed Separately) REPORTS – PLANNING, HOUSING AND COMMUNITY SERVICES COMMUNITY PLANNING p) P-06-041, Initiation of an Amendment to the Regional Official Policies Plan to Consider Designation and Protection of Dumfries Conservation Areas 136 TRANSPORTATION PLANNING q) P-06-056, South Kitchener Transportation Corridor Study – Preferred Alternative and Upcoming Public Meeting 4. INFORMATION/CORRESPONDENCE 5. OTHER BUSINESS a) Council Enquiries and Requests for Information Tracking List 6. NEXT MEETING – May 16, 2006 Document Number: 266174 Document Name: P&W AGENDA - MAY 2 2006 141 188 Agenda 7. -3- May 2, 2006 CLOSED SESSION (motion required) THAT a closed meeting of Planning & Works Committee be held on Tuesday, May 2, 2006, following the regular meeting of the Planning and Works Committee, in accordance with Section 239 of the Municipal Act, 2001, for the purposes of considering the following subject matters: i) 8. A proposed or pending acquisition of land for municipal purposes ADJOURN Document Number: 266174 Document Name: P&W AGENDA - MAY 2 2006 Agenda -4- May 2, 2006 NEXT MEETINGS Date Time Description Location Planning and Works Committee Tues., May 9, 2006 7:00 P.M. Public Meeting Re: South Kitchener Transportation Corridor Study. Council Chamber 2nd Floor, Regional Administration Building 150 Frederick Street Kitchener, Ontario Tues., May 16, 2006 8:30 A.M. Planning and Works Committee 11:00 A.M. Environmental Education Centre – Ribbon-Cutting Waterloo Region Emergency Services Training & Research Complex (WRESTRC) 1001 Erb’s Road Waterloo, Ontario 9:00 A.M. Planning and Works Committee Tues., June 6, 2006 Council Chamber 2nd Floor, Regional Administration Building 150 Frederick Street Kitchener, Ontario Planning, Housing and Community Services Transportation and Environmental Services Thurs., May 11, 2006 7:00 P.M. – 9:00 P.M. Open House Re: Heidelberg Watermain Replacement Project New Apostolic Church 2891 Lobsinger Line Heidelberg, Ontario Wed., May 24, 2006 3:00 P.M. – 5:00 P.M. Water Efficiency Advisory Committee Room 218 2nd Floor, Regional Administration Building 150 Frederick Street Kitchener, Ontario Wed., May 24, 2006 4:30 P.M. – 8:30 P.M. Open House Re: Middleton Class Environmental Assessment Middleton Pumping Station 50 Middleton Street Cambridge, Ontario Document Number: 266174 Document Name: P&W AGENDA - MAY 2 2006 Report: E-06-040.1 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Design and Construction TO: Chair Jim Wideman and Members of Regional Council DATE: May 2, 2006 SUBJECT: IRA NEEDLES BOULEVARD, STAGE 3, VICTORIA STREET TO SOUTH OF ERB STREET, REVIEW OF TWO-LANE CROSS SECTION ALTERNATIVES THAT WILL FACILITATE FUTURE ROAD WIDENING TO FOUR LANES FILE CODE: C04-30, 5349 RECOMMENDATION: THAT the Regional Municipality of Waterloo maintain the current cross-section design, identified as Option 1 in Report E-06-040.1 and described as initially constructing two paved inside lanes on a two lane granular base with concrete curb and gutter and 1.0 metre wide concrete boulevard edging for the proposed construction of Ira Needles Boulevard, Stage 3, from Victoria Street to south of Erb Street. SUMMARY: Regional Council at the March 1, 2006 Council Meeting approved the initial two-lane construction of Ira Needles Boulevard Stage 2 (Highway 7/8 to Victoria Street). In addition, staff was directed to review twolane cross-section design options that could provide increased flexibility and reduced costs for the future widening to four lanes for Stage 3 (Victoria Street to south of Erb Street). Staff assessed five alternative cross-section designs and (based on an assessment of initial cost savings, future maintenance and widening costs and potential delays associated with re-design) has concluded the best approach for Stage 3 is to maintain the current cross-section as two paved inside lanes on a two-lane granular base with concrete curb and gutter and 1.0 metre concrete boulevard edging (Option 1). It should also be noted that based on current permitted zoning, widening of Stage 3 to four lanes is not required until 2022. Since the proposed initial two lane road is expected to last 17 years before any pavement rehabilitation is required, implementation of Option 1 (Current Design) will provide a stable maintenance-free road platform that will serve the community well in both the short and long term. REPORT: 1. Background Regional Council at the March 1, 2006 Council Meeting approved the initial two-lane construction of Ira Needles Boulevard Stage 2 (Highway 7/8 to Victoria Street). Regional Council at the March 1, 2006 Council Meeting also directed staff to review two-lane cross-section design options (prior to issuing the Stage 3 contract) that could provide increased flexibility and allow the number of lanes for Stage 3 of Ira Needles Boulevard (Victoria Street to south of Erb Street) to be more easily and cost effectively increased from two to four lanes in the future. The tender for Stage 3 is currently scheduled for advertisement in July/August 2006 with construction commencing in September of 2006 and completion in the Autumn of 2007. The agreement to purchase the last remaining property required to complete Stage 3 from the developers on the west side of Ira Needles between the GEXR tracks northerly to West Hill Drive was signed and returned by the developer on March 22, 2006 and the Agreement is set to close on April 28, 2006. DOCS #: 275112-v9 Page 1 of 13 May 2, 2006 Report: E-06-040.1 2. Alternative Two-Lane Cross-Section Designs for Stage 3 of Ira Needles Boulevard Table 1 summarizes five two-lane cross-section design options investigated by staff to explore the feasibility of providing increased flexibility and reduced costs for the future widening of Ira Needles Boulevard Stage 3 from two to four lanes. It should be noted that according to the latest traffic projections based on the current permitted zoning, Ira Needles Boulevard will not need to be widened to four lanes until 2022. Staff, however, wished to consider the potential for an earlier-than-2022-need for the four-laning of Ira Needles Boulevard when assessing the advantages and disadvantages of the five two-lane cross-section design options. Therefore, the assessment of each option was based on two time frames, widening to four lanes in the short term (in 2011) and in the long term (in 2022). DOCS #275112-v9 Page 2 of 13 May 2, 2006 Report: E-06-040.1 Table 1: Alternative Two-Lane Cross Section Designs for Stage 3 of Ira Needles Boulevard WIDENING OCCURS IN 2022 ADVANTAGES DISADVANTAGES OPTION WIDENING OCCURS BEFORE 2011 ADVANTAGES DISADVANTAGES Option 1 - Current Design • • Initially construct 2 paved inside lanes on a 2 lane granular base with 1.0 m wide concrete boulevard edging and storm sewers Future widening to four lanes would occur on the outsides and would involve granulars, curb and gutter and concrete boulevard edging Option 2 • Initially construct 2-paved inside lanes on 2 lane granular base. Reduce width of concrete boulevard edging to 0.5 m. • Future widening to four lanes would occur on the outsides and would involve granulars, curb and gutter and concrete boulevard edging. • Concrete boulevard edging could be substituted with asphalt to further save costs DOCS #: 275112-v9 • • • • • • • • • Initial 2 lanes would open in 2007 Easily widened in future No further delays for initial Stage 3 construction No change to current designs or specifications • Initial two lanes would open in 2007 Initial Net Savings of approximately $60,000 (Concrete boulevard edging) or $110,000 (asphalt boulevard edging) Easily widened in future No further delays to Stage 3 initial construction Minimal change to current drawings, quantities and specifications. • None • • • • • Reduced boulevard edging would increase potential for increased maintenance costs over Option 1 due to smaller platform for stalled cars. These increased maintenance costs would affect initial net savings of $60,000 ($110,000) This option would result in less space for vehicles to pull over to allow emergency vehicles through. Concrete boulevard edging could be substituted with asphalt to save additional costs ($50,000) but a high quality asphalt edging is very difficult to construct and leads to early failure requiring significant patching and maintenance Initial two lanes would open in 2007 Easily widened in future No further delays for initial Stage 3 construction • No change to current designs or specifications • Initial two lanes would open in 2007. Initial Net Savings of approximately $60,000 (concrete boulevard edging) and $110,000 (asphalt boulevard edging) Easily widened in future No further delays to Stage 3 initial construction Minimal change to current drawings, quantities and specifications • • • • • Future throw away costs for curb and gutter, boulevard edging, catchbasin relocation ($500,000) • Future throw away costs for curb and gutter, concrete boulevard edging, catchbasin relocation ($440,000) OR Future throw away cost of $390,000 (If asphalt boulevard edging) Reduced boulevard edging would increase potential for increased maintenance costs over Option 1 due to smaller platform for stalled cars. This option would result in less space for vehicles to pull over to allow emergency vehicles through. • • • Concrete boulevard edging could be substituted with asphalt to save additional costs ($50,000) but a high quality asphalt edging is very difficult to construct and leads to early failure requiring significant patching and maintenance Page 3 of 13 May 2, 2006 Report: E-06-040.1 WIDENING OCCURS IN 2022 ADVANTAGES DISADVANTAGES OPTION WIDENING OCCURS BEFORE 2011 ADVANTAGES DISADVANTAGES Option 3a • • • Initially construct two inside paved lanes on a two-lane granular base. Delete curb & gutter and replace with narrow paved shoulder and shallow swales, instead of full ditches. Future widening to four lanes along the outsides and includes granulars, curb and gutter and concrete boulevard edging. DOCS #275112-v9 • • Initial Net Savings by not initially constructing curb and gutter and boulevard edging of approx. $150,000; however would likely result in increased future costs due to premature road failure. • • Would require re-design resulting in a delay of the initial construction of Stage 3 by 2-3 months minimum to revise all plans and crosssections Initial two lanes may not open until 2008 due to substantial re-design required • Design would lead to premature failure of road platform due to inadequate pavement drainage; substantial reconstruction cost would occur before 2022 at an estimated cost of $5 million plus. • Substantial increased maintenance costs – edges breaking and swale maintenance Easily widened in the future (minimal removals) • • Initial Net Savings by not initially constructing curb and gutter and boulevard edging of approx. $150,000. Easily widened in the future (minimal removals) • • Would require re-design resulting in a delay of the initial construction of Stage 3 by 2-3 months minimum to revise all plans and cross-sections Initial two lanes may not open until 2008 due to substantial re-design required • If road is not widened before 2011, it will require installation of curb and gutter to avoid pavement failure; and additional throwaway work (for creating swales, placing asphalt aprons at catchbasins, readjusting catchbasins and replacing frames and grates) whose total impact would be future throwaway cost of $1,500,000 plus • Design may lead to some premature failure of road platform due to inadequate pavement drainage. • Increased maintenance costs. Page 4 of 13 May 2, 2006 Report: E-06-040.1 WIDENING OCCURS IN 2022 ADVANTAGES DISADVANTAGES OPTION WIDENING OCCURS BEFORE 2011 ADVANTAGES DISADVANTAGES Option 3b • • • Initially construct two inside paved lanes on a two-lane granular base. Delete curb & gutter and replace with narrow, paved shoulder and full ditches Future widening to four lanes would occur along the outsides and includes granulars, curb and gutter and concrete boulevard edging. • Initial Net Savings by not initially constructing curb and gutter and boulevard edging of approx. $50,000; however would result in increased maintenance costs due to asphalt edges breaking • Easily widened in the future (minimal removals) • Design would allow gravel road base to drain properly. • Would require re-design resulting in a delay of the initial construction of Stage 3 by 2-3 months minimum to revise all plans and crosssections • Initial 2 lanes may not open until 2008 due to substantial re-design required Unsightly design in an urban environment • • • • Substantial increased maintenance costs would offset initial net savings of $50,000 – edges breaking and ditch maintenance Guide rails at increased cost may be required for roadside protection. There would be insufficient space in portions of the right of way for multi-use trail in some sections because of space needed for ditch. • Initial Net Savings by not initially constructing curb and gutter and boulevard edging of approx. $50,000; however would likely result in increased maintenance costs due to asphalt edges breaking • Easily widened in the future (minimal removals) • Design would allow road base to drain properly. • Would require re-design resulting in a delay of the initial construction of Stage 3 by 2-3 months minimum to revise all plans and cross-sections • Initial 2 lanes may not open until 2008 due to re-design required This option would involve throwaway work of $800,000 in the near term because it includes excavating temporary ditches and placing temporary culverts • • • • • DOCS #275112-v9 Unsightly design in an urban environment Increased maintenance costs for ditches and asphalt edges breaking Guardrails at increased cost may be required for roadside protection. There would be insufficient space in portions of the right of way for multi-use trail in some sections because of space for ditch. Page 5 of 13 May 2, 2006 Report: E-06-040.1 WIDENING OCCURS IN 2022 ADVANTAGES DISADVANTAGES OPTION WIDENING OCCURS BEFORE 2011 ADVANTAGES DISADVANTAGES Option 4 • • Initially construct two paved outside lanes on a 2 lane granular base. Future widening to four lanes would be done in the median. • • Initial Net Savings of approx $60,000. Outside curbs and catchbasins in their ultimate location and would not need to be removed for future widening. • • • • DOCS #275112-v9 Would require re-design resulting in a delay of the initial construction of Stage 3 by 2-3 months minimum to revise all plans and crosssections Initial two lanes may not open until 2008 due to redesign required Future widening in the median would be cumbersome and more disruptive to traffic and will likely increase future construction costs by more than the initial cost savings. ($550,000 plus premium) Operational safety concerns for this option due to potential weaving of traffic at the rail bridge and intersections. • • Initial Net Savings of approx $60,000. Outside curbs and catchbasins in their ultimate location and would not need to be removed for future widening. • • • • Would require re-design resulting in a delay of the initial construction of Stage 3 by 2-3 months minimum to revise all plans and cross-sections Initial two lanes may not open until 2008 due to substantial redesign required Future widening in the median would be cumbersome and more disruptive to traffic and will likely increase future construction costs by more than the initial cost savings. ($550,000 premium) Operational safety concerns for this option due to potential weaving of traffic at the rail bridge and intersections. Page 6 of 13 May 2, 2006 Report: E-06-040.1 WIDENING OCCURS IN 2022 ADVANTAGES DISADVANTAGES OPTION WIDENING OCCURS BEFORE 2011 ADVANTAGES DISADVANTAGES Option 5 • • Initially construct 2 paved inside lanes on a 4 lane granular base with catchbasin installed at ultimate edge of future 4 lane road. Future widening to four lanes would occur along the outsides and would include curb and gutter and concrete and boulevard edging. • Ultimate road platform, granulars and catchbasins are initially placed in ultimate location. • Avoids future throwaway costs for curb and gutter subdrains and concrete edging of approximately $500,000 Can be widened easily in the future by paving granular shoulder. • • • • • • • Would require re-design resulting in a delay of the initial construction of Stage 3 by 2-3 months minimum to revise all plans and crosssections Initial two lanes may not open until 2008 due to substantial redesign required Initial Net Cost increase of $750,000 is needed for early construction of the extra road base This cross section on other projects has led to premature road failure due to poor drainage of the granular road base and requires complete reconstruction much sooner (at an estimated cost of 5 million dollars plus) Catchbasins would require future readjustment. Increased maintenance costs. • Ultimate road platform, granulars and catchbasins are initially placed in ultimate location. • Would require re-design resulting in a delay of the initial construction of Stage 3 by 2-3 months minimum to revise all plans and cross-sections • Avoids future throwaway costs for curb and gutter subdrains and concrete edging of approximately $500,000 • Initial two lanes may not open until 2008 due to substantial redesign required This cross section on other projects has led to premature road failure due to poor drainage of the granular road base; and potential for increased granular rehabilitation costs in the amount of approximately $350,000 can be expected in the near term. Catchbasins would require future readjustment. • • Can be widened easily in the future by paving granular shoulder. • • Increased maintenance costs. See Appendix B for a sketch of each above Option DOCS #275112-v9 Page 7 of 13 May 2, 2006 Report: E-06-040.1 3. Risk Analysis of Alternate Cross-Sections Upon comparing the advantages and disadvantages of each of the five alternative two-lane cross-sections for Stage 3, one concludes that deciding which initial construction option is “best” to implement is a risk management exercise heavily dependent upon whether one believes Stage 3 will be widened to four lanes in the near term (say by 2011) or whether it will be widened in the long term (say by 2022). If one believes Stage 3 will be widened to 4-lanes by 2011, then Option 3a (Initially constructing 2 Inside Lanes with Shallow Swales for Drainage) would appear to be the “best” option, because it would save an estimated $150,000 of initial construction costs; however, the risk of initially implementing Option 3a is that if the timing assumption for future widening to four lanes proves to be wrong and this future widening occurs after 2011, then the Region runs the substantial risk of incurring significant additional costs in excess of $5,000,000 to fully reconstruct the initial 2 lanes of road because of premature road failure caused by inadequate subgrade drainage. Based on this risk analysis, one concludes for Stage 3 that the $5,000,000 potential cost of reconstructing a prematurely-failed road subgrade in the near future far exceeds any $150,000 benefit of initial cost-savings resulting from implementing Option 3a for the initial construction of Stage 3. If one believes Stage 3 will not be widened to 4 lanes before 2022, then the current design, Option 1 (Initially constructing 2 Inside Lanes with Storm Sewers and Curb and Gutter) would be the “best” Option because it fully avoids the potential $5,000,000 risk of reconstructing a prematurely-failed road grade in the near future. The only downside of implementing Option 1 for the initial 2 lane construction of Stage 3 is that it would involve premature “throw-away” costs of approximately $500,000 (for curb and gutter, boulevard edging and catchbasin relocations) if the widening to four lanes were to occur by 2011. Based on this risk analysis, one concludes for Stage 3 that the benefit of avoiding the $5,000,000 risk of reconstructing a prematurely-failed road subgrade in the near future far exceeds the near term benefit of avoiding $500,000 of premature “throw-away” costs should the widening to four lanes occur by 2011. CONCLUSIONS AND RECOMMENDATIONS Based on a thorough cost-benefit analysis and a thorough risk analysis of the five alternative two-lane cross-sections for Stage 3, staff has concluded that the best approach is to maintain the current cross-section design, Option 1 (i.e. build two inside paved lanes on a two-lane granular base with curb and gutter and 1.0 m concrete boulevard edging). Although some of the other crosssection options would result in some minor initial cost savings, Option 1 would result in an overall lower life-cycle cost than the other options due to lower maintenance and reconstruction costs. In addition, any initial cost savings (up to $150,000 maximum) identified with the other options are considered negligible considering the overall $10 million construction cost of Stage 3, not to mention the possible $5,000,000 premature reconstruction risk associated with some of the other options. Implementing the existing cross-section design would also avoid the lengthy delays for re-design (up to four months) associated with some of the other options and would allow the road to open in 2007. Some of the other options may result in a delay of the road opening until 2008 due to the extensive redesign required and resubmission of revised plans to approval agencies for their review. It should be noted that during the preliminary design of the Needles Boulevard corridor and the current detailed design of Stage 3, staff thoroughly reviewed various design options and recommended a design that is robust and can be easily widened in the future. All the intersections (roundabouts) have been designed for the ultimate four lane road and would only require pavement re-striping at the roundabout approaches (i.e. no future widening at the intersections will be required); proposed development accesses have been incorporated in the design and will be constructed with left and right turn lanes incorporated prior to or simultaneously with development DOCS #: 275112-v9 Page 8 of 13 May 2, 2006 Report: E-06-040.1 projects. The GEXR railway overpass structure has been designed to locate the full abutments in their ultimate 4 lane location so that future widening from a two to four-lane bridge will only require the installation of additional pre-cast girders and deck expansion. All grading for the ultimate four lane embankment approaches for the railway overpass is included in the initial construction of Stage 3. Lastly, in the future when warranted, the road can be easily widened by removing the curb and boulevard edging and extending catchbasins, granulars and paving easily while maintaining 2 way traffic. CORPORATE STRATEGIC PLAN: Implementation of the Ira Needles Boulevard project is in harmony with Focus Areas 1 and 4 of the Corporate Strategic Plan in that it will ensure that adequate infrastructure capacity is in place to meet planned growth and it will improve the Regional Roads Network. FINANCIAL IMPLICATIONS: The 2006 Transportation Capital Budget includes a total of $10.8 million in 2005 and 2006 for this project. This project is being funded by the Development Charges and Roads Capital Levy Reserve Funds and funding from the Government of Ontario Millennium Partnership Initiative. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: A copy of this report has been provided to the Clerks of the City of Kitchener and the City of Waterloo. ATTACHMENTS Appendix A – Location and Staging Plan Appendix B – Two-Lane Cross Section Options for Stage 3 PREPARED BY: Marcos Kroker, Senior Project Manager, Design and Construction APPROVED BY: Thomas Schmidt, Commissioner of Transportation and Environmental Services DOCS #275112-v9 Page 9 of 13 Report: E-06-040.1 DOCS #: 275112-v9 Page 10 of 13 Report: E-06-040.1 APPENDIX B DOCS #275112-v9 Page 11 of 13 Report: E-06-040.1 APPENDIX B-2 DOCS #275112-v9 Page 12 of 13 Report: E-06-040.1 APPENDIX B-3 DOCS #275112-v9 Page 13 of 13 IRA NEEDLES BOULEVARD STAGE 3 –VICTORIA STREET TO SOUTH OF ERB STREET R WD VIE H HIG TRUSSLER RD PRESENTATION TO PLANNING & WORKS COMMITTEE MAY 2, 2006 PROJECT BACKGROUND March 1, 2006 Regional Council – Approved Stage 2 construction for 4 lanes of Ira Needles Blvd. from Highway 7&8 to Highview Ave. and 2 lanes from Highview Ave. to Victoria St. – Requested staff to review design options that would provide increased flexibility and reduced costs for the future 4 laning of Stage 3 of Ira Needles Blvd. from Victoria St. to south of Erb St. OPTIONS INVESTIGATED 1 OPTIONS INVESTIGATED OPTIONS INVESTIGATED OPTIONS INVESTIGATED OPTIONS INVESTIGATED 2 Explored 2 Scenarios for Timing of 4 Lane Widening Based on current permitted zoning, future widening is not needed until 2022 Despite current permitted zoning, the six design options were analyzed for 2 timing scenarios: – Widening to 4 lanes occurs by 2011 – Widening to 4 lanes occurs in 2022 ANALYSIS OF DESIGN OPTIONS If widening to 4 lanes occurs in 2022 – Option 1 –Current design ( construct 2 inside paved lanes with curbs and gutters) is “best” – Avoids potential $5 million risk of reconstructing a prematurely failed road in the near future – Stage 3 can be opened in 2007 ANALYSIS OF DESIGN OPTIONS If widening to 4 lanes occurs by 2011 – Option 3a ( construct 2 inside paved lanes with swales is “best”) results in $150,000 of initial net savings – However if 4 laning occurs beyond 2011, substantial risk of incurring $5 million of additional costs in future due to premature subsub-grade failure – Delays due to redesign would delay road opening until 2008 STAFF RECOMMENDATIONS Construct the current design (Option 1) – “best” from a risk analysis perspective – Avoids $5 million risk of reconstructing prematurely– prematurely– failed road in the future – Allows construction to be completed in 2007 Based on the above risk analysis the Option 1 benefit of avoiding a $5 million reconstruction cost far outweighs any potential short term saving of avoiding $500,000 of throwaway costs should widening occur before 2011 3 QUESTIONS QUESTIONS ?? ERBSVILLE RD EE IRA N DL ES BL VD 4 Report: E-06-051 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Design and Construction TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: GERBER ROAD IMPROVEMENTS, NAFZIGER ROAD TO MOSER-YOUNG ROAD, WELLESLEY AND WILMOT TOWNSHIPS - APPROVAL OF ROADWAY IMPROVEMENTS AND APPROVAL OF SPEED LIMIT CHANGES FILE CODE: C04-30, 5439 RECOMMENDATION: THAT the Regional Municipality of Waterloo approve the plans for roadway improvements on Gerber Road between Nafziger Road and Moser-Young Road on the boundary of Wellesley and Wilmot Townships as outlined in Report E-06-051 and amend Traffic and Parking By-law 00-032 as amended, upon construction of the improvements as follows: a) Existing 80km/h speed zone situated 400m East of Nafziger Road extending easterly to 1300m West of Moser - Young Road, amended to 400m East of Nafziger Road extending easterly to 500m West of Moser - Young Road; and b) Existing 60km/h speed zone situated 1300m West of Moser - Young Road extending easterly to 300m East of Moser - Young Road, amended to 500m West of Moser - Young Road extending easterly to 300m East of Moser - Young Road. SUMMARY: Gerber Road (Regional Road 12) between Nafziger Road and Moser-Young Road is 6 kilometres in length and is a boundary road between the Townships of Wellesley and Wilmot. (Please refer to the project keyplan attached in Appendix A.) This section of Gerber Road had been identified for reconstruction in 2006 as part of the Region’s Transportation Capital Program for many years. Gerber Road is a two lane road and requires improvements to rehabilitate the existing deteriorated asphalt surface, to correct drainage problems, to improve visibility and to provide adequate shoulder widths. A Project Team was established to direct the study of alternative designs for this project and includes staff from the Region and the Townships of Wellesley and Wilmot as well as Regional Councillor Ross Kelterborn, Township of Wellesley Councillor Dusan Cizman and Township of Wilmot Councillor Ralph Shantz. As part of its alternative design considerations for this project, the Project Team considered alternatives to improve road safety on Gerber Road by improving sight distance along the road at a number of hills and at individual accesses and sideroads. In addition, the Project Team considered options for the provision of different widths of paved shoulders to enhance safety for all users of the road (pedestrians, motorists, cyclists, agricultural vehicles, horse and buggy traffic, mail and newspaper deliverers). Docs #: 272590 Page 1 of 15 May 2, 2006 Report: E-06-051 A Public Information Centre (PIC) was held on March 08, 2006 to present the Project Team’s technical recommendations for improvements on Gerber Road. Based on the public comments received and the technical considerations for this project, the Project Team is recommending that the following proposed improvements on Gerber Road be approved: replacement of the paved surface; widening of the road platform to include 2 metre wide paved shoulders; reconstruction of two sections of Gerber Road to lower hill profiles and raise valley profiles; placement of curb and gutter on the north side of Gerber Road from Greenwood Hill Road to the Nith River bridge; and adoption of posted speed limits of 60 km/hr (300 metres east of Moser-Young Road to 500 m west of Moser-Young Road), 80 km/hr (500 m west of Moser-Young Road to 400m east of Nafziger Road) and 70 km/hr (from 400m east of Nafziger Road to Nafziger Road). These improvements will correct the identified deficiencies on Gerber Road, will improve safety for all roads users and will provide for the short and long term needs of the Regional Transportation Master Plan and the Regional Cycling Master Plan. Wellesley Township, at its regular Council Meeting of April 18, 2000 had no objection to the recommendations of Report E-06-051. The total estimated cost of the Gerber Road Improvements is $ 2,700,000. REPORT: 1.0 Introduction Gerber Road (Regional Road 12) between Nafziger Road and Moser-Young Road is a 2-lane road 6 kilometres in length and is a boundary road between the Townships of Wellesley and Wilmot. (Please refer to the project keyplan attached in Appendix A.) This section of Gerber Road had been identified for reconstruction in 2006 as part of the Region’s Transportation Capital Program for many years. Gerber Road requires improvements to rehabilitate the existing deteriorated asphalt surface, to correct drainage problems, to improve visibility and to provide adequate shoulder widths. A Project Team was established to direct the study of alternative designs for this project and includes staff from the Region and the Townships of Wellesley and Wilmot as well as Regional Councillor Ross Kelterborn, Township of Wellseley Councillor Dusan Cizman and Township of Wilmot Councillor Ralph Shantz. As part of its alternative design considerations for this project, the Project Team considered alternatives to improve road safety on Gerber Road by improving sight distance along the road at a number of hills and at individual accesses and sideroads. In addition, the Project Team considered options for the provision of different widths of paved shoulders to enhance safety for all users of the road (pedestrians, motorists, cyclists, agricultural vehicles, horse and buggy traffic, mail and newspaper deliverers). In early 2005, a local resident appeared as a delegation at Planning and Works Committee requesting consideration of a speed limit reduction on a 1.5 km section of Gerber Road within the project limits. The speed reduction request cited safety concerns related to pedestrian usage and farm equipment traffic on the narrow road platform. Regional Council agreed to implement a one-year trial period with a speed limit reduction from 80 km/h to 60 km/h in the 1.5 km section of Gerber Road from the MoserYoung Road intersection westerly. It was noted that the speed limit reduction would be reviewed by the Gerber Road Improvements Project Team after the one-year trial period and any permanent changes to the speed limit could be incorporated into the final approval for the overall project. Docs #: 272590 Page 2 of 15 May 2, 2006 2.0 Report: E-06-051 Alternatives Considered for Improvements on Gerber Road 2.1 Road Cross-Section Alternatives The Project Team developed a number of road cross-section alternatives to improve safety for users of Gerber Road. The alternatives included varying widths of lanes and combinations of paved and gravel shoulders. Since the Region’s Cycling Master Plan designates Gerber Road as a designated cycling route, all alternatives needed to incorporate a paved cycling lane adjacent to the travelled driving lane. Based on the road classification, the overall projected traffic volume and the percentage of heavy trucks, a minimum cycling lane width of 1.0m was established for this roadway. Since the road usage also includes large farm equipment and horse and buggy traffic (as well as mail and newspaper deliveries) in the shoulder area, additional width was required beyond the cycling lane. It was also noted that the shoulders would have to be fully paved since there would be insufficient width behind the paved bike lane area for maintenance of a gravel surface. The Project Team determined that the desirable paved shoulder width for this section of Gerber Road is 2.0 metres (beyond a 3.35m driving lane) which provides adequate extra space for the safety of all road users while at the same time, it is not so wide as to encourage speeding or unsafe passing manoeuvres. At the extreme west limit of the project, the roadway is located within the limits of the village of Wellesley (from Greenwood Hill Road westerly). In this area, the Project Team proposed that an urban cross-section be constructed with curb and gutter on the Wellesley village (north) side of Gerber Road. The curb and gutter would be placed beyond a 1.65m paved shoulder and will facilitate drainage and better integrate the roadway cross-section with the future residential development frontage in this area. 2.2 Improved Sight Distances and Speed Limits The Project Team considered a number of alternatives for safe and reasonable posted speeds along the 6 kilometres of Gerber Road. Sight distance is currently deficient at a number of locations based on the posted speeds. In order to correct the deficient sight distance areas, the Project Team proposed the reconstruction of approximately 1 km of Gerber Road to lower hills and fill valley areas to improve sight distance for drivers along the road and for vehicles entering and exiting at driveways and sideroads. With the proposed reconstruction and re-profiling of approximately 1 km of Gerber Road, an 80 km/hr speed limit can be maintained for most of Gerber Road. Based on speed surveys conducted in the past, the average travel speed on this section of Gerber Road is approximately 80 km/hr, regardless of the posted speed. One exception to this 80 km/hr speed limit is the section of Gerber Road from Moser-Young Road westerly 500 metres where it is proposed that the current 60 km/hr posted (trial period) speed remain since road profile changes to achieve an 80 km/hr design profile would have severe impact on adjacent properties. The other exception to the 80 km/hr speed limit is at the west limits of the project from 400m east of Nafziger Road to Nafziger Road within the Wellesley village limits. The existing speed limit of 70 km/hr will remain in this area until such time as the proposed new residential development is in place. After this development is completed, there will be consideration that a 50 km/hr speed limit be adopted in this area. Docs #: 272590 Page 3 of 15 May 2, 2006 3.0 Public Consultation 3.1 Public Information Centre – March 08, 2006 Report: E-06-051 A Public Information Centre (PIC) was held at the Wellesley Community Centre on Wednesday March 08, 2006. Plans showing the proposed improvements were on display and Project Team representatives were present to answer questions and receive feedback. The plans included the following proposed improvements to Gerber Road to correct the identified deficiencies: a. complete replacement of the paved surface to provide a smooth riding surface b. widening of the 2-lane road platform to include 2 metre wide paved shoulders for designated cycling lanes and to enhance safety for all modes of transportation (vehicles, cyclists, pedestrians, horse and buggy, farm traffic, mail and newspaper deliveries) c. reconstruction of portions of Gerber Road to lower hill profiles or raise valley profiles to improve the existing sight distances along the road and at existing access locations (driveways, farm entrances, sideroads) d. placement of curb and gutter on the north side of Gerber Road with a graded boulevard area for a future sidewalk from Greenwood Hill Road to the Nith River bridge east of Nafziger Road. e. Adoption of the following posted speed limits: Section 1 (500 metres west of Moser-Young Road to 300 metres east of Moser Young Road) retain the existing 60 km/hr speed limit Section 2 (500 metres west to 1300 metres west of Moser-Young Road) - increase the current speed limit from 60 km/hr to 80 km/hr Section 3 (1300 metres west of Moser-Young Road to 400 metres east of Nafziger Road) retain the existing 80 km/hr speed limit Section 4 (400 metres east of Nafziger Road to Nafziger Road) - retain the existing 70 km/hr speed limit A copy of the proposed Gerber Road cross-sections that were presented at the PIC is included as Appendix B. Approximately thirty seven (37) members of the public attended the PIC and twenty-five (25) written comments were received. Please refer to Appendix “C” for a summary of all written comments received. 3.2 Issues Raised by the Public Based on the comments received from the PIC, the following main issues and concerns were raised by the public: Docs #: 272590 Page 4 of 15 May 2, 2006 Report: E-06-051 a) Concerns with Visibility at the Crest of the Hill West of Moser-Young Road Public Comments: Three respondents from the PIC requested that the hill 200 metres west of the Moser-Young Road Intersection be lowered. Two comments cited a need for increased visibility to see oncoming eastbound vehicles cresting the hill before backing out of the driveway located just east of the hill (at the Brenner property at 1011 Gerber Road). The other comment requested the hill lowering in order to maintain a consistent 80 km/hr speed limit all the way to Moser-Young Road. Five comment sheets received were in support of leaving the hill as is to discourage speeding. Project Team Response: The plans at the PIC did not include a proposed lowering of the hill located approximately 200 metres west of Moser-Young Road. The hill meets the stopping sight distance criteria for the posted 60 km/hr speed limit and therefore does not represent a deficiency requiring reconstruction to increase sight distance. It should be noted that the intersection of Gerber Road and Moser-Young Road is fully stop controlled. Traffic approaching Moser-Young Road must come to a stop at this 3-way stopcontrolled intersection and vehicles are already therefore slowing down for the approach to the intersection; in fact rumble strips are in place on this intersection approach before the hill is crested and these rumble strips will be reinstated to current Region standards as part of this project. In addition, the “stop ahead” sign is also encountered before the crest of the hill alerting drivers to the stop condition beyond the hill. The Project Team did further review a number of design alternatives which would increase sight distance at the Brenner driveway. Improvements to the hill to achieve an appreciable increase in sight distance would require a significant lowering of the hill by up to 1.5m metres as well as cause severe impacts to adjacent properties requiring the purchase of property and the removal of approximately ten (10) mature trees. For these reasons, the Project Team is not recommending a lower design profile at this location. In addition, the Project Team noted that any improvement to the sight distance over the crest of the hill would likely encourage speeding even if the posted speed were to remain at 60 km/hr. Regional staff has agreed to meet with the Brenners on site to review alternative solutions to increase their comfort level in leaving their driveway. Considerations will include: construction of a small turn-around area at their driveway so that vehicles can always face Gerber Road as they exit the driveway; relocation of the Gerber driveway to the crest of the hill which would increase visibility to the west when exiting the driveway. If the cost of either of these alternative considerations is reasonable, it is proposed that the Region cost-share with the Brenners in the one-time costs to increase visibility and safety at this driveway location. b) Concerns with Proposed Speed Limits Public Comments: The proposed speed limit changes presented at the PIC included an increase in the speed limit from 60 to 80 km/hr within part of the one year trial area, from 500m west to 1300m west of Moser-Young Road. Seven respondents from the PIC were opposed to the proposed speed limit changes shown at the PIC and specifically requested that the speed limit of 60 km/hr be retained throughout the entire trial area (from Moser-Young Road to 1300m metres westerly). Fourteen respondents were in favor of the proposed speed limit changes shown at the PIC. Docs #: 272590 Page 5 of 15 May 2, 2006 Report: E-06-051 In addition to the PIC comments, staff has received other feedback from the public with respect to the current speed limit reduction on Gerber Road within the trial area, from Moser-Young Road intersection westerly 1.3 km. Since the time that the speed limit reduction was implemented on a trial basis early in 2005, Transportation Division staff has received 16 comments from the public. Of the 16, 14 voiced concerns that the 60 km/hr speed limit was unreasonably low. Of the 2 in favour of the speed reduction, one later concurred that the 60 km/hr speed limit should be retained in the built-up area closer to the intersection of Gerber Road and Moser-Young Road, but that it is unreasonable if continued further west. Project Team Response: The one year trial period lowering the speed limit on Gerber Road (from the Moser-Young intersection westerly 1.3 km) was put in place in early Spring, 2005 and lowered the speed limit in this area from 70 km/hr to 60km/hr. The changes proposed at the PIC included the following: a) Section 1 - retain the 60 km/hr speed limit in the area from the stop sign at MoserYoung Road westerly 500 metres, i.e. past the hill at the Brenner property; b) Section 2 - raise the speed limit to 80 km/hr from this point to the limit of the trial area to match the 80 km/hr speed limit from that point westerly to Wellesley. Transportation Division staff undertook speed surveys on Gerber Road in the vicinity of Section 2 (500 metres west to 1300 metres west of Moser-Young Road). During three separate 24 hour surveys taken in May 2005, July 2005 and October 2005, the average speed for all vehicles ranged from 78 km/hr to 80 km/hr, even though the posted speed limit was 60 km/hr. It should be noted that these speeds observed in 2005 in Section 2 (with a posted 60 km/hr speed limit) were in fact higher than speeds recorded in earlier years on this section when the speed limit was posted at 70 km/hr. The common expectation is that arbitrarily lowering the speed limit will increase safety by encouraging at least some drivers to slow down. This expectation is erroneous because an unrealistically low speed limit increases the speed dispersion, resulting in an undesirable mix of slower and faster drivers. An unrealistically low speed limit may also provide a false sense of security for drivers and pedestrians. It should be noted that good engineering practice sets speed limits at or about the average speed because this is most likely to produce a uniformly moving traffic stream. Traffic flowing at a uniform speed results in increased safety and fewer collisions. Drivers are less impatient, pass less often, and are less likely to tailgate, which reduces both head-on and rear-end collisions. The posting of an appropriate speed limit also simplifies the work of enforcement officers because most of the traffic is moving at or near the posted speed. Blatant speeders are easily spotted, safe drivers are not penalized, and police officers are not asked to enforce and defend unrealistic and arbitrary speed limits. Based on the foregoing, the Project Team is recommending that the speed limit changes proposed at the PIC be implemented. c) Safety Issues Public Comments: Six respondents commented on the need to improve road safety, widen shoulders, and increase poor sight distances. Docs #: 272590 Page 6 of 15 May 2, 2006 Report: E-06-051 Project Team Response: These comments support the Project Team’s cross-section and road re-profiling recommendations as displayed at the PIC. The Project Team is proposing the reconstruction and re-profiling of 1.1 km of Gerber Road in order to achieve the vertical geometrics to maintain a consistent 80 km/hr speed limit for all but the two ends of the 6 km project limits. The profile corrections are proposed at the following two locations: a) 900 metre long cut and fill section from 1100 metres to 2000 metres west of Moser-Young Road; b) 200 metre long cut section west of Sandhills Road. 4.0 Recommended Alternative Based on the public comments received and the technical considerations of the Project Team, it is recommended that the proposed improvements on Gerber Road be approved as presented at the PIC and as described in this report. The recommendations include: replacement of the paved surface; widening of the road platform to include 2 metre wide paved shoulders; reconstruction of two sections of Gerber Road to lower hill profiles and raise valley profiles; placement of curb and gutter on the north side of Gerber Road from Greenwood Hill Road to the Nith River bridge; and adoption of the posted speed limits of 60 km/hr (500 metres west of Moser-Young Road to 300 metres east of Moser-Young Road), 80 km/hr (500 m west of Moser-Young Road to 400 m east of Nafziger) and 70 km/hr (from 400 m east of Nafziger Road to Nafziger Road). These improvements will correct the identified deficiencies on Gerber Road, will improve safety for all roads users and will provide for the short and long term needs of the Regional Transportation Master Plan and the Regional Cycling Master Plan. 5.0 Project Cost Based on the final recommendations developed by the Project Team, the total estimated cost of the Gerber Road Improvements is $ 2,700,000. 6.0 Presentation to Township of Wellesley Council A DRAFT copy of this report was distributed to members of Wellesley Township Council at the Council meeting on Monday April 18, 2006. At the meeting, staff also made a presentation of the report contents and the Project Team's recommendations. Wellesley Council had no objections to the recommendations contained in the report. The only issue raised by Wellesley Council was to verify that sufficient sight distance exists at the intersection of Gerber Road and Parkview Drive. Staff have subsequently confirmed that the sight distance on Gerber Road at Parkview Drive meets the requirements for the posted 70 km / hr speed limit. Docs #: 272590 Page 7 of 15 May 2, 2006 Report: E-06-051 7.0 Next Steps Subject to project approval at the May 10, 2006 Regional Council meeting, the following project schedule is proposed: Finalize Detailed Design Tender Construction April 2006 May 2006 July - early September 2006 CORPORATE STRATEGIC PLAN: This project is in harmony with the strategic directions of the Corporate Strategic Plan in that it would address objectives of the Region’s Transportation and Cycling Policy Master Plans. FINANCIAL IMPLICATIONS: The 2006 Transportation Capital Budget includes funding of $1,699,000 in 2006 for the improvements on Gerber Road to be funded from the Roads Rehabilitation Reserve Fund. The program budget was based on benchmarking costs for a simple rehabilitation of the deteriorated Gerber Road pavement. The final recommendations include the additional work and cost to widen the road platform to provide paved shoulders and undertake profile corrections. The current total project cost is estimated to be $ 2,700,000. The provision of additional funds for this project will be addressed in the Region’s mid-year review of the Capital Budget in mid-May, 2006. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: NIL ATTACHMENTS Appendix A Appendix B Appendix C Key Map PIC Cross-sections Gerber Road Improvements - Public Information Centre Comment Sheets PREPARED BY: John Lee, Project Manager APPROVED BY: Thomas Schmidt, Commissioner Transportation and Environmental Services Docs #: 272590 Page 8 of 15 Report: E-06-051 APPENDIX A Docs #: 272590 Page 9 of 15 Report: E-06-051 APPENDIX B Docs #: 272590 Page 10 of 15 May 2, 2006 Report: E-06-051 APPENDIX C Name & Address Mrs. Brenner George and Mary Brenner (separate letter) Support speed limit Y Comments • • • • • • • • • • S. Prange 9 Firella N0B 2T0 Corry Kittle 1011 Gerber Rd. St Agatha, ON N0B 2L0 Y • Y • Joyce Bariler 44 Lawrence St. N0B 2T0 Y • Wendy & Rod Schickler 125 Lawrence St. N0B 2T0 Barbara & Andrew Detzler 1300 Greenwood Hill Rd. N0B 2T0 Y • • Y • Docs #: 272590 • • Coming out of her driveway can’t see cars coming over hill Support widening road to include 2 metre wide paved shoulders Believe should lower the 1st hill profile as much as possible and raise the valley profiles to ensure visibility for the adjacent driveways and motorists Driveways are difficult to exit due to lack of visibility. Family and visitors are extremely nervous exiting the driveway and some find the only way to get out is to back onto the wrong side of the road until the way is clear. This at least allows oncoming traffic to see the vehicle By lowering this hill it will enable heavily loaded trucks to accelerate easier and should decrease emissions and improve air quality Better visibility would decrease the need for additional rumble strips By lowering the profile of the hill this would enhance the safety of motorists entering and exiting driveways Cyclists and pedestrians and other modes of transportation use the road and would increase safety for them as well With the last road improvement, this item was discussed and abandoned. We strongly feel this should be acted on as a safety issue, otherwise the same debate will surface later Better to be proactive and not wait until we have a fatality that will raise this debate again Good to see improvements to deal with traffic level I am in support of this speed limit only if the proposed 80 is lowered to 70 just after the 500 m west of Moser Young We have to live on this street, safety is our main concern. Any argument to increase the limit is the result of a ticket or the lower limit is an inconvenience, which compared with human safety is meaningless. If the limit is increased to 80 km/hr past the 500 m starting at Moser Young Rd., this means people will be driving 70/75 km in the 60 zone to ramp up to the 80 at this point. 70 km/hr is an acceptable limit past the 500 m 60 zone, not 80. Any reduction of a hill on this 60 stretch will create a straight-away and a safety hazard The change is needed in order to be consistent with other rural roads in and out of a community. The current situation is nothing but a speed trap and an expense to the tax payers to have police sit to ticket drivers who are not completely aware of brief changes in speed Recommending speed limit returned to 80 K in the “trial area” Traffic congestion at intersection of Gerber and Moser Young due to shoppers at farm promote hazard by not being off the road when they park. Road should be widened there as well This is the minimum distance to 60 speed limit should be on the east end by Kittels Parking for produce should be prohibited along the road – let them drive onto the property Page 11 of 15 May 2, 2006 Report: E-06-051 C-2 Jamie McDermid 1181 Queens Bush Rd. N0B 2T0 Y • • • George Hosea 3574 Nafziger Rd. N0B 2T0 Y • • Ron McCormick 1171 Gerber Rd. RR #1 St. Agatha N0B 2L0 Mrs. Kittle 1171 Gerber Rd. RR. #1 N0B 2L0 Rosemary KittelMcCormick 1171 Gerber Rd. RR. #1 N0B 2L0 • • • • • • • N N • • • • • • • • • • Rosemary KittelMcCormick 1171 Gerber Rd. RR. #1 N0B 2L0 (separate letter) N • • • • • • • • Docs #: 272590 Inclusion of paved shoulders for bikes, buggies, etc is a good idea, so is the curb gutter, blvd and walkway from Green Hill to Nafziger My concern is pedestrian traffic at the bridge across from the hardware store. At this point the bicycle path will narrow, the space continuing on up to Nafziger is limited My suggestion to council is to proceed with sidewalk installation at the time of construction and to implement creative designs to ensure pedestrian safety from the bridge to Nafziger Rd. I support speed limit changes (the sooner the better) 2 metre wide paved shoulders for cyclists and pedestrians are good ideas Shoulder should be marked There shouldn’t be any parking of cars or trucks on shoulders Lower hills or raised valleys is a good idea I have seen an adult cross Gerber Rd on two occasions who did not stop and look both ways. Should hills be lowered on Kittel’s corner? Section 1- I agree with leaving posted speed limit at 60 km but would like this to be extended past 1171 Gerber Road for safety reasons Section 2 - I would like to see this, if increased up to 70 kph not 80 kph for safety reasons. (As it was before the 60 km/hr trial, it was 70 km/hr before this trial period) Please leave hill at 1011 Gerber Rd. so people don’t go too fast over the hill Also please increase sight distances at 1171 Gerber Rd. Rumble strips in (one missed at barn) Wants 60 limit to stay (re: farm vehicles) Hill not cut down is preference Please keep the 60 zone and not go up to 80 km. if anything please keep it at the previous 70 km Please see our paper work from previous meetings We really want to keep our 60 zone the same as the train and in the same spot Keep rumble strips in place Please consider our safety! And not just because Wellesley residents complained about the 60 km zone getting tickets In favour of wider shoulders and extra pavement for vehicles to pull onto at side of road at father’s residence (Wilfred Kittel) Pleased rumble strips and signage will remain Wish hill by the barn and stone drive shed remain untouched Fear if hill is removed that it will turn into a speed zone and make it difficult to deal with regarding walking and farm implements crossing the road Relived to see the 60 km zone from Moser young to 500 m west Does not like 70 km zone stopped to where it originally was and complete gone Suggestion 1 – extend 60 km zone so it reaches end of their property at 1171 Gerber Road as they drive and cross with slow moving vehicles all the time and allow extra time for large trucks to slow down for the dangerous area at the barn Cars are currently going 84 km in 60 zone, and fears they will go 100 km in an 80 zone. Page 12 of 15 May 2, 2006 Report: E-06-051 C-3 • Jeremy Kittel RR. 1 St. Agatha 1011 Gerber Rd. N0B 2L0 N Wilfred Kittel RR. 1 St. Agatha 1011 Gerber Rd. N0B 2L0 Donna Kittlel RR. 1 St. Agatha 1011 Gerber Rd. N0B 2L0 Peter van Oberbeek Y Murray Klages 3204 Notre Dame Dr. St. Agatha N0B 2L0 Y L. Gawron RR. 1 1184 Gerber Rd. Wellesley N0B 2T0 N Christine, Jan, Anna, and Mary Gawron, Keith Turner 1184 Gerber Rd. (RR#1) Wellesley N Docs #: 272590 Y Y Suggestion 2 – keep 60 zone as proposed (Moser-Young to 500 m west) and from this point keep the original 70 km to where it originally started (1300 m west of Moser Young) • Concerned about the future and traffic worsening • Please keep our hill intact the way it is now, it will turn into a fast speedway if it is off making it dangerous for us • In agreement with having the 60 km zone as indicated in Section 1 • In Section 2, we disagree. It should be 60 km until the end of our farm at 1171 Gerber Rd. It is needed for the school bus stop and where we drive with tractors • I would like to see 1300 metres west of Moser Young Road 60 kph. • Keep driveway to stone shed the same height • Rumble strips on the hill so I can hear the cars coming when I walk across to barns and keep all the signs up • We are in agreement having the 60 km zone as indicated in section 1 • In section 2 we think it should stay 60 or 70 pass McCormick’s driveway • It is too dangerous with the grandchildren getting on the bus • We hope the hill is kept as is • I feel that the deceleration zone at Moser Young Rd (500 m) is probably too long • As is the situation now, I fear the public will largely ignore the 60 km limit • Frequent user of the road and has a big concern regarding the hill just from the stop at Notre Dame Dr. • When you come over the hill travelling east, you are never sure whether you will find children, animals or farm machinery. It is especially dangerous during produce season and pumpkin time as cars park on both sides of the road and children and adults cross this highway • When coming out of the driveway of 1021 Gerber Rd., (Mary Brenner) you have to go on the wrong side of the road and it does not give you enough time to get out of the road for traffic coming over the hill which is very dangerous • The very fact that police caught numerous commuters going 80 km and above points to the fact that more than a few drivers will exceed the 80 km limit probably 20 above to 100 km which creates more high risk and danger to residents who live here • In St. Clements a person was killed this year • Last year (2005) Mr. Kittle crossing with his tractor was really injured and escaped a near death situation due to fast drivers • Raising the speed limit just to satisfy commuters is a very big mistake! And pays no consideration to people who live in this area! Factors that are a concern: • Increased residential population density in this area • Increased commuter through traffic • Varied mix of traffic i.e.: farm equipment, pedestrians, cyclists, commuter vehicles • Varied terrain limits and line of sight visibility • All of these factors combined interact to counter indicate an increase in the speed limit at this time Page 13 of 15 May 2, 2006 Report: E-06-051 C-4 Kirby Marreck 19 Water St. New Dundee N • • • • David & Melanie Hackbart 1175 Hackbart Rd. 656-2930 • • • • • • Cheryl McCabe 84 Reiner Cres. N0B 2T0 Y • • Mark Dietrich Y • Steven Bryant 1184 Gerber Rd. N0B 2T0 • • • • • • Docs #: 272590 In regards to the purposed changes of the speed limit increase on Gerber Rd. I am opposed I drive down this road daily and with an increase in speed, I fear for the safety of the children and the farmers along this road who use it often Please reconsider your proposal and put the safety of others first, along with the preservation of valuable farmland 4-5 years ago there was a culvert put in just up from our road because there was a problem with water running across Gerber Rd. ever since the culvert was put in, it seems that the culvert is not taking the run off water away fast enough and it backs up in Abraham Martin’s field, then our field, then into Mr. Calma’s Field This problem seems to be getting worse as the years go by I had said something to the road crew workers when they were back checking the culvert and finishing their work that I had a concern that the water wasn’t going away fast enough and it was backing up into our fields, but we have not complained otherwise up until now With all the rain we had in the last 1-2 weeks, you can just drive up our road from Gerber Rd. and see the water (frozen again at the moment) sitting in Mr. Martin’s field, our field and Mr. Calma’s field. We realize when you have rain in the winter things will back up because of frozen ground but this happens year round We would appreciate this problem corrected when you are making changes to Gerber Rd. The current 60 km is an extreme measure for one household If speed/traffic is a concern then the vegetables/seasonal business that is located directly at the stop should possibly review their business plan and locate it behind the property or have a driveway off of Moser Young I would like to see the hill by Moser-Young taken down and the speed limit to 80 all the way through Keep the speed limit as is Currently the distance from Moser Young Rd. W. is 1 km. The information document states that the distance is to be changed to 500 km for the marking of the 60 km signs I am not sure the reasoning behind this decision, currently 7 homes are in a secure safety zone of 60 km on this section of Gerber Rd. If the signs are changed, then there will only be 2 homes affected and in a safe and secure 60 km zone 3/4 of the people on this road will be eliminated from the safe zone. I can not understand only protecting ¼ of the residents There are many areas in the Region of Waterloo that have lowered speed limits with similar characteristics: o hidden driveway signs o many homes and farmland clustered close together o children that frequent the roadway at various times of the day o high speed limits lowered to allow effective defensive driving Some of the areas are: o Moser Young Road from Weimer line to Hessen Straus o Hessen Straus Rd. near the intersection of Maplewood & Hengott Rd o Kressler line starting near Hessen Straus and continuing toward Erbsville Rd. Page 14 of 15 May 2, 2006 Report: E-06-051 C-5 A completely lowered speed limit of 70 km the entire length of Benjamin Rd. o Near Erbsville a speed limit of 50 km o Berlets Rd. south of Wilmot line It takes a vehicle 60 seconds to travel 1 km at 60 km/hr. the distance from the current sign on Gerber Rd. to Moser Young road marking the 60 km speed is approximately 1 km. That means a vehicle should take 1 minute to travel that distance. The proposed changes as recommended by this information document would allow traffic to travel faster on Gerber Rd. and they would only save themselves 15 seconds if the signs were changed. The loss a life on this section of roadway would be tragic. o • • Docs #: 272590 Page 15 of 15 GERBER ROAD IMPROVEMENTS Township of Wellesley Gerber Road Key Map Why Improvements To Gerber Road ? • Deteriorated asphalt surface • Deficient sight distances • Road width inadequate for road users (school children, pedestrians, farm traffic, horse and buggy, mail and newspaper deliveries and cyclists) Deteriorated Asphalt Surface 1 Deficient Sight Distances Proposed Improvements. At Public Information Centre •Reconstruct road pavement •Provide 2 metre wide paved shoulders •Correct profile at 2 locations •Construct curb and gutter on north side of road (Greenwood Hill Road to Nith River) Road Width Inadequate Proposed Improvements. At Public Information Centre •Changes to posted speed limits 60 km/hr (Moser –Young Road to 500 metres westerly) 80 km/hr (500 metres west of MoserYoung Road to 350 metres west of Greenwood Hill Road), 70 km/hr (from 350 metres west of Greenwood Hill Road to project limits) 2 Issues Raised by Public Issues Raised by Public Visibility at Hill West of Moser-Young Road Visibility at Hill West of Moser-Young Road Project Team Response: – Existing profile meets minimum stopping sight distance criteria for 60kmh posted speed – Traffic already slowing for existing 3 way stop Project Team Response: – Lowering of existing hill would require: Significant removal of mature trees Significant property acquisition Encourage speeding – Region Staff to meet with Brenner’s (turn-around or driveway relocation) Issues Raised by Public Proposed speed limit changes Project Team Response: - The majority of respondents were in favour of speed limit changes - By re-profiling of Gerber Road, an 80 km/hr speed limit can be maintained for most of Gerber Road Issues Raised by Public Issue: Need to improve road safety, widen shoulders, and increase sight distances Project Team Response: - Comments support the Project Team’s recommended cross-section and road reprofiling 3 Final Recommended Improvements Final Recommended Improvements • Complete replacement of the deteriorated pavement • Widening of the road platform and paved surface to include 2 metre wide paved shoulders • Reconstruction of 2 sections of Gerber Road to improve sight lines • Placement of curb and gutter on the north side of Gerber Road from Greenwood Hill Road to the Nith River bridge including grading boulevard for a future trail or sidewalk Final Recommended Improvements • Adoption of the following posted speed limits • 60 km/hr (Moser –Young Road to 500 m westerly) • 80 km/hr (500 m west of Moser-Young Road to 350 m west of Greenwood Hill Road) • 70 km/hr (from 350 m west of Greenwood Hill Road to project limits) Next Steps • Letters to all PIC attendees and residents (April 2006) • Recommendation to Region of Waterloo P&W Committee, May 2006 • Construction (July to mid September, 2006) • Road will be closed to through traffic for 4 weeks • Access to driveways, maintained during construction 4 Gerber Road Improvements • Questions ? 5 Report: E-06-054 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Transportation TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: ROUNDABOUT AT THE INTERSECTION OF REGIONAL ROAD #17 (AMENT LINE) AND REGIONAL ROAD #10 (HERRGOTT ROAD), IN THE TOWNSHIP OF WELLESLEY FILE CODE: C04-30, T02-30/17 RECOMMENDATION: THAT the Regional Municipality of Waterloo take no action with respect to the request for the installation of a roundabout at the intersection of Regional Road #17 (Ament Line) and Regional Road #10 (Herrgott Road), in the Township of Wellesley: SUMMARY: NIL REPORT: On November 19, 2005, a fatal collision occurred at the Ament Line/Herrgott Road intersection, in the Township of Wellesley. Since then, collision countermeasures that staff have implemented or are about to implement include improvements with respect to signing, the flashing beacon, pavement markings, and rumble strips. On March 22, 2006, Planning and Works Committee requested staff to bring forward a report outlining the option of installing a roundabout at the Ament Line/Herrgott Road intersection. Staff considered this option and determined that it is technically possible to construct a roundabout at this location with the purchase of some additional property. However staff recommend that no action be taken at this time with respect to a roundabout at the Ament Line/Herrgott Road intersection for the following reasons: • The intersection currently experiences on average approximately 2 injury collisions per year. Installing a roundabout may reduce these collisions, however the number of collisions is typical of similar rural intersections; • The construction of a roundabout at this location would cost over $500,000 and because of the limited funding available for road projects staff feel there are other higher-priority projects that should be considered first; and • It is the Region’s practice to implement appropriate collision countermeasures in an incremental fashion. Staff will monitor this intersection to determine the effectiveness of the countermeasures already implemented or planned. Page 1 of 2 May 2, 2006 Report: E-06-054 CORPORATE STRATEGIC PLAN: This report addresses the Region’s goal to provide a high quality Regional transportation system. FINANCIAL IMPLICATIONS: The cost to construct a roundabout at this location would be over $500,000. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Staff in the Design and Construction Division contributed to the preparation of this report. ATTACHMENTS: NIL PREPARED BY: Nancy Button, Manager, Transportation Engineering APPROVED BY: Thomas Schmidt, Commissioner of Transportation and Environmental Services Name: E-06-054 Document Number: 274390 Page 2 of 2 Report: E-06-057 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Transportation TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: ROUNDABOUT EDUCATION PROGRAM FILE CODE: C04-30, T04-10 RECOMMENDATION: For information. SUMMARY: The Region’s 2006 roundabout education program includes: • • • • • • • A training video; A radio campaign; Increased police presence; Updates to the education brochure; Roundabout awareness signs; Enhancements to the roundabout pages on the Region’s web site; and Improvements to traffic control signs. REPORT: In preparation for the new roundabouts that the Region of Waterloo will be constructing this year, Regional staff will be re-launching in 2006 the roundabout education program that was initially started in 2004. The program is timed to have its main impact in June 2006, just before the opening of this year’s first new roundabout, at the intersection of Sawmill Road (Regional Road #17) and Arthur Street (Regional Road #85). The other locations where the Region will be constructing roundabouts in 2006 are: • • • Ira Needles Boulevard (Regional Road #70) at Highview Drive, Highland Road (Regional Road #6) and Victoria Street (Regional Road #55); Can-Amera Parkway (Regional Road #80) at Conestoga Boulevard; and Fountain Street (Regional Road #28) at Blair Road (Regional Road #42). Training Video The City of Lacey, the City of Olympia and the Washington State Department of Transportation cooperatively produced an excellent roundabout training video, set in the City of Lacey, entitled Driving Modern Roundabouts and available for viewing at www.ci.lacey.wa.us. With permission from the State of Washington, the Region of Waterloo has retained C to C Productions to adapt the Lacey video to create a Region of Waterloo version of the video. The introduction and conclusion to this video will feature an Inspector from the Waterloo Regional Police Services (WRPS), speaking in front of a Region of Waterloo roundabout. Page 1 of 5 May 2, 2006 Report: E-06-057 To provide sufficient capacity, most of the Region’s new roundabouts will have 2-lane entries. The roundabouts are sized to reduce speeds while accommodating large vehicles. The training video clearly addresses the issues of: • • • • • How a driver should travel through a 2-lane roundabout; The operation of a large vehicle through a 2-lane roundabout; Pedestrian and cyclist movements through a roundabout; What to do when an emergency vehicle approaches a roundabout; and What not to do when driving in a roundabout. The Region of Waterloo video will be distributed in mid-June 2006, in conjunction with the first week of the radio education campaign. The video will be available for viewing on the Region’s web site. Staff will also distribute this training video to agencies within the Region including: • • • • • • • • • • • • Local municipalities; WRPS; Grand River Transit; Trucking companies and associations; Insurance companies; Driver education schools; The Canadian Automobile Association; Ministry of Transportation driver licensing offices; Libraries; School boards; Seniors centres; and Visitor/tourism information centres. It is anticipated that many of these agencies will use the video for staff and public training with respect to the use of roundabouts. Regional staff will also explore opportunities to have the video aired on television both locally and provincially. Radio Campaign Staff have booked time for a radio education campaign for roundabouts. The radio campaign will reinforce that at roundabouts drivers should slow down, yield, ease in and then ease out of the roundabout, and will direct drivers to the Region’s web page for further information. The radio campaign is planned to occur over 2 weeks starting June 18, 2006, just before the opening of the Sawmill Road/Arthur Street roundabout at the end of June 2006. Police Presence WRPS have agreed to increase police presence at the new roundabouts in the weeks following the opening of each roundabout. They will provide an initial “gentle” level of enforcement, aimed more at educating drivers rather than punishing drivers who drive incorrectly through a roundabout. The WRPS also plan to add a link so that the public can view the Region’s roundabout training video through the WRPS road safety web site. Page 2 of 5 May 2, 2006 Report: E-06-057 Education Brochure Appendix A contains a draft of the Region’s roundabout education brochure, All About Roundabouts. Staff updated this brochure from the 2004 version by simplifying the language, updating the photos to show Region of Waterloo roundabouts, adding tips for drivers of large vehicles, and providing advice on how to drive at a roundabout when an emergency vehicle approaches. Staff will distribute the brochure in mid-June 2006, in conjunction with the first week of the radio education campaign. The distribution list for the brochure includes every household in the Region of Waterloo, as well as every agency receiving the training video. The brochure will be printed and delivered to households through the same company that delivers the Region’s Environews. Copies of the brochure will be provided to the roundabout construction contractors to distribute to drivers who are flagged to stop for roundabout construction, as was done during the 2004 roundabout construction. WRPS will distribute the brochures to stopped drivers during their increased police enforcement at the new roundabouts. Roundabout Awareness Signs In advance of construction, staff will place roundabout awareness signs on Regional roads approaching new roundabouts. The signs indicate that roundabouts are coming and provide the Region’s web site address and a telephone number. Figure 1 shows a roundabout awareness sign placed on Highland Road at the proposed Ira Needles Boulevard. The number of roundabout awareness signs will include: • • • • 5 for Ira Needles Boulevard Stage 2; 3 for the roundabout at Sawmill Road/Arthur Street; 2 for the roundabout at CanAmera Parkway and Conestoga Boulevard; and 3 for the roundabout at the intersection of Fountain Street and Blair Road. Figure 1: Roundabout Awareness Sign Page 3 of 5 May 2, 2006 Report: E-06-057 Web Site Improvements to the roundabout pages on the Region’s web site will include: • • • • Updates to the text and photos; A link to the Region’s roundabout training video; Improvements to the animation sequences of vehicles travelling through a roundabout, including the addition of a large vehicle and some examples of what not to do (with animation to be provided by the eSolutions Group); and A video clip showing traffic flow at Regional roundabouts. The web page improvements are scheduled for completion by the beginning of June 2006. Traffic Control Signs Staff reviewed the Region’s practice for traffic control signs at roundabouts and made changes to make the signing simpler, clearer and more consistent with overall Regional signing practice. Examples of changes to the signs include: • • • • • • • • Removal of the roundabout circle inside the “yield” sign, to make the sign consistent with other “yield” signs throughout the Region and Province; Use of “yield ahead” signs where recommended as per the Ontario Traffic Manual; Removal of the speed tab from the “roundabout ahead” sign because there is a potential need to stop at the approach to the roundabout. Speeding has not been an issue at the existing roundabouts and is not typically posted for travel through an intersection; Removal of the text from the lane designation signs. This simplification will make it easier for a driver to absorb the required lane designation information in the short time that the driver has to read and understand the sign; Standardization of the colour of guide signs (signs that provide street name or destination information). Standard colours help drivers to more easily recognize and interpret signs. Guide signs are to be white lettering on green background, consistent with Regional and Provincial practice; Optimized font for increased legibility and recognition. Larger fonts are needed for higher operating speeds in advance of the roundabout. Use of upper and lower case letters makes words more easily recognizable by their shape; Improved placement and spacing of signs; and Increased size of the chevron signs in the central islands, to clearly indicate that drivers should proceed counterclockwise in the roundabout. CORPORATE STRATEGIC PLAN: The roundabout education program addresses the Region’s goal to provide a high quality Regional transportation system. FINANCIAL IMPLICATIONS: Currently, the approved 2006 Transportation Capital Budget does not include any funding in 2006 for roundabout education. As part of the 2006 mid-year review of the 2006 Transportation Capital Budget, staff will be identifying budget transfers of $65,000 for the 2006 roundabout education program. Page 4 of 5 May 2, 2006 Report: E-06-057 OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: This report was prepared with assistance from the Design and Construction Division, the Corporate Communications and Citizen Service Division, and the Waterloo Regional Police Services. ATTACHMENTS: Appendix A - draft brochure entitled All About Roundabouts PREPARED BY: Nancy Button, Manager, Transportation Engineering APPROVED BY: Thomas Schmidt, Commissioner of Transportation and Environmental Services Name: E-06-057 Document Number: 276766 Page 5 of 5 Report: E-06-058 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Transportation TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: ONTARIO’S MILLENNIUM PARTNERSHIP FUNDING AGREEMENT FOR THE REGION OF WATERLOO INTERNATIONAL AIRPORT SERVICING AND LAND DEVELOPMENT PROJECT FILE CODE: C04-30, T02-30/SBM, T18-01 RECOMMENDATION: THAT the Regional Chair and Clerk be authorized to sign an agreement with Her Majesty the Queen in Right of Ontario (by its Ministry of Agriculture, Food and Rural Affairs) to provide for $1,112,608 of capital funding from the Millennium Partnerships Initiative for the Region of Waterloo International Airport servicing and land development project as described in Report E-06-058. SUMMARY: NIL REPORT: Regional Council on July 7, 2004 (Report E-04-091) approved nominating (a) The Region of Waterloo International Airport servicing and land development project and (b) Regional Road #24 (Hespeler Road), Munch Avenue to Dunbar Road widening and operational improvements project for the remaining $1 million (approximate) in capital funds available to the Region from the total $40 million in Ontario Millennium Partnership (OMP) funding to replace the originally nominated Regional Airport Runway Extension project which was not approved by the Province for Millennium Partnership funding. On March 29, 2006, Region staff received confirmation from the Province approving the Region’s request to commit the remaining $1,112,608 in capital funds remaining in the Region’s $40 million OMP notional allocation to the Region of Waterloo International Airport servicing and land development project (refer to Appendix A). This will finalize all Provincial funding commitments related to the $40 million notional allocation to the Region of Waterloo. The next step for the Region is to formalize a funding agreement with the Province and the Ministry of Agriculture, Food and Rural Affairs (OMAFRA). As part of finalizing this agreement, the Province has requested that Regional Council pass a by-law approving the authorization for the Regional Chair and Clerk to execute the funding agreement for the Region of Waterloo International Airport servicing and land development project. Once executed by the Region, the agreement be forwarded to the OMAFRA. Page 1 of 2 May 2, 2006 Report: E-06-058 Status of Project and Agreement Regional staff has completed negotiation of the Provincial Agreement with OMAFRA staff and recommends that the agreement be executed. It should be noted, however, that many of the substantive provisions of the Provincial Agreement are somewhat onerous and not open to negotiation by the Province. Since the Project was completed in 2005, most of these provisions are not of concern. However, Regional staff notes the following provisions of the Provincial Agreement: • • • The Province may withhold, or deduct from, any payments due to the Region under any provincial programme, present or future, if it does not receive required information in respect of the Project or if it determines that there has been an “overpayment” in respect of the Project; The Region is required to indemnify the Province against any claims, damages, expenses and costs, etc. incurred by the Province relating to the Provincial Agreement or the Project and maintain insurance coverage in this regard; and In order for costs to be eligible for Financial Assistance, they must relate to “infrastructure problems that cause an immediate and serious issue for human health or the environment.” Provincial staff is unwilling to revise this criterion in the Provincial Agreement but has provided written confirmation that the Project meets this criterion. Since this construction project was completed in 2005, once this agreement is fully executed, the Region will submit a financial claim to OMAFRA for processing and payment. CORPORATE STRATEGIC PLAN: The implementation of this infrastructure projects supports the Region’s goal of creating and supporting a climate that encourages economic prosperity. FINANCIAL IMPLICATIONS: The Region’s share of the project costs has been funded from debentures and the Provincial funding of $1,112,608 has been accounted for in this project budget. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Staff from the Finance and Corporate Resources (Legal Services) Departments has reviewed this report, and will be involved in finalizing the agreements with the Province. ATTACHMENTS: Appendix A – Letter from David Caplan, Ministry of Public Infrastructure Renewal PREPARED BY: Rob Gallivan, Manager, Transportation Program Development APPROVED BY: Thomas Schmidt, Commissioner of Transportation and Environmental Services Document Name: E-06-058 Document #: 276617 Page 2 of 2 Report: CR-RS-06-025 REGION OF WATERLOO CORPORATE RESOURCES Legal Services TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: DISPOSAL OF EASEMENT INTEREST, NAFZIGER ROAD, TOWNSHIP OF WILMOT FILE CODE: RECOMMENDATION: THAT the Regional Municipality of Waterloo: a) declare the Region’s existing easement interest in Parts 9 and 11, Reference Plan 58R13951, Township of Wilmot as surplus and enter into such documentation as is required to release the Region’s interest established by the easement for $1.00 plus costs, subject to the Region's property disposition by-law and to the satisfaction of the Region’s Solicitor, as detailed in Report CRRS-06-025 dated May 2, 2006; and b) give the Regional Solicitor authority to execute and register, electronically or otherwise, any documentation required to give effect to the foregoing. SUMMARY: Nil REPORT: The Regional Municipality of Waterloo acquired an easement over Part 1, Reference Plan 58R11306, which easement was registered on title on June 9, 1998 as Instrument Number 1382338. The easement was conveyed by Alloy Casting Industries Limited (the “Owners”) to the Region for a nominal cost to construct a drainage ditch on the lands. The drainage ditch is located on the west side of Nafziger Road south of Snyder’s Road West, in New Hamburg in the Township of Wilmot. The Owners are currently developing the lands. Due to the development of the lands a portion of the drainage ditch was relocated and an easement was registered on August 8, 2005 from the Owners to the Region over the required lands for the maintenance of the relocated drainage ditch at the expense of the Owner as a condition of severance. As a result, part of the existing easement is no longer required on the lands referred to in the Recommendation above. These lands are now owned by The Corporation of the Township of Wilmot and the Township has registered a by-law dedicating and opening the lands as public highway, namely Kaster Court. Planning, Housing and Community Services staff and Transportation and Environmental Services staff have advised they have no objection to the Region releasing the easement interest in the lands. The Region's property disposition by-law requires that we advertise the disposal of surplus interest in land in the local newspaper. The release of easement as it affects the lands will be finalized only after all requirements of the Region’s property disposition by-law are met. All associated costs of the release of easement, such as public notification and registration of documentation, will be paid by the Owners. The location of the subject lands are as shown attached in Appendix “A” and Appendix “B”. Page 1 of 4 May 2, 2006 Report: CR-RS-06-025 CORPORATE STRATEGIC PLAN: The recommendation does not directly fall under one or more of the objectives of the five focus areas; however, it does support the Region’s Vision, Mission and Values in that it provides good citizen service. FINANCIAL IMPLICATIONS: All associated costs of the release of easement will be paid by the Owners. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Transportation and Environmental Services staff and Planning, Housing and Community Services Department staff have been consulted in the preparation of this report. ATTACHMENTS Appendix “A” – location map of lands Appendix “B” – partial copy of Reference Plan 58R-13951. PREPARED BY: Joan Moore, Property Agent APPROVED BY: Gary Sosnoski, Commissioner of Corporate Resources # 276283 Page 2 of 4 May 2, 2006 Report: CR-RS-06-025 Appendix “A” Subject Area: Kaster Court # 276283 Page 3 of 4 May 2, 2006 Report: CR-RS-06-025 Appendix “B” Partial Copy Reference Plan 58R-13951 Subject Lands: Parts 9 and 11, Plan 58R-13951 Kaster Court # 276283 Page 4 of 4 Report: CR-RS-06-027 REGION OF WATERLOO CORPORATE RESOURCES Legal Services TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: AUTHORIZATION TO EXPROPRIATE PERMANENT EASEMENTS (2ND REPORT) ALONG SHANTZ STATION ROAD, TOWNSHIP OF WOOLWICH, RELATING TO REGION OF WATERLOO INTERNATIONAL AIRPORT REQUIREMENTS FILE CODE: RECOMMENDATION: That the Regional Municipality of Waterloo approve the expropriation of the property detailed in Report CR-RS-06-027 dated May 2, 2006 described as follows: Permanent Easements: 1. Part Lot 88, German Company Tract, Township of Woolwich, being Reference Plan 58R-15013 (1163 Shantz Station Road) 2. Part Lot 87, German Company Tract, Township of Woolwich, being Reference Plan 58R-15013 (municipal address unavailable) 3. Part Lot 103, German Company Tract, Township of Woolwich, being Reference Plan 58R-15013 (1292 Shantz Station Road) 4. Part Lot 87, German Company Tract, Township of Woolwich, being Reference Plan 58R-15013 (municipal address unavailable) Part 1 on Part 5 on Part 6 on Part 7 on And that staff be instructed to register a Plan of Expropriation for the property within three months of the granting of the approval to expropriate the property, as required by the Expropriations Act; And that the registered owners be served with a Notice of Expropriation and a Notice of Possession for the property after the registration of the Plan of Expropriation; And that an Offer of Compensation be served upon the registered owners of the property in the amount of the market value of the land as estimated by the Region’s appraiser; And further that the Regional Solicitor be authorized to discontinue expropriation proceedings or any part thereof, in respect of the above described lands, or any part thereof, upon the registration on title of the required documentation to complete an acquisition of the required interest. SUMMARY: Nil REPORT: As part of the approved Airport 2006 Capital program and the Airport Master Plan it has been identified that there is a need to achieve a precision approach for aircraft on Runway 07/25. As part of the requirement for precision approach the Region requires the lowering of Shantz Station Road to the east of Runway 07/25 (in 2007) and to remove obstacles for incoming aircraft, which include the existing hydro poles on Shantz Station Road which must be removed and replaced with underground works. Currently the right of way for Shantz Station Road is very limited and as a result property is required for burying the hydro lines and for placing new poles and guys along Page 1 of 4 May 2, 2006 Report: CR-RS-06-027 Shantz Station Road, which will not interfere with the precision approach requirements. Waterloo North Hydro has confirmed that they will require permanent easements along Shantz Station Road for the relocation of existing hydro utilities as a result of airport requirements. It is the intent that these easements will be transferred to the hydro authority if they are acquired through a negotiated settlement prior to expropriation. Council approved the commencement of expropriation of the subject properties on November 29, 2005 as detailed in report CR-RS-05-089. The appropriate forms under the Expropriations Act were served in order to initiate formal proceedings under the Act for these properties. All of the affected property owners were previously contacted by Legal Services staff and informed of the project as well as the Region’s intention to commence the expropriation process and the Region’s Expropriation Information Sheet was provided to each of them. Legal Services staff also contacted all property owners and informed them of the Region’s intention to continue with the expropriation process in order to ensure that the construction timeline is maintained, including this report being presented to Council, as detailed in the Region’s Expropriation Information Sheet. Negotiations have been proceeding with the affected property owners and if an agreement is reached and the conveyance of property rights is completed, that property will be dropped from the expropriation process by the Regional Solicitor. The Region did not receive a notice for a Hearing of Necessity within the statutory time frame established by the Expropriations Act from any of the affected property owners. The next step in the proceedings is for Council to approve the expropriation of the property. This approval will ultimately be endorsed upon a certificate of approval on the Plan of Expropriation for those properties not acquired under agreement. The Plan is then registered within three months of the approval. Ownership of the property vests with the Region upon the registration of the Plan. Notices of Expropriation are then served upon all registered owners, including tenants as shown on the assessment roll. Once ownership by the Region is secured through the registration of the Plan, it is possible to serve the Notice of Possession. The date for possession can be no sooner than three months following the date of service of the Notice of Possession. The Notices of Expropriation and Notices of Possession may be served at the same time. After the registration of the Plan of Expropriation and prior to the taking of possession of the property the expropriating authority is required to serve the registered owners with an offer in full compensation for their interests in the land. The offer must be accompanied by the immediate payment of one hundred (100%) percent of the appraised market value of the land to the registered owners as estimated by the Region's appraiser. The registered owners are also to be served with a report appraising the market value of the property, which report formed the basis for the offer of compensation The expropriation process is proceeding in an attempt to ensure that the Region has possession of the permanent easements to coincide with the scheduled construction of hydro works in 2006. Transportation and Environmental Services staff advises that they are not aware of any environmental concerns with respect to the subject lands. The expropriation of the permanent easements is on an “as is” basis. The subject lands are shown on the attached appendix “A”. #277827 Page 2 of 4 May 2, 2006 Report: CR-RS-06-027 CORPORATE STRATEGIC PLAN: This project supports the goal of creating and supporting a climate that encourages economic prosperity. FINANCIAL IMPLICATIONS: Transportation and Environmental Services staff advise the approved Airport 2006 Transportation Capital program includes $176,000 for the relocation of the overhead hydro to underground and property costs, and it is estimated that the existing budget is sufficient to cover these costs. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Transportation and Environmental Services have been consulted in the preparation of this report. ATTACHMENTS Appendix “A” – location map of lands. PREPARED BY: W. Duncan Leggett, Solicitor, Property APPROVED BY: Gary Sosnoski, Commissioner of Corporate Resources #277827 Page 3 of 4 May 2, 2006 Report: CR-RS-06-027 Appendix “A” 3 2 4 Shantz Station Road Airport Lands 1 Permanent Easements: 1. 2. 3. 4. #277827 Part 1, Plan 58R-15013 (1163 Shantz Station Road) Part 5, Plan 58R-15013 (municipal address not available) Part 6, Plan 58R-15013 (1292 Shantz Station Road) Part 7, Plan 58R-15013 (municipal address not available) Page 4 of 4 Report: E-05-103.1 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Waste Management TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: FOOD WASTE ORGANICS PILOT PROJECT UPDATE FILE CODE: E21-20 RECOMMENDATION: THAT the Regional Municipality of Waterloo: a) b) Approve the scope of the Food Waste Organics Pilot Project as presented in Report E-05-103.1 dated May 2, 2006; and Amend the existing waste collection contract with Waste Management Canada to include curbside collection and transfer of the Food Waste to the processing facility for the duration of the pilot project. SUMMARY: The Food Waste Organics Pilot Project is tentatively scheduled to begin on October 23, 2006. Residents in five different selected pilot areas will receive green bins and education packages during the first weeks of October. The pilot will involve two neighbourhoods in Cambridge, two in Kitchener, and one in Waterloo. Collected materials will include food waste kitchen scraps, as well as soiled tissues, paper towels, pet wastes, and kitty litter. The organics will be collected by our existing waste collection contractor, Waste Management Canada, using an individual truck dedicated to the pilot program, and delivered to Integrated Municipal Systems in Thorold, Ontario for processing. Communication with and education of program participants will begin several weeks before the start of the pilot and will continue throughout the year. REPORT: Background The “Three Year Waste Reduction Sequencing Plan” was approved by Regional Council on October 19, 2004. One of the components of the plan is a Food Waste Organics Pilot Project scheduled for the fall of 2006. Completion of the pilot project also fulfills one of the objectives of the Corporate Strategic Plan. The Food Waste Organics Pilot Project will run from October 2006 through September 2007, allowing 12 months to evaluate the program. Approximately 5,000 households in the tri-cities area will participate in this program, which will be evaluated based on the amount of waste diverted; number and nature of complaints/concerns received; program costs; participation rate and capture rate. Following completion of the pilot, long term options for processing and the potential for Region-wide rollout will be fully reviewed. Page 1 of 9 May 2, 2006 Report: E-05-103.1 Collection of Materials Collection Containers Residents will be given a 40-litre curbside collection bin with latching lid (commonly referred to as a “green bin”) and a smaller sized kitchen-bin to collect materials. A supply of paper liner bags with a water-resistant cellulose liner will also be delivered to residents along with the cart. Although the use of liners for the bin is not necessary for participation, the liners will assist residents in keeping bins clean and odour free. Once residents have used up their supply, they can wrap food waste in other acceptable paper products, such as take out bags, or flour/potato bags. They will also have the option of obtaining additional paper bag liners as required from the Region at cost. Collection Method The collection of food waste organics will take place weekly in the pilot areas, on residents’ regular garbage collection day. Weekly garbage and recycling pickup and bi-weekly leaf and yard waste collection in these areas will remain unchanged. A dedicated truck will be used to collect the food waste. Participation in the pilot program is not mandatory, but all residents in the designated collection area will be encouraged to participate. Staff developed the five pilot areas to include a mix of housing styles across the Region. Most pilot areas match existing daily collection routes to provide a basis for evaluating the effectiveness of the collection program. For the pilot, collected food waste will be delivered to the Cambridge Transfer Station, where it will be stored in sealed containers and then transferred for processing as required. The Region’s two existing waste collection contractors were invited to bid to supply the single truck required for the pilot program. The bid received from Waste Management Canada is competitive and consistent with the collection current contract cost. The all inclusive daily cost for collection services is $770.00 and includes daily transfer of the food waste collected to the Cambridge Transfer Station. Plein Disposal declined to bid. Designated Materials for Diversion The following materials are acceptable in the Food Waste Organics Pilot: Kitchen Waste Baked goods, bones, bread/toast, butter and margarine, cake, candy, cereal, cheese, cookies, coffee filters and grounds, corn cobs and husks, dough, eggs and eggshells, fish and fish parts, flour, fruit, grains, gravy and sauces, grease/lards/fats, herbs and spices, jams and jellies, mayonnaise, meat and meat products, nuts and shells, oatmeal, pasta, peanut butter, pizza, popcorn, pumpkins, rice, salads and dressings, shellfish, sour cream, sugar, syrup, tea bags, vegetables, yogurt. Paper Products Facial tissues, flour/sugar/potato bags, freezer paper, greasy pizza boxes, microwave popcorn bags, paper napkins/plates/cups, paper towels, soiled waxed paper and cardboard, wrapping paper. Other Cat litter, dryer lint, feathers, hair, houseplant waste, nail clippings, pet hair, pet droppings, sawdust, toothpicks, wood chips, wood ashes (cold). Plastic bags and other plastics products are not acceptable in the green bin. Wrapping food waste in plastic bags cause extreme problems in processing and composting the food waste. 264030 Page 2 of 9 May 2, 2006 Report: E-05-103.1 By not accepting plastic bags in the green bin, the quality of the finished compost will be high with very little residue. Processing System Public and private organics processing facilities were invited to bid on the composting of the collected organics. Integrated Municipal Systems (IMS) of Thorold, Ontario has been selected to undertake processing for this pilot as they met the required technical evaluation criteria and were the lowest bidder. IMS was also one of only two bidders willing to accept kitty litter and pet wastes along with food organics for processing. This is a significant issue as it is estimated that over 9,000 tonnes of kitty litter is landfilled locally each year. The cost to process the food waste is $60/tonne. IMS will mix the Region’s food waste with yard waste received from elsewhere. IMS assumes ownership of the food waste once received. Collection Areas Five areas on current collection routes in the tri-cities are proposed for the pilot, providing a diverse cross-section of the Region. Precise maps of the collection areas, including participating streets are included in Appendix A and described verbally below. • • • • • Monday Collection Area: City of Cambridge, north of Cedar Street to Blenheim Road (not included), south of Cedar Street to Wedgewood Drive Tuesday Collection Area: City of Kitchener, north of Ottawa Street South between Windflower Drive and International Place, southwest of Fischer Hallman and southeast of Ottawa Street to Wilderness Drive and Bush Clover Crescent Wednesday Collection Area: City of Waterloo, area bordered by Columbia Street (not included), Albert Street (not included), Weber Street N. (not included) and Blythwood Road. Thursday Collection Area: City of Cambridge, area bordered by Townline Road (not included) to the east, Ellis Road to the south, and River Road (not included) to the northwest. Friday Collection Area: City of Kitchener, area bordered by Frederick Street to the north, East Avenue to the east, Weber Street East and Stirling Avenue North in the south, and Lancaster Street East in the west. Communication/Education Strategy The communication plan for the food waste pilot includes the following steps: 1. Letter of Information hand delivered to residents in pilot areas; 2. Community open house sessions in each pilot area; 3. Green bin, lined paper bags and educational materials distribution in the two weeks prior to program start up; 4. Ongoing communication to pilot participants via a quarterly newsletter; and 5. Participant survey at regular program intervals. Next Steps The start date for the pilot has been tentatively set for October 23, 2006. The communication and education program for participating residents will begin within one month of the start date. 264030 Page 3 of 9 May 2, 2006 Report: E-05-103.1 CORPORATE STRATEGIC PLAN: This pilot program will evaluate the effectiveness and cost of curbside food waste collection as a method of diverting waste from our landfill. This is consistent with the Corporate Strategic Plan of reducing reliance on landfill disposal, while ensuring that we spend wisely the dollars that we are entrusted with and maximize their use for those we serve. FINANCIAL IMPLICATIONS: As part of the 2006 Budget Process, Regional Council approved a one-time expenditure of $1.5 million over the years 2006 and 2007 for the pilot program. All program costs confirmed to date are within budget estimates. Processing costs are based on actual tonnes received and processed. Therefore, actual costs will be based on program participation. A complete update on the pilot program will be provided to Planning and Works Committee in February 2007. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: The Finance Department has reviewed this report. ATTACHMENTS Appendix A: Proposed Collection Routes PREPARED BY: Cari Howard, Project Manager APPROVED BY: Thomas Schmidt, Commissioner of Transportation & Environmental Services 264030 Page 4 of 9 May 2, 2006 Report: E-05-103.1 APPENDIX A - Collection Area Maps Monday Collection Area: City of Cambridge VVEE RYY AA UR ISBBU ALLIS S SA D R RD RAAYY RR UR M MU R DR OD RO OR O LLSSBB H HIILL VVEE N AA ON RO YR B BY E VE AV EA ALLE D DA STT NS EN HE PH EP S STTE STT NTT S EN K KE E VE AV WA EW RE D DR RTT CR IM C S SIM R DR ILLL D HIL CH RC UR HU C CH D RD ER ATTE GA HG UTTH OU S SO PPLL YAALL OY RO NTT R UN OU M MO S ES RE CR DC ND AN HLLA IGH H HIG R DR DD OD OO WO KW RK AR P PA E NE AN Y LLA EY NLLE EN K KE STT YS AY D DA W WEES STT C CO OVVE E CCRR EESS TTCC RRTT D RD ER ATTE GA HG UTTH OU S SO RTT CR YC NY AN BA A ALLB D VD BLLV IN B WIN RW OR C CO CRT PACIFIC PACIFIC CRT R DR STT D ES RE CR ILLLC H HIL B BLLE EN NH HE EIM IM R RD D R DR AD EA NLLE ON D DO STT RS AR DA ED C CE REESS CR RC AR DA ED C CE D RD KR EK EE RE CR RC R A A D D E E C C DD AANN G GRR RTT CR NC AN VA IIV L L L L U SSU DDRR GEE DDG RRII R DR DD OD OO WO HW UTTH OU S SO RTT CR DC OD OO WO R RW DEE ND U UN EESS CCRR D D OOOO W W LLEE P P AAPP S ES RE CR HC TH R R DR D O O W SW OAAKK DS AD TTEE O I I H H W WA W W W WO OO OD DVV AALLEE CR C RTT E E V V A A N N W W A HLLA CH B BIR IRC R DR ND N AVVAA ELLA D DE EESS CCRR ODD OO WO RRW DDEE SS AALL REE CR DC OD OO W WO SSTT W WEE D RD DR OD OO WO RW AR H HA R DR DD OD OO WO EW GE DG ED W WE © © Teranet Teranet Land Land Information Information Services Services Inc. Inc. and and its its licensors, licensors, 2006. 2006. not be be reproduced reproduced without without permission. May May not permission. THIS THIS IS IS NOT NOT AA PLAN PLAN OF OF SURVEY SURVEY Produced by Planning, Housing and Community Services 264030 Monday Collection Area: City of Cambridge N © Region of Waterloo 2006 Page 5 of 9 May 2, 2006 Report: E-05-103.1 Tuesday Collection Area: City of Kitchener R R ND IIN OBB R RO KKEE W WAA SS REE CR NC IIN OBB R RO KKEE W WAA SS REE CR R RC E E W OW LLO DFF N ND W WII LL R R PP WEE O OW L L DFF N ND W WII SS SSTT W WAA TTAA O OTT RTT CCR SS EESS CRR RRC TTEE W WAA DDRR EERR W W LLOO SS DDFF RREE IINN W W LLCC I I OO IILLFF M M LL LL PP NAA N O O TTII NNAA EERR T T IINN TT CCRR W OOW ILLLL W WI EERR AATT W W 264030 Tuesday Collection Area: City of Kitchener N SS REE C CR Produced by Planning, Housing and Community Services W WO OO OD DP OP PO PP PYY C RTT CR R EER OVV CLLO H HC USS BBU Information Services © © Teranet Teranet Land Land Information Services Inc. Inc. and and its its licensors, licensors, 2006. 2006. not be be reproduced reproduced without without permission. May not permission. May THIS THIS IS IS NOT NOT A A PLAN PLAN OF OF SURVEY SURVEY SSTT YY RRRR E E BB CCKK HHAA RRDD AANN M M LL AALL --HH R R HHEE SSCC FFII SS REE CR DC IID CH RC O OR R D DR OXX FFO REEYY G GR S ES RE CR EC OTTTTE RLLO AR HA CH NC EN EE UE Q QU S ES RE C CR INTT MIN IN M AIN NTTA UN OU M MO R DR SD SS ES NE RN ER DE ILD W WIL S ES RE CR IN C RTTIN AR MA EM INE P PIN A AC CTTIV IVA AA AV VEE © Region of Waterloo 2006 Page 6 of 9 May 2, 2006 Report: E-05-103.1 Wednesday Collection Area: City of Waterloo TT CRR D DC O O O W WO RRKK PPAA D D D RR OD OO W WO H H YYTT BBLL PPLL RIIEE R RR BBAA VVE DD AA R R O LLFFO M MII TT NN RR SS BBEE W WEE LL D PP OD OO WO HW TTH BBLLYY L PPL DD O O OO W DW ILILD W W DDRR CCKK RRAA M MAA TTAA LL EE AAZZ HH PPLL SSO OR RR REE LL SSMM AALL LLW W OOO ODD DDR R SSTT SSTT LLYY OLL H HO SSTT RTT EER AALLBB R D DR N TTIIN S S U AAU SS REE CR LL C L L I I RRDD CCAA SSTT GHH G HHII W W SSTT BBIIAA M M U U OLL C CO Information Services © Teranet Teranet Land Land Information Services Inc. Inc. and and its its licensors, licensors, 2006. 2006. © May May not not be reproduced reproduced without without permission. permission. IS NOT THIS THIS IS NOT A A PLAN PLAN OF OF SURVEY SURVEY Produced by Planning, Housing and Community Services Wednesday Collection Area: City of Waterloo N © Region of Waterloo 2006 Page 7 of 9 May 2, 2006 Report: E-05-103.1 Thursday Collection Area: City of Cambridge S ES RE CR NC ON PTTO KIIP S SK R RIIV VE ER RR RD D Y AY WA DW OD OO W WO E E V V I I O OLL R DR ND EN KE EK E EE M M C C M M R DR RD NEER NN EN R RE REESS CR EE C ALLEE RA AR K KA EENN DDEE AAVV O OUU RR D DRR G GIIBB BBSS TT R DR ND ON SO RS ER DE A ALLD R DR ND AN RA ELLR M ME PLL AP MA E ELLM D RD YR NTTY UN OU C CO ST AL ST TTAL UTT N NU P PLL ATTTT RA PPR R RR R E TTEE INE STTIN RS ER W WE RTT CR MC AM IILLLLIIA W W G G N K KIIN R DR KD ICK MIC RM OR CO CC M MC R DR ND AN DA RD OR JJO S ES RE CR NC ON STTO RS AR M MA R DR YD RY RR ER JJE E NE AN R LLA ER SLLE US OU H HO RTT CR NC IAN BIA AB FFA DR ND ON RO OFFR S SO S ES RE CR EC IFFFE CLLIF HC RTTH OR N NO 264030 S ES RE CR RC ER ME H HAAM Produced by Planning, Housing and Community Services S ES RE CR OC RO AR CA EC D DE STT IN S HLLIN GH UG AU CLLA M MC Y AY WA SW ES EE G GE © © Teranet Teranet Land Land Information Information Services Services Inc. Inc. and and its its licensors, licensors, 2006. 2006. not be be reproduced reproduced without without permission. May not permission. May THIS THIS IS IS NOT NOT AA PLAN PLAN OF OF SURVEY SURVEY R DR RD ER ATTE WA EW UE B BLLU R DR DD OD OO WO RW ER K KE RTT CR EC NE EN RLLE ER M ME D RD ER NE NLLIIN WN OW TTO S ES RE CR YC EY NE EN EE WE S SW S ES RE CR YC CY RC AR M MA 3344 N N D 1100 OAAD RO ER IDE S SID D RD IS R E ELLLLIS Thursday Collection Area: City of Cambridge N © Region of Waterloo 2006 Page 8 of 9 May 2, 2006 Report: E-05-103.1 Friday Collection Area: City of Kitchener SSTT CKK C I I EERR EEDD FFRR VVEE TT AA EEAASS EE AAVV R R NEE RN R M MEE STT S DIIAA LLYYD VVEE R AA R NEE N H H O H HO TT LL SS UEE M MU SSAA ST E E TER ST CASTER LAN LANCAS TT LL SS PPEE A A H C CH TT N SS ON O MEE SSIIM TT N SS M MAA E E G NG BBIIN D R RD AALLEE D D N EEN G GLL TT R R SS HEE CH AAC B B U RU BBR TT G SS UG RU KKR SSTT OYY RO TTR N EE N AAVV R RAA O O D N ND PPAA NN VEE G AA G I I N N RLL R SSTTII FFAAII RRVV IIEEW W AAVV EE SSTT EE OSS R RO W WEE BBEE RR SSTT EE N N SSTT ONN RRO E E M M C CAA SS REE CR AC R R O DO N ND PPAA © © Teranet Teranet Land Land Information Information Services Services Inc. Inc. and its licensors, 2006. 2006. May May not not be be reproduced reproduced without without permission. permission. THIS THIS IS IS NOT NOT A A PLAN PLAN OF OF SURVEY SURVEY Produced by Planning, Housing and Community Services 264030 Friday Collection Area: City of Kitchener N © Region of Waterloo 2006 Page 9 of 9 Report: E-06-047 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Waste Management TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: WASTE MANAGEMENT EDUCATION PROGRAM FILE CODE: C04-30 RECOMMENDATION: For information. SUMMARY: Public interest in waste management, particularly diversion from landfill, has grown significantly over the last decade. Municipalities are investing in education programs on the importance of the 3 Rs and how individual waste management practices can reduce what is being sent to landfill. This report provides details on the comprehensive, hands-on Waste Management education program focused on the youth in the Region of Waterloo. A small vacant building at the front gate of the Waterloo Landfill has been converted to accommodate school groups for on-site educational presentations, including tours of the landfill and Materials Recycling Centre. A formal opening and ribbon cutting ceremony is planned for May 16, 2006, at 11:00 a.m. following the Planning and Works Committee meeting to be held at the WRESTRC facility. All Regional Councillors are invited to participate. REPORT: Background In November 2001, Regional Council endorsed a recommendation to develop and implement a student-focused, Waste Management environmental education program, and to launch the “Don’t Litter Bug” vehicle as a trademark representing the new initiative. Introduced to the public at the 2002 Waterloo-Wellington Children’s Groundwater Festival, the “Bug” and blue box trailer is widely recognized in the Region and continues to be used in parades and in many public events as a visual prompt for better waste management habits. As intended, the “Bug” has been very popular with children and teachers, stimulating requests for school presentations on waste management issues. In late 2002, a school-based environmental educational program called “Catch the Bug” was initiated, with a focus on Grades K to 6. This program continues to be presented at schools, engaging children in informative, hands-on activities, with a theme on recycling and “what we can do”. Page 1 of 3 May 2, 2006 Report: E-06-047 Education Program Details The objectives of the educational program are: • to build awareness of Waste Management issues, both regionally and within the broader global environment; • to provide practical techniques on how each one of us can implement reduction and diversion practices; • to positively encourage participation through building a heightened sense of personal commitment and community pride; and • by providing education on environmental issues, the rich environmental history of the area and the Region’s continued progressive initiatives. To ensure that these objectives are being met, regular evaluation of the program content and delivery are performed by the teacher user groups. Suggestions/recommendations are recorded and reviewed by Staff for program improvements. Feedback on the program has been enthusiastic and consistently positive, increasing the referrals and requests for next-year bookings. A welcome outcome of this popularity has been the interest from higher grades, with increasing demand from Grades 7 – 11. Since its inception in 2002, the number of participants has grown by over 350 percent, to over 6,200 students experiencing the at-school or on-site program in 2005. The force behind the growth has come primarily from word-of-mouth amongst the teacher user group. Promotion continues on the Region’s website and through Environews. The education program has been an overwhelming success and continues to evolve. High demand for the “Catch The Bug” program and on-site tours led to an expansion of the school-based education program. A small, vacant building at the front gate of the Waterloo landfill has been converted to accommodate school groups for on-site educational presentations, incorporating a full tour of the Materials Recycling Facility and landfill. Hosting school groups on site will greatly increase the number of students that can participate, as compared to staff traveling to schools. Another objective for this on-site program is to provide an even more in-depth learning experience. Through pilot testing, teachers have indicated that the new on-site program, supported by a physical tour of the waste management facility, provides a stronger impact and lasting impression with the students. To quote one teacher on the benefit of this program as an educational tool: “This was one of the best and most valuable school trips I have ever participated in. The students learned so much that we have been able to take back to our school and homes.” A formal opening and ribbon cutting ceremony is planned for May 16, 2006, at 11:00 a.m. following the Planning and Works Committee meeting to be held at the WRESTRC facility. All Regional Councillors are invited to participate. CORPORATE STRATEGIC PLAN: This program supports the Corporate Strategic Goal of maintaining a sustainable and livable community. 264988 Page 2 of 3 May 2, 2006 Report: E-06-047 FINANCIAL IMPLICATIONS: Education program costs are provided for in the 2006 operational budget for the Waste Management Division. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: NIL ATTACHMENTS NIL PREPARED BY: Susan White, Manager, Waste Collection and Diversion APPROVED BY: Thomas Schmidt, Commissioner, Transportation and Environmental Services 264988 Page 3 of 3 Report: E-06-056 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Waste Management TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: WATERLOO LANDFILL MONITORING PROGRAM UPDATE FILE CODE: C04-30/E28-40 RECOMMENDATION: THAT the Regional Municipality of Waterloo enter into a consulting agreement with Conestoga-Rovers and Associates (CRA) to provide engineering and hydrogeologic services necessary to support the Region with environmental monitoring activities at the Waterloo Landfill Site to an upset limit of $194,750 plus applicable taxes. SUMMARY: NIL REPORT: Background As required by the Waterloo Landfill Site Certificate of Approval, the Region undertakes a number of environmental monitoring programs including groundwater and surface water quality assessments. Due to our expanded site environmental infrastructure and increased involvement and commentary by the Ministry of Environment (MOE) and the Waterloo Landfill Liaison Committee (WLLC), the groundwater and surface water monitoring programs have grown. At present, groundwater and surface water samples are collected from a sampling network comprised of over 180 monitoring wells and five surface water ponds both on site and on adjacent properties. Results from our monthly monitoring activities are summarized, assessed in terms of acceptable limits and provided to the MOE in the form of Annual Monitoring Reports (AMRs). In addition, quarterly meetings are held to discuss operational and monitoring program issues with the WLLC. This report presents an overview of proposed activities to meet our monitoring program objectives. Proposed Monitoring Program Activities i) Monitoring Well Installations Upwards of ten (10) new monitoring wells are proposed in 2006. Eight (8) of these wells will be situated along the western perimeter of the landfill site. The remaining two (2) wells will replace older, nonfunctioning wells. These new installations will further enhance groundwater monitoring data in this area and provide additional input for the updated landfill hydrogeology assessment discussed below. In addition, monitoring data will be compiled and verified as it becomes available including ongoing optimization of the environmental monitoring program. Page 1 of 4 May 2, 2006 ii) Report: E-06-056 Updated Landfill Hydrogeology Assessment A comprehensive update of the hydrogeology around the Waterloo Landfill Site is ongoing and is intended to clarify the impact and potential future impact of landfill activities. This task involves the development and implementation of an expanded water level monitoring program to supplement existing groundwater data. iii) Environmental Control Measures Continuing activities aimed at reducing environmental impacts from the landfill site are proposed and include an assessment of the effectiveness of large diameter collection sumps (wells) in the northwestern portion of the old landfill area (OLA). The existing groundwater extraction well system located in the southern portion of the site will also be evaluated and updated including an assessment for the need for additional extraction wells. iv) Annual Reporting to The Ministry of Environment This task has evolved considerably over the past few years and involves the preparation and finalization of the 2006 AMR and the 2007 monitoring program for submission to the MOE. As well, separate reporting related to individual monitoring tasks is now required as part of our monitoring program activities. v) Hydro One/MOE/WLLC Technical Support Due to ongoing consultation with neighbouring property owners Hydro One, the MOE and the WLLC, it is anticipated that there will be a requirement for attendance at meetings and the preparation and submission of technical response comments on the Region’s behalf. This is necessary as we are now undertaking more activities related to the approved southern landfill expansion including an increase to our monitoring network in relation to initial construction of landfill cells in the SEA in 2006 (cells SE-1 and SE-3) as well as the upcoming relocation of a hydro corridor. Consultant Assignment Staff recommend entering into a Consulting Agreement with CRA to provide monitoring program assistance as outlined herein. CRA prepared all the original detailed designs for the landfill expansion and authored the June 1990 hydrogeologic report that formed the basis of our successful EA approval. CRA has also reviewed monitoring results at the site on an annual basis and has provided valuable assistance to date. The consultant Project Manager involved in the preparation of the landfill expansion documents remains committed to the project and will provide an invaluable link in discussions with the MOE regarding what was assumed in the past compared to current conditions. CRA has prepared a detailed workplan and cost estimate to perform the work and staff have thoroughly reviewed the workplan and costs, made modifications as appropriate and consider the negotiated fee to be fair and reasonable given the scope and complexity of the assignment. Given CRA’s previous involvement and quality of work, staff are recommending to forgo the standard consultant selection process and retain CRA to perform the work. A detailed list of tasks to be completed and associated costs is provided on Appendix A. Overall, the consulting costs for this assignment will not exceed an upset fee of $194,750. CORPORATE STRATEGIC PLAN: Development and implementation of the monitoring program activities is consistent with the Corporate Strategic Goal of developing policies and practices to protect our groundwater resources. 270140 Page 2 of 4 May 2, 2006 Report: E-06-056 FINANCIAL IMPLICATIONS: The approved 2006 Waste Management Capital Budget includes $550,000 for hydrogeology and leachate control initiatives which is sufficient for tasks related to monitoring program activities. The remaining capital budget will be used for retaining drilling and excavation contractors necessary to undertake the works related to the monitoring program activities described herein. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Staff from the Region’s Purchasing Division and water resource protection group were consulted in the preparation of this report as well as the local resident group (WLLC) and the MOE. ATTACHMENTS: APPENDIX A – Monitoring Program Activities, Summary of Major Tasks and Upset Fees PREPARED BY: Jon Arsenault, Manager, Engineering and Programs APPROVED BY: Thomas Schmidt, Commissioner, Transportation & Environmental Services 270140 Page 3 of 4 May 2, 2006 APPENDIX A Report: E-06-056 Monitoring Program Activities Summary of Major Tasks and Upset Fees Tasks Fees 1. Supervision of Monitoring Well Installations & Program Assistance $ 26,250 2. Updated Landfill Hydrogeology Assessment $ 29,000 3. Environmental Control Measures $ 72,000 4. Annual Reporting to MOE $ 52,500 6. Hydro One/MOE/WLLC Technical Support $ 15,000 Total Upset Fee $194,750 270140 Page 4 of 4 Report: CR-RS-06-026 REGION OF WATERLOO CORPORATE RESOURCES Legal Services TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: HYDRO CORRIDOR RELOCATION, WATERLOO LANDFILL SITE FILE CODE: RECOMMENDATION: That the Regional Municipality of Waterloo enter into agreements as required for the relocation of the Hydro One corridor and transmission lines at the Waterloo Landfill site as follows: a) convey to Hydro One Networks Inc. an easement over lands described as part of Part Lot 39, German Company Tract, City of Kitchener, subject to registration of a reference plan, for the sum of $2.00 plus associated taxes and costs on terms and conditions satisfactory to the Commissioner of Transportation and Environmental Services and the Regional Solicitor, as detailed in report CR-RS-06-026 dated May 2, 2006; b) convey to the Province through Ontario Realty Corporation the fee simple interest in the lands described as part of Part Lot 39, German Company Tract, City of Kitchener, subject to registration of a reference plan, for the sum of $2.00 and the conveyance to the Regional Municipality of Waterloo of the existing corridor acquired under Recommendation c) below plus associated taxes and costs on terms and conditions satisfactory to the Commissioner of Transportation and Environmental Services and the Regional Solicitor, as detailed in report CR-RS06-026 dated May 2, 2006; c) acquire from the Province through Ontario Realty Corporation the fee simple interest in the lands, being the existing corridor, described as Parts 2 and 3 on Plan 58R-7999 in the City of Kitchener for the sum of $2.00 and the conveyance to the Province through Ontario Realty Corporation of the new corridor conveyed under Recommendation b) above, plus associated taxes and costs on terms and conditions satisfactory to the Commissioner of Transportation and Environmental Services and the Regional Solicitor, as detailed in report CR-RS-06-026 dated May 2, 2006; and d) give the Regional Solicitor authority to execute and register, electronically or otherwise, any documentation required to give effect to the foregoing. SUMMARY: Nil REPORT: The Region is in the process of expanding the Waterloo Landfill Site along its southern boundary. This expansion requires the relocation of an existing Hydro One transmission line to a location situated farther south onto lands which are owned by the Region. The Provincial Crown represented by Ontario Realty Corporation is the owner of the corridor lands on which the existing Hydro One transmission lines are situated. An agreement is proposed whereby the Region provides an easement to Hydro One on the lands to be transferred to the Province so that Hydro One can construct new transmission lines in anticipation of a later land exchange. These lines would then be Page 1 of 3 May 2, 2006 Report: CR-RS-06-026 activated, the existing corridor would be deactivated and removed by Hydro One and the existing Hydro One easement would be released. The Region and Province represented by Ontario Realty Corporation would then exchange lands for a nominal sum, the Region being conveyed the existing corridor from which the hydro lines have been relocated, and Ontario Realty Corporation acquiring the new corridor onto which the hydro lines were relocated pursuant to the easement. The lands to be conveyed to Ontario Realty Corporation will be the same lands on which the easement was previously provided to Hydro Ontario to facilitate the relocation of the hydro lines. The costs of the relocation and removals was detailed and approved in Report E-06-036 dated March 7, 2006. Previously Report CR-RS-05-022 dated April 5, 2005 approved the recommendation that declared the new Hydro corridor (Region owned lands) surplus to its requirements. Certain matters have been finalized since that Report as a result of negotiations with Hydro One. Therefore, the Recommendations in this Report provide approval as to price as required by Recommendation c) of Report CR-RS-05-022 as although Hydro One is still obtaining the easement from the Region for a nominal sum, the price is otherwise being satisfied, both as to the acquisition of the old corridor and the disposition of the new corridor, by the exchange of these lands between the parties. The transmission line relocation is scheduled to commence this year and it is estimated that completion of said relocation will occur in 2007. CORPORATE STRATEGIC PLAN: This project is a component of an overall waste management system designed to be consistent with the corporate strategic focus area of protecting and enhancing the environment. FINANCIAL IMPLICATIONS: The Region and Hydro One/Ontario Realty Corporation have agreed to exchange lands and easement needs for nominal sums. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Staff of the Transportation and Environmental Services Department have been consulted and have assisted in the preparation of this Report. ATTACHMENTS Appendix “A” –Sketch of Waterloo Landfill Site, Proposed Hydro One Relocation PREPARED BY: Bruce McNaughton, Administrator, Real Estate Services APPROVED BY: Gary Sosnoski, Commissioner of Corporate Resources. #276090 Page 2 of 3 May 2, 2006 #276090 Report: CR-RS-06-026 Page 3 of 3 Report: E-06-039 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Water Services TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: WATER SUPPLY UPDATE FILE CODE: C04-30/P&W/WS.06 RECOMMENDATION: For information. SUMMARY: The Regional Municipality of Waterloo’s Water Services Division (WSD) has a number of ongoing projects and initiatives that are intended to increase water supply capacity, reduce peak demand and ensure adequate water supply in the short, medium and long term. This report summarizes these ongoing projects and initiatives and puts them into the context of current and future water demands and capacity. The Region is one of the fastest growing communities in Ontario. One of the impacts of growth is a steady increase in water demands. To ensure adequate water supply, the Region approved the Long Term Water Strategy (LTWS) in May 2000. Updates on the specific LTWS activities related to increasing water supply are discussed in this report. The WSD has also implemented several short and medium term programs related to water supply capacity. These include treatment of 1,4 Dioxane to restore the Greenbrook well field to operation; Infrastructure Asset Management System for the well water supply and optimization of the Mannheim Water Treatment Plant. These projects focus on restoring water supply capacity. A number of initiatives in the Water Efficiency Master Plan (WEMP) have successfully achieved savings of 1.2 MIGD over a seven-year period. Implementation of the Stage 2 Outdoor Water Use Restrictions in 2005 successfully reduced total per capita water use by 10% over the summer months. Combined, these water efficiency initiatives have effectively reduced water demands and ensure continued commitment to meet the objectives of the WEMP. REPORT: Background The WSD has a number of ongoing projects and initiatives that are intended to increase water supply capacity, reduce demand and ensure adequate water supply in the short, medium and long term. This report summarizes these ongoing projects and puts them into the context of current and future water demand and capacity. Page 1 of 7 May 2, 2006 Report: E-06-039 As the Region is one of the fastest growing areas in Ontario, planning for growth requires planning for steadily increasing water demand. The Region monitors two primary measures of water demand: • Average Day Water Demand: This measures usual daily residential and industrial water use. Average day water use is impacted by growth and/or changes in indoor water use (i.e. implementing water efficiency measures, etc.) • Maximum Day Water Demand: This measures the maximum amount of water used on one day during a year. Maximum day water demand is impacted primarily by weather and outdoor water use. Graph 1 shows monthly average day water demands from 2002 to 2005. The graph shows that the overall average day demands have changed minimally over the past four years even with a 7% growth in population over this period. Although growth has continued, our average day demands have essentially remained unchanged. Average day per person water demand has reduced 10% from 390 litres/person to 354 litres/person (includes residential and industrial). Increased Water Efficiency is one of the factors that has caused the reduction and some of the measures include: 1. New residential and industrial development is more water efficient than existing structures; 2. Impact of regional water efficiency programs on existing residential and business water use; and 3. Shift from higher water use industries to lower water use industries. Integrated Urban System Avg. Day (2002) Avg. Day (2003) Avg. Day (2004) Avg. Day (2005) 50 45 Average Daily Consumption (Million Imperial Gallons) 40 35 30 25 20 15 10 5 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Graph 2 compares the annual average day and maximum day from 1998 to 2005. Again, the annual average day consumptions show minimal change in the period of eight years. The maximum day is heavily dependent on the weather conditions and outdoor water use with significant yearly variations. Hot and dry summers generally result in higher peak water demands. The 2005 maximum day clearly highlights the reduced peak water demand resulting from the Outdoor Water Use restrictions as compared to similar summer weather conditions in 2001 and 2002. It is important to note that requirements to provide increased water supply capacity are driven by peak water demands. DOCS #271802; File: E02-40/4644-20 Page 2 of 7 May 2, 2006 Report: E-06-039 Tri City Consumption Average Day (Imp.G) Maximum Day (Imp.G) 60 Consumption (Million Imperial Gallons) 50 40 30 20 10 1998 1999 2000 2001 2002 2003 2004 2005 Implementation of the LTWS Master Plan The approved LTWS contained a number of recommendations to increase water supply capacity in the short, medium and long term. The primary recommendations of the LTWS are: • • • 10 MIGD Aquifer Storage and Recovery (ASR) facility; New 5 MIGD of ground water supply in 2018; and Immediately pursue acquisition of a water taking permit, land for treatment and transmission facilities and other approval/consultation/notifications necessary for the construction of a Great Lakes pipeline. Approval of LTWS in 2000 coincided with events in Walkerton. The tragedies in Walkerton started an unprecedented number of regulatory changes and reactions in the water industry. The WSD initially concentrated on complying with new regulations and little time was available for the immediate implementation of the LTWS Master Plan. Over the past two years, increasingly more time has been directed towards implementation of the LTWS. Progress on several recommendations in the LTWS is summarized later in this report. Current Status In the short term, the Region’s water supply capacity has been impacted for a number of reasons. These include reductions in capacity caused by increasing regulatory requirements, increasing well maintenance requirements and the temporary shutdown of the Greenbrook wellfield. Capacity increases have been realized from the first phase of the ASR at Mannheim, increasing maintenance and rehabilitation of Region wells and optimization of the treatment process at the MWTP. Graph 3 shows the Region’s current water capacity and future planned increases. The remainder of this report highlights a number of activities within Water Services to ensure appropriate water supply for the Region of Waterloo. DOCS #271802; File: E02-40/4644-20 Page 3 of 7 May 2, 2006 Report: E-06-039 Water Demands & Capacity 80 60 Production (IGPD) ASR Phase 2 Average Demand Max. Day Demand Average Demand Projected Max. Day Demand Projected System Capacity 70 Ongoing Projects to Restore Lost Capacity of Water Sources Greenbrook Shut-Down Grand Reservoir + New Groundwater ASR Phase 1 50 40 30 20 10 0 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Year Ongoing Projects and Initiatives LTWS ASR In the spring of 2005, the first phase of the ASR was commissioned with a system of four injection/recovery wells and two recovery wells to provide approximately 5 MIGD of peak summer capacity. During the summer of 2005, the ASR was still being commissioned and was operated in a short term storage mode with alternating days of injection and recovery, dependent primarily on weather conditions. A total of 176 ML of water was injected and 87 ML was recovered. During the summer of 2006, monitoring of both injection and recovery capacities will continue to ensure the ASR system achieves maximum efficiencies. Phase 1 of the ASR has added approximately 5 MIGD of peak summer capacity. The second phase of the ASR has been scheduled for completion in 2009 and completion of Phases 1 and 2 of the ASR will add approximately 10 MIGD of peak summer capacity. LTWS- 5 MIGD New Groundwater Source To address a decline in capacity and performance of the well supply system and to find up to 5 MIGD of new groundwater capacity (as approved in the LTWS Master Plan), the Integrated Urban System (IUS) optimization and expansion project was initiated in 2005. A Planning and Works Committee report, E-06-012, provided an update on the status of the project and identified program activities for 2006. In Cambridge East, test wells have been installed and will be evaluated over the next six months with the Environmental Assessment to be completed in 2007. The performance evaluation of two existing wells, P16 and W5, will also be finalized in 2007. The next steps for these projects, including construction and regulatory licensing, is scheduled for the following three to five years. The investigation of new well supply sources in Erbsville, Chicopee and Breslau are in the initial stages. Completion of these projects will add approximately 5 MIGD of supply capacity by approximately 2010. LTWS-Water Supply Master Plan Update Since the Region’s LTWS was approved and since the March 2004 update report on the LTWS, there have been a number of changes including: population projections as a result of the Places to DOCS #271802; File: E02-40/4644-20 Page 4 of 7 May 2, 2006 Report: E-06-039 Grow from the province, a new Great Lakes-St. Lawrence Basis Sustainable Water Resources Agreement, new regulating framework, and decline in infrastructure performance. To evaluate the impact of these issues, and others, on the recommended activities from the LTWS, a Water Supply Master Plan (WSMP) update has been initiated. A P&W Committee report recommending the consultant to update the WSMP is also being presented at this May 2 meeting. Pending Council approval, the update is to be completed in the spring of 2007. Concurrent with the completion of the WSMP update, staff are pursuing an opportunity to partner with other municipalities in the Grand River watershed to review a Lake Erie-based water supply system option. Region staff have met with staff from Haldimand County, County of Norfolk, City of Brantford, Brant County, City of Guelph, Six Nations, Mississaugas of the New Credit First Nation over the last nine months. The existing infrastructure (constructed in the 1970s) located in Haldimand County was planned and constructed as the basis for a water supply for municipalities in the watershed. The existing infrastructure includes twin 6.7 m diameter intake pipe, low lift station, control building, high lift pump station, 36.5 Hectare area for treatment plant, and associated licences including a Permit to Take Water for 412 MIGD. The existing infrastructure is sized for a capacity of 400 MIGD. Considerable infrastructure including water treatment facilities, pumping and piping would still be required. The infrastructure currently supplies water to several industrial customers and Haldimand County. Regional staff are participating in an informal working group to exchange information on the current status of the water supply system, discuss current master plans and share information on timeline and common concerns with future water supply. The working group identified a common concern as related to the continued supply of water to support future growth. A memorandum of understanding is currently being developed between the stakeholders to be brought forward to committee later this year. A complete update will be provided at that time. Completion of the WSMP update and development of a Lake Erie-based water supply option will help to ensure long term supplies for the Region. Greenbrook WTP Since the fall of 2004, the Greenbrook well field has been offline as a precaution after the detection of levels of 1,4-Dioxane at levels higher than anticipated. Over the past months, several related projects have been running concurrently. The treatability study starting with a literature review of various advanced oxidation process (AOP) technologies and bench scale testing of these AOP was completed last year. In January and February of this year, three pilot projects were conducted to evaluate the technologies and equipment performance. These pilots including ultra violet treatment with hydrogen peroxide, ozone treatment with hydrogen peroxide and a proprietary technology were tested at the Greenbrook Treatment Plant. An environmental assessment and predesign have also been undertaken with an extremely aggressive time frame. For the scope of this project, the well supply capacity for Greenbrook was maintained at current levels allowing for streamlining of the environmental assessment process. A detailed pre-design is being completed to streamline construction activities. Preliminary discussions with the MOE have indicated that no provincial regulatory standard will be issued within the time frame of this project. A Health Canada Drinking Water Guidance Value was issued at a level of 0.03 mg/L. For this project, a more conservative target of 0.01 mg/L has been used for the design criteria. A detailed report on the status of the Greenbrook project is scheduled for the P&W Committee in June. A second report for P&W Committee recommending consultant selection is also scheduled for this summer. Completion of this project will restore the capacity of Greenbrook to its previous level. DOCS #271802; File: E02-40/4644-20 Page 5 of 7 May 2, 2006 Report: E-06-039 Mannheim Water Treatment Plant The MWTP supplies approximately 20% of the drinking water to the Region’s IUS. Due to operational constraints and regulatory restrictions, the plant has not consistently achieved the design capacity of 72.7 MLD (16 MIGD). In March 2006, the MWTP Operating Strategy Review Update (Report E-06-032) identified alternatives to bring the MWTP to its original design capacity. A detailed assessment of the unit processes at the MWTP indicated that the pre-treatment system (rapid mixing, flocculation and sedimentation) and filtration system require upgrades. During the summer of 2005, optimization of the plant chemistry resulted in increase in production levels up to approximately 12 MIGD. Filter upgrades scheduled for fall of 2006 are anticipated to provide improved treated water quality and increase filter performance efficiency. Currently, the capacity of the plant is reduced during periods of variation in water quality typical of the late fall and early spring when the plant produces between 36 and 55MLD (8 to 12 MIGD). Further filter upgrades to the under-drain system are to be completed in 2008 to address seasonal variations and further evaluation of the plant performance will confirm the pretreatment upgrade requirements. Completion of this project will restore the capacity of the MWTP to its original level as early as the end of 2009. Infrastructure Asset Management In 2003, a comprehensive well rehabilitation and well pump asset management program was implemented for the well supply system. The program incorporated recommendations from the source water protection section on best management practices for well rehabilitation and well pump maintenance methods. Over the past three year period a total of sixteen wells have been rehabilitated and thirty-four well supply pumps have been serviced or replaced. In 2005, the program was further enhanced by expanding the program to include smaller submersible well supply pumps. These programs ensure the continued reliability of the well supply system. However, based on improved performance monitoring, a decline in performance efficiencies has been observed at some wells over the past five-year period. As our monitoring information improves, we are working to obtain better information on these trends. While this program does not address capacity, it does ensure that the capacity we have is available when it is needed. Water Efficiency In keeping with the 1998 WEMP Plan targets, WSD has been successful in achieving cumulative water savings from 1998 to 2005 of 1.2 MIGD. As the WEMP is now being updated, staff are evaluating proposed measures and associated budget implications. One of the new successful programs was the creation of the Outdoor Water Use Bylaw in 2003 with updates in 2005 and 2006. The promotion of once-per-week lawn watering and implementation of Stage 2 restrictions in the summer of 2005 were successful in reduction of peak demands as noted previously in Graph 3. Comparing the peak demand in 2005 with comparable peak demands under historical summer conditions, total per capita water use was reduced by 10% from June till August. Implementation of measures to reduce water demand are an important part of the Region’s strategy to ensure adequate water supply capacity for both current and future needs. Overall Summary The Region is undertaking a number of projects and initiatives to meet the water needs of the community, both current and future. As summarized in this report, these projects and initiatives address the short, medium and long term needs of the community. Appropriate and timely construction of new capacity, maintenance of existing capacity combined with the Region’s Water Efficiency effort will ensure an adequate water supply now and into the future. DOCS #271802; File: E02-40/4644-20 Page 6 of 7 May 2, 2006 Report: E-06-039 CORPORATE STRATEGIC PLAN: This update on the water supply supports Focus Area 1: “Manage Regional Growth to Enhance Quality of Life” to ensure adequate infrastructure capacity to meet current and planned growth. FINANCIAL IMPLICATIONS: Nil OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Nil ATTACHMENTS - Nil PREPARED BY: Nancy Kodousek, Director, Water Services APPROVED BY: Thomas Schmidt, Commissioner, Transportation & Environmental Services DOCS #271802; File: E02-40/4644-20 Page 7 of 7 Water Supply Update Introduction • Current Status • Average Day • Maximum Day • Water Supply Capacity • Implementation LTWS • ASR • New Water Supply • Water Supply Update Water Services Water Supply • Water Supply Projects • • • • Greenbrook WTP Mannheim WTP Asset Management Water Efficiency 09/05/2006 09/05/2006 Current Status Water Supply Integrated Urban System Avg. Day (2002) • Average Day Demand Avg. Day (2003) Avg. Day (2004) Avg. Day (2005) 50 • Growth average 7 % from 2002 to 2005 45 • 10 % lower per capita consumption (June – Aug 2005) • System Capacity • Demand vs. System Capacity • Water Supply Unique Average Daily Consumption (Million Imperial Gallons) 40 • Maximum Day Demand 35 30 25 20 15 10 5 • Groundwater (80%) • Surface Water (20%) 0 Jan 09/05/2006 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 09/05/2006 1 Tri City Consumption Average Day (Imp.G) Water Demands & Capacity Maximum Day (Imp.G) 80 60 Production (IGPD) Consumption (Million Imperial Gallons) 60 40 30 ASR Phase 2 Average Demand Max. Day Demand Average Demand Projected Max. Day Demand Projected System Capacity 70 50 Ongoing Projects to Restore Lost Capacity of Water Sources Greenbrook Shut-Down Grand Reservoir + New Groundwater ASR Phase 1 50 40 30 20 20 10 10 - 0 1998 1999 2000 2001 2002 2003 2004 2005 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Year 09/05/2006 Implementation LTWS • Water Supply Projects ASR (10 MIGD Peak) • Greenbrook WTP • Construction 2009 • New ground water supply (5MIGD) – – – – Breslau Area Erbsville Area • Treatability & Predesign Projects • Detailed Report P&W in June % • Mannheim WTP (16 MIGD) W5 Cambridge East Breslau P16/W5 Restore Chicopee Ski Resort K42 • Optimization Project to restore capacity W14 K41 Chicopee Chicopee Area P16 Pinebush Well Field • Construction 2010 • Clemens Mill Well Field Water Supply Master Plan – Technical Update • Report Summer 2007 09/05/2006 kilometers 0 4 0 0.5 1 kilometres 8 Shades Mills Well Well Field 09/05/2006 • Asset Management • Ensure capacity is available when needed • Water Efficiency • Target 1.5 MGD by 2009 (6820 cubic meters/day) • Annual Budget $ 0.5 million annual • Update Master Plan June 2006 09/05/2006 2 Report: E-06-033 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Water Services TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: CONSULTANT SELECTION FOR THE WATER SUPPLY STRATEGY UPDATE FILE CODE: C04-30/P&W/WS.06 RECOMMENDATION: THAT the Regional Municipality of Waterloo enter into a Consulting Services Agreement with XCG Consultants Ltd. of Kitchener, Ontario, to provide consulting engineering services for the Water Supply Strategy Update, at an upset limit of $172,000 plus applicable taxes. SUMMARY: The Region’s Water Supply Master Plan (MP) provides a strategy for ensuring adequate water supply to the Region of Waterloo to 2041. Since its approval by Regional Council in May 2000, significant changes with planning, technical and regulatory issues have occurred. These changes will be addressed through an update of the MP. A Request for Proposal to provide engineering services by prospective consultants to undertake the Water Supply Strategy Update was advertised in local newspapers. Based on the Region’s Consultant Selection Policy, which includes a review of the Letter of Interest, detailed work plans, schedules and upset fee cost estimates provided by the consultants, the Consultant Selection Team recommends that XCG Consultants Ltd. of Kitchener, Ontario be retained to undertake this assignment at an upset fee limit of $172,000 plus applicable taxes. REPORT: Background In May 2000, the Long Term Water Strategy (LTWS) study was approved by Regional Council. This study provides direction on long term water supply with a planning horizon of 2041. The LTWS included a detailed water demand forecast, analysis of the existing system capacity and evaluation of numerous water supply alternatives and staging scenarios. These scenarios consisted of various water supply and storage combinations including: groundwater, surface water (Grand River and/or Great Lakes), and aquifer storage and recovery (ASR). The LTWS included the following key recommendations: • • • Immediate construction of a 22,700m3/d (5 MIGD) ASR facility; Construction of an additional 22,700m3/d (5 MIGD) ASR facility in 2007; Construction of 22,700m3/d (5 MIGD) of additional groundwater facilities in 2018; Page 1 of 5 May 2, 2006 • • • Report: E-06-033 Immediately pursue acquisition of a water taking permit, land for treatment and transmission facilities and other approvals/consultations/notifications necessary for the construction of a Great Lakes displacement pipeline (either from Lake Huron or Lake Erie); Construction of a 432,000m3/d (95 MIGD) displacement pipeline in 2035; and Continued use of groundwater to meet the requirements of the rural water supply systems. The impact of significant changes in planning, technology and regulations will be addressed by this update to the MP. Key changes are highlighted as follows: 1. The Provincial Places to Grow Act, has a growth plan for the Greater Golden Horseshoe, including the Region of Waterloo. Increased growth patterns will result in increased demand for water; 2. Improved technology has identified some decline in capacity at specific well fields and has impacted water taking and treatment methods; and 3. New legislation including the Great Lakes-St. Lawrence River Basin Sustainable Water Resources Agreement, the Clean Water Act, Safe Drinking Water Act, etc. will impact water taking and impose supply restrictions. Consultant Selection A Request for Expression of Interest to provide consulting engineering services for the Water Supply Strategy Update was advertised in the Kitchener-Waterloo Record, Cambridge Reporter and the Daily Commercial News on Friday, January 13, 2006. Five consulting firms responded to the advertisement by submitting an Expression of Interest. Three firms were short listed based on the Quality Factors and asked to submit detailed work plans and upset fees for this assignment. The three short listed consultants were: § § § Stantec Consulting Ltd. XCG Consultants Ltd. MacViro Consultants Inc. The Project Team involved in the consultant selection consisted of: § § § § N. Kodousek, Director, Water Services J. Cavalcante, Manager, Engineering and Planning, Water Services K. Yajima, Sr. Planning Engineer, Water Services C. Mathews, Principal Planner, Community Planning, Planning, Housing & Community Services Department The evaluation criteria used for selecting the successful consultant were consistent with the Region’s Purchasing By-Law. The evaluation criteria and their respective weightings were as follows: Quality Factors § Project Approach and Understanding (25%) § Experience of the Project Manager (25%) § Experience of the Project Support Staff (20%) § Experience on Similar Projects (15%) DOCS#274095 Page 2 of 5 May 2, 2006 Report: E-06-033 Equity Factors § Current Workload for Region (3%) § Local Office (2%) § Price Factor § Upset Price (10%) The Expression of Interest and Detailed Work Plans submitted by the three short-listed consultants demonstrated a good understanding of the project, capable project teams and experience on similar projects. After reviewing the Expressions of Interest, detailed work plans, schedules, and upset fees, XCG Consultants Ltd. was evaluated to have the highest overall score and presented the lowest cost estimate. Based on this evaluation, the project team recommends that XCG Consultants Ltd. be retained to undertake this assignment at an upset fee limit of $172,000 plus applicable taxes. Scope of Work The scope of work for this assignment includes: § § § § § § § Collection and review background information; Update of the water demand forecast; Update of the existing system capacity; Review of the current and advise on forthcoming regulatory requirements; Refinement of original assumptions and implementation scenario of the MP; Presentation of results to the public, Regional Council and the local area municipalities; and Preparation of the final report. Additional details relating to the major tasks in this assignment can be found in Appendix A attached. Schedule Subject to Council’s approval of this assignment, the proposed schedule for the assignment is approximately a 10 month period commencing in May 2006 and ending in March 2007. Consultant Upset Limit The upset limit for consulting fees and disbursements for the Water Supply Strategy Update is $172,000 plus applicable taxes. A breakdown of the successful consultant’s upset fee is included in Appendix A attached to this report. CORPORATE STRATEGIC PLAN: Completing the Water Supply Strategy Update supports Focus Area 1 of the Corporate Strategic Focus to Manage Regional Growth to Enhance Quality of Life. This project is consistent with the objective of ensuring Adequate Infrastructure Capacity to Meet Current Needs and Planned Growth in the Region of Waterloo. DOCS#274095 Page 3 of 5 May 2, 2006 Report: E-06-033 FINANCIAL IMPLICATIONS: The Region’s approved 2006 Water Capital Program provides a budget of $300,000 for preparation of the LTWS. The consulting assignment for completing the Water Supply Strategy Update is an upset limit of $172,000 plus applicable taxes within the budget allowance. The project is 100% financed through the Regional Development Charges. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: The Planning, Housing and Community Services Department and the Finance Department are involved in the preparation of the Master Plan. ATTACHMENTS Appendix 1 - Breakdown of Consultant’s Upset Fee PREPARED BY: Kaoru Yajima, Senior Planning Engineer APPROVED BY: Thomas Schmidt, Commissioner of Transportation and Environmental Services DOCS#274095 Page 4 of 5 May 2, 2006 Report: E-06-033 Appendix A – Breakdown of Consultant’s Upset Fee Task 1 Data Review and Update Water Demand Forecast $40,905 Task 2 Data Review and Update Existing System Capacity $28,700 Task 3 Review Current and Advise on Forthcoming Regulatory Requirements $36,365 Refinement of Original Assumptions and Implementation Scenario $30,886 Task 5 Presentation of Results $14,705 Task 6 Report Finalization $20,439 Task 4 Total Consultant Upset Fee: DOCS#274095 $172,000 Page 5 of 5 Report: E-05-099.3 G3 REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Transit Services TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: GRT FLEET MAINTENANCE UPDATE FILE CODE: C04-30, T19-80 RECOMMENDATION: For information. SUMMARY: In August 2005, a report was presented to Planning and Works Committee to outline the progress made in response to several recommendations contained in two consultant reports which were completed for Transit Services in 2004 as part of their review of operational effectiveness and regulatory compliance. The reports contained 79 recommendations most of which have since been completed. Regional Council directed staff to provide progress updates and several fleet update reports have subsequently been provided to document the ongoing progress in response to these recommendations. In addition, Regional Council directed that two external follow-up audits be conducted to monitor the progress on the consultants’ recommendations, and also an external compliance review be completed of bus purchasing, refurbishing and disposals to financial and purchasing policies. These reviews have all been completed and are attached as appendices to this report. A summary of the contents of each of these reports is provided below. The reports highlight that significant progress has been made since the initial reports were presented in late 2004. There were no outstanding safety related issues identified and there were positive references to GRT’s current state of operations and to the ongoing continuous improvement efforts underway. These improvement initiatives are intended to make sure operating practices are introduced and sustained to ensure the ongoing availability of a transit fleet which is maintained in a high quality, safe and effective manner. The financial audit of bus purchasing, refurbishing and disposals reveals that the Regional financial and purchasing polices were generally followed with some areas of non-compliance and some suggested improvements. The implementation of the Region’s new purchasing bylaw at the beginning of 2005 along with several changes to transit management practices have resulted in significant improvements. REPORT: In August 2005, a report was presented to Planning and Works Committee to outline the progress made in response to several recommendations from two consultant reports which were completed for Transit Services in 2004 as part of their review of operational effectiveness and regulatory compliance. Of the 79 recommendations contained in these two reports, most have been completed Page 1 of 7 May 2, 2006 Report: E-05-099.3 and the remaining items are actively in progress. Subsequently a number of additional fleet update reports have been provided to outline the ongoing progress in response to these recommendations. In addition, Regional Council directed that two external follow-up audits be conducted to monitor the progress on the consultants’ recommendations along with an external review of bus purchasing, refurbishing and for disposals to Regional financial and purchasing policies. These reviews have been completed and are attached as appendices to this report. A summary of the contents of each of these reports is provided below. Transit Maintenance Review – ENTRA Consultants In October 2004 ENTRA Consultants completed a review of operating practices in the transit fleet section and offered several recommendations to implement industry best practices to enhance the effectiveness of the fleet repair section at Grand River Transit. In November 2005 ENTRA returned to review the progress being made in accordance with their initial recommendations. This report is attached as Appendix A. ENTRA indicated; “Overall GRT has made commendable progress on implementing these recommendations. There is now an effective process in place, which has set GRT on the path to becoming a leader in fleet management practice.” The following is the Assessment Profile from their recent audit report which summarizes the progress to date for the 44 recommendations originally identified in their October 2004 report. The specific details of each of the recommendations and their current status are outlined in their attached report. Assessment Profile of Recommendations Successfully implemented – 26 Recommendations. Indicates implementation is complete. Those initiatives where ongoing performance monitoring is required to ensure continued success have been also noted. Satisfactory Progress – 12 Recommendations. Indicates the implementation is not fully complete but was at or above the expected level of completion given the complexity or duration of the task. Further Action Required – 2 Recommendations. Indicates the action was outstanding. Both of these items were considered lower priority initiatives and relate to the parts supply process which was recently transferred from transit services to the purchasing division. Early Implementation Stage – 4 Recommendations. Indicates the work had just begun on items which had been identified and prioritized as later stage tasks. ENTRA indicated there was no concern over their status. The report concluded with; “Implementing a process of change of the magnitude and scope achieved by GRT over the past year is a commendable effort, and has been achieved through the direct involvement of management and supervisory staff and the cooperation of staff.” The ENTRA fleet program recommendations continue to be managed and monitored by the Maintenance Steering Committee. Items which were recently identified as requiring ongoing monitoring will also be closely tracked. The remaining recommendations will be managed over the coming months to ensure their successful implementation is also achieved. Docs #276240 – v3 Page 2 of 7 May 2, 2006 Report: E-05-099.3 Audit of Bus Procurement Processes - Grant Thornton In December 2005 Grant Thornton LLP, Chartered Accountants were selected to conduct an audit of bus procurement process. The objective of this review was an evaluation of the processes used for; i) bus purchase transactions between 2001 and 2005 ii) bus refurbishment procurements between 2003 and 2005 iii) disposal of buses between 2000 and 2005 These transactions were then compared for compliance purposes with Regional procurement policies, guidelines, procedures and the purchasing by-laws. For the period 2000 until 2004 purchasing by-law 61-91 was used and then effective 2005, by-law 04-093 was used. A copy of their full report is attached as Appendix B and is briefly summarized below. Bus Purchases The audit reviewed all three bus purchase tenders completed since 2001 and concluded the tender process for each purchase was in compliance with the Region’s by-laws and purchasing policies. They recommended using a documented evaluation process, similar to the one used for the most recent bus purchases, whereby the bids are reviewed to determine if they are compliant to the Region’s bus specifications and in cases of non-compliance the financial impact is determined to build a business case for selection based on the overall lowest cost versus the lowest tender price. Bus Refurbishing The audit examined 25 bus refurbishment transactions which occurred between 2003 and 2005, representing approximately 70% or $1,089,836 of all work completed. Since 8 transactions were for nominal bodywork repairs the final sample was based on 17 major bus refurbishing transactions. The focus of this review included both how vendors were selected and how additional work was approved. The majority of the refurbishing occurred under purchasing by-law 61-91, since the work was completed before 2005. However 4 of the 17 refurbishments were measured against the new purchasing by-law 04-093. All of the identified issues of non-compliance occurred prior to the new purchasing by-law being enacted in 2005. The audit identified instances of non-compliance, to the former purchasing by-law, including cases where there were less than 3 quotes for work beyond $10,000, occasions where there was not a sealed tender bid for work expected to exceed $50,000 and also cases where extra work for more than $10,000 was completed, although three quotes were not secured. The report outlines the Bus Refurbishing program which was launched in 2004 to refurbish 49 buses or 25% of the fleet. A refurbishment program of this magnitude, while continuing to meet GRT service expansion goals, represented a significant undertaking. The distribution of this work was managed by employees in the fleet section at GRT, who were concerned with the expediency of repair work to ensure continued bus availability to meet service requirements. Since there were only four companies who performed bus refurbishments, contracts were often awarded without three quotes and provided to the contractor with available capacity. Major bus refurbishment is a complex process that can often take several weeks (4 to 6 weeks) to complete. Often, the complete scope of work required for a bus refurbishment is not obvious until the bus has been partly dismantled by the refurbisher. At that time, it is not practical to get multiple quotes from other companies to undertake the additional work which may be needed on a bus. The audit identified that the one company in particular often identified the need for additional work, not included in the original quotes or tenders. Docs #276240 – v3 Page 3 of 7 May 2, 2006 Report: E-05-099.3 In an effort to quantify the potential cost impact of this extra work, the total cost of the 7 refurbishments completed by this company were compared to the next lowest bid and the difference was calculated at approximately $60,000. The total cost for these seven refurbishments, including the extra costs was $598,058. What is unknown from this comparison is whether this work would have resulted in extra billings from other companies, had they been retained to conduct these refurbishments. In all cases, a Transit Services representative agreed that the work was needed, approved the work before completion, and verified the work was performed as required. Many of these issues were previously identified by transit management staff in 2004 and a number of process changes were implemented into the bus refurbishment procurement process during the latter part of 2004. These included a requirement for multiple bids for all bus refurbishing, having the bids forwarded directly to the purchasing department, the bid evaluation and selection process is conducted by purchasing in consultation with GRT and all bids now include potential optional items which may be discovered when the bus is dismantled along with the proposed hourly rate for this work. In addition extra work requires a new purchase requisition be completed once the work has been approved by a transit management representative. Finally, the audit reviewed four (4) bus refurbishment transactions from 2005 against the new by-law and determined all were compliant. This highlights the success of the changes introduced by transit management staff during 2004 in improving the refurbishment procurement process. Bus Disposals The audit also reviewed bus disposals between 2000 and 2005, in accordance with the Region’s bylaws and purchasing policies and determined all 17 transit bus disposals were in compliance. The total dollar value of the transactions related to the disposal of buses from 2000 to 2005 was $12,373. They recommended the disposal process could be enhanced by maintaining a list of surplus transit buses which have been disposed. This recommendation has been adopted by staff in the Purchasing division. Commercial Vehicle Operator Registration (CVOR) compliance - THSAO In October 2004 the Transportation Health and Safety Association of Ontario (THSAO) were engaged to conduct a legislative compliance review to the Highway Traffic Act, known as a Facility Audit. This report provided a number of recommendations to ensure compliance and also offered suggestions to implement additional industry best practices to enhance workplace safety. This organization is one of 14 sector specific associations dedicated to promoting safe workplace practices in businesses throughout Ontario. These groups are mandated and funded by the Workplace Safety and Insurance Board (WSIB) and are engaged in education, training, consulting and safety assessments. The THSAO is primarily dedicated to working with companies in the transportation sector and regularly provide CVOR compliance audits. Since they audit to a zero tolerance standard they indicate that their Facility Audit Reports will always result in findings and recommendations to assist organizations, like the Region of Waterloo, who wish to improve their safety effectiveness. In December 2005, THSAO returned to conduct a follow up review of the progress to date and to identify any areas of concern from a legislative compliance or an industry best practice perspective. This audit report is attached as Appendix C. The THSAO report noted in their introduction; “Numerous system improvements were observed throughout the course of this follow up review. System improvements include the hiring of an experienced planner/scheduler to assist in planning and scheduling of vehicle preventative Docs #276240 – v3 Page 4 of 7 May 2, 2006 Report: E-05-099.3 maintenance, a lock out system to ensure all safety related defects are repaired prior to the release of a vehicle, upgrading the hours of work tracking system and the issuing of numerous notices related to driver responsibilities.” There continue to be a few administrative issues identified in the following areas; General CVOR Administration The THSAO report recommends programs should be implemented across the transit services division. This resulted because the hours of work tracking system and the scheduling of preventative maintenance and MTO safety inspections were piloted in one location and then expanded to the other. Both of these systems are now operating at both transit operations facilities in Kitchener and Cambridge. Accident Program Administration As an industry best practice the THSAO is recommending the collision review process be amended to remove the assessment of discipline as a factor for consideration by the employee based Accident Review Committee. They are concerned the assessment of discipline, which is a management responsibility, may bias the ruling of driver culpability by the committee. They further suggest increasing the Committee’s emphasis on analyzing the accident and the situations leading up to it, as a means of gathering information to assist in developing employee training in accident prevention techniques. A revised Collision Investigation and Review process was recently develop by the Regions’ corporate health and safety staff and once implemented will result in the adoption of these recommended industry best practices identified in the THSAO report. Licensing Administration As identified in their previous report the THSAO recommends GRT’s bus operators be licensed as school bus drivers’ with a class B license because of the transportation provided to students at local high schools. This issue remains a grey area of interpretation to the Highway Traffic Act (HTA), for regular transit services; however there are plans to upgrade all transit operators to a B license before the end of 2007. Currently about half of the bus operators have this qualification since many employees were recruited with this class of driver license. The report also identified one case where a school charter trip was conducted with an operator who held a class C rather than a class B (school bus) license and the legislation is clearer for these trips. As a result all future school charter trips will be driven only by operators with a school bus or class B driver license. From a best practice perspective the THSAO also recommended a system be implemented to regularly road test all employees who drive Regional equipment and to develop another system to notify employees and their supervisor when their license is due to expire. Hours of Work Administration A system to track hours of work was developed in 2005 which monitors hours to the Employment Standards Act limit of 64 hours in a 7 day period. However when charter work is performed the limit is reduced to 60 hours in accordance with the Highway Traffic Act. The tracking system will be amended to include this exception. Docs #276240 – v3 Page 5 of 7 May 2, 2006 Report: E-05-099.3 Other recommendations included ensuring employee’s hours of work outside GRT are provided in a timely manner and recorded since they must be included in the maximum hours of work. A system was developed in 2005 and reminders are posted for information, however they suggest employees continue to be regularly reminded of their obligation to provide this information. Also they identified the tracking system should be expanded to include all employees (ie mechanics who drive buses during road tests) who drive Regional equipment. This amendment to the tracking system is currently being developed Preventative Maintenance Administration The report acknowledges the introduction of the preventative maintenance program, scheduling of MTO inspection and PM assignments and the introduction of improved vehicle files and the new lock out system in the transit fleet section. Their four recommendations focused on the following items. Ensuring all vehicles continue to be inspected and maintained in accordance with the new program and all supporting information attached to the work order record. Also ensure the completeness of all information. This was identified due to recording discrepancies with the vehicle odometer readings. A new fuel dispensing system, which will be operational in the coming weeks, will enhance the integrity of the data which is currently recorded manually. Thirdly, consider modifying the lock out policy to include all highway/public road use rather than the current reference to ”in revenue service” This editorial amendment has been made to the policy. Finally, continue to monitor drivers to ensure they conduct effective pre-trip inspections. This function is closely monitored and reported on daily by transit operations supervisors. The THSAO concluded; “Extensive improvements were made between the 2004 and 2005 audit. Some systems are extremely complicated and take many months to resource and implement. Ongoing discussions strongly suggest that even during the development of this report, improvements continued to be made.” CORPORATE STRATEGIC PLAN: The Regional Strategic Plan, approved by Regional Council in July 2004, and the Transportation and Environmental Services Department Strategic Plan include a number of objectives and actions related to Transit Services’ role in ensuring a High Quality Regional Transportation System and also ensuring Operational Effectiveness and Efficiency. FINANCIAL IMPLICATIONS: The financial impacts of implementing the recommendations from the Consultant reports have been included in the 2006 budget. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: The Finance and Corporate Resources Departments have been consulted during the preparation of this report. Docs #276240 – v3 Page 6 of 7 May 2, 2006 Report: E-05-099.3 ATTACHMENTS: Appendix A – ENTRA Consultants – Transit Maintenance Review – March 2006 Appendix B – Grant Thornton LLP, - Audit of Bus Procurement Processes – March 2006 Appendix C - THSAO – Facility Audit Follow up Report – April 2006 PREPARED BY: Eric Gillespie, Director Transit Services APPROVED BY: Thomas Schmidt, Commissioner, Transportation and Environmental Services Docs #276240 – v3 Page 7 of 7 May 2, 2006 Report: E-05-099.3 APPENDIX A ENTRA Consultants Grand River Transit Transit Maintenance Review Summary Status Report March 2006 Docs #: 278282 Grand River Transit Transit Maintenance Review Summary Status Report March 2006 Excellence in Transportation Planning Grand River Transit Transit Maintenance Review Summary Status Report In October 2004, ENTRA Consultants produced a working paper on the findings and preliminary recommendations for the Grand River Transit Maintenance Review. IN conjunction with staff and management at GRT, an action plan to address those recommendations was developed, beginning in November 2004, with implementation of major action items beginning in 2005. Throughout 2005, ENTRA performed periodic reviews of the progress of the implementation. In November 2005, GRT requested ENTRA to complete a comprehensive review of the progress and results of the new programs. This report summarizes the results of that review. This assessment is presented with a review of each of the recommendations from the October 2004 report, in the same format as they were presented in that report. 1. Summary Conclusion Implementing a process of change of the magnitude and scope achieved by GRT over the past year is a commendable effort, and has been achieved through the direct involvement of management and supervisory personnel and the cooperation of staff. Overall GRT has made commendable progress on implementing these recommendations. There is now an effective process in place, which has set GRT on the path to becoming a leader in fleet management practice. As part of this evolution, each of the following recommendations and their implementation need to be constantly monitored with processes and procedures adjusted as necessary. Emphasis should be placed on “Team Building” and “Employee Involvement” to ensure all maintenance and service personnel can work together to continue to improve work performance and overall efficiency. ENTRA Consultants 2006-03-29 Page 1 2. Assessment Summary In the following sections, the original recommendations are presented in their original form, and italicized in this report. Each recommendation is then followed by a summary of the November 2005 status of progress in this area. This assessment is followed by a summary status statement in one of the following categories: ~ Successfully implemented (26 recommendations): indicates that the implementation was complete, and has been successful. Where the recommendation also indicates that monitoring is required, this indicates that the area is a key function for on-going performance monitoring. ~ Satisfactory Progress (12 recommendations): indicates that implementation was not yet complete or requires additional follow-up, but progress was at or above the level expected, given the complexity or duration of the task. ~ Further Action Required (2 recommendations): indicates that action on these items had been deferred, and was still pending. Both items in this category relate to parts supply processes, and are considered lower priority items. ~ Early Implementation Stage (4 recommendations): indicates areas where work had just begun, and had not progressed sufficiently to form a proper assessment. In each case, these represent recommendations that were identified as later-stage tasks, and there is no concern over their status. 2.1 Preventative Maintenance Recommendations A formal preventive maintenance program be developed as soon as possible A program was developed, with the assistance of a mechanics working group, based on the industry best practices and Ministry of Transportation requirements. The format of the document is such that each item to be inspected must be “checked-off” when completed. This preventive maintenance program formed the basis for the specific action plans and assessment presented here. Once the new preventative maintenance program is developed, the program be strictly followed The new maintenance procedures which include the MTO requirements were introduced in May 2005 and the regular PM program was initiated in June of 2005. All of these programs are now performed as follows: ~ MTO Annual – every 12 months – includes a complete brake safety inspection ~ MTO Semi Annual – every 6 months ~ PM Inspection -- every 10,000 KM -- includes oil and filter change. Items that are not required to be changed every 10,000 Km’s, are scheduled in multiples of 10,000 kilometres. ENTRA Consultants 2006-03-29 Page 2 Assessment Summary: Successfully implemented, ongoing monitoring required The practice of “fix when broken” for transmissions, engines and other components cease as soon as possible; A new component rebuild strategy be developed as quickly as possible and GRT purchase one or two replacement engines and transmissions for the shop, and a‘ remove and replace” program be established. This program has started for small components, however, for the larger components such as engines and transmissions, a “kilometre-failure rate” bench mark has yet to be developed. Once the planner/ scheduler becomes more familiar with the vehicle history, she will be able to research and determine an appropriate benchmark for engine and transmissions. This will allow both a schedule and a budget to be developed for the change out of these components. Currently, GRT is limited for space in the maintenance area and therefore major engine repair and removal should continue to be contracted out. However, consideration should be given to budget for a spare transmission and engine, for the newer transit buses. This would assist in a faster vehicle in house repair turn around. Assessment Summary: Satisfactory Progress 2.2 Work Plans GRT establish a process for the development of annual, monthly, weekly and daily work plans for its shop A maintenance planner/ scheduler started in the fall of 2005 and work plans are now being developed with the initial focus on preventative maintenance. Once all the schedules for the preventive maintenance programs are firmly established, other programs will be initiated. Assessment Summary: early implementation stage, continued review necessary following implementation All vehicle kilometers be recorded on a daily basis when the vehicles are serviced on the fuel island: To accurately schedule Preventive Maintenance programs, daily readings of vehicle kilometers are recorded daily and entered into the database for the maintenance programs. This information is now recorded on a nightly on the service-line check sheet, and entered to IFIS. Assessment Summary: Successfully implemented, ongoing monitoring required ENTRA Consultants 2006-03-29 Page 3 Standard times be established as a basis for the annual, monthly, weekly and daily work plans: For the supervisory staff and the planner/ scheduler to forecast and plan the work schedule for the maintenance shop, it is important to know the time requirement for the planned work. A working group committee, consisting of mechanical and supervisory staff, has been established to determine reasonable times required for jobs performed in the maintenance shop. Committee meetings were held during December and this project should be completed in February 2006. Assessment Summary: Satisfactory Progress Supervisors meet at least once per week to review progress during the week, and to plan for next week and next month Due to management and supervisory staff changes, work scheduling in the shop has been somewhat slow to take hold. However, the maintenance manager position is now permanently filled and supervisory planning meetings have been initiated. These meetings will be scheduled on a regular basis in the near future. Assessment Summary: Satisfactory Progress The Parts supervisor attend these “production meetings” The parts supervisor has not been involved in these meetings, and has continued to rely on information from other departments for direction. Assessment Summary: Further Action Required The practice of allowing staff to pick and choose their work cease as soon as possible, so that supervisors can establish priorities for meeting daily and weekly targets, and for ensuring that daily service commitments are met. This practice has stopped. Supervisors on duty on duty now assign work with the assistance of the scheduler/ planner, supervisors know in advance what Preventive Maintenance work and MTO inspections are due and work can be assigned to personnel best suited for certain type of work. Assessment Summary: Successfully implemented, ongoing monitoring required 2.3 Work Activities A strategy be developed with the trades staff to increase the frequency of jobs that are started by one shift to be completed by the next shift Licensed mechanics are required to sign the MTO’s safety inspection certificate, and in some cases are reluctant to take over uncompleted work performed by another mechanic. A procedure has now been implemented to allow the “signing” mechanic to re-inspect the work performed by the other mechanic to ensure the work was completed properly. ENTRA Consultants 2006-03-29 Page 4 This process will allow work started on another shift to be continued by the following shift and therefore not waste valuable hoist capacity. Assessment Summary: Successfully implemented, ongoing monitoring required Vehicle history be made available to staff when they initiate work on a vehicle Vehicle history files are now available to mechanical staff and a computer has been located on the shop floor allowing mechanics to access vehicle files and research past vehicle problems. Assessment Summary: Successfully implemented, ongoing monitoring required A consistent policy regarding which vehicles or which jobs will be contracted out be established and followed A new policy has been established which dictates that only major bus body/ structural refurbishing and MTO inspections (when necessary) be contracted out and the maintenance manager be part of the decision process. Assessment Summary: Successfully implemented, ongoing monitoring required A consistent policy regarding how and why change-offs will be conducted be established and shared with Operations A bus change-off protocol has been developed and introduced to operations. This will be an ongoing process and education to new operators. Although it is a bit early to compare year over year to date, the number of nonmechanical “change-offs” in 2005 (up to the end of October) showed a 20 percent improvement over 2004. Assessment Summary: Satisfactory Progress The tire program be reviewed for cost effectiveness, bogey, re-grooving, siping, tire pressure monitoring Tires are now “bumped” nightly on the service line to ensure tires are not flat. Also tire pressures are checked and adjusted on each PM and MTO inspection The cost effectiveness of a re-grooving and siping program has not been completed at this time. Assessment Summary: Satisfactory Progress A formal cleaning program (including training for cleaners) for transit vehicles be established, including the requisite number of staff A formal detailed cleaning program has been developed and initiated, including a scheduled timing cycle and staff trained to ensure a unit is to a standard that reflects a positive corporate image of GRT to the public. ENTRA Consultants 2006-03-29 Page 5 During the summer period, several students were hired to complete a thorough cleaning of the GRT fleet. This program is expected to bring the buses up to a “clean standard” and once completed, regular GRT staff should be able to maintain this standard. Buses should be cycled approximately every 3 months for a detailed cleaning. High mileage vehicles may have to be cycled more often. Assessment Summary: Satisfactory Progress 2.4 Staff Levels GRT consider pre-hiring two additional mechanics to assist through the transition period from the current reactive to the future proactive maintenance work plan: Two mechanics were pre- hired to replace two retiring mechanics. Further, to bring GRT up to industry standard for bus to mechanic ratio, four additional mechanics were hired (approved in 2005 budget). With these additional mechanics, mechanic staff can be dedicated to Preventive Maintenance work to ensure that PM’s do not fall behind schedule. Additional mechanics are included in the 2006 budget Assessment Summary: Successfully implemented The current vacant supervisory position be converted to a maintenance planning supervisor position This was approved and a scheduler/ planner person started in late August of 2005. Assessment Summary: Successfully implemented 2.5 Staff Scheduling Current staff schedules be maintained at this time, and that they be reviewed once the formal preventive maintenance programs and other work plans have been developed, with the following noted exceptions: ~ the specific pros and cons of the 10-hour shifts be reviewed for effectiveness and efficiency and ~ consideration be given, to operating the South Garage on weekdays onlyA working group has been formed to review the ten-hour shifts and its effectiveness and also to ensure it meets the Ministry of Labor guidelines. Assessment Summary: early implementation stage, continued review necessary ENTRA Consultants 2006-03-29 Page 6 2.6 Garage Equipment and Layout A detailed review be conducted of the garage layout and equipment, including the fueling, servicing and cleaning lines The review was conducted and several upgrades and improvements are being initiated to increase productivity and safety. See Hoists and Service line. Assessment Summary: Successfully implemented, ongoing monitoring required The decision to install three In-ground hoists in the North Garage be reviewed as soon as possible, and the alternatives to the in-ground hoists, such as wheel lifts or scissor lifts be explored This decision was reviewed and it was changed to the following: ~ -one portable wheel lift ~ -two in-ground hoist Assessment Summary: Successfully implemented Some form of separation wall or curtain be installed to keep the dust from the body area from the mechanical work area: Discussions are currently underway with the body shop staff to determine the best practical method to achieve this objective and the appropriate funds to be included in the 2006 budget. Assessment Summary: early implementation stage, continued review necessary Information regarding all safety inspections of shop equipment should he reported at the monthly Occupational Health and Safety Committee meetings and posted In an appropriate location0 This information is now passed on to the Safety Committee and all information is posted. Assessment Summary: Successfully implemented 2.7 Service Line The servicing data collected at the South Garage be linked with or recorded into the IFIS system The Data from the South garage is now linked to the IFIS system Assessment Summary: Successfully implemented ENTRA Consultants 2006-03-29 Page 7 Service attendants at the North Garage service line record bus kilometers daily — either into the card reader at the pumps, or on paper at the service line The service attendants are currently recording the kilometres onto the paper checklist. This will be eliminated as soon as the new computerized card readers are installed. ( due to be completed by end of the year) Assessment Summary: Satisfactory Progress The sheet at the North Garage service line be revised by eliminating the numerous columns regarding duties, and replacing the columns with: employee number, bus number, kilometers, oil added (check mark only), and antifreeze added (check mark only) The sheet was revised and only necessary information is recorded. Assessment Summary: Successfully implemented The North Garage service line be upgraded, with input and suggestions from the service attendants Several meetings were held with the service attendants to discuss their input and the requirements to improve the work environment of the fueling area and the general servicing of the vehicles. Numerous suggestions were identified and the majority have or will be implemented, including: ~ The fueling and service lane has been upgraded to allow two buses to be fueled at one time ~ Additional fuel hoses were installed on the opposite wall to fuel the smaller buses that have the fuel tank opening on this side, eliminating the need to drag the fuel hose across the bay. ~ Overhead fuel hoses are being installed to enhance the movement of the long, heavy fuel hoses. ~ Two new computerized fuel pump card readers are being installed. The employee enters the vehicle-kilometres and his employee number to begin the fueling process and the system has “safeguard limits” built-into avoid entering the wrong mileages. These new readers will transmit all the fueling data into the IFIS system data base and the mileages can then be used to schedule the Preventive Maintenance programs. ~ Additional oil, windshield washer fluid and anti-freeze dispensers were installed to assist in servicing the smaller buses. Assessment Summary: Satisfactory Progress The service attendants be trained on servicing the new Nova Bus vehicles as soon as possible: All service attendants have been trained on the new buses. Assessment Summary: Successfully implemented ENTRA Consultants 2006-03-29 Page 8 The service attendants be issued tire pressure gauges (and be trained in their use), new brooms, flashlights, and any other small tools as suggested by service attendants The required equipment has been issued, however, tire pressure gauges were not introduced; instead the service attendant will “bump” tires on a nightly basis. Assessment Summary: Successfully implemented A roof be installed over the outside fuelling station: External fueling is the exception and the addition of a roof has been deferred for future review as part of the facility expansion in 2007. Assessment Summary: Not Applicable Consideration be given to lowering the fare box receptacles to ground level, so that service attendants will no longer be required to use stairs to service the fare boxes This has been completed. Assessment Summary: Successfully implemented Defective or hard-to-read hub odometers be repaired or replaced: This will not be necessary, since the “odometer” reading will be used for recording mileages. Assessment Summary: Not Applicable Hire 2 additional service attendants for the North Garage, and use North Garage service attendants as South Garage back-ups Completed—Two additional attendant have been hired. Assessment Summary: Successfully implemented With the additional service attendants, consider options for spot cleaning on the service island (rather than just sweeping) continue with the South Garage service attendants process of checking engines until the new PM program is operational, and then review this process vis-àvis the new PM program to determine its continued effectiveness once the new PM program is in place The spot cleaning has been tried and it is workable providing that the required service attendant are at full complement. Staffing has been a problem in this area in the past and at best, the system had operating at about 65 percent to 70 percent, making it difficult to perform additional cleaning duties other then the basic sweeping. Additional resources have added as part of the 2006 budget. The South Garage will continue the current process. Assessment Summary: Satisfactory Progress – further monitoring required following new staff additions ENTRA Consultants 2006-03-29 Page 9 Consider installing garbage containers in all buses and encouraging customers to use them, and operators to dump them two or three times per shift All buses now have a container for garbage. Assessment Summary: Successfully implemented Consider sweeping the buses in the service line rather than in the parking garage, in order to increase efficiency The sweeping is completed just prior to entering the service bay, while waiting for serviced buses to clear the service lane. Assessment Summary: Successfully implemented Consider a North Garage “parking attendant” (one of the service attendants) to direct operators from 17:30 to 19:30 on weeknights. This duty is being performed by a person who is on modified- light duty. This practice should be monitored to ensure its effectiveness and to determine if dedicated resources are required. Assessment Summary: Satisfactory Progress – monitoring required 2.8 Parts Supply and Inventory Management A series of parts supply performance indicators be developed, recorded and shared monthly with the maintenance department and senior GRT management The parts department is currently performing a review with the finance department. Assessment Summary: early implementation stage, continued review necessary following implementation The current value of inventory be reviewed vis- a-vis the annual work plan to ensure that the parts rooms are not overstocked This is currently under review. It is important that the parts supervisor be aware of what the maintenance department is planning re special projects and such, and imperative that a representative from stores attend the weekly planning meetings to ensure that material is at hand. The Region’s Finance Department completed a review of the parts supply function and has determined that it should be centralized as part of the regional corporate structure. Once this transition is complete, GRT should monitor to ensure the continued effective supply of parts when required. Assessment Summary: Further Action Required ENTRA Consultants 2006-03-29 Page 10 2.9 Maintenance Management System GRT maintenance supervisory and clerical staff be fully trained on the IFIS system The current staff and the new scheduler/ planner have now been trained on this system and this will be an on-going process. Assessment Summary: Successfully implemented, ongoing monitoring required A supervisory or management person, or persons, be held responsible to ensure that data is accurately recorded in the IFIS system Currently all information recorded into the IFIS system is performed by supervisors and the maintenance clerk. The scheduler/ planner checks to ensure that the information is entered properly. Assessment Summary: Successfully implemented, ongoing monitoring required A set of formal Key Performance Indicators be developed to measure the effectiveness and efficiency of the GRT Maintenance Department A number of indicators have been developed to track Preventive Maintenance, MTO inspections and in-service bus breakdowns or change-offs. More indicators and performance measures are being developed to give management the tools to see where improvements are occurring and where more are necessary. Assessment Summary: Satisfactory Progress 2.10 Staff Training and Human Resources A comprehensive technical skills training program be developed for GRT maintenance staff, consisting of individual training courses based on current and future needs Staff be provided opportunity to practice new skills on the job: The maintenance manager is currently gathering information on past employee training and future requirements to ensure that new skills can be utilized on the job. The required funding for the training courses will be included in the 2006 budged. Assessment Summary: Satisfactory Progress A comprehensive internal communications program for GRT maintenance staff be developed jointly with staff A new bi-monthly newsletter “The Maintenance Monitor” has been developed informing staff of all the latest developments in the transit and maintenance area. Assessment Summary: Successfully implemented ENTRA Consultants 2006-03-29 Page 11 2.11 North and South Garages Management and staff at GRT maintenance recognize that there is one maintenance department with two garages that need to work together to address the future success of the maintenance department: All maintenance programs are being implemented at both garage locations and supervisory meetings include staff from all locations. Mechanical staff is also to move between locations when the need arises. Assessment Summary: Successfully implemented 2.12 Building Maintenance GRT meet with the Region’s building department in an attempt to streamline building maintenance processes The GRT has meet with the Regional Building department to ensure GRT maintenance department repairs are performed by the building department in a timely manner. Assessment Summary: Successfully implemented, ongoing monitoring required 2.13 Vehicle Purchases and Vehicle Retirements GRT form a Bus Specification Committee to plan the next vehicle purchase: The committee was formed prior the last bus order and input was received. Assessment Summary: Successfully implemented GRT review the effectiveness of the Bus Specification Committee work after the next vehicle purchase has been completed This committee will meet after some the next bus order has been received and operators and maintenance personnel will be given an opportunity to review the changes recommended by them for the order. Assessment Summary: Successfully implemented 2.14 Conclusion All of the above recommendations and their implementation need to be constantly monitored with processes and procedures adjusted as necessary. Emphasis should be placed on “Team Building” and “Employee Involvement” to ensure all maintenance and service personnel can work together to continue to improve work performance and overall efficiency. Implementing a process of change of the magnitude and scope achieved by GRT over the past year is a commendable effort, and has been achieved through the direct involvement of management and supervisory personnel and the cooperation of staff. ENTRA Consultants 24-31Brep06-03-29StatusRepREV: 2006-03-29 Page 12 May 2, 2006 Report: E-05-099.3 APPENDIX B GRANT THORNTON Grand River Transit Audit of Bus Procurement Processes To the Chair and Council of the Region of Waterloo March 24, 2006 Docs #: 278314 Audit of Bus Procurement Processes To the Chair and Council of the Region of Waterloo March 24, 2006 Grant Thornton LLP Chartered Accountants Management Consultants AUDITOR’S REPORT To the Chair and Council of the Region of Waterloo We have audited the Region of Waterloo’s compliance with purchasing By-law 61-91 and By-law 04093 and the related purchasing practices of the Region for all of the bus purchase procurement processes from 2000 to 2005, bus refurbishments procurement processes for major repairs and refurbishments from 2003 to 2005, and all of the disposal of buses during the period 2000 to 2005. Our responsibility is to express an opinion on the Region’s compliance with the purchasing By-law 61-91 and By-law 04-093 and the related purchasing practices based on our audit. We conducted our audit in accordance with the standards for assurance engagements of the Canadian Institute of Chartered Accountants. Those standards require that we plan and perform an audit to obtain reasonable assurance whether the Region’s compliance with By-law 61-91 and 04-093 and related purchasing practices are free of material misstatement. Our audit includes examining, on a test basis, evidence supporting the compliance with the established criteria and any related disclosures. In our opinion, the bus tender process was in compliance with the Region’s By-law 61-91 and By-law 04-093 and the related purchasing policies. In our opinion, the Region complied with the bus refurbishment procurement process for transactions conducted under By-law 04-093. In our opinion, the bus disposal process was in compliance with the Region’s By-laws and purchasing policies. We noted certain instances of non-compliance with the Region’s purchasing By-law 61-91 in the bus refurbishment process. These instances of non compliance are detailed in the attached report. Hamilton, Canada March 24, 2006 Suite 1040 Standard Life Centre 120 King Street West Hamilton, Ontario L8P 4V2 T (905-525-1930 1-800-858-3092 (Ontario) F (905) 527-4413 E Hamilton@GrantThornton.ca W www.Grant Thornton.ca Canadian Member of Grant Thornton International Grant Thornton LLP Chartered Accountants Audit of Bus Procurement Processes March 24, 2006 Contents Executive Summary ......................................................................................................................................1 Background and Objectives ......................................................................................................................1 Conclusions...............................................................................................................................................2 Background…………………………………………………………………………………………………4 Our Assignment ............................................................................................................................................5 Scope.............................................................................................................................................................6 Approach.......................................................................................................................................................7 Findings Bus Purchase Procurement Process - Assignment #1……………………………………………………9 Bus Refurbishment Process - Assignment #2…………………………………………………………..12 Bus Disposal Process - Assignment #3…………………………………………………………………22 Audit of Bus Procurement Processes March 24, 2006 1 Executive Summary The Chair and Council, Region of Waterloo, 150 Frederick Street, 4th Floor, Kitchener, Ontario, N2G 4J3. Dear Regional Chair Seiling and Members of Council: BACKGROUND, OBJECTIVES, AND CONCLUSIONS The Council of the Region of Waterloo directed the Region’s administration to undertake an external audit of certain business transactions of Grand River Transit (“GRT”) relating to the purchase of buses, the refurbishment of buses and the disposal through sale of buses and that the external auditor was to provide a report back to the Council thereon. In December 2005, the Region issued a call for proposals (Proposal #P2005-52) pursuant to the direction of Council. Grant Thornton LLP, a national chartered accounting firm, was selected on January 16, 2006 to conduct the engagement and report the results to Council. The objectives of the audit were to evaluate directly, using suitable criteria, the transactions under review and the compliance with policy and procedures and the applicable purchasing By-law at the time for: 1) all of the bus purchase procurement processes in this period (Tender 2001-128 in 2001, Tender 2003114 in 2003, and Tender 2005-130 in 2005); 2) bus refurbishing procurement processes for major repairs and refurbishments from 2003 to 2005; and 3) all of the disposal of buses during the period 2000 to 2005. The deliverables of the audit included a reporting on the compliance with purchasing By-laws and practices within the Region and providing an evaluation of the policies and procedures utilized in each of the three components of the assignment. As well, the report was to indicate any potential non-compliance with key portions of the purchasing By-law. From 2000 to 2004, the transactions were considered in relation to the Region’s purchasing By-law 6191. Effective for 2005, the Region enacted purchasing By-law 04-093 and the transactions were measured against this new standard. Audit of Bus Procurement Processes March 24, 2006 2 CONCLUSIONS BUS PURCHASES In our opinion, the bus tender process was in compliance with the Region’s By-laws and purchasing policies. For the bus purchase tenders examined prior to 2005, we did note that the tendering process could have been more robust by enhancing the documentary evidence in the following areas: I. It would have been desirable to completely document the Region’s evaluation of the bids, the bidder’s compliance with the detailed specifications, and the financial impact of any noncompliant components; and II. The business case for selecting the successful bidder should have been clearly supported and documented to show that the bid represented the lowest overall cost and not just the lowest overall price. BUS REFURBISHMENTS In our opinion, the Region complied with the bus refurbishment procurement process for transactions conducted under the new purchasing By-law 04-093 in 2005. We did note instances of non-compliance with the Region’s purchasing By-law 61-91 in the bus refurbishment process, including: I. RFP’s where less than 3 quotes were obtained when work was expected to exceed $10,000; II. RFP’s for refurbishments when the cost was expected to exceed $50,000 but sealed tenders were not obtained; and III. Instances where additional costs exceeded $10,000 but three quotes were not obtained. We understand from management that in certain situations where 3 quotes were not obtained, it was owing to the circumstance whereby the usual suppliers of the refurbishments were already working on GRT buses and the work was awarded to a supplier that had capacity at that time. We observed that sealed tenders are now obtained as required under By-law 04-093. In cases for which the vendor discovered extra work was required, the Region approved and paid for these extras totaling $162,359. If the next lowest bid had been accepted and no additional work discovered, the total expenditure would have been $60,000 less. For clarity, all of the instances of non-compliance occurred with transactions applied under By-law 61-91 and there were no instances of non-compliance noted with transactions applied under By-law 04-093. Audit of Bus Procurement Processes March 24, 2006 3 BUS DISPOSALS In our opinion, the bus disposal process was in compliance with the Region’s By-laws and purchasing policies. There were 17 transit bus disposals in the period 2000 to 2005 and only approximately $12,000 was involved in this activity. The bus disposal process could be enhanced by adopting the following best practice: I. A list of surplus transit buses should be maintained by the Purchasing division to enhance its ability to track transit bus disposals. CHANGES IN 2005 Our review covered the time period from 2000 to 2005 and considered the policies and procedures that were governed under the By-law in effect at the time. The Region enacted the new purchasing By-law 04-093 effective January 1, 2005, and implemented revised policies and processes in Transit Services. We have concluded that the bus procurement, bus refurbishment and bus disposal processes are more comprehensive than the procedures that were followed under By-law 61-91. We understand that improvements were implemented by the Purchasing division for 2005 and we observed that the documentary evidence supporting the purchasing procedures is much more substantial after these enhancements came into practice. Thank you for the opportunity to provide professional services to the Region of Waterloo. Should you have any questions regarding our report, please contact us. Yours truly, Grant Thornton LLP Evan McDade, CA.CBV Partner jem/jm Audit of Bus Procurement Processes March 24, 2006 4 Report to Council on External Audit of Bus Procurement Processes The Chair and Council, Region of Waterloo, 150 Frederick Street, 4th Floor, Kitchener, Ontario, N2G 4J3. Dear Regional Chair Seiling and Members of Council: Background In 2000, the Region of Waterloo assumed operation of the transit system of the cities of Cambridge and Kitchener and consolidated these operations into a single transit system for the Region known as Grand River Transit (“GRT”). Since then, GRT has experienced rapid growth to provide increased levels of service to the residents of the Region. The expansion of service, including increases to the fleet of buses, together with replacements and refurbishments of the older fleet, has resulted in increased expenditures for purchase of buses and maintenance and refurbishment of buses. Several studies and reviews have been undertaken for the Transit Services Division to determine the state of the fleet and look for opportunities for improvements in practices. The Region’s purchasing division and GRT’s management are proactively committed to improving the purchasing and operating processes. In 2005, changes were made to the internal controls around bus refurbishment procurement to prevent extra billings and to maintain the integrity of the procurement processes. The Council of the Region of Waterloo directed the Region’s administration to undertake an external audit of certain business transactions of Grand River Transit during the years 2001 to 2005. The purpose of the audit procedures and the findings follow in this report. Audit of Bus Procurement Processes March 24, 2006 5 Our Assignment We were engaged under your RFP #2005-52 to provide a Section 5025 Report to Council. A 5025 Report is a direct reporting engagement where the auditor will evaluate directly, using suitable criteria, the transactions which are under review and the compliance with policy and procedures in these circumstances. The Region desired a high level of assurance from the review and concluded that an audit engagement is appropriate in the circumstances. To that end, we reviewed all of the bus tenders, all of the bus disposals, and approximately 70% of the dollar value of the bus refurbishments for the period under review. Therefore, the audit did achieve the high level of assurance that it was seeking. The objective of this engagement was to audit specific bus purchasing, bus refurbishing and bus disposal transactions in the years 2000 to 2005 to determine if the Region’s procurement policy, guidelines, procedures and By-laws were followed and to provide an audit report to Council on the results of this review. There were three components to this assignment: 1) A review of all of the bus purchase procurement process used for the acquisition of buses, looking at all the tenders that were issued in this period (Tender 2001-128, Tender 2003-114, and Tender 2005130); 2) A review of the bus refurbishing procurement process used for the major repairs and refurbishments of buses in the GRT fleet from 2003 to 2005; and 3) A review of all the disposal of buses during the period 2000 to 2005. Each of the three components of the assignment is specifically addressed in our report. Audit of Bus Procurement Processes March 24, 2006 6 Scope The review of the bus purchase procurement process included all the tenders that were issued during this period: Tender 2001-128, Tender 2003-114, and Tender 2005-130. The bus refurbishment review included sampling transactions occurring during the period January 1, 2003 to December 31, 2005 totaling approximately $1.55 million. The review of all the disposal of buses covered the period between 2000 and 2005. The actual transactions subject to this audit are as follows: Bus purchases Tender 2001-128 (Two awards totaling 30 buses) $13,731,000 Tender 2003-114 (Two awards totaling 34 buses) 15,998,000 Tender 2005-130 (One award totaling 12 buses) 5,139,000 $34,868,000 Bus refurbishment 2003 - 14 transactions $ 222,197 2004 - 47 transactions 987,519 2005 - 31 transactions 345,767 $ 1,555,483 Disposals 17 transactions from 2000 to 2005 $ 12,373 Audit of Bus Procurement Processes March 24, 2006 7 Approach Our overall approach to the engagement included the following steps: 1. Initial interviews with senior Region personnel in the Finance department, the Internal Auditor, and senior personnel at Grand River Transit; 2. Initial interviews with the Regional Chair, the Chair of the Planning and Works Committee, and the Chair of the Administration and Finance Committee; 3. An opportunity to meet with individual Councillors was available; 4. A review of background material to confirm our understanding of the systems, processes and protocols put in place related to the procurement, refurbishment, and disposal of buses; 5. The development of an audit plan to design appropriate procedures to test transactions in each area of the assignment; 6. Additional interviews to determine the processes actually followed from 2000 to 2005 in procuring, refurbishing, and disposing of buses; 7. An examination of Tender 2001-128, Tender 2003-114, Tender 2005-130 and review of documentation associated with these tenders including instructions to bidders, copies of bids, addendums, purchase orders, invoices, communications with respect to design changes and negotiations on closing, inspection reports and receiving documents; 8. Receipt of a listing of refurbishment transactions in 2003, 2004 and 2005 and a selection of a statistical sample of transactions and supporting documentation for analytical and compliance procedures; 9. An identification of specific bus refurbishments to be evaluated as part of the audit of refurbishments; 10. A review of documentation relating to known bus disposals; 11. A review of the work plan initially communicated to the Region on proposing for the engagement; 12. Modification of the above procedures as appropriate; and 13. A review of each of the assignments was directed by the requirements of the proposal document. Audit of Bus Procurement Processes March 24, 2006 8 Results BUS PURCHASE PROCUREMENT PROCESS - ASSIGNMENT #1 BACKGROUND The Region of Waterloo provides transit services in the urban areas of Cambridge, Kitchener and Waterloo seven days a week. With population growth and increased ridership, as well as an aging fleet, the Region needed to acquire new buses to meet demand, provide service expansion and replace older buses and stay within budgetary requirements. In 2001, in accordance with capital plans, a request for proposal (RFP) was issued for the purchase of 10 transit coaches (with an option to purchase an additional 20 coaches in 2003) to replace buses that were nearing the end of their useful life. A 2003 RFP continued Grand River Transit’s 5 year business plan to expand the fleet. Update reports were submitted to Council considering both the environmental impact and cost of replacement. In 2005, the capital acquisition program continued with the Region issuing a tender for the purchase of 10 transit coaches for delivery in 2006, and an option to purchase an additional 20 coaches in 2007. We were directed to look at all the bus procurement tenders from 2001 to 2005, and we understand that these tenders are T2001-128, T2003-114, and T2005-130. We were to determine if the tenders were in compliance with the Region’s purchasing By-laws and procedures. Audit of Bus Procurement Processes March 24, 2006 9 TENDER T2001-128 In accordance with By-law 61-91, Tender T2001-128 was sent to 3 bidders on August 2, 2001 inviting submissions for the supply of 10 transit coaches for delivery in 2002 and an optional 20 additional coaches in 2003. The tender documents included detailed vehicle specifications. It was the Region’s expressed intent to purchase vehicles that closely conformed to the detailed specifications, although non-compliant items could reasonably be expected on the bids. The following were the tender bids received for diesel buses for tender T2001-128: Company Manufacturer #1 Manufacturer #2 Manufacturer #3 Price for each of first 10 transit buses $457,700 $455,714 $479,437 Price for each optional 20 Sub total transit buses $4,577,000 $457,700 $4,557,140 $465,765 $4,794,370 $479,437 Sub total Total Cost $9,154,000 $13,731,000 $9,315,300 $13,872,440 $9,588,740 $14,383,110 The Finance Department Report dated December 12, 2001 recommended that Manufacturer #1 be awarded the tender for the 10 buses. This bid was the second lowest price, but an appropriate business case documented that this bid would result in the lowest overall cost owing to the materials used in the body of the buses and the warranty offered by the manufacturer. The Finance Department Report dated April 2-3, 2002 recommended that the tender bid from Manufacturer #1 be accepted at a price of $9,154,000 for the optional 20 buses. This recommendation was in compliance with the purchasing By-law. Conclusion – Tender #T2001-128 Tender #T2001-128 was issued in accordance with the Region’s purchasing By-law 61-91. We did note that, although the documentation maintained for this tender was extensive, the process could have been enhanced by documenting the financial impact of non-compliance with technical specifications provided by the bidders. It would also have been desirable to completely document the Region’s evaluation of the bids, the bidder’s compliance with the detailed specifications, and the financial impact of any non-compliant components to fully support the determination of the bid with the lowest overall cost. Audit of Bus Procurement Processes March 24, 2006 10 TENDER T2003-114 In accordance with By-law 61-91, Tender T2003-114 was sent to 4 bidders, the three from the 2001 tender plus one other, inviting tender submissions for the supply of 18 transit coaches for delivery in 2004 and an optional 12 additional transit coaches in 2005. The tender documents included detailed vehicle specifications on which the bidder was to document their compliance with each specification or their deviation from the specification. It was the Region of Waterloo’s expressed intent to purchase vehicles that closely conformed to the detailed specifications. Bids were received from three manufacturers, but one bid was received late and returned unopened (in accordance with the purchasing By-law). The following were the tender bids for diesel buses for tender T2003-114: Company Manufacturer #1 Manufacturer #2 Price for each of first 18 transit buses $476,425 $466,319 Price for each optional 12 Sub total transit buses $8,575,650 $490,718 $8,393,742 $480,309 Total Extended Sub total Cost $5,888,616 $14,464,266 $5,763,708 $14,157,450 The Administration and Finance Committee meeting dated June 17-18, 2003 recommended to Council the purchase of 18 transit buses from Manufacturer #2, which was the lowest price. The Administration and Finance Committee meeting dated April 21, 2004 recommended to Council the purchase of 16 additional transit buses from this manufacturer, bringing the total to 34 buses compared to the specified 30. Proper approval from Council was obtained for both bus procurement purchases under this tender, including the 4 additional buses costing $1,921,236. The total invoiced amount was $15,998,127 which agreed to the final purchase orders and was paid in full. The difference between the invoiced amount and the amount approved by Council was a result of changes to the tender bid price based on options and changes made during the time of pre-production meetings with the manufacturer, which is in accordance with the by-law. Conclusion – Tender #T2003-114 Tender #T2003-114 was issued in accordance with the Region’s purchasing By-law 61-91. We did note that the tendering process could have been more robust by enhancing the documentary evidence. It would have been desirable to completely document the Region’s evaluation of the bids, the bidder’s compliance with the detailed specifications, and the financial impact of any non-compliant components. The business case for selecting the successful bidder should have been clearly supported and documented to show that the bid represented the lowest overall cost and not just the lowest overall price. Audit of Bus Procurement Processes March 24, 2006 11 TENDER T2005-130 In accordance with By-law 04-093, Tender T2005-130 was sent to three transit bus manufacturers on August 4, 2005 inviting submissions for the supply of 12 transit coaches for delivery in 2006 and an optional 20 additional coaches in 2007. The tender documents included detailed vehicle specifications on which the bidder was to document their compliance with each specification or their deviation from the specification. It was the Region of Waterloo’s expressed intent to purchase vehicles that closely conformed to the detailed specifications. The following were the tender bids received for transit buses for tender T2005-130: Company Manufacturer #1 Manufacturer #2 Manufacturer #3 Price for each of first 12 transit buses $429,180 $436,989 $432,165 Price for each optional 20 transit buses $5,150,160 $424,888 $5,243,868 $443,934 $5,185,980 $439,703 Sub total Sub total $8,497,760 $8,878,680 $8,794,060 Total Extended Cost $13,647,920 $14,122,548 $13,980,040 The Purchasing division analyzed the tenders and summarized all items that were in non-compliance with the tender specifications. GRT staff then reviewed the listing of non-compliant items and assessed their impact and on December 9, 2005, letters were sent to the three Bidders informing them that each bid was non-compliant with the requirements of the tender. Documentation supporting the assessment process was greatly improved for this tender. In accordance with By-law 04-093, the Region cancelled Tender T2005-130 and exercised its right to negotiate as set out in the Tender documents. The Purchasing By-law, which came into effect January 1, 2005, prevents the Region from accepting non-compliant bids. The Finance Department Report dated February 16, 2006 recommended the purchase of 12 transit buses from Manufacturer #3 at a final negotiated price of $428,223 per bus, after adjustments to their original bid for minor part changes. Proper approval from Council was obtained for the bus procurement purchases under this tender. A properly authorized purchase order was issued. Conclusion – Tender #T2001-128 Tender #T2005-130 was issued in accordance with the Region’s purchasing By-law 04-093. Under By-Law 04-093, any negotiated acquisition must be approved by Council if the value of the acquisition exceeds $100,000 and Council must be informed of the fact that all bids were non-compliant. Both of these requirements were followed by the Region with respect to this tender. Audit of Bus Procurement Processes March 24, 2006 12 BUS REFURBISHMENT PROCESS – ASSIGNMENT #2 BACKGROUND The Region of Waterloo has one of the largest low floor bus fleets in Ontario. While this enhances accessibility for customers who have mobility difficulties, it reduces road clearance and causes the bus to vacuum up road salt, trapping the salt on the bus undercarriage, and leading to more rapid structural deterioration. This deterioration is more pronounced on the right side of the bus, due to the fact that the bus is constantly pulling up to the curbs. The Region of Waterloo has a fleet of 193 transit buses today which include Orion V, Classics, New Flyers, Nova and Motor Coach Industry buses. The potential costs for refurbishment depends on many factors including the type of bus, its age and life expectancy, whether it’s low-floor, and the type of frame. In 2004, the Region developed a Refurbishing Program which recommended that 49 buses undergo some level of refurbishment in 2004 and 2005. This created significant challenges in terms of scheduling the work while maintaining service levels. Transit buses are expected to be in operation a minimum of 18 years, with many buses being retired after 20 years. Refurbishment of transit buses in Ontario usually takes place after 10 to 12 years of service. The objectives of the external audit were to evaluate directly, using suitable criteria, the transactions relating to bus refurbishments during 2003 to 2005 to determine the extent of the Region’s compliance with its policies and procedures and the purchasing By-law in effect at the time. SAMPLE SIZE The refurbishing expenditures were grouped by year and then a sample was selected. This method of sample selection ensured a representative selection of transactions for all years was included and that various refurbishers were tested. Our sample selection resulted in the following coverage: Refurbisher Company A Company B Company C Company D Other Total Total transactions from 2003 -2005 ($) $608,143 Number of Samples 12 Value of Samples ($) $555,056 413,660 272,229 129,362 132,090 7 3 3 -- 316,454 122,448 104,878 -- 76.5% 45.0% 81.1% --% $1,555,484 25 $1,098,836 70.6% Coverage Percentage 91.3% Audit of Bus Procurement Processes March 24, 2006 13 MEASUREMENT CRITERIA – PROCESS & BY-LAWS Our examination of the refurbishments was focused on the process followed in selecting a vendor, compliance with Region protocols and By-laws, and completeness of supporting documentation including bids received and authorization of any additional work completed. Specifically, we considered the requirements of By-law 61-91 and the impact of the By-law 04-093 effective January 1, 2005. 4 of the 17 major refurbishments reviewed were measured under the new purchasing By-law requirements. Audit of Bus Procurement Processes March 24, 2006 14 FINDINGS The 25 transactions examined for refurbishment covered a significant amount (70%) of the total refurbishing expenditures incurred. Of these 25 transactions, 17 related to full refurbishments and the remainder to extra billings or other work. We found instances of non-compliance with the By-law 61-91 in the transactions examined as outlined below. Bylaw 61-91 > $50,000 Quotes Estimated on file Cost Tender 3 70,820 0 46,932 N/R 1 64,080 No 3 35,148 N/R 2 74,900 No 0 32,177 N/R 1 68,880 No 3 55,111 No 0 70,628 No 0 61,611 No 3 61,210 No 3 61,210 No 0 65,754 No 3 74,648 Best Cost Bus # 521 522 8801 8901 8905 8912 9201 9202 9206 9207 9208 9210 9410 9203 By-Law 61-91 61-91 61-91 61-91 61-91 61-91 61-91 61-91 61-91 61-91 61-91 61-91 61-91 04-093 9404 04-093 N/R 0 25,270 N/R -- 9417 9420 04-093 04-093 N/R N/R 0 3 38,170 74,648 N/R -- No No No N/R -- -- -- - Finding Compliant Note 1 Notes 1, 2 & 3 Note 3 Notes 1, 2 & 3 Note 1 Notes 1&2 Note 2 Notes 1, 2 & 3 Notes 1&2 Notes 2 & 3 Notes 2 & 3 Notes 1&2 Compliant Compliant Note 4 Compliant Note 4 Compliant Note 1 - 3 quotes were not obtained/no quotes were obtained or the quote is not in the file; Note 2 - Estimated cost exceeded $50,000 but no call for a sealed tender; Note 3 - Additional work required exceeded $10,000 and two other quotes not obtained; and Note 4 – Region was compliant as purchasing had the authority to award work without 3 quotes on file. N/R – not required Audit of Bus Procurement Processes March 24, 2006 15 The level of non-compliance varied. Some refurbishments had instances of non-compliance where less than 3 quotes were received and it was not part of a sealed tender, while others had one relatively minor instance of non-compliance (i.e. two quotes obtained and lower bid awarded). ¾ Of the 17 full refurbishments reviewed, only 7 had the required 3 quotes on file and only 3 of these were part of a formal tender; ¾ If the estimated cost exceeded $50,000, By-Law 61-91 required that Purchasing and Fleet Maintenance officials call for a sealed tender. In 9 cases, the cost of the refurbishment exceeded $50,000 and a sealed tender had not been undertaken; ¾ In all instances when more than one quote was obtained, the lowest quote was awarded the contract to refurbish the bus. We discussed with management the circumstances whereby only one quote was obtained. We were informed that there were four main refurbishers available to complete the work and in some cases, three of the refurbishers were already busy completing refurbishments on Region of Waterloo buses. In an effort to expedite the refurbishments, the contract was awarded to a refurbisher that had capacity at that time. In these instances, time and capacity was the reason for awarding the contract versus pricing. This occurred in the refurbishment decision for buses 9404 and 9417 as allowed for under By-law 04-093. In 2003 and for the first half of 2004, quotes were received via fax at Grand River Transit. There were no deadlines placed on requests for quotes and as a result, quotes for specific bus refurbishments were received on different days from the refurbishers. By-law 61-91, section C-5 indicates “Where the requirement for goods or services is estimated to exceed $10,000 but is less than $50,000, the purchase may be made on the authority of the Director of Purchasing and Fleet Maintenance upon such terms and conditions as he/she shall deem advisable subject to him/her first obtaining at least 3 quotations for such goods whenever possible.” This indicates that the decision should have been made through the Region of Waterloo Purchasing division and not at Grand River Transit. Section C-6 further states “All requirements for goods or services estimated to exceed $50,000 in value shall be obtained by calling for sealed tenders by the Director of Purchasing and Fleet Maintenance upon such terms and conditions as he/she deems advisable. This may be done by advertising in daily local or trade newspapers or by invitation.” Under these circumstances, the decision should again have been made through the Region’s Purchasing division. SUPPORTING DOCUMENTATION Quotes were either not obtained or not retained on file for 7 of the 17 refurbishments reviewed. An additional 2 refurbishments had only one quote on file. It was not clear if other quotes had been obtained, but only the quote from the refurbisher awarded the work was available for review in these two instances. In all cases, there was appropriate evidence of authorization for the work to be performed and for payment to be made. Audit of Bus Procurement Processes March 24, 2006 16 For the two refurbishment tenders examined, appropriate documentation was received under all By-law criteria. All bids obtained were included as documentation in the Purchasing division’s file as well as any amendments to the original instructions. Audit of Bus Procurement Processes March 24, 2006 17 TRENDS IN THE REFURBISHING PROCESS We summarized the total transactions by year and by major refurbisher and determined that one company (“Company A”) received a significantly higher amount of refurbishment contracts in dollar terms in 2004 as compared to the other major refurbishers. $700,000 $600,000 $500,000 Company A $400,000 Company B Company C $300,000 Company D Other $200,000 $100,000 2003 2004 2005 Total From this information, the 17 major refurbishments selected were broken down by type of bus to enable further trend analysis. There were 4 categories of buses included in the sample: 1. Conventional diesel, Motor Coach Industries with an average life span of 14-18 years, 1987 or 1989 models. Not accessible (not low-floor). 2. Conventional diesel, New Flyer Industries D40LF with an average life span of 11-18 years, 1992 model. Accessible. 3. Conventional diesel, New Flyer Industries D40LF with an average life span of 9-18 years, 1994 model. Accessible. 4. Conventional diesel, Orion Bus with an average life span of 14 to 18 years, 1989 model. Our sample included a number of buses under category 1 and 2 above to enable an analysis for any type of trends. Audit of Bus Procurement Processes March 24, 2006 18 THE REFURBISHING PROCESS – TIMELINES We noted that Company A was often the lowest bidder during a certain period of time and accordingly was awarded the contract. However, Company A did extra bill for work that resulted in an overall cost exceeding the quoted price of the other bidders. It cannot be determined whether the other bidders would have extra billed for the work had they been awarded the contract. The following timeline indicates the awarding of selected contracts and the incidence of extra billing: Motor Coach Buses Bus 8901 Company A Company B Company C Bus 8905 Company A Company C Bus 8801 Company A Bus 521 Company A Company B Company C Bid Date Dec 16/02 Dec 10/02 Dec 17/02 Bid Date Feb 16/04 Feb 17/04 Bid Date Bid Amount $35,147 $38,936 $49,825 Bid Amount Tender Tender Tender $35,147 Awarded $74,900 $85,524 Bid Amount No quotes on file Bid Date Awarded $74,900 Awarded -- Bid Amount $70,821 $81,582 $106,231 $64,081 Awarded $70,821 Extra Bill $18,085 Extra Bill $26,194 Extra Bill $16,889 Extra Bill $10,716 Total Cost $53,232 Total Cost $101,094 Total Cost $80,970 Total Cost $81,537 Timing of Extra work Jan-03 Timing of Extra work May-04 Timing of Extra work Apr-04 Timing of Extra work Dec-04 To summarize, Company A was awarded all 4 of these specific Motor Coach Industries bus refurbishments. The first bid was awarded in December 2002 for $35,147 and the final cost was $53,232. In February 2004, it was awarded the refurbishment of bus 8905 based on a quote of $74,900 and the total cost was $101,094. In April 2004, the refurbishment of bus 8801 was awarded to Company A for $64,081 and it was determined that additional work of $16,889 was required. The total cost for this refurbishment was $80,970. Audit of Bus Procurement Processes March 24, 2006 19 In September 2004, a call for tenders was done for the refurbishment of bus 521. All bidders attended a pre-bid meeting on September 27, 2004 where they were able to inspect the bus before finalizing their bids. Company A was awarded this refurbishment with a quote of $70,821. Additional work of $10,716 was required. Experience gained on the refurbishment of bus numbers 8905 and 8801 showed that initial quotes provided by Company A may have been too low, given that additional billings were required to complete all necessary work. Company A provided a bid on bus 521 that was consistent with its initial bid for both 8905 and 8801 but did not factor in any likely extra requirements to complete the refurbishment. Although the final costs per bus for 8905 and 8801 were significantly higher than the initial estimates, Company A provided a quote of $70,821 on bus 521 which was almost $10,500 less than the next lowest bid. The final cost for bus 521 was only $45 lower than Company B’s bid for this work. Total hours estimates were 461 for Company A and 428 for Company B. In each instance where extra work was required, a representative of Grand River Transit approved the additional work before it was completed. The hourly rates for the initial 461 hours quoted by Company A were at bid rates of $50 per hour and any additional time spent was charged at a retail rate of $65 per hour. 1992 D40LF Flyers Bus 9206 Company A Buses 9208 and 9210 Bid Date Bid Amount Mar-04 Bid Date Awarded -- Bid Amount Company A Jun -04 $61,210 Company B Company C Other Jun -04 Jun -04 Jun -04 $73,591 $77,685 $91,046 $61,416 Awarded $61,210 Extra Bill $27,992 Extra Bill $34,401 $26,783 Total Cost $89,408 Total Cost $95,611 $87,993 Timing of Extra work Jun-04 Timing of Extra work Sep-04 This table summarizes the timelines surrounding Company A being awarded all three of these specific New Flyer bus refurbishments. The first bid provided by Company A, in March 2004, was for $61,416 and extra billings moved the final cost to $89,408. In June 2004, Company A was awarded the refurbishment of buses 9208 and 9210 based on a quote of $61,210 per bus. Extra billings moved the total cost to the Region to $95,611 for bus 9208 and $87,993 for bus 9210. Audit of Bus Procurement Processes March 24, 2006 20 The quotes provided for buses 9208 and 9210 were identical. Total required hours estimated for each bus were: Company A: 621 hours Company B: 769 hours Company C: 814.5 hours Other: 753 hours It was determined that Company A did not use the list of required work provided by Grand River Transit (GRT). The quote provided did not break down hours and materials costs by item. It also included key wording changes and the removal of some of the specific requirements that were on the list provided by GRT. Looking at specific items where these deviations in wording occurred or where items were removed from the quotes, the average cost of these per the estimates of Company B and Company C was $8,600. Total average hours for these specific items was 92 and these would have been billed at the additional retail rate of $65 per hour from the original quoted rate of $50 per hour provided by Company A. TRENDS IN THE REFURBISHING PROCESS – ADDITIONAL BILLINGS Major refurbishments examined Total instances of additional billing Cost of additional billings $ A 7 7 150,710 Company B C 5 2 1 0 $ 11,649 $ - D 3 0 $ - Other 0 0 $ - Of the sample selected, each major refurbishment completed by Company A contained additional work beyond the original scope of the contract. There was only one instance of additional billing from Company B and this related specifically to repairs needed as a result of an accident. There were no further instances of additional billing from the Company B, Company C or Company D. We have calculated the potential extra cost to the Region. For the 7 refurbishments completed by Company A that resulted in additional billings, we compared the quote to the next lowest bid. The difference between the final cost to the Region and the next lowest quote was as follows: Audit of Bus Procurement Processes March 24, 2006 Bus 521 8801 8901 8905 9206 9208 9210 Total Awarded Bid 70,821.91 64,080.91 35,147.79 74,900.01 70,628.28 61,209.95 61,209.95 Next Lowest Bid 81,581.91 None 45,236.41 85,524.35 None 73,591.25 73,591.25 21 Total Cost (including extra cost) 81,537.69 80,969.59 53,232.88 101,093.71 98,620.56 95,611.33 87,992.64 Difference (44.22) 7,996.47 15,569.36 22,020.08 14,401.39 $ 59,943.08 In all instances, a member of the GRT staff approved the work to be done in advance of it being completed. Again, it cannot be determined whether the other bidders would have billed for extra work had they been awarded the contract. We understand that management at GRT and the Region’s Purchasing Department are looking at ways to minimize the exposure to additional billings and keep the bidding process fair. These changes were made in 2005 so that there would not be the need for extra billings. This includes having two lists of specifications; one that details the known items that need to be repaired/replaced and a second that lists possible repairs required based on the history of the bus type. The overall best cost would then be selected, factoring both quotes into the equation on a weighted scale in an effort to reduce GRT’s exposure to extra billings at a higher hourly rate. CONCLUSION In our opinion, the Region complied with the bus refurbishment procurement process for transactions conducted under By-law 04-093. We did note instances of non-compliance with the Region’s purchasing By-law 61-91 in the bus refurbishment process, summarized as follows: I. not obtaining three quotes for the work when it was expected to exceed $10,000; II. not calling for sealed tenders when the estimated cost exceeded $50,000; and III. additional work estimates exceeding $10,000 but additional quotes were not obtained. There is evidence that all of the work was performed by the supplier. Therefore, the potential maximum additional cost incurred by the Region is likely under $60,000. We understand that new processes were put into place in 2005 to minimize the costs of extra billings. Audit of Bus Procurement Processes March 24, 2006 22 BUS DISPOSAL PROCESS – ASSIGNMENT #3 BACKGROUND Grand River Transit and other Regional staff maintain a listing of transit buses which outlines their expected year of retirement which originally is based on the 18 year expected life of a transit bus. Obsolete transit buses have minimal value as there is a very limited resale market. Traditionally, scrap metal dealer and wreckers have shown little interest in purchasing obsolete transit buses as the metal in an 18 year old bus frame has deteriorated to the point of being worthless. Buyers for obsolete transit buses are found through contacts established with other transit authorities or bus repair facilities. We examined the Vehicle Continuity Schedule for 2002 to 2005 provided by GRT Fleet Services and the annual submissions to the Ministry of Transportation of Ontario (MTO) for the same period and established that there were 17 bus disposals during this time frame for total proceeds of $12,373 (an average of $728 per bus). For 2000 and 2001, when the above schedule and submissions were not prepared, we reviewed the General Ledger detail for the general revenue and recharge revenue north and south accounts for any potential bus dispositions. MEASUREMENT CRITERIA – PROCESS & BY-LAWS Our examination of transit bus disposals focused on the compliance with the Region’s by-laws, the completeness of supporting documentation and the receipt of sale funds. Specifically, we considered the requirements of the Purchasing By-laws 61-91 and 04-093 which were in effect during the period under review. A Financial Management Manual which was updated on November 17, 2005 also dealt with the disposition of motor vehicles and equipment. CONCLUSION In our opinion, the bus disposal process was in compliance with the Region’s By-laws and purchasing policies. There were 17 transit bus disposals in the period 2000 to 2005 and only approximately $12,000 was involved in this activity. The bus disposal process could be enhanced by adopting the following best practice: I. A list of surplus transit buses should be maintained by the Purchasing division to enhance its ability to track transit bus disposals. May 2, 2006 Report: E-05-099.3 APPENDIX C TRANSPORTATION HEALTH & SAFETY ASSOCIATION OF ONTARIO (THSAO) Facility Audit Follow Up Report Grand River Transit April 6, 2006 Docs #: 278301 Facility Audit Follow Up Report Prepared for: Grand River Transit April 6, 2006 Introduction On September 27 – October 1, 2004 Transportation Health and Safety Association of Ontario (THSAO) conducted a National Safety Code compliance audit to review Grand River Transits (GRT) systems as they relate to the legislative requirements found largely in the Highway Traffic Act of Ontario. The audit was similar in scope to one which might be conducted by the Ontario Ministry of Transportation (MTO). In addition to a legislative review, the audit reviewed areas of transportation from a best practice perspective or standards generally accepted as industry norms. Three main components of transportation were reviewed; the driver component, the vehicle component and the training and monitoring component. A final report with Observations and Recommendations was issued to key staff within GRT. At the request of Grand River Transit, specifically Eric Gillespie, Director of Transit Services a follow up review was conducted by THSAO on November 30 and December 1, 2005. This review focused on steps and actions taken by GRT related to the recommendations issued in the 2004 audit. The audit commenced with an interview with key personnel. The focus of the discussion was the steps taken to date related to the recommendations from the 2004 audit along with the scope of this audit. At the completion of the discussion, a review of current processes and files was conducted to verify progress in the recommendations. As with the initial review, this review was based on a zero tolerance review of applicable legislation and/or Ministry Facility Audit criteria. Numerous system improvements were observed throughout the course of this follow up review. System improvements include the hiring of an experienced planner / scheduler to assist in planning and scheduling of vehicle preventative maintenance, a lock out system to ensure all safety related defects are repaired prior to the release of a vehicle, upgrading the hours of work tracking system and the issuing of numerous notices related to driver responsibilities. Notices include; “Completing of Pre Trip Inspection Reports”, “Driver Fatigue”, “Reporting of Non GRT Driving Hours”, “How to read MTO Inspection Stickers”, “Hours of Work and Rest Periods”. Discussions with GRT staff subsequent to the audit suggest that additional system improvements have be made. As these systems were not verified, inclusion in this report could not be made. However it is quite evident that GRT has made numerous system improvements between the initial audit in 2004 and the audit in 2005. Improvements appear to be actively ongoing. This report contains a summary of the results of the initial interview, general observations made throughout the review and additional recommendations. Legislation is quoted to support recommendations made that are based on a legislative standards. If no legislative standard is quoted, the recommendation is based on industry standard or best practice standards. Observations and Recommendations CVOR * The Commercial Vehicle Operator's Registration (CVOR) System is an automated monitoring system that tracks the on-road safety performance of commercial vehicle operators. Carrier monitoring systems such as the CVOR System are an integral part of the National Safety Code standards throughout Canada. The goals of the CVOR System are to improve safety for all users of Ontario highways and develop effective compliance strategies with emphasis on safety and protection of the highway infrastructure. The CVOR System monitors a carrier's CVOR Record over a two-year period. This automated computer system contains information that includes: • Carrier information (i.e. fleet size, commodity, violation rate, safety rating) • Convictions • Reportable • Vehicle accidents mechanical safety inspections • Ministry interventions (i.e. letters, interviews, audits and sanctions) * Excerpts from the MTO web site explaining the CVOR system. http://www.mto.gov.on.ca/english/trucks/guideline/cvor.htm#quest1 Number Name Address Rating Date Record Summary 010 545 855 The Regional Municipality of Waterl,oo 150 Fredrick St 3rd Floor HR Kitchener Satisfactory 2005 06 08 Number of Events Accidents Convictions Inspections 286 9 6 Violation Rate Total Points 189 23 0 Percent of Threshold 46.3 % 01.5 % 0.0 % 23.5 % Notes: The record Summary represents two years of data from June 2003 – June 2005 Last MTO Audit date was 2002 01 25. Audit Score – Vehicle 81.6, Driver 100. Collisions are the leading cause of CVOR points. Although CVOR covers all of the Region of Waterloo, GRT vehicles cause the majority of the incidents that lead to points. Multiple Reports Comparison June 05 Oct 04 Accidents Number of Events 238 263 Total Points 186 188 Percent of Threshold 46.3 48.2 Convictions Number of Events 9 6 Total Points 23 15 Percent of Threshold 01.5 01.0 Inspections Number of Events 6 15 Total Points 0 2 Percent of Threshold 00.0 08.0 23.5 26.4 Violation Rate Dates: Recommendation Ensure that all GRT vehicles, drivers and branches or divisions are included in system safety improvements HTA sec 16 The audit only reviewed system improvements at the Strasburg facility in Nov / Dec 2005. Discussions with staff suggest that although some improvements were made system wide, not all aspects of the GRT operation may have been included in all updates. Collisions Collisions continue to be a significant cause of incidents and pointable occurrences on the CVOR. 47 collisions were registered on the Region of Waterloo CVOR between Jan 1 and June 8, 2005, 46 of which involved GRT vehicles. 34.7% of these collisions resulted in Points being assessed on the CVOR record. Points are only assessed on the CVOR if the investigating Police Officer determines an impropriety by either GRT or the Operator (driver) contributed to the collision. The collision review process appears to be very lenient towards the operator regarding preventability findings. Files of non preventable collisions were reviewed and the conclusion in several of the files was debatable. One file overturned a police report finding of driver impropriety without any documentation or investigation to justify the non preventable ruling. Some Collision files continue to be lacking in both content and degree of investigation. One file viewed did not have a police investigation report while another file focused on the “other drivers” lack of avoidance actions. Discipline continues to be linked directly to the collision review process. Once a collision is deemed to be preventable a predetermined point / discipline system is activated. Discipline directly linked to the review process can lead to a biased or perceived biased ruling on preventability by the committee. An internal point system is assigned to each preventable collision. Points are used for disciplinary purposes. Actual or estimated repair costs are a factor in determining points. Based on preventability concepts along with accepted collision causation theories, degree of damage should not be a significant determination of risk or severity. In the case of damage, colliding with an older model vehicle might cause minor financial damage with a severe collision, while a relativity minor collision with a newer luxury vehicle would cause significantly more financial damage. Minimal focus should be on the degree of damage. The primary focus should be on the event and the situations leading to the event. Recommendations The number of collisions which GRT vehicles are involved in must be reduced. Furthermore the number of Pointable collisions must be reduced. The Region of Waterloo is currently reviewing the Collision Investigation and Review process. The focus of Collision Investigations and Review should be to determine root and apparent cause of the collision. The investigation must include a fair and unbiased review of the facts. The prevention of collisions requires that collisions investigations and reviews focus on “prevention” of similar future reoccurrence or how could “we” have prevented the collision. All personnel must take collisions and their prevention seriously. Policies and standards should be developed and enhanced to prevent future similar collisions from occurring. Consider a system that will systematically enhance the preventability standard. Investigations must be thorough followed by a fair and unbiased review of the facts. Licencing Operators continue to be scheduled for routing based on seniority with no consideration to licence class. Regular transit operations clearly require a Class “C” licence. School specials could be interpreted to require either a “C” or a “B” class licence. As Charters are contracts negotiated to provide a specific service and School Charters are contracts with a “school board” usually to transport “children”, Charters with a school board to transport children clearly require a Class “B” licence. Several examples were seen where Class “C” operators conducted school charters. The Region of Waterloo and by extension GRT is a Recognized Authority with the Ministry of Transportation. This designation enables GRT to upgrade and renew drivers licences. The Region is in the process of upgrading its licencing abilities to include Class “B” licencing. Currently approximately half of the operators have a Class “B” licence. Driver Abstracts are ordered 2 – 3 times annually by the safety department. Licence qualifications are constantly monitored. Although the Region is authorized by MTO to renew driver’s licences, operators have the option of not using this complimentary service. When an operator chooses to go to MTO to renew his / her licence there is no requirement to inform GRT of the renewal state. There is a several week time delay from when MTO updates its systems to when GRT becomes aware of the renewed licence and a further administrative delay for GRT to update its electronic systems. An operator could have his / her licence expire and operate a GRT vehicle for several weeks with all GRT’s documentation confirming the invalid state of the licence. On Nov 5, 2005 an operator’s licence expired. GRT only verified a valid licence on December 3, 2005 Only new hires receive a regular road tests or reviews of driving ability. No evidence that non operators such as mechanics receive driver qualification reviews. Operators do not receive on going driver qualification reviews. An operator may however receive a road test as part of a Return to Work evaluation or upon recommendation from the Collision Review Committee Recommendations Consider developing a system that will inform a drivers supervisor and the driver of when his/ her licence status may be become invalid. The system should place an equal onus on the driver to provide satisfactory proof of a valid licence prior to operating privileges being permitted once the GRT monitoring systems reveal an invalid licence. Verbal indication of a valid licence by a driver should not be considered satisfactory proof. Only permit Class B licenced drivers to conduct School Charters. HTA sec 32 (1), (10) Consider only permitting Class B drivers to conduct School Specials Continue the process of enhancing the Signing Authority system to permit the upgrading of operators to a Class “B” licence status. Consider a system that includes regular and ongoing monitoring of driving abilities (road test) for all personnel who may operator GRT equipment. Personnel include bus operators, supervisory staff and mechanics. Hours of Work An upgraded Excel hours of work program has been developed to track operator hours. This new system tracks legislative limits such as 8 hour off duty time, and all daily and weekly cycle limits. This system has been in effect since September 2005. Note that a 64 hour 7 day cycle is used rather than the HTA 60 hour cycle. All regular routes are preloaded into the monitoring system to ensure compliance. The audit revealed that operators are not being permitted to conduct a switch off or charter that might place them in violation of the 64 hour rule. Operator are however occasionally exceeding the 60 hour on duty cycle rule. Although general transit operations may be exempt from the 60 hour rule, when performing a non - transit service such as when conducting a charter, the transit exemption no longer applies. Not all activity is recorded in the Hours of Work tracking system. On Oct 9, 2005 a two hour charter was conducted without being noted in the tracking system. Drivers are required to report any hours worked outside of GRT. A log sheet has been developed and a notice of the new requirement was posted in October 2005. Although evidence of drivers reporting extra hours was seen, there is often a significant time delay in the reporting of these extra hours. Mechanics hours are not currently tracked to ensure compliance with legislative limits. Recommendation Although general transit operations may be exempt from Highway Traffic Act Hours of Work On Duty and Driving limitations, when not exempt the HTA requirements apply. Modify the Hours of Work monitoring system to include the regulated On Duty Cycles. The HTA limits driving after 60 hours in 7 days cycle. HTA sec 190(6) & reg 4/93 sec 3(2) Ensure that all On Duty activity is recorded and used to monitor available hours. On Duty Activity must include all On Duty Activity for all operators. The activities should be recorded in a timely manner to ensure effectiveness in proactively monitoring driver availability HTA sec 16 and 190 (6) & Reg 4/93 sec 13, 15 All persons who may operate GRT equipment must be monitored to ensure compliance with legislated On Duty Driving limitations. HTA sec 16 and 190 (6) & Reg 4/93 sec 13, 15 Preventative Maintenance In September 2005 a planner / scheduler was hired to assist in the planning and scheduling of all GRT vehicles for preventative maintenance. The planner / scheduler tracks, schedules and monitors vehicles for Preventative Maintenance (PM), Annual and Semi Annual Inspections. Scheduling lists are provided to the maintenance department weekly. The new PM system was implemented October 2005. This review did not audit the PM system that existed between October 2004 and August 2005. Vehicle maintenance files viewed were more detailed in content than from the previous audit. Each file contains a separate slot for Work Orders, Annual and Semi Annual Inspections Certificates, Preventative Maintenance Inspections, Vehicle Specifications and Other. The PM schedule allows for a 56 week cycle for PM’s. The documented PM schedule requires vehicles to be inspected at least every 18,000 kms. Maintenance and Scheduling staff interviewed state that they try to inspect vehicles closer to a 10,000 km interval. In October 2005 the PM scheduling and completion rate was recorded at 93%. In November 2005 the PM scheduling and completion rate was recorded at 93% successful. The Planner / Scheduler was able to justify the remaining 7 % or 2 vehicles with reasonable explanations such as vehicles being out of service and vehicles out sourced for extended repairs. Odometer readings recorded on work orders and subsequently recorded into electronic data bases continue to be of concern. Some readings have variances that can not be explained through regular vehicle usage. eg unit 2203 had a reading of 254,375 on November 30, 2005 and a reading of 257, 003 on December 1, 2005, a variance of 2628 km in 24 hrs. In May 2005 a lock out system was implemented. The system is designed to ensure that “vehicles are not deployed for revenue service with known vehicle safety defects”. This system has undergone several operation improvements since its implementation date, with the latest occurring on November 2, 2005. The audit only reviewed sample files and systems at the Strasburg facility. No review was conducted at the Cambridge facility, therefore it is not known if system improvements have been implemented throughout the GRT. Recommendations Continue to ensure that all vehicles owned and operated by GRT are inspected and maintained as per the Preventative Maintenance policy and program. Once inspected, a list or check sheet should be attached to the work order or invoice detailing what items were inspected and the result of the inspection. HTA sec 107 (3) Ensure that all maintenance records contain the required information. The Odometer reading used must be the actual reading taken at the time of repair or maintenance HTA Sec 107 and Reg 575 sec 10 (b) Continue to ensure that no vehicle is used that may have a safety related defect. Consider modifying the “Lockout and Release Procedure” to include all highway / public road use. The current policy only restricts the “revenue serviced” use of GRT vehicles. HTA Sec 84 Continue to monitor drivers to ensure they conduct effective pre trip inspections and that they record such inspection prior to vehicle usage. HTA sec 107 (4) & Reg 575 sec 2, 4 GRT Policy Procedure and Practice 33.10 a Conclusion Throughout the audit process, it was evident that management and staff at GRT are sincerely interested in improving operations to provide a safer commercial fleet. Extensive improvements were made between the 2004 and 2005 audit. Some systems are extremely complicated and take many months and resources to implement. Ongoing discussions strongly suggest that even during the development of this report, improvements continued to be made. Report: P-06-054 rwoo REGION OF WATERLOO PLANNING, HOUSING AND COMMUNITY SERVICES Housing TO: Chair Jim Wideman and Members of the Planning and Works Committee Chair Jane Brewer and Members of the Community Services Committee DATE: May 2, 2006 SUBJECT: HOUSING INCENTIVES AND FUNDING RESOURCE GUIDE FILE CODE: RECOMMENDATION: For information. SUMMARY: The Region of Waterloo produced its first Housing Incentives and Funding Resource Guide (the Guide) in 2002 to provide Affordable Housing Strategy proponents with clear and concise information on affordable housing funding programs. More recently, the Regional Growth Management Strategy, the Community Action Plan for Housing and other community requests confirmed the need for a more comprehensive inventory of housing resources. Consequently, the Guide has been expanded to include key housing related incentives and resources offered by the Region of Waterloo, Local Municipalities, senior levels of government and non-government organizations. REPORT: The Affordable Housing Strategy, first approved by Regional Council in May 2001, identified the need to develop and maintain a comprehensive data base of affordable housing “assistance/programs”. In response, the Region of Waterloo prepared a Housing Incentives & Funding Resource Guide (the Guide) and made it available to the public in 2002. The Guide was found to be very useful to both non-profit and private sector proponents as they sought funding assistance to develop projects under the Region’s Affordable Housing Strategy. By capitalizing on the information contained in this Guide, the Region and its partners have already made significant progress on the implementation of the Regional Growth Management Strategy (RGMS) and the Affordable Housing Strategy. The RGMS and new Provincial policy direction will require a greater share of residential growth to occur within the existing built-up areas through reurbanization and to encourage a range and mix of housing types to meet the needs of all residents. The previous Guide was, therefore, updated to include a broader range of incentives and resources. This new Guide builds on the earlier version and expands the focus beyond affordable housing to include incentives for adaptive reuse, downtown housing, brownfield remediation and other forms of housing development. The need for a comprehensive incentives guide is also supported by the Reurbanization Working Group and the Community Action Plan for Housing (Action Plan) that recommends that the Region “provides support to housing stakeholders and promote information on housing issues, programs and links to other services” (Action 46, p. 119). The incentives and resources identified in the Guide are a compilation of programs offered not only by the Region, but by other community partners, including the Government of Canada, Province of 260101 Page 1 of 2 May 2, 2006 Report: P-06-054 Ontario, Local Municipalities, non-profit agencies and private organizations. To make it easier for users to navigate the various incentives and resources, the information has been organized under three main categories: programs that support the creation of housing, programs for providing community support services/projects and programs to assist individuals/homeowners/landlords. The table of contents further identifies the programs by "type of program” to aid in identifying relevant incentives and resources. The Guide will be made available on the Region’s website and in hard copy format. To ensure that the Guide remains a valuable resource for housing stakeholders in the Region, information will be regularly updated. CORPORATE STRATEGIC PLAN: The incentives and resources contained in the Guide will help to increase reurbanization by promoting financial incentives to support the implementation of Council’s Strategic Focus, identified under Focus Area 1: Manage Regional Growth to Enhance Quality of Life. The Guide will also aid in meeting the objective to improve the accessibility to housing and reduce homelessness under Focus Area 2: Enhance Community Health and Social Well Being in the Corporate Strategic Plan. FINANCIAL IMPLICATIONS: The costs of producing the updated Guide can be accommodated using approved budget funds. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Staff from Finance and Social Services provided input into several programs included in the Guide. ATTACHMENTS: Attachment #1: Housing Incentives & Funding Resource Guide PREPARED BY: Jeffrey Schumacher, Principal Planner Peter Walberg, Principal Planner APPROVED BY: Rob Horne, Commissioner of Planning, Housing and Community Services 260101 Page 2 of 2 Overview • The Original Guide • The Updated Guide: Housing Incentives & Funding Resources Guide Presented to: – – – – Benefits Structure and Layout Incentives and Funding Resources How Proponents can Benefit • Implementation and Next Steps Planning & Works Committee May 2, 2006 The Original Guide The Updated Guide... • Produced in 2002 • Developed as a important part of the Affordable Housing Strategy (AHS): – Develop and maintain a comprehensive data base of affordable housing “assistance and programs” • Intent: – To provide affordable housing proponents with clear and concise information on funding programs • Useful to both non-profit and private sector developers 1 Updated Guide • Better respond to and advance multiple initiatives: – – – – – Regional Growth Management Strategy Affordable Housing Strategy Community Action Plan for Housing Brownfield Financial Incentive Pilot Program Community requests for information • Incorporates a broader range of housing incentives and resources • Includes programs offered by different levels of government and several organizations • More ‘user friendly’ and engaging Updated Guide • Structure and layout of the Guide: – Information is first divided into separate categories: Updated Guide • Benefits of the expanded scope include: – Quicker and easier access to a full range of housing related incentives and resources – The piggy-backing of incentives and funding resources – Better opportunity for policy and program integration – More efficient allocation of staff time and resources – Easier monitoring and update – Improved marketing and promotion Updated Guide – Categories further subdivided by the sponsoring government or agency – Incentives and resources are also grouped by the type of program • Programs that support the creation of housing • Programs for providing community support services and projects • Programs to assist individuals, homeowners, and landlords 2 Updated Guide • Among the incentives and resources listed include: – – – – Updated Guide • How proponents can benefit: Heartwood Place on Gaukel • • • • • • • Development charge exemption (Cities & Region) Toilet Replacement Program (Region) Emergency Repair Program (Federal/Provincial) Residential Energy Efficiency Project (Private Organization) Canada-Ontario Affordable Housing Program Affordable Housing Strategy Capital Grant Rent Supplement Funding Optional Property Tax Class Regional and City of Kitchener Development Charge Exemptions Trillium Grant Habitat for Humanity volunteer crew The Bridges • • • • • • • • Canada-Ontario Affordable Housing Program National Homelessness Initiative - SCPI Funding Affordable Housing Strategy Capital Grant Rent Supplement Funding Optional Property Tax Class Emergency Shelter Purchase of Service Agreement with Social Services Regional and City of Cambridge Development Charge Exemptions City of Cambridge Grant and waiving of fees Implementation and Next Steps • Hardcopies to be printed and circulated to: – Housing proponents and stakeholders – Local Municipal and Waterloo Regional Libraries • Guide to be posted on the Region’s website • Incentives and funding resources to be updated on a regular basis • Guide to be expanded based on ongoing collaboration with community partners and other agencies Housing Incentives & Funding Resources Guide Presented to: Planning & Works Committee Community Services Committee May 2, 2006 3 Report: P-06-041 REGION OF WATERLOO PLANNING, HOUSING, AND COMMUNITY SERVICES Community Planning TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: INITIATION OF AN AMENDENT TO THE REGIONAL OFFICIAL POLICIES PLAN TO CONSIDER DESIGNATION OF DUMFRIES CONSERVATION AREA FILE CODE: D04-90/GS RECOMMENDATION: THAT the Regional Municipality of Waterloo approve the following with regard to a Regional Official Policies Plan amendment as explained in P-06-041, dated May 2, 2006: a) authorize the initiation of an amendment to the Regional Official Policies Plan to establish mapping and policy to address the role of Dumfries Conservation Area in the City of Cambridge within the City Urban Area; and b) direct staff to initiate discussions with the Grand River Conservation Authority and the Local Municipalities to define the role of other major open space areas in the implementation of the Urban Greenlands Strategy. SUMMARY: Among the many comments received during the process to designate the first two Environmentally Sensitive Landscapes (ESLs) in the Region of Waterloo, was the request that the Dumfries Conservation Area be evaluated for potential inclusion in the proposed Blair-Bechtel-Cruickston ESL to provide it with an appropriate level of differentiation from adjoining urban uses. After careful review, Regional staff is of the opinion that the inclusion of this area within the Blair-BechtelCruickston ESL is not warranted in that it does not fulfill sufficient scientific criteria, and because it is physically separated from the body of the ESL by a strip of urban residential development along Coronation Boulevard. Consideration of a different type of classification, however, is now warranted. The Dumfries Conservation Area, along with other major open space areas, play a significant environmental and social role in terms of their contribution to the overall quality of life within urban communities. These contributions will become ever more important with the implementation of the Regional Growth Management Strategy and the Province’s Places to Grow initiative which promote intensification of development within urban areas. In urban communities, greenspace and natural areas such as conservation areas are essential for human well-being. This report recommends the initiation of an amendment to the Regional Official Policies Plan to recognise the significant role the Dumfries Conservation Area plays in the environmental and social well being of the community. The report also recommends that the Region convene discussions with the Grand River Conservation Authority (GRCA) and the Local Municipalities aimed at defining the role of other major open space areas in the implementation of the Urban Greenlands Strategy. This proposed designation of the Dumfries Conservation Area has been discussed with and is supported by senior staff at the GRCA. 250125 Page 1 of 5 May 2, 2006 Report: P-06-041 REPORT: The Dumfries Conservation Area is a 75 hectare (185 acre) expanse of woodlands, plantations, wetlands, and open fields bounded by Hespeler Road on the east, Dunbar Road on the north, and a railway line on the west. The property was donated by Percy Hilborn to the Province of Ontario in 1967 for use as a park. Three years later, it was transferred to the Grand River Conservation Authority (GRCA) to be managed and operated as a park. Starting in the 1970s, the construction of an east-west arterial from Franklin Road to Blair Road was planned for the City of Cambridge. This alignment was shown in the 1976 and 1985 Regional Official Polices Plans (ROPP) as traversing the southern part of the Dumfries Conservation Area. The current ROPP shows a much wider “Proposed Regional Road Corridor” encompassing virtually the entire Conservation Area. During the Cambridge Area Route Selection Study, public concern was expressed about the potential construction of the East-West Arterial through the Dumfries Conservation Area. Subsequently, it was concluded through the Detailed Transportation Network Review (DTNR) not to construct what had become known as the East-West Arterial or the associated new bridge over the Grand River to connect to a proposed West-Side Arterial. On November 24, 2004, Regional Council adopted the recommendations in Report P-04-126 which identified transportation network improvements to address transportation issues in the City of Cambridge. In the process, it recommended removal of the proposed East-West and West Side Arterials from the Regional Official Policies Plan. A ROPP Amendment to implement that change was tabled at the Planning and Works Committee meeting of April 18, 2006, and is anticipated to be formally considered by Regional Council on May 10, 2006 (Report P-06-022). While review of the Cambridge transportation system was proceeding, Regional Council adopted the Regional Growth Management Strategy (RGMS) on June 25, 2003. One action of the RGMS is to “initiate a process to identify and protect Environmentally Sensitive Landscapes.” The RGMS identifies six candidate Environmentally Sensitive Landscapes (ESLs), including one proposed to be traversed by the East-West Arterial on the rare (formerly Cruickston Charitable Research Reserve) lands located immediately to the west of the City of Cambridge in North Dumfries Township. As Council subsequently adopted the results of the DTNR on November 24, 2004, it also adopted the following resolution: “Authorize staff to proceed with the processing of an amendment to the Regional Official Policy Plan to consider the designation of the Cruickston lands, the south portion of the Grand River in North Dumfries containing the old growth Carolinian forest, and the Dumfries Conservation Area as Environmentally Sensitive Landscape, and to hold a public meeting as required by the Planning Act to receive public input on such an amendment;” Through the processing of the amendment to designate the first two ESLs (Report P-06-040), including the Blair-Bechtel-Cruickston ESL which encompasses the rare lands, it was determined that the Dumfries Conservation Area does not warrant inclusion in the ESL because it does not fulfill the rigorous scientific criteria for designation, and also because it is physically separated from the body of the ESL by a strip of urban residential development along Coronation Boulevard. At the second Public Meeting on the proposed amendment to the ROPP to establish the first ESLs, held on November 10, 2005, Councillor Jane Brewer requested staff to prepare a report on the pros and cons of the designation of the Dumfries Conservation Area as an ESL. Rather than simply restate the technical rationale for excluding the Dumfries Conservation Area from the Blair-BechtelCruickston ESL, staff wish to propose a new and different approach for addressing the role of the Dumfries Conservation Area. The Places to Grow initiative seeks to create more liveable, transit-supportive, economically viable urban communities, while optimising public infrastructure and protecting natural resources and 250125 Page 2 of 5 May 2, 2006 Report: P-06-041 productive farmland. In order to achieve these goals and prevent further urban sprawl, it is prescribing targets for intensification and minimum densities for residential and employment development on a regional scale that will result in increased densities within the urban communities. A necessary complement to higher urban densities, however, is publicly accessible greenspace and parkland. Such areas provide a rich variety of environmental benefits which include: • • • • helping to mitigate the urban “heat island effect” generated by paved and built-over surfaces and heavy energy consumption in transportation, heating, and cooling, and thereby improve the local climate; providing areas where urban runoff can be attenuated in quality and quality before being discharged to streams and rivers or infiltrated to groundwater; helping to protect and maintain groundwater quality in that some urban greenspace and parkland areas comprise part of identified wellhead protection areas; and providing relatively large areas of wildlife habitat in close proximity to urban communities. Of no less importance, however, is the contribution of these areas to our urban quality of life. In addition to the usual opportunities for walking and nature appreciation, urban greenspace and parkland provide for indoor and outdoor recreation areas, education centres, picnic areas, campgrounds, and beaches. Increasingly, such recreational activities are seen to contribute to our physical and mental health and well-being of the community. While many of the major open spaces within the Region of Waterloo are owned by and maintained under the responsible leadership of the GRCA and the Local Municipalities, there is increasing perception in the public that the need to increase urban densities associated with the Places to Grow initiative may affect the future of such areas. One of the four major goals of the Greenlands Strategy endorsed by Council on April 13, 2005, is the development of an Urban Greenlands Strategy to complement re-urbanisation and intensification of the main urban areas “in order to ensure healthful, liveable, attractive communities.” This report recommends the initiation of an amendment to the ROPP to recognise the significant role Dumfries Conservation Area will play in the environmental and social well being of the future regional community, and the initiation of a process to define the role of other major open space areas within the Urban Greenlands Strategy. The initiation of a ROPP amendment for the Dumfries Conservation Area has been discussed with and is supported by senior staff at the GRCA. The process to define the role of other major open space areas would be undertaken in direct collaboration with the GRCA and the Local Municipalities through their participation on the Greenlands Working Group. CORPORATE STRATEGIC PLAN: This report will help realise the objective to Protect Sensitive Land Resources in Focus Area 3. That objective calls for development of a Greenlands Strategy, one component of which is creation of an Urban Greenlands Strategy. FINANCIAL IMPLICATIONS: NIL 250125 Page 3 of 5 May 2, 2006 Report: P-06-041 OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: NIL ATTACHMENTS: Attachment #1: Dumfries Conservation Area PREPARED BY: Chris Gosselin, Manager of Environmental Planning APPROVED BY: Rob Horne, Commissioner of Planning, Housing and Community Services 250125 Page 4 of 5 May 2, 2006 Report: P-06-041 Attachment #1 – Location of Dumfries Conservation Area, City of Cambridge (Preston) 250125 Page 5 of 5 Report: P-06-056 REGION OF WATERLOO PLANNING HOUSING AND COMMUNITY SERVICE Transportation Planning TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: May 2, 2006 SUBJECT: SOUTH KITCHENER TRANSPORTATION CORRIDOR STUDY – PREFERRED ALTERNATIVE AND UPCOMING PUBLIC MEETING FILE CODE: RECOMMENDATION: For information. SUMMARY: The South Kitchener Transportation Corridor Study was initiated in 2004 to consider transportation needs for an area of Kitchener, illustrated in Appendix A. The Steering Committee has identified a preferred solution and is presenting it to the Planning and Works Committee for information prior to the formal public meeting scheduled for May 9, 2006. The preferred solution identified as Alternative 4C is shown in Appendix B. Further investigation is also recommended to consider undertaking additional Land Use and Transportation Studies in the Fairway Road corridor. These studies would include identifying opportunities for mixed land use, identify methods of improving the pedestrian and cycling environment, opportunities to enhance the landscaping and design of the area, possible improvements to the safety and efficiency of auto and truck movements, and to identify locations for transit priority measures. The South Kitchener Transportation Corridor Study followed the Class Environmental Assessment (Phase I and II) which included extensive public consultation with local residents, businesses, interested public, special interest groups, and review agencies. Three Public Consultation Centres and a workshop were held with a total attendance of over 400 and the receipt of over 250 written submissions, emails and facsimiles. Key public and agency feedback is noted below: • There is consensus that there are transportation issues in the area that need to be addressed. Many people have also stressed the importance of maintaining the natural area that exists today that includes ESPA 27 and two Provincially Significant Wetlands (PSW) (as illustrated in Appendix A); • The Ministry of Natural Resources and the Grand River Conservation Authority are supportive of Alternative 4C and strongly encourage a design speed of 70 km/hr, rather then the typical 80 km/hr to minimize impact on the PSW. Both agencies will continue to be part of the process in order to have input on mitigation techniques for minimizing disruption to the natural environment; • The City of Kitchener Environmental Committee has recommended that the boundaries of ESPA 27 be expanded and that no transportation corridor be constructed in the Hidden Valley area. • The Ecological and Environmental Advisory Committee (EEAC) of the Region of Waterloo has stated that Alternatives 1 and 3 would have negligible affect on the Hidden Valley natural area and that Alternative 4 would have localised serious adverse environmental impacts on the Hidden Valley natural area but that if the study determines a new road is required, it would have the least impact on the Hidden Valley natural area and might be approved subject to appropriate mitigation. EEAC also recommended that the boundaries of ESPA 27 be expanded. 278675 May 2, 2006 Report: P-06-056 The input received from the May 9, 2006 Public Meeting of the Planning and Works will be incorporated into a final staff report and recommendation to the Planning and Works Committee. If approval is received from Council to proceed, next steps would include; • • • • • • Continue to examine detailed design concepts and mitigation techniques for natural area impact and well head area mitigation: Continue to work with the Stonegate Drive residents and the City of Kitchener to consider the design of the connection of Stonegate Drive with the new road; Determine property requirements and initiate land purchase with owners; Determine final project costs; Report to Regional Council and complete the Environmental Study Report; File the Environmental Study Report with the Ministry of the Environment. REPORT: 1.1 Introduction The South Kitchener Transportation Corridor Study commenced in 2004. The scope of the study included the establishment and protection of possible transportation corridors to provide future east-west access through South Kitchener to meet the transportation needs of people and goods movement. The study area is illustrated in Appendix A. A transportation link in the Hidden Valley area is contained in both the Regional and City of Kitchener Official Plans. The 1999 Regional Transportation Master Plan confirmed the need to create a new corridor within the study area along with a new Highway 8 interchange between Fairway Road and the Grand River. The Regional Cycling Master Plan (2004) also identified the need for a cycling facility in conjunction with planned roadway upgrades and transportation system expansion in the study area. This study considered the established road corridor along with several other alternatives. The study area has varying existing and planned land uses including commercial, light and heavy industrial and a variety of housing densities. The study was guided by a Steering Committee comprised of Regional staff and Councillors, City of Kitchener staff and Councillors, Grand River Conservation Authority staff, Ministry of Natural Resources staff and Ministry of Transportation staff. The following Regional and Municipal Councillors sit on the Project Team: • • • Councillor John Gazzola (City of Kitchener) Councillor Jean Haalboom (Region of Waterloo) Councillor Jim Wideman (Region of Waterloo) • The study has followed Phases I and II of the Provincial Class Environmental Assessment process including; • • • • • • 1.2 Problem definition and needs assessment, Involvement of the public and review agencies on an on-going consultation basis, Conducting investigations for social/cultural and heritage environment in the study area, Land use and economic considerations, Inventories of natural/cultural environment in the Hidden Valley area, and Transportation and environmental impacts of alternative planning solutions. Existing Conditions A large portion of the Hidden Valley area is designated as ESPA 27. However, much of the area has also been either zoned or designated by the City of Kitchener for uses such as Business Park and residential. Appendix C illustrates the land use designation in the area. Currently there is a holding provision on the land designated as business park and residential because of the lack of servicing infrastructure for water and sewage as well as transportation access. The holding provision related to transportation can be removed with the completion of Wabanaki Drive or if other road access is provided in the area. 278675 Page 2 of 47 May 2, 2006 1.2.2 Report: P-06-056 Road Operations Roadway traffic conditions in the South Kitchener study area are generally constrained by intersection configurations and the minimal access to Highway 8. Various through traffic movements and especially turning movements along Fairway Road are already operating at capacity. The area has many other transportation challenges including an unfriendly, disconnected pedestrian and cycling environment, and delays to transit operations. Specific problem areas are identified in Appendix D and summarized below; • Fairway Road Much of Fairway Road is operating at capacity during peak hours and many intersections along Fairway Road are operating at poor levels of service, including Fairway Road & Manitou Drive, Wilson Avenue and King Street. Commercial access points are also highly congested creating unsafe turning movements. Due to this congestion, heavy vehicles are being forced to choose Homer Watson Boulevard to access Highway 401, causing out of direction travel. • Manitou Drive The intersections of Manitou Drive at Fairway Road and at Bleams Road and the twolane section between these intersections cause delays that result in auto traffic using streets such as Wilson Avenue, Goodrich Drive and Wabanaki Drive that are key corridors for goods movement in the area. • Highway 8/Fairway Road Interchange Heavy congestion on the ramps results in traffic diverting to King Street East during the afternoon peak periods. Traffic from the many side streets and driveways along Fairway Road makes it difficult to improve the progression of traffic because of the many stops and delays. 1.2.3 Transit Operations Transit buses travelling Fairway Road between the Fairview Park Mall entrance and King Street during peak hours experience long delays due to heavy congestion. During afternoon peak hours the entrance to the Mall and the internal routes to the station are often congested. In addition, several transit stops along Fairway Road are not provided with sidewalks, making pedestrian access difficult during the winter months. On Bleams Road, congestion is forcing transit vehicles to wait several cycles to turn left onto Manitou Drive during the afternoon peak. 1.2.4 Pedestrian and Cycling Facilities Highway 8 presents a major barrier to pedestrian and bicycle traffic, where the Fairway Road underpass is the only crossing in the area. Along Fairway Road, many driveways and few sidewalks result in a poor level of service for pedestrians or cyclists. Many roads within the industrial area such as Bleams Road, Manitou Drive, Homer Watson Boulevard don’t have sidewalks. 1.2.5 Environmental and Natural Heritage Conditions The study also included a significant environmental inventory component. This data was used to determine areas that meet the Regional requirements of an ESPA under the Regional Official Policies Plan and to define the PSW boundaries. The Hidden Valley area contains Environmentally Sensitive Policy Area (ESPA) 27 and a PSW as shown in Appendix E. ESPA 28 and 31 are also located within the study area, but are not associated with any proposed roadway alignments. Information directly related to ESPA 27 in the Hidden Valley area has also been updated as part of the environmental inventory. Appendix E illustrates additional lands that meet the Region’s criteria for ESPAs. 278675 Page 3 of 47 May 2, 2006 Report: P-06-056 Some of the more important findings from these inventories include: • Documented in the area were 25 different vegetation communities, 111 bird species, 344 different plant types, 28 mammal species, 17 Reptile and Amphibian species • Creeks within the study area do not support fish habitat, but ponds provide habitat for amphibians and reptiles. No protected species were found; • The quality of the woodlands within the study area is considered outstanding, and include a number of rare plant species of regional and provincial significance; • Wildlife is diverse in the area, but while previous studies had identified several protected species, none are now found likely owing to human encroachment; City of Kitchener and Waterloo Region records include two properties listed on their Heritage Inventory along Hidden Valley Road, and heritage buildings in the German Mills area immediately north of the Bleams Road/Manitou Drive intersection. None of these buildings are designated under the Ontario Heritage Act. A Stage 1 archaeological resource assessment was conducted of the study area, and although small portions of land have had previous archaeological fieldwork, no materials were recovered. However, since the study area was found to have archaeological potential, any previously un-assessed lands will require further inventory. A preliminary geotechnical investigation of the study area concludes that it is a significant groundwater recharge zone, and three Regional wells are located off Manitou Drive near Bleams Road. As a result, any new road construction will have to follow strict design and maintenance standards. 2.0 Development of Planning Alternatives 2.1 Initial Planning Alternatives To address the needs in the South Kitchener area the following alternatives were initially developed. Appendix H provides further details about each alternative. During the development of alternatives, the design speed of the road sections was a point of much discussion. The “design speed” of a road is used to define the speed at which a vehicle can safely travel the road. Generally, Regional practice is to design a road at 10 km/hr to 20 km/hr higher then the posted speed limit. Alternative 1: Do-Nothing • No River Road Extension • Assumes planned road improvements within the area, including Highway 8 widening, Fairway Road, Block Line Road and Wabanaki Road extensions and Manitou Drive widening, projects were also common to all other planning alternatives. • Included an increase in the transit mode share from 5% in 1996 to 7% in the AM Peak Hour by 2016. Alternative 2: River Rd. Extension • Original alignment as approved in 1984 • Full Highway 8 interchange • Bike lanes, and sidewalks • 6-lanes on Fairway Road between King Street and Wilson Avenue. 278675 Page 4 of 47 May 2, 2006 Report: P-06-056 Alternative 3: Transit Emphasis • Partial River Road Extension from King Street to Highway 8, Goodrich Drive Extension to Manitou Road • Fairway Road widening (6-lanes from 4-lanes) King Street to Manitou Drive • External to the study area, the transit mode share is assumed to be 7%, within the study area the transit mode share was increased to 15%. Alternative 4: River Rd. Extension plus Transit (Bus-only lanes on River Road) • Combination of Alternatives 2 and 3 with the River Road Extension aligned around the edge of the Hidden Valley area • Partial Highway 8 interchange • Directional ramp off of Fairway Road to southbound Highway 8. • Includes the widening of Homer Watson Blvd to 6-lanes from Highway 401 to Ottawa Street • External to the study area, the transit mode share is assumed to be7%, within the study area the transit mode share was increased to 15%. Alternative 5: Multi-Use River Rd. Extension • Similar to Alternative 2 but uses a road alignment that aligns closely with the existing Hidden Valley Road (transit-only lanes on River Road extension) • External to the study area, the transit mode share is assumed to be7%, within the study area the transit mode share was increased to 15%. 2.2 Alternatives for Road Section Between Manitou Drive and Wilson Avenue In alternatives two to five, the road section between Manitou Drive and Wilson Avenue was examined resulting in two available options. The area of this road section is highlighted as Area A on Appendix B Map. Option 1 – (Identified by the dashed line) The Region of Waterloo owns most of the current road allowance from Wilson Avenue to just east of Manitou Drive. This road corridor was acquired as a result of a previous road alignment study that was completed with the installation of the water main to Manheim. This corridor used a design speed of 40 km/hr because of land availability at the time of the study. The project team directed that this alignment be revisited due to the low design speed and proposed function of the road. Option 2 – (Identified by the solid line) This current study considered the alignment of this road with an 80 km/hr design speed. This new alignment eliminates the need to fragment the property directly to the east of Manitou Drive. However, a portion of the rear of the industrial lot fronting onto Webster Road is required. The current use of this lot is for long term storage and there has been no objection from the land owners after initial discussions. 2.3 Public Consultation Three Public Consultation Centres and a Workshop (see Appendix F) were held during the study to obtain opinions and preferences from the public on the problem/opportunity definition, potential alternative planning solutions, evaluation criteria and the preferred alternatives. There has been extensive public involvement in the process with over 400 attendees . Approximately 250 comments have been submitted to date in the form of comment sheets, facsimiles, and emails. Public Consultation Centre #1 At the first Public Consultation Centre, the top six issues of interest in order of significance as noted are: general road congestion, natural environment, highway access, water/air quality, transit and walking. Significant concerns were raised about the preservation of Hidden Valley and the retention of the natural habitat, wetlands, protection of ESPA and impacts to the natural environment. Significant transportation concerns were raised about bottlenecks on Fairway Road, congestion, connections and interchange improvements to Highway 8, and east-west access for business and personal trips. 278675 Page 5 of 47 May 2, 2006 Report: P-06-056 Public Consultation Centre #2 At the second Public Consultation Centre there continued to be significant interest about both the preservation of the natural environment and protection of Hidden Valley and in improving east-west transportation connections. The top evaluation criteria that people felt were important were the Natural Area Impact, Groundwater Impact and Roadway Continuity. Public Consultation Centre #3 At the last public meeting, 170 people attended to view the preferred alternatives. The majority of people indicated that they preferred an alternative that limited impact on the natural environment but provided improved highway access. There were a few comments indicating that no road should be built and that the whole area should be preserved. Most people understood that there are congestion and delay issues in the study area for all types of road users (trucks, motorists, cyclists, pedestrians and transit) and that a transportation connection is needed. In addition, at the last public meeting, several residents of the Stonegate Drive area (Appendix G) stated concerns with the connection of the ramps on the east side of the highway to Stonegate Drive. Their concerns included potential cut through traffic in their neighbourhood and safety. City of Kitchener policy requires that there must be two access points to a neighbourhood for emergency vehicles. The current access near River Road and King Street must be closed because it is too close to the intersection. Residents were informed that there will be a separate meeting with Stonegate Drive residents as part of the preliminary design phase of this project. At this meeting, Regional and City of Kitchener staff will explore solutions with the residents, to minimize neighbourhood impacts of the connection related to potential cut through traffic. 2.4 Additional Alternatives Developed After Public Input The alternatives below were developed in response to input from the public, agencies and Steering Committee on the initial five alternatives. Alternative 1A: Alternative1 Do-Nothing with Development Cap – A development cap was assumed in the area. Alternative 3A: Transit Emphasis with Partial Highway 8 Interchange – Similar to Alternative 3 along with a partial Highway 8 interchange on the east side of the highway. Alternative 4A: Mixed Traffic Lanes – Similar to Alternative 4 but without bus lanes on the River Road extension Alternative 4B – Similar to Alternative 4A but with no Homer Watson Widening Alternative 5A River Road Extension with Mixed Lanes – Similar to Alternative 5 with the Bus Only/HOV lanes open for mixed traffic use. 3.0 Evaluation of Planning Alternatives 3.1 Evaluation Criteria and Principles The Steering Committee concluded that the following principles should be used during the evaluation process; • The original plan adopted by the Region of Waterloo and City of Kitchener in 1981, and again in 1994 to extend a River Road extension from King Street west to Goodrich Drive along the north edge of Environmentally Sensitive Policy Area (ESPA) #27, in the Hidden Valley area, should be abandoned. It should be replaced with a routing solution that is sensitive to natural conditions and approved development opportunities within the study area, while effectively addressing transportation needs; 278675 Page 6 of 47 May 2, 2006 Report: P-06-056 • The new routing solution should maximize the use of existing roads within the Study Area, taking into account roadway design standards; • An interchange connection between a new River Road extension and Highway 8 is preferred, but whether it is a full or partial interchange is dependent on public and stakeholder input, agency responses, design considerations and cost. In addition, consideration should be given to the impacts of this interchange on Highway 8 and Fairway Road, including Kitchener-Wilmot Hydro plans, and associated redevelopment projects on and in the vicinity of Fairway Road. The criteria used in the evaluation of alternatives and the details of the results of the evaluation are shown in Appendix I. 3.2 Summary of Evaluation Alternative 1 and 1A did not address traffic and related transportation deficiencies in the South Kitchener Corridor, or improve conditions for transit operations, cycling and pedestrian movements and goods movement. Also, implementing a development cap on lands designated, zoned, and/or approved for development would only delay the need for transportation improvements. Alternative 2 would result in extensive natural environmental and groundwater impacts within the Hidden Valley Forest. Alternative 3 and 3A did increase transit ridership, but not enough to offset the increased travel demand in the corridor. Alternative 4, 4A and 4B responded well to the transportation needs in the area and improved transportation operations in the Corridor while minimizing impacts on area properties and the Hidden Valley Forest. However, there was a high capital cost of a new southbound directional ramp from Fairway Road to Highway 8, and limited opportunities to operate a River Road extension as a transit-only route. Alternative 5 and 5A responded well to the transportation needs in the area but had increased impact on the forest edge at the interchange location, including a small PSW adjacent to Highway 8 that would be eliminated. Overall, the initial evaluation resulted in Alternatives 4B and 5A being presented to the public as preferred by the Steering Committee. Alternative 4B was selected because it responded very well to transportation needs in the Corridor without the cost and impacts of the Homer Watson Boulevard widening, but still had the potential groundwater impacts and the high cost of the Fairway Road directional ramp. Alternative 5A was selected because it responded the best in addressing Corridor transportation needs. 3.3 Additional Variations to Planning Alternatives Some members of the Steering Committee noted concern about the localized Hofstetter wetland PSW impacts from the west side interchange ramps in Alternative 5A, and the feasibility and cost of a Fairway Road directional ramp in Alternative 4B. These preferred alternatives also included modern roundabouts at the Highway 8 Ramp terminals to minimize ramp impacts on natural features. When the Ministry of Transportation informed the Committee that roundabouts would not be permitted at highway ramp terminals, the Committee decided to evaluate two additional variations on these alternatives without roundabouts to determine impacts: Alternative 4C River Road Extension with Partial 3-directional Interchange: Alternative 4C (Appendix B) was developed with all the same design elements as Alternative 4B, except the east to south ramp on Fairway Road to Highway 8 was removed and a southbound Highway access provided directly from River Road. This alternative provided highway access in all directions except the southbound exit from Highway 8 to River Road without the higher costs of constructing a highway ramp from Fairway Road. Given the MTO improvements at the Fairway Road interchange that are under construction now, this exiting movement may be able to be accommodated with consideration for a full-turn access at Wabanaki Drive and Fairway Road. 278675 Page 7 of 47 May 2, 2006 Report: P-06-056 Alternative 6 River Road Extension with Full Interchange (no Ramp Terminal Roundabouts) – (Appendix I) was developed with all the same design elements as Alternative 5A, except without a roundabout. This alternative was evaluated to compare the amount of the Hofstetter wetland PSW and forest area impacted by a River Road Extension with a full highway interchange compared to Alternative #4C. The impact area is larger owing mainly to the need for ramp terminal setbacks required by MTO on the River Road extension. It is expected that the Hofstetter wetland would be lost because of fill placement. In order to accommodate the MTO required spacing of signalized intersections; the road alignment would have further penetrated into the Sugar Maple area and come closer to the current ESPA boundary. This alternative was not considered further because of the environmental impact. 4.0 Preferred Alternative 4.1 Steering Committee Preferred Alternative At the last Steering Committee meeting on March 22, 2006, the following statement was developed and unanimously accepted. “The preferred alternative for the South Kitchener Transportation Corridor Study is Alternative 4C (Appendix B) with a design speed of 70 km/hr, if feasible and with mitigation and treatment for any wetland and forest impacts. Full consideration should be given to alternative design speeds, minimizing tree loss, narrower road widths, alternative methods for winter maintenance (no road salt), and recovering and replanting of disturbed vegetation. The new corridor is recommended to have pedestrian facilities and cycling lanes on both sides.” 4.2 Description of Steering Committee Preferred Alternative – 4C The preferred alternative involves many design and policy elements (some noted above) that will need to be refined and confirmed at the next stage of this study. Starting at the West side of the study area going to the East side, the following elements are included; • • • • • • • • • • • A roundabout at the intersection of Manitou Drive and Bleams Road/River Road extension will be constructed, Use of an 80 km/hr design speed on the River Road Extension section between Wilson Avenue and Manitou Drive will be used, Infiltration impacts will be mitigated around the Water Supply Well located near Schneider’s Creek south of the River Road Extension from Manitou Drive to Wilson Avenue, Traffic control measures at the intersection of Wilson Avenue and River Road Extension (formerly Goodrich Drive) will be further considered during the design stage, Goodrich Drive from Wilson Avenue to Hidden Valley Road would be assumed as a Regional Road, A roundabout at the intersection of River Road Extension and Hidden Valley Drive/Future Wabanaki Road Extension will be constructed, Wabanaki Drive from Hidden Valley Drive to south of the rail corridor would be assumed as a Regional Road. This road section would be constructed in the future to 4 lanes entirely to the east as per the Wabanaki Drive Environmental Assessment, Wabanaki Drive would remain a City of Kitchener Street from Fairway Road to River Road Extension. This short section would intersect with the River Road Extension, River Road Extension would follow the Hidden Valley Road alignment from Wabanaki Drive until the bend near Highway 8, The design speed for the section of the River Road Extension that is parallel to Highway 8 will be 70 km/hr, if feasible, a final decision will be may at the next stage of this project, There will be a partial Highway 8 River Road Extension interchange constructed that provides for all movements except the Highway 8 southbound exiting movement to the River Road Extension. 278675 Page 8 of 47 May 2, 2006 • • • • • Report: P-06-056 A road access to the designated residential lands south of River Road will be provided; further details will be developed in cooperation with the developer during the next stage of this study, Hidden Valley Road will be closed south of the River Road extension and a Cul-de-sac will be constructed, The ramp terminal intersection with River Road and Stonegate Drive will be signalized and the design of the connection with Stonegate Drive will be considered as part of the next stage of this study, A private Road access from the existing residence will be provided to the River Road Extension, Design features that mitigate and offset negative impacts on the natural environment will be included. 5.0 Agency Participation 5.1 Regional Ecological and Environmental Advisory Committee (EEAC) EEAC was consulted at the onset of the study to ensure that the Terms of Reference for the study included all necessary environmental data collection and analysis. EEAC formed a sub-committee that reviewed the findings of the Environmental Consultant and the Interim Report of the Evaluation of the Five Planning Alternatives. The recommendations from the EEAC Report 05-016.3 (Appendix K), state that EEAC would consider Alternatives 1 and 3 to have negligible impact on the Hidden Valley natural area. EEAC stated that Alternative 4 would have localised serious adverse environmental impacts on the Hidden Valley natural area by removing an area of Provincially Significant Wetland and some adjoining successional woodland, but that if the study determines a new road is required, it would have the least impact on the Hidden Valley natural area, and that it might be approved pursuant to Policies 4.3.17(c) and 4.4.9(c) of the ROPP subject to appropriate mitigation. EEAC also made recommendations to staff that involve the expansion of ESPA 27 boundaries; which are being explored with the City of Kitchener and the land owner. 5.2 City of Kitchener City of Kitchener staff have been members of the Steering Committee and will be giving formal input to the Preferred Alternative over the next few weeks. Initial input from the Economic Development Committee has been supportive of a new transportation link to serve the area. The Environmental Committee supports Alternative 1 only (Do Nothing: Baseline). They also recommended, similar to EEAC, that the boundaries of ESPA 27 be expanded. The City of Kitchener will work closely with the Region during the next phase of the project to ensure that the residents of Stonegate Drive are considered and all potential solutions to their issues are explored. 5.3 Grand River Conservation Authority (GRCA) The Grand River Conservation Authority supported Alternative 4B, initially. When Alternative 4C was brought forward, the GRCA requested more field work and mapping of specific features to enhance understanding of the specific differences between the alternatives. The GRCA is supportive of Alternative 4C at this time, but strongly recommend that the design speed of 70 km/hr be considered in the detailed design phase. The GRCA will continue to be involved with the study process in the detailed design phase. 5.4 Ministry of Natural Resources (MNR) The Ministry of Natural Resources have been continually involved in the study process. The information collected as part of the study has been used by MNR staff to refine the PSW boundaries in the Hidden Valley area. The MNR is supportive of Alternative 4C, but similar to the GRCA would like to see consideration given to a 70 km/hr design speed. The MNR states that this project will have localized significant impacts on the natural features. As a result, during the next phase of this process, mitigation and offsetting habitat projects will be identified specifically related to; • Wildlife passage culverts • Maintaining existing flow patterns under the proposed road bed • Barrier to stop amphibians and reptiles from getting onto roads • Forestation to offset de-forestation 278675 Page 9 of 47 May 2, 2006 • • • • Report: P-06-056 Wetland creation, Bridge options Plantings Transplanting plants 6.0 Conclusions As part of the Kitchener Transportation Corridor Study, the Steering Committee has identified a preferred alternative and is presenting it to the Planning and Works Committee for information and Public Input. The preferred Alternative is identified as 4C, shown in Appendix B. Further investigation is also recommended to consider undertaking studies in the Fairway Road corridor in order to encourage the completion of the pedestrian network, examine mixed land use opportunities, improve the landscaping and design environment, improve safety and efficiency of auto and truck movements, and identify locations for transit priority measures. The Class Environmental Assessment (Phases I and II) for the South Kitchener Transportation Corridor is nearing completion and has included consultation with the public and agencies as summarized below. • Extensive Public Consultation has occurred over the course of the study involving local residents, businesses, interested public, special interest groups, and review agencies. Three Public Consultation Centres and a workshop were held with a total attendance of over 400 people and the receipt of over 250 written submissions, emails and facsimiles; • There is consensus that there are transportation issues in the area that need to be addressed. Many have also stressed the importance of maintaining the natural area that exists today that includes ESPA 27 and two Provincially Significant Wetlands(PSW); • The Ministry of Natural Resources and the Grand River Conservation Authority are supportive of Alternative 4C and strongly encourage a design speed of 70 km/hr, rather then the typical 80 km/hr to minimize impact on the PSW. Both agencies will continue to be part of the process in order to have input on mitigation techniques for minimizing disruption to the natural environment; • The City of Kitchener Environmental committee has recommended that the boundaries of ESPA 27 be expanded and that no transportation corridor be constructed in the Hidden Valley area. • The Ecological and Environmental Advisory Committee of the Region of Waterloo has stated that Alternatives 1 and 3 would have negligible affect on the Hidden Valley natural area and that Alternative 4 would have localised serious adverse environmental impacts on the Hidden Valley natural area but that if the study determines a new road is required, it would have the least impact on the Hidden Valley natural area and might be approved subject to appropriate mitigation. EEAC also recommended that the boundaries of ESPA 27 be expanded. 7.0 Next Steps The input received from the May 9, 2006 Public Meeting of the Planning and Works will be incorporated into a final staff report and recommendation to the Planning and Works Committee. If approval is received from Council to proceed, next steps would include; • Continue to examine detailed design concepts and mitigation techniques for natural area impact and well head area mitigation; • Continue to work with the Stonegate Drive residents and the City of Kitchener to consider the design of the connection of Stonegate Drive with the new road; 278675 Page 10 of 47 May 2, 2006 Report: P-06-056 • Determine property requirements and initiate land purchase with owners; • Determine final project costs; • Report to Regional Council and complete the Environmental Study Report; • File the Environmental Study Report with the Ministry of the Environment. CORPORATE STRATEGIC PLAN: The examination of the South Kitchener Corridor as a possible future all-modes transportation facility supports the Strategic Focus Area 4: Ensure High Quality Regional Transportation System by maintaining and improving the Regional Road Network. FINANCIAL IMPLICATIONS: The Region's 2006 Transportation Capital Budget includes $160,000 in 2006 for the South Kitchener Transportation Study to cover the costs associated with the design and completion of the Class Environmental Assessment to be funded from the Regional Development Reserve Fund. The 2006 Transportation Capital Program includes funding for this project totaling $23.5 Million in 2007 to 2011. Once final project costs and staging is determined, they will be incorporated into the Transportation Capital Program. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Staff from Transportation and Environmental Services participate as members of the Steering Committee for this study. ATTACHMENTS: Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Appendix H Appendix I Appendix J Appendix K - Study Area - Steering Committee Preferred Option - Hidden Valley Land Use Map - Summary of Transportation Conditions - Areas that Meet ESPA Criteria - Public Consultation Centres and Workshop Dates and Purposes - Map of the Stonegate Drive Area - Description of Planning Alternatives - Evaluation Criteria and Comparison of Alternatives - Alternative 6 - EEAC Recommendation (Report 05-016.3) PREPARED BY: Paula Sawicki, Transportation Planning Engineer APPROVED BY: Rob Horne, Commissioner, Planning, Housing and Community Services 278675 Page 11 of 47 May 2, 2006 Report: P-06-056 Appendix A – Study Area Study Area 278675 Page 12 of 47 May 2, 2006 Report: P-06-056 Appendix B – Steering Committee Preferred Alternative * The “design speed” of a road is used to define the speed at which a vehicle can safely travel the road. Generally, Regional practice is to design a road at 10 km/hr to 20 km/hr higher then the posted speed limit. ALTERNATIVE 4C - 70 KM/HR DESIGN SPEED* FUTURE RESIDENTIAL ACCESS ALTERNATIVE 4C - 80 KM/HR DESIGN SPEED* AREA A REGIONAL WELL HEAD 278675 Page 13 of 47 May 2, 2006 Report: P-06-056 Appendix C – Hidden Valley Land Use Map 278675 Page 14 of 47 May 2, 2006 Report: P-06-056 Appendix D – Summary of Transportation Conditions Roadway traffic conditions in the South Kitchener study area are generally constrained by intersection configurations and the access to Highway 8. Various through traffic movements and especially turning movements along Fairway Road are already operating at capacity as shown on the Exhibit below, and at the Bleams Road/Manitou Drive intersection. AV E HIG HW AY 8 KI NG SW AY W ILS ON DR Traffic Operation Deficiencies S ANA KI DR WEBSTER R D GOODRICH DR HID VAL DEN LEY RD Legend WILS Intersections at Capacity VE ON A MAN ITOU DR D SR AM E L B E WAB RD WAY FAIR KING ST Congested Areas Peak Hour Level of Service ( 2004) AM Peak Hour Intersection Fairway Road & Manitou Drive Fairway Road & Fairview Park Mall Main Entrance Fairway Road & Wilson Avenue Wilson Avenue & Kingsway Drive Bleams Road & Manitou Drive Homer Watson Blvd & Manitou Drive Wabanaki Drive & Manitou Drive Hwy 8 Ramp & Fairway Road King Street & Fairway Road Fairway Road & Harvey’s/Swiss Chalet/Mark’s Work Warehouse Fairway Road & River Road King Street & River Road Bleams Road & Homer Watson Blvd Fairway Road & Midas/Quiznos/Part Source 278675 Delay (secs) 30 21 38 10 13 28 10 25 31 PM Peak Hour Overall Delay LOS LOS (secs) C 87 F C 185 F D 65 E A 20 B B 37 D C 117 F B 18 B C 218 F C 217 F 8 A 57 E 13 21 25 31 B C C C 16 19 34 9 B B C A Page 15 of 47 May 2, 2006 Report: P-06-056 Appendix E – Continuous Natural Areas that Meet the Region’s ESPA Criteria Continuous natural areas that meet the Region’s ESPA criteria Existing ESPA 27 Exhibit 1 278675 Page 16 of 47 May 2, 2006 Report: P-06-056 Appendix F – Public Consultation Centres and Workshop Dates and Purposes Public Consultation Centre #1 – May 27, 2004 - Provided an orientation to the South Kitchener Transportation Corridor Study - Provided background and study process information - Gained public input before developing the problem/opportunity statement and creating alternative planning solutions Stakeholder Workshop – July 27, 2004 The following questions were addressed at the Workshop. 1. Describe what you think the problem is with the existing and future transportation conditions in the South Kitchener Corridor. 2. How would you improve transportation in the South Kitchener Study Area over the next 10 to 20 years? 3. How do we get there? What considerations should be taken into account in making decisions about future transportation demand? 4. What advice do you have for the Region of Waterloo in assessing the various transportation opportunities and constraints? Public Consultation Centre #2 – January 19, 2005 - Summarized the transportation and development history in the South Kitchener Transportation Corridor study area. - Presented the existing and expected transportation challenges in the study area. - Reported on the opportunities and constraints to improve transportation in the study area. - Introduced some alternative ways to address the transportation challenges. - Gained public input before evaluating the alternative solutions. Public Consultation Centre #3 – October 4, 2005 278675 - Described the transportation improvement alternatives considered for the South Kitchener study area; - Presented the findings of the examination of these transportation improvement alternatives; - Presented preferred alternatives endorsed by the Study Steering Committee for public consideration and comment; and - Outlined the further steps in the Study process Page 17 of 47 May 2, 2006 278675 Report: P-06-056 Page 18 of 47 May 2, 2006 278675 Report: P-06-056 Page 19 of 47 May 2, 2006 278675 Report: P-06-056 Page 20 of 47 May 2, 2006 278675 Report: P-06-056 Page 21 of 47 May 2, 2006 278675 Report: P-06-056 Page 22 of 47 May 2, 2006 278675 Report: P-06-056 Page 23 of 47 May 2, 2006 278675 Report: P-06-056 Page 24 of 47 May 2, 2006 278675 Report: P-06-056 Page 25 of 47 May 2, 2006 278675 Report: P-06-056 Page 26 of 47 May 2, 2006 278675 Report: P-06-056 Page 27 of 47 May 2, 2006 278675 Report: P-06-056 Page 28 of 47 May 2, 2006 278675 Report: P-06-056 Page 29 of 47 May 2, 2006 278675 Report: P-06-056 Page 30 of 47 May 2, 2006 278675 Report: P-06-056 Page 31 of 47 May 2, 2006 278675 Report: P-06-056 Page 32 of 47 May 2, 2006 278675 Report: P-06-056 Page 33 of 47 May 2, 2006 278675 Report: P-06-056 Page 34 of 47 May 2, 2006 278675 Report: P-06-056 Page 35 of 47 May 2, 2006 278675 Report: P-06-056 Page 36 of 47 May 2, 2006 278675 Report: P-06-056 Page 37 of 47 May 2, 2006 Report: P-06-056 Appendix G: Stonegate Drive Area N 278675 Page 38 of 47 May 2, 2006 Report: P-06-056 Appendix H: Description of Planning Alternatives: Alternative #1: The Baseline In this alternative, transportation system improvements for the study area are limited to “road” projects currently approved or planned in South Kitchener, including the Highway 8 widening, Fairway Road extension, Manitou Drive widening, Block Line Road extension and Wabanaki Drive extension. In addition, there would be a modest increase in the amount of transit use over the next 10 years as planned by Waterloo Region. The Baseline alternative performs very poorly from a transportation perspective since it does not add needed east-west roadway capacity of South Kitchener or improve deficient intersections on the major roads. It also responds poorly to the social and economic criteria since the lack of transportation improvements in the South Kitchener corridor is expected to result in added roadway enhancement projects elsewhere in the area. 1.A. Baseline with a Cap was tested as a sub-alternative to determine if and how South Kitchener transportation challenges would be impacted by limiting the amount of development in the Hidden Valley area and along Fairway Road, as suggested by some members of the public. Owing to the amount of through and local traffic already in the study area, and the amount of traffic expected to be generated by already approved development lands to the west and east of the study area, restricting further Fairway Road and Hidden Valley development would have little impact on traffic growth and related transportation challenges in South Kitchener. Alternative #2: River Road Extension This planned road extension, approved in 1981 through the Study Area from King Street to Manitou Drive as a 4-lane arterial road, is shown on Exhibit 1. This alternative performs well in addressing traffic deficiencies and improving overall accessibility to the study area, including improved access to and from Highway 8 with a new full interchange and reduced impacts on natural areas compared to a more direct road extension. However, it does result in significant impacts to the Hidden Valley natural area, specifically ESPA #27. This natural impact outweighs the transportation benefits of this alternative, making it a low ranking option. Alternative #3: Transit Emphasis – This transportation alternative is based on a larger increase in transit ridership, along with widening of Fairway Road to 6 lanes from King Street to Manitou Drive to add Bus-Only lanes, and a 2-lane extension of Goodrich Drive from Wilson to Manitou. The emphasis on transit service creates positive impacts by attracting more people from their cars to transit, but at the cost of deteriorating roadway capacity since widening Fairway Road for Bus-Only lanes would not serve the projected growth in through and destination traffic. Current deficiencies for cycling, pedestrian and goods movement are not addressed. Also capital costs for roads are replaced in this alternative with costs for transit expansion and operation. 3.A. Transit Emphasis with Partial Interchange on Highway 8 for northbound on and off access onto River Road east of the highway was tested as a sub-alternative. The results show some limited improvement in forecast traffic conditions, a slight increase in traffic volumes on the existing River Road east of the highway and minor natural and social impacts east of Highway 8 and west of Wilson Avenue in the Schneider Creek area. When considering the combined effects and impacts, this sub-alternative is ranked one of the lowest of all evaluated alternatives; 278675 Page 39 of 47 May 2, 2006 Report: P-06-056 Exhibit 1 – Planning Alternative #2 River Road Extension Alternative #4: Hybrid River Road Extension/Partial Interchange – This alternative was developed as an alternative route to the original River Road extension shown in Alternative #2. It includes a new 4-lane arterial road on a new alignment extending from King Street to Manitou Drive, but with reduced impact on the Hidden Valley area by following much of existing Hidden Valley Road and Wabanaki Drive alignments as shown on Exhibit 2. Alternative #4 has one lane per direction on the new River Road extension reserved only for buses and other high occupancy vehicles. It also includes a partial interchange on the east side of Highway 8 to allow northbound traffic on and off the highway, and a new ramp off Fairway Road eastbound to Highway 8 southbound to replace the existing left turn from Fairway Road onto the highway on-ramp. Alternative #4 also assumes that Homer Watson Boulevard is widened to six through lanes as planned from Bleams Road to Highway 401 to provide enhanced north-south capacity in South Kitchener. From a transportation perspective, Alternative #4 performs well with improved roadway operations, less congestion and better transit operations than some of the other alternatives. However, its added vehicle capacity is limited with two of the lanes reserved for buses and high occupancy vehicles. Also, with the partial interchange, it requires a new ramp off Fairway Road eastbound onto Highway 8 southbound to provide improved highway access. The cost and constructability of this ramp may be affected by Kitchener-Wilmot Hydro plans to expand and improve their operation immediately south of Fairway Road near the highway. Like Alternative #2, Alternative #4 also provides a new continuous east-west arterial route across South Kitchener for motorists, trucks, transit, cyclists and pedestrians, while reducing the direct social and natural impacts on the Hidden Valley area. It utilizes as much existing road allowance as possible, with a “modern roundabout” on the west side of Highway 8 to direct traffic around 278675 Page 40 of 47 May 2, 2006 Report: P-06-056 rather than through the Hidden Valley area. It’s cost is high if the estimated $20 million to widen Homer Watson Boulevard is included. While this cost is attributed to the Regional Transportation Master Plan, its inclusion as part of Alternative #4 elevates the associated capital cost to about $42 million, which is at least double the cost of the other comparable alternatives. A moderate ranking is given to Alternative #4 as compared to the other alternatives. 4.A. Alternative #4 with Mixed Travel Lanes - Unlike Alternative #4, this sub-alternative assumes the River Road extension is available for all roadway traffic, with no exclusive Bus-Only or high occupancy vehicle lanes. This essentially doubles the vehicle capacity of the road, with resulting improvements to traffic operations and virtually no negative impacts. It also responds to two other concerns; 1) that Bus-Only lanes may be difficult to enforce in mixed traffic, and 2) that all Grand River Transit routes now serving the Fairview Park Mall terminal use Fairway Road. This sub-alternative has a moderate ranking in part because of the highest capital cost of including the Homer Watson widening. 4.B. Alternative #4A with no Homer Watson Widening – If the major widening of Homer Watson Boulevard is removed as a part of Alternative #4A, the economic performance of Alternative #4 is enhanced by reducing the capital cost to about $22 million. When the other criteria are considered, this sub-alternative ranks first compared to the other alternatives. Exhibit 2: Planning Alternative 4 River Road Extension with Partial Interchange (Identified as one of two Preferred Alternative Initially) 278675 Page 41 of 47 May 2, 2006 Report: P-06-056 Alternative #5: Alternative River Road Extension/Full Interchange – This alternative offers all the transportation system features and socio-environmental advantages of Alternative #4, but with the added advantage of full access to and from Highway 8. With this increased highway access, Alternative #5 is expected to generate some added traffic growth on the surrounding road network, but the involved roads can accommodate this growth. As shown on Exhibit #3, this alternative has been designed to minimize impacts of the west side highway interchange ramps on the natural area by using modern roundabouts as part of the interchange design. This approach would require Ministry of Transportation approval. In addition, the new southbound ramp from Fairway Road to Highway 8 is included in Alternative #4 is not required with the full interchange provided in Alternative #5. This alternative (Exhibit 3) ties as the second ranking for the Study Area. 5.A Alternative 5 with Mixed Travel Lanes – With no exclusive Bus-Only travel lanes on the new River Road extension in this sub-alternative, traffic operations are improved similar to that provided in Alternative #4A. Also, as with Alternative 5, this sub-alternative reduces the social and natural impacts on the natural area edge along Hidden Valley Road using modern roundabouts as part of the interchange design, also requiring Ministry of Transportation approval. This sub-alternative ranks first overall. Exhibit 3 – Alternative #5 Alternative River Road Extension with Full Interchange (Identified as one of two Preferred Alternative Initially) 278675 Page 42 of 47 Report: P-06-056 SOUTH KITCHENER TRANSPORTATION CORRIDOR STUDY SUMMARY OF ROAD IMPROVEMENTS INCLUDED IN EACH PLANNING ALTERNATIVE Alt 1 2 3 4 5 River Rd. – Hwy 8 to Wabanaki River Rd – King to Hwy 8 Goodrich Dr./Bleams Rd Manitou to Wilson River Rd / Hwy 8 Fairway Rd Widening Interchange Direct Ramp East on Fairway to South Hwy 8 Homer Watson Widening Bleams to 401 QueueJump Lanes / Transit Priority Fairway Rd / Wabanaki Full Turns Intersection Bike Lanes – E-W Direction Transit mode share target (2021) N/A Double by 2016 – 7% mode share 15% locally, 7% external to study area No Yes; four lanes; standard alignment No No Yes No Yes No Yes, full interchange No 6 lanes King to Wilson; no HOV lanes No No No No No No No No No River Rd – King to Manitou No Yes No 6 lanes King to Manitou; with HOV lanes No No Yes Yes Yes; four lanes with HOV lanes and alternative alignment Yes; four lanes with HOV lanes Yes Yes Partial, East side ramps 6 lanes King to Wilson; no HOV lanes Yes Yes Yes Yes Goodrich – Wilson to Wabanak i, Fairway Wabanak i to King River – King to Manitou Yes Yes Yes, full interchange 6 lanes King to Wilson; no HOV lanes No No Yes Yes River Rd. -King to Manitou 15% locally, 7% external to study area 15% locally, 7% external to study area Page 43 of 47 May 2, 2006 Report: P-06-056 Appendix I – Evaluation Criteria 1. Transportation Criteria: 1.1 Roadway Network Performance 1.2 Transportation System Performance 1.3 Transit System Performance 1.4 Transit Ridership 1.5 Cycling/Walking Network Performance 1.6 Roadway Network Continuity 1.7 Good Movement Performance 1.8 Transportation System Accessibility 2. Social-Cultural Environment Criteria: 2.1 Direct Property Impact 2.2 Regional Growth Management Strategy 2.3 External Traffic Impacts 2.4 Cultural Landscape Impact 2.5 Noise Impact 2.6 Visual Impact 3. Natural Environment Criteria: 2.1 Natural Area Impact 2.2 Groundwater Impact 2.3 Surface Water Impact 2.4 Air Quality Impact 2.5 Resource Consumption 4. Economic Environment Criteria: 4.1 Capital Cost 4.2 Operation & Maintenance Cost 4.3 Property Impact Potential "\"Insert DOCS Number ie., DOCS #69587\"" Page 44 of 47 May 2, 2006 Report: P-06-056 Appendix I Continued– Comparison of Alternatives Criteria Alt. 1 Baseline Alt. 1A Baseline w Cap Alt. 2 RTMP/Riv er Rd Extend Alt. 3 Transit Emphasis Alt. 3A Transit Emphasis/ Part Interchange Alt. 4 Hybrid River Rd Extend/ Part Interchange Alt 4A 4 with mixed traffic lanes/ Part Interchange Alt 4B 4A with no Homer Watson Widening Alt. 5 Hybrid River Rd Extend/ Full Interchange Alt 5A 5 with mixed traffic/ Full Interchange SUMMARY RANKING: Transportation SUMMARY RANKING: Socio-Cultural SUMMARY RANKING: Natural SUMMARY RANKING: Economic TOTAL SUMMARY RANKING Least responsive Most responsive • Alternative #4B with a new River Road extension from King Street to Manitou Drive utilizing existing road allowances around as much of the Hidden Valley area north edge as possible and extending west along Goodrich Drive to Manitou Drive, and with a partial interchange on the east side of Highway 8 and a new southbound Highway ramp from Fairway Road; and • Alternative #5A with the same River Road extension alignment, but with a full interchange at Highway 8.K "\"Insert DOCS Number ie., DOCS #69587\"" Page 45 of 47 Report: P-06-056 Appendix J – Alternative #6 - Refined Alternative 5A Alternative #6 – Duplicate of Alternative 5A - Except No Roundabouts at ramp terminals Page 46 of 47 May 2, 2006 Report: P-06-056 Appendix K – EEAC Recommendation (Report 05-016.3) 1. THAT the Ecological and Environmental Advisory Committee advise Planning, Housing and Community Services staff: 1.1 that, based on recent field investigations carried out as part of the South Kitchener Transportation Study, the Committee is of the opinion that the northern boundary of the Hidden Valley Environmentally Sensitive Policy Area [ESPA 27] established in 1981-84 is not ecologically appropriate, and that the area indicated on Map 4 fulfills sufficient criteria for designation, and should therefore be re-included in the Environmentally Sensitive Policy Area; 1.2 that, being cognizant of the high ecological values of the natural area specified in 1.1 as well as the fact that a significant part of it has been zoned for business park development, the Committee urges the Region, City of Kitchener, and landowner to give serious consideration to protecting the lands through a potential exchange of appropriate developable lands; and 1.3 that the Committee is willing to work with Regional and Kitchener staff and the landowner to mitigate impacts to the remaining natural area through the potential alignment and detailed design of a new road and the anticipated approval of new development in the area. 2. THAT the Ecological and Environmental Advisory Committee advise Planning, Housing and Community Services staff that, based on a review of the proposed alternatives presented in the South Kitchener Transportation Corridor Study 2.1 that Alternatives 1 and 3 would have negligible impact on the Hidden Valley natural area, and that they are therefore the preferred overall alternatives from a natural heritage perspective, and that either could be approved pursuant to Policies 4.3.17(a) and 4.4.9(a) of the Regional Official Policies Plan; 2.2 that Alternative 2 be rejected pursuant to Policies 4.3.17(b) and 4.4.9 (b) of the Regional Official Policies Plan; 2.3 that Alternative 4 would have localised serious adverse environmental impacts on the Hidden Valley natural area by removing an area of Provincially Significant Wetland and some adjoining successional woodland, but that if the study determines a new road is required, it would have the least impact on the Hidden Valley natural area, and that it might be approved pursuant to Policies 4.3.17(c) and 4.4.9(c) of the ROPP subject to appropriate mitigation; and 2.4 that Alternative 5 would have more serious adverse environmental impacts on the Hidden Valley natural area than Alternative 4 in that it would remove a swath of the mature woodland along with the area of Provincially Significant Wetland and adjoining successional woodland, and should therefore be rejected. 2.5 that Alternative 6 would have more serious adverse environmental impacts on the Hidden Valley natural area than Alternatives 4 and 5 in that it would remove a more extensive swath of the mature woodland along with the area of Provincially Significant Wetland and adjoining successional woodland, and should therefore be rejected. 3. THAT the Ecological and Environmental Advisory Committee advise Planning, Housing and Community Services staff that, in the event a River Road extension is approved in principle, that the Committee be requested to provide further detailed input to minimize impacts to the residual natural areas. 4. THAT the Ecological and Environmental Advisory Committee request staff to forward Report EEAC-05016.3 to the South Kitchener Transportation Corridor Project Team as the Committee’s comments and recommendations on the environmental aspects of this undertaking, dated January 31, 2006. 278675 Page 47 of 47 REGIONAL MUNICIPALITY OF WATERLOO PLANNING AND WORKS COMMITTEE MINUTES Tuesday, May 2, 2006 9:00 a.m. Council Chamber 150 Frederick Street, Kitchener, Ontario Present were: Vice-Chair B. Strauss, D. Craig, K. Denouden, H. Epp, J. Haalboom, W. Roth**, K. Seiling and C. Zehr* Regrets: J. Wideman Also present: R. Kelterborn and M. Connolly*** DECLARATIONS OF PECUNIARY INTEREST UNDER THE MUNICIPAL CONFLICT OF INTEREST ACT None declared. DELEGATIONS a) Rosemary Kittel-McCormick, St. Agatha, appeared before Committee regarding Report E-06-051, Gerber Road Improvements. She requested Committee review extending the 60km zone in order that it reaches the end of her property at 1171 Gerber Road. If this is not possible, R. Kittel-McCormick requested keeping the 60km zone as proposed, and from this point keeping the original 70km to where it originally started (approx. 1300m west of Moser Young Road). She stressed the importance of the speed limit in regards to the school bus stopping in the area. R. Kittle-McCormick requested she be informed of Council’s decision to the report. (R. Kittel-McCormick provided Committee with a written submission) R. Kelterborn indicated he is in support of the recommendation, but recognizes the McCormick’s issues with the school bus stop in front of their lane. He suggested that the appropriate bus sign marks be made at this stop. R. Kelterborn would like the road construction to be completed in time for the Wellesley Apple Butter and Cheese Festival. REPORTS – TRANSPORTATION AND ENVIRONMENTAL SERVICES DESIGN AND CONSTRUCTION a) E-06-051 Gerber Road Improvements, Nafziger Road to Moser-Young Road, Wellesley and Wilmot Townships - Approval of Roadway Improvements and Approval of Speed Limit Changes John Lee, Project Manager provided a brief report on Gerber Road improvements. He indicated improvements are required, due to deteriorated asphalt surface, deficient sight distances and the inadequate road width for road users (school children, pedestrians, farm traffic, horse and buggy, mail and newspaper deliveries and cyclists). J. Lee outlined the proposed improvements and issues raised at the Public Information Centres. P&W -2- 06/0502 MOVED by W. Roth SECONDED by C. Zehr THAT The Regional Municipality of Waterloo approve the plans for roadway improvements on Gerber Road between Nafziger Road and Moser-Young Road on the boundary of Wellesley and Wilmot Townships as outlined in Report E-06-051 and amend Traffic and Parking By-law 00032 as amended, upon construction of the improvements as follows: a) Existing 80km/h speed zone situated 400m East of Nafziger Road extending easterly to 1300m West of Moser - Young Road, amended to 400m East of Nafziger Road extending easterly to 500m West of Moser - Young Road; and b) Existing 60km/h speed zone situated 1300m West of Moser - Young Road extending easterly to 300m East of Moser - Young Road, amended to 500m West of Moser Young Road extending easterly to 300m East of Moser - Young Road. CARRIED DELEGATIONS - continued b) Rod Muir, Waste Diversion Campaigner, Sierra Club of Canada, appeared before Committee regarding Report E-05-103.1, Food Waste Organics Pilot Project Update, and expressed the interest from the Sierra Club of Canada in providing their support to the project. c) Elinor Hueton, Puslinch, appeared before Committee regarding Report P-06-041, Initiation of an Amendment of the Regional Official Policies Plan (ROPP) to Consider Designation and Protection of Dumfries Conservation Area. She expressed her support for the proposal to amend the ROPP in order to establish mapping and policy to address the role of the Dumfries Conservation Area in Cambridge. (E. Hueton provided Committee with a written submission) REPORTS – PLANNING, HOUSING AND COMMUNITY SERVICES COMMUNITY PLANNING b) P-06-041 Initiation of an Amendment to the Regional Official Policies Plan to Consider Designation and Protection of Dumfries Conservation Areas MOVED by D. Craig SECONDED by W. Roth THAT The Regional Municipality of Waterloo approve the following with regard to a Regional Official Policies Plan amendment as explained in P-06-041, dated May 2, 2006: a) authorize the initiation of an amendment to the Regional Official Policies Plan to establish mapping and policy to address the role of Dumfries Conservation Area in the City of Cambridge within the City Urban Area; and b) direct staff to initiate discussions with the Grand River Conservation Authority and the Local Municipalities to define the role of other major open space areas in the implementation of the Urban Greenlands Strategy. CARRIED P&W -3- 06/0502 d) Dave Aston, MHBC Planning appeared before Committee regarding Report E-06-040.1, Ira Needles Boulevard, Stage 3. He spoke on behalf of his clients, Ira Needles Commercial Group, to request a deferral of the report until the May 16th Committee meeting. He explained his clients would appreciate the chance to review the report with staff before a decision is made. Staff indicated a deferral of the report would not implicate the construction. In response to a concern from H. Epp that stakeholders were not consulted, Thomas Schmidt Commissioner, Transportation and Environmental Services responded that Regional Council had directed staff to review options that could provide increased flexibility and reduce the cost of future expansion of the road from two to four lanes. Staff as requested reviewed numerous options, as presented in the report, and is recommending that Ira Needles be constructed as a two lane road with an urban cross section as originally approved in the environmental assessment. As the option being recommended remained unchanged from that approved as part of the Environmental Assessment it was felt that no additional consultation was required. REPORTS – TRANSPORTATION AND ENVIRONMENTAL SERVICES – continued DESIGN AND CONSTRUCTION - continued c) E-06-040.1 Ira Needles Boulevard, Stage 3, Victoria Street to South of Erb Street, Review of Two-Lane Cross Section Alternatives that will Facilitate Future Road Widening to Four Lanes MOVED by K. Seiling SECONDED by C. Zehr That The Regional Municipality of Waterloo maintain the current cross-section design, identified as Option 1 in Report E-06-040.1 and described as initially constructing two paved inside lanes on a two lane granular base with concrete curb and gutter and 1.0 metre wide concrete boulevard edging for the proposed construction of Ira Needles Boulevard, Stage 3, from Victoria Street to south of Erb Street; and DEFER the decision until the Planning and Works Committee meeting of May 16, 2006, in order for staff to meet with the Ira Needles Commercial Group. CARRIED TRANSPORTATION d) E-06-054 Roundabout at the Intersection of Regional Road #17 (Ament Line) and Regional Road #10 (Herrgott Road), in the Township of Wellesley MOVED by K. Seiling SECONDED by W. Roth THAT The Regional Municipality of Waterloo take no action with respect to the request for the installation of a roundabout at the intersection of Regional Road #17 (Ament Line) and Regional Road #10 (Herrgott Road), in the Township of Wellesley. CARRIED e) E-06-057 Roundabout Education Program Nancy Button, Manager, Transportation Engineering showed a video pertaining to how round-abouts function. The video showed how drivers should safely negotiate within a round-a-bout and P&W -4- 06/0502 is an example of the type of video the Region of Waterloo is proposing to generate in order to educate the public. N. Button responded to questions regarding the size of the round-a-bout in the video verses the size of the Region’s round-a-bouts. Received for Information. f) E-06-058 Ontario’s Millennium Partnership Funding Agreement for the Region of Waterloo International Airport Servicing and Land Development Project MOVED by C. Zehr SECONDED by J. Haalboom THAT The Regional Municipality of Waterloo authorize the Regional Chair and Clerk to sign an agreement with Her Majesty the Queen in Right of Ontario (by its Ministry of Agriculture, Food and Rural Affairs) to provide for $1,112,608 of capital funding from the Millennium Partnerships Initiative for the Region of Waterloo International Airport servicing and land development project as described in Report E-06-058. CARRIED g) CR-RS-06-025 Disposal of Easement Interest, Nafziger Road, Township of Wilmot MOVED by W. Roth SECONDED by C. Zehr THAT The Regional Municipality of Waterloo: a) declare the Region’s existing easement interest in Parts 9 and 11, Reference Plan 58R13951, Township of Wilmot as surplus and enter into such documentation as is required to release the Region’s interest established by the easement for $1.00 plus costs, subject to the Region's property disposition by-law and to the satisfaction of the Region’s Solicitor, as detailed in Report CR-RS-06-025 dated May 2, 2006; and b) give the Regional Solicitor authority to execute and register, electronically or otherwise, any documentation required to give effect to the foregoing. CARRIED h) CR-RS-06-027 Authorization to Expropriate Permanent Easements (2nd Report) Along Shantz Station Road, Township of Woolwich, Relating to Region of Waterloo International Airport Requirements MOVED by W. Roth SECONDED by K. Denouden THAT The Regional Municipality of Waterloo approve the expropriation of the property detailed in Report CR-RS-06-027 dated May 2, 2006 described as follows: Permanent Easements: 1. Part Lot 88, German Company Tract, Township of Woolwich, being Part 1 on Reference Plan 58R-15013 (1163 Shantz Station Road) 2. Part Lot 87, German Company Tract, Township of Woolwich, being Part 5 on Reference Plan 58R-15013 (municipal address unavailable) P&W -53. 06/0502 Part Lot 103, German Company Tract, Township of Woolwich, being Part 6 on Reference Plan 58R-15013 (1292 Shantz Station Road) Part Lot 87, German Company Tract, Township of Woolwich, being Part 7 on Reference Plan 58R-15013 (municipal address unavailable) 4. AND THAT staff be instructed to register a Plan of Expropriation for the property within three months of the granting of the approval to expropriate the property, as required by the Expropriations Act; AND THAT the registered owners be served with a Notice of Expropriation and a Notice of Possession for the property after the registration of the Plan of Expropriation; AND THAT an Offer of Compensation be served upon the registered owners of the property in the amount of the market value of the land as estimated by the Region’s appraiser; AND FURTHER THAT the Regional Solicitor be authorized to discontinue expropriation proceedings or any part thereof, in respect of the above described lands, or any part thereof, upon the registration on title of the required documentation to complete an acquisition of the required interest. CARRIED WASTE MANAGEMENT i) E-05-103.1 Food Waste Organics Pilot Project Update Cari Howard, Project Manager, gave an overview of the report highlighting materials that can be included in the “green bin”; and how neighbourhoods within the Region of Waterloo were selected for the pilot project. She indicated the bin being considered for use in the pilot project is used by the City of Toronto. MOVED by C. Zehr SECONDED by K. Denouden THAT The Regional Municipality of Waterloo: a) Approve the scope of the Food Waste Organics Pilot Project as presented in Report E-05-103.1 dated May 2, 2006; and b) Amend the existing waste collection contract with Waste Management Canada to include curbside collection and transfer of the Food Waste to the processing facility for the duration of the pilot project. CARRIED j) E-06-047 Waste Management Education Program T. Schmidt reminded Committee members of the May 16th Planning and Works Committee meeting to be held at the Waterloo Region Emergency Services Training & Research Complex (WRESTRC). Received for Information. k) E-06-056 Waterloo Landfill Monitoring Program Update P&W -6- 06/0502 MOVED by J. Haalboom SECONDED by K. Denouden THAT The Regional Municipality of Waterloo enter into a consulting agreement with ConestogaRovers and Associates (CRA) to provide engineering and hydrogeologic services necessary to support the Region with environmental monitoring activities at the Waterloo Landfill Site to an upset limit of $194,750 plus applicable taxes. CARRIED l) CR-RS-06-026 Hydro Corridor Relocation, Waterloo Landfill Site MOVED by D. Craig SECONDED by W. Roth THAT The Regional Municipality of Waterloo enter into agreements as required for the relocation of the Hydro One corridor and transmission lines at the Waterloo Landfill site as follows: a) convey to Hydro One Networks Inc. an easement over lands described as part of Part Lot 39, German Company Tract, City of Kitchener, subject to registration of a reference plan, for the sum of $2.00 plus associated taxes and costs on terms and conditions satisfactory to the Commissioner of Transportation and Environmental Services and the Regional Solicitor, as detailed in report CR-RS-06-026 dated May 2, 2006; b) convey to the Province through Ontario Realty Corporation the fee simple interest in the lands described as part of Part Lot 39, German Company Tract, City of Kitchener, subject to registration of a reference plan, for the sum of $2.00 and the conveyance to the Regional Municipality of Waterloo of the existing corridor acquired under Recommendation c) below plus associated taxes and costs on terms and conditions satisfactory to the Commissioner of Transportation and Environmental Services and the Regional Solicitor, as detailed in report CRRS-06-026 dated May 2, 2006; c) acquire from the Province through Ontario Realty Corporation the fee simple interest in the lands, being the existing corridor, described as Parts 2 and 3 on Plan 58R-7999 in the City of Kitchener for the sum of $2.00 and the conveyance to the Province through Ontario Realty Corporation of the new corridor conveyed under Recommendation b) above, plus associated taxes and costs on terms and conditions satisfactory to the Commissioner of Transportation and Environmental Services and the Regional Solicitor, as detailed in report CR-RS-06-026 dated May 2, 2006; and d) give the Regional Solicitor authority to execute and register, electronically or otherwise, any documentation required to give effect to the foregoing. CARRIED WATER SERVICES m) E-06-039 Water Supply Update Nancy Kodousek, Director, Water Services, provided a presentation highlighting the current status of water supply in the Region of Waterloo. She outlined water supply projects and indicated detailed reports regarding Greenbrook and the Water Efficiency Update Master Plan would be forwarded to the Committee in June 2006. P&W -7- 06/0502 *C. Zehr left the meeting at 10:20 a.m. Received for Information. n) E-06-033 Consultant Selection for the Water Supply Strategy Update MOVED by J. Haalboom SECONDED by H. Epp THAT The Regional Municipality of Waterloo enter into a Consulting Services Agreement with XCG Consultants Ltd. of Kitchener, Ontario, to provide consulting engineering services for the Water Supply Strategy Update, at an upset limit of $172,000 plus applicable taxes. CARRIED TRANSIT SERVICES o) E-05-099.3 GRT Fleet Maintenance Update Eric Gillespie, Director, Transit Services gave a brief overview of the report and introduced the Consultants working with Transit Services, in attendance. He indicated the report is an update outlining significant, ongoing progress has been made since the initial reports were presented in late 2004. There were positive references to GRT’s current state of operations and to the ongoing continuous improvement efforts underway. M. Connolly indicated he was pleased with the report. With regard to bus refurbishments, he acknowledged that new procedures were in place but asked how past experiences with noncompliance might be avoided in the future. It was suggested that he could discuss this further with staff. Received for Information. **W. Roth left the meeting at 10:35 a.m. ***M. Connolly left the meeting at 10:35 a.m. JOINT REPORT p) P-06-054 Housing Incentives and Funding Resource Guide Peter Walberg, Principal Planner provided a brief presentation indicating the current guide has been expanded to include key housing related incentives and resources offered by the Region of Waterloo, local municipalities, senior levels of government and non-government organizations. J. Haalboom emphasized the importance of incentives pertaining to heritage restoration projects in the Region of Waterloo. Rob Horne, Commissioner of Planning, Housing and Community Services indicated staff would review the issue. Received for Information. REPORTS – PLANNING, HOUSING AND COMMUNITY SERVICES - continued P&W -8- 06/0502 TRANSPORTATION PLANNING q) P-06-056 South Kitchener Transportation Corridor Study – Preferred Alternative and Upcoming Public Meeting R. Horne advised Committee members of the Public Meeting to be held in Council Chambers on May 9th regarding the matter. J. Haalboom requested the team leader on the project continue as team leader into the next phase of the project. Received for Information. OTHER BUSINESS a) Council Enquiries and Requests for Information Tracking List was received for information. b) J. Haalboom requested further information regarding a water pipeline and what it means for the Region of Waterloo if the City of Guelph’s water supply is not sufficient. T. Schmidt had been in discussion with the City of Guelph. He indicated Regional Council had approved a pipeline, and staff is looking at acquiring a consultant and pursuing acquisition of water taking permit, land for treatment and transmission facilities and other approval/consultation/notifications necessary for the construction of a Great Lakes pipeline. c) R. Kelterborn brought forward a letter from Gary Lovie, Environmentally Sensitive Property Owner Association (ESPO), to Committee requesting the deferral of the proposed Environmentally Sensitive Land (ESL) due to new development pertaining to the Conservation Authorities initiating new measures for the environment and water. G. Lovie in his letter suggests Regional staff fully investigate whether these measures could be used in place of the ESL. Committee members concurred the matter has been deferred to the Regional Council meeting on May 10, 2006, and any further decisions required to be made will be done at that meeting. Regional staff indicated they would formally communicate this to G. Lovie. ADJOURN/CLOSED SESSION The meeting adjourned at 11:00 a.m. MOVED by K. Denouden SECONDED by H. Epp THAT a closed meeting of Planning & Works Committee be held on Tuesday, May 2, 2006, following the regular meeting of the Planning and Works Committee, in accordance with Section 239 of the Municipal Act, 2001, for the purposes of considering the following subject matters: i) A proposed or pending acquisition of land for municipal purposes CARRIED COMMITTEE CHAIR, B. Strauss COMMITTEE CLERK, I. Sa Melo #279689